City of Fort Worth
Change Order Request
Project Name! HMAC Surface Overlay ( 2011-12) At Various Locations
Client Project #(s)j C293-541200-209620173083 City Project No : 01730
Project Description HMAC Surface Overlay Throughout the City
(!t!)i=Jy J_ C, F" ~
g~:;~e:'t, ljtil 7q -col
I City Sec # 42079
DOE: 6675
Contractor! JLB Contracting , LLC
City Project Mgr.! Kristian Sugrim
Change Order # Date 5/30/2012
(817) 392-8902 City Inspector Anthony Host (817) 223 -2281
Enter Department(s) to the Right and TPW Totals Contract Time
Contract Day Type (CD)
Original Contract Amount $918 ,529.50 $918 ,529 .50 120
Extras to Date
Credits to Date
Pend ing Change Orders (in M&C Process)
Contract Cost to Date $918 ,529 .50 $918 ,529 .50 120
!Amount of Proposed Change Order $0.00 147
Revised Contract Amount $918 ,529 .50 $918 ,529 .50 267
Original Funds Available for Change Orders $0 .00
Rema ining Funds Ava ilable for th is CO $0.00
Additiona l Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS% OF ORIGINAL CONTRACT 0.00%
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) $1 ,148 ,161 .88
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Th is change order is to request that an additional 147 Calendar Days (CD) be added to this contract due to ATMOS Energy having to relocate
or upgrade supply lines on Foch St , Granger St , Peach St & Washington Ave.
OFFICIAL RECORD
CITY SECRETARY
FT, WORTH, TX
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of, or incidental to , the above Change Order.
~~~~~~~~__i;_~---i-~~~~~~~-L-~~~~
~~~~~====----~~~~--.sl..~~-::::!.::_~~~-~"=-J,J..}.~~t ~
t--=f,~~b;ifi~------t--;,;-~=---:::--~~~~~----t\----J---~~41J
~
L__ __ M_&c_N_um_be_r -===:t=:::::==---------~----====------!~'¢
0 6 -14-12 A09:28 IN \) ~
City of Fort Worth
Change Order Request
Project Name! HMAC Surface Overlay ( 2011-12) At Various Locations
Client Pmject #(s)j C293-541200-209620173083 City Project No : 01730
Project Description HMAC Surface Overlay Throughout the City
l/1t 11 -tol
City Sec # 42079
DOE : 6675
Contractor! JLB Contracting , LLC
City Project Mgr. I Kristian Sugrim
Change Order# Date 5/30/2012
(817) 392-8902 City Inspector Anthony Host (817) 223-2281
Enter Department(s) to the Right and TPw////
(:;ii' !~ Contract Time "' ~ TQ als Contract Day Type (CD)
Original Contract Amount $918 ,529.50 $918 ,529 .50 120
Extras to Date
Credits to Date \ 1111 \ -'
Pend ing Change Orders (in M&C Process) l I
Contract Cost to Date $918 ,529 .50 $918 ,529 .50 120
!Amount of Proposed Change Order $0.00 147
Revised Contract Amount $918 ,529 .50 $918 ,529 .50 267
Original Funds Available for Change Orders $0 .00
Remaining Funds Available for th is CO $0 .00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS% OF ORIGINAL CONTRACT 0.00%
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) $1 ,148 ,161 .88
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Th is change order is to request that an additional 147 Calendar Days (CD) be added to this contract due to ATMOS Energy having to relocate
or upgrade supply lines on Foch St , Granger St , Peach St & Washington Ave .
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs aris ing out of, or inc idental to , the above Change Order.
Date
0-S-/
M&C Number
FORT WORTH .,
~
City of Fort Worth
Change Order Request
Project Name! HMAC Surface Overlay ( 2011-12) At Various Locations
Client Project #(s)! C293-541200-209620173083 City Project No : 01730
Project Description HMAC Surface Overlay Throughout the City
l/1t'71 (t I
City Sec# 42079
DOE : 6675
Contractor! JLB Contracting , LLC
City Project Mgr.! Kristian Sugrim
Change Order# Date 5/30/2012
(817) 392-8902 City Inspector Anthony Host (817) 223-2281
Enter Department(s) to the Right and .... Contract Time TPW ., , Totals Contract Day Type (CD)
Original Contract Amount $918 ,529.50 $918 ,529 .50 120
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date $918 ,529 .50 $918 ,529 .50 120
!Amount of Proposed Change Order $0.00 147
Revised Contract Amount $918,529 .50 $918 ,529 .50 267
Original Funds Available for Change Orders $0 .00
Remaining Funds Available for this CO $0.00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 0.00%
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) $1 ,148 ,161 .88
JUSTIFICATION (REASONS) FOR CHANGE ORDER
This change order is to request that an additional 147 Calendar Days (CD) be added to this contract due to ATMOS Energy having to relocate
or upgrade supply lines on Foch St, Granger St , Peach St & Washington Ave .
(rll J17_
I '
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs aris ing out of, or incidental to , the above Change Order.
Contractor's Com an Name Contractor Name
JLB Contractin , LLC S.4-
M&C Number M&C Date Approved
FORT WORTH .
~
City of Fort Worth
Change Order Request
\
' Project Namel HMAC Surface Overlay ( 2011-12) At Various Locations City Sec # 42079 .__ _____ ____.
