HomeMy WebLinkAboutContract 40610-CO1.. I FORT WORTH ' . ~ City of Fort Worth Change Order Request CITY SECRETARY CONTRACT NO. 4 o \:2 \ D -co\ Project Name! Water and Sewer Relocations for SH121T Crossing West of the Hulen Street Bridge City Sec No . 40610 ...._ ______ __. Project No.(s)jP265-603170133287and P275-703 170133287 DOE No .! .... _6_3_3_8 ___ __, City Pro . No . 01332 .__ ______ __, Project Description Water and Sanitary Sewer Relocations for SH 121 T Crossing West of the Hulen Street Bridge Within the Union Pacific Railroad Davidson Rail Yard , Part 2-Hulen Street Brid e and Water Main Extension from Hulen Street to Como Pum Station , Part 2 Contractor! S.J. Louis Construction ofTX, Ltd . Change Order# I Date : !1125/2011 City Project Mgr.! Phone Number.I Liam Conlon City Inspector I Raymond Brice :=::========::;------' Phone Number:! 817-392-8452 817-392-6824 I Dept. Water A-1 Water A-2 Sewer Totals Contract Time (Calendar davs) Original Contract Amount $1,958 ,606 .73 $2 ,352,962.50 $1 ,595 ,105.60 Extras to Date Cred its to Date Pending Change Orders (in M&C Process) Contract Cost to Date $1 ,958,606.73 $2,352,962.50 r• $1 ,595 ,105.60 IAmount of Proposed change Order 1·, ~15,767.91 ' $126,788.!>0 Revised Contract Amount $1,958,606.73 , ~2,869, 730.41 ·. $:t, 721,894.10 Original Funds Available for Change Orders $59 ,000 .00 $71,000 .00 $48,000.00 Remain ing Funds Ava ilable for this CO $59,000.00 $71 ,000 .00 $48 ,000.00 Additional Funding (if necessary) . $445,767 .91' ·--~-~~ $78,788.50 ~. CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS% OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) JUSTIFICATION (R SONS) FOltC . ~0.006,014.83 ,·,,,. $5 ,906,674.83 ~643 ,556.41 .. $6,550 ,231.24 I"-::~..'';_'. • $178,000.00 $178 ,000.00 I<;! $524 ,556 .41 10.90% $7 ,383 ;343.54 The project includes the installation of a 36/48 inch water main to accommodate the construction of the new Hulen Street Bridge at the SH121 T crossing. The construction of the ident ified water main will requ ire shu tt ing down the existing water main in order to connect the new water main . In order to maintain uninterrupted water service to res idents and businesses in the vicin ity that will be affected by the sh ut down , it is necessary to conduct the following : • The installat ion of an 8-inch water main north of the Oak Park Lane/Overton Park west intersection . • The installati on of a 10-l nch water ma in and pressure plane valve to transfer water from the Souths ide 11 pressure plane boundary to the Ho ll y pressure plane boundary . • The installation of 8 and 16-inch water mains on Stonegate Bou levard . • The installation of an 8-inch water main on Riverglen Drive. It is understood and agreed that the acceptance of this Change Order by the con (both time and money) for all costs arising out of, or incidental to , the above Change Order. Contractots Com an Name " Contractor Name- Pete Stahl () I '2 M&C Number 24699 410 410 41(} V FORT WORTH . City of Fort Worth Change Order Additions Project Name Project No .(s) • I I Water and Sewer Relocations for SH121T Crossing West of the Hulen Street Bridge City Sec No . P265-603170133287and P275-703170133287 DOE No .j 6338 I City Pro. No . 40610 01332 Project Water and Sanitary Sewer Relocations for SH121T Crossing West of the Hulen Street Bridge Within the Union Pacific Railroad escnp on Contractor S.J. Louis Construction of TX, Ltd . Change Order# c::I:J Date : I 1/25/2011 City Project Mgr. Liam Conlon ._ _______________ _. City Inspector Raymond Brice ADDITIONS II t:M· ':.:a,. -·'-·--.--· .. -. .,,;.:,,•,£ ,-·~ -···11un _ ;.::c.