NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Great Hearts Harmon
City Project No.: 103715
Improvement Type(s): x❑ Paving ❑x Drainage x❑ Street Lights ❑ Traffic Signals
Original Contract Price:
$178,763.38
Amount of Approved Change Order(s):
$9,785.00
Revised Contract Amount:
$188,548.38
Total Cost of Work Complete:
$188,548.38
Lucas Gizas 0,20231�6:19 CST) Nov 30, 2023
Contractor Date
Director
Title
Tegrity Contractors
Company Name
Rand, orton(Nov 30,202316:23CST) Nov 30, 2023
Project Inspector
Date
aa<6"-�.. w
Nov 30, 2023
Project Manager
Date
Rebecca Diane Owen (Dec 1, 202307:50 CST)
Dec 1, 2023
CFA Manager
Date
x
Lauren Prieur (Dec 1, 202308:32 CST)
Dec 1 2023
TPW Director
Date
WJ---'1
William J,hn,on Mic S. 202308.58 CST)
Dec 5 2023
7
Asst. City Manager
Date OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Page 1 of 2
Notice of Project Completion
Project Name: Great Hearts Harmon
City Project No.: 103715
City's Attachments
Final Pay Estimate ❑x
Change Order(s): ❑x Yes ❑ N/A
Contractor's Attachments
Affidavit of Bills Paid -
Consent of Surety
Statement of Contract Time
Contract Time 210 WD Days Charged: 196
Work Start Date: 8/9/2022 Work Complete Date: 11/30/2023
Completed number of Soil Lab Test: 268
Completed number of Water Test: 17
Page 2 of 2
FORT WORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name GREAT HEARTS HARMON
Contract Limits
Project Type DRAINAGE, PAVING, LIGHTING
City Project Numbers 103715
DOE Number 3715
Estimate Number 1 Payment Number 1 For Period Ending 11/30/2023
WD
City Secretary Contract Number Contract Time 21WD
Contract Date 3/8/2022 Days Charged to Date 196
Project Manager NA Contract is 100.00 Complete
Contractor TEGRITY CONTRACTORS
202N ALLEN DR, STE E
ALLEN, TX 75013
Inspectors GLOVER / OVERSTREET
Thursday, November 30, 2023 Pagel of 5
City Project Numbers 103715
Contract Name GREAT HEARTS HARMON
Contract Limits
Project Type DRAINAGE, PAVING, LIGHTING
Project Funding
UNIT III: STORM DRAIN IMPROVEMENTS
DOE Number 3715
Estimate Number I
Payment Number 1
For Period Ending 11/30/2023
Item
Description of Items
Estimated Unit
Unit Cost
Estimated
Completed
Completed
No.
Quanity
Total
Quanity
Total
1
REMOVE 24" STORM LINE (CO #3)
23 LF
$80.00
$1,840.00
23
$1,840.00
2
24" STORM ABANDONMENT PLUG
1 EA
$1,200.00
$1,200.00
1
$1,200.00
3
REMOVE 10' RECESSED CURB INLET
1 EA
$2,400.00
$2,400.00
1
$2,400.00
4
REMOVE 20' RECESSED CURB INLET
1 EA
$2,990.00
$2,990.00
1
$2,990.00
5
SWPPP 1 ACRE
1 LS
$1,000.00
$1,000.00
1
$1,000.00
6
TRENCH SAFETY (CO #3)
3203 LF
$1.50
$4,804.50
3203
$4,804.50
7
24" RCP CLASS III (CO #3)
40 LF
$125.00
$5,000.00
40
$5,000.00
8
10' RECESSED INLET
2 EA
$4,950.00
$9,900.00
2
$9,900.00
9
20' RECESSED INLET
1 EA
$9,670.00
$9,670.00
1
$9,670.00
Sub -Total of Previous Unit $38,804.50 $38,804.50
UNIT IV: PAVING IMPROVEMENTS
Item
Description of Items
Estimated Unit
Unit Cost
Estimated
Completed
Completed
No.
