HomeMy WebLinkAboutContract 41730-CO3';:
•
FORT WORTH .
~
City of Fort Worth
Change Order Request
CITY SECRETARY
CONTRACT NO . l-\ h::{)' to ~
Project Name! McAlister Road Improvements City Sec# 41730 ..._ _____ ____.
Client Project#(s)! 01078
:=====================================================================~
Project Description I Paving and Drainage
DOE 6467
Contractor! McClendon Const Co . Inc . Change Order# 3 Date 3/18/2013
City Project Mgr .... ! _W_i_lm_a_S_m_it_h --------------' City Inspector Michael Collier
Dept. TPW Water Sewer Totals Select Day Type
Original Contract Amount $1 ,125 ,078.81 .
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date $1 ,125 ,078.81
I Go to ADD & DEL Tabs to Enter CO Backup $0.00 $0.00 $0.00
Revised Contract Amount $1 ,125 ,078 .81
Original Funds Available for Change Orders $33 ,752 .00
Remaining Funds Available for this CO $33 ,752 .00
Additional Funding (if necessary)
CHANGE ORDERS to DA TE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
$1 ,125 ,078 .81
$1 ,125 ,078 .81
$1 ,125 ,078 .81
$33,752 .00
$33 ,752 .00
0.00%
$1,406 ,348 .51
JUSTIFICATION (REASONS) FOR CHANGE ORDER
This project was delayed due to several issues and additional time was not added with the prior Change Orders : 1 ). TxDOT requested an
exclusive right-turn lane from the Southbound Frontgage Road onto McAlister Rd .; 2). We had to coordinate with UP Railroad on their
improvements in the project.; 3). Street Light issues ; and 4). Additional construction items.
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
290
290
125
415
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of, or incidental to , the above Change Order.
Contractor's Com an Name ontractoc
McClendon Const Co . Inc .
uired
M&C Number M&C Date Approved
RECEIVED APR 2 2 20i3
'" ,
'/ f0 1!,.T ;ORTij .. City of Fort Worth
Change Order Request
Project Name!.-_M_c_A-lis-te-r-Ro_a_d_lm_p_ro_v_e_m-en-ts------,,-------------. ~ity Sec# 41730
ClientProject#(s)!.__0_10_7_8 ________________________ D_O_E_6_46_7 ____ __J
Project Description I Paving and Drainage
Contractor! McClendon Const Co. Inc . Change Order# 3 Date 3/18/2013
' City Project Mgr .l.__W_i_lm_a_S_m_ith __________ __. City Inspector Michael Collier
.,,:,, , /
Dept. TPW Water ~ Sewe /-1r _,..,
J rl>tals Select Day Type
Original Contract Amount $1 ,125 ,078.81 -
Extras to Date ....) 11' ,, ,...
Credits to Date -1 \i. d
Pending Change Orders (in M&C Process) 1. I 1 -' '
,~ ./
Contract Cost to Date $1 ,125 ,078 .81 1 I I ../ .
I Go to ADD & DEL Tabs to Enter CO Backup $0.00 $0.00 $0.00
Revised Contract Amount $1 ,125 ,078 .81
Original Funds Ava ilable for Change Orders $33 ,752 .00 ..,)
Remaining Funds Available for this CO $33,752 .00 ,
Additional Funding (if necessary)
CHANGE ORDERS to DA TE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
JUSTIFICATION (REASONS) FOR CHANGE ORDER
$1 ,125 ,078 .81
I '~ ' U/•5
l , ., ,, r 11v1 (. --
$1 ,125 ,078 .81
I -
$1 ,125,078.81
$33,752.00
$33,752 .00
0.00%
$1,406 ,348 .51
This project was delayed due to several issues and additional time was not added with the prior Change Orders : 1 ). TxDOT requested an
exclusive right-turn lane from the Southbound Frontgage Road onto McAlister Rd .; 2). We had to coordinate with UP Railroad on their
improvements in the project.; 3). Street Light issues ; and 4). Additional construction items.
\
)
;JL,JJ~
290
290
125
415
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of, or incidental to , the above Change Order.
/
Date Date 1
-9 I J f, 1 ° I) Jf /~
i--,:..;~~~.:Jrl;,f,,+.!,,,"J'--------i---'.~~-=--b=-...;..;.;,;,,,.,,f-..,;;,..,_,_~,.......>f---,+----t-T D_a--:te,---, ~,
13
M&C Number
..
, ....
FORT WORTH .
~ City of Fort Worth
Change Order Request
Project Name! McAlister Road Improvements City Sec # 41730 ~--------'
Client Project #(s)j 01078 DOE 6467
;:=======================================================================~
Project Description! Paving and Drainage
Contractor! McClendon Const Co . Inc . Change Order #
City Inspector
3 Date 3/18/2013
City Project Mgr..._! _W_i_lm_a_S_m_it_h ___________ -' Michael Collier
Dept. TPW Water '{; Sewer ( 1,
rotals Select Day Type
Original Contract Amount $1 ,125 ,078.81
Extras to Date ...
