HomeMy WebLinkAboutOrdinance 26630-12-2023 Ordinance No. 26630-12-2023
AN ORDINANCE ADJUSTING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE STORMWATER CAPITAL PROJECTS FUND, BY
INCREASING ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE
BASSWOOD BOULEVARD AT OLD SANTA FE TRAIL TRAFFIC SIGNAL
PROJECT (CITY PROJECT NO. 103998) IN THE AMOUNT OF $80,000.00 AND
DECREASING ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE
DRAINAGE IMPROVEMENT PROJECTS PROGRAMMABLE PROJECT (CITY
PROJECT NO. P00043) BY THE SAME AMOUNT; PROVIDING FOR A
SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF
PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT
HEREWITH;AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2023-2024 in the
Budget of the City Manager, there shall also be adjusted estimated receipts and appropriations in the
Stormwater Capital Projects Fund, by increasing estimated receipts and appropriations in the Basswood
Boulevard at Old Santa Fe Trail Traffic Signal project(City Project No. 103998)in the amount of$80,000.00
and decreasing estimated receipts and appropriations in the Drainage Improvement Projects programmable
project(City Project No.P00043)by the same amount.
SECTION 2.
That should any portion,section or part of a section of this ordinance be declared invalid,inoperative or void
for any reason by a court of competent jurisdiction,such decision,opinion or judgment shall in no way impair
the remaining portions,sections,or parts of sections of this ordinance,which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 26453-09-2023 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations,in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETARY
Mack(Dec 21,2023 13:30 CST) �✓0000 `1
Jannette S. Goodall OQ c' bti ;�a
:..,;
Assistant City Attorney City Secretary oo
G�'$
ADOPTED AND EFFECTIVE:December 12 2023 woo
�O0
1V
Mayor & Council Map I CPN 103998 FORTWORTH®
Baswood & Old Santa Fe Traffic Signal Project
(CD #2, 7)
�N 1
r•t •lamer_ -. � � n1,'. r-.r^. �•� - � !�
■
BASSWOOD
■ �.:ars
I Min
■
i ■
BASSWOOD 1�
■
w� w�LL� LL,
Vicinit °I °
. Map qI
Project Extent
Major&Minor Streets 1
Fort Worth City Limits "
Data Source:CFW GIS,NearMap2022 I Map generated August 2023
I Amy LaMar,TPW Business Support Services
r' r
o is so ioo
e Fet
i
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 12/12/23 M&C FILE NUMBER: M&C 23-1056
LOG NAME: 20BASSWOOD BLVD AT OLD SANTA FE TRL ENGINEERING CONTRACT
SUBJECT
(CD 2 and CD 7)Authorize Execution of Amendment No. 1 in the Amount of$35,000.00 to an Engineering Services Agreement with LJA
Engineering Inc.for a Revised Contract Amount of$131,395.00 for the Basswood Boulevard at Old Santa Fe Trail Traffic Signal Project,Adopt
Appropriation Ordinance,and Amend the Fiscal Years 2024-2028 Capital Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of Amendment No. 1 to City Secretary Contract Number 57860,an Engineering Services Agreement with LJA
Engineering Inc.,to increase the contract amount by$35,000.00 for a revised contract amount of$131,395.00 for the Basswood Boulevard
at Old,Santa Fe Trail Traffic Signal project(City Project No. 103998);
2. Adopt the attached appropriation ordinance adjusting estimated receipts and appropriations in the Stormwater Capital Projects Fund in the
amount of$80,000.00 by increasing estimated receipts and appropriations in the Basswood Boulevard at Old Santa Fe Trail Traffic Signal
project(City Project No. 103998)and by decreasing estimated receipts and appropriations in the Drainage Improvement Projects
programmable project(City Project No.P00043)by the same amount;and
3. Amend the Fiscal Years 2024-2028 Capital Improvement Program.
DISCUSSION:
In July 2022,City Secretary Contract Number 57860 was administratively approved authorizing LJA Engineering Inc.to provide engineering
services for the design and construction of the Basswood Boulevard at Old Santa Fe Trail Traffic Signal project(City Project No. 103998).This
project was identified as part of the 2022 Bond Traffic Signals Program with initial project funding authorized by City Council in January 2021 with
Mayor and Council Communication(M&C)21-0076.The scope of this project includes design and construction of a new traffic signal,accessible
pedestrian signals(APS),and Americans with Disabilities Act(ADA)ramps.The design for this project is close to completion,and the City will be
issuing a task order using the existing on-call contract with Bean Electrical, Inc.for construction of the project. During one of the community
outreach meetings for this project,residents requested to improve drainage conditions near the intersection,The City reviewed the request and
made the decision to update the scope of this project to include drainage improvements.This Amendment No. 1 and additional funding
appropriated with this M&C will be used for engineering and construction services related to the drainage improvements.
The following table summarizes previous contract action and amendments:
Engineering Contract Date Amount
Original Contract Amount(CSC 57860) 07/19/2022 $96,395.00
Amendment Number 1 This M&C $35,000.00
Revised Contract Amount - $131,395.00
The following table summarizes the funding for the Basswood Boulevard at Old Santa Fe Trail Traffic Signal project:
� Fund Existing Additional Project
"� Funding Funding Total
30100-General Capital Projects $600,000.00 $0.00 $600,000.00
L
04-Developer $71,245.00 $0.00 $71,245.00
tribution
34014-2014 Bond =$231,834.43 $0.00 $231,834.43
Program
52002-Stormwater $0.00 $80,000.00 $80,000.00
Capital Projects
Project Total $903,079.43 $80,000.00 $983,079.43
Funding for this project was not included in the Fiscal Years(FY)2024-2028 Capital Improvement Program due to scope of the work was unknown
at the time of the development of the Capital Improvement Program. The action in this M&C will amend the FY2024-2028 Capital Improvement
Program as approved in connection with Ordinance 26453-09-2023.
Funding is budgeted in the TPW Dept Highway&Streets Department's Drainage Improvement Projects programmable project within the
Stormwater Capital Projects Fund for the purpose of funding the Basswood&Old San Fe Traff Signal project,as appropriated
This project is located in COUNCIL DISTRICT 2 and COUNCIL DISTRICT 7.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Drainage Improvement Projects programmable project within the
Stormwater Capital Projects Fund and upon approval of the above recommendations and adoption of the attached appropriation ordinance,funds
will be available in the current capital budget,as appropriated, in the Stormwater Capital Projects Fund for the Basswood&Old San Fe Traff Sig
project. Prior to an expenditure being incurred,the Transportation&Public Works Department has the responsibility to validate the availability of
funds.
Submitted for City Manager's Office b . William Johnson 5806
Originating Business Unit Head: Lauren Prieur 6035
i
Additional Information Contact: Monty Hall 8662