Quanity
Total
Quanity
Total
1
REMOVE CONC CURB & GUTTER
435 LF
$17.00
$7,395.00
435
$7,395.00
2
CONC. PVMT REPAIR, ARTERIAL/INDUSTRIAL
201 SY
$115.50
$23,215.50
201
$23,215.50
(CO #3)
3
HYDRATED LIME
12 TN
$190.00
$2,280.00
12
$2,280.00
4
8" LIME TREATMENT
669 SY
$30.02
$20,083.38
669
$20,083.38
5
10" CONC PVMT
654 SY
$88.00
$57,552.00
654
$57,552.00
6
4" CONC SIDEWALK
3574 SF
$5.50
$19,657.00
3574
$19,657.00
7
BARRIER FREE RAMP TYPE P-2 (CO #4)
1 EA
$2,500.00
$2,500.00
1
$2,500.00
8
8" SLD PVMT MARKING TAPE (W)
320 LF
$6.50
$2,080.00
320
$2,080.00
9
LANE LEGEND ARROW
1 EA
$130.00
$130.00
1
$130.00
10
LANE LEGEND ONLY
1 EA
$160.00
$160.00
1
$160.00
11
REFL RAISEDE MARKER TY II-C-R
16 EA
$20.00
$320.00
16
$320.00
12
TOOPSOIL
10 CY
$75.00
$750.00
10
$750.00
13
BLOCK SOD PLACEMENT
150 SY
$6.00
$900.00
150
$900.00
14
--------------------------------------
INSTALL ALUM SIGN GROUND MOUNT
3 EA
$225.00
$675.00
3
$675.00
Sub-Total of Previous Unit
$137,697.88
$137,697.88
Thursday, November 30, 2023 Page 2 of 5
City Project Numbers 103715
Contract Name GREAT HEARTS HARMON
Contract Limits
Project Type DRAINAGE, PAVING, LIGHTING
Project Funding
UNIT V: STREET LIGHTING IMPROVEMENTS
Item Description of Items
No.
1 FURNISH/INSTALL ELEC SERV POLE MNT
2 FURNISH/INSTALL LED LIGHTING FIXTURE (70
WATT ATBO COBRA HEAD)
3 FURNISH/INSTALL W WOOD LIGHT POLE ARM
4 #4 INSUALTED ELEC CONDUCTOR (#4 XHHW
COPPER)
DOE Number 3715
Estimate Number I
Payment Number 1
For Period Ending 11/30/2023
Estimated Unit Unit Cost Estimated Completed Completed
Quanity Total Quanity Total
1 EA $5,200.00 $5,200.00 1 $5,200.00
2 EA $1,083.00 $2,166.00 2 $2,166.00
2 EA $870.00 $1,740.00 2 $1,740.00
400 LF $7.35 $2,940.00 400 $2,940.00
Sub -Total of Previous Unit $12,046.00 $12,046.00
Thursday, November 30, 2023 Page 3 of 5
City Project Numbers 103715
Contract Name GREAT HEARTS HARMON
Contract Limits
Project Type DRAINAGE, PAVING, LIGHTING
Project Funding
Contract information Summary
Original Contract Amount
Change Orders
Change Order Number 3
Change Order Number 3
Change Order Number 4
Total Contract Price
DOE Number 3715
Estimate Number I
Payment Number 1
For Period Ending 11/30/2023
$178,763.38
$11,665.50
$619.50
($2,500.00)
$188,548.38
Total Cost of Work Completed $188,548.38
Less % Retained $0.00
Net Earned $188,548.38
Earned This Period $188,548.38
Retainage This Period $0.00
Less Liquidated Damages
Days @ / Day
LessPavement Deficiency
Less Penalty
Less Previous Payment
Plus Material on Hand Less 15%
Balance Due This Payment
$0.00
$0.00
$0.00
$0.00
$0.00
$188,548.38
Thursday, November 30, 2023 Page 4 of 5
City Project Numbers 103715
Contract Name GREAT HEARTS HARMON
Contract Limits
Project Type DRAINAGE, PAVING, LIGHTING
Project Funding
Project Manager NA
