THIRD AMENDMENT TO CITY SECRETARY CONTRACT NUMBER 51820
AN ENHANCED COMMUNITY FACILITIES AGREEMENT BETWEEN
THE CITY OF FORT WORTH AND AMERICAN AIRLINES, INC.
This THIRD AMENDMENT TO CITY SECRETARY CONTRACT NUMBER
51820 ("Third Amendment") is made and entered into by and between the City of Fort Worth
("City"), a home -rule municipal corporation of the state of Texas, and American Airlines, Inc.
("Developer"), a Texas limited liability company.
WHEREAS, City and Developer entered into an Enhanced Community Facilities
Agreement, City Secretary Contract No. 51820 ("ECFA"), by which Developer is constructing
certain public infrastructure Improvements; and
WHEREAS, City and Developer executed the First Amendment to the ECFA, City
Secretary Contract Number 51820-A1, to expand the scope of the ECFA to include the
construction of additional public infrastructure; and
WHEREAS, City and Developer executed the Second Amendment to the ECFA, City
Secretary Contract Number 51820-A2, to extend the Completion Deadline to January 31, 2020;
and
WHEREAS, the public infrastructure improvements were substantially completed on
October 22, 2020 and the final inspection was conducted on March 11, 2021; and
WHEREAS, City has worked with Developer, the contractor, and the Texas Department
of Transportation on the final accounting of the project in order to make the final payment to
Developer and close out the project; and
WHEREAS, City and Developer desire to amend the ECFA to extend the completion
deadline to January 30, 2022 and to increase City Participation by $103,609.90, and to increase
City Participation with Regional Toll Revenue by $191,990.40;
NOW THEREFORE, City and Developer, acting herein by and through their duly
authorized representatives, enter into the following agreement, which amends City Secretary
Contract No. 51820:
1.
Section L, subsection i of the ECFA is amended to be and read as follows:
OFFICIAL RECORD
City of Fort Worth, Texas CITY SECRETARY
Third Amendment to City Secretary Contract No. 51820 FT. WORTH, TX
Page 1 of 6
Notwithstanding anything to the contrary herein, the City's obligation to participate
(exclusive of front foot charges) in this Agreement shall terminate if the
Improvements are not completed by January 30, 2022, subject to extension due to
events of force majeure in accordance with subsection vi below. If the
Improvements are not complete by such time, Developer shall be in default under
this Agreement and the City may terminate this Agreement by providing written
notice to Developer, with no obligation by the City to pay any of the City
Participation Amount.
2.
Section L, subsection iv of the ECFA is amended to be and read as follows:
iv. The City may utilize the Developer's financial guarantee submitted for this
Agreement to cause the completion of the construction of the Improvements if the
Improvements are not completed and accepted by the City by January 30, 2022,
subject to extension due to events of force majeure in accordance with subsection
vi below.
3
Section L, subsection v of the ECFA is amended to be and read as follows:
V. The City may utilize the Developer's financial guarantee to cause the payment of
costs for construction of the Improvements before January 30, 2022 if the
Developer breaches this Agreement, becomes insolvent, or fails to pay costs of
construction.
9
The Cost Summary Table in the ECFA is amended to be and read in its entirety as set forth
in Exhibit A of this Third Amendment, which is attached hereto and incorporated herein by
reference. The revised Cost Summary Table reflects revisions made by Change Order 2.
5.
a. All other terms and conditions of the ECFA shall remain in full force and effect except as
specifically set forth in this Third Amendment.
b. All terms of this Third Amendment that are capitalized but not defined shall have the
meanings assigned to them in the ECFA.
[REMAINDER OF PAGE INTENTIONALLY BLANK]
City of Fort Worth, Texas
Third Amendment to City Secretary Contract No. 51820
Page 2 of 6
IN WITNESS WHEREOF, the parties hereto have executed this Third Amendment to
be effective on the date signed by the City's Assistant City Manager.
CITY OF FORT WORTH DEVELOPER
American Airlines, Inc.
A anda han ec7, 202308:25 CST)
15ana 8cuu�u%d
Dana Burghdoff (Dec , 202315.48 CST) Name: Amanda Zhang
Dana Burghdoff Title: Vice President
Assistant City Manager Date: Dec 7, 2023
Date: Dec 7, 2023
ATTEST:
Recommended by: American Airlines, Inc.
Bichson &'chf oiien 7, 20i 8: CST) Mike L �=:
21 CST)
Dwayne Hollars/Bichson Nguyen Name: Mike Long
Contract Compliance Specialist Title: Project Manager
Development Services Date: Dec 7, 2023
Approved as to Form & Legality:
Richard A. McCracken (Dec 7, 2023 09:36 CST)
Richard A. McCracken
Sr. Assistant City Attorney
M&C No. 22-0735
Date: 9/27/22
Form 1295: N/A
44UUU4�� Contract Compliance Manager:
ATTEST: �.*�-Pl
F....o By signing, I acknowledge that I am the
v°:o�?'.,d person responsible for the monitoring and
City Secretary v� oo s,
* administration of this contract, including all
Q° ° '
A aan� rEza544a performance and reporting requirements.
�Raaaaa
Jannette S. Goodall Rebecca Diane Owen (Dec 7, 2023 08:50 CST)
City Secretary
Rebecca Owen
Development Manager
City of Fort Worth, Texas
Third Amendment to City Secretary Contract No. 51820
Page 3 of 6
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Exhibit A
Cost Summary Sheet
Project Name: American Airlines Headquarters Trinity Blvd., SH 360 Frontage, American Blvd.