Credits to Date \ I
Pending Change Orders (in M&C Process)
Contract Cost to Date $1 ,125 ,078 .81
I Go to ADD & DEL Tabs to Enter CO Backup $0.00 $0.00 $0.00
Revised Contract Amount $1 ,125 ,078 .81
Original Funds Available for Change Orders $33,752 .00
Remaining Funds Available for this CO $33,752 .00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
JUSTIFICATION (REASONS) FOR CHANGE ORDER
$1 ,125 ,078 .81
l
•.d.! I. <. --
$1 ,125 ,078 .81
$1 ,125 ,078 .81
$33,752 .00
$33 ,752 .00
0.00%
$1 ,406,348.51
This project was delayed due to several issues and additional time was not added with the prior Change Orders : 1). TxDOT requested an
exclusive right-turn lane from the Southbound Frontgage Road onto McAlister Rd .; 2). We had to coordinate with UP Railroad on their
improvements in the project.; 3). Street Light issues ; and 4). Additional construction items .
V
290
290
125
415
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of , or incidental to , the above Change Order.
Date
Date 1-1i
i--,.;...:..:..;;:.:~~~~· I'::,,---------+--'..:....;..:_' -;-+-:-=f--r:----'--=-~---+Q+-----+--,-Da_te-.----1 ; ~-
Council Action if re uired
M&C Number M&C Date Approved
FORT WORTH
~
City of Fort Worth
Change Order Request
\ \ i.
Project Name I McAlister Road Improvements City Sec# 41730 .__ ______ __.
ClientProject#(s)!.__0_10_7_8 _________________________ D_O_E_6_4_67 ____ _.
Project Description I Paving and Drainage
Contractor! McClendon Const Co. Inc. 3 Date
City Project Mgr.I Wilma Smith
Change Order#
City Inspector Michael Collier .__ ______________ ___.
Dept. TPW Water Sewer
Original Contract Amount $1 ,125 ,078 .81
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date $1 ,125 ,078 .81
I Go to ADD & DEL Tabs to Enter CO Backup $0.00 $0.00 $0.00
Revised Contract Amount $1 ,125 ,078 .81
Original Funds Available for Change Orders $33,752 .00
Remaining Funds Available for this CO $33,752 .00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS% OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Totals
$1 ,125 ,078 .81
$1 ,125 ,078 .81
$1 ,125 ,078 .81
$33,752 .00
$33 ,752 .00
0.00%
$1,406,348.51
3/18/2013
Select Day Type
290
290
125
415
This project was delayed due to several issues and additional time was not added with the prior Change Orders : 1 ). TxDOT requested an
exclusive right-turn lane from the Southbound Frontgage Road onto McAlister Rd.; 2). We had to coordinate with UP Railroad on their
improvements in the project.; 3). Street Light issues ; and 4). Additional construction items .
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of , or incidental to , the above Change Order.
Contractor's Company Name I Contractor (Name) I Contract SiQnature Date
McClendon Const Co . Inc . I I I L .
" I 1 -. I --.
Inspector/Inspection Supervisor Date Project ManaQer/ProQram ManaQer Date
' I L:z,
Assistant Director (Dept) Date Director , ContractinQ Department (Dept} Date
~
Assistant City Attorney Date Assistant City ManaQer Date
r . , .
'7 '• ""~ ·-... ""' --...
'
Council Action if required)
M&C Number I ,/ ~ I M&C Date Approved I I
I
FORT WORTH ------.---City of Fort Worth
Change Order Additions
Project Name Paving and Drainage for McAlister Road from UP RR to l-35W City Sec# 41730
DOE 6467 Client Project# 01078
::=======================================================================:::::
Project Description Paving and Drainage
Contractor McClendon Const Co . Inc . Change Order # 3 Date 3/18/2013
City Project Mgr. Wilma Smith .__ ______________ __, City Inspector Michael Collier
ADDITIONS
llt::M UC::.:>v~lt' I IUN Ut.t' I lJty Unit Unit 1,;0St Total
I t'VV
fPW
fPW
IPW
IPW
IPW
IPW
IPW
I t'VV
IPW
IPW
IPW
IPW
IPW
IPW
IPW
IPW
IPW
IPW
lt-'VV
TPW
Water
Sewer
Sub Total Add1t1ons
Change Order Additions Page 1 of 1
$0.00
$0 .00
$0 .00
.
' .
