HomeMy WebLinkAboutIR 24-1784 INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 24-1784
To the Mayor and Members of the City Council January 9, 2024
Page 1 of 1
i
i7 Y
SUBJECT: 2026 BOND PROGRAM PLANNING OVERVIEW
r6 rn
Yg7'3
The purpose of this report is to provide the City Council with an overview of 2026 Bond Program planning
and draft program development components.
Exhibit A provides more information on the status of 2026 Bond Program planning, including DRAFT 2026
Bond Program components, including:
• Program philosophy
• Program goals and objectives
• Anticipated project categories
• Project prioritization criteria
• Proposed timeline
Should you have any questions, please contact Eric Fladager, Assistant Director, at 817-392-8011.
David Cooke
City Manager
Attachment: Exhibit A—2026 Bond Program Planning Overview Presentation
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
FORTWORTH.
2026 Bond Program Planning
Overview
Informal Report Exhibit
January 9, 2024
IR Exhibit A—2026 Bond Program Planning Overview Presentation
, by
PhIX
o5op
ram
Ord
Pr°g
6 8° rt
Q2 . • ceoe
t 2 • ep�a
rat 01A
one renova •
dete��
. ` •.
��e Cost t
e �`i ecy �a'�'�ed
. V s and p
�
osts \delopnt`
�u�r�rg op
er at�rg
. Re �, • 026
�s Nay 2 022
d to 2
. • nda a ,me as
0
nd Reece ertage osa `` others
. 8 ct peCc 2 °
C P tat °n �
1�
2026 Bond Program Goals • Objectives
ntain/Improve Existing Infrastructur
obility & City Services in Growth Areas
Enhance Transportation and Recreational Corridors
Allow for Flexibility and Partnership Opportunities
Achieve Balance and Fiscal Stewards (choices & trade-offs are Jill I
always required)
Support Areas that Produce High Tax Generation per Acre
relatedsite
Ca'te%of
building ateg�c prior�t�es.
�,t, eXisting they s
raft prole abilitatJonhousing or °acement'ea t affordable d assoc,ated
n rep\tur relat rk amenities an
aci\jt%eS new cons fo cinfrastruc e
F potentwal of eXist�ng pa
ects include t,on
prof vements• abilita ent.
t
imPrO .Cal) lacemen e park developm school s keo ds
r10..vert, nstructi f langiof futur t re labili'at`.on, and 'Par
parks k ude new co uis,t�on ° ood scree e rehab�l�
projects inclrer and aca
tructu truCtUre .dors, �e,ge bect ons�br\dg
imfras 5 corn ,nt
f ra na ental
MOV%Vltl ,r . n, estab\ts.et jlc s,g \s, en�ifonm
Streets and ia\ c0nstrucs'�treetl�gh er
St rter ss�ng �acilitat�e°recreatiOna\
a ter auaes and pass-
lncludes,deWalks►RR Cro
lots• air ford ra�llinkag
.zones, rk�ng aCe ante.
nh e
and p en Sp ide to e roved
ea5 and Op s of \and d ng concerns, gents.
tv►ra1 Ar r0vemen igate(loon deve\Opm
a ding
1�1 and i e osiov I\ue to sumo
AcauisitiO control d add
oenei*,lt'syities, an
P
Project Development — Influencing Factors
Data Collection
and Analysis Master Plans and
Strategic Goals
Neighborhood J
Meetings
Development
Activity
Boards and PROJECT
Commissions
City Council
Public Waitlisted Projects from
Meetings 2022 Bond Program
Service Demand
5
Departments Provide Project Details
Data and Analytic Support
nticipated Cost and Spen ing Schedule — an esig
Operating and Maintenance Cost
Identify Additional Funding Sources
Collaboration Opportunities
oje Delivery Compone s a Proposed Schedule
Department Project Ranking
FORT WORTH.
