Loading...
The URL can be used to link to this page
Your browser does not support the video tag.
Home
My WebLink
About
Contract 53181-CO6
CSC No. 53181-CO6 F_ ORT K_ un-rm City of Fort Worth --^`�m Change Order Request Project Name] Watercress Low Pressure Sewer Extension CitySec No.: 1 53181 Project No.(s)] 66016-070043MO1783 I DOE No. I N/A CityProj. No.:1 101002 1 Project Description:) Extend low pressure sewer in Watercress Drive and connecting streets. Install grinder pumps at each home, Contractod William J. Schulz, Inc. dba Circle C Construction Co. Change Order # 6 1 Date: 11/27/2023 City Project Mgr.1 Walter Norwood CityInspector: ' John Kula Phone Number:1 817-392-5026 Phone Number (682)352-6651 Dept. Unit 1 Sewer Unit 2 Paving Unit 3 Water Totals Contract Time Calender days) Original Contract Amount $4,905,476.50 $510,107.50 $0.00 $5,415,584.00 7 0 Extras to Date $93,596.50 $0.00 $51,400.00 $162,996.50 0470 Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date $4,999,073.00 $610,107.60 $69,400.00 $5,568,580.50 jt20.0 'Amount of Proposed Change Order 'wf980.00 0.00 "12 980.00 Q.DO j80 Revised Contract Amount $4,955,093.00 5 0,107.50 $ YI.380,00 $5,5 8,580,50 1,380 Original Funds Available for Change Orders $147,164.0025,505.00 $0.00 $172,669.00 Remaining Funds Available for this CO $53;567.50 I $_25,506.00 $0.00 $79,072.50 Additional Funding (if necessary) ! CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 2.83% MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) $6,769,480.00 JUSTIFICATION (R QNS) FOR CE ORDER This Change Order No. 6 provides for the following: • The delivery of additional sewer grinder pumps to sewer operations storage for future installation • Installation of a 12 inch dia. force main in Hatch Road that eventually connect to Casino Beach Lift Station. • AdditonaI water services and water service reconnections • Drains for water heaters to allow installation of thermal expansion tanks • Substitution of 6" water line in Tyler Place Rd. and Sommerville Place Rd. in lieu of 8" water lines. • Installation of 6" water line by other than open cut method. The affected locations are currently provided water by Lakeside but must be converted to Fort Worth water per the terms of a Transfer Agreement with Lakeside. I Staff recommends the addition of 180 calendar days for the additional work. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. Contractor's Company N ontr0eW Name A tte William J. Schulz, Inc. dba Circle C Constmctlon Co. Ten' Skelly 7 Director (Water Dept) fhric+anher Na✓dP✓ senior zAssistant City AUomet 1a1,., ,. M&C Number NIA 11-30-2023 i L�AG%�iIY�� " �%u�� J-♦'� 3 Supervisor S . I Dec 1, 2023 Dec 1, 2023 6. � I Dec 1, 2023 M&C Date Approved NIA I OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX FORT WORTH City of Fort Worth Change Order Additions Project Name Watercress Low Pressure Sewer Extension City Sec No.: 53181 Project No.(s): 56016-0700430-CO1783 DOE No.1 N/A City Proj. No.: 101002 Project Extend low pressure sewer in Watercress Drive and connecting streets. Install grinder pumps at each home. Description I Contractor William J. Schulz, Inc. dba Circle C Construction Co. Change Order:© Date: 1 11/27/2023 City Project Mgr. Walter Norwood City Inspector I John Kula ADDITIONS I I tM MbUMP I IUN 2D Crane Pump for City Maintenance 76 12" Force Main (Hatch Rd.) 18 1" Water Service, Meter Reconnection 19 1" Water Service 20 Extend Water Heater Drain Outside Home 21 Install City Meter in Meter Box(Tyler PI., Sommerville PI., Jacksboro Hwy) 22 6" PVC Water Line (Tyler PI. & Sommerville Pl. Rd.) 23 6" PVC Water Line BOTOC Page 1 of 1 DEPT Q� Unit Unit Cost Total Unit 1 Sewer EA 4,500.00 T31,500.00 Unit i Sewer 340.00 LF 1165.00 $56,100.00 Unit 3 Water 28 EA $550.00 $15,400.00 Unit 3 Water 28 EA $725.00 $20,300.00 Unit 3 Water 30.00 Fro $200.00 $6,000.00 Unit 3 Water 11.00 EA $250.00 $2,750.00 Unit 3 Water 872.00 LF $115.00 $100,280.00 Unit 3 Water 30.00 LF $275.00 $8,250.00 Unit 1 Sewer $87,600.00 Unit 2 Paving Unit 3 Water $152,980.00 Additions Sub Total $240,580.00 FU;K-r Woo RTH City of Fort Worth Change Order Deletions Project Name Watercress Low Pressure Sewer Extension City Sec No.: 53181 Project No.(s): 56016.0700430-CO1783 DOE No. I N/A City Proj, No.: 101002 Project Description I Extend low pressure sewer in Watercress Drive and connecting streets. Install grinder pumps at each home. I Contractor I William J. Schulz, Inc. dba Circle C Construction Co,Change Order: I 6 I Date I 11/27/2023 City Project Mgr. Walter Norwood City Inspector: I John Kula DELETIONS ITEM DESCRIPTION DEPT City Unit Unit Cost Total 2A Crane Crane Sewer Grinder Pump Unit 1 Sewer 7.00 EA $13,500.00 $94,500.00 30 5' Wide Asphalt Pvmt Repair (2" HMAC, 10" Conc. Base Material) Unit 1 Sewer 674,1818 LF $55.00 $37,080.00 4 8" PVC Water Pipe by Open Cut Unit 3 Water 872.00 LF $125.00 $109,000.00 Page 1 of 1 Unit 1 Sewer Unit 2 Paving Unit 3 Water Deletions Sub Total 1$131,580.00 1 1$109,000.00 1$240,580.00 M1WBE Breakdown for this Change Order MWB Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders Co # DATE AMOUNT . ..... ... Total $0.00 Page 1 of 1 Contract Compliance Manager By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. Signature Walter Norwood Name of Employee Project Manager Title 44onn�� � " FORT OF000000000�L �� oo O p C — g�A ATTEST: pv'. s=d o C� T 0 a p a zip � o o000 5 a a x � exO lannette Goodall City Secretary OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX 11/27/2023 CPN 101002 Watercress Low Pressure Sewer Extension Change Order 6 Notes Staff has reviewed the requested prices and considers them to be fair and reasonable.