Inspectors GLOVER / OVERSTREET
Contractor TEGRTTY CONTRACTORS
202N ALLEN DR, STE E
ALLEN , TX 75013
DOE Number 3715
Estimate Number I
Payment Number 1
For Period Ending 11/30/2023
City Secretary Contract Number
Contract Date
3/8/2022
Contract Time
210 WD
Days Charged to Date
196 WD
Contract is .000000
Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
Total Cost of Work Completed $188,548.38
Less % Retained $0.00
Net Earned $188,548.38
Earned This Period $188,548.38
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty
$0.00
Less Previous Payment
$0.00
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$188,548.38
Thursday, November 30, 2023 Page 5 of 5
DEVELOPER -AWARDED -PROJECT CHANGE ORDER
PROJECT NAME:
Great Hearts Harmon
CHANGE
Water, Sewer, Paving. Drainage & Street Lights
ORDER No:
�CONTRACT:
CFA#
CFA21-0167 CITY PARTICIPATION:(
NO
ICITY PROJECT #
103715
IFID #
30114-0200431-103715-EO7685
1
IX -FILE #
X-27098
IFILE #
K-2870
INSPECTOR:
Travis Overstreet Phone No:
469-247-7716
REVIEWED
PROJECT MANAGER:
Debbie J. Willhelm Phone No:
817-392-2481
By Debbie J. Willhelm at 4:18 pm, Aug 23, 2022
CONTRACT UNIT
WATER
SEWER
PAVING
DRAINAGE
STREET LIGHTS
CONTRACT
Developer
Developer
Developer
Developer
Developer
DAYS
Cost
City Cost
Cost
City Cost
Cost
City Cost
Cost
City Cost
Cost
City Cost
ORIGINAL CONTRACT
$514,982.50
$580,344.25
$128,532.38
$38,185.00
$12,046.00
210
EXTRAS TO DATE
(CREDITS TO DATE
ICONTRACT TO DATE
$514,982.50
$0.00
I $580,344.25
$0.00
$128,532.38
$0.00
$38,185.00
$0.00
I $12,046.00
$0.00
210
(AMOUNT OF PROP. CHANGE ORDER
I ($7,160.00)
IREVISED CONTRACT AMOUNT
$514,982.50
$0.00
I $573,184.25
$0.00
$128,532.38
$0.00
I $38,185.00
$0.00
I $12,046.00
$0.00
I 210
TOTAL REVISED CONTRACT AMOUNT
PER UNIT
$514,982.50
$573,184.25
$128,532.38
$38,185.00
$12,046.00
REVISED COST SHARE
Dev. Cost: $1,266,930.13
City Cost:
$0.00
TOTAL REVISED CONTRACT
$1,266,930.13
Revised: 10-12-2011 Page 1
You are directed to make the following changes in the contract documents:
CITY BID ITEM
UNIT II - SEWER IMPROVEMENTS
PAY ITEM # # QUANTITY
UNIT ITEM DESCRIPTION
UNIT PRICE
TOTAL
Item 15 3331.4212 -358
LF 12" DIP Sewer
$145.00
($51,910.00)
NEW 3311.0461 358
LF 12" DR-14 Green Pressure Pipe
$125.00
$44,750.00
SUBTOTAL UNIT II - SEWER IMPROVEMENTS
($7,160.00)
REASONS FOR CHANGE ORDER Due to unavailability of Ductile Iron Pipe, pressure rated sewer pipe to be used inside of casing. Changes correspond to Revision No. 1 as shown on
sheet 12 of
the construction plans.
NO CITY FUNDS INVOLVED
IN THIS CONTRACT. DEVELOPER IS RESPONSIBLE FOR 100% OF THE CHANGE ORDER COST AND NO
REIMBURSEMENT FROM THE CITY WILL BE SOUGHT BY THE DEVELOPER
RECOMMENDED:
APPROVED: APPROVED:
mma, inc.
Great Heart ca - Texa Tegrity Contractors, Inc.
