HomeMy WebLinkAboutContract 39655-CO2• I City of Fort Worth Change Order Request CITY SECRETARY CONTRACT NO. :fl lo55 -Ci)~ Project Name! Village Creek Reclaimed Water Delivery System Pump Station No.1 City Sec# 39655 ....... _____ __. Client Project #(s) ;:::=============================================:::::: Project Description Change Order # 2 Date 11/22/2010 City Inspector Mike Hill Contractor! Ark Contracting Services City Project Mgr.! Farida S Goderya, PhD, PE .._ ___________ ....., Original Contract Amount Extras to Date Credits to Date Dept. Pending Change Orders (in M&C Process) Contract Cost to Date Amount of Proposed Change Order Revised Contract Amount Original Funds Available for Change Orders Remaining Funds Available for this CO Additional Funding (if necessary) Water 3,167,580 .00 $42,427 .00 This Chan e Order #2 is t OFFICIAL RECORD CITY SECRETARY 'ned sum amount of$312,705 .00 and O Cale~ by: Totals Select Day Typ 3,167,580.00 It is unde tance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. 0·1-2 1-·1 1 P0 4 :5 1 I N CTIY OF FORT WORm PROPOSED CONTRACT MODIFICATION (PCM) Project Village Creek R.eclaim-~ &alioo No.I PmjectNo. (!0213 P27S-70530023183 Fund: Accoulll c.. Contrctur Azk CootlaetiDK Services Conlraclal''s Project No. 09128 Hngineer CP&Y Engmeer'1 Projeet Number CFW08085 . Comlructlm Comtmcomu-pr>, 00213 Manager Project Number PCM Dmcriptiaa TaafF.E.1-22 (F.atf"IIIII EfflucatOam l-22) PCMNo. 003 . TIie Oner pnp11u 1D make tbe foJlowlas addJtlom, modfflr.tiolll or deledom te tile work described hi the C•tnct Doc:ulmts. Aatllorizadn 1D proceed with tlaae m.anaes mmt be appnmd by Field Order or Chop Order ID accordace witlt tile Coetract Doc:maeam. Cott 1-CCIIb'lc:tm' :&unisbes all materials and labor 1. Replace c:xisting ElM Gato Actuator and giw old Actuator to plant mf[ 2. Provide Rotmk IQ70-173 with Stan and required mounting awmleoaoces Comractor shall ficlcl wrify moantiDg ~ 3. Remove cables ftom panel to actuamr, bot maintain conduit for future use. 4. Provide 3#10, #100 cable from dilcomlect to Actuat.or. Cable to be outdoor rated and DO longer than 2.S' in length. s. Provido 3 pole 30A cin:uit bieab:r in emaing panel 6. Provide 3#10, #100 cable from dilcolmect to AdUatDI'. Cablo to be out.door rated and DO }anger than 2.5• in length 7. Provide 30A NEMA4X-316 SS cfilconncct 8. Caanect cxi1ting control cables from BIM Gate Actuator 9. Replace Stan Guide 10. Adjust guides md seats Colt 1-Contracmr to perfarm all the wm:k u sta~ in Cost 1 with CFW providing actuator and mm ~ I,\~~ ~~'-~~ -b~ ~< P-\...<l, ~~\-~~~~.._, ~~ Pc.rt-~~~ ~<-'-~ ~(.c... ~ . ·~A-... ,r-o,.,. BY: ~ l f"t>y~~ - OFFICIAL RECORD CITY SECRETARY FT, WORTH, TX . ~ ~~--r_,' """2:: Om: lo h . ..st/1 ~ i>"-.11 'L) r ( - CITY OF FORT WORTH PROPOSED CONTRACT MODMCATION (PCM) Project ViUa&e 0-Reclaim-Pua, Slation No.I Project No. P27S-'70S30023l 83 Fund: Account Cealer ContracliDC Ark CoaCractiD& Semces Coa1nctm's Project No. 09128 F.ngjneer CP&Y Enamemr'• Project Number CFW08085 ec...rueticm Comtradioa Mwpr°I . 00213 Mamas' Project Numbs PCM Decipaoa Tia# P.E.1-22 (Bat PIIIII Efflamt. Gate 1-22} PCMNo. 