HomeMy WebLinkAboutContract 57837-PM1PROJECT MANUAL
FOR
THE CONSTRUCTION OF
Karis Phase 1 - CFW Sanitary Sewer Connection
IPRC Record No. IPRC22-0020
City Project No. 103920
FID No. 30114-0200431-103920-E07685
X File No. X-27227
Mattie Parker David Cooke
Mayor City Manager
Christopher P. Harder, P.E.
Director, Water Department
Prepared for
The City of Fort Worth
February 2022
Graham Associates, Inc
TBPE Firm F-1191 | TBLS Firm 101538-00
03/02/2022
CSC No. 57837-PM1
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 1 of 6
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN:103920
Revised March 20, 2020
SECTION 00 00 10
TABLE OF CONTENTS
DEVELOPER AWARDED PROJECTS
Division 00 - General Conditions Last Revised
00 11 13 Invitation to Bidders 03/20/2020
00 21 13 Instructions to Bidders 03/20/2020
00 41 00 Bid Form 04/02/2014
00 42 43 Proposal Form Unit Price 05/22/2019
00 43 13 Bid Bond 04/02/2014
00 45 11 Bidders Prequalification’s 04/02/2014
00 45 12 Prequalification Statement 09/01/2015
00 45 13 Bidder Prequalification Application 03/09/2020
00 45 26 Contractor Compliance with Workers' Compensation Law 04/02/2014
00 45 40 Minority Business Enterprise Goal 08/21/2018
00 52 43 Agreement 06/16/2016
00 61 25 Certificate of Insurance 07/01/2011
00 62 13 Performance Bond 01/31/2012
00 62 14 Payment Bond 01/31/2012
00 62 19 Maintenance Bond 01/31/2012
00 72 00 General Conditions 11/15/2017
00 73 00 Supplementary Conditions 07/01/2011
00 73 10 Standard City Conditions of the Construction Contract for Developer
Awarded Projects 01/10/2013
Division 01 - General Requirements Last Revised
01 11 00 Summary of Work 12/20/2012
01 25 00 Substitution Procedures 08/30/2013
01 31 19 Preconstruction Meeting 08/30/2013
01 31 20 Project Meetings 07/01/2011
01 32 33 Preconstruction Video 08/30/2013
01 33 00 Submittals 08/30/2013
01 35 13 Special Project Procedures 08/30/2013
01 45 23 Testing and Inspection Services 03/20/2020
01 50 00 Temporary Facilities and Controls 07/01/2011
01 55 26 Street Use Permit and Modifications to Traffic Control 07/01/2011
01 57 13 Storm Water Pollution Prevention Plan 07/01/2011
01 60 00 Product Requirements 03/20/2020
01 66 00 Product Storage and Handling Requirements 04/07/2014
01 70 00 Mobilization and Remobilization 04/07/2014
01 71 23 Construction Staking 04/07/2014
01 74 23 Cleaning 04/07/2014
01 77 19 Closeout Requirements 04/07/2014
01 78 23 Operation and Maintenance Data 04/07/2014
01 78 39 Project Record Documents 04/07/2014
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 2 of 6
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN:103920
Revised March 20, 2020
Technical Specifications which have been modified by the Engineer specifically for this
Project; hard copies are included in the Project’s Contract Documents
None.
