HomeMy WebLinkAboutContract 56638-FP1FORT WORTH,
TRANSPORTATION AND PUBLIC WORKS
NOTICE OF PROJECT COM ON
-FP1
City Secretary No: 56638
Date Received: 12/11/2023
City Project N!?: 101452-2
Regarding contract 56638 2018 Bond Year 3 Contract 6 for as required by the
TRANSPORTATION AND PUBLIC WORKS DEPARTM as approved by City Council on 9/28/2021 through
M&C 21-0754 the director of the TRANSPORTATION AND PUBLIC WORKS DEPARTM upon the
recommendation of the Assistant Director of the Transportation & Public Works Department has accepted the project as
complete.
Original Contract Amount:
Amount of Approved Change Orders:
Revised Contract Amount:
Total Cost Work Completed:
Less Deductions:
Liquidated Damages:
Pavement Deficiencies:
Total Deduction Amount:
Total Cost Work Completed:
Less Previous Payments:
$ 7,192,666.51 Days 450
$ 1,395,532.48No 0 Days Added by CO_120
$ 8,588,198.99 Total Days 570
$ 7,132 ,379.01 Days Charged 567
0 Days @ $
$ 0.00
$ 7,226,379.01
$ 6,865,060.06
Final Payment Due $ 361,318.95
Pa--f icier L. wadsac)( Dec 11, 2023
Patricia L. Wadsack (Dec 11, 202310:04 CST)
Recommended for Acceptance Date
Asst. Director, TPW - Capital Delivery
'-'a.- Dec 11, 2023
Lauren Prieur (Dec 11, 202310:07 CST)
Accepted Date
Director, TRANSPORTATION AND PUBLIC WORKS DEPARTMENT
William Johnson lD c 11, 2.0)311:42 CST)
Asst. City Manager
Comm nts:
Dec 11, 2023
Date
/ Day
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
C-620 Signature Page
Contractor's Application for Payment
To (Owner): City of Fort Worth Invoicing Period (From - To):
11/01/2023 to 11/30/2023
P. o. FW020-0000006894 From (Contractor):
Number: Texas Materials Group, Inc
Project: 1 O 1452-2 Contractors CFW Vendor No.:
0000000257
City Secretary Contract 56638 Contract
Number: Name:
Application For Payment
Change Order Summary
(Approved Change Orders
Number
Additions
Deletions
1
$851,816.79
2
$424,788.51
$424,999.60
3
$570,564.07
$26,637.29
4 I
$21,409.67
$21,409.67
5 I
$25,055.78
$25,055.78
6
7
8
TOTALSI
$1,893,634.82
$498,102.34
NET CHANGE BY
$1,395,532.48
CHANGE ORDERS
Contractor's Certification
The Contractor certifies with the submittal ofthis document and associated Payment Request Submittal
on the City of Fort Worth Buzzsaw system that to the best of their knowledge: (1) all previous progress
payments received from Owner on account of Work done under the Contract have been applied on
account to discharge Contractor's legitimate obligations incurred in connection with Work covered by
prior Applications for Payment; (2) title of all Work, materials and equipment incorporated in said
Work or otherwise listed in or covered by this Application for Payment will pass to Owner at time of
payment free and clear of all Liens, security interests and encumbrances (except such as are covered by
a Bond acceptable to Owner indemnifying Owner against any such Liens, security interest or
encumbrances); and (3) all Work covered by this Application for Payment is in accordance with the
Contract Documents and is not defective.
Liquidated Damages $650.00 x day
Invoice No. 23
Invoice Date:
11/30/2023
Remit to ( If Not Automatic Deposit):
2018 Bond Year 3 - Contract 6
11. ORIGINAL CONTRACT PRICE.......................................................... $
12. Net change by Change Orders................................................................ S
13. Current Contract Price (Line 1 t 2)....................................................... $
14. TOTAL COMPLETED AND STORED TO DATE
I(Progress Estimate, Construction Allowance and Change Orders)....... S
5. RETAINAGE:
a. X $7,226,379.01 Work Completed.......... $
b. X Not Used $
c. Total Retainage (Line 5a + Line Sb)................................ $
6. AMOUNT ELIGIBLE TO DATE (Line 4 - Line 5c)............................. $
7. LESS PREVIOUS PAYMENTS (Line 6 from prior Application)........ $
8. AMOUNT DUE THIS APPLICATION................................................I $
9. BALANCE TO FINISH, PLUS RETAINAGE
(Column G on Progress Estimate+ CA + Cos + Line 5 above) .............. S
10. CONTRACT TIME:
a, Days Awarded
b, Days Added by CO
C. Total Days
d, Days Charged
e, Days Remaining
Consent of Surety
Affidavit of Bills Paid
$7,192,666.51
$1,395,532.48
S8,588,198.99
$7,226,379.01
$7,226,379.01
$6,865,060.06
$361,318.95
$1,361,819.99
450
120
570
567
3
This document has been modified from its original form as an EJCDC document and the user did not highlight the
modifications. You are encouraged to read the document carefully and consult Legal Counsel prior to its execution.
C-620 Unit Prim Progress Estimate
Progress Estimate
For(wn=t): 2018 Bond Year 3 - Contract 6
APp6ratios Period: 11/01/2023 to 11/30/2023
It=
Bid Itam No. D-nptisn
City Saemmry 56638
Contract Num:
A B C
Specification Bid Quantity Unit Pries Bid Md.. Estimated Quantity
No. Udt ofMemuro Imtdled
Contractor's Application
AFplicatisn N=ml .. 23
APplicaeon Dotc 11/30/2023
D E F -r
To
tal Completed % Balance to Finish
V41us Previously lnsmlkJ Volvo Vdue This Pmiod Materials l'revndY dSmrel m Date
Stared (not in C) (--
(D+E) B
17 PVC Water Pipe _-..-
LF3795000000
$13693 $450.854.85
_... 3207.00000000
$438 M 8181 -.- --.-.
$438,813.81
543t1,613.81 97.3%
51204194
LF
100.000000
$14,449.00
81_00000000
$11,703.69
$11,703.69 81.0%
$2.745,31
_17DIPW.Wr, - - -_
Ir PVCWater Pli_
- LI
2314.000000
__$14L49
$93.01 $215,79458
2289.00000000
S212y88S6
__$11,703_69
t212958.55
_ $21IZ968_56 _9B9%
-522=00
ON PVC WaIM pipe--
LF _
88.000000
57991 $7,03208
74.00000000
$5,97334
$5,913.34 -..
$5,973.34 84.1%
$1.118.74
12Gale VahT
EA
13.000000
534064_91 5
84383 1200DOOMO
336.77892
S23%
53,064.97
_
B'Gete V.N. - - - - ------ --
EA -
11.000000
$1$7030 $21,671M
11.00000000
_ _.
SY7.67330
_.-$W.77892 _
521,673.30
-._ --$36.778.92
$21,6TJ.30 100.0%
Gate Valve
FA
9.000000
S+z270.6
7.00000000
39,%093
778%
$2,845.98
- _ _ _ _-- _
8' Waterline Lgwednq -
_fr
_
EA
3.000000
58,756.88 a16,270.64
$8.756.88
_ 200000000
517,513.76
. 17,56093 _ _ _
$17,513.76
17.513.76
_ $17.513.76 66.7%
E8,756.811,
_
Flre Hydrant and E>Qenslan
_
8_000000
$4,925_75 E39406.00
_
7.00000000
$34,48025
$34,480.25-
$34,48025 87S16
54,925.75
_ -_
Connection to Existing 4'-12'Waler Main
_ _EA __.
EA
_
11.000000
$4,925.75 $54.18325
11.00000000
554,18325
-
$54,18325
$54,18325 100.0%
-
1'Water Service, Motor Reeonneellon
EA
62.000000
E35575 522,056.50
66.00000000
52347950
$23,479,50
E23,479_50 706.5%
314q.00
1'Waror Service
$7,970.30 $722158.60
66.00000000
5130,03990
$130,039.80
$130,039.80 106
37,BB720
_
V Private Water Service Reloeabon
-EA -
LF
--_62000000
50.000000
$4926 SZ463.00
-_
_....-
111.00000000
;j ,dV.86
S5,467.86 --
_5%
$5,467.86 2226%
43,00496
- --- -
112'Waror Service, Meter Reconnadion
-_.
EA
- -
2000000
_..-_
578823 $7,53246
---_.
..-
-_
1 12" Water Serviw
EA
2.000000
$2,900.72 SW."$5,801.44
_ _ _-_
-
_$153245
2_Wrter Service, Meter Remnnadion
_
EA
14.000000
S875.69 572,259.66
9.00000000 _
_ 21_
S7,e8121
643%
$4,378.45
7 Water Service
EA _
14_000000
5339399 547,506.05
_
9.011040000 _-
_-$7,881_
-SWMA Al
_ ._
_$30,539.61
_57,88121
$30.539.61 643%
576,%6.45
Ductile Iron Water Fntinas w/Restraint - ----
_
TON
6.0000010
59,B51S0 $59,109.00
__-
5.70000000
E56,15355
$W.153.55
S%,15355 95.D%
$2955.45
Water Une Grouting
CV
76.000000
532838 524,956.B8
$74,956.B6
d'-1YWater Abandonment Pluq_------
EA
3.000000
$764.19_
$49257 3.00000000
$49257__--
$492.57
$49257 100.0%_
Remove and SaMae 6'Wrtar VeNe
10_000000
E109.48 31094.60
70.00000000
$1.60_
$1,094.60
$1,094_60100.0%
___ _ _
Removeand Salva..WWrter VSNe
___EA _.
EA
6.000000
3109.46
$656.76 6.00000000
$656.76
E656.76
$656.76 100.0%
Remove Fire 17 WrterVelve_
EA
$109.46
$995.14 9.00000000_
5995.14
E995.14
$298.66 100.0%
Hydrant-
Selvage Fire HWmn[_- _ _ _
_
_EA -
._9.000.000
$328.73 $3M.66
_
_ _ _ -. 7.00000000 _
52,721 64
- ._..
_--._ - _.. - $2,298.64 t00.0%
SeMao 3/d'WaterMder
EA
8.000000
BB:000OOD
554_73 33721.64_
68.00000000_
_ 53,721.60
$3.721.66
33.721.64
53.721_64 100.0%
_
SaNecel'Water Maier
_
200DOW
554.73
$-109.46--__ 1.000000_D_
4..73
$5_4..73- --
-.-_ $54.7-3 50_.0.%
$54.73
SaMae2WrterMrte
- -_FA_
EA
10.000000
$54_73
$Q. 0 9.00000000
$49757
$4927
149257 - 0.0% -
513
-Remove.Selvage, and Ransil Brlelu(AM Mary's Croak) -
_SV__
50.000000
$216.73 S1083SA0._..
_$_5
13.77000000
S2,98437 ..._-.__.
32,984.37
_. _52,984.37 275%
S7=113
T,*ad Gob!- - -
CY
100.000000
51,23CE $120.407A0
4837000000
S58,240.87
$59.240.97
55B,24097 48.4%
$62,166.13
- Concrete Flu.. with Steel Past,
Sy - --
- -_
- 25.000000
$34490 S8.620,00
_
15.33000000
-_
S5,285.78
$5,285.78
S5,2t15.70 613%
$3,33422
Concrete Rlprao_
Sy -
120.000000
536i41
60920 _ 6208C00000 _
522,560.49 --
_522,580.49
522560.19 51.7%
521,048.71
6' Wide Asphalt Pvmt Roper. Realtlentlal _-_
LF
50.000000
56020 53,0543,10.00
-
_ _ _
_
_ _$3,07090
Asphalt Pvmt Repolr B y nd DeMed Wldlh, Rmidentlal
Sy
100.000000
$6020 $6,020.00
air (7 HMAC on 6' Fledble Bose
LF _ 7505.000D00 521.89 5164,284.45 _ 6626.00000000 _ __$145,043.14 _ -__ $145,043.14
SF 120.000000 $1.90 $=.SO 1049.92000000 S2089.34 520B934
_- - - ___.. -... _--_.-__
sr _ 120.0000a0 s17e.ez azl,alo.eo 579i000000 _ s1o.33aa9 _ $10.33ao9
- --- - .