003 NOTD'ICATION TO CONTRACl'OR: We ue comidering making die cbanF to the contract described in the atlached materiaJs, and request that you tab the folJowina actim: _ Notify us that yoa cmar that this dlanp docs not n,quim a c:bmp in c:omract time er amount. ~ ordCl'will be issued. Submit a prlc:e propmal with clllCailed COit breakdown of labor, mamials, equipnmt, and all odiar COltl mo ilffl'l witb this change, ad a reYiled schedule for pa&• rc.in1 lhe dmcribed c:bange. __ Proceed with 11m cmmgo.onlllr under time wl materials provisions of the comract. ~r-~tf:~¢J-\b It~ BY: C\ I CONTRACTOR'S RESPONSE: We respond to yourrequmt as fullows: _ We concur that 1his is a no cost or time dmlge. See atlllched field ordCI'. __ Wo submit the aUacbcd price propcml with detailed COil broakdown and rwised schedule fbr. Ptdb:miug tho cbcribed cbanp. _·_ We are proceedi• wi1h change under time and mataials provisions oflhe cootract. BY: Dale: ACflON TAICBN: _ Propc.ed COldlal:t Modificatim rqeclm. Coalndlarnocifled not 10 nspoad. BY: Field Order limed: -- -Chlnae Ord.-Issued: Page 1 of2 OFFICIAL RECORD CITY SECRETARY No. No. Date - Dm - By By °'* 111.c"'""o St.~ \ I t~\\\ .. -·-· FT. WORTH, TX -· 8,. '( I ,~c, • f'N ---·----·--------------. e-P-J .... ---------·-.. (') 0 ;!I =i "" "" -< -~ (') tA -m ,,. :::a (') ... -t ::a ?! ::c m :.. ;! 4 lmi >< :::a 1• , -< .. , DNcrlDClon 1t• llulce Oatl ONrator with Item Rotork Elec:tric C>Derator PC S11m 2.75" dia . 210.11 lanath , 304 SST Tilruat Nut PC Stam Gulde lmounta k> well) 3e" Floor Stand Control Station Stand 1 /2 SS anchor Bolla 30am FPE BrNk« Satatv Switch 1"Seallb 1• Sealtlta Connector lt'IOXHHWV'tb FleldC:0.t IMurance/Bond (S.1f7) OHandP-11% Quant Unit 1 .. 1 .. 1 .. 1 .. 1 .. 2 .. 1 .. 4 .. 1 .. 1 •• 2 ~ 2 .. 400 " To«al GrendTotal Total 29,222 21,222 121 30,147 4,122 34,170! Labor Extent 2,172 ,, - Pa&el PCM--00 Labor/ burden 11awr1a1 llllwrlall Equip. Equl1ment lub Subcontractor Unit Cos Total Extent Unit Colt Total Emnt Jnlt Col Total Extent UnltCos1 Total 750 750 13 ,1172 13,1172 0 0 500 500 7,431 7,431 0 0 175 175 1,189 1,189 0 0 200 200 1,318 1,318 0 0 150 300 934 1111111 0 0 25.00 25 178.00 178 .00 0 0 2.50 10 9.53 38.12 0 0 50 .00 50 285.00 285 .00 0 0 50.00 50 750 .00 7.50 .00 0 0 2.00 4 2.20 uo 0 0 8.75 18 18.50 37.00 0 0 0.23 90 0.25 100.00 0 0 27,051 Project Manager -Ark Contracting Services October 28, 2010 Ms. Farida Goderya, PE, PhD Project Manager Partners for a Better Quality of Ufa City of Fort Worth Water Department 1000 Throckmorton Street Fort Worth, TX 76102 RE: Village Creek Reclaim -Pump Station No.1, Project No. P27S-70530023183 PCM-003 Tag# F.E.1-22 (East Final Effluent Gate 1-22) CP&Y Project No. CFW08085 Dear Ms. Goderya: CP&Y recommends approval of PCM-0>3. Justification for approval of the PCM Is presented in the following paragraph. The Village Creek Reclaimed Water Eastern Delivery System Pump Station No. 1 is located at the Village Creek Chlorine Contact Basin 2 effluent. Chlorine disinfected water from the CCB supplies the reclaimed water pump station. Chlorine Contact Basin 2 has two parallel plug-flow chlorination basins, each with gates at the influent and effluent ends of the basin. Either or both sides of the CCB may be in service as required to treat the plant flow. To properly operate the CCB and to provide chlorinated water to the Reclaimed Water Eastern Delivery System, the gates within the CCB must be functional. The effluent sluice gate on the eastern half of Chlorine Contact Basin 2 was damaged during a storm event on September 8, 2010 and cannot be operated. The required repair will involve replacing the stem, stem guides, electric operator and associated