HomeMy WebLinkAboutContract 57278-CO2FORT WORTH
Project Name:
Project No.(s):
Project Description:
Contractor:
City Project Mgr.
Phone Number:
City of Fort Worth
Change Order Request
Westside III/IVN (Markum Ranch Pump Station -PS & Ground Storage Tank-GST)
56020 / 0600430 / 001680
DOE No.
N/A
CSC No. 57278-0O2
City Sec No.:
City Proj. No.:
57278
103010
PS Building; Three 4,750 gpm horizontal split case pumps w 400 HP motors;Three 7,000 gpm horizontal split case pumps w 300 HP motors; A
3 MG Concrete GST; Electrical & Controls, 1,600 kW generator, necessary piping, vaults and site work, etc.
Crescent Constructors, Inc.
Farida Goderya, PE
817-392-8214
Dept.
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
!Amount of Proposed Change Order
Revised Contract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%)
Change Order #
City Inspector:
Phone Number:
2
Date:
12/5/2023
Ivan Rocha, P.E. (KHA) / Ronnie Cardenas
682-234-2767
Water
$20,993,000.00
$25,400.00
Sewer
Contract Time
(Calender days)
$20,993,000.00 640
$25,400.00 09
Totals
$21,018,400.00
-$56,100.00
$20,962,300.00
$419,860.00
$394,460.00
$21,018,400.00 649
-$56,100.00 151
$20,962,300.00 800
$419,860.00
$394,460.00
-0.15%
$26,241,250.00
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Change Order No. 2 (CO2) is for the following modifications to the contract:
- The addition of a second intrusion switch on second Ground Storage Tank (GST) hatch,
- The modifications to pipe backfill for the yard piping in non paved areas (Deduct)
Staff concurs with the contractors request for an additional 151 calendar days on the contract for the delay in
switchboard delivery.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Contractor's Company Name
Contractor Name
Contractor Signn""
Date
Crescent Constructors, Inc.
Ryan Glanz, PE
'
;` ' gg-
12
. 2 0 .
2 3
Inspector Field Representative (KHA)
Date
Project Manager
Date
Iv-cutiRo-ch-ate
12/20!23
F,J; o,L (-,r,',--O
12/20/2023
Director (Water Dept)
Date
Construction Supervisor
Date
CI f;rto/ heI ltaWet
, s,
Dec 22, 2023
4.2—;/ i_3
Senior Assistant City Attorney
Date
Assistant City Manager
Date
Dec 22, 2023
Dana eury1c1°Cf
Dec 26, 2023
Council Action (f Required)
M&C Number N/A
M&C Date Approved
N/A
FORT WORTH
City of Fort Worth
Change Order Additions
Project Name
Project No.(s):
Project
Description
Contractor
City Project Mgr.
Westside III/IVN (Markum Ranch Pump Station -PS & Ground Storage Tank-GST)
56020 / 0600430 / 001680
DOE No.
N/A
City Sec No.:
City Proj. No.:
L 57278
103010
L,, uvuUuly, I Iu cc `L,I vv ypiii ILulILvl lL11I Jpul LQJc'pull ipb vv'ivu 1 Ir IIlULUI 3, I III cc 1 ,IJUU ypill ILUIlLOI I ldl 31.J11I LQJc
pumps w 300 HP motors; A 3 MG Concrete GST; Electrical & Controls, 1,600 kW generator, necessary piping, vaults
--yuc: ran uv,rL, nfn
Crescent Constructors, Inc.
Farida Goderya, PE
ADDITIONS
DESCRIPTION
PCM 06 - GST INTRUSION SWITCH
CMR04 - Deduct for Pipe Backfill Modifications (Deduct)
Change Order:
City Inspector
Water
Water
$4,900.00
-$61,000.00
2
Date:
12/5/2023
Ivan Rocha, P.E. (KHA) / Ronnie
Unit Unit Cost Total
1.00 LS $4,900.00
1.00 LS -$61,000.00
Water
Sewer
Additions Sub Total
($56,100.00)
($56,100.00)
FORT WORTH
Project Name
Project No.(s):
Project Description
Contractor
City Project Mgr.
City of Fort Worth
Change Order Deletions
Westside III/IV/V (Markum Ranch Pump Station -PS & Ground Storage Tank-GST)
56020 / 0600430 / 001680
DOE No.
N/A
City Sec No.:
City Proj. No.:
57278
103010
PS Building; Three 4,750 gpm horizontal split case pumps w 400 HP motors;Three 7,000 gpm horizontal split case
pumps w 300 HP motors; A 3 MG Concrete GST; Electrical & Controls, 1,600 kW generator, necessary piping,
Crescent Constructors, Inc.