2026 Bond-Funded Project Request Form
Department: Date Form Completed:
Project Project Name: Project Location:
rct escr P oje iption:
Project D
Justification(including adopted plans supporting the protect,consequence of not funding,state or federal
mandated requirement,city ordinance/contract agreement,council directive/priority,etc.):
Development Is this protect shared with another city department? Yes ❑ No❑ If yes,please specify:
Is this protect shared with an outside(federal or state)agency? Yes ❑ No❑ If yes,please specify:
Is this protect timed to coordinate with another protect? Yes ❑ No❑ If yes,please specify:
Project Request Does this protect have a known impact on another Yes ❑ No❑ If yes,please specify
department(s)operational budget?
Department Name: Department Name:
Form (example) Personnel Costs $ Personnel Costs $
Operating Costs:$ Operating Costs:$
Other Costs:$ Other Costs:$
List all funding sources for this protect:
A, General Obligation(GO.)Bonds Yes ❑ No ❑ $
B. Grants—Federal Yes ❑ No ❑ $
C. Grants—State Yes ❑ No ❑ $
D. Grants-Local Yes ❑ No ❑ $
E. Transfers from Other Funds Yes ❑ No ❑ $
F. Certificates of Obligation Yes ❑ No ❑ $
G. Impact Fees Yes ❑ No ❑ $
H. Other(specify) Yes ❑I No ❑ $
TOTAL: I I$
Schedule of total protect costs(using total funding amount from above funding chart)
FISCALYEAR
2027 2028 2029 2030 2031
Property Acquisition $ $ $ $ $
Right-of-way $ $ $ $ $
Design $ $ $ $ $
Construction $ $ $ $ $
Equipment/Furnishings $ $ $ $ $
Other Required $ $ $ $ $
Infrastructure
(Water/Sewer)
Projected O&M Costs $ $ $ $ $
Total $ $ $ $ $
Additional Notes:
7
Draft Prioritization '
Criteria
Project Collaboration — Project connects with existing or proposed projects, and/or will share
other departments. are resources with
Federal, State or other Legal Requirements — Project satisfies federal, state or local man
court order, as well as contractual obligation, date, grantor
Leverage Opportunities — Project has committed funds from outside organizations.
Approved/Adopted Master Plan — Project advances the City's strategic goals and is consis
tent with
approved/adopted Master Plan(s).
Capital Replacement — Project replaces existing se or facility that is beyond economic
increasing risk of failure. asset
useful life with
Infrastructure — Project improves the City's transportation infrastructure.
Service Deficiencies — Project addresses significant deficiency in the level of service provided
community. p ded to the
Public Health and Safety — Project eliminates or prevents existing health, environmental
Economic Development/ROPI — Project stimulates significant job creation through ' or safety concerns.
corporate relocation, or the development of walkable mixed-use urban places. Project directly supportsxp on,
locations with high tax generation per acre.
Equity— Project is located within, or directly serves, a Social Vulnerability Index (SVI area with
score of Most Vulnerable. (Note: SVI replaces Super-Majority Minority Area (S-MMA) with a minority
mutative
Population of 75% or greater.) ty
0
. t;**jeS
objec
. comfv�jttee
anon
. or�t�z . . •
pry -
D t
ra , .
. • ' F - a tments
IL
. . • • . . • structure dep r
. • • , • from ,nfra needed
• • adersh;p date if
• rimari�y °f le and up
ee �onnprised p se\ect;on
cr;ter�a
. Cornnj,tt rev1ew draft
bcOvnmittee to
. Su
Draft Timeline
2024 Jan Feb Mar Apr May Jun Jul Aug Sep OctDec2024
Public outreach meetings begin
Departments submit projects
is
Draft funding recommendations for each category
Refine estimates and reprioritize projects
Finalize preliminary project list
2026 Bond IR Update meeting -debt capacity, prioritization criteria, project updates
1w Mar 2024
Draft Timeline
2025 Jan Feb I Mar I Apr May Jun Jul Aug Sep OctDec2025
Public outreach meetings continue
Finalize project list
Approve final project list
' Dec 2025
11
Draft Timeline
2026 Jan Feb Mar Apr May 2026
Public education meetings
Set bond election Bond
election
Jan 2026 May 2026