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 3 of 6
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN:103920
Revised March 20, 2020
Technical Specifications listed below are included for this Project by reference and can be
viewed/downloaded from the City’s website at:
http://fortworthtexas.gov/tpw/contractors/
or
https://apps.fortworthtexas.gov/ProjectResources/
Division 02 - Existing Conditions Last Revised
02 41 13 Selective Site Demolition 12/20/2012
02 41 14 Utility Removal/Abandonment 12/20/2012
02 41 15 Paving Removal 02/02/2016
Division 03 - Concrete
03 30 00 Cast-In-Place Concrete 12/20/2012
03 34 13 Controlled Low Strength Material (CLSM) 12/20/2012
03 34 16 Concrete Base Material for Trench Repair 12/20/2012
03 80 00 Modifications to Existing Concrete Structures 12/20/2012
Division 26 - Electrical
26 05 00 Common Work Results for Electrical 11/22/2013
26 05 10 Demolition for Electrical Systems 12/20/2012
26 05 33 Raceways and Boxes for Electrical Systems 12/20/2012
26 05 43 Underground Ducts and Raceways for Electrical Systems 07/01/2011
26 05 50 Communications Multi-Duct Conduit 02/26/2016
Division 31 - Earthwork
31 10 00 Site Clearing 12/20/2012
31 23 16 Unclassified Excavation 01/28/2013
31 23 23 Borrow 01/28/2013
31 24 00 Embankments 01/28/2013
31 25 00 Erosion and Sediment Control 12/20/2012
31 36 00 Gabions 12/20/2012
31 37 00 Riprap 12/20/2012
Division 32 - Exterior Improvements
32 01 17 Permanent Asphalt Paving Repair 12/20/2012
32 01 18 Temporary Asphalt Paving Repair 12/20/2012
32 01 29 Concrete Paving Repair 12/20/2012
32 11 23 Flexible Base Courses 12/20/2012
32 11 29 Lime Treated Base Courses 12/20/2012
32 11 33 Cement Treated Base Courses 12/20/2012
32 11 37 Liquid Treated Soil Stabilizer 08/21/2015
32 12 16 Asphalt Paving 12/20/2012
32 12 73 Asphalt Paving Crack Sealants 12/20/2012
32 13 13 Concrete Paving 12/20/2012
32 13 20 Concrete Sidewalks, Driveways and Barrier Free Ramps 06/05/2018
32 13 73 Concrete Paving Joint Sealants 12/20/2012
32 14 16 Brick Unit Paving 12/20/2012
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 4 of 6
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN:103920
Revised March 20, 2020
32 16 13 Concrete Curb and Gutters and Valley Gutters 10/05/2016
32 17 23 Pavement Markings 11/22/2013
32 17 25 Curb Address Painting 11/04/2013
32 31 13 Chain Fences and Gates 12/20/2012
32 31 26 Wire Fences and Gates 12/20/2012
32 31 29 Wood Fences and Gates 12/20/2012
32 32 13 Cast-in-Place Concrete Retaining Walls 06/05/2018
32 91 19 Topsoil Placement and Finishing of Parkways 12/20/2012
32 92 13 Hydro-Mulching, Seeding, and Sodding 12/20/2012
32 93 43 Trees and Shrubs 12/20/2012
Division 33 - Utilities
33 01 30 Sewer and Manhole Testing 12/20/2012
33 01 31 Closed Circuit Television (CCTV) Inspection 03/03/2016
33 03 10 Bypass Pumping of Existing Sewer Systems 12/20/2012
33 04 10 Joint Bonding and Electrical Isolation 12/20/2012
33 04 11 Corrosion Control Test Stations 12/20/2012
33 04 12 Magnesium Anode Cathodic Protection System 12/20/2012
33 04 30 Temporary Water Services 07/01/2011
33 04 40 Cleaning and Acceptance Testing of Water Mains 02/06/2013
33 04 50 Cleaning of Sewer Mains 12/20/2012
33 05 10 Utility Trench Excavation, Embedment, and Backfill 12/12/2016
33 05 12 Water Line Lowering 12/20/2012
33 05 13 Frame, Cover and Grade Rings – Cast Iron 01/22/2016
33 05 13.10 Frame, Cover and Grade Rings – Composite 01/22/2016
33 05 14 Adjusting Manholes, Inlets, Valve Boxes, and Other Structures to
Grade 12/20/2012
33 05 16 Concrete Water Vaults 12/20/2012
33 05 17 Concrete Collars 12/20/2012
33 05 20 Auger Boring 12/20/2012
33 05 21 Tunnel Liner Plate 12/20/2012
33 05 22 Steel Casing Pipe 12/20/2012
33 05 23 Hand Tunneling 12/20/2012
33 05 24 Installation of Carrier Pipe in Casing or Tunnel Liner Plate 06/19/2013
33 05 26 Utility Markers/Locators 12/20/2012
33 05 30 Location of Existing Utilities 12/20/2012
33 11 05 Bolts, Nuts, and Gaskets 12/20/2012
33 11 10 Ductile Iron Pipe 12/20/2012