Farida Goderya, PE
Change Order:
City Inspector:
DELETIONS
2
Date
12/5/2023
Ivan nu1na, r.L.. Iry in) r rwnnre
rnrfdnnnc
ITEM
DESCRIPTION
DEPT
Qty
Unit
Unit Cost
Total
Water
Sewer
Page1of1
Deletions Sub Total
MIWBE Breakdown for this Change Order
MIA/BE Sub
Type of Service
Amount for this CO
Same as original Contract
Miscellaneous
-$56,100.00
Total
-$56,100.00
Previous Change Orders
co #
DATE
1
1/9/2023
AMOUNT
$25,400.00
Total
$25,400.00
Page 1 of 1
FORT WORTH
PROPOSED CONTRACT MODIFICATION (PCM
OWNER: City of Fort Worth
PROJECT: Westside III/IV/V (Markum Ranch PS & GST)
CONTRACTOR: Crescent Constructors, Inc (CSC # 57278)
ENGINEER: Kimley-Horn and Associates, Inc
ENGINEER'S CONTACT: Josh Kercho, P.E.
PROJECT NO.: 103010
Description: GST Intrusion Switch
PCM NO. 006
NOTIFICATION TO CONTRACTOR:
WE ARE CONSIDERING MAKING THE CHANGE TO THE CONTRACT DESCRIBED IN THE ATTACHED
MATERIALS AND REQUEST THAT YOU TAKE THE FOLLOWING ACTION:
❑ NOTIFY US THAT YOU CONCUR THAT THIS CHANGE DOES NOT REQUIRE A CHANGE IN CONTRACT
TIME OR AMOUNT. A FIELD ORDER WILL BE ISSUED.
® SUBMIT A PRICE PROPOSAL WITH DETAILED COST BREAKDOWN AND REVISED SCHEDULE FOR
PERFORMING THE DESCRIBED CHANGE.
❑ A CHANGE ORDER WILL BE ISSUED FOR PAYMENT AT THE UNIT PRICE BID
❑ PROCEED WITH THE CHANGE UNDER THE TIME AND MATERIALS PROVISIONS OF THE CONTRACT.
BY: Josh Kercho, P.E. DATE: September 14, 2023
DESCRIPTION OF PROPOSED CHANGE:
® DESCRIBED HEREIN ® SEE ATTACHED
Provide a second intrusion switch on second Ground Storage Tank (GST) hatch, and install in series with the
other intrusion switch as indicated on Sheet 14.
CONTRACTOR'S RESPONSE:
WE RESPOND TO YOUR REQUEST AS FOLLOWS:
❑ WE CONCUR THAT THIS IS A NO COST OR TIME CHANGE, ISSUE FIELD ORDER.
® WE SUBMIT THE ATTACHED PRICE PROPOSAL WITH DETAILED COST BREAKDOWN AND REVISED
SCHEDULE FOR PERFORMING THE DESCRIBED CHANGE.
❑ WE ARE PROCEEDING WITH THE CHANGE AT THE UNIT PRICE BID
❑ WE ARE PROCEEDING WITH THE CHANGE UNDER THE TIME AND MATERIALS PROVISIONS OF THE
CONTRACT.
BY: Ryan Glanz, P.E.
DATE: 1 0/11/23
ACTION TAKEN: ® RECOMMENDED ❑ NOT ACCEPTED —REVISE AND RESUBMIT ❑ CANCELLED
COMMENTS:
BY:
Engineer and City recommend approval (see attached City
approval email).
DATE: 10/19/23
2560 Technology Drive #400
Plano, TX 75074
CONTRACT MODIFICATION REQUEST:
PROJECT:
ATTENTION:
PCM-006
MARKUM PUMP STATION
PROJECT NO. 103010
CITY OF FORT WORTH
1000 THROCKMORTON STREET
FORT WORTH, TX 76102
ATTN: FARIDA GODERYA
Attention:
The following change in contract on this project is proposed:
A breakdown of cost SHALL be attached.
Work shall not commence until authorized by the OWNER.