AaareaatP SF 120.000000 $15.43 $1,851.60 5909000000D 59,117.59 39,11759
9Y _- _ 50.000000 $179.42 __. $8,921.00 . -
3305.0202_lmoaned Embedment/Backfill. CSS
3305.0203 Impeded Embed ment/Back011, CLSM
3305.0207 Impeded Emlwdment/Backfll, Select Fill
0261.1300 Remove Cone Curb E Guitar
0241.140D_Ramwe Cont, Valley Guner
0261.1700 11* Pavement Pulver®Bon
61
3471.0001 T.Mo Conirol(Water)
62
0171.0001 Construction Swldm (Wotan
63
01719001 Construction Survw (GPS Red Line Survey)
64
9999.0004 Water Construction Alb -race
UNn 2-San6ary Sewer Improvements
1
3331.4WB 47 Flberoloaa Sewer PIPe (SN 72)
2
3331_4317 24' Sewer Pipe (PS.115)
3
3331.432124'DIPSewarw/Protective401 Coatlno
_ 4
3305.1007 47 Ceaing By Open Cut
5
3337.4175B' Sewer Pi. (PVC SDR 261 --_ -.-
6
3331.41198'DIP Sewer Pipe w/ Prowedw 401 Casing
7
3339.1001 4'Manhob _-.
8
3339.1_003 4' Etlra Dedh Manhole --
9
--
3339.1101 S Manhole
10
.
3339.1103 5' Extra Deoth Manhole
11
3339.1201 T Manhole
12
3339.1203 G Fstre DePN Manhole_
13
3303.0001_Bvoass Pumol_no
14 -- -
- ..1. Uner-4'Sawar MH
-- 15
3339.0004_Une 5_S--r MH
16
_3339.ODD5 Uner-GSewer MH-_--
LS
1.000000
SMAS
$273.65
LF
3871.000000
$0,05
$183.55
3671.00000000
_ S183S5
_ _ _ E783.55
_
-- -EA- ---
_
- 8.000000
311 A13M
$105C8.24
8.00000000
E105U824
$10.50824
CY
50.000000
$109.45
- $5.473.00
_
CY
_
50.000000
E15325
S7,662.50
cv
50.000000
E3294
_
LF
__
1192000000
$5.75
_E7.642.00
$6.854.00
570.32000000
S327934
$3,27934
Sy
75.000000
S51.74
S3,B80.50
1C8.89000000
_
E5,63397
_
$5,633.97
Sy
2165.0000DO
_
SBS6
_
$18.703.60
_
2075.46000000
_ ---
$17,76594
$17,76594
CY
26.000000
S2S.49
$740.74
3200000000
$911.60
$911.68
-TN
__-36000000
$221.11
_ _ $7,9%96
44.000WWO
$9,728.84
$9,72B.84
sv
2f85.000000
528.05
- _
567,28925
_
1984.46000000
555,664.t0 -
-
$55.664.10
LF
1197000000
_ _
E5001
$59,731.12
_
432.32000000
$21,663.56
$21,66356
Sy
715.000000
$72423
E7,951.75
10425000000
$72950.98
E1295098
EA
7.000000
$3722
$3722
CV
---104.000000 -
-_-E50,36 -
$5236.40
Sy
_
630.000000 __.
_- $420
_ _
$2,64800
EA
3.000000
S75.08
$22524
EA - --
- 9.000000 - -
- - - $479.65
$4,316.85
9.00000000
$4,316.85
$4.316.85
sF
9_20.000000
$42.26
s3B,87920
945.00000000
S39,935.70
SW.935.70
_
LS
_
1.00DD00
$3.831.13
$3,831.13 -
- _ - 1.00000000
$3.831.13
$3,831.13
-- -LS- - -
1.000000
$131,353.25
$131AS326 ---
140000000
$131,35326
$131,35325
MG
.000000
$1,.8
$8,209.80
5.00000DW
LS--__--1.000000
_
$B.7575 6.89 _.-
_
$8.75889
-. _S8,2(_I9.80
$8,756.89
$8.756.89
LS_
1.1100000
$4,370.44
54,378.44
_1.00000000
1.00000000
54,378.14
LS
1.000000
SBQ000.00
$BO,COC.CO
_
_$4,378.44
_ _
LF--1030.000000
LF-
549257
5507,347.10
1030.000OOOCO
-
5507,347.10
.._ ..
$507,347.10
LF
1872.000000
575723
5494,396.06
1804.00000000
_-_ E464,01292
$464,04292
LF
325.000000
$333.86
E108,504.50
-
_
LF
60.000000
$547.31
532838.60
60.00000000
$32838.60
532,838.60
------1293.000000
LF
$125.88
$16Z7S284 --
-- 1333.00000009
5167,798.04
$167,798.04
-- - -
_-
_
LF
65.000000
S164.19
$10,67235
-
FA
71.000000
56,567.66
_
572,24426
_ __--
11.00000000
572,24426
VF
9.000000
521345
$1,921.05
797000000
_.
57,70120
-57224426
$7,70120
- ----------
000000
31$32221
_
$170759.68
11.000OOOW
5$12,4BB.43
5744,258.63
-- VF
48.000000
532455
_-_-
.__
37.%000000
_
512,254_43
_
- _--
FA
_ ..
9.000000
$15.3_$474.55
137=,6B _
$$14.76096
__
- 9.00000000
___?12,254.43
$$14.17095
_ $$14.17095 _
--- VF
3_1.000000
5476.78
514,760%
79.76000000
514,17052
574,t70.52
LS
1.000000
_
5295,546.84
$295544.84 ...
-. _- Vle
10.000000
$344.80
$3,448.00
Vle -..._-126.000000
$492.57
$52409.70
13B.00WW00
$57,401$39.110.06 _._
VF
75.000000
$492.57
- _E36,94275 _
79.10000000 -
539,110.06 _
$39,11.10
539,110.06
06
E145,043.14 88.3%
519,24131
- ---- - --- - S2,089.34 _674.9%
_ _ _ 41,850.54
--
S70,334.09 48.3%
$11,078.31
S9,117.59 492.4%
-.-.---
47265.99
.___.
- _.
36,921.00
_3273.65
SiB3.55 100.0%
$10,60824 100.0%
--------S51473A0
E7,662.W
$1,94200
53,279.34 47.8%
$3.574.65
55,63397 7452%
31,753.47
S17,76594 95.0%
$937.66
$911.68 123.1%
417094
_ $9,728.84
_1222%
355,664.16 908%
_41,7688t1
55675.15
- 521.663.56 363%
$38,06796
E7295098 46.3%
-
$15000.77
$3722
52,646.00
522524
--
E4,316.85 100.0%
$39,935.70 1027% LLL41,05650
i3,831.13 100.0%
$131,35326 100.0%
--
- $8209.60 100.0%
_SB.756.89 100.0%
-- $4,378.44 100.0%
SBQ000.00
$507,347.10------
$464,04292 93.9%
$30,353.14
$108 504.50
_ S3283S.60 100.0%
5167.798.04 103.1%
45,03520
- _
$10.07235
_- -- - - -.
- - -- S72.24426 100.0%
_ $1.70120 BOB%
-$46%
S219.65
_ $144,488.63
$2QY70-65
$12,254:43 79.1%
$3.245.25
$137,920.95 100.0%
$14.170.52 95.0%
$590.44
$3,448.00
_ 557,401.10 1095%
44,991.40
SW,110.06 105.9%
32,167.31
This d-oa, It. been modified f ip oil f m on E)CDC doenment and the use did rot highlight the
modi6rati- You ens prcoumgsd tP reed the document -11.11y and comult Legal Com I Prior to to -pion.
C-620 UM P6en Pr"g,— E dimaf
Progress Estimate
2018 Bond Year 3 - Contract 6
IA�gcotion Pciod: 1VOW023 to W30l2023
A
Itw 111
Bid I— N. I — 1)eettipfion I Speci -- lhdt oCMwure
Section No.
City seeremty 56638 Contractor's Application
Conhnct Num:
Applim6an Number. 23 l
AFPlimfion Dote: I1l302023 1
H C D F. F C —
T"W Completed % B"lonce to Finieh
Qum b EsfunotM QunntlN M_iols p_Uy
Bid li Unit Face Bid Vnloc W. P—ioucly fsmlled Value Vnlue 7Nslsaiod and Slmdm Dnte (F) (B -F)
]totalled Stmcd (oot m C7 (D I B _
27.000000 53,283.83_ _ SB8663.41 _ _ 25.00000000 582r0%75 582,09.5.75 112 �.75 926% 36567.66
34.000. $229.87 $7,815.58 29.00000000 36,66623 _ 56,66623 _ S_6,66623 55.3% 57,149.35
This documrnt hen been modified Qom iN "riciul farm ® m FJC➢C document and the usm did not highlight the
modifiafions. You me rneoutoged W rend the docummt mreflly and —It Le W Counsel pdar m i6 —fian.
C-620 Unit Price Progress Estimate
Progress Estimate
Far (OnhvC)' 2018 Bond Year 3 - Contract 6
Applioatien Paind: 11/OM023 to 11l30l1023
A
City Seentacy 56638
Co.-, Num:
C
Contractor's Application
Applimtion Number 23
Application Daa: 11/3012023
lam
SpeciDcatian
Bid Quantity
Unit Not,
Bid Value
Esame8led Questiy
Value
Pmwaudy Wattled Vnluc V"lue Thin Paiad
Bid lass No.
Dassdptipe
Unit ofMawro
Sattios No.
led
19
3305.0116 Concrete Enemement far U9lty Pipn
CY
3.000000
$65fi.77
51,970.31
10.00000000
56567.70
_- - - $6,567.70
20
9999.0D01 30" Dhgad Peir, Complete and In Plena
__
CV
36.OWWO
$1.034.41
S37,238.78
4.500W000
$4.654.85
_ _
Sg654.85
21
Pier Head for 47 Casmo Pioe. Canplete end In Place
EA
-
$4,376el
$8.756.90
200000000
$9,75690
_§8,756.91
22
3305.0112 Concrete Collar
3305.0112
_ _
---- EA
7.OWWZ000000
37.000000
N,099.61
_
540,500.57
_
31.00000000
f33,93291
_ _ _
$33,93291
-23
0241TW7 Sanaery Une Gnutln_q
CY
198.000000
$197.W
$39,01194
61.0000001110
E12,016.63
_ _ 572018.83
24
3135.0103 Twisted Gabions - --_
- _-_
CY
-- ---
30.000000
---75.000000
$71150
- - -
527,345.00
-
37.33000DOO
$26,580.30
_ ---
_
-- $26,550.30 - - - - -
75
3736Af00 Twisted Gabion Mattresaas - -- -
CY
St
,$602D
37.19000000
�
--
�
25
3201.0113 V Wide Permanent Asphaft Pvmt Receir, Residential
- - - --- - LF
- 1SO.O0m00
E8020
59,030.00
- - _
- _
27
_ _
3207A201 Aiphett Pvrrit Repair Beyond Defl� Wkth, Residential
-
BY
150.00000.0_
$60,20
19,030,00
3201.0400 Temporary Asphalt Paving Repair (r HMAC an 6" Fletlble Base
28
Course) --_.-
LF
4665.000000
-
$40.50
S188,93250
-
4384.00000000
5177,55200
E177,55200
29
-
3201.0614_Conc Pvmt Repair, Residential -
BY _
50.000000
§178.42
_ $3,921.00
_._ _ 78.38000000
$13,984.56
- E13,984.56 _- --'
30
3211.0112 6' Marble Be.. Type A GR-1
-
SY _
_
_ 150.000000
E25.67
33,850.50 -
-- --
--- _
31
3213.0301 4" Cem Sidewalk - -
SF
685.00WW
$8.99
36,158.15
782.200W000
S7,03198
$7,031.98
32
3231.0121 4' Chain Unk Aluminum
LF
150_000000
$29.17
54,375.50
50.00000000
$7,45850
_ _ $1,45850
33
3231A212 Smooth Wes Fence, Metal Posts_
_----
LF
40.000000
$29.01
_
$1.160.40
170.00000000
34,937.70
_ _
$4.931.70
34
3231.0472 6 Fences. Wood
-
LF
160_000000
$45_70
57,31200
- -
6200000000
52851.40
- --
- - S2B33.40
35
9999.000-4,r Fence. Wood Past Rall(SeNaw S Reuse) -
LF
75.000000
$17.19
..._._
$128925
BOA0000000
$1.37520
_
$1,37520
36
02412207 Remove 4' S-1 Manhole- _
EA
15.000000
$49257
S7,388.55
15A000DDOD
_
S7,3BB.55
- - -- --$7,380.55 -- -
37
02412202 Remove SSewer Manhole
FA
1.000000
E858.78
$656.78
7.00000000
$656.76
§656.76
02412301 Remove Sawm Junction Structure (Uno `A"Ste. 10*83.50, Sh.26)
38
_
LS
1,000000
$2,079.76
$2,079.76.______-,
1.00000000 _-
§2079.76
$2,079.76
39
-_
02412301 Remove Sower JunClonSWcture(Une"B"Ste. 10+30, Sh.29)
LS
1.000000
$4,925.74
_ $4,925.74
_
0241.Z101 Remove Sewer JuncllanSWeturo (Etna"E"Ste. 70*66.60,
40
LS
7.000000
54,9$1.59
3
- --
41
_ 0241.0
0261.0700 Remove Sidewalk
SF
250.000000
_
_ E7_59
. _
$39774
539750
78220000000
51243.70
_
42
0241.0500 Remove Fence
360.000300
576.42
55,97120
_
11200000000
51,839_04
$1,839.04
E1,839.04
_
43
0241.1300 Remove Cons Curb S Gunar
_LF
LF
150.00WW
$5.75
seam
_
_
M
3110,0102 6'-17Tm"R"mova1 -
--- EA
7.000000
SM23
S5,363,61
5,00000000
53,831.15
$3.831.15 -
45
_
3110.01012'-18"Tree Removal
FA
5.000000
$1,313.53
6,567.65
1.00000000
$1,313.53
$1,313.53
4 6_
3110.0104 18'-26"Troe Removal
_ _
FA
3.000000
52,798.fiB
$6,896.04
_ _
47
3110.0105 24' and Lesser Tree Removal
FA
_
1.000000
53.283.8.4_
$3,283.84
-
- - -
_ _ _
48
_
3305.0202_ Imported Embed-ra/6 1,50. CSS
CY
50,000000
$109.46
E5,473.00
- - - 49
3305.0203 Imported EmbedmeneBackfll, CLSM
CY
50.000000 _
-50.000000
3153.25
E7,66250
50
-_ 3305.0207_ Imported Embedment/Backfill. Select FIII
CY
_ $32.6.