By:4v�/i�
By: %Name:
`
ier
E
Gabby VIIIaIOVOS
Name: Todd Name: Lucas Groves
Title: Project Engineer
Title: Owne-'s Representative Title: PM
Revised: 10-12-2011 Page 2
DEVELOPER -AWARDED -PROJECT CHANGE ORDER
IPROJECT NAME: Great Hearts Harmon
CHANGE
(CONTRACT: Water, Sewer, Paving. Drainage & Street Lights ORDER No:
ICFA# CFA21-0167 I CITY PARTICIPATION: NO
ICITY PROJECT # 103715
IFID # 30114-0200431-103715-EO7685 2
IX -FILE # X-27098
I FI LE # K-2870
INSPECTOR: Travis Overstreet Phone No: 469-247-7716 REVIEWED
PROJECT MANAGER: Debbie J. Willhelm Phone No: 817-392-2481 By Debbie J. Willhelm at 11:34 am, Sep 21, 2022
CONTRACT UNIT
WATER SEWER PAVING DRAINAGE I STREET LIGHTS I CONTRACT
P
P
P
Cost City Cost
$12,046.00
$12,046.00 I $0.00
$12,046.00 I $0.00
$12,046.00
REVISED COST SHARE Dev. Cost: $1,256,685.63 City Cost: $0.00
TOTAL REVISED CONTRACT I $1,256,685.63
210
210
210
Revised: 10-12-2011 Page 1
You are directed to make the following changes in the contract documents:
CITY BID ITEM
UNIT II - SEWER IMPROVEMENTS
PAY ITEM #
#
QUANTITY
UNIT
ITEM DESCRIPTION
4
3305.0109
-33
LF
Trench Safety
7
3311.0061
-5
LF
4" PVC Water Pipe
9
3311.0261
-28
LF
8" PVC Water Pipe
14
3312.2003
-1
EA
1" Water Service
18
3312.3003
-1
EA
6" Gate Valve
19
3312.3005
-2
EA
8" Gate Valve
SUBTOTAL
UNIT I - WATER IMPROVEMENTS
UNIT PRICE TOTAL
$1.50
($49.50) 1
$61.00
($305.00)
$85.00
($2,380.00)
$660.00
($660.00)
$1,950.00
($1,950.00) I
$2,450.00
($4,900.00)
($10,244.50)1
REASONS FOR CHANGE ORDER Removed water services for adjacent property which will be constructed by others. Changes correspond to Revision No. 2 as shown on sheet 7-9 of the
construction plans.
NO CITY FUNDS INVOLVED IN THIS CONTRACT. DEVELOPER IS RESPONSIBLE FOR 100% OF THE CHANGE ORDER COST AND NO
REIMBURSEMENT FROM THE CITY WILL BE SOUGHT BY THE DEVELOPER.
RECOMMENDED:
m%ma, inc.
By:
Name: Gabbv Villalovos
Title: Project Enqineer
APPROVED:
Great Hearts America - pl-1;1911�1
sBy: T,.
Name: Todd Roper
Title: Owner's Representative
APPROVED:
Tegrity Contractors, Inc.
By:
Name: Lucas Groves
Title: Proiect Manager
Revised: 10-12-2011 Page 2
DEVELOPER -AWARDED -PROJECT CHANGE ORDER
PROJECT NAME:
Great Hearts Harmon
CONTRACT:
Water, Sewer, Paving. Drainage & Street Lights
CFA #
CFA21-0167 CITY PARTICIPATION: NO
CITY PROJECT #
103715
FID #
I30114-0200431-103715-EO7685
X-FILE #
IX-27098
FILE #
IK-2870
INSPECTOR: Travis Overstreet Phone No:
PROJECT MANAGER: Debbie J. Wilhelm Phone No:
I
WATER SEWER
Developer Developer
Cost City Cost Cost City Cost
ORIGINAL CONTRACT $514,982.50 $580,344.25
EXTRAS TO DATE
CREDITS TO DATE
I ($10,244.50)
I ($7,160.00)
CONTRACT TO DATE
$504,738.00 $0.00
I $573,184.25 I+ $0.00
AMOUNT OF PROP. CHANGE ORDER
REVISED CONTRACT AMOUNT
I $504,738.00 I $0.00
I $573,184.25 I $0.00
TOTAL REVISED CONTRACT AMOUNT
