City of Fort Worth
Change Order Request
Project Name! 2007 CIP DISTRICT 7 PART 2 --DOE#5856,#5857,#5860
Client Project #(s)! #00931 ,00935 ,00932 .
CITY SECRET~\<'} b4'-CO 1-coNTRACT NO . t--
City Sec # 41264 .__ _____ ___,
Project Description Pavement, Water & Sanitary Sewer Replacement (Fletcher, Goodman , Lake Como , Hervie, Curzon & Penticost)
Contractor! Stabile & Winn Change Order# 2 Date ~ 911'~
City Project Mgr.~j _Go_p_al_Sa_h_u ___________ _. City Inspector Kim Brenz ..._ ___________ __,
Dept. TPW WATER SEWER
Original Contract Amount $1,780 ,557 .20 $472 ,867 .50 $174 ,127 .50
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process) $113 ,231 .00 $18 ,373 .00
Contract Cost to Date $1,780 ,557 .20 $586,098.50 $192,500 .50
IAmount of Proposed Change Order $0.00 $0.00 $73,236.70
Revised Contract Amount $1 ,780,557 .20 $586 ,098 .50 $265 ,737 .20
Original Funds Available for Change Orders $69 ,386 .00 $26 ,324.00 $9 ,622 .00 ·
Remaining Funds Available for this CO $69,386.00 $0.00 $0 .00
Additional Funding (if necessary) $73 ,236 .70
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
JUSTIFICATION· (REASONS) FOR CHANGE ORDER
(
Contract Time
Totals (CD)
$2,427,552 .20 300
$131 ,604 .00 25
$2 ,559 ,156 .20 325
$73,236.70 60
$2,632 ,392.90 385
$105,332 .00
$69 ,386 .00
$73 ,236 .70
8.44%
$3,034,440.25
" .
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of, or incidental to , the above Change Order.
M&C Number IC-2. S'Z 8 o j
(_
fo tff Wo 1n H -----.---
Project Name
City of Fort Worth
Change Order Additions
2007 CIP DISTRICT 7 PART 2 --DOE#5856 ,#5857 ,#5860
Cli ent Project# #00931 ,00935 ,00932 .
City Sec#
ProJ ect Description Pavement , Water & Sanitary Sewer Replacement (Fletcher, Goodman, Lake Como , Hervie , Curzon & Penticost)
Contractor Stabile & Winn Change Order# I 2 Date 9/15/2011
41264
City Project Mgr. ,__G_o...._pa_l_S_ah_u ____________ _. City Inspector L.I _K_im_B_re_nz _________ _.
ADDITIONS
-new
TPW
WATER
SEWER
,t,ons
Change Order Additions Page 1 of 1
0.00
$0 .00
$73 ,236.70
fo 1n WOlffH ----,...--City of Fort Worth
Change Order Deletions
Project Name 2007 CIP DISTRICT 7 PART 2 --DOE#5856 ,#5857 ,#5860
Client Project# #00931 ,00935 ,00932.
City Sec#
Proj ect Description Pavement, Water & Sanitary Sewer Replacement (Fletcher, Goodman , Lake Como, Hervie, Curzon & Penticost)
Contractor Stabile & Winn Change Order # ! 2 Date 9/15/2011
41264
Ci ty Project Mgr . Gopal Sahu .__ _______________ ____, City Inspector !.__K_im_B_re_n_z ________ _.
DELETIONS
IIEM Ut~vKlt-' I IUN Utt-'I Qty Unit unit cost 1otal
TPW
WATER
SEWER
Sub Total Deletions
Change Order Deletions Page 1 of 1
$0 .00
$0 .00
$0 .00
M/WBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00
...
I& -Stabile &
Concrete Paving and Construction
.Winn, Inc.
Kim Benz ..
City of Fort Worth :.
1100 Throckmorton Street
Fort Worth, Texas 76102
RE: District #7. Part 2 -Change Order #2
Dear Mr. Benz,
July 14, 2011
The following are the changes required to add the sewer line on Penticost as requested on the above
referenced project.