$1,642.00
---
----- -- - -
51
3301.OD01 P,.CCNlnsoactlan
LF -
500.00D000
_
$7.66
$3,83BDO
52 --
330.1.0002_Paet-CCN Impeetlan - -
LF
4600.000000
$1095
ESD,370.00
4523.00000000
$49,526.85
$49,526.85
--53--
9999.0005_Flriel-CCN lrupectbn. Manhole
EA
32000000
$109_46-
54
3305.0103 Evio Mory Etas vatlon of Exhtine 1. ch ies
4.000D00
S1.313.53
55,254.12
4.00000000
3$,2,.1.12
_ $5254.12
55
3305.0109 Trench Safety
-EA -
LF -
_ _ _ _
_ 4680.000000
$1_09
55,10720 _
3438.00000000
E3,747A2
_ _
_-_ - S3,747.42 _
56
9999.0006 Temporary Construction Fare, Cheln Unk
LF _.
-__13BO 000000
$3.83
55,285.40-
742000WDOO
S2,B4196
S2541.86-
57
3291.0100 Topsail
CY
74.000000
$513.35
5372S_90 _
30.000WO00
51,51OS0
_ _ 51,51050 -- -
58
_ _ -- - -
32920100 Block Sad Plecemem
-- SY _
1900.000000
$7,990.00
716.670D0000
_53.070A1
_ $3.010.01
59
_
329ZD400 Seeding. Hvdromulch
SV_-_
1040.000000
_$420
St.75
51,820.00
2950.0000000)
55,JSVM
- $5,16250
GO
_ _
0241.1700 11" Pavement PulvarfaBan
_
SY
1980.000000
$925
$18,315.00
1446.91000000
E13,3B3.92
$13,383.92
61
3211.999 Unclaasl0ed ErqqwIssISYtlon by Plan
CY _ -
$633.3t
62
3211.9999 Cem-Ume 301ba/SY
TN
30 ODOWO
30.000000
221-11
§221,11
$6,633.30
-
24.00000000
_---
$5,306.64
----_-_
E5,306.64 _.
63
321203033"AspMlt Pvmt Tvo_eD
_-____-.
-
1900.000000
_--
$2B.T7
554,663.00
14469100000D
$41627.60_
$41,627.60
64
3216.0101 S" Conc Curb and Gutter
_ -Sy
LF
150.DWD M
$50.11
S7,516.50
65
3125.0101 SWPPP 21 sere
LS
1_000000
=2.736.53
E2,736.53
100000000
52,736.53
52736.53
65
_
3471.W01 Traffic Conwl(Sevmm)_•
MO_
S.ODOO60
$1,64192
SBXk.60
_5110000000
___
$8,209.60
67
0171.0001 Ocomaraction SurveY_(GPS Red Lm Slaayl_
LS
1A00000
_
57,6512E
57.66228
1.00000000
_$6.209.60
S7.66=
Be
0171.0001 Cemtructen
LS
000000
$4,378W
$4,378_44
1.00000000
E4,378.44
_..$7.66228
E4,378A4
--BB
uction lloyam-__
9999.0OW Sewer Comwction Allowance -- ---
- --LS
1.000000
5700,OODAO
510D,OOD.00
_-
-
33392WI SenitarySower Junction Bes,Shnderd Comm wkh Conshield
70A
Admbdure(11Lx9Wk8&D-Llne"E"Sta.10+66.60.Sh.34R)
-_.-_
_ LS
1.000000
S60,203.58
S60,20148
UNITS-Pl. Improves ment
_
1a
07A7.1700_1J"Pavement Pulvedmtan
SV
14920.000000
$6.98
5104,141.60
1103ii6.80000000
E97,976.86
$97,976.86
3
_
3123.0107 UnclassEad Esevatlon by Plan
CY
654.000000
$34.85
322,791.90
$8,434.75
S8,434.75 -
_
3
3217999 Cem-Ume 30bs5Y
_
TN
-
242000W0
E221.11
_
58.62
_24203000000
184.000000
S40,fi8424
-
540,fi8424
M
32120303 3'Asphalt PwntTYpe D -
SY
14820.000000
$28.04
$388,576.80
13963.30000000
$363,604.33
_$363,604.33
A
3216.0101 6- Conc Curb and G1mer
LF
_
10210.000000
_ _
550.11
._._
S511 623.10
-.._
9954.50000000
5498,820.00
-....___ -
E498,B20.00
Be
32769999_lav Down Care Curb endGwar_
LF
25.00000U
$1,10150
25.00000000
$1,101.50
7.
3216.0301 rCam V&WG" Realdamial
SY
150.000000
_544.06
f12423
S18,63450
9278000000
-57,101.50
8•
33D5.0111 Valve Bot,AdiushremL lndudim Concrete Collar
-
FA
26.000000
S537_41
$13,472.66
22000ODOOD
_51�526.06
$11,623A2
__$11,526.06
E71,823.C2
----9.
_
3305.0112 Concrete Cedar
_
_
1.000000
_E1930.44 _
- -
_ 57230.44
- - -- - -
10e
_
9999.DD07 TXDOT Item 422 - Bpwo ridae Aech Slab MAS-Al
_EA
SF
92f1.000000
$4226
§3B,87920
945.00000000
539,935.70
$39,935.70
8
0177.0001 Construction Stekinq (Paving)
LS
1.000000
810,946.10
$10,946.10
1.00000000
$70,946.t0
$70,946.10
10
0241.0100 Remove Sidewalk
SF
2412.000000
E1.59
E3,035.08
2387.44000000
$3,764.23
11
0261.0200 Rempv-e Step
SF
50.000000
-
$5.60 -
$280.00
_53,764.23
12
0241.0300 Remove ADA Ramp
_
EA
1.000000
5345.65
5345.65
13
0247.0401 Remove Camrete Drive
SF
10300.000000
E7.14
E71 74200.
7901.7B000000. _--
$9,008.03
$9,008.03
14
0241.0402_Remove Asphak Ddve_
_. -_
SF
820.00WOO
51.42
_-
_
-- 15
0241.0500 Remove Fame
LF
50.000000
$1642 -
_ $821.00
5821_00
_-
_
16
0241.10DO Remove Cam Pvm
--- ---- SY
_
4760.000000
59.07
$43,17320 -
23482200DWO
$21,29836
321,29636
17
0241.13DO Remove Cane Curb S GLOW
LF
8796.000000
$3.37
$29 64252
10394.10000000
$35,028.12
$35,028.12
18
0247.7400 Remove Cane Valley GWW
SY
150.000000
E71.44
57,716.00
9278000600
$1,061.40
$1,061.40
19
.0Remo" Speed Goshen
3.000000
5W.43
S6B229
.00000000
5.
2
-
3110.0101 SaeCl nnq --- ---
------B-
BY -
200.000000
--
=99
§4,598.00 -
_$68229
200.00000000
54,598.00
-54,598.00
- 21
_ -- _.--_
3110.0102 6"-12' Tree Removal
_ _ EA
2000000
$766.23
$1.532.46
22
3170.0703 17-18 Tna Removal
EA
4.000000
$1,313.53
§5,254.12
1.00000000
E7,313.53
E1,313,53
_
23
_
3110.0104_18"-24'Troe Removal
_
_ EA
_
5.000000
52,298.68
$17,493.40 _
200000000
S4S97.36
$4,597.36
E IF G
Ca rpletod ,
Bolen to Finish
foal
dS st m Dme (F)
g,on,dsmin Ci
Stored (net lu C)
(D - E) B
- - -- $6,567.70 333.3%
34,597.39
$4,654.85 125%
532,M.92
SB,75690 700.0%
$33.93291 _83.8%
S6,567.66
$12018.63 30.8%-__--526,993_71
$26,560.30 124.4%
35,215.30
544,77936 49.6%
589
$9,,30030..00
59,030.00
_E17755200 94.0%
E11,3BO.W
___ $73,98456 156.8%
.35,053.56
S3.850.50
-- S7,031.98 11142%
5873-83
E_7,45650 -333%
32,91700
-------$4,931.70 425.a%
_..
S2.833.40 38A%
._33,771.30
54,478.60
$1,37520 105715_
485.95
$7,388.55 100.0%
_
3656.76 100.0%
S2079.76 100.0%
$4,925.74
$4,925.74
_- __S1L243_70 312.9%
384620
31AM.04 31.1%
-54,07216
$86250
$3.831.15 71.4%
SI,SM416
$1.313.53 23.0%
55,754.12
_
$6,6%.04
53283.84
$5.47.3.00
57,66250
_ §1164200
53,830.00
549,5WM 98.3%
_-_ S843.i5
..
53,50772
$5.254.12 100.0%
_- -_ $3.747.42 73.5%
$1.353.78
S2841.86 53.816_
-__ S2,443.54
--
$1,51010 40,5%
--$3.010.01
52,2f 5.40
_37.7%
$4,969.99
_ 55.162SO 283.7%
S3.34250
-- $13.383.92 73.1%
56,931.0E
-
$5,306.64 80.0%
_ $1,326.66
S41,E27.60 762%
__ $13,035.40
$7,516.50
szPew 100.0%
se,x .60 100.0%
_ -- 57,85229 100.0%
$437E.44 100.0%
- --_ _ --
-S100,000.00
$60,203_58
$97.976.86 94.1%
$6,164.74
- _
$0.434.75 37.0%
$14,357.15
- - - - -- - $40,68421 76.0%
E72,824.38
$363.604.33 916%
_ _ $24.912-47
S498,820.00 97.5%
S72,BO:d.10
$7,701M 100.0%
-- -
311526_06 61.9%
37,708.44
_ $11.8M.02 84.6%
S2149.64
_--
5I $1 1116
$39,935.70 1027%
_
_31,056.50
- - - $10.946.10 1910%
$3.76423 982%
Raw
__.. S280A0
$345.65
- _$9,608.03 mm
$2,733.97
$B90.40
SBY7.00
_- $21.298.36 493%
$21,874.B4
_ $35,02B.12 1182%
s5=.6060
$1,051.40 619%
$654.60
$68229 100.0%
S4,596.00 100.0%_
51,532A6
E1,313.53 25.0%
$3,940.59
$4,597.36 40.0%
$6,896.04
This ducmnmt has Iem modi6cd fmm iu ori6insl fort man E1CDC document and 11 user did not highlight the
modifimtima. You are eocaumged a reed the dowmm[ wcfuily and eortmlt Legal Counsel prior to its arcutian.
