HomeMy WebLinkAboutContract 40566-CO1City of Fort Worth Change Order Request CllY SECRETARY y (e CONTRACT NO. 0 S (e .. Project Name! Rolling HiBs WTP -Laboratory Building Dual Electric Power Feed City Sec# .__ ____ __, 40566 Client Project #(s ·::=======================::::::: ~~ ::::==========~------;::::=~----;:=== ConlradDrf TeXSlll Eledrical Contraclcrs, Inc. Chalge Ona# I 1 Dalla 3110'2011 City Project Mgr.I Farida s Goderya. PhD, PE City lnspecu :=I =M=ike=H=il~---=======:::: Original Connet Amount Exlras lo Dae Credils lo Date Dept. Pending Change Orders (n M&C Process) Conlract Cost t> Dale Origilal Funds Available for Change Orders Remaililg Funds Avalable br this CO Addiional Funding (If necessay) Water CHANGE ORDERS ID OATE (INCLUDING THIS ONE} AS" OF ORIGIHAL CONTRACT MAX ALLOWABLE COKTRACT AIIOONT (ORIGINAL CONTRACT COST+ 2ftl Totals ,725.00 4.ri I $172.500.00 ~:; . ' , : , ' . .. , , . . . .·: . . . ,. . . ' . . . . . ' ;. . ·,' Change Order No. 1 incbfes 1he folowing: PCM 001 -Medium Voltage Gable Routing; Additional Amount of $6725.00; No Contract Tme Chalge. The actual site condition is considerably <ifferent than what was desaibed in the site plat (Sheet E2). There is 111 addlllonal 320 LF of medium voltage cab6e requied m inst.al the new feeder ttm what is shown. It is understood aid ai,1l8d that the acceptaice of this Change Ona by the COllbacD conslbes Ill accord aid saisfdoll aid rapresl!llls payment i1 ful (both tine aid money) for al cos1s arising out of, or ilcidental to, the abo¥9 Cha,ge Order. co , I = .. Roling HIia Wais Treatment Plal( PROJECT: LabonllD!l Bulldl~ Dual Elactrlc POWIII' Faed PROJECT NUMBER: OWNER: C~olFortWortl'I 01454 CONTRACTOR: Texaun Electrical Contrac:tora Inc:. 10 SUB-CONTRACTOR ARCHITECT/ENGINEER: Muttalach Ena!!!.!!!!!JI Inc l.EW'09188 REFERENCE DATA: Contractor's Submittal No. PCll-001 Speclficallon Section:· Plan Sheet No.; Description: Medium Voltage Cable R0Uti!!9 CONTRACTOR'S CERTIFICATION: I hereby ce,tKy thal th/a &UbmJltlll has been rSYlewed by the COlllrBctor and i. alrlct r:ontonna111» with the Conlract Documents as modJtled by Al/denm, Change Orders and Reid O'dwa. CERTIFIED BY: Steve MIUer DATE: 1/6/2011 TYPE # DESCRIPTION #SENT #RErI) .. STATUS . CMR ConlraCIDr'I Modfflcallon Request D Approved CTR Car1llled Tat Report o ApplDVlld 11a No1ec1 EIR ll=nulnment lnatallaton Renntt D Not Approved O&M Operation & malntltnance Manual D Rev11e & Reeubm1t NBC Notllcallon Bv Contractor D Fllad Al Recelwd PCM 001 Pmnnsed Connel Modllcallon amal D Final D1llrlbut1on PR Pavment Reauest D Change Order Issued pp Pmlacl Pllomaraohs 0 Fleld Order Issued RD RtlCOIIS data D Recommended For Appn,yal RFI R""'-'IISt For Information D Ra1umed W/0 Review SAM Samolll D Aden Information Reqwed SCH Sc:hedule Of PrnmMII D canceled D See Reviewed Comments SD Shnn Drawlna D Pending Change Order .. FOR ARCHITECT.I ENGINEER USE .ONLY . · .. DATE RECEIVED I )., I \\ BY E~ L!.,. DATE RETURNED 2-htcl 11 BY ~ j '-c_ COMMENTS: Ann .