items. We have reviewed the proposed costs and are of the opinion the costs are reasonable and fair . Please feel free to contact me should you have any questions. Sincerely yours, CP&Y, Inc. Michael F. Graves, PE (TX, OK) Senior Associate MFG/Ism Enclosure OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX _J 115 West. 7th Street. Suite 1500 Fort Worth , Texas 76102 817 .354 .0189 • 817 .354.4935 fax www.cpyi .com OFFICIA CITY OF FORT WORffl PROPOSED CONTRACT MODIFICATION (PCM) Project Village Creek Reclaim-Pump Station No.l Fund: Account ---------- Project No. Centrr 00'213 P275-70530023183 Contractor Ark Contracting Secviccs Contractor's Project No. 09128 ----------------------- Engineer Construction Manager CP& Y Engineer's Project Number CFW08085 ------------- Construction Manager's 00'213 _F_arida_._S_Godcrya. ___ -'--PhD--' ...... P_.E_. __ Project Numbea' PCM Description _W~et~W~ell~Mc:J~nm~~-ficati~~·om~--------PCMNo. _004 ____ .... The Owner proposes to make the following additions, modifications or deletlom to the work described in the Contract Documents. Authorization to proceed with these changes must be approftd by Field Order or Change Order in accordanee with die Contract Documents. A change orda' is necessary to modify the Reclaimed Water Wet Well to provide isolation of reclaimed water from flow in the Chlorine Contact Basin and to provide adequate wet well volume. The contractor shall incrca.se the si7.e of the reclaimed water wet well by connecting a second bay which contains a CCB high-flow effluent pump. The pump and motor shall be removed and this bay sball provide additional volume to the reclaimed water wet well The walls of the two existing bays will be modified to create the reclaimed wab:r wet well. Portions of the walls that form tho oub:r perimcta' of the wet well will be raised 11 feet to a height of 472. 7 ft, which is equal to the height of the walkway platform abo~ the CCB. The oUb:r walls of the wet well will also be strengthened with concrete columns and beams to withstand the potential water depth diffi:rcntial between the wet well and the CCB. A 6 ft x 7 ft slide gate and a bulkhead will be added on the openings between the CCB and the Reclaimed Water Wet Well. All General Specifications of the original contract shall apply. See the following attached rcfereoccd construction drawings and specification. PCM-004 the "Work" 1. Specification Section 11281-Slidc Gate 2. Drawings: M..()I) thru. M-10 3. Drawings: S-07 thru. S..16 I ha~ reviewed tho construction documents with the Contractor and the proposed Time and Material estimates provided by the Contractor. The estimated costs appear reasonable for the proposed work. The work has also been coordinated with plant staff u well as our design team. No additional contract time is req~bythe~~~ ReviewedBy: ~,/~---Dale: J~~/zo10 Midlael P. Ora PB CITY S-.....;,;;,;;,r.--,.....,.-----..;;:;;;;;.;------1_...f_~_O;..:.,_~_(.