CS= Unit Prim Pragnns Estimate
Progress Estimate
city S—y
Coaeaa Num:
56638
Contractor's Application
Fa (mnaaa):
2018 Bond Year 3 -Contract 6
-
Application Number. 23
Apphmhm Prnod. 1 VOW023 to 1 WO/2023
Application Date: 11/30/2023 JJ
A
B C
C
D I E F
Ran
IitG IWn No. D-shine
Speeifiwfion
Umt ofMeoaae
Sation No.
Bid Qumtiry Unit Ri¢
Esamated Q.. V
Bid Value
h.WW
ou Balance to FinI
Malaiols)' y
Vnlu Prep ly 1n 11ed Value Value This Period and Stored to➢etc (F) (B�
Stored (aotw C)
(D - E) 0
24 3110.0105 24' and L,erAerTree Removal
25 3,23.0,05 Barrow by_Delivery_ ..— — - —
EA
CY
1_000000 E3,283.84
810.000000 $33.31
E26,gB1.10 _ _.. _ _._
_ _ - $25.981.10
This daa—t has been modi5cd fmm iv o igiwl farm as m FJCDC dommmt and the ma did not highlight the
madi5wtiom. You me rncoumgcd to read the dommrnt cmefully and —11, Lego[ Counsel prior to its aaccuea.
C-6M Unit Pdce Progress Estimate
Progress Estimate
For (Contra°)` 2018 Bond Year 3 - Contract 6
Applimn. Paio L 11/01/2023 to 11/30/2023
A
City S-Y
Conhvct Nam:
I-
Bid Ikon No.
I)miptim
specitiimdon Unit of Mmme
Bid Quantity
Unit Pd.
Sation No.
26
3125.0101 9WPPP a7 sae
LS_-
_ 1.000000
- _
SZ73
27
3217.0172 8' R.N. Be.. Tvee A GR-1
_ __.
- - - SV _
312000000
--25.000D00
E2
28
32I20401 HMAC TranalUo_n - --
TN
29
_ _
3213.0101 6' Cone Pvmt -
Sy
26.000000
$17
30
3213.0301 4" Cone Sidewalk.SF
--_ _.-
- _750.000000
S
31
321&0311 4" Cone Sldewalk, Adraced to Curb
S F
000000
$
32
3273.0321 Con Sldewalk. Adlacem to Rot Wall
_
SF
_am
SWOOD00D
$
33
3213.0322 Conc Curb at Back or Skla lk-
- -----LF---
12CEOD0000
$2
34
3 & W01 6"Conte Drivwmy
_
SF
_
1277a000000
S
35
321&0403 B" Concrete Dri-V -
-- - SF
250AGODDO
$1i
36
3213.0451 6• Concrete Drivavay. Elmoeed lwareoate
_
SF
15OD. OMM
St'
37
3213.0322 Cone Curbat BaakdSiW-k
_ _
- LF
WOOD 00
Sy
38
3213.0505 Bonier Free Ramp.Type M4
EA
_
2000000
5273
39
3213.0506 Border Free Ramp. Tvpe P-1 -
_
-- - EA
2000WO
SZ71'.
40
3213.0507 8aMer Free Rama. Tvee P-2
_
EA
3.OD0000
52ef
47
3214.0300 Brick Sidewalk Reeelr
Sy
_ _125.000OW
$21_i
42
3217.0002 4' SLD Pvmt Markin HAS (Y)
_
LF
750.000000
$
43
3217.0501 24" SLD Pvml Markin HAE (W)
LF
15.000000
v.
44
3217,21 n3 REFL Rabed Marker TY II -A -A
_ _
38.000000
S
45
3217.5001 Curb Address Paintino
_ _ _ _ _ ____EA___
- EA
80.00000D
$3
46
3231.0111 4' Chain Unk Steel
_ _
_ _ LF
_
50.000000
9
47
32370100 Conc Re Wall Adlaeonito_Sklewalk
_ _
SF
200.000000
SIR
48
329t.0100 Toonal
1825.000000
S51
49
3292.0100 8lack Sad Plpcamo d
_ _ _CV
SV
107W.000000
S
W
3305,0107 Manhde Adlustment Mhuu_
EA
32000000
S58
51
3305.0108 Mlscelleneeuo Adiustmera(Idaation)
_. _.
LS
1.000000
SW ,OG
52
3305.0108MIseallannous Swpturo Adiustment(WM). S' or Hlaher
---
EA
73.000000
Sa
53
3346.0008 4 Piee Underdain, Tyro 8 � -
- - LF _
_ 100.000000
_ S4
54
3441.1301 Loop Detector Cable Sawcut
_
LF
175.000000
52
55
3441.130214 AWG Loop Detect Cable
_ LF
190.000000
S
-_
56
-
3447.4003 Fum&Mnslall Alum Spn Ground Mount City Std..
EA_
_ 2000000
_ $471
-
57
34414004 FumishAnstall Alum Sion Ex Pole Mount
_ _
EA
_ 2.000000
$131
se
3441.4006 Ineall Alum Sion Ground Mount
_
EA
1.000000
$411
59
_
3"1.4110 Remove end Reinstall Sion Panel and Pod
_
EA
-
10.000000
SSe
W
3471.0001 Tmfnc Control
_.
MO
_
5.000000
_
_§7,34
61
9999.0001 Concrete Steps
SF
50.000000
__"
62
9999.0002 Remove and Replace Etc Mail Bax. (Bdckl_
EA
_ 1.000000
4za
63
9999.0003 Remove and Relocale Mail Box (Post)
_
EA
1.D00000
-
SBT.
64
9999.0004 ScourStopp1 Mat Cover(Graen)
Sy
25.D00000
$12
65
9999.0005 Stone Sidewalk Reeair
Sy
_ _ W.000000
614
66
lovm
9999.000E Paving Construction Awa _
LS
1.000000
__ SIOD OIX
Totals
56638
Contractor's Application
APplicatioe Nambm:
23
...
APPliwtian Dak:
11/302023
B
C
D
E
F
G
E+lmatd QuaetilY
MmmiAaP ay
TaI!CompltW ••
Balance to FWeh _
Bid Vdue
IaWkd
VA.
Prevkedyfewlkd Velae
Velee 7ltia Period Stored(.or in C)
and S(-d to Dote (F) _
(0
D -E) B
q 57,736.53
0.75000000
3205240
32,05240
42 052.40 75.0%
_-$684.13
7 $8,OD9.04
9.0000000D
5231.03
$231.03
E231.03 29%
$7,778.01
b 53,750.00
5200000W
_ _- -
3780.00
E780.00
_ _
- _
E780_00
52,97n.DO
12 $4,638.92
_20_8%
S4,6W.92
p
2845.6_40._00._0-00
$35,
52,53Z3o
S7&839.W
,74250
B $769177.W
5044.47000000
..2W
_$46.308Z
_,3OB23
546,30823
Is S3.00
- _ -
_58,5%_ __-_.532B927
.
$338.00
1 $277320 _
144.5000000D
$3,339.40
--- $3,339.40 _
53.339.40 _ 2-D. %_
456620
13 $125,607.74
11707.93000000
$115,OB8.95
$115,08825
_
$115.08895 91.6%
$10,$18.79
q E23,145A0
117.00000000
$1,80531
$7,80531
31.805.31 79%
$21,339.69
q 51A16.50.
51,016.50
N 55,168.68
_-_2000001100
$5,468.68
___55,468.68
_ _ _ _.
35,468.68 100.0%
5 S5,42490
_._
200000000
35,42490
55,424.90
$5,424.90 100.0%
_
W 7,9
_ _
3.1700000W
-
37,___7.838___
._ _
__- _552
$7008.52 100.0%
3 E_Z_7,0912525
.__.
$27,09125
5 3945.00
750.OD0 00OOD
59d5.W
_-
$945.00
_ _..
_ $945.00 100.0%
_ _..
i0 5234.W
14.00000000
E278.40
_.. _
$218.40
.
$218.40
$15.60
_
'6 $180.88
_
21.00D0000D
_
599.96
----_-$99.96
_-
_93,3%
$99.96 55.3%
$8D_92
_
2 $2,977,60
63.D0000D00
_ $2,344.86
__. _ S2,344.86
_
$2.344.86 _ 78.8%_
_
q $1,094,50
-
_
_$63274
51,094.W
7_ -- -- $12.314.00
_$4,788.29
54,768.29
._
$4,168.29 339%
S8,145.77
5 391,888.75
8SODO00000
185.00000000
59,314.75
E9,314.75
$9,374.75 10.1%
E82,574.00
D SA.5,371LW
5508.33000000
523,13199
_$73,734.99 57.1%
57L183A1
8 $18.661.76
__
_
9.00000000
56248_82
-t23,13199
$5,24&B2
.. _ _ -
_
$5248.62 2B.1%
$13,41&14
0 360.000110
_ 0.03227755
51,936.65
_ 51,936.65
- -
51,836.85 32%
$58,063.35
'1 54,SO4.B3
_ _._
_ _ ._
-._. _
-___-_--
$4,504.83
B 54,926.W
30.00000000
$1,47790
51,47790
_
31,477.80 30.0%
$3,44820
0 54_,214.W
_
S4x4-W
7 $1,03930
$7,039.30
8 582096
17,00000000
56,978.16
116,378.16
56978.18 BW.O%
_
- 46,15720
3 1.
00000 2000
5273.68
__ $273.E_6 __.._
.__ �
__ 5273.8E 100.0%$4
8 5410.4848
$410.48
3 35,478.30
_
35,=96
2 SB,209.W _
450000000
SJ3B8_64
$7,388.64
E7�38B64 W.0%
$820.8E
3 3273653
_--_
52736.53
B SB75.69
6 53,OW.00 _
_._ _ 3022000000
53,70991
53,70991
_-_
$3,709.8181 1209%
4610.81
$7,224.50
31WA MOD
$7,192,666.51 SS4oe,667,65 SS466,667.65 SBAOS,687.65 752% $1,793.998.36
Thmdacam-t barnmdif.W it oigiWI uen FJCDC d-arcm ad the a am did not highlight We
mdi8wtiam. Ym, ma-mogd to rend Nc document c 19,11y and eomalt Legal C-1 Prim is iv a<acation.
C-620 Change Order
Progress Estimate Construction Allowance Usage
Contractor's Application
ADDITIONS
For (contract): 2018 Bond Year 3 - Contmct 6
101452-2
City Secretory
56638
Application Number
23
Contmct Nam:
Apphmtion Period'. 11/01/2023 to 11/30/2023
Apphwnan Dme.
11/30/2023
A
B
C
D
E
F
Item
Balanm to Finish
Toml Completed
Specification Quannry to Add
Unit Prim Addition ValueInsmlled
&timuted Quantity
Previously
Volvo
Value This Materials Presently
and Stored to Date (F) (D -F)
Item Number Description Unit of Measure
Section No.
imntled Venue
Period Stored(not m C)
(DIE) B
11148 j217.1016 Preformed Thermoplastic Contrast MndUnes-Leand Yi Paving-UNfF3 EA 30.00000000
S47.25 _ SI.417.50
12.00000000
$567.00 S567.00
_
_ S567.00 40.0% S850.50
M-89 3217.0502Prcformcd Thermoplastic Contmct Madrings-24-CmssWaving-UNFF3 LF _ 7200000000
S23.89 __ $1,720.08
70.00000000 _
S1.672.30 _ S1.672.30
_ ____
31,672.30 97.2% S47.78
This document bas bran modified from its original form as an EICDC dusancnt and the user did not highlight the
modirentions. You me encoumgod to read the document —fully and consult Legal Counsel prior to its esecutioa
C-620 Change Order
Totals I I I I I 53,137.591 I 52.239.301 52,239.301 I I 52.239.301 71.4% 1 S698.281
This dwumrnt een has bmodificd from its original form as an E1CDC document and the — did not highlight the
modi6wtions. You me cnwumgcd to read the document cmefully and conadl Legal Counsel prior to its e.N=ution.
