HomeMy WebLinkAboutContract 40241-CO3FORT WORTH .. ~
City of Fort Worth
Change Order Request
Project Name I Hyde Park Transit Plaza/ 9th St Improvements
Cli ent Project #(s)I C202-697700205 ; GR76-006302393850
Project Description! Reconstruction of 9th St and Hyde Park
Contractor! The Fain Group Change Order # 3
City Sec # 40241 ~-----~
Date 7/14 /2011
City Project Mgr .l~B_ec_k~y_Pi_ls __________ ~ City Inspector Mike Myers ~-----------~
Dept. Hyde Park 9th St.
Or iginal Contract Amount $1,484 ,640 .71 $1 ,127 ,031 .90
Extras to Date $143 ,664.43 $33 ,044 .72
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date $1,628 ,305 .14 $1 ,160 ,076 .62
!Amount of Proposed Change Order ·$87, 180.85 $87,180.01
Revised Contract Amount $1,541,124 .29 $1,247 ,256 .63
Original Funds Available for Change Orders $148 ,464 .00 $112 ,703 .00
Remaining Funds Ava il able for this CO $4,799.57 $79,658 .28
Additional Fund ing (if necessary) $7 ,521.73
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
' J STIFICAJION (REASONS) FOR CHANGE ORDER '
Justification sheet attached
Totals Select Day Type
$2 ,611 ,672.61
$176,709 .15
$2,788 ,381 .76
-$0.84 .
$2,788 ,380 .92
$261 ,167 .00
$84,457 .85
$7 ,521 .73
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money ) for all costs arising out of , or incidental to, the above Change Order.
M&C Number M&C Date Approved
fORTWORTH ----.----City of Fort Worth
Change Order Additions
Project Name Hyde Park Transit Plaza/ 9th St Improvements
Client Project # C202 -69 7700205 ; GR76-006302393850
Project Description Reconstruction of 9th St and Hyde Park
Contractor The Fain Group
City Sec# 40241
Change Order# 3 Date 7/14/2011
City Project Mgr. Becky Pils --~--------------' City Inspector Mike Myers .__ _ ____, _________ __,
ADDITIONS
Change Order Additions Page 2 of 6
-I
Hyde Park $66 ,268 .78
9th St. $138 ,127 .27
Sub I otal Additions $LU4 ,J~o .U5
Change Order Additions Page 3 of 6
fO R T W O RTH ---.-----
Project Name
City of Fort Worth
Change Order Deletions
Hyde Park Transit Plaza/ 9th St Improvements
Client Project# C202-697700205 ; GR76-006302393850
Proje ct Description Re co nstruction of 9th St and Hyde Park
Contractor The Fa in Group
City Sec# 40241
Change Order # 3 Date 7/14/2011
City Project Mgr. Bec ky Pil s .__ _ _.__ ____________ ___. City Inspector Mike Myers '-----'----------~
DELETIONS
Change Order Deletions Page 4 of 6
-l
48 LANDSCAPt PAVtRS 8th St. 403.00 SY $1 Lb.4L $00 ,84/.Lb
!l 1 KtMOVt SM KU SN SUP & ARM Hyde Park 10.00 EA $84 .Lf $!l4L . /U
Hyde Park $153 ,449 .63
9th St. $50 ,947.26
Sub Total Deletions $204 ,J\:Jb .89
Change Order Deletions Page 5 of 6
-· .
M/WBE Breakdown for this Change Order
MWBE Sub Type of Service ·Amount for this CO
Total $0.00
'
Previous Change Orders
CO# ,. DATE AMOUNT
Total $0.00
'
-· . ..
... '
Hyde Park Transit Plaza DOE 5285/Ninth Street Improvements DOE 5276
Justifications for Change Order 3
Item 145 -When the proposed intersection of Ninth Street and Throckmorton Street was excavated in
preparation of the pavement sub -grade , a twelve foot section of a 30 inch storm drain was found to be
previously damaged . The corrugated steel section was removed, a section of a concrete tunnel serving
the old public library basement demolished and disposed of, and a new reinforced concrete storm drain
placed and reconnected to the existing adjacent pipelines . The total cost of this work is $11 ,967.54 .
