HomeMy WebLinkAboutContract 40920-CO7Lor~ l, FORT WORTH . City of Fort Worth Change Order Request cm SECRETARY 4ffl1/J-t01 COll'f RACT NO.~~-------- ~ Project Name! 2007 Capital Improvements Project-District 7 Part 1 City Sec# 40920 ~-------' Client Project #(s)! #00930-DOE #5855 Mattison Paving , #009380-DOE #5880 Clarke Paving , #00933-DOE #5858 Atenia Paving Project Description Water/ Sewer/ Paving Reconsruction of Athenia , Mattison , Haskell , Clarke and Washington Terrace Contractor! Stabile & Winn Change Order # 7 Date City Project Mgr.~! _G_o_pa_l_S_ah_u ___________ ~ City Inspector Mike Huddleston Dept. TPW Water Sewer Orig inal Contract Amount $1,479 ,197.01 $356,590 .00 $230 ,043.50 Extras to Date $45 ,519 .06 $79 ,667.50 $74 ,844.50 Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date $1 ,524 ,716 .07 $436 ,257.50 $304 ,888 .00 IAmount of Proposed Change Order $9,630.00 $0.00 $0.00 Revised Contract Amount $1 ,534 ,346 .07 $436 ,257 .50 $304 ,888 .00 Original Funds Available for Change Orders $71 ,044 .00 $17 ,830 .00 $15 ,311 .00 Remaining Funds Available for this CO $25 ,524 .94 $0 .00 $0.00 Additional Funding (if necessary) CHANGE ORDERS to DA TE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) Totals $2 ,065 ,830 .51 $200 ,031 .06 $2 ,265 ,861 .57 $9,63Q.OO $2 ,275,491.57 $104 ,185.00 $25 ,524 .94 10.15% $2 ,582,288 .14 JUSTIFICATION (REASONS) FOR CHANGE ORDER OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX 3/20/2012 Contract Time (CD) 365 58 423 158 581 It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfact ion and represents payme nt in full (both ti me and money) for all costs ari sing out of, or incidental to , the above Change Order. uired M&C Number I AJ/ /Jr M&C Date Approved ( . ! fO li,T ;OJTH. I ~ City of Fort Worth Change Order Request -Project Name! 2007 Capital Improvements Project-District 7 Part 1 City Sec # 40920 .__ _____ ___, Client Project #(s)j #00930-DOE #5855 Mattison Paving , #009380-DOE #5880 Clarke Pav ing , #00933-DOE #5858 Atenia Paving Project Descript ion Water/ Sewer/ Paving Reconsruction of Athenia , Mattison , Haskell , Clarke and Washington Terrace Contractor! Stabile & Winn City Project Mgr.! Gopal Sahu Change Order# 7 Date ~~--------------' City Inspector Mike Huddlesto n Dept. TPW Water Sewer ,r Original Contract Amount $1 ,479 ,197 .01 $356 ,59 [00 $230 ,043 :50 I Extras to Date $45 ,519 .06 $79 ,667 .50 $74 ,844.50 Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date $1 ,524,716.07 $436 ,257.50 $304 ,888.00 !Amount of Proposed Change Order $9,630 .00 $0.00 $0.00 Rev ised Contract Amount $1 ,534 ,346 .07 $436 ,257.50 $304 ,888.00 Original Funds Available for Change Orders $71 ,044 .00 $17 ,830 .00 $15 ,311 .00 Remaining Funds Available for this CO $25 ,524 .94 $0 .00 $0 .00 Additional Funding (if necessary) CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS% OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) JUSTIFICATION (REASONS) FOR CHANGE ORDER Totals ... $2 ,'065 ,830 .51 $200 ,031 .06 $2 ,265 ,861 .57 $9,630.00 $2 ,275 ,491 .57 $104 ,185 .00 $25 ,524.94 10.15% $2 ,582 ,288 .14 3/20/2012 Contract Time (CD) 365 58 423 158 581 The contractor discovered an existing gas main on Haskell that was in conflict with the proposed construction. It was determined that the gas ma in would have to be relocated before the excavation of Haskell could begin. Additional days requested are for 128 days of down time waiting for the gas company to complete their work . Addit ional 30 days for moving off of job site , remobilizing and reconstructing an additiona l 93 ' section of Modlin Avenue not originally on the plans . !)tw L-I / y ' A# It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or inc idental to , the above Change Order. Contracto~s Com an Name