C-620 Change Order
Progress Estimate Construction Allowance Usage
Contractor's Application
CONSTRUCTION ALLOWANCE ITEMS TO BE REDUCED
For (contract):
101452-2 2018 Bond Year 3 - Contract 6
Applieunon Number.
23
Application Period:
11/01/2023 to 11/30/2023
Application Date:
11/30/2023 1
A
B C I D
E
F
Item
i
Sp,,,ion Quantity to Delete Unit Prim Rduction Value Not Used
Not Used
Not UsedNot Used Not Uacd
Not Und Not Uxd Na Used
Hid Item Number
Description
I Section No. Unit of Mmsure
M-66
Paving Construction All-
Pavia¢-UNIr3 IS 0.03137590 $100,000.00 S3,137.58
Torah I I S3,137M
This document he, been modified from its originol form as an EICDC document and the user did not highlight the
modi5rntions. You are, encouraged to read the document carefully and consult D.cgnl Counsel prior to its cvecutioo.
C-620 Change Order
Progress Estimate Change Order Number 1
1
1
Contractor's Application
ADDITIONS
For (contract):
101452-2 2018 Bond Year 3 - Contract 6
City Secretary
56638
Application Number:
23
Contract Num:
Application Period:
11/01/2023 t0 11/30/2023
Application Date:
11/30/2023
A
B
C
D
E
F
Itvn
Addition
Total Complaed %
Balance to Finish
Change Orden Rent
Specification
CO Quality to Add
Unit Price
Changc Order
Estitnnted Quantity
Installed
Value
Perviously
Installed Value
Value This Materials at in C)y
Period Stored (vat in C)
ad Storal to Date (F)
(B - F)
No.
Description
Section No. Unit ofMeacure
Value
(D+E) B
3201.0400 Temporary Asphalt Paving Repair (2" 1114AC on 6"
LF
I1-28
Fle, iblc Base Course)
1200.00000000
S40.50
S48,600.00
1177.00000000
S47,668.50
$47,66930
S47,668.% 98.1%
$93130
II-52
3301.0001 Pm CCTVImpmfion
_ _ _ _ IF
1197.00000000
$10.95
$13.107.15
_
- S13.107.IS
0.55
3305.0109 Trench Salhry
_ LF
1200A0000000
$1.09
$1,308.00
1085.00000000_
$1,182+65
51.182.65
$1,182.65 90.4%
S125.35
IIS6
3471.0001 Tragic Control (Sewn)
MO
_2.00000000
$1.641.92
S3=.94
_ _
S3.283.84
0-71
exy
3331.440430- SForce Main(SDR121)
LF
_1197.00000000
S607.40
S727,057.80
_ _1193.00000000
$724,62920
5724,628.20
SM.62510 99.7%
S2.429.60
B-72
Sewa Fittings P401 Lived
1S
1.000.00000
S54,600.00
554.600.00
_ 1.00000000
S54,600.00
354,600.00
_
354,60D.W 100.0%
_
B-73
3305.0114 Manhole Adjustment, Major ww/Co von
EA
1.00000000
$3,860.00
33,860.00
1.00000000
$3,860.00
$3,860.00
53.860.00 100.0%
This document has been modified from its original Corm as an EJCDC document and the user did not highlight the
modifications. You are enceumgcd to read the document carefully and consult Legal Counsel prior to its execution.
Totals ......79 563...135 5831,939.35
This doeramm' has been malifi d from its original farm as an FJCDC document and the user did not highlight the
modificntions. You arc encouraged to read the doeranrnt carefully and eousult Legal Counsel prior to its execution.
5831,939.35I 97.7% 1 519,677.411
C-620 Change Order
C-620 Change Order
Progress Estimate
Change Order Number I 1
I
Contractor's Application
DELETIONS
IFor (contract)_ 101452-2
2018 Bond Year 3 - Contract 6
Application Number.
23
Application Period
11/01/2023 to 11/30/2023
Application Datc:
11/30/2023
A
B C
D E
F
Item CO Quantity to
Dcletion
Change Orda Itan
Spccifieation
Dexnpmn Unit ofMeosme Dddc
Uni[ IRia Change Order Not Used
Not Used Not Used Net Used Not Used
Not Used Not Used Net UsedNo.
I
Section No.
I
I
I I I
I
I
I I
Value
I
I
I I
I I
I I I
I
I
I
I I I
I I I
I I I
I I
I I
I
I
I
I
I
I
Totals
This doam eat has been modified from its original form as an FJCDC dm:mnmt and the user did not ltighlighl the
modifications. You we mmartgcd to read the docmmem arefully and consult Legal Counsel prim to its ermution.
C-620 Change Order
Progress Estimate
Change Order Number
1 2
Contractor's Application
ADDITIONS
For (convect):
101452-2 2018 Bond Year 3 - Contract 6
City Secretary
56638
Application Number.
23
Contract Nu re
Application Period:
11/01/2023 to 11/30/2023
Applien6an Dote:
11/30/2023
A
B
C
D
E
F
Item
Balance to Finish
Change Ober Item
Sp ioUnit of
Addition Change
CO Quantity to Add Unit Price
F tireated Quantity
V.1.e
Previously Value This
Materials Presently
Total Completed
and Stored to Date (F) (B - F)
No.
1l ription
SectLionon NNo.. Mrnvure
Order Value
Insmlled
Lutalled Vnluc Period
Stored (not in C)
(D � E) B
I1-74
24' C-900 DR-25-Green
_ LF _
_325.00000000_ $328.90 _S106,11_92.50
_ 325.00000000_
S106,892.50
S106,892S4
_
S106,892.5%, 100.0% _
11-75
Connect to Junmion Box
_ EA
1.00000000 $10292.50 $1029250
1.000DWO
$10.292.50
_ _S70}92.50
S10.29250 100.0%
11-76
30' Hole & Cover in Junction Box
_ EA
1.00000000 53,105.00 S3,105.OD
1.00000000 _
33,105.00
53,105.00
$3,105.00 100.0%
❑-77
Rehab and coat e<istingjunction structure
EA
1.00000000 $26,063.60 S26,063.60
1.00000000
$26,963.60
_ _526,063.60
S226063.60 100.0X
11778
�yposs Pumping
LS
1.00000000 $263,034.91 _5263,034.91
1.00000000
S263.034.91
_S263,034.91
_ _ _ _
$263,034.91 100.0%
Q-79
4-Drop Mnnholc
EA
1.00000000 $15,400.00 515,400.00
2.00000000_ _
_ S30,800.00
_530800.00 _
S30,800.00 200.0% 415400.00
Tm.h
8424.78&51
S440,18&51
S440.18851
S440.188.51 103.6% SIS.400.00
This docomrnt has been modified from its original form
or an FJCDC dacmnent and the user did not highlight the
modifications. You are encouraged to read the document
carefully and wnsult Legal
Counsel prior to its execation.
Progress Estimate
Change Order Number 1 2
DELETIONS
For (contract):
101452-2 2018 Bond Year-3 -Contract
6
Application Period:
11/01/2023 to 11/30/2023
A
B C
Change Item
Item
Description
CO Quantity to
o. I Unit of
Delete
Sectiion
Unit Price
Deletion Change Not Used
Order Value
Noo .
3
24' MASS 0011 LinarLF
No. Mmwtre
Sect No.
173.00000000
$333A
_S57.757.78
7
139.1001 V Manhole
EA 1.00000000
$6,567.66
_ S6.567.66
13
Bypass PadtP_w
_
_ _ LS 1.00000000
$295,544.84
S295.344.84
40
Remove Sexy Jtmction swo t se
LS 1.00000000
54 9, 25.74
54y25.74 _ ___
70A
ni Sewn Jwtion Box Standard Condole with Conshield_ LS LOW00000
$60.203.58
$60,203.58
Totals
S424.999.60
Contractor's Application
Application Number. 23
Application Date. 11/30/2023 1
D E F
Not Used Not Used Not Used Not Used Not Used Not Used Not Used
This docunent has barn modified from its original form as an EJCDC doeumont and the user did not higMight the
modircations. You are encouraged to rend the document carefully and consult Legal Counsel prior to its esmutioa
C-620 Change Order
C-620 Change Order
Progress Estimate Change Order Number
ADDITIONS
For (contact): 101452-2 2018 Bond Year 3 - Contract 6
Application Period:
uera
Chonge order Item Description
Na.
11/012023 to 11/30/2023
City Secretary 56638
Contact Now
Contractor's Application
Application Number: 13
Application Date: 11/30/2023
Balance to Finish
Addition Estimated Quantity Previously Value This Matedals Presently
Total Completed % (B - F)
Specifiati.n Unit of CO Quantity to Add Unit Price Change Order Value and Stated to Dole (F)
Section No. Measure Vale Installed Installed Value Period Stored(not in C) (DIE) B