. No. Description Estimated Quantity Unit Price Extension
UNIT II Sanlii!:ll §!i!wer
DOE #5857 Curzon, Pentlcost, & Sanguinet
1 8" SDR-35 Sewer Pipe NEW 366 LF $28 .00 · $10,248.00
2 4' Stand . Manhole (0'-61 NEW 1.00 EA ·$2,200;00 $2,200 .00
3 4" Sewer Sel"llice NEW 100.00 LF $7 .50 $750.00
4 4" Sewer Sel"lli.ce Tap NEW 4 .00 EA $550 .00 $.2,200 .00
5 4 " 2-Way Sel"llice Cleanout NEW 4 .00 EA $55 .00 $220.00
6 Post lV Cleaning/Inspection NEW 366.00 LF · $1.60 $585.60
7 Trench Safety NEW 450.00 LF $0 .90 $405.00
8 Temp. H~C Repair 2" HM.AC ori 6" Flex Base NEW 450.00 LF $13.50 $6,075.00
9 Connect to Existing Manhole NEW 2.00 EA $950.00 $1,900.00
TOTAL CHANGE ORDER AMOUNT $24,583.60
At this time I am requesting an additional 30 calendar days for this work. If you have any questions,
please call. Thank you.
Sincerely ,
~/14 Q.._ ___
Jerry Henderson, P.E.
Stabile & Winn , Inc.* P .O. Box 79380 * Saginaw, Texas 76179-0380 * Office 817.847.2086 * Fax 817 .847.2098
Stabile &
Concrete Paving and Construction
Kim Benz , ,
City of Fort Worth , __
1100 Throckmorton Street
Fort Worth, Texas 76102
RE: District #7 Part 2 -Change Order #3
Dear Mr. Benz,
Winn, Inc.
August 10, 2011
The following are the changes required to add the sewer line on Goodman as requested on the above
referenced project.
No. Description Estimated Quantity Unit Price Extension
UNIT II ~anlta!:ll ~!W!r
DOE #5856 Retcher & Goodman
3 8" SDR-35 Sewer Pipe INCR 761 LF $28 .00 $21,308 .00
7 4' Stand. Manhole (0'-61 INCR 4 .00 EA $2,200.00 $8,800.00
9 32" Manhole Frame & Cover INCR 2 .00 EA $50 .00 $100 .00
10 Interior Protecti11e Coating !NCR 13.00 \IF $155.00 $2,015.00
13 Rem Manhole INCR 3.00 EA $350.00 $1,050.00
15 4" Sewer Service . INCR 40.00 LF $7.50 . $300.00
17 4" Sewer Service Tap INCR 2 .00 EA $550.00 $1,100 .00
18 4" 2-WaySei\1ce Cleanout INCR 2.00 EA $55.00 $110 .00
27 Post 1V Cleaning/Inspection INCR 761.00 LF $1 .60 $1,217.60
28 Pre lVCleaning/lnspection INCR 761 .00 LF $2.50 $1 ,902 .50
31 Perm. HMAC Paving Repair INCR 150.00 SF $10 .00 $1,500.00
39 Traffic Control INCR 1 .00 LS $2,000.00 $2,000 .00
41 C0#1 Temp. 2" HMAC on 6" Flex Base INCR 700.00 LF $13 ;50 $9,450 .00
TOTAL CHANGE ORDER AMOUNT $50,853.10
At this time I am requesting an additional 30 calendar days for this work. If you have any questions,
please call. Thank you.
Sincerely,
~-~Q,,__ -
Jerry Henderson, P.E.