Contractor Name /~ I~ ~~~~~~~~~---+-=---r--~~,--~--+-~-------l ~~ \, M&C Number I FORT WORTH . ~ City of Fort Worth Change Order Request Project Name! 2007 Capital Improvements Project-District 7 Part 1 City Sec # 40920 ______ ___, Client Project #(s)! #00930-DOE #5855 Mattison Paving , #009380-DOE #5880 Clarke Paving , #00933-DOE #5858 Atenia Paving Project Description Water/ Sewer/ Paving Reconsruction of Athenia , Mattison , Haskell , Clarke and Washington Terrace Contractor! Stabile & Winn Change Order# 7 Date City Project Mgr ..... ! _G_o""""pa_l_S_ah_u ___________ _, City Inspector Mike Huddleston Dept. TPW Water Sewer Original Contract Amount $1,479 ,197 .01 $356 ,590 .00 $230 ,043 .50 Extras to Date $45 ,519 .06 $79 ,667 .50 $74 ,844 .50 Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date $1 ,524 ,716 .07 $436 ,257 .50 $304 ,888 .00 IAmount of Proposed Change Order $9,630.00 $0.00 $0.00 Revised Contract Amount $1 ,534 ,346 .07 $436 ,257.50 $304 ,888 .00 Original Funds Available for Change Orders $71 ,044 .00 $17 ,830.00 $15 ,311 .00 Remaining Funds Available for this CO $25 ,524 .94 $0 .00 $0 .00 Additional Funding (if necessary) CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS% OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) JUSTIFICATION (REASONS) FOR CHANGE ORDER Totals $2 ,065 ,830.51 $200 ,031 .06 $2 ,265,861 .57 $9,630.00 $2 ,275,491 .57 $104 ,185 .00 $25 ,524 .94 10 .15% $2 ,582 ,288 .14 3/20/2012 Contract Time (CD) 365 58 423 158 581 The contractor discovered an existing gas main on Haskell that was in conflict with the proposed construction . It was determined that the gas main would have to be relocated before the excavation of Haskell could begin . Add itional days requested are fo r 128 days of down time wait ing for the gas company to complete thei r work . Additional 30 days for moving off of job site , remobilizing and reconstructing an additional 93 ' section of Modlin Avenue not originally on the plans . I I It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to , the above Change Order. M&C Number FORT WORTH ., ---...,...--- , . I City of Fort Worth Change Order Request ( ( Project Name! 2007 Capital Improvements Project-District 7 Part 1 City Sec# 40920 .__ ______ __, Client Project #(s)! #00930-DOE #5855 Mattison Paving , #009380-DOE #5880 Clarke Paving , #00933-DOE #5858 Atenia Paving Project Description Water/ Sewer/ Paving Reconsruction of Athenia , Mattison , Haskell , Clarke and Washington Ter race Contractor! Stabile & Winn 7 Date City Project Mgr.~! _G_o~p_al_S_a_hu ___________ ___, Change Order# City Inspector Mike Huddleston Dept. TPW Water Sewer Original Contract Amount $1 ,479 ,197.01 $356 ,590 .00 $230 ,043 .50 Extras to Date $45 ,519 .06 $79 ,667 .50 $74 ,844 .50 Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date $1 ,524 ,716 .07 $436,257.50 $304 ,888.00 IAmount of Proposed Change Order $9,630.00 $0.00 $0.00 Revised Contract Amount $1 ,534 ,346 .07 $436 ,257 .50 $304 ,888 .00 Original Funds Ava ilable for Change Orders $71 ,044 .00 $17 ,830 .00 $15 ,311 .00 Remaining Funds Available for this CO $25 ,524 .94 $0 .00 $0 .00 Additiona l Funding (if necessary) CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS% OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) JUSTIFICATION (REASONS) FOR CHANGE ORDER Totals $2 ,065 ,830 .51 $200 ,031.06 $2 ,265 ,861.57 $9,630.00 $2 ,275,491 .57 $104 ,185.00 $25 ,524 .94 10 .15% $2 ,582 ,288.14 3/20/2012 Contract Time (CD) 365 58 423 158 581 The contractor discovered an existing g'as main on Haskell that was in conflict with the proposed construction. It was determined that the gas main would have to be relocated before the excavation of Haskell could begin . Additional days requested are for 128 days of down time waiting