165
1TPVCWmcr(DR-18) A8313
_ LF
7W-00000000
S136.93
$107,001.06
797.00000000
$109453.51
3109.053.51
$109.053.51 101.9%
42.052.45
1-66
IT HOPE Water
LF
75.00000000
S169.05
$12A78.75
60.00000000
$10,143.00
$10,143.00
S10143.00 90.0%
$2,535.75
I-3
3311.02618"PVC Water Pipe
_LF
moo000000
S93.G4
�4.72
_18A0000000
SI.674.72
$1,674.72
31% ,674.72 100.0_
1-43311.0161
6" PVC Water Pipe
_
LF
10.00000000_
_ $79.91
S799_10
10.00M0000
$799.10
_ 5799.10
_ $799.10 100.0% _
1-5
3312.3005 12" Got. Volvo
EA
6.00000000
S3,064_91
319}99.46
_ 6.00000000
$18,389_46
_518,389.46
S18,389A6 100.0%
16
3312.30038" Got. Valve
EA
1.00000000
_ $1,970_30
$1,970.30
1.00000000
$1 MOO
$197030 _
$1.970.30 100.0%
1-7
3312.3002 6" Gate Valve
FA
1.00000000
51,422.99
$1,422.99
1.00000000
_ _S1.422.99_
S1,422.99
51,422.99 100.0%
_
1-9
3312.0001 Fire Hydrant and Extension
EA
1.00000000 _
54. 25,75
54,925.75
_ 1.00000000
$4,925.75
_ 54.925.75 _
$4,925.75 100.0%
I-10
3312.0117 Connection to Existing 4%12"Water Main _
EA
5000000000
_ 54,925.75
$24,628.75
5.00000000
S24.628.75_
S24,628.75
_ S24,628.75 100.0%
I-11
3312.20011" Won. Service, Meter Reconnection
PA
1.0000000_0
$355.75
$355.75_
1.00000000
S355.75
$355_75
$355.75 100.0%
I-11
3312.20031"Water S.rvi«
EA
1.0000000_0
_S1.970_30
$I,970.30 _
1_00000000
$1,97030
-- S1,970.30 _
$1,9M.30 100.0%
1-18
3311.0001 Ductile Ian Water Fittings w/Rcstrnint _
TN
1.50000000 _
$9,851_50
$14.777.25
1.50000000 _
$14,77725
$14,77715
$14,7I7]5 100.0%
I-21
0241.1302 Remove and Salvage 6" Water Value _
EA
1.00000000 _
$109.46
$109.46_
1_00000000
_ _ $109.46
S)09A
$109.46 100.0%
_
1-22
0241.1303 Remove and Salvage 8" Water Value _
EA
_1.00000000 _
$109A6
$109.46
_1.00000000
_ $109A6
$109.46
$109.46 100.0%
1.23
0241.1305 Remove and Salvage 12" Water Value
EA
_ 4.00000000
$109A6
S437.84
_ 4.00000000
$437.94
5437.84
$437.84 100.0%
I-24
M41.1510 Salvage Fne Hydrant
PA
_1.00000000 _ _
_ _ 3328.39
$328.38
1.00000000
_ _ 532838
-
_5326.38
_ $329.39 100.0%
I-26
0241.1512 Salvage 1" Water Meta
FA
1.00000000 _
- _ SUM
$54.73 __1A0000000
$54.73
$54.73
S54.73 100,0%
I-34
3201.0400 Temporary Asphalt Paving Repair (2" FM1AC on 6" Fle.
LF
830.00000_0_00_
$21.89
S18,168.70
_830.000.00000
$18.169.70
518,166.70 _
S18168.70 100.0%
_
I-36
3201.0614 Caner Pvmt Repair, Residential
SY
30.00000000
$178.42
$5.352.60
_ _
_
S5352.60
I-00
3305.0109 Trench Safety _ _
LF
865.00000000
$0.05
$4425
_885.00000000
_ $4425_UC
S442S 100.0%
143
3305.0203 Imported EmbodmenVBaekliill, CLSM
CY
50.00000000
$1$325
S7,662.50
_ _
_
$7,662.50
145
0241.1300 Remove Cone Carl, &Gana
LF
_ 10.0000000
$5.75
W.50
_
S57_50
146
0241.1400 Remove Cone, Valley Gutter
SY
65.00000000
$51.74
53,363.10
65.00000000
S3,363.10
S3,363.10
S3363.10 100.05E
147
0241.17001 V Pavement Pulvcimlim _
SY
55.011000000
S&56
S470.80
_
_
___
S470_80
I-50
3212.03033" Asphalt Pvmt Type D
SY
55.00DWOW
S2&OS
$IS42.75_
.__
$IS42.7$
1-51
3216.01016-Cow Cmb and Gucr
LF
10.00000000
$50.11
$501.I0
_
_
$501.10
1.52
3216.0301 7" Cone Valley Gutter, Residential
SY
65.00 WWO
$124.23
$$074.95 _
65.0000000o
_ $9,074.95
_ $8074.95 _
_ $8,074.95 100.0%
1.55
3292.0100 Black Sod Placement
SY
100.00000000
S420
_ S420_00
1.57
3305.0111 Valve Box Adjustment, Including Concrete Collor _
FA
1.00000000
$479.65
S479AS
_ _ _
_ -
$479.65
167
Remove &Reset Guardrail _ _
LS
1.00000000
$13,900.00
$13,800.00 _
1.00000000
_ $13,900.00
SI3,900.00
$13800.00 100.014
_
11-5
3331.4115 8" Sewer Piper (PVC SDR 26)
LF
326.00000000
$125.88
541,036.88
_326.00000000
_ 341,036_88
S41036_88
S41,036.88 100.0%
11-7
3339.1001 4"Manhole _
EA
3.0000W00
56,567.66
S19,7M.98
_3.00000000
S19,702.98
_ 519,702.98
_ $19,702.98 100.0%
II-8
3339.10034" Ewa Depth Manhole
VF
_ I.WwwW
$213.45
S213.451.00000000_
__
_ $213.45
_S213AS
S213.45 100.0%
II-14
3339.0003 Later -4"Sews MH
VF
7.00000000
$344.80
S2,413.60
_
$2,413.60
_
11-17
333131014" Sewer Service _
EA
1.00000000
W83.83
$3.293.93
_110000000_
S3283.83
_3338i83 _
$3.283.93 100.0%
11-I8
1301.0101 Manhole Vacuum Testing
FA
3.00000000
S229S7
$689.6l
_ 3A0000000
_ S689.61
$689.61
S689 61 100.0%
_
31-28
3201.0400 Temporary Asphalt Paving Repair (2" HMAC an 6" FIB
LF
345.000001)00
$4050
S ,13 97250
_345.00000000 _
V13,97250
$11,972.50
$13,972.50 100.0%
11-36
02412201 Remove 4" Sewer Manhole
EA
1.00000000
$492_57
S492.57
1.00000000 _
$49257
$49257 _
S49257 100.0%
11.52
3301.0002 Post CCTV inspection
LF
326.00000000
S10.95
33369.70
126.00009000_S3,569.70
53,569.70
$3,569.70 100.0%
II-53
9999.0005 Final CCTV Inspection. Manhole
EA
2_00000000
$109.46
$2t8.92 _
_ _
-
_
$219.92
1144
3305.0103 Exploratory Ecavation of Existing Utilities _
EA
1.00000000
S1,31333
$1,313.53
_1.00000000
$1,313.53
_5j,31353
_ $1,313.53 100.0%
11-55
3305.0109 Trench Safety _ _
LF
326,00000000
$1.09
_ $355.34
326.0W00000
$355.34
_$35534
$355_34 100.0%
II-73
3305.0114 Mwdad. Adjushent, Major w/Cava
FA
5.00000000
$19300.00_
500000000__
$19,300.00_
S1�.00
$19300.00 100.0%
II-76
30"Hel.& Cover in Junction on Box
1.00000000
_53,860.00
S3,105_00
$3,105.00
1.00000000
53,105.00_S3,105_00
_
- S3,105.00 100.0%
11-80
Conueet 42" SS to Junction Box
FA
1.00000000
__ _ 59.020.00
59,020.00
_
1.00000000_
$9,020.00
02
_ S9,0.00 _
$9,020.00 100.09E
MI
Rework invert to Junction
IS
1_00000000
S5280.00
$5,280.00
1.00000000
$5.280.00_
S5,280.00 _
$__00 100.0%
1142
Junction Box Coating _ _
_ IS
_ 576.00000000 _
S33.30
319,180.80 _
597.00000000
519.880.10
219,880.10
_ $19,880.10 103.6%
4699.30
M-9
0171.0001 Comwctiam Staking (Paving) _
IS _
_ 020000000 _
$10,946.10
52.19922
020000000_
$2.18922
_ S2.13922 _
$2,18922 100.09E
III-13
0241.0401 Removc Concrete Drive
SF
S1.14
$536.94
47L00000000
_ _ $536_94
__ $536.94 _ _ _
_ S536.94 100.0%
M-I6
0241.1000 Remove Co. Pvmt
SY
_471.00000000
10.00000000 ___---_
19.07
$90.70
_-
_ _ _ _ _
S90 70
M-17
0241.1300 Remove Cone, Curb & Gutter
LF
70.00000000 _
$3.37
$235.90
70.00 WWO
$235.90
_ _ $235.90 _
_ _ $235.90 100.0%
This document has been modified from its original f es an EICDC document and the user did not highlight the
modifications. You me encouraged to rend the document emefuliv and consult Legal Counsel prior to its cveeution.
M-26
3125.0101 SWPPP 1 Acre
IS
0.02000000
_52�.736.51 554.73
_ 020000000
5547.31
_$547.31 _
ID-27
3211.01126•Flcxible Base, Type A,GR-1
SY
132.00000000
325_67 53,78&44_____
M-28
3212.0401 HMAC Transition
TN
2.00000000_
5150.00 $300.00__
M-34
3213.04016-Concrete Dria-ay
SF
471.00000000
59_33 $4629.93
471_00000W0
54,629.93
Ili-38
3213.0505 Bonier Free Ramp, Type M-3 _
BA
1.00000000
$2 734.34 $2 734.34
1.00000000
52,734.34
_$2 734.34 _
M45
3217.5001 Curb Address Painting _ _
EA
3.00000000
33722 $11166
M48
3291.0100 Topsoil
CY
200.00000000
550.35 SI0,070.00
M49
3292.0100 BIok Sod Plaoemeot
SY
594.00000000
$420 32,494_80__.___
M-50
3305.0107 Manhole Adjustment, Minor _
FA
SA0000000
5583.18 _ 915.90
M-58
3441AO06 losall Alum Sign Ground Mount
_ FA
1.00000000
$410.43 $410.48
M-59
WIA110 Removeand Rch.Wl Sign Panel and Post
FA
6.00000000__
5541.83 $3,25098
M60
3471.0001 Traffic Control
MO
020000000_
SI,641.92 $328.38 __
020000000_
_ $328.38
_ 332839 __
III -la
0241.170011• Pavement Pulverimtion _
SY
1640.00000000
$698 $II1 7.20
_1154.98000000
_ _58,061_76
_$8061.76 _
ID-3a
3211.9999 Can -Lime 30 lbs/SY _ _
7N
42.00000000
3221.11 $9,286.62
_ 20.00000000
_ _ 54,42220
_ 54,42220 _
ID4a
3212.0303 3^Asphalt Pvmt Type D
SY
_ 1640.00000000_
$26.04 �705.60 _
_1154.98000000
_ $30,TS.68
530,075.68
M.S.
3216.01016• Cone Curb and Guncr
LF
_300.00000000
550.11 SI50, 33.00
_300.00000000
_ $1503300
$15013.00 _
M6n
3216,9999 Lay Down Conc Curb and Goner _
_ LF
1309.00000000
$44 06 $57 67454 _
991.50000000_
_ 543,685.49
S13 685.49 _
3305.0111 Valve Box AdjuslmraL Including Concrete Collar _
_ FA
5.00000000 _
_ 5537AI P 687A5
_ 5.00000000 _
52,687A5
_ _ $2,687_05 _
_ID-84,
M-9a
9999.9999 Vines Maier Periwin le%%Groundcovcr) f4-PoN Plant 0
SF
450.00000000
37.26 53267.00
450.00000000
53267.00
$3267.00
Turn l5
5570.564.07
5494251.44
549425I.44.
This daatmrnt h. be v modified from its original form os an FJCDC document and the uscr did not highlight the
modifications. You me encouraged to read the decumrnt carefully and consult Legal Counsel prior to its ococution.
5547.31 1000.0% -$492.58
$3.389.44
5300.00
34,9%93 100.0%
52,734.34 100.0%
$111.66
_ 310,070.00
$Z494.80
--_ 52,915.90
- $410.48
-- 53250.98
5328.38 100.0%
58,061.76 70.4%
$3,385.44
_ 54,42220 _47.6%
54,864.42
$30,075.68 70A%
S12_,6_29.92
515,033.00 100.0%
_ $43,685.49 75.7%_
$13.999.05
_ 52.687.05 _ 100.0%_
$3267.00 100.0%
5494.251.44 86.6%
$76,31Z64
C620 Change Order
C-620 Change Order
Progress Estimate
Change Order Number 3
Contractor's Application
DELETIONS
For(wntract): 101452-2 2018 Bond Year 3 - Contract
6
Application Number:
23
Application Period
11/01/2023 to 11r30n023
Application Date:
11/30/2023
A
B C
D E
F
dram
CO Quantity to
Dciclion
Change Ord m Item D—
Specifi-u- Unit of Delete
Uoit Priw
Change Ord,T Not U.ed
Not Uscd Not Used Not Used Not Used
Not U. d Not Uscd Not Uscd
No.
II-5 6-Mm1ole
Swtion No. Measure
FA 1.00000000_
_
S15,324.55
Value
SI5,324.Sir
II! 6' Extra DryW Man6de
_
VF 1.00000000
$476616
_ _ 5476.16
II-7 I.inc-6 Sauer MH
w 1200000000
$492.57
55,910.84
II-8 Remove Sewer JuntiouSwctme (Lirm.B-St. 10,30) IS 1.0000a000
_ S4,M74
_$4,925.74
Totnls
S26,637.29
This document has b— modified from its original form as an EJCDC domnwt and die user did net higWight the
modifications. You one weomaged to read the document w fully and consult Ixgal Counsel prior to its evewtion.
C-620 Change Order
Progress Estimate Change Order Number
1 4
Contractor's Application
ADDITIONS
For (cantmct):
101452-2 2018 Bond Year 3 - Contract 6
City Secretary
56638
Application Number.
13
Confct Nam:
Application Period
11/01/2023 to
11/30/2023
Application Date:
11/30/2013
A
D
C
D
E
F
item
I .1- to Finish
Addition
Estimated Quantity
Previously
Value This Materials Presently
Total Completed %
(B_F)
Chow Order It®
DescriptionSection
Specification Unit of
CO Quantity to Add
Unit Price
Chang. Order
installed
Value
Value
Value
Period Stored (not in C)
and Stored to Dote (F)
No.
No. Measure
V.I..
