Description Water & Paving Improvements.( 5th Ave ,W. Cantey ,Willing)
Contractor! Conatser Construction TX , LP Change Order# 3 Date 3/27/2013
City Project Mgr.._l _G_o..:..p_al_S_ah_u __________ __, City Inspector Richard Salazar
Dept. TPW Water Sewer Contract Time
Original Contract Amount $1 ,438 ,700 .10 $488 ,138 .00
Extras to Date $49 ,040 .00 $33 ,309 .25
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date $1,487,740 .10 $521 ,447 .25
IAmount of Proposed Change Order $18,335.00 $0.00 $0 .00
Revised Contract Amount $1 ,506 ,075 .10 $521 ,447 .25
Original Funds Available for Change Orders $71 ,935 .01 $24 ,406 .90
Rema ining Funds Available for th is CO $22 ,895 .01 $0.00
Add itional Fund ing (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Totals (CD)
$1 ,926 ,838 .10 270
$82 ,349.25 190
$2 ,009 ,187.35 460
$18,335.00 15
$2 ,027 ,522 .35 475
$96 ,341 .91
$22 ,895 .01
5.23%
$2 ,408 ,547 .63
This change order is to make provisions for payment to the contractor for lowering the street light conduit so that driveways and wheelchair
ramps can be installed on Willing Ave , West Cantey and 5th Ave . The scope of work included the installation of new conduit and wiring and the
relocation of pull boxes. Also , at the request of T/PW's Light and Signal Division , additional pull boxes were installed to bring the system up to
code.
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and sat isfaction and represents
payment in full (both time and money) for all costs arising out of, or incidental to, the above C ange Order.
Conatser Construction TX , LP
I
.. ' :
ORT WORTH .
-~
City of Fort Worth
Change Order Request L}2L/ /{;---( (' '3
Project Name! 2007 Critical Capital Project (Council District 9) Part Ill -Group 9C
Client Project #(s}! 00983 -DOE# 6647
City Sec# 42410 I
Project
Description Water & Paving Improvements .( 5th Ave ,W. Cantey.Willing)
Contractor! Conatser Construction TX , LP Change Order# 3 Date
City Project Mgr.~! _G_o_p_al_S_a_hu ___________ ___, City Jnspector If Richard Sa laza; / ~ .
~/I I
Dept. TPW Water l Se~er ,-.. ) -
I Totals
Original Contract Amount $1 ,438 ,700 .10 $488 ,138.00 $1 ,926 ,838 .10
Extras to Date $49 ,040 .00 $33 ,309 .25 $82 ,349 .25
Credits to Date ....) ( 'I I I
Pending Change Orders (in M&C Process) ,' y
Contract Cost to Date $1 ,487,740 .10 $521 ,447 .25 / $2 ,009 ,187 .35
!Amount of Proposed Change Order $18,335.00 $0.00 $0.00 $18,335.00
Revised Contract Amoun t $1 ,506 ,075 .10 $521 ,447 .25 .ft $2 ,027 ,522.35
Original Funds Available for Change Orders $71 ,935 .01 $24 ,406 .90 / ri ,111 7 $96 ,341.91 ..... '-
Remaining Funds Available for this CO $22 ,895 .01 $0 .00 f f / $22 ,895.01
Additional Funding (if necessary)
I
CHANGE ORDERS to DATE (INCLUDIN 11HIS ONE) AS% OF ORIGINAL CONTRACT 5.23%
MAX ALL OWABLE CONTRAC 'AMOUNT (ORIGINAL CONTRACT COST+ 25%) $2,408 ,547.63
JUSTIFICATION (REASONS) FOR CHANGE ORDER
3/27/2013
Contract Time
(CD)
270
190
460
15
475
,
This change order is to make provisions for payment to the contractor for lowering the street light conduit so that driveways and wheelchair
ramps can be installed on Will in ~ Ave , West Cantey and 5th Ave . The scope of work included the installation of new conduit and wiring and the
relocation of pull boxes . Also , at the request of T/PW 's Light and Signal Division , additional pull boxes were installed to bring the system up to
code .
