Change Order No. 0 1
CHANGE ORDER
CITY SECRETARY
CONTRACT NO . j-()5 .::l~ -\.P \
---------------------
Date: December 2, 201 O
Project Name: Fort Worth Phase I P25 -TX-091171A
Customer Name: City of Fort Worth -~-------------------
Customer Project Mgr: Alan Girton ---------------------
The purpose of this Change Order is to:
Update the contract documents with c hanges determined during the Design Review. Th is is a no-
cost change order that includes clarificat ions and correcti ons to verbiage in the System Design
and Statement of Work sections of the orig inal contract documents. The updated System
Description and Statement of Work are attached with this document.
Contract# City of Fort Worth : Contract Date: 6/28/10
Contract 40526
Motorola Contract:
10-15074/RH/CB
In accordance with the terms and condit ions of the contract identified above between
The C ity of Fort Worth and Motorola, Inc., the following changes are approved:
Contract Price Adjustments
Original Contract Value : $1 ,649,850.04
Previous Change Order amounts for Change Order
numbers I I through I I N/A
This Change Order: $0
New Contract Value: $1 ,649 ,850 .04
Completion Date Adjustments
Original Completion Date : 7/8/2011
Current Completion Date prior to this Change Order: 7/8/2011
New Completion Date : 7/8/2011
Chan es in Equipment: (additions , deletions or modifications
The only material equipment adjustment relates to a minor length and type of coaxial cable ..
There are no other equipment changes to the originally priced equ ipment. C larifications and
corrections to the prev ious System Description and Statement of Work verbiage about
equipment, which are incorporated in the updated documents , include:
1. Only two (not four) antennas are being provided at the Burnett Plaza s ite
2. No equipment is to be provided for the Aledo radio s ite
In both cases above , the final version of the verb iage had not been updated properly during final
o ,a ions . ,s· han e Order, these corrections will be com leted .
5'1 Page 1 of 2 Fort Worth Phase I-P25 -TX-
CITY SECRETARY 091171A
FT. WORTH . Tl(
• MOTOROLA CHANGE ORDER
Chanaes in Services: (additions, deletions or modifications)
There are no service changes with this change order. Clarifications and corrections to the
Statement of Work that relate to services include:
1. Only two antennas are being provided at the Burnett Plaza site
· 2. No equipment is to be provided for the Aledo radio s ite
3 . Clarified the number of electrical circuits needed for Burnett Plaza and Eagle
Mountain sites
4 . Clarified the T1 requirements for the project, to be suoolied by the City of Fort Worth
Schedule Chan es: describe chan e or NIA
There are no schedule changes
Pricina Chanaes: (describe chanae or NIA)
There are no pricing changes
Customer Responsibilities: (describe change or NIA)
There are no customer responsibility changes, although some responsibilities were clarified in the
updated Statement of Work ··
Payment Schedule for this Change Order:
(describe new payment terms aoolicable to this chanae order)
There is no change in payment schedule
Reviewed by : ___________ _
City of Fort Worth Project Manager
MOTOROLA, INC .
Printed Na::: =~==~::,:f;;:=:~:::!:======
Title: 4-GttJAMl Svcs: ttf~
Date: I /g.7 l.zotl , I •
OF l~"BC8 ver 3 .o Page 2 of 2
CITY SECRETARY
FT. WORTH, TX
By : :L,.~~::_~~-___:=-___;21
Printed Name:
Title:
Date:
KaPcn L. Montgomery
Assistant City Manage r
2-:ZJ--d--71 1
APPROVED )\S TO FORM AND LEGAL .... _"" .
As~Pl'l!!'Yr x-
0911?1A