Client Project #(s)I C293-541200-209620173083 City Project No : 01730 DOE : 6675
Project Description HMAC Surface Overlay Throughout the City
Contractor! JLB Contracting , LLC
City Project Mgr . I Kristian Sugrim (817) 392-8902
Change Order# Date 5/30/2012
City Inspector Anthony Host (817) 223-2281
Enter Department(s) to the Right and TPW Totals Contract Time
Contract Day Type
Original Contract Amount $918 ,529 .50
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date $918 ,529 .50
!Amount of Proposed Change Order $0.00
Revised Contract Amount $918 ,529 .50
Original Funds Available for Change Orders
Remaining Funds Available for this CO $0 .00
Additional Funding (if necessary)
CHANGE ORDERS to DA TE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
JUSTIFICATION (REASONS) FOR CHANGE ORDER
(CD)
$918 ,529 .50 120
$918 ,529.50 120
147
$918 ,529 .50 267
$0 .00
0.00%
$1,148 ,161 .88
This change order is to request that an additional 147 Calendar Days (CD) be added to this contract due to ATMOS Energy having to relocate
or upgrade supply lines on Foch St , Granger St , Peach St & Washington Ave .
' J ' ( -
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of , or incidental to , the above Change Order.
Contractor's Com an Name Contractor Name Contract Si nature Date
I ,
lnsoector/lnsoection Supervisor , . 10ate Project Manager/Proaram Manaaer Date
1 ..... ~ 1, ... v-,, -I ·-
Assistant Director (Deot) Date Director, Contracting Department (Dept) Date ..
Assistant €ity Attorney Date Assistant City Manaaer Date
r . ·, ;I . I
Council Action if reQu ired)
M&C Number I -I M&C Date Approved I I
•.
~
fORTWORTH -----.----
Project Name
Client Project#
City of Fort Worth
Change Order Additions
HMAC Surface Overlay ( 2011-12) At Various Locations
C293-541200-209620173083 City Project No : 01730 DOE : 6675
Project Description HMAC Surface Overlay Throughout the City
Contractor JLB Contracting , LLC Change Order #
City Project Mgr. ...__K_ris_ti_an_S_u..._gr_im ___ ___.(_81_7) ..... 3_9_2-_89_0_2 __ ___. City Inspector Anthony Host
ADDITIONS
11 t:M Ut:.:>LiKII"' 1 IUN Ut:I"' I c.ity Unit
NA 11me Only 11-'W 14/.UU uays
Change Order Additions Page 1 of 2
City Sec# 42079
Date 5/30/2012
(817) 223-2281
Unit (.;OSI 1ota1
;i>U.Ul. ;i,u .uu
TPW $0 .00
Sub Total Add1t1ons :t,U .00
Change Order Additions Page 2 of 2
FORT WORTH ------.---City of Fort Worth
Change Order Deletions
Project Name HMAC Surface Overlay ( 2011-12) At Various Locations
Client Project# C293-541200-209620173083 City Project No : 01730
Project Description HMAC Surface Overlay Throughout the City
Contractor JLB Contracting , LLC
DOE : 6675
Change Order #
City Project Mgr. _K_ris_ti_an_S_u~gr_im ____ ~(8_17-)_3_92_-8_9_02 __ ~ City Inspector Anthony Host
DELETIONS
11 t:M ;t-{lt-'IIUN Ut:t' I u.iy Unit
Change Order Deletions Page 1 of 2
City Sec# 42079
Date 5/30/2012
(817) 223-2281
Unrt t,;ost Total
TPW $0 .00
Suo I otal ue1elions
Change Order Deletions Page 2 of 2
M/WBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00
PROJECT SUMMARY SHEET
(Change Order Attachment)
PROJECT NAME:
BuySpeed No (T/PW):
HMAC 2011-12 Surface Overlay @ various locations
P0-11-00067 500
BuySpeed No (Water):
City Project No :
Contract No :
0 .0 .E. No :
Attachment to Change O rder No:
Today's Date :
Original Contract Amoun t
Extras to Date :
Credits to Date :
Contract Amount to Date :
N/A
01730
CS42079
6675
1
5/31/12
Amount of Proposed Change Order:
Revised Contract Amount:
Contingency Funds Avail. for Admin . Change O rders :
Remaining Funds Available for Change Orders :
Additional Funding (if necessary):
Additional Time Requested: 147days
Prepared By : Chri.-•· · -
Original M & C, C-25016, approved 07-19-11
TOTAL
$ 918,529.50
$
$
$ 918,529.50
TIME NLY
$ 918,52 .60
$
$
$
\
PROJECT SUMMARY SHEET
(Change Order Attachment)
PROJECT NAME:
BuySpeed No (T/PW):
HMAC 2011-12 Surface Overlay @ various locations
P0-11-00067500
BuySpeed No (Water): NIA
City Project No: 01730
Contract No : CS42079
D.O .E. No : 6675
Attachment to Change Order No : 1
Today's Date: 5/31/12
Original Contract Amount:
Extras to Date :
Credits to Date :
Contract Amount to Date:
Amount of Proposed Change Order:
Revised Contract Amount:
Contingency Funds Avail. for Admin. Change Orders:
Remaining Funds Available for Change Orders:
Additional Funding (if necessary):
Additional Time Requested: 147 days
Original M & C, C-25016, approved 07-19-11
TOTAL
$ 918,529.50
$
$
$ 918,529.50
TIME ONLY
$ 918,529.50
$
$
$
Prepared By: Christy Ezernack T/PW Construction Services
•,