HomeMy WebLinkAboutContract 40539-CO3.,.. • FORT WORTH. ~ Project Name! Harley Street Relocation City of Fort Worth Change Order Request Client Project #(s~ 01468 (Water/Sewer) 00143 (T/PW) DOE# 5380 CITY SECRETARY coNTRACTNO. Lfps:;H -Cc~ City Sec # 40539 ....._ _____ __, Project Description Paving, Drainage, Water, Sewer (University @ Harley) from Conservatory Dr. to Montgomery Street Contractor! S.J. Louis Construction Change Order# 3 Date City Project Mgr ..... ! _L_eo_n_Wi_1lso_n __________ _. City Inspector Carlos Vasquez Original Contract Amount Extras to Date Credits to Date Dept. Pending Change Orders (in M&C Process) Contract Cost to Date T/PW Water 1,375,302.70 $4,887.50 2/24/2011 Contract Time CD 340 340 72 412 High early yield concrete was used for utility trench repairs on University Drive to minimize the interruption to traffic associated with various activities within the Cultural District area. We also used high early yield concrete on Bumett-Tandy and on Rip Johnson due to the time frame of the upcoming horse shows at the Will Rogers Memorial Center. The 36" casing pipe exceeded the contract amount because there was a section of water line that was not included in the plans. This was on water line "A" from Sta. 53.82 to Sta.1+10. Additionally, the change in the size and location of the fire line service was based on coordination with the design consultant for the proposed Multipurpose Facility. ~~~i>.ll.4ll #~~ by: ~~. 0 /l ,_o• ,n 'L,j.,,,.,~ So' ~~~~~~:....!..!.:~c:::::_ NO M&C REQU I RED ' a \ .__ _______ ..J .... °o fORTWORTH ---....--- Project Name Harley Street Relocation City of Fort Worth Change Order Additions Client Project# 01468 (Water/Sewer) 00143 (T/PW) DOE# 5380 Project Description Paving, Drainage, Water , Sewer (University @ Harley) from Conservatory Dr. to Montgomery Street City Sec# Contractor S.J. Louis Construction Change Order# I 3 Date 2/24/2011 City Project Mgr . Leon Wilson '--------------------J City Inspector I Carlos Vasguez ADDITIONS IICM Ut:::il,;Klt-' I IUN Ut:t-' I I.HY Unit Unit l,;OSt (::;ect A) Pnce amerenuai tor n1gn eany yield concrete-s· Deptn vvater 1 , HSl.fl:l -> T ~t:i.J~ 66-New ( ::;ea A)Pnce amerential ror n1gn eany yield concrete-1 o· Deptn Wa1er lU4 .45 ::;y :>I .~~ 36-lnc . (::;ect A) Jt>" CaS1ng With 24" tsar wrappea 1.,;0ncrete Cylinder Pipe Water ( (.00 LF :>t:i::>l .Ul 45-New :::;ea EI Pnce amerenuai ror nign eany yield concrete-8" Deptn sewer 52.22 ::;y :>t:i.J~ 46-New :::;ea EI Pnce amerenuai for High early yield concrete-10· Deptn Sewer 103.33 ::;y :>t.~ 13-NeW (Unit II Pnce amerenuai ror high early yield concrete-a• Depth(Electricaij rTPW ::,u .56 ::;y ~t:i .J~ w (Unit II) Add1uonc11 Trame 1.,;0ntrol tor tne mgnt work on university rTPW 1.00 LS $3,945.o.: 11-mc (Umt IV} t:1811T1uda ::;ca (t:iecu ,_, 1.,;0ndu1t) 1/tJW 2,UH/.00 ::ii" $U.Jl no T/JW Water Sewer SUb I ota1 Additions Change Order Additions Page 1 of 1 40539 lotal :>t ,otS~.91 $1 ,t:iJJ .::>t:i :>::>U, l l/ .00 :>JJJ.6S :>tsl::>.61 ;)J"J.Ul:l $J ,~::>.oo ;)O"O . llJ $4 ,894.n $59,350 .47 $1,159.30 $0!