Item 146 -After installation of the paver brick in the Ninth Street and Jones Street intersection the
mastic material bonding the pavers to the asphalt leveling course began to wick to the surface and stain
the pavers . It was found that this type of paver placement is not recommended for use i n this climate
and that a sand leveling course is preferable. Using sand bedding in lieu of the specified asphalt with
mastic system of paver placement for three intersections and asphalt only bedding in the remaining
sidewalk construction yields a credit of $14 ,402.25.
Item 147 -After both sidewalk accessibility ramps were constructed on a steep slope on Ninth Street at
Jones Street, handra i ls were recommended to be added . The handrails will serve to eliminate a tripping
hazard caused by grade differences between the sidewalks and the ramps as well as compliance with
Federal ADA and State TAS requirements . The total cost for this work $3,220.00 .
Item 148 -The removal, storage and resetting of two existing marble benches located near the Panther
Fountain prior to construction was not included in the construction documents. The total cost for this
additional work is $1,000.00 .
Item 149 -A 150 foot 4-inch diameter electrical conduit was proposed to be installed by boring under
pavement. The contractor was able to install the conduit by open trenching for a total savings of
$1,156 .50.
Items 2, 13, 16, 17, 18, 21, 23, 31, 49, & 73 -These items are listed to represent the increase in
quantities on the project .
Items 7, 8, 12, 14, 15, 17 , 20, 22 , 29 , 31, 43 , 44, 45, 47, 49, 54 , 59, 63 , 66, 68, 69 , 70, 72 , 75, 76 , 77, 80,
83 , 111, 48, & 81-These items represent deletions of quantities not used on the project.
PROJECT NAME :
TXDot CSJ No :
BuySpeed No (T/PW):
C ity Project No :
Contract No :
0 .0 .E. No :
Attachment to Change Order No :
Today's Date :
PROJECT SUMMARY SHEET
(Change Order Attachment)
Hyde Park Transit Plaza and Ninth Street Improvements
0902-48-495
P0-10-00061285
GR76-006302393830
CS40241
5285 / 5276
3
7/19/11
H~de Park
TOTAL H~de Park Traffic Signal Ninth Street
O ri g inal Contract Amount:
Extras to Date :
Credits to Date :
Contract Amount to Date :
Amount of Proposed Change Order:
Revised Contract Amount:
Contingency Funds Ava il. for Admin . Change Orders :
Remaining Funds Available for Change Orders:
Additional Funding (if necessary):
$ 2,611,672.61 $ 1,380,468.60 $
$ 176,709.15 $ 143 ,664 .43 $
$ $ $
$ 2,788,381.76 $ 1,524 ,133 .03 $
$ (0.84) $ (87 ,180 .85) $
$ 2,788,380.92 $ 1,436 ,952.18 $
$ 261,167.00 $ 148,464 .00 $
$ 84,457.85 $ 4 ,799.57 $
$ (7,521.73) $ $
Prepared By : Christy Ezernack T/PW Construction Services
104 ,172.11 $ 1,127 ,031.90
$ 33,044.72
$
104 ,172 .11 $ 1,160 ,076 .62
$ 87 ,180.01
104 ,172.11 $ 1,247,256.63
$ 112 ,703.00
$ 79 ,658 .28
$ (7 ,521 .73)
•• ~,41,
Hyde Park Transit Plaza/Ninth Street Change Order #3
PLEASE RETURN SIGNED CHANGE ORDER TO BECKY PILS
SIGNATURES REQUIRED:
~ Doug Black, Assistant City Attorney /Lu. ·J1-l 'f -I I/ (fJi;;, { · ( q. I/
~ Fernando Costa, Assistant City Manager
The purpose of change order #3 is to adjust field measured quantities for both units in the
contract, Hyde Park and Ninth Street. It also includes line items for work not included in
the original contract. The change order does not incur any additional cost to the project.
Please let me know if you have any questions.
Becky Pils
Senior Planner
Planning and Development Department
817-392-7645
PLEASE RETURN SIGNED CHANGE ORDER TO BECKY PILS