} -~ ~~ \. ( __ ..Ji._ -- "~" 11~ 0 I . DISTRIBUTION REVIEW NO SENTTO. SENTTO. BY DATE SENT' DATERET'O. = ·- Submittal PCM-001 Additional Comments Rolling HNII Walllr Treatment Plant PROJECT: LabofalD!}'. Bulldl!!i Dual Elactrtc Pow. Feed PROJECT NUMBER: OWNER: Cl!}: of Foll Worth 014!54 CONTRACTOR: Taxsun Electrtcal Conlrac:lora Inc. 10.1009 SUB-CONTRACTOR 0 0.0000 ARCHITECT/ENGINEER: Mullalech EnginMrt!!II Inc LEW09183 Description: Medium Voltage Cable Routl!:!9 - NOTE: The site plan E2 shows the meduim voltage feeder running north from existing switchgear SGO to PMH-3. See Attachment #1 . .. The actual site condition is considerablely diferant than described. The actual routing is the feeder conduit from SGO runs south to the manhole located south of SGO. The raceway continues out the west side of this manhole and runs continuous to EMH-22. See Attachment #2 There is an additional 320' of cable required to install the new feeder than what Is shown. Attached Is the proposed additional cost associated with the addlUonal cable length. '• Thanks, Steve Miller I I 1' I ~· I I I ·I I ·-......................... _ ... ,, .. _ .. " ~ Jll'",.vr,¥A'A'WWl'I •WI.' ····--.................. . I I.. ....... ·----·- -.................... . ...,.,.. ----~-"' / .. 1 1 .-/ 1. I .... \ \ • l I j ·1 ) J Ii " . ···,. . .J'- • • J 1 1 '1 ; I '··" / ...... -.. ···-·-·······--······-······-................ ' ... ! .. -~g~ qQ~ (i} C) i ~~ Ctn ~ :f rnZ G) ~ '\ ... DNcripllon Tllholf Qly 1IOIO Electrical Material$ 11UI IOO Volt Blllldlng WIN • 1/C Cclppel' THHN .. 320.00 Int\ n PdyNlht111" 350.00 lnl IOI Volt Blllldlng WI,. , .. Laborhaurl 11121 IKY P-r C.ble 4II08 lkv 100% "'4 EPR IN-105 Tapa 980.00 lnft INd PYC JKT CU IKY "-Cable 57.IO Labor holn 111M Wn Pulllnt AooNaorm · 102 YlllkM 77 5 gallon 1.00 EACt- 10I OuctT8f19 1.00 E.:h -PVC Elal:trfcal Tape 1.IIO E:ac:tl Wife Pullq MONI~ 1.-40 Labar houri Semi~..,.,.,. 8',580 labor houri UttltColt Sianaani Estimate Report RoUing HIiis Lab CO Amount UnltCO.t 0.24 Anft n 0.90 Anll 0.80 Anft 210 0.05 Anft ZIT 1.80 llnfl 1.728 2.40 l1nft 1,728 30.00 /EACH 30 40.00 /EACH e.oo /Each 6 3.50 /Each 6.00 /Each 15 2.60 IEech 42 2,057 AlnOIMt 288 18 306 2.304 2,304 <10 .. 3 ... 2,656 Amount 365 2'l8 5112 4,032 4.032 70 10 e · .. 4,712 Pagez 114/2011 2:32 PM Standard Esiimate Report ROUing Hills Lab CO esumate Totals ''",:'~P.;ffe.r :· ::'1!~~,;l11!:iri,i:.::;m~s~~··:':fl~iif::~'~'··:•.:!.S~'!:!~5111!1!Eii"'~·"'!milt>1l:1:',t,l,l,,~~-'.!:~P .. ~ ....... llf' •• '-•• \" • ,l:i ..... ~ . .;..n .~;;w .. .s .~ ... .ri~INlilt .r . -Illa-JI~~ .. lAWI!~ ,•• I .. Llbor 2,067 88.680 In 30.98% ..... rial 2,11118 39.49'1(, Subc:mract ~ Olts I.A80R BURDEN 1•0VERHEAD JOB EXPENSE BOND TOlal 823 830 191 188 8,725 40.000 % 16.000 % 3.000 ~ C T T B 12.23% 12.35% 2.84% 2.50% Pag83 114/2011 2:32 PII