33 11 11 Ductile Iron Fittings 12/20/2012
33 11 12 Polyvinyl Chloride (PVC) Pressure Pipe 11/16/2018
33 11 13 Concrete Pressure Pipe, Bar-Wrapped, Steel Cylinder Type 12/20/2012
33 11 14 Buried Steel Pipe and Fittings 12/20/2012
33 12 10 Water Services 1-inch to 2-inch 02/14/2017
33 12 11 Large Water Meters 12/20/2012
33 12 20 Resilient Seated Gate Valve 12/20/2012
33 12 21 AWWA Rubber-Seated Butterfly Valves 12/20/2012
33 12 25 Connection to Existing Water Mains 02/06/2013
33 12 30 Combination Air Valve Assemblies for Potable Water Systems 12/20/2012
33 12 40 Fire Hydrants 01/03/2014
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 5 of 6
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN:103920
Revised March 20, 2020
33 12 50 Water Sample Stations 12/20/2012
33 12 60 Standard Blow-off Valve Assembly 06/19/2013
33 31 12 Cured in Place Pipe (CIPP) 12/20/2012
33 31 13 Fiberglass Reinforced Pipe for Gravity Sanitary Sewers 12/20/2012
33 31 15 High Density Polyethylene (HDPE) Pipe for Sanitary Sewer 12/20/2012
33 31 20 Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe 06/19/2013
33 31 21 Polyvinyl Chloride (PVC) Closed Profile Gravity Sanitary Sewer
Pipe 12/20/2012
33 31 22 Sanitary Sewer Slip Lining 12/20/2012
33 31 23 Sanitary Sewer Pipe Enlargement 12/20/2012
33 31 50 Sanitary Sewer Service Connections and Service Line 04/26/2013
33 31 70 Combination Air Valve for Sanitary Sewer Force Mains 12/20/2012
33 39 10 Cast-in-Place Concrete Manholes 12/20/2012
33 39 20 Precast Concrete Manholes 12/20/2012
33 39 30 Fiberglass Manholes 12/20/2012
33 39 40 Wastewater Access Chamber (WAC) 12/20/2012
33 39 60 Epoxy Liners for Sanitary Sewer Structures 12/20/2012
33 41 10 Reinforced Concrete Storm Sewer Pipe/Culverts 07/01/2011
33 41 11 High Density Polyethylene (HDPE) Pipe for Storm Drain 12/20/2012
33 41 12 Reinforced Polyethlene (SRPE) Pipe 11/13/2015
33 46 00 Subdrainage 12/20/2012
33 46 01 Slotted Storm Drains 07/01/2011
33 46 02 Trench Drains 07/01/2011
33 49 10 Cast-in-Place Manholes and Junction Boxes 12/20/2012
33 49 20 Curb and Drop Inlets 12/20/2012
33 49 40 Storm Drainage Headwalls and Wingwalls 07/01/2011
Division 34 - Transportation
34 41 10 Traffic Signals 10/12/2015
34 41 10.01 Attachment A – Controller Cabinet 12/18/2015
34 41 10.02 Attachment B – Controller Specification 02/2012
34 41 10.03 Attachment C – Software Specification 01/2012
34 41 11 Temporary Traffic Signals 11/22/2013
34 41 13 Removing Traffic Signals 12/20/2012
34 41 15 Rectangular Rapid Flashing Beacon 11/22/2013
34 41 16 Pedestrian Hybrid Signal 11/22/2013
34 41 20 Roadway Illumination Assemblies 12/20/2012
34 41 20.01 Arterial LED Roadway Luminaires 06/15/2015
34 41 20.02 Freeway LED Roadway Luminaires 06/15/2015
34 41 20.03 Residential LED Roadway Luminaires 06/15/2015
34 41 30 Aluminum Signs 11/12/2013
34 41 50 Single-Mode Fiber Optic Cable 02/26/2016
34 71 13 Traffic Control 11/22/2013
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 6 of 6
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN:103920
Revised March 20, 2020
Appendix
GC-4.01 Availability of Lands
GC-4.02 Subsurface and Physical Conditions
GC-4.04 Underground Facilities
GC-4.06 Hazardous Environmental Condition at Site
GC-6.06.D Minority and Women Owned Business Enterprise Compliance
GC-6.07 Wage Rates
GC-6.09 Permits and Utilities
GC-6.24 Nondiscrimination
GR-01 60 00 Product Requirements
END OF SECTION
02/23/2022
00 45 11 - 1
BIDDERS PREQUALIFICATIONS
Page 1 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS [Insert Project Number]
Revised April 2, 2014
SECTION 00 45 11
BIDDERS PREQUALIFICATIONS
1. Summary. All contractors are required to be prequalified by the City prior to submitting
bids. To be eligible to bid the contractor must submit Section 00 45 12, Prequalification
Statement for the work type(s) listed with their Bid. Any contractor or subcontractor who is
not prequalified for the work type(s) listed must submit Section 00 45 13, Bidder
Prequalification Application in accordance with the requirements below.