Stabile & Winn , Inc.* P.O. Box 79380 * Sag in aw, Texas 761 79-0 380 * Office 817 .847 .2086 * Fax 817.847.2098
PROJECT NAME:
PROJECT SUMMARY SHEET
(Change Order Attachment)
2007 CO's CD7 Part 2
PROJECT LIMITS: Fletcher, Goodman, Lake Como, Hervie, Curzon, Penticost
Client Project #'s: 00931,00935,00932
BuySpeed No :
Contract No : CS41264
D.O.E. No : 5856,5857,5860
Attachment to Change Order ~ 2 ------Today's Date : 11/22/11
TOTAL TPW
Original Contract Amount: $ 2,421,552.20 $1,780,557.20 $
Extras to Date: $ 131,604.00 $ $
Credits to Date: $ $ $
$
$
Contract Amount to Date: $ 2,559,156.20 $1,780,557.20 $
Amount of Proposed Change Order: $ 73,236.70 $ $
Revised Contract Amount: $ 2,632,392.90 $1,780,557.20 $
$
$
Contingency Funds Avail. for Admin. Change Orde~ $ 105,332.00 $ 69,386.00 $
Remaining Funds Available for Change Orders: $ 69,386.00 $ 69,386.00 $
Additional Funding (if necessary): $ 73,236.70 $ $
Prepared By : Karen Striker T/PW Business Servi ces
Water Sewer
472 ,867 .50 $174,127.50
113,231.00 $ 18,373 .00
$
586,098.50 $192,500.50
$ 73 ,236.70
586,098.50 $265,737 .20
26,324.00 $ 9,622.00
$
$ 73,236.70
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 11/15/2011
DATE: Tuesday, November 15 , 2011 REFERENCE NO.: **C-25280
LOG NAME : 20SW_CD7 _PT2_C02
SUBJECT:
Authorize Change Order No . 2 in the Amount of $73,236 .70 to C ity Secretary Contract No . 41264 with
Stabile & Winn, Inc., for Sanitary Sewer Main and Sanitary Sewer Service Replacements on Goodman
Street and Penticost Street Resulting in a Total Contract Amount of $2 ,632 ,392 .90 (COUNCIL DISTRICT
7)
·~------------------
RECOMMENDATION:
It is recommended that the City Council authorize the execution of Change Order No . 2 in the amount of
$73,236.70 to City Secretary Contract No . 41264 , a construction contract with Stabile & Winn, Inc., for
sanitary sewer main and sanitary sewer service replacements on Goodman Street and Pent icost Street ,
thereby revising the original contract amount to $2 ,632 ,392 .90 .
DISCUSSION:
This is a 2007 Critical Capital Neighborhood Street project for pavement reconstruction and water and
sanitary sewer replacements on portions of seven different streets . The contract was awarded to Stabile &
Winn, Inc ., on December 14, 2010 (M&C 24663). During the construction of Goodman Street and
Penticost Street, it was found that some of the existing sanitary sewer main was old clay pipe and required
replacement. The original contract did not provide for the replacement of sanitary sewer lines on the
subject portions of Goodman and Penticost streets.
Change Order No. 2 includes replacement of 1,126 linear feet of eight-inch sanitary sewer main , four
manholes, 140 sanitary sewer services, interior manhole coatings , sanitary sewer cleanouts and
appurtenances. The Water Department has concurred with the add itional work for this change order. The
contractor is requesting $73 ,236.70 and an additional 30 calendar days for the additional work and Staff
considers this to be fair and reasonable for the work proposed . Funds for th is change order w i ll be
prov ided from the Sewer Capital Project Fund by the Water Department.
Stabile & Winn , Inc., is in compliance with the City's M/WBE Ordinance by comm itting to an additional 93
percent M/WBE participation on this Amendment/Change Order No . 2. The City 's goal on this amendment ,
change order or extra work is 15 percent.
This project is located in COUNCIL DISTRICT 7 .
FISCAL INFORMATION/ CERTIFICATION:
The Financial Management Services Director certifies that funds are available in the current capital
budget , as appropriated of the Sewer Capital Projects Fund .
FUND CENTERS:
TO Fund/Account/Centers
Log nam e: 20SW _ CD7 _PT2_ C02 Pa1:1:e 1 of 2
CERTIFICATIONS:
Submitted for City Manager's Office by:
Originating Department Head:
Additional Information Contact:
ATTACHMENTS
FROM Fund/Account/Centers
P258 541200 707170093183
P258 541200 707170093283
Fernando Costa (6122)
Douglas W . Wiersig (7801)
Gopal Sahu (7949)
1. 20SW CD7 PT2 CO2 FAR 00931 .pdf (CFW Internal)
2. 20SW CD7 PT2 CO2 FAR 00932 .pdf (CFW Internal)
3. 20SW CD7 PT2 CO2 MWBE2 .pdf (CFW Internal)
4. 20SW CD7 PT2 C02.pdf (Publ ic)
5. P258 -476045-701139990100 .doc (CFW Internal)
Logn am e: 20SW _C D7 _PT2_C02
$50.853 .10
$22.383 .60