HomeMy WebLinkAboutContract 41005-CO1FoRTrRTI(.
CITY SECRETARY, r \ " _
CONTRACT NO. I' C)(.)5" -'-'-> l
,,
City of Fort Worth
Change Order Request
Project Name! Ruidosa Bandera Drainage, Improvements
Client Project #(s~ P227-541200-203280111983
City Sec # 41005
Construction of storm drain system for Plantation Creek @ the end of Geronimo Tr.ii along Bandera Rd. to Ruidosa Trt.
Contractor! Jackson Construction
City Projed Mgr.! Michael Owen
Original Contract Amount
Extras: to DatB
Credits to DatB
Dept.
Pending Cha,ge Orders (in M&C Process)
Contract Cost to Dale
T/PW
Change Order# 1 Dale
City Inspector Ph~ Teague
$0.00 $0.00
12/3/2010
Contract Time
CD
130
130
5
135
Existing material was too rocky and unsuitable for use.~-~ asphalt to miU, therefore it was decided to pulverize the
pavement instead . ~, f.O!J' ~"(l {~~~ n,., ~I ;-i ozr4 ~o,.\ / ... ~by:
----"II\ 00o00oo /Kr"\,"-I. _a,_~,O ,~ A /)
NO M&C REQUIRED ~~t-<>,(), J Y \ ~ ~
Marty Hendrix. ity Secretary
It is understood and agreed that the acceptance of this Cha,ge Order by the contractor con ·
in fuH (both time and money) for all costs arising out of, or incidental to, the above Cha,ge
1/10/11
. '
City of Fort Worth
Change Order Deletions
Project Name Ruidosa Bandera Drainage Improvements
Client Project# P227-541200-203280111983
City Sec#
Project Description Construction of storm drain system for Plantation Creek @the end of Geronimo Trail along Bandera Rd. to Ruidosa Tri.
Contractor Jackson Construction Change Order # I 1 I Date 12/3/2010
41005
City Project Mgr . Michael Owen ---------------City Inspector .... I _P_hi_l T_e_.ag.._u_e _______ ____.
DELETIONS
IICM ----,ll"'IIVN UCl"'I ~ty Unit unit c.;ost IOtal
12 Pavement -2 Inch -Surface Milling -r/PW 2,680 .00 SY $3 .50 $9,380 .UlJ
14 Pavement 'l' Min . HMAC on 2:27 Base T/PW 4,300.00 SY $8.00 $34,400.00
II W $43,/1:SU.UlJ
suo 1 otal ue1etions ~.,,fOU.UlJ
Change Order Deletions Page 1 of 1
_,
City of Fort Worth
Change Order Additions
Project Name Ruidosa Bandera Drainage Improvements
Client Project# P227 -541200-203280111983
City Sec#
Project Description Construction of storm drain system for Plantation Creek @ the end of Geronimo Trail along Bandera Rd . to Ruidosa Tri .
Contractor Jackson Construction Change Order # l 1 I Date 12/3/2010
41005
City Project Mgr. Michael Owen ~----------------' City Inspector !....._P_hi_l T_e...,ag._u_e _______ ___.
ADDITIONS
IIC.M .J~~'..~lt' I IUN UC.l"'I Yty Unit Unlt~l IOtal
20 Haul-in of Backfill Material 1/t'W 1,280.00 liY $15.Ul $19,lUU.00
21 Pavement with 6"Base for Trench Repair T/PW 4,300.00 SF $4.65 $19,995 .00
22 6"Cement Stabilized Subgrade @30# S.Y . T/PW 2,680.00 SY $8.30 $22,244.00
T/ >W io1,439 .UU
::,uo Total Aaa1tions ~01,439.UU
Change Order Additions Page 1 of 1
' .
M/WBE Breakdown for this Change Order
Total
Previous Change Orders .
'' .,,,-. '
PROJECT SUMMARY SHEET
(Change Order Attachment)
PROJECT NAME: Ruidosa-Bandera Drainage Improvements
BuySpeed No [r/PW):
City Project No:
Contract No:
D.O.E. No:
Attachment to Change Order No:
Today's Date:
Original Contract Amount:
Extras to Date:
Credits to Date:
Contract Amount to Date:
CSC0-11-00063529
01119
CS41005
6198
1
1/4111
Amount of Proposed Change Order:
Revised Contract Amount:
Contingency Funds Avail. for Admin . Change Orders:
Remaining Funds Available for Change Orders:
Additional Funding (if necessary):
TOTAL
$ 296,715.00
$
$
$ 296, 715.00
$ 17,659.00
$ 314,374.00
$ 15,000.00
$ 15,000.00
$ (2,659.00)
Prepared By : Christy Ezernack T/PW Construction Services