The prequalification process will establish a bid limit based on a technical evaluation and
financial analysis of the contractor. The information must be submitted seven (7) days prior
to the date of the opening of bids. For example, a contractor wishing to submit bids on
projects to be opened on the 7th of April must file the information by the 31st day of March
in order to bid on these projects. In order to expedite and facilitate the approval of a Bidder’s
Prequalification Application, the following must accompany the submission.
a. A complete set of audited or reviewed financial statements.
(1) Classified Balance Sheet
(2) Income Statement
(3) Statement of Cash Flows
(4) Statement of Retained Earnings
(5) Notes to the Financial Statements, if any
b. A certified copy of the firm’s organizational documents (Corporate Charter, Articles
of Incorporation, Articles of Organization, Certificate of Formation, LLC
Regulations, Certificate of Limited Partnership Agreement).
c. A completed Bidder Prequalification Application.
(1) The firm’s Texas Taxpayer Identification Number as issued by the Texas
Comptroller of Public Accounts. To obtain a Texas Taxpayer Identification
number visit the Texas Comptroller of Public Accounts online at the
following web address www.window.state.tx.us/taxpermit/ and fill out the
application to apply for your Texas tax ID.
(2) The firm’s e-mail address and fax number.
(3) The firm’s DUNS number as issued by Dun & Bradstreet. This number
is used by the City for required reporting on Federal Aid projects. The DUNS
number may be obtained at www.dnb.com.
d. Resumes reflecting the construction experience of the principles of the firm for firms
submitting their initial prequalification. These resumes should include the size and
scope of the work performed.
e. Other information as requested by the City.
2. Prequalification Requirements
a. Financial Statements. Financial statement submission must be provided in
accordance with the following:
(1) The City requires that the original Financial Statement or a certified copy
be submitted for consideration.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
00 45 11 - 2
BIDDERS PREQUALIFICATIONS
Page 2 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS [Insert Project Number]
Revised April 2, 2014
(2) To be satisfactory, the financial statements must be audited or reviewed
by an independent, certified public accounting firm registered and in
good standing in any state. Current Texas statues also require that
accounting firms performing audits or reviews on business entities within
the State of Texas be properly licensed or registered with the Texas State
Board of Public Accountancy.
(3) The accounting firm should state in the audit report or review whether
the contractor is an individual, corporation, or limited liability company.
(4) Financial Statements must be presented in U.S. dollars at the current rate
of exchange of the Balance Sheet date.
(5) The City will not recognize any certified public accountant as
independent who is not, in fact, independent.
(6) The accountant’s opinion on the financial statements of the contracting
company should state that the audit or review has been conducted in
accordance with auditing standards generally accepted in the United
States of America. This must be stated in the accounting firm’s opinion.
It should: (1) express an unqualified opinion, or (2) express a qualified
opinion on the statements taken as a whole.
(7) The City reserves the right to require a new statement at any time.
(8) The financial statement must be prepared as of the last day of any month,
not more than one year old and must be on file with the City 16 months
thereafter, in accordance with Paragraph 1.
(9) The City will determine a contractor’s bidding capacity for the purposes
of awarding contracts. Bidding capacity is determined by multiplying the
positive net working capital (working capital = current assets – current
liabilities) by a factor of 10. Only those statements reflecting a positive
net working capital position will be considered satisfactory for
prequalification purposes.