~---------~ FT. WORTH, CITY OF FORT WORTH PROPOSED CONTRACT MODIFICATION (PCM) Project Villye Creek Reclaim -Pume Station No. I Project No. P27S-70S30023 I 83 Fund: Account Center Contractor Arie Contracting Services Contractor's Project No. 09128 Engineer CP&Y Engineer's Project Number CFW08085 Construction Consb'uction Manager's 00213 Manager Farida S God!!l'.a, PhD, P.E. Project Number PCM Description Wet Well Modifications-PCMN~ 004 NOTIFICATION TO CONTRACTOR: We are considering making the change to the contract described in the attached materials, and request that you take the following action: __ Notify us that you concur that this change does not require a change in contract time or amount A field order will be issued. Submit a .. Not to Exceed" price proposal with detailed cost breakdown of labor, materials, equipment, and all other costs associated with this change, and a revised schedule for performing _x_ the described change. __ Proceed with the change order under time and materials provisions of the contract. BY: Date: CONTRACTOR'S RESPONSE: We respond to your request as follows: __ We concur that this is a no cost or time change. See attached field order. X We submit the attached "Not to Exceed" price proposal with detailed cost breakdown and revised __ schedule for performing the described change. ~time ,nd materials provisions of the conttacL BY: ~ -Date: JO idD I r ACTION TAKEN: __ Proposed Contract Modification rejected. Contractor notified not to respond. BY: Field Order Issued: -- _ Change Order Issued: OfflCIAL RECORD CITY SECRETARY fT. WORTH, TX No. No. Date Date By Date By /:::. ~ October 28, 2010 Ms. Farida Goderya, PE, PhD Project Manager Partners for a Better Quality of Life City of Fort Worth Water Department 1000 Throckmorton Street Fort Worth, TX 76102 RE: Village Creek Reclaim -Pump Station No. 1, Project No . P275-70530023183 PCM-004 Wet Well Modifications CP&Y Project No. CFW08085 Dear Ms. Goderya: CP&Y recommends approval~ Justification for approval of the PCM Is presented in the following paragraph. -~ Future upgrades at Village Creek Wastewater Treatment Plant will involve adding UV disinfection of filtered effluent to better ensure a high reuse water quality. Water that is reclaimed and provided to reuse customers connected to the VIiiage Creek Eastern Delivery System will lnitlally be disinfected in the existing chlorine contact basin, but this will change when the future UV disinfection system ls installed. A change order is necessary to modify the Reclaimed Water Wet Well to provide isolation of reclaimed water from flow in the Chlorine Contact Basin and to provide adequate wet well volume. The current wet well is located near the effluent of the CCB in a single pump bay originally designed for an expansion CCB high-flow effluent pump. However, the pump was never installed and this bay was converted for installation of the three reclaimed water pumps that will feed the Eastern Delivery System. The size of the reclaimed water wet well will be increased by connecting a second bay which contains a CCB high-flow effluent pump. The pump in this second bay has been out of service for several years and Is not needed. The pump and motor shall be removed and this bay shall provide additional volume to the reclaimed water wet well. The walls of the two existing bays will be modified to create the reclaimed water wet well. Portions of the walls that form the outer perimeter of the wet well will be raised 11 feet to a he ight of 472.7 ft, which is equal to the height of the walkway platform above the CCB. The outer walls of the wet well will also be strengthened with concrete columns and beams to withstand the potential water depth differential between the wet well and the CCB. A 6 ft x 7 ft slide gate will be added on the opening between the CCB and the Reclaimed Water Wet Well. Initially the wet well wiU receive flow from the CCB through the slide gate which will be open for normal operation. In the future, the proposed influent pipe to the wet well will be connected to the UV system .