Loading...
HomeMy WebLinkAboutContract 41401-CO1FORT WORTH. CITY SECRETARY CONTRACTNO .:\\L\-D\/(0 ~ City of Fort Worth Change Order Request Project Name! 2007 Critical Capital Project District 9 Partll, 98 Client Project#(s~ P275-541200-70917-0098083 City Sec# 41401 Project Descrip . Pavement Reconstruction and Water and Sanitary Sewer Main Replacement on Portions of Biddison Street Blodgett Avenue, Eu e Avenue and East Buder Street DOE#5923 Contractor! Conatser Construction Change Order# 1 Date 6/6/2011 City Project Mgr.! Gopal Sahu City Inspector ._Lu_isa_Al_lbrig--=· :....ht ______ -..J Original Contract Amount Extras to Date Credits to Date Dept. Pending, Change Orders (in M&C Process) Contract Cost to Date CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS% OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25"} Contract Time CD 270 270 0 270 The original contract <Id not include the replacement of the water line in Biddison Ave. However, during the reconstruction of Biddison Ave., it was discovered that the water line was too shallow and had to be replaced . Items 15, 18, 20 & 22 are associated with that water line replacement. Also,.the Water Dept requested that a Temporary Air Release be installed at the point of the water line where it dead-ends at the intersection of Biddison Ave. and Eco Lake Drive. Additionally, at Sanitary Sewer Station 17+09 on Lateral 4343, 31 LF of sewer line had to be replaced with SD~ 26 Sewer Pipe because of the ~.!Rt{\:crossed in close proximity of an existing Storm Drain line. No additional time was requested for the'additional work . *~~f OR ,:-'Q.'Q~ ff otcPooOOOOooff o ~Q¢ . Attested by: ~ t.tl~\~~ ~ ·11nJ~lwuL ~-! g%~~ l d~l ' ~ Cl i 0 l ~ Ronald P. Gonzales, Asst. City SeaetarY ~ .,,.._ o o TJ:I '<11. "'f" 00 00 ,c:/ V 000000° '°' l:l.'tl.'ll.'\l.'\l.~'(\.~ It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. M&C Date Approved 05:02 IN Project Name Cl ient Project # City of Fort Worth Change Order Additions 2007 Critical Capital Project District 9 Partll , 98 P275-541200-70917-0098083 City Sec# Project Description Pavement Reconstruction and Water and Sanitary Sewer Main Replacement on Portions of Biddison Street, Blodgett Avenue , Eugene Avenue and East Butler Street (DOE#5923) Contractor Conatser Construction Change Order# I 1 Date 6/6/2011 City Project Mgr. .._G_o __ pa_l_Sa_h_u ___________ __. City Inspector I Luisa Allbright ADD1T10N5 llt::M Ut:-:>1..,t<II-' I IUN Ut:I"' I \..It}' Unit Unit \,;OSt :a·,&-!.. I-(AUUJ H" ~UK-lti .:>ewer LUU.VU Lt· ~Jl .Ul 00121-U (ADD) Temporary Air Release Valve Water 1.UU EA ~:, I :,uu . Ul 00018-15 {INC) Pipe Pressure H" lnSlclll water tiUl.UU LI" ~lb.UU 00(49-18 (INC) Valve 8" Gate vaive install W/Box Water 1.Ul; EA ~~uu .uu 00758-20 (INC}Water l:)erv1ce 1· install water lbJ.UU U· ~.!ti.VU WfOi.·ll (INC)Water Mam ~rv,ce 1 men tap to main install water 1 b .UU t:.A ~lHb.UU Water Sewer TPW SUD I Otal Aaa1tions Change Order Additions Page 1 of 1 41401 IOtal ~ti,i.UU .UU ~o,ouu .uu ~l b,UOU .UU ~~uu.uu ~o,oro.uu ~i.,f ro.UU ~JU ,HUJ.UU $6 ,200 .00 $0 .00 ~J/,UUJ .00 City of Fort Worth Change Order Deletions Project Name 2007 Critical Capital Project District 9 Partll , 98 Client Project# P275-541200-70917 -0098083 City Sec# Project Description Pavement Reconstruction and Water and Sanitary Sewer Main Replacement on Portions of Bidd ison Street, Blodgett Avenue, Eugene Avenue and East Buijer Street (DOE#5923) Contractor Conatser Construction Change Order # l 1 Date 6/6/2011 City Project Mgr. ....._G_o.._pa_l_Sa_h_u ___________ __, City Inspector I Luisa Allbright DELETIONS lfEM Ut:til,;t<I~ I IUN Ut:~I I.J.ty Unit Unit cost . Water Sewer TPW Sub Total Deletions Change Order Deletions Page 1 of 1 41401 1ota1 $0.00 $0 .00 $0 .00 M/WBE Breakdown for this Change Order ,,,, MWBESub •. .:~,1 ' . Type of Service : ·~·, · c"' Amount for this CO , Total ·' · 1~~;i{; -~.P .r,,•, . , ~-' ' . ' . ' ;;_fr·Ji ' ~.oo c, .. ::.;,.: .. ~. . .. , .. , Previous Change Orders ,~1-CO#. '/• i < -·''-, i, . DATE:,!. , ; , • .. : .L ',, ;.\. :,, • . AMOUN'F: i (.:;(\.,, .,,;i;'; ,,,· • ., • ' ,c, ?:'?''::,, ' ' ··-·~ . Total PROJECT NAME: PROJECT LIMITS: BuySpeed No (T/PW): BuySpeed No (Water): Qty Project No: Contract No: D.O.E. No: Attachment to Change Order No: Today's Date: Original Contract Amount: Extras to Date: Credits to Date: Contract Amount to Date: Amount of Proposed Change Order: Revised Contract Amount: PROJECT SUMMARY SHEET (Change Order Attachment) 2007 CO's CD9 Neighborhood Streets Group 98 Blddlson, Blodgett, Eugene & Butler csco-11-ooo&s3s3 csco-11-ooo&s29a 00980 CS41401 Original M & C approved 01-25-11 , C-24716 5923 1 9/14/11 TOTAL $ 1,148,630.90 $ 641,721.00 $ 250,910 .40 $ 255,999.50 $ $ $ $ $ $ $ $ $ 1,148,630.90 $ 641,721.00 $ 250,910.40 $ 255,999.50 $ 37,003.00 $ $ 30,803 .00 $ 6,200.00 $ 1,185,633.90 $ 641,721.00 $ 281,713.40 $ 262,199.50 Contingency Funds Avail. for Admin. Change Orders: $ $ $ 37,546.00 $ 37,546.00 $ $ 25,000.00 $ 25,000.00 $ $ 12,546.00 $ 12,800.00 12,546.00 $ 12,800.00 Remaining Funds Available for Change Orders: Additional Funding (if necessary): Prepared By: Christy Ezernack T/PW Construction Services