(10) In the case that a bidding date falls within the time a new financial
statement is being prepared, the previous statement shall be updated with
proper verification.
b. Bidder Prequalification Application. A Bidder Prequalification Application must be
submitted along with audited or reviewed financial statements by firms wishing to be
eligible to bid on all classes of construction and maintenance projects. Incomplete
Applications will be rejected.
(1) In those schedules where there is nothing to report, the notation of
“None” or “N/A” should be inserted.
(2) A minimum of five (5) references of related work must be provided.
(3) Submission of an equipment schedule which indicates equipment under
the control of the Contractor and which is related to the type of work for
which the Contactor is seeking prequalification. The schedule must
include the manufacturer, model and general common description of
each piece of equipment. Abbreviations or means of describing
equipment other than provided above will not be accepted.
3. Eligibility to Bid
a. The City shall be the sole judge as to a contractor’s prequalification.
b. The City may reject, suspend, or modify any prequalification for failure by the
contractor to demonstrate acceptable financial ability or performance.
c. The City will issue a letter as to the status of the prequalification approval.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
00 45 11 - 3
BIDDERS PREQUALIFICATIONS
Page 3 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS [Insert Project Number]
Revised April 2, 2014
d. If a contractor has a valid prequalification letter, the contractor will be eligible to bid
the prequalified work types until the expiration date stated in the letter.
END OF SECTION
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
02/23/2022
SECTION 00 45 13
PREQUALIFICATION APPLICATION
Date of Balance Sheet ,
Mark only one:
Individual
Limited Partnership
General Partnership
Corporation
Limited Liability Co mpany
Post Office Box City State Zip Code
Street Address (required) City State Zip Code
( ) ( )
Telephone Fax Email
Texas Taxpayer Identification No.
Federal Employers Identification No.
DUNS No. (if applicable)
Email/mail this questionnaire along with financial statements to the appropriate group below . A separate submittal is required for water/sewer, paving, and lighting:
Work Category – Water Dept - Water/sewer Work Category – TPW Paving Work Category – T PW Ped/Rdwy Lighting
john.kasavich@FortWorthTexas.gov Alicia.Garcia@fortworthtexas.gov clint.hoover@fortworthtexas.gov
Fort Worth Water Department Engineering and
Fiscal Services Division 200 Texas St. Fort
Worth, TX 76102
City of Fort Worth Transportation and Public
Works Dept. 8851 Camp Bowie West Blvd. Fort
Worth, Texas 76116 Attn: Alicia Garcia
City of Fort Worth TPW Transportation
Management Attn: Clint Hoover, P.E. 5001
James Ave. Fort Worth, TX 76115
*Financial Statements must be mailed. Mark the envelope: “Bidder Prequalification Application”
Name under which you wish to qualify
00 45 13 - 2
BIDDER PREQUALIFICATION APPLICATION
Page 2 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS [Insert Project Number]
Revised August 13, 2021
BUSINESS CLASSIFICATION
The following should be completed in order that we may properly classify your firm:
(Check the block(s) which are applicable – Block 3 is to be left blank if Block 1 and/or Block 2 is
checked)
Has fewer than 100 employees
and/or
Has less than $6,000,000.00 in annual gross receipts
OR
Does not meet the criteria for being designated a small business as provided in Section
2006.001 of the Texas Government Code.
The classification of your firm as a small or large business is not a factor in determining eligibility to
become prequalified.