>,404.:>(J Project Name Harley Street Relocation City of Fort Worth Change Order Deletions Client Project# 01468 (Water/Sewer) 00143 (T/PW) DOE# 5380 Project Description Paving, Drainage , Water, Sewer (University@ Harley) from Conservatory Dr. to Montgomery Street City Sec# Contractor S.J. Louis Construction Change Order # I 3 Date 2/24/2011 City Project Mgr . Leon Wilson .__ ______________ __, City Inspector I Carlos Vasquez DELETIONS IICM ----''"\Ir I IVN UCl""I Yty Unit Unit vOSt £•U8C (Unit 1v11-'avement Kepair v0ncrete wim i-1owao1e rm \!'(IP Jonnson) 1/l""VV , , l ,u .w .::,r ~12 .0l 3-Dec (Unit IV) Pavement-Permanent HMAC 1/1-'W 1,4U/.UU .::,r ~/.Ol 4-uec (Unit 1v14· U>ncrete ;:;ioewalK· install T/PW J, 100 . lt .:>r ~J .oU 7·U8C (Unit IV) nencn .:,arety system 5 toot Depm 1/l""VV l,o4B.uu Lf ~U.Ul 6-Dec (Unit 1v15· .:icrl . 40 PVC U>nau1t m group or 4 I/PW t:540 .UU LF ~L4.UU 9-Dec (Unit IV) 6" .:icrl . 4U PVC U>naUit In group OT 2 I/PW B.uu LF ~1/.UU 10-Dec (Unit IV) 4 XB'X4' V:"''""LJto( Approved Heavy Duty Pull ~xes IWVV 2.W EA ~t:i ,l:IUU .Ul. -I ... -.... '""'! '"ft :"'I -i. ~ ..ii' u, ;:: ; n r--~ := --='.I ~ '!111111 SQ ;; --... -T/ )W Water Sewer SUb Total Deletions Change Order Deletions Page 1 of 1 ~, 40539 10@1 ~lJ,010.UU ~lU,O::>L .::>U ~ll,141WJ ~lo.4tl ~15,JOU.UU ~l Jt:i .Ul. ~ l J,OUU .Ul. $64,888 .01 $0 .00 $0.00 ~t:>4,BBB.01 .. M/WBE Breakdown for this Change Order MWBE' Sub " ' . Total Previous Change Orders Amount for this CC) ' .: OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX PROJECT NAME: BuySpeed No (T/PW): BuySpeed No (Water): City Project No : Contract No : D.0 .E. No: Attachment to Change Order No: Today's Date : Original Contract Amount: Extras to Date: Credits to Date : o ntraat Amount to Date: PROJECT SUMMARY SHEET (Change Order Attachment) Harley Street Relocation Pending Pending 01468 (W&S) & 00143 (TPW) CS40539 5380 3 2/24/11 TOTAL IlI:i:i $ 4,696,805.66 $ 2,065,071.46 $ 4,887.60 $ $ $ Water Sewer $ 1,375,302.70 $1,255,431.50 $ 4,887.50 $ $ $ ~ , rnQ n of Proposed Change Order: :e eiie Contract Amount: o m J> $ 4,700,693.16 $ 2 ,065 ,071.46 $ 1,380,190.20 $1,255 ,431.50 $ 516.49 $ (59 ,993 .28) $ 59,350 .47 $ 1 ,159.30 $ 4,701,209.65 $ 2,005,078.18 $ 1,439,540 .67 $1,256,590.80 :::a n .- -t :::a :::a :c m m -.... , tl n ency Funds Avail. for Admin. Change Orders : >< e inmg Funds Available for Change Orders: A 1t1onal Funding (if necessary): $ $ $ 152,200.00 $ 147,312.50 $ 22,237.97 $ 72,200.00 $ 72,200.00 $ $ Prepared By : Christy Ezernack T/PW Construction Services 42 ,000 .00 $ 38 ,000 .00 37,112 .50 $ 38,000.00 22,237.97 $