--....ai~M-slfffe1~!"111,tf. I be closed for normal operation. The reclaimed water wet well will be Isolated 0 CITY SECRETARY !FT. WORTH, TX eiVe only the UV treated water. 115 West 7th Street, Suite 1500 Fort Worth , Texu 76102 817 .354 .0189 • 817 .354.4935 tax www.cpyi .com ' • We have reviewed the proposed costs and are of the opinion the costs are reasonable and fair. Please feel free to contact me should you have any questions. Sincerely yours, CP&Y, Inc. ~~ Michael F. Graves, PE (TX, OK) Senior Associate MFG/Ism Enclosure OFFICIAL RECORD CITY SECRETARY FT, WORTH, TX Partnffl for o Better Quolity of Life C I\Y j .. , , . .. : ·-· . ! . . ' Village CrNk Pump Sta. PCIMXM Oct. i,2010 llaml 11 • DNcrlDtlon Qum,t . ''"!I ~N RAL COND"10NS ;1'1 li'm M ln<Hlr (50%) 0 .5 • ii 1 • n -·-l'll88 0 ' ii ~ ~.2Q/dumnatar 0 ldl I iatetv 2 --. ..i Storaaa/dull'IDIOffl 0 ... • 0 ... no/Dlatn 0 9 la Item 1 10 Pick UD/ one-tonaltrallers 0 11 28tncrane 1 12 RT 1135 0 13 85zJIOz 0 14 Air Como/ welder/ narwatJ llnht n1a 0 15 Cone. Pumol hoau 0 18 I Reoalra/ maintenance 1 17 Fuell tlltera/ olV rubber 1 ....... -Quant Effl. PumD Station DIDlna 1 a.,,w lite a,;ceu/ femD aCC888 1 2 Oewaw mtAI water control 1 3 4 Drtll/ IIOOXV dow9la 830 5 Acceea acaffolellno/ n1attorma 1 e Cone. BMma/ walla-tormnnatall 88 7 Cone M 11 .12\/DUfflD 78 8 Rebar/ drautmallJ acceuortea 15 9 10 Slide aates-&'x7'·SS n1Ate na, ... 1 11 Anchora 1 12 Mlle. Iron-1 13 Clld Dlt-3111" alum 292 14 Framlnll' beema-55316 80 15 C12x20 SS318 9 11 II 111 llulk head 1 17 Tie end DUfflD CIIS8 1 18 f'IUa 54" VI/ rotate can-FE 15 180 19 38" mnncJJ BF/ weldlnnl lnAn-.t, 180 20 Pine ~.·---;;.;beam• 1 21 Electrtcal/ demo 1 22 ~ 1 Unit Total Labor mo la mo mo mo la II la la mo mo mo mo la mo la la 7,271 2,171 Unit Total Labor la la .. II r:N r:N tn .. II la at If If II .. mnh mhr II Is la 240,888 41,402 Ark Contracting Services, LLC Labor/ burden ....... .......... Unit Cost Total Ext.nt Unit Cost Total 3750 1 875 0 100 100 0 0 0 0 0 0 0 0 50 100 50 100 100 0 80 0 0 500 0 0 200 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 800 0 0 0 96 96 180 180 0 960 960 1.220 Labor/ burden llatllrlal llaterlala Unit Cost Total ·-Unit Cost Total 3 .800 3800 1 .20ll 1.ll'Olc 2200 2?M 4800 4800 0 0 12 7580 11 .40 7182 5800 5800 9800 9800 40 2720 20 1360 0 80 8080 0 850 12750 800 800 18.000 18000 2800 3800 0 24.- 8 1752 0 16.40 1 312 0 22 198 0 800 IOO 11 000 11000 0 0 1.200 1.200 1-200 1.200 19 3420 2000 19 3040 39736 1.200 2.000 0 0 3600 3600 1 800 1800 0 0 147.218 1] Equip. Eau1 i,ment Subcontractor Extent Unit Cost Total Sub Extent Unit Cost Total 0 0 0 0 0 0 0 0 0 0 0 0 150 0 0 0 0 0 0 0 0 500 600 0 0 800 0 0 3.200 3.200 0 3500 0 0 32Uli 0 0 4500 0 0 3.200 0 0 0 0 0 80 80 0 0 3,200 880 Equip. Eau• i,ment 8ubcontractor i:vtant UnltCost Total Ruh 11:'vtant UnltCost Total 0 800 600 3500 3500 1.200 1~ 0 0 3 1 890 0 0 0 0 280 19040 0 15 1140 0 300 4Mll 0 2500 2 !'irV1 0 0 0 0 0 0 0 0 0 0 (1\ 0 0 0 0 0 0 0 1.200 :l 0 0 3500 0 0 0 0 0 0 0 11 000 11 000 (. 