& American Blvd/Transformation Way Improvements American Airlines Trinity
Complex
CFA No.: 2017-192 City Project Nos.: 101314 and 101828
CITY PROJECT NUMBER 101314
Items Developer's Impact Fee RTR Cost
Cost funds
A. Water and Sewer Construction
1. Water Construction $
2. Sewer Construction $
Water and Sewer Construction Total $
B. TPW Construction
1. Street $
2. Storm Drain $
3. Street Lights Installed by Developer $
4. Signals $
TPW Construction Cost Total $
Total Construction Cost (excluding the fees): $
Construction Fees:
C. Water/Sewer Inspection Fee (2%) $
D. Water/Sewer Material Testing Fee (2%) $
Sub-Totalfor Water Construction Fees $
E. TPW Inspection Fee (4%) $
F. TPW Material Testing (2%) $
G. Street Light Inspsection Cost $
H. Signals Inspection Cost $
J.Civil/Geotechnical Engineering & Survey( $
TPW Construction Fees Subtotal $
Total Construction Fees $
TOTAL COST CPN 101314 $
$ 128,154.00 $ 1, 654, 524.80 $
$ 123, 947.20 $
$ 582,984.80 $
$ 128,154.00 $ 2,361,456.80 $
$ 128,154.00 $ 2,361,456.80 $
$
66,130.90 $
$
33,065.46 $
$
20, 647.73 $
$
$
119, 844.09 $
$ 119,844.09 $
$ 128,154.00 $ 2,481,300.89 $
City of Fort Worth, Texas
Third Amendment to City Secretary Contract No. 51820
Page 4 of 6
City's Cost Total Cost
413, 631.20 $ 2,196, 310.00
30, 986.80 $ 154, 934.00
145, 746.20 $ 728, 731.00
590,364.20 $ 3,079,975.00
590,364.20 $ 3,079,975.00
16,532.73 $ 82,663.66
8,266.37 $ 41, 331.83
5,161.93 $ 25, 809.66
219,177.00 $ 219,177.00
249,138.03 $ 368,982.15
249,138.03 $ 368,982.15
839,502.23 $ 3,448,957.15
Items
CITY PROJECT NUMBER 101828
Developer's Impact Fee RTR Cost
Cost funds
A. Water and Sewer Construction
1. Water Construction $
2. Sewer Construction $
Water and Sewer Construction Total $
B. TPW Construction
1. Street $
2. Storm Drain $
3. Street Lights Installed by Developer $
4. Signals $
TPW Construction Cost Total $
Total Construction Cost (excluding the
fees): $
Construction Fees
C. Water/Sewer Inspection Fee (2%) $
D. Water/Sewer Material Testing Fee (2%) $
Sub -Total for Water Construction Fees $
E. TPW Inspection Fee (4%) $
F. TPW Material Testing (2%) $
G. Street Light Inspection Cost $
H. Signal Inspection Cost $
J. Civil/Geotechnical Engineering & Survey $
TPW Construction Fees Subtotal $
Total Construction Fees $
TOTAL PROJECT COST $
City's Cost Total Cost
$
163,493.85
$
163,493.85
$
57,367.00
$
57,367.00
$
243,835.25
$
243,835.25
$
464,696.10
$
464,696.10
-
$
464,696.10
$
464,696.10
$
$
- $
7,814.00
$
7,814.00
$
$
- $
3,907.05
$
3,907.05
$
$
- $
8,549.25
$
8,549.25
$
$
$
20,270.30
$
20,270.30
$
$
$
20,270.30
$
20,270.30
- $
- $
- $
484,966.40
$
484,966.40
City of Fort Worth, Texas
Third Amendment to City Secretary Contract No. 51820
Page 5 of 6
Items
A Water and Sewer Construction
1. Water Construction
2. Sewer Construction
Water and Sewer Construction Total
B. TPW Construction
1. Street
2. Storm Drain
3. Street Lights Installed by Developer
4. Signals
TPW Construction Cost Total
Total Construction Cost (excluding the fees)
Construction Fees
C. Water/Sewer Inspection Fee (2%)
D. Water/Sewer Material Testing Fee (2%)
Sub -Total for Water Construction Fees
E. TPW Inspection Fee (4%)
F. TPW Material Testing (2%)
G. Street Light Inspection Cost
H. Signal Inspection Cost
J. Civil/Geotechnical Engineering & Survey
TPWConstruction Fees Subtotal
Total Construction Fees
TOTAL PROJECT COST
COMBINED CITY PROJECT NUMBERS 101314 & 101828
Developer's
Impact Fee
RTR Cost
City's Cost
Total Cost
Cost
Funds
$
$
128,154.00
$ 1,654,524.80
$
577,125.05
$
2,359,803.85
$
$
-
$ 123,947.20
$
88,353.80
$
212,301.00
$
$
-
$ 582,984.80
$
389,581.45
$
972,566.25
$
$
128,154.00
$ 2,361,456.80
$
1,055,060.30
$
3,544,671.10
$
$
128,154.00
$ 2,361,456.80
$
1,055,060.30
$
3,544,671.10
$
$
$ 66,130.93
$
24,346.73
$
90,477.66
$
$
$ 33,065.46
$
12,173.42
$
45,238.88
$
$
$ 20,647.73
$
13,711.18
$
34,358.91
$
$
$ -
$
219,177.00
$
219,177.00
$
$
$ 119,844.12
$
269,408.33
$
389,252.45
$
$
-
$ 119,844.12
$
269,408.33
$
389,252.45
$
$
128,154.00
$ 2,481,300.92
$
1,324,468.63
$
3,933,923.55