~.:..r-,;l--~ ...... Ut:t'J -t:'':;t~ ,.Qty Unit. Unit cost, 17 SWPPP Water A-2 5.00 EA $1 ,000 .00 18 Trench Safety Water A-2 1681,00 LF $0 .01 19 Traffic Control Water A-2 4.00 EA $2 ,000.00 24 16-inch DI by open cut Water A-2 35 .00 LF $150.00 25 12-inch DI by open cut Water A-2 15.00 LF $120 .00 26 10-inch PVC by open cut Water A-2 86.00 LF $100.00 27 8-inch DI pressure pipe by open cut Water A-2 336.00 LF $95.00 28 8-inch PVC pressure pipe Water A-2 1224.00 LF $100.00 29 6-inch water by open cut Water A-2 10.00 LF $30.00 30 3-inch water by open cut Water A-2 10.00 LF $25.00 31 16-inch connection-install Water A-2 2.00 EA $2,000.00 32 12-inch connection -install Water A-2 2.00 EA $3,000.00 33 10-inch connection-install Water A-2 2.00 EA $3,000.00 34 8-inch connection-install Water A-2 5.00 EA $2 ,500.00 35 6-inch connection-install Water A-2 1.00 EA $3 ,000 .00 36 3-inch water by open cut Water A-2 1.00 EA $1 ,500 .00 37 15-inch gate valve with vault Water A-2 3.00 EA $7,000.00 38 12-inch gate valve wth box Water A-2 2.00 EA $2,000 .00 39 10-inch gate valve with valve box Water A-2 2.00 EA $2 ,000 .00 40 10-inch pressure plane valve with box Water A-2 1.00 EA $18,750 .00 41 8-inch gate valve with valve box Water A-2 8.00 EA $1 ,500 .00 42 6-inch gate valve box with box Water A-2 1.00 EA $1,400 .00 43 Pipe fittings Water A-2 3.10 TN $1 .00 44 Abandon 8-inch water line with flowable fill Water A-2 300 .00 LF $3 .00 45 8-inch tapping sleeve and valve Water A-2 2.00 EA $3 ,500.00 46 Concrete pavement-5-inch min Water A-2 1800.00 LF $85 .00 47 Concrete sidewalk-install Water A-2 288 .00 SF $6.00 48 D-Hole Water A-2 1.00 EA $2 ,000 .00 49 Remove and replace concrete curb and gutter Water A-2 50 .00 LF $25 .00 50 Concrete Encasement Water A-2 10.00 LF $100 .00 51 Casing pipe annular space grouting Water A-2 1444.00 LF $50.00 14 Manhole Standard 4 ft diameter 0-6" Sewer 6.00 EA $3,400 .00 15 Manhole Standard 4 ft dia additional depth Sewer 25 .00 VF $85 .00 17 Concrete collar-manhole Sewer 6.00 EA $350 .00 18 Manhole-vacuum test Sewer 6.00 EA $200 .00 22 Cut and plug existing sanitary sewer Sewer 4.00 EA $3 ,000 .00 23 lnspection-preconstruction cleaning and TV Sewer 390 .00 LF $1.75 24 Inspection-post construction cleaning Sewer 600 .00 LF $1 .50 30 Traffic control Sewer 1.00 LS $2 ,000 .00 35 Trench safety Sewer 600.00 LF $0.01 36 Pavement-5 inch min. concrete Sewer 600 .00 SY $50.00 37 10-inch SS by open cut Sewer 415 .00 LF $100 .00 38 8-inch SS by open cut Sewer 185.00 LF $75 .00 Water A-2 Sewer Page 2 of 4 Additions Sub Total Total $5 ,000.00 $16.81 $8 ,000.00 $5,250 .00 $1,800 .00 $8 ,600 .00 $31 ,920 .00 $122,400.00 $300.00 $250 .00 $4 ,000 .00 $6,000 .00 $6,000.00 $12,500 .00 ' $3,000.00 $1 ,500.00 $21 ,000.00 $4,000.00 $4 ,000.00 $18 ,750 .00 $12,000 .00 $1,400 .00 $3 .10 $900.00 $7 ,000 .00 $153,000 .00 $1,728 .00 $2 ,000 .00 $1 ,250 .00 $1,000.00 $72 ,200 .00 $20,400 .00 $2,125 .00 $2 ,100.00 $1 ,200 .00 $12,000 .00 $682.50 $900 .00 $2,000 .00 $6 .00 $30 ,000 .00 $41,500.00 . $13 ,875 .00 $516,767 .91 $126 ,788 .50 $657 ,431.41 .. F O R T WORT H • City of Fort Worth Change Order Deletions Project Name j Water and Sewer Relocations for SH121 T Cross ing West of the Hulen Street Bridge City Sec No . Project No .(s} jP265-603170133287and P275-703170133287 DOE No . I 6338 I City Pro . No . 40610 01332 Contractor S.J. Louis Construction of TX, Ltd. 1/25/2011 City Project Mgr. Liam Conlon .__ ____________ _, City Inspector Raymond Brice DELETIONS ITEM DESCRIPTION ... ~'Jc;: '.: ... ..:. ..... ,;::,,.;':;~'~--:,..;""'~ :'1·;."t't.:i.~~ -DEPT _ -~j£ ,,,..Qty; .. Un i.L Unit Cost f Total Water A-1 Water A-2 Sewer Page 3 of 4 Deletions Sub Total A•>• ~ ·rt,_,,..,,,, "'"" ,, ·. M/WBE Breakdown for this Change Order l.i:,,_.;; MWBESub Type of Service ·· · Amount for this CO · " .