0 2000 2000 ~ 5,390 46,680 Village Cl'Nk Pump &ta. PCIMJ04 Oct. 1, a.no 247,959 43,573 ,,aoo 0 $280,000 Ark Contracting Services, LLC 148,436 ' ; 2) 8,590 47,360 10/28/2010 .. Page 1 of 2 City of Fort Worth, Texas Mayor and Council Communication COUNCIL ACTION: Approved on 1/4/2011 DATE: Tuesday, January 04 , 2011 REFERENCE NO.: **C-24675 LOG NAME: 60RECLAIMED PUMP STATION CO2 SUBJECT: Authorize Change Order No. 2 in the Amount of $312,705 .00 to City Secretary Contract No. 39655 with Ark Contracting Services, LLC , for the Village Creek Reclaimed Water Eastern Delivery System Pump Station No. 1, Located at the Village Creek Wastewater Treatment Plant (COUNCIL DISTRICT 5) RECOMMENDATION: It is recommended that the City Council authorize the City Manager to execute Change Order No. 2 in the Amount of$312 ,705.00 to City Secretary Contract No. 39655 with Ark Contracting Services, LLC , for the Village Creek Reclaimed Water Eastern Delivery System Pump Station No. 1, located at the Village Creek Wastewater Treatment Plant, thereby revising the total contract to $3 ,522 ,712.00 . DISCUSSION: On December 08, 2009, (M&C C-23964) the City Council authorized the City Manager to execute a construction contract in the amount of $3 ,167,580 .00 with Ark Contracting Services , LLC , for the Village Creek Reclaimed Water Eastern Delivery System Pump Station No. 1. On November 16 , 2010 , (M&C C-24603) Change Order No. 1 (in the amount of $42,427 .00) was authorized to include the installation of a 96-inch Sluice Gate Actuator and a Total Suspended Solids (TSS) meter. Change Order No . 2 includes the following two items. One is the repai r and replacement of a 96-inch sluice gate stem and electric operator. The existing 96-inch sluice gate is located between the east chlorine contact basin and final effluent pumps basin where the reclaim pump station is located . Th is sluice gate is old and was damaged during a storm event. A replacement is needed to operate and isolate the two basins when the reclaim pump station is in operation . The second, is the modification of the reclaimed water wetwell to provide adequate volume , as well as the isolation of reclaimed flows from the chlorine contact basin and other regular plant effluent for the purpose of additional disinfection. Staff has reviewed th is change order and is in agreement with the scope of work and costs associated with the work . Ark Contracting Services , LLC , is in compliance with the City's M/WBE ordinance by committing to an additional nine percent M/WBE participation on this Change Order No. 2 . The City's goal on this change order is seven percent. This project serves the eastern and northern parts of the City and is located in COUNCIL DISTRICT 5, MAPSCO 68N . FISCAL INFORMATION/ CERTIFICATION: The Financial Management Services Director certifies that funds are available in the current capital budget, as appropriated , of the ARRA 2009 SRF Reclaim Water Fund . FUND CENTERS: http ://apps .cfwnet.org/ ecouncil/printrnc. a sp ?id= 144 7 O&print =true&DocType= Print 1/5/2 011 TO Fund/Account/Centers CERTIFICATIONS: Submitted for City Manager's Office by: Originating Department Head: Additional Information Contact: ATTACHMENTS FROM Fund/Account/Centers P256 541200 701300021383 Fernando Costa (6122) S . Frank Crumb (8207) Farida S . Goderya (8214) 1. 60RECLAIMED PUMP STATION CO2 FAR Correctecl .pdf (CFW Internal) 2. 60RECLAIMED PUMP STATION CO2 MAP.pdf (Public) 3. 60RECLAIMED PUMP STATION CO2 MWBE.pdf (CFW Internal) http://apps.cfwnet.org/ ecouncil/printmc.asp ?id= 144 7 O&print=true&DocType= Print Page 2'of2 "· $312.705.00 1/5/2011