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents
payment in full (both time and money) for all costs arising out of, or incidental to , the above Cp ange Order.
Date
'-I-II -
-/7 -/ J
Date
I
Council Action if required ~().~
M&C Number M&C Date Approved •v
L__ _____ -=::::::::=======--------------.....'.:::::========-----..,..)\~
tS' ~-
~' ORT WORTH .
-~
City of Fort Worth
Change Order Request L/1. l / / l -I c '3
Project Name! 2007 Critical Capital Project (Council District 9) Part Ill -Group 9C
Client Project #(s)! 00983 -DOE# 6647
City Sec# 42410 !
Project
Description Water & Paving Improvements .( 5th Ave ,W. Cantey ,Willing)
Contractor! Conatser Construction TX , LP 3 Date
City Project Mgr.! ... _G_o...;..p_al_S_a_hu ___________ _.
Change Order#
City Inspector Richard Salazar
Dept. TPW Water I,• Sewer I -
Original Contract Amount $1 ,438 ,700 .10 $488 ,138 .00
Extras to Date $49 ,040 .00 $33 ,309 .25
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date $1 ,487 ,740.10 $521 ,447 .25
!Amount of Proposed Change Order $18,335.00 $0.00 $0.00
Revised Contract Amount $1 ,506 ,075 .10 $521,447 .25
Original Funds Available for Change Orders $71 ,935.01 $24,406 .90 1,/J ,I,
Rema ining Funds Available for this CO $22 ,895 .01 $0 .00 C,
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
/
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
JUSTIFICATION (REASONS) FOR CHANGE ORDER
I •.
Totals
$1 ,926 ,838.10
$82 ,349 .25
$2 ,009 ,187.35
$18,335.00
$2 ,027 ,522 .35
$96 ,341 .91
$22 ,895 .01
5.23%
$2,408 ,547 .63
3/27/2013
Contract Time
(CD)
270
190
460
15
475
This change order is to make provis ions for payment to the contractor for lowering the street light conduit so that driveways and wheelchair
ramps can be installed on Willing Ave , West Cantey and 5th Ave . The scope of work included the installation of new conduit and wiring and the
relocation of pull boxes. Also, at the request of T/PW 's Light and Signal Division , addit ional pull boxes were installed to bring the system up to
code.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents
payment in full (both time and money) for all costs arising out of , or incidental to , the above Change Order.
Contractor's Com an Name Contractor Name Contract Si nature Date
Conatser Construction TX , LP / I • I
Date
I./· I-I _,, t IM
Date
Ai• ; i ' )
Date
~ 3 ·1 ~
M&C Number
\)$'
I
~a~ ~-
·. FORT WORTH .
~
City of Fort Worth
Change Order Request
Project Name! 2007 Critical Capital Project (Council District 9) Part Ill -Group 9C
Client Project #(s)! 00983 -DOE# 6647
City Sec# 42410 '---------'
Project Description Water & Paving Improvements.( 5th Ave,W . Cantey ,Willing)
Contractor! Conatser Construction TX , LP Change Order# 3 Date
City Project Mgr. !.__G_o-'-pa_l_S_ah_u ___________ __. City Inspector Richard Salazar
Dept. TPW Water Sewer
Original Contract Amount $1,438 ,700 .10 $488 ,138 .00
Extras to Date $49 ,040 .00 $33 ,309 .25
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date $1 ,487 ,740 .10 $521 ,447 .25
!Amount of Proposed Change Order $18,335 .00 $0 .00 $0.00
Revised Contract Amount $1 ,506 ,075 .10 $521 ,447 .25
Original Funds Available for Change Orders $71 ,935 .01 $24 ,406 .90
Remaining Funds Available for this CO $22 ,895 .01 $0 .00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS% OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Totals
$1 ,926 ,838.10
$82 ,349.25
$2 ,009 ,187 .35
$18,335.00
$2 ,027 ,522 .35
$96 ,341 .91
$22 ,895 .01
5.23%
$2 ,408 ,547 .63
3/27/2013
Contract Time
(CD)
270
190
460
15
475
This change order is to make provisions for payment to the contractor for lowering the street light conduit so that driveways and wheelchair
ramps can be installed on Willing Ave , West Cantey and 5th Ave. The scope of work included the installation of new conduit and wiring and the
relocation of pull boxes . Also , at the request of T/PW's Light and Signal Division , additional pull boxes were installed to bring the system up to
code.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfact ion and represents
payment in full (both time and money) for all costs arising out of , or inc idental to , the above Change Order .
Contractor's Company Name I Contractor (Name) I I Contract Siqnature Date
Conatser Construction TX , LP I I /£}~ .. t/ /Y ..,,.,....--f/-/1-fs
I I-
Inspector/Inspection Supervisor . ,t • Date Project Manager/Program Manager Date
i'."' <," r -...:-,:f {/(---4...-1"1· II·/., I I
(' ,I' , , l '
Assistant Director (Dep~ Date Director, Contractinq Department (Dept) Date
.~
Assistant City Attorney Date Assistant City Manaqer Date
• ,; ~---,,-
~ ; ~
, _ ...
Council Action if required)
M&C Number I -I M&C Date Approved I I ..,.,
I
.. ' ~
FORT WORTH -----.---
Project Name
Client Project #
City of Fort Worth
Change Order Additions
2007 Critical Capital Project (Council District 9) Part Ill -Group 9C
00983 -DOE# 6647
Project Description Water & Paving Improvements .( 5th Ave ,W. Cantey .Willing)
Conatser Construction TX, LP Change Order# 3 Contractor
City Project Mgr. Gopal Sahu City Inspector Richard Salazar
ADDITIONS
lltM Ut::>vKII"' I IUN LJl:PI Uty Unit
IN\,;· 'J1 Install Pull ~oxes IPW o.uu 1:A
IN\,;· 'J2 Install 2" PV(.; PV(.; conduit IPW LUU.UU LI·
IN\,;· 'JJ I Install ~ wire and terminate !PW 1,U4/.UU LF
New-o4 [AdJustPull ~oxes IPW 1.UU l:A
New-o'J [Lowering conduit to grade IPW JO .UU LI·
New-oo 12" ~ore at s1dewa11< rPW 2o .Ut; LF
New-'JI Kelocate Pull ~oxes 11-'W 2.UL EA
Change Order Additions Page 1 of 2
City Sec# 42410
Date 3/27/2013
Unit (.;OSt 1ota1
~/OU.UU $4,0UU.UU
~JU .UU $0,uuu.uu
$'J .UU $0,LJO .UU
$4UU .uu $4UU .uu
$10 .UU $020 .UU
$20.Uu ~OLO.UU
$525 .U\. !lil ,UoU .UU
TPW $18 ,335 .00
Water $0 .00
Sewer $0 .00
Sub 1 otal Add1t1ons $18 ,JJb .UU
Change Order Additions Page 2 of 2
fORTWORTH ----.---City of Fort Worth
Change Order Deletions
Project Name 2007 Critical Capital Project (Council District 9) Part Ill -Group 9C
Client Project# 00983 -DOE# 6647
Project Description Water & Pav ing Improvements .( 5th Ave ,W. Cantey.Willing)
Contractor Conatser Construction TX, LP Change Order# 3
City Project Mg r. Gopal Sahu ,....____._ _____________ ___, City Inspector Richard Salazar
DELETIONS
lltM U!:~I_ ~::--1 IUN Ut,-,1 Uty Unit
Change Order Deletions Page 1 of 2
City Sec# 42410
Date 3/27/2013
Unit cost Total
TPW $0 .00
Water $0 .00
Sewer $0 .00
Sub l otal Deletions
Change Order Deletions Page 2 of 2
M/WBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00