Loading...
HomeMy WebLinkAboutContract 42305-CO1<C C\J I °' I '° 0 ;; . . FORT WORTH •• City of Fort Worth Change Order Request (2lffl~ CONTRACT NO. LJZ2 DY -to; Project Name! Water and Sewer Relocations for SH 121 T (Southwest Parkway), Part 4 City Sec No . .__4_23_0_5 ____ _, Project No .(s)!P275-709170020388 I DOE No .!.--6-5-80-----, City Pro . No . .__0_02_0_3 ____ _, Project Description Relocation of Sanitary Sewer Mains to Accommodate SH121T Co'nstrution Contractor! Conatser Construction TX , LP Change Order# .... I __ 2 __ _, Date : !617/2012 City Project Mgr ..... ! _L_ia_m_C_o_nlo_n __________ __, City Inspector .... I _M_a_rk_O_w_e_n __________ _, Phone Number: I 817-392-6824 Phone Number: I 871-223-2267 Dept. TPW Water Sewer Totals Contract Time (Calendar days) Original Contract Amount $819,420 .00 $819,420.00 150 Extras to Date $38 ,537 .50 $38,537.50 20 Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date $857,957.50 $857,957.50 IAmount of Proposed Change Order $47,331.50 $47,331.50 Revised Contract Amount $905,289.00 $905,289.00 170 Original Funds Available for Change Orders $25 ,000 .00 $25,000.00 Remaining Funds Ava il able for this CO Additional Funding (if necessary) $47 ,331.50 $47,331.50 CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) 10.48% $1,024,275.00 This change order will allow for the relocation of a 120 foot segment of an existing sanitary sewer main that was encountered in direct conflict with the proposed piers for Chisholm Trail (SH12 l T) over the Clear Fork of the Trinity River near the Bryant Irvin Road/Arborlawn Drive intersection. OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX ,• , FORT WORTH • City of Fort Worth Change Order Additions Project Name Water and Sewer Relocations for SH121 T (Sou thwest Parkway), Part 4 Project No .(s) P275-709170020388 Project Descr iption Water and Sewer Reloca ti ons for SH121 , Part 4 City Sec No . 42305 DOE No .j 6580 I City Pro . No. 00203 Contractor Conatser Construction , TX, LP Change Order# CJ:] Date : I 6/7/2012 City Project Mgr . Liam Conlon -------------------' City Inspector Mark Owen i..._;.;=~..;;.;.;_ _____ __, ADDITIONS llt:M =----.... ·11vn DEPT Qty Unit Unit Cost Total 6 Install 8" SOR 26 Sewer 120 .00 LF $50 .00 $6 ,000 .00 8 48" Std MH Sewer 1.00 EA $3 ,000 .00 $3 ,000 .00 10 Additional Depth 48 " MH Sewer 11 .50 VF $175 .00 $2 ,012 .50 17 Post Construction TV Sewer 120 .00 LF $2 .00 $240 .00 24 Trench Safety Sewer 120 .00 LF $3.00 $360.00 34 60 "' STD MH Sewer 2.00 EA $4 ,500.00 $9 ,000.00 35 Additional Depth 60" MH Sewer 23 .50 VF $250 .00 $5 ,875 .00 36 Mobil ization Sewer 1.00 LS $7 ,500 .00 $7 ,500 .00 37 Abandon and grout 30 " Sanitary Sewer Sewer 96 .00 LF $64.00 $6 ,144 .00 38 Install Bollards around three MHs Sewer 12 .00 EA $600 .00 $7 ,200 .00 Water Sewer $47 ,331.50 Page 2 of 4 Additions Sub Total $47 ,331.50 .-FORT WORTH • City of Fort Worth Change Order Deletions Project Name 1,--W-a-te-r -an_d_S-ew_e_r_R-el-oc-at-io-ns-f-or_S_H_1-21-T-(S_o_u-th-we_s_t P-a-rk-w-ay-),_P_a_rt_4 ____ __, Project No.(s) !P275-709170020388 DOE No . 6580 Project Descr iption Relocation of Sani tary Sewe r Mains to Accommodate SH121T Constrution City Sec No . City Pro . No . 42305 00203 Contracto r Conatser Construction TX , LP City Project Mgr. Liam Conlon ------------- Change Order #[TI Date -' __ 6_17_/2_01_2_~ City Inspector !_M_a_rk_O_w_e_n ------~ DELETIONS ITEM DESCRIPTION DEPT Qty Unit Unit Cost !Total TPW Water Sewer Page 3 of 4 Deletions Sub Total ... M/WBE Breakdown for this Change Order MWBE Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders CO# DATE AMOUNT Total $0.00 PROJECT SUMMARY SHEET (Change Order Attachment) PROJECT NAME: BuySpeed No : City Project No : Contract No : D.O .E. No : Attachment to Change Order No : Today's Date : Original Contract Amount: Extras to Date : Credits to Date : Contract Amount to Date : SH T121 Part 4 P0-12-00068936 00203 CS42305 6580 2 6/6/12 Amount of Proposed Change Order: Revised Contract Amount: Contingency Funds Avail. for Admin . Change Orders : Remaining Funds Available for Change Orders : Additional Funding (if necessary): C-25149 approved 09-13-11 TOTAL $ 819,420.00 $ 38,537.50 $ $ 857,957.50 $ 47,331.50 $ 905,289.00 $ 25,000.00 $ $ (47,331.50) Prepared By: Christy Ezernack T/PW Construction Services . '