FORT WORTH -----,..---City of Fort Worth
Change Order Deletions
Project Name Paving and Drainage for McAlister Road from UP RR to l-35W City Sec# 41730
DOE 6467 Client Project# 01078 ..._ ___________________________________ _,
Project Description Paving and Drainage
Contractor McClendon Const Co . Inc . Change Order# 3 Date 3/18/2013
City Project Mgr. Wilma Sm ith .__ ______________ ____. City Inspector Michael Collier
DELETIONS
11t:M Ut:::il..iKlt-' I IUN Ut:t-' I I.II}' Unit unit L;ost 1ota1
TPW
Water
Sewer
sue Tota Deletions
Change Order Deletions Page 1 of 1
$0 .00
$0 .00
$0 .00
M/WBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00
Offlo al s,t e of the City of Fort Worth, Texas
CITY COUNCIL AGENDA fORTWORTH
~
COUNCIL ACTION: Approved on 4/5/2011
DATE: 4/5/2011 REFERENCE NO.: C-24844 LOG NAME: 20MCALISTER-UPR-
IH35W
NON-PUBLIC
CODE: C TYPE: CONSENT HEARING: NO
SUBJECT: Authorize Execution of a Contract with McClendon Construction Company, Inc., in the
Amount of $1,125,078.81 for Pavement and Drainage Improvements for McAlister Road
from Union Pacific Railroad to Interstate Highway 35W (COUNCIL DISTRICT 6)
RECOMMENDATION:
It is recommended that the City Council authorize the City Manager to execute a contract with
McClendon Construction Company, Inc., in the Amount of $1,125,078.81 for Pavement and Drainage
Improvements for McAlister Road from Union Pacific Railroad to Interstate Highway 35W.
DISCUSSION:
Street Improvements along McAlister Road from its intersection with the southbound frontage road of
Interstate Highway 35W to just west of the Union Pacific Railroad have been planned in order to
address congestion and safety problems. The City's portion of funding for this project will come
through the Community Facilities Agreement {CFA) line item in the 2004 Capital Improvement
Program in conjunction with CFA funding collected from adjacent developers. In as much as that
portion of the improvements west of the railroad are within the city limits of Burleson {1,466 feet), the
City of Burleson has also agreed to contribute funding for the design contingent upon a commitment
from the City of Fort Worth that they will be reimbursed for the design fees if the road is not ultimately
constructed.
On May 9, 2009, the City Council authorized the execution of an lnterlocal Agreement (ILA) {M&C C-
23500) with the City of Burleson in the amount of $240,000 .00 to lead the design of McAlister Road in
accordance with City of Fort Worth standards and the execution of a design contract with Kimley-
Horn and Associates in the amount $226,000.00 for the design work.
The construction contract was advertised for bid in the Fort Worth Star-Telegram on October 28 ,
2010 and November 4, 2010. On November 18, 2010 , the following bids were received :
Bidder Amount
McClendon Construction $1,125,078.81
Companv , Inc.
JLB Contractina , LLC $1,146,473.93
Jackson Construction. Ltd . $1 200,621.00
Conatser Construction TX , LP $1,248,023.70
CPS Civil, LLC $1 ,250,106.00
The Fain Group, Inc. $1,329,845.40
Stabile & Winn, Inc . $1,342,677.40
Time of completion : 270 calendar days
The City reserves the right to increase or decrease quantities of individual pay items within the
contract , provided that the total contract amount remains within plus or minus 25 percent of the
contract award .
http://apps.cfwnet.org/council_packet/mc _review .asp?ID= 14827&councildate=4/S/2011 4/20/2011
--i::,-----
In addition to the contract cost, funding in the amount of $81,000.00 is included for TPW associated
costs for survey , project management, material testing , field inspection and project close out. The
contingency funds to cover change orders for pavement reconstruction work total $33,752 .00 .
McClendon Construction Company, Inc., is in compliance with the City's M/WBE Ordinance by
committing to 18 percent M/WBE participation. The City's goal on this project is 17 percent.
This project is located in COUNCIL DISTRICT 6 .
FISCAL INFORMATION/CERTIFICATION:
The Financial Management Services Director certifies that funds are available in the current capital
budget, as appropriated , of the New Development Fund .
TO Fund/Account/Centers FROM Fund/Account/Centers
c202 541200 206760107883 St 125.078 .81
Submitted for City Manager's Office by:
Originating Department Head:
Additional Information Contact:
AUACl:tMENll
01078MCAL1STERMAP .pdf
Fernando Costa (6122)
Greg Simmons (7862)
Wilma Smith (8785)
http://apps.cfwnet.org/council_packet/mc _ review.asp?ID= 14827&councildate=4/S/2011 4/20/2011 ..
. .
. ' •
PROJECT NAME :
BuySpeed No (T/PW):
BuySpeed No (Water):
City Project No:
Contract No :
D.O .E. No :
Attachment to Change Order No :
Today's Date :
Original Contract Amount:
Extras to Date :
Credits to Date :
Contract Amount to Date :
PROJECT SUMMARY SHEET
(Change Order Attachment)
McAlister Road Improvements
P0-11-0067030
N/A
01078
cs 41730 I
6467 I
3
3/18/13
TOTAL
$ 1, 125,078.81 $1 ,125,078 .81
$ -$ -
$ -$ -
$ 1, 125,078.81 $ 1,125,078 .81
Amount of Proposed Change Order: $ -
Revised Contract Amount: $ 1, 125,078.81 $ 1,125 ,078 .81
Contingency Funds Avail. for Admin . Change Orders : Ii Remaining Funds Available for Change Orders:
Additional Funding (if necessary):
Prepared By: Alicia Garcia T/PW Construction Services
I
$ -$ -
$ -$ -
$ -$ -
$ -$ -
I :