Description of the Proposed Change & Clarifications
DATE:
10.11.23
PCM-006: Add conduit run at base of the GST mowstrip to additional intrusion switch on hatch
TOTAL AMOUNT
$ 4,900
All work shall be in accordance with the terms, stipulations, and conditions of the
original Contract Documents. If the work herein provided for is Approved by
Change Order, the time of completion will be:
Increased
Decreased
Unchanged
By 0 Calendar Days
'ACCEPTED
City of Fort Worth
REJECTED
Ryan Glanz
Crescent
Date
CHANGE ORDER SUMMARY
Front Sheet
MARKUM PUMP STATION
CHANGE DESCRIPTION:
CONTRACT MODIFICATION REQUEST # PCM-006
Job #:
2022-01
Description
Labor
Material
Equipment
Subcontract
Total
DIRECT COSTS
-
-
-
4,481
4,481
LABOR BURDEN & FRINGES 55%
-
-
SUBTOTALS
-
-
-
4,481
4,481
CONTRACTOR MARKUP 15%
-
CONTRACTOR MARKUP 5% (SUBS)
224
BONDS & INSURANCE 3%
141
54
R
TOTAL
-
- - -
4,900
CLARIFICATIONS:
1
2
3
4
frPFSCFNT
CONS IIlUC1 .*$. NI:
2560 Technology Drive #400
Plano, TX 75074
CONTRACT MODIFICATION REQUEST:
PROJECT:
ATTENTION:
CMR-04.1
MARKUM PUMP STATION
PROJECT NO. 103010
CITY OF FORT WORTH
1000 THROCKMORTON STREET
FORT WORTH, TX 76102
ATTN: FARIDA GODERYA
Attention:
The following change in contract on this project is proposed:
A breakdown of cost SHALL be attached.
Work shall not commence until authorized by the OWNER.
Description of the Proposed Change & Clarifications
DATE:
10.11.23
(1) 24" CSS Cap for Backfill for the Steel yard pipe in the grass area (RFI 40)
Deletion of 588 CY of Cement Stabilized Sand Backfill. (1337 LF long x 4 wide x 3 VF)
TOTAL AMOUNT
$ (61,000)
All work shall be in accordance with the terms, stipulations, and conditions of the
original Contract Documents. If the work herein provided for is Approved by
Change Order, the time of completion will be:
Increased
Decreased
Unchanged
By 0 Calendar Days
'ACCEPTED
City of Fort Worth
REJECTED
Ryan Glanz
Crescent
Date
(CRESCENT
CONSTRUCTO*S. INC.
CHANGE ORDER SUMMARY
Front Sheet
MARKUM PUMP STATION
CHANGE DESCRIPTION:
CONTRACT MODIFICATION REQUEST # CMR-04.1
Job #:
2022-01
Description
Labor
Material
Equipment
Subcontract
Total
DIRECT COSTS
-
(66,146)
-
-
(66,146)
LABOR BURDEN & FRINGES 55%
-
-
r
SUBTOTALS
-
(56,146)
-
-
(56,146)
CONTRACTOR MARKUP CREDIT (5%)
(2,807)
CONTRACTOR MARKUP 5% (SUBS)
-
BONDS & INSURANCE 3%
(1,769)
(278)
s
TOTAL - 1 - - -
(61,000)
CLARIFICATIONS:
1
2
3
4
Crescent Constructors, Inc.
2560 Technology Dr. Suite 400
Plano, TX 75074
Office: 972.422.0014 Ce11: 469.576.0612 Fax: 972.422.0016
11.01.23
Farida Goderya
Senior Project Manager
City of Fort Worth
200 Texas Street
Fort Worth, TX 76102
Reference: Markum GST & Pump Station
CMR-05.2 Time Extension Request (Thru 10.10.23)
Here is a written request for a time extension of 151 days to take the project completion
to 06.12.24 based on the 10.10.23 CPM schedule update.
Below is a summary of a few of the items that has impacted the project thru 10.10.23.
Markum Ranch Pump Station
Time Impact items: 04/04/22 thru 10/10/23
Date: 10.10.23
ITEM
DELAY DESCRIPTION
PERIOD (TIME)
IMPACT (TIME)
1
ELECTRICAL SWITCHBOARD SUBMITTAL APPROVAL PROCESS
06.15.22 - 09.28.22
+42 Days
ACTUAL = 106 DAYS VS. 64 DAYS BASELINE
2
ELECTRICAL SWITCHBOARD MANUFACTURER DELAY
09.29.22 -12.08.23
+176 Days **
ACTUAL = 436 DAYS VS. 260 DAYS BASELINE
3
WS5 PUMP MANUFACTURER DELAY
09.20.23 -12.15.23
87 Days
4
RAIN EVENTS (04.04.22-09.30.23)
04.04.22 - 09.30.23
38 Days
Total of ** Items =
176 Days
Time Extension Request (As of 10.10.23)
Change Order #1 Days Added
NTP Date =
4/4/2022
Days
Original SC = 11/5/2023 580
CO#1 = 11/14/2023 9
CO#2 = 4/13/2024 151
Current SC (Thru CO#2) = 4/13/2024 160
Original FC = 1/4/2024 640
CO#1 = 1/13/2024 9
CO#2 = 6/12/2024 151
Current FC (Thru CO#2) = 6/12/2024 160
Sincerely,
Ryan Glanz, PE
Project Manager
+ 151 Days
+ 9 Days
.Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Farida Goderya, PhD, PE
Name of Employee
Senior Project Manager
Title
ATTEST:
Jannette Goodall
City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX