City of Fort Worth
Change Order Request
Project Name! 2010 Signal Grant Task Order Construction Services at Various Locations to be! City Sec# 41210
Client Project #(s~ 01021 , TPW-TS-2010-00030
Project Descriptio Signal Contruction Contract used to expedite contruction as plans become available.
Date 4/22/2011 Contractor! Durable Specialties , Inc .
City Project Mgr.! Marisa Conlin
Change Order# 1 :=====-----=======! City Inspector Ken Brock ____________ __,
Orig inal Contract Amount
Extras to Date
Credits to Date
Dept.
Pending Change Orders (in M&C Process)
Contract Cost to Date
Revised ontract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
TPW Water Sewer
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
$600,000.00
,000 .00
$0 .00
t' . -~ . ~ ~ ' ! ' -; ' ! -
0 2 -1 7 -1 2 P 1 2 : 3 9 I N
Contract Time
WO
180
180
180
FORT WORTH
. " .
City of Fort Worth
Change Order Additions
Project Name 2010 Signal Grant Task Order Construction Services at Various Locations to be Determined
Cl ient Project# 01021 , TPW-TS-2010-00030
Project Description Signal Contruction Contract used to expedite contruction as plans become available .
Contractor Durable Spec ialties , Inc . Change Order# [TI
City Sec# 41210
Date 4/22/2011
City Project Mgr. Marisa Conlin ----------------City Inspector Ken Brock ____________ _,
ADDITIONS
I IC:M ----· ,,. I ION Ut:~I Qty Unit Unit l,;OSt IOtal
1u:, ~1gna1-1nternauona1 ~eaestnan ~1gna1 1 ype 1,,;oumaown-install WW :,u.u1.1 l:A :>O"L .U\. J31 ,ow.w
lUo 1~1gnal-Peaestrian Pushbutton & Sign Assembly Type Countdown-Install fPW 50 .UlJ EA :>LOL .UU ~14,lW.UU
TPW $45,700.00
Water $0 .00
Sewer $0 .00
Sub Total Add1t10ns ~:,.ruu .oo
Change Order Addit ions Page 1 of 1
J
/
FORT WORTH . w-City of Fort Worth
Change Order Deletions
Project Name 2010 Signal Grant Task Order Construction Services at Various Locations to be Determined
Client Project# 01021, TPW-TS-2010-00030
Project Description Signal Contruction Contract used to expedite contruction as plans become available .
Contractor Durable Specialties, Inc . Change Order# CD
City Sec# 41210
Date 4/22/2011
City Project Mgr. Marisa Conlin ..__ ______________ _.. City Inspector Ken Brock ~-------------'
DELETIONS
111:M DESCRlt' 1 IUN Ut.t' I UtY Urnl Um( L;OSl 1ora1
35 S1gna1-1nterna11ona1 Pe<lestnan Signal lype P-Install 11-'W OV .Ul l:A ~:>UU .Ul ~L:>,UUU .Ul
40 ::i1gnal-Pedestr1an Pushbutton & Sign Assembly-Install TPW 50 .UU EA $240.UL ~lL,UUU.Ul
36 Signal-Loop Detector Saw Cut -Install lPW 7.UU EA $1,.WU.00 ~l!,4UU .Ul
'L'L i;,11 Matenal-Flowable Fill -Install TPW 2.0C t;Y ~150.uu $300 .Ul
TPW $45,700.00
Water $0 .00
Sewer $0.00
sub I otal Ueletions ~45 ,700 .Ul
Change Order Deletions Page 1 of 1
)
/
,. ' .-.
PROJECT SUMMARY SHEET
(Change Order Attachment)
PROJECT NAME: 2010 Signal Grant Task Order Const. Serv. @Various Loe.
BuySpeed No:
Contract No: CS41210
D.O .E. No:
Attachment to Change Order No: 1 ------Today's Date: 5/9/11 ------
TOTAL
Original Contract Amount: $ 600,000.00
Extras to Date : $
Credits to Date: $
Contract Amount to Date: $ 600,000.00
Amount of Proposed Change Order: Time Only
Revised Contract Amount: $ 600,000.00
Contingency Funds Avail. for Admin. Change Orders: $
Remaining Funds Available for Change Orders: $
Additional Funding (if necessary): $
Prepared By : Karen Striker T/PW -Business Support