for the gas company to complete their work. Additional 30 days for moving off of job site , remobilizing and reconstructing an additional 93 ' section of Modlin Avenue not originally on the plans . It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to , the above Change Order. Contractor's Compan Name Contractor Name Stabile & Winn Inspector/Inspection Supervisor . Date Project ManaQer/Pr~ram ManaQer Date , ,, / ·' .. J ,.,. ' --I , t' .. ...,_.i,,,.. .... . Assistant Director (Dept) Date Director, Contracting Department (Dept} Date Assistant City Attorney Date Assistant City Manager Date / l J!._ ...... -' I 1;,_ ,,. ... .... -·/' Council Action if required) M&C Number I I -I M&C Date Approved I I ( FORT WORT H ----.---City of Fort Worth Change Order Additions Project Name 2007 Capital Improvements Project-District 7 Part 1 City Sec# Client Project# #00930 -DOE #5855 Mattison Paving , #009380-DOE #5880 Clarke Paving , #00933-DOE #5858 Atenia Paving Project Description Water/ Sewer/ Paving Reconsruction of Athen ia, Mattison , Haskell , Clarke and Wash ington Terrace Contractor Stab ile & Winn Change Order# I 7 Date 3/20/2012 City Project Mgr. Gopal Sahu .__ ________________ __. City Inspector I Mike Huddleston ADDITIONS IIEM Ut~~RII.., I ION Utt'I Uty Unit Unit {.;OSt 42 NEW-Remobilization Excavation/ Stabi li zation (00930) TPW 1.00 LS $1 ,500.00 43 NEW-Remobilization Cone . Crews (00930) TPW 1.00 LS $4 ,500 .00 44 NEW-Additional Barri cades (00930) TPW 1.00 LS $3 ,630 .00 TPW Water Sewer Sub Total Additions Change Order Additions Page 1 of 1 ., 40920 1 otal $1 ,500 .00 $4 ,500 .00 $3 ,630 .00 $9 ,630 .00 $0 .00 $0 .00 $9 ,oJU .UU FORT WORTH ---.......- Project Name Client Project# City of Fort Worth Change Order Deletions 2007 Capital Improvements Project-District 7 Part 1 City Sec # #00930 -DOE #5855 Mattison Paving , #009380-DOE #5880 Clarke Paving , #00933-DOE #5858 Aten ia Pav ing Project Description Water/ Sewer/ Paving Reconsruction of Athenia , Mattison , Haskell , Clarke and Wash ington Terrace Contractor Stabile & Winn Change Order# I 7 Date 3/20/2012 City Project Mgr . Gopal Sahu L..---=------------------' City Inspector Mike Huddleston DELETIONS 11 t:M Ut::;CK II-' I IUN Ut:I"" I Uty unit unit cost TPW Water Sewer Sub Total Deletions Change Orde r Deletions Page 1 of 1 .. 40920 IOtal $0 .00 $0 .00 $0 .00 , . .' .. M/WBE Breakdown for this Change Order MWBE Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders CO# DATE AMOUNT Total $0.00 ,, .. . ~ ., PROJECT NAME: BuySpeed No (T/PW): BuySpeed No (Water): City Project No : Contract No : D.O.E. No : Atta chment to Change Order No : To day's Date : Contract 2007 CO's CD 7 A, 7C & 7G CSC0-11-00063808 CSC0-11-00063863 00930 / 00933 / 00938 CS40920 5855 I 5858 I 5880 7 3/30/12 TOTAL Original Contract Amount: Extras to Date: $ 2,065,830 .51 $ $ 200,031.06 $ Credits to Date : $ $ Con t ract Amount to Date : $ 2,265,861.57 $ Amount of Proposed Change Order: (Additions) $ 9,630 .00 $ Rev ise d Contract Amount: $ 2 ,275,491 .57 $ Con t ingency Funds Avail. for Admin . Change Orders : $ 104,185.00 $ Remaining Funds Available for Change Orders : $ 25,524 .94 $ Additional Fundin if necessa $ $ Allocated for Inspection Charges $ 119 ,344 .00 $ Allocated for Material Testing Charges $ 15 ,812 .00 $ PROJECT SUMMARY S (Change Order Attachme Haskell Street & Mattison Avenue (7C DOE 5865 I CPN 00930 ~ ~ater 558 ,336 .04 $125 ,536 .50 22 ,973 .51 $ 25 ,810 .00 $ 581 ,3 09 .55 $151 ,346 .50 9 ,630 .00 $ 590,939.55 $151,346.50 30 ,313 .96 $ 6 ,276 .50 7 ,340 .45 $ $ 33 ,330.00 $ 7 ,532 .00 2 ,778.00 $ 1 ,255 .00 Sewe $ 45 ,453 $ 19 ,987 $ $ 65 ,440 $ $ 65,44 $ 4 ,54 $ $ $ 2 ,227 $ 45 5 $ 2 ,065 ,830 .51 $ 1,479 ,197 .01 $356,590.00 $230 ,043 Prepared By: Christy Ezernack T/PW Cons1