(D+ E) B
1 168
Lay Down Curb Correction(25%)
Water
IF
12.90000000
$44.06
$1,409.92
_ 32.00000000 _
SIA09.92
$1.409.92
_
$1,409.92 100.0%
169
Construction Staking for Lay Down Curb(25%)
Water _
_ _ LS
1.00000000_
$561.00
$561.00
_ 1.00000000
$56100
S56100
_ _
$561.00 100.0%
I.70
Rcrravc Curb &Gutter for Lay Do -Curb Correction.(25%)__
Water
_ LF
32.00000000 _
$3.37
3107.84
32.00000000_ _
_._ _ S107.94
S107.84
_ _ _ _
$107.84 100.0%
1-71
HMAC Level Up for lay Do- Curb (25%)
Wotcr_
_ IN
15.00000000_
S150.00
5240.00_20.50000000__
S3.075A0
$30M.00
53,075.00 136.7% 4825.00
I--72
R®obilimtion-Flnhvmk Crew(25%)
Water
LS
1A0000000
S1,000.00
SI,000.00
_100000000 _ _
_$1,000.00
$1,000.00
_ _ _ _
$1,000,00 100.04:
11-93
Lay Down Curb Correction (25%) _ _
Sena
LF
33.00000000 _
$44.06
S1,451"
33.00000000
$1,433.98
_51,453Aq
_ _ _
S1,453.99 100.0%_
11-84
Conswction Staking for Lay Down Curb (25%)
_ Sewer
LS
1.00000000
S561.00
S561.00
__ 1.00000000 _
S561.00
_ S561A0
_ _ _
$561.00 100.0%
11-85
Ranove Cur ,@ bGana for Lay Down Cmb Correction (25%)Sewer
LF
_
_ 33.00000000
S3.37
$111.21
33_00000000
$11121
_311121
_ SIM21 100.0%
11-87
IIMAC Level Up fa lay Down Curb (25%)
Sewer
TN
15.00000000
$150.00
52,250.00
_20.50000000
$3,075.00
_ 53,07500
_ _ _ _ _ _
S3,075.00 136.7% 4825.00
1.86
Rcmobilwation-Flnt%wrk Crew(25%)
Sewer
LS
1.00000000 _
_ $1,000.00
51,000_00
_ 1.00000000 _
51,000.00
SI,000.00
_ _ _
_ $1,000.00 100.0%
M-ft
Lay Down Carl,
Paving_
LF
p.00000000 _
$44.06
52,863.90
50.00000000_
S2,203.00
$2,203_00
_ _
_ _ _ _ _ _ _
S2,203.00 76.9% S660.90
M67
Construction Staking fa lay Down Curb(50%) _
_ Paving_
LS
1.U00000
_ $1,121.77 5,1121.77
I.00000000_
$1,121.77
SI,121_77
_. _ _ _ _ _ _
S1,121.77 100.0%
M-17
Rwovc Curb & Gutter
Paving_
LF
65.00000000
$3.37
$219.05
61.50000000
S20726
5207.26
S20726 94.6% $11.90
M-28
HMAC Level Up
_ Paving__
7N
30_00000000
_ S150.00
$4500.00_41.00000000
_
S6,150.00
$6,150.00
._ _ _ _
S6,150.00 136.7% 41,650.00
M-97
Rcmobilntion-Flatvork Crew(50%)
Paving
LS
1.00000000
S2000.W
52,W0.00
__ 1.00000000
52,000.00_
S2,000.00
S2,000.00 100.0%
This docmnent has been modified from its original loran as an EUCDC docmnent and the user did not highlight the
modifications. You arc eneoumged to read the doe urx at earefully and consult legal Counsel prior to its aseeution.
C-620 Change Order
Tomb I I I I I S21.409.671 I S24.036.98I $24.036.981 1 I S24.Q36.98I 112.3% I-52.627.31I
Thu doaumemt has been modified from its original form os an EJCDC document and the user did not highlight the
modifneations. You arc encouraged to read the document carefully and consult Legal Counsel prior to its -tion.
C-620 Change Order
Progress Estimate Change Order Number 1 5
Contractor's Application
ADDITIONS
For (mnbmt): 101452-2 2018 Bond Year 3 - Contract 6
City Semetmy
56638
Appllention Number:
23
Contract Num:
Application period: 11/01/2023 to 11/30/2023
Application Dote:
11/30/2023
A
B
C
D
E
F
Item
Mon. to Finish
Addition
Estimoted
Previously
Value This Materials Presently
Total Completed
(B _ p)
Change t hem Speeim Unit of CO Quantity to Add
Description
Unit Price
Change Order
led
Iusm11M
Value
Insmlled Vnlm
Pmiod Stored (not in C)
and Stored to Dote (F)
No.
o. Section No. Meosnc
No.
Value
(p+E) B
➢-87 Shor-Flex Slope Protection Sewer LF 39.00000000
S500.90
$19,535.10
39.00000000 _
$19.535.10
$19,535.10
$19,535.10 100.0%
II-S8 12"Coovctc Curb _ Scwcr iF 24.00000000
$74.60
$1,790.40
24.00000000
$1,790.40
51,790,40
_ _
51,790.40 100.0%
➢-89 Cl mmut Debris at Sewer & Creek Crossing Sewer LS _U00009MCL
$3,73018
53,73028
1.00000000
53,73028
53,73025
_ _ _
$3,730.28 100.0X
This document has been modified from its original form as an FJCDC document and the u r did not highlight the
modifications. You ore enwumged to read the document carefully and consult Legal Counsel prior to its —utioa
Cfi20 Change Order
Tamer I I I I I 525,055.781 I 525,055.781 525.055.781 I I 525,055.781 100.0% 1
This document has hcrn modified from its original form as an FJCDC document and the user did not highlight the
modifications. You we encourugcd to read the document carefully and consult Legal Counsel prior to its —cation.
C-620 Change Order
Progress Estimate
Change Order Number 5
Contractor's Application
DELETIONS
For (contract): 101452-2 2018 Bond Year 3 -Contract
6
Applieution Numbcr:
23
AppliwtionPeriod.
11/01/2023 to 11/30/2023
Application Date:
11/30/2023 1
A
B I C
D E
F
hem
Change Order Item
Speaifiation Unit of CO Quantity to
Deletipn
Unit Prig Change Order I Not Used
Not Used Not Used Not Used Not Used
Not Used Not Used Not Used
Description
No.
Delete
Section No. Measure
Value
69 9999.0007 Sewnr Cooswction Allowma
Sewer__ IS 025055780
5100,000.0 $25,055.78
S25.055.781
This document has been modified from its original form as an, EtCDC doeument and the user did not highlight the
madifiations. You are encouraged to read the document carefully and consult Legal Counsel prior to its execution.
City of Fort Worth Summary of Charges
City Secretary Contract Num: I 56638 I
2018 Bond Year 3 - Contract 6
I P. 0.:
FW020-0000006894
Project Number.
101452-2
Application Period:
I 11/01/2023 to 11/30/2023
I Application I
Number:
23
Application Date:
11/30/2023
Funding Identification (FID)
Total Completed Amt Remaining
1
Gross
Retainag-e---7
Net
Original Contract
�
I
56002-0600430-5740010-101452-001780-9999
$1,702,075.74
$377,421.45
56002-0700430-5740010-101452-001780-9999
$2,259,228.73
$856,378.49
34018-0200431-5740010-101452-002480-9999-18010199
$1,449,602.48
$547,959.62
10
_ ..
to
10
�'�
_
"'D
o
- -
-U _6 i
O
.-
V.JG I
--. -'..
.•G. JI.
0
o
I
Change Order
156002-0600430-5740010-101452-001780-9999
156002-0700430-5740010-101452-001780-9999
$831,939.35
$19,877.44
134018-0200431-5740010-101452-002480-9999-18010199
? I
I
7'I
o
Jo
io
o���
10
U I I
u.
i0
10
10
jo
-
J I
I C I
1
Change Order 2
_
1
56002-0600430-5740010-101452-001780-9999
;,.,.n-
,. "•,
;J }L
56002-0700430-5740010-101452-001780-9999
$440,188.51
($440,399.60)
34018-0200431-5740010-101452-002480-9999-18010199
o
o
0
UPI I
I
1
0
J.
0
;r0.00 I i
;(
I C. IC I
0
U. J I
0
City of Fort Worth Summary of Charges
City Secretary Contract Num: I 56638 2018 Bond Year 3 - Contract 6 I P. 0.: FW020-0000006894
Application Period: I 11/01/2023 to 11/30/2023 I Application I 23
Number.
Funding Identification (FID) I I Total Completed
I Change Order I
156002-0600430-5740010-101452-001780-9999 I
$234,601.75
156002-0700430-5740010-101452-001780-9999 !
$141,215.49
134018-0200431-5740010-101452-002480-9999-18010199
$118,434.20
10
10
10
I 00 1
10
g;J,JO
10
10
I 1
10
I
10
156002-0700430-5740010-101452-001780-9999
134018-0200431-5740010-101452-002480-9999-18010199
10
10
'0
10
10
10
10
0
$6,201.19
$11,682.03
Amt Remaining
I
$16,970.20
($24,704.07)
$57,409.22
t$6,201.19 j
($11,682.03)1
Project Number: 101452-2
Application Date: 11/30/2023
Gross Retainage Net
1 �
J
!
J-, II 1
I
I I I I i
156002-0600430-5740010-101452-001780-9999
156002-0700430-5740010-101452-001780-9999
$25,055.78 . I
($25,055.78)1
134018-0200431-5740010-101452-002480-9999-18010199
j.j !
10
o.o0 1 I
I
10
1
to
1 1
10
1s. J1
I
:oJol 1
s_ao1
!o
Io
to
j0 1 1
•o.o� I I
�� J=' I
10
I
I I
J 1
i
J.
City of Fort Worth Summary of Charges
City Secretary Contract Num: 1 56638 2018 Bond Year 3 - Contract 6 P. 0.: FW020-0000006894 Project Number: 101452-2
Application Period: I 11/01/2023 to 11/30/2023 1 ApplicatI
(on 23 Application Date: 11/30/2023
Number.
1 7 1 i Gross RetainaFe--', Net
Funding Identification (FID) I Total Completed I Amt Remaining I
Change Order 6
156002-0600430-5740010-101452-001780-9999
156002-0700430-5740010-101452-001780-9999
134018-0200431-5740010-101452-002480-9999-18010199
10
10
10
10
10
10
1
i 0
156002-0600430-5740010-101452-001780-9999
156002-0700430-5740010-101452-001780-9999 I
I Tc. 1�0 I
"j
34018-0200431-5740010-101452-002480-9999-18010199
1
D
0 I
J .
I
10
f-
0
0
T
to
ju
0
J,
10
Change Order 8
156002-0600430-5740010-101452-001780-9999
3
156002-0700430-5740010-101452-001780-9999
134018-0200431-5740010-101452-002480-9999-18010199
10
10
10
10
10
10
Ili
CC
10
'J
10
kj I
ao l
City of Fort Worth Summary of Charges
City Secretary Contract Num: I 56638 I
2018 Bond Year 3 - Contract 6
I P. 0.: FW020-0000006894
Project Number: 101452-2
Application Period:
I 11/01/2023 to 11/30/2023
Application I 23
Number:
Application Date: 11/30/2023
Funding Identification (FID)
1 Total Completed Amt Remaining Gross
Retainage Net
Totals
-
56002-0600430-5740010-101452-001780-9999
$1,942,831.25
$388,237.89
56002-0700430-5740010-101452-001780-9999
$3,703,829.05
$379,895.29
34018-0200431-5740010-101452-002480-9999-18010199
1 $1,579,718.70 1
$593,686.81
0
p
i0
10
10
10
10
-
10
Grand Total
j $7,226,379.01 1 1
$1,361,819.99 1 1 $0.00 1 1
($361,318.95)1 1 $361,318.95
PROJECT NAME:
PROJECT NUMBER:
DOE NUMBER:
PIPE LAID
PVC
PVC
DIP
PVC
FIRE HYDRANTS: 7
PIPE ABANDONED
DENSITIES:
NEW SERVICES:
PIPE LAID
FIBERGLASS
PVC
PVC
PIPE ABANDONED
DENSITIES:
NEW SERVICES:
(D
FORTWORTH
-- %k �
s
TRANSPORTATION AND PUBLIC WORKS
PIPE REPORT FOR:
2018 Bond Year 3 Contract 6
101452-2
WATER
SIZE
TYPE OF PIPE
LF
12"
C-900
3,207
8"
C-900
2,289
12"
DUCTILE IRON
81
6"
C-900
74
VALVES (16" OR LARGER)
SIZE
TYPE OF PIPE
LF
YES
SEWER
SIZE TYPE OF PIPE LF
42" SN-72 1,030
24" PS-115 1,804
8" SDR-26 1,333
SIZE TYPE OF PIPE
YES
TRANSPORTATION AND PUBLIC WORKS
The City of Fort Worth • 1000 Throckmorton Street • Fort Worth, TX 76012-6311
(817) 392 - 7941 • Fax: (817) 392 - 7845
LF
FORTWORTH.