PER UNIT
$504,738.00
$573,184.25
REVISED COST SHARE
Dev. Cost:
$1,268,970.63
TOTAL REVISED CONTRACT
469-247-7716
817-392-2481
CHANGE
ORDER No:
3
REVIEWED
By Debbie J. Willhelm at 4:42 pm, Mar 15, 2023
CONTRACT UNIT
PAVING
DRAINAGE
STREET LIGHTS
Developer
Developer
Developer
Cost
City Cost
Cost
City Cost
Cost
City Cost
$128,532.38
$38,185.00
$12,046.00
$128,532.38
$0.00
I $38,185.00
$0.00
I $12,046.00
$0.00
$11,665.50
I $619.50
$140,197.88
$0.00
I $38,804.50
I $0.00
I $12,046.00
$0.00
$140,197.88
$38,804.50
I $12,046.00
City Cost:
$0.00
$1,268,970.63
CONTRACT
DAYS
210
210
210
Revised: 10-12-2011 Page 1
You are directed to make the following changes in the contract documents:
CITY BID ITEM
UNIT III - STORM DRAIN
PAY ITEM #
#
QUANTITY UNIT
ITEM DESCRIPTION
UNIT PRICE
TOTAL
1
241.3015
3 LF
Remove 24" Storm Line
$80.00
$240.00
6
3305.0109
3 LF
Trench Safety
$1.50
$4.50
7
3341.0205
3 LF
24" RCP, Class 111
$125.00
$375.00
f
SUBTOTAL UNIT III - STORM DRAIN IMPROVEMENTS
$619.50
CITY BID ITEM
UNIT IV - PAVING
PAY ITEM #
#
I
QUANTITY UNIT
ITEM DESCRIPTION
UNIT PRICE
TOTAL
2
3201.0614
101 SY
Conc. Pvmt. Repair, Aterial/Industrial
$115.50
$11,665.50
SUBTOTAL UNIT IV- PAVING IMPROVEMENTS
$11,665.50
REASONS FOR CHANGE ORDER Inlet relocation changed due to powerpole conflict. Changes correspond to Revision No. 3 as shown on Sheet 30 of the construction plans
NO CITY FUNDS INVOLVED IN THIS CONTRACT. DEVELOPER IS RESPONSIBLE FOR 100% OF THE CHANGE ORDER COST AND NO
REIMBURSEMENT FROM THE CITY WILL BE SOUGHT BY THE DEVELOPER.
RECOMMENDED:
mma, in
By:
Name: Andrea Taylor
Title: Principal
APPROVED:
Great Hearts America - Texas
By: f ,
Name: Brendan Miniter
Title: Superintendent
1 /17/2022
APPROVED:
Tegrity Contractors, Inc. Q .
Name: Lucas Groves
Title: Proiect Manaaer
Revised: 10-12-2011 Page 2
DEVELOPER -AWARDED -PROJECT CHANGE ORDER
PROJECT NAME:
Great Hearts Harmon
(CONTRACT:
Water, Sewer, Paving, and Street Lights Improvements
CHANGE
ORDER No:
JCFA#
CFA21-0167
I CITY PARTICIPATION:
NO
CITY PROJECT #
103715
FID #
30114-0200431-103715-EO7685
I
4
X #
X-27098
IPRC #
IPRC21-0118
FILE #
K-2870
INSPECTOR:
Travis Overstreet Phone No:
469-247-7716
REVIEWED
PROJECT MANAGER:
Debbie Willhelm
Phone No:
817-392-2481
By Debbie J. Willhelm at 9:14 am, Jul 11, 2023
CONTRACT UNIT
WATER
SEWER
PAVING
DRAINAGE
STREET LIGHTS
I CONTRACT
Developer
Developer
Developer
Developer
DAYS
Developer Cost
City Cost
Cost
City Cost
Cost
City Cost
Cost
City Cost
Cost
City Cost
ORIGINAL CONTRACT
I $514,982.50 I $0.00
$580,344.25
$0.00
$128,532.38
$0.00
$38,185.00
$0.00
$12,046.00
$0.00
120
EXTRAS TO DATE
I
I $11,665.50
I $619.50
CREDITS TO DATE
I ($10,244.50) I
($7,160.00)
CONTRACT TO DATE
I $504,738.00 I $0.00
I $573,184.25
$0.00
I $140,197.88
I $0.00
I $38,804.50
$0.00
$12,046.00 I $0.00
I 120
AMOUNT OF PROP. CHANGE ORDER