·· -. Total $0.00 "· .. Previous Change Orders If; .. CO# DATE I, AMOUNT _,. ~ ' C ·-·-C• -:·· ·:,-·~ ·-, ~---· $0.00 Total -~ ~ ~-~ -.. Off1c1al site of the Ci ty of Fort 'North , Texas ITY COUNCIL:; AGENDA DATE: CODE: 1/25/2011 C COUNCIL ACTION: Approved on 1/25/2011 REFERENCE NO.: **C-24699 TYPE: CONSENT LOG NAME: PUBLIC HEARING: 6040610C01- SJLOUIS NO SUBJECT: Authorize Change Order No. 1 in the Amount of $643,556.41 to City Secretary Contract No. 40610 with S.J . Louis Construction of TX, Ltd ., for Water and Sanitary Sewer Relocations for SH 121 T Crossing West of the Hulen Street Bridge within the Union Pacific Railroad Davidson Rail Yard, Part 2-Hulen Street Bridge and Water Main Extension from Hulen Street to Como Pump Station , Part 2 (COUNCIL DISTRICT 3) RECOMMENDATION: It is recommended that the City Council authorize the City Manager to execute Change Order No. 1 in the amount of $643 ,556.41 to City Secretary Contract No. 40610 with S.J. Louis Construction of TX , Ltd ., for Water and Sanitary Sewer Relocations for SH121T Crossing West of the Hulen Street Bridge within the Union Pacific Railroad Davidson Rail Yard, Part 2-Hulen Street Bridge and Water Main Extension from Hulen Street to Como Pump Station , Part 2 , thereby increasing the contract amount to $6,550,231 .24 . DISCUSSION: On July 20 , 2010, (M&C C-24358) the City Council authorized the City Manager to execute a contract in the amount of $5,906,674.83 with S.J. Louis Construction of TX , Ltd., for Water and Sanitary Sewer Relocations for SH121T Crossing West of the Hulen Street Bridge within the Union Pacific Railroad Davidson Rail Yard, Part 2-Hulen Street Bridge and Water Main Extension from Hulen Street to Como Pump Station , Part 2. The project includes the installation of a 36/48 inch water main to accommodate the construction of the new Hulen Street Bridge at the SH 121 T crossing. The construction of the identified water main will require shutting down the existing water main in order to connect the new water main . In order to maintain uninterrupted water service to residents and businesses in the vicinity that will be affected by the shut down , it is necessary to conduct the following via Change Order No . 1: The installation of an eight-inch water main north of the Oak Park Lane/Overton Park west intersection. The installation of a 10-inch water main and pressure plane valve to transfer water from the Southside II pressure plane boundary to the Holly pressure plane boundary . The installation of eight and 16-inch water mains on Stonegate Boulevard. The installation of an eight-inch water main on Riverglen Drive. In addition, the change order will also allow for the relocations of the water and sanitary sewer mains that are in direct conflict with the proposed bridge at the Clear Fork Main Street/South Hulen Street intersection and grouting the casing pipe annular space at all tunnel locations. Staff considers the change order amount to be fair and recommends approval. M/WBE -S.J. Louis Construction of TX , Ltd ., is in compliance with the City's M/WBE Ordinance by committing to an additional 66 percent M/WBE participation on this Change Order No. 1. The C ity's goal on this change order is 1 O percent. Logname: 6040610C01-SJLOUIS Page 1 of2 • ··- This project is located in COUNCIL DISTRICT 3. FISCAL INFORMATION/CERTIFICATION: The Financial Management Services Director certifies that funds are available in the current capital ----t::J 1t1d§ets, as 0Pf3F8J:1Fiatea, of tke-Water Capital Projeets Fund and the-Sewer Capital--Projeets Futid. TO Fund/Account/Centers Submitted for City Manager's Office by: Originating Department Head: Additional Information Contact: ATTACHMENTS 6Q4QG 10CQ 1:SJLOU_1 S MAP .Qdf Logname: 604061 OCO 1-SJLOUIS FROM Fund/Account/Centers P275 541200 703170133287 $126 .788.50 P265 541200 603170133287 516 767.91 Fernando Costa (6122) S . Frank Crumb (8246) Liam Conlon (6824) Page ~:Q.f 2 ,