TRANSPORTATION AND PUBLIC WORKS
December 5, 2023
Texas Materials
420 Decker Dr. Suite 200
Irving, Texas 75062
RE: Acceptance Letter
Project Name: 2018 Bond Year 3 Contract 6
Project Type: Water, Sanitary Sewer, Paving
City Project No.: 101452-2
To Whom It May Concern:
On July 27, 2023 a final inspection was made on the subject project. There were punch list items
identified at that time. The punch list items were completed on December 5, 2023. The final inspection
and the corrected punch list items indicate that the work meets the City of Fort Worth specifications and
is therefore accepted by the City. The warranty period will start on December 5, 2023, which is the date
of the punch list completion and will extend of two (2) years in accordance with the Contract
Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at 817-
392-8785.
Sincerely,
Jose Orozco, Project Manager
Cc: Steve Cisneros, Inspector
Mike Glover, Inspection Supervisor
Randy Horton, Senior Inspector
Greg Robbins, Program Manager
Stream Water Group, Consultant
Texas Materials, Contractor
N/A, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev. 8/20/19
CONSENT OF SURETY
TO FINAL PAYMENT
AIA Document G707
(Instructions on reverse side) Bond No.
TO OWNER:
(Name and address)
City of Fort Worth
200 Texas Street
Forth Worth, TX 76102
PROJECT:
(Name and address)
2018 Bond Year 3 - Contract 6 City project # 101452-2
OWNER
ARCHITECT
CONTRACTOR
SURETY
014225406 OTHER
ARCHITECT'S PROJECT NO:
CONTRACT FOR:
2018 Bond Year 3 - Contract 6 City project # 101452-2
CONTRACT DATED:
In accordance with the provisions of the Contract between the Owner and the Contractor as indicated above, the
(Insert name and address of Surety)
Liberty Mutual Insurance Company
175 Berkeley Street Boston, MA 02116
on bond of
(Insert name and address of Contractor)
Texas Materials Group, Inc. dba TexasBit, A CRH Company
,SURETY,
420 Decker Drive #200 Irving, TX 75062 CONTRACTOR,
hereby approves of the final payment to the Contractor, and agrees that final payment to the Contractor shall not relieve the Surety of
any of its obligations to
(Insert name and address of Owner)
City of Fort Worth
200 Texas Street Forth Worth, TX 76102
OWNER,
as set forth in said Surety's bond.
IN WITNESS WHEREOF, the Surety has hereunto set its hand on this date: December 6, 2023
(Insert in writing the month followed by the numeric date and year.)
Liberty Mutual Insurance Company
(Surety)
(Signature ofauthorized representative)
Attest/Witness:
(Seal): `(� Stephanie Gross, Attorney -in -Fact
Jessica Richmond, Witness (Printed name and title)
1NSUR
�JPGOPOR,yT�20
AIA DOCUMENT G707 w CONSENT OF SURETY TO FINAL PAYMENT w 1994 EDITION w AIA 1912
01994 HE AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVENUE, NW, WASH- Y y 0
INGTON, D.C. 20006-5292 w WARNING: Unlicensed photocopying violates U.S. copy-
right laws and will subject the violator to legal prosecution. ssI CHUS� -aa
0/7 * Ala
G707-1994
Seal No. 4440
10�
This Power of Attorney limits the acts of those named herein, and they have no authority to
Liberty bind the Company except in the manner and to the extent herein stated.
Mutual. Liberty Mutual Insurance Company
SURETY The Ohio Casualty Insurance Company Certificate No: 8204866
West American Insurance Company
POWER OF ATTORNEY
KNOWN ALL PERSONS BY THESE PRESENTS: That The Ohio Casualty Insurance Company is a corporation duly organized under the laws of the State of New Hampshire, that
Liberty Mutual Insurance Company is a corporation duly organized under the laws of the State of Massachusetts, and West American Insurance Company is a corporation duly
organized under the laws of the State of Indiana (herein collectively called the "Companies', pursuant to and by authority herein set forth, does hereby name, constitute and appoint,
Stephanie Gross
all of the city of Houston state of Texas each individually if there be more than one named, its true and lawful attomey-in-fact to
make, execute, seal, acknowledge and deliver, for and on its behalf as surety and as its act and deed, any and all undertakings, bonds, recognizances and other surety obligations, in
pursuance of these presents and shall be as binding upon the Companies as if they have been duly signed by the president and attested by the secretary of the Companies in their
own proper persons.
IN WITNESS WHEREOF, this Power of Attorney has been subscribed by an authorized officer or official of the Companies and the corporate seals of the Companies have been affixed
thereto this 15th day of February, 2021.
Liberty Mutual Insurance Company
The Ohio Casualty Insurance Company
P� \NSU� P�IY INS& � \NSURq
West American Insurance Company
?`DµPD/j9T�'QyyC, 2Irn oaPOR,yTo�J•�
g$1912g0 0 1919 a 1991 o By: �
Yd�13SgCMU`'� as y�Z�HAMP`'�\eaaO '�S+ �NDIANP' ,aa
C6 ��� * 1a -yl David M. Carey, Assistant Secretary
N
STATE OF PENNSYLVANIA ss
COUNTY OF MONTGOMERY
NCD
p� On this 15th day of February, 2021, before me personally appeared David M. Carey, who acknowledged himself to be the Assistant Secretary of Liberty Mutual Insurance Company,
U The Ohio Casualty Company, and West American Insurance Company, and that he, as such, being authorized so to do, execute the foregoing instrument for the purposes therein
o 2 contained by signing on behalf of the corporations by himself as a duly authorized officer.
L >
U IN WITNESS WHEREOF, I have hereunto subscribed my name and affixed my notarial seal at King of Prussia, Pennsylvania, on the day and year first above written.
7 9P PAST
'y �Q NWe9<�<< Commonwealth of Pennsylvania - Notary Seal
0O ° = v Teresa Pastella• Notary Public
L of Montgomery County
Qj O �,.Q My commission expires March 28, 2025 By
" N �Ns��P �G Commission number 1126044
c+, orgRy �e� Teresa Pastella, Notary Public
N Member, Pennsylvania Association of Notaries
a� This Power of Attorney is made and executed pursuant to and by authority of the following By-laws and Authorizations of The Ohio Casualty Insurance Company, Liberty Mutual
rnCQ
jv Insurance Company, and West American Insurance Company which resolutions are now in full force and effect reading as follows:
y ARTICLE IV — OFFICERS: Section 12. Power of Attorney.
O C: Any officer or other official of the Corporation authorized for that purpose in writing by the Chairman or the President, and subject to such limitation as the Chairman or the
E - President may prescribe, shall appoint such attorneys -in -fact, as may be necessary to act in behalf of the Corporation to make, execute, seal, acknowledge and deliver as surety
o CU any and all undertakings, bonds, recognizances and other surety obligations. Such attorneys -in -fact, subject to the limitations set forth in their respective powers of attorney,
_0 >, shall have full power to bind the Corporation by their signature and execution of any such instruments and to attach thereto the seal of the Corporation. When so executed, such
M c instruments shall be as binding as if signed by the President and attested to by the Secretary. Any power or authority granted to any representative or attorney -in -fact under the
> ;v provisions of this article may be revoked at any time by the Board, the Chairman, the President or by the officer or officers granting such power or authority.
Z=3 ARTICLE XIII - Execution of Contracts: Section 5. Surety Bonds and Undertakings.
Any officer of the Company authorized for that purpose in writing by the chairman or the president, and subject to such limitations as the chairman or the president may prescribe,
shall appoint such attorneys -in -fact, as may be necessary to act in behalf of the Company to make, execute, seal, acknowledge and deliver as surety any and all undertakings,
bonds, recognizances and other surety obligations. Such attorneys -in -fact, subject to the limitations set forth in their respective powers of attorney, shall have full power to bind
the Company by their signature and execution of any such instruments and to attach thereto the seal of the Company. When so executed such instruments shall be as binding
as if signed by the president and attested by the secretary.
Certificate of Designation —The President of the Company, acting pursuant to the Bylaws of the Company, authorizes David M. Carey, Assistant Secretary to appoint such attorneys-
infact as may be necessary to act on behalf of the Company to make, execute, seal, acknowledge and deliver as surety any and all undertakings, bonds, recognizances and other
surety obligations.
Authorization — By unanimous consent of the Company's Board of Directors, the Company consents that facsimile or mechanically reproduced signature of any assistant secretary
of the Company, wherever appearing upon a certified copy of any power of attorney issued by the Company in connection with surety bonds, shall be valid and binding upon the
Company with the same force and effect as though manually affixed.
I, Renee C. Llewellyn, the undersigned, Assistant Secretary, of Liberty Mutual Insurance Company, The Ohio Casualty Insurance Company, and West American Insurance Company
do hereby certify that this power of attorney executed by said Companies is in full force and effect and has not been revoked.
IN TESTIMONY WHEREOF, I have hereunto set my hand and affixed the seals of said Companies this 6th day of December 2023
P�11( INS& a \NSUQq
°01' o 4. " y
VQ' °pP 0/2,aT 2
J 3 Fo t� a• 3 Fo C,
g 1912 oy19190 a
41991 0 B +~
Y:
!1�9SSACHUS��.da SO �hNAMP9��? a '! �NDIANP a3
*�a Renee C. Llewellyn, Assistant Secretary
vi E
00
'L U
m
c
o�
m�
U �
Q D
Cl)
�O
Q) @
E
O Q)
Q o
oCD
� N
ON
�cy.)
L
00
0—
CO
c
co —
O U
O
L
O N
LL Q
Marsh MSurety POA LMIC OCIC WAIC Multi Co 022021
Liberty Mutual®
SURETY
As part of its business continuity efforts during the pendency of the COVID-19 pandemic, Liberty
Mutual Insurance Company ("LMIC") on behalf of itself and the companies listed below has
authorized its Attorneys -in -Fact to affix its corporate seal for surety obligations in a digital format
in lieu of its traditional raised seal to any bond issued on its behalf by any such Attorney -in -Fact:
Liberty Mutual Insurance Company
Liberty Mutual Fire Insurance Company
The Ohio Casualty Insurance Company
West American Insurance Company
Safeco Insurance Company of America
American States Insurance Company
LMIC agrees and affirms on behalf of itself and the other companies listed herein, that the digital
corporate seal referenced above has the same binding effect when affixed to a bond or a Power
of Attorney document as if it were a raised corporate seal.
Effective this 23Id day of March, 2020.
By: 5��- le-��
Renee C. Llewellyn, Assistant Secretary
AFFIDAVIT
STATE OF TEXAS
COUNTY OF TARRANT
Before me, the undersigned authority, a notary public in the state and county
aforesaid, on this day personally appeared Donnie Blackburn, Vice President of Texas
Materials Group, Inc., known to me to be a credible person, who being by me duly sworn,
upon his oath deposed and said;
That all persons, firms, associations, corporations, or other organizations
furnishing labor and/or materials have been paid in full;
That the wage scale established by the City Council in the City of Fort Worth has
been paid in full;
That there are no claims pending for personal injury and/or property damages;
On Contract described as;
2018 CIP Year 3, Contract 6 CPN # 101452-2
Donald Blackburn"
BY,..,.,,.
Donnie Blackburn
GM/Vice President
Texas Materials Group, Inc.
Subscribed and sworn before me on this U' day of , 2023.
JAMIE GREENWAY
_Notary Public, State of Texas
+� Comm. Expires 08 26-2024 NOT RY PUBLIC AND R
Notary ID 12115454 T RA COUNTY, TEXAS
r
My commission expires er>1�r of . I--