I I
I $ 10,240.00
I $ (2,500.00)
REVISED CONTRACT AMOUNT
I $504,738.00 I $0.00
I $583,424.25
$0.00
I $137,697.88 I
$0.00
$38,804.50 I
$0.00
$12,046.00 I $0.00
I 120
TOTAL REVISED CONTRACT AMOUNT
PER UNIT
$504,738.00
$583,424.25
$137,697.88
$38,804.50
$12,046.00
REVISED COST SHARE
Dev. Cost:
$1,276,710.63
City Cost:
$0.00
TOTAL REVISED CONTRACT
I
$1,276,710.63
Revised: 10-12-2011 Page 1
You are directed to make the following changes in the contract documents
UNIT II - SANITARY SEWER IMPROVEMENTS
PAY ITEM # CITY BID ITEM # QUANTITY UNIT ITEM DESCRIPTION
18 33 39 10, 33 39 20 2 EA 3339.1001 4' MANHOLE
3 3301 30 2 EA 3301.0101 MANHOLE VACUUM TESTING
SUBTOTAL UNIT II -SANITARY SEWER IMPROVEMENTS
TOTAL
UNIT IV - PAVING IMPROVEMENTS
PAY ITEM # CITY BID ITEM # QUANTITY UNIT ITEM DESCRIPTION
7 32 13 20 -1 EA 3213.0507 BARRIER FREE RAMP, TYPE P-2
SUBTOTAL UNIT V -PAVING IMPROVEMENTS
TOTAL
REASONS FOR CHANGE ORDER
UNIT PRICE TOTAL
$ 4,920.00 $ 9,840.00
$ 200.001 $ 400.00
1
1 $ 10,240.00
UNIT PRICE TOTAL
$ 2,500.00 $ (2,500.00)1
1
1 1
1 $ (2,500.00)1
6" SERVICE REQUIRES MANHOLES. CHANGES CORRESPOND TO REVISION 4 AS SHOWN ON SHEET 14 OF THE CONSTRUCTION PLANS.
RECONCILED BARRIER FREE RAMP QUANTITY TO MATCH ORIGINAL PLANS
NO CITY FUNDS INVOLVED IN THIS CONTRACT. DEVELOPER IS RESPONSIBLE FOR 100% OF THE CHANGE ORDER COST AND NO
REIMBURSEMENT FROM THE CITY WILL BE SOUGHT BY THE DEVELOPER.
RECOMMENDED:
mma inc.
By:
Name: Andrea Taylor, PE
Title: Principal
APPROVED:
Great Hearts America - Texas
By. -
Name: Brendan miniter
Title: Superintendent
APPROVED: 6/29/2023
Tegrity Contractors, inc. � {I
By:
Name: Lucas Groves
Title: Proiect Manaaer
Revised: 10-12-2011 Page 2
FORTWORTH.
TRANSPORTATION AND PUBLIC WORKS
November 30, 2023
Tegrity Contractors
202 N. Allen Dr. Unit E
Allen, Texas 75013
RE: Acceptance Letter
Project Name: Great Hearts Harmon
Project Type: Storm Drain, Paving, Street Lights
City Project No.: 103715
To Whom It May Concern:
On September 20, 2023 a final inspection was made on the subject project. There were punch list items
identified at that time. The punch list items were completed on November 30, 2023. The final
inspection and the corrected punch list items indicate that the work meets the City of Fort Worth
specifications and is therefore accepted by the City. The warranty period will start on November 30,
2023, which is the date of the punch list completion and will extend of two (2) years in accordance with
the Contract Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at 817-
392-2481.
Sincerely,
T e66e � G(��lralm
Debbie Willhelm, Project Manager
Cc: Randy Horton, Inspector
Mike Glover, Inspection Supervisor
Randy Horton, Senior Inspector
Andrew Goodman, Program Manager
MMA, Consultant
Tegrity Contractors, Contractor
Great Hearts America, Developer
File