Select major work categories for which you would like to be prequalified (City may deem you are not
qualified for selected category or may approve you at a lesser size/length and maximum size may
not be listed specifically under a major work category):
MAJOR WORK CATEGORIES
Water Department
Augur Boring - 24-inch diameter casing and less
Augur Boring - Greater than 24-inch diameter casing and greater
Tunneling – 36-Inches – 60 –inches, and 350 LF or less
Tunneling - 36-Inches – 60 –inches, and greater than 350 LF
Tunneling – 66” and greater, 350 LF and greater
Tunneling – 66” and greater, 350 LF or Less
Cathodic Protection
Water Distribution, Development, 8-inch diameter and smaller
Water Distribution, Urban and Renewal, 8-inch diameter and smaller
Water Distribution, Development, 12-inch diameter and smaller
Water Distribution, Urban and Renewal, 12-inch diameter and smaller
Water Transmission, Development, 24-inches and smaller
Water Transmission, Urban/Renewal, 24-inches and smaller
Water Transmission, Development, 42-inches and smaller
Water Transmission, Urban/Renewal, 42-inches and smaller
Water Transmission, Development, All Sizes
Water Transmission, Urban/Renewal, All Sizes
Sewer Bypass Pumping, 18-inches and smaller
Sewer Bypass Pumping, 18-inches – 36-inches
Sewer Bypass Pumping 42-inches and larger
CCTV, 8-inches and smaller
CCTV, 12-inches and smaller
CCTV, 18-inches and smaller
CCTV, 24-inches and smaller
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
00 45 13 - 3
BIDDER PREQUALIFICATION APPLICATION
Page 3 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS [Insert Project Number]
Revised August 13, 2021
MAJOR WORK CATEGORIES, CONTINUED
CCTV, 42-inches and smaller
CCTV, 48-inches and smaller
Sewer CIPP, 12-inches and smaller
Sewer CIPP, 24-inches and smaller
Sewer CIPP, 42-inches and smaller
Sewer CIPP, All Sizes
Sewer Collection System, Development, 8-inches and smaller
Sewer Collection System, Urban/Renewal, 8-inches and smaller
Sewer Collection System, Development, 12-inches and smaller
Sewer Collection System, Urban/Renewal, 12-inches and smaller
Sewer Interceptors, Development, 24-inches and smaller
Sewer Interceptors, Urban/Renewal, 24-inches and smaller
Sewer Interceptors, Development, 42-inches and smaller
Sewer Interceptors, Urban/Renewal, 42-inches and smaller
Sewer Interceptors, Development, 48-inches and smaller
Sewer I nterceptors, Urban/Renewal, 48-inches and smaller
Sewer Pipe Enlargement 12-inches and smaller
Sewer Pipe Enlargement 24-inches and smaller
Sewer Pipe Enlargement, All Sizes
Sewer Cleaning , 24-inches and smaller
Sewer Cleaning , 42-inches and s maller
Sewer Cleaning , All Sizes
Sewer Cleaning, 8-inches and smaller
Sewer Cleaning, 12-inches and smaller
Sewer Siphons 12-inches or less
Sewer Siphons 24-inches or less
Sewer Siphons 42-inches or less
Sewer Siphons All Sizes
Transportation Public Works
Asphalt Paving Construction/Reconstruction (LESS THAN 15,000 square yards)
Asphalt Paving Construction/Reconstruction (15,000 square yards and GREATER)
Asphalt Paving Heavy Maintenance (UNDER $1,000,000)
Asphalt Paving Heavy Maintenance ($1,000,000 and OVER)
Concrete Paving Construction/Reconstruction (LESS THAN 15,000 square yards)*
Concrete Paving Construction/Reconstruction (15,000 square yards and GREATER)*
Roadway and Pedestrian Lighting
NOTE *There is not a prequalific ation requirement for installation of concrete sidewalk, curb & gutter,
driveways, and panel replacement, only concrete paving
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
00 45 13 - 4
BIDDER PREQUALIFICATION APPLICATION
Page 4 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS [Insert Project Number]
Revised August 13, 2021
1. List equipment you do not own but which is available by renting
DESCRIPTION OF EQUIPMENT NAME AND DETAILED ADDRESS OF OWNER
2. How many years has your organization been in business as a general contractor under your present
name?
List previous business names:
3. How many years of experience in construction work has your organization had:
(a) As a General Contr actor: (b) As a Sub-Contractor:
4. *What projects has your organization completed in Texas and elsewhere?
CONTRACT
AMOUNT
CLASS
OF
WORK
DATE
COMPLETED
LOCATION
CITY-COUNTY-
STATE
NAME AND DETAILED
ADDRESS OF OFFICIAL TO
WHOM YOU REFER
*If requalifying only show work performed since last statement.
5. Have you ever failed to complete any work awarded to you?
If so, where and why?
6. Has any officer or owner of your organization ever been an officer of another organization that failed to
complete a contract?
If so, state the name of the individual, other organization and reason.
7. Has any officer or owner of your organization ever failed to complete a contract executed in his/her
name?
If so, state the name of the individual, name of owner and reason.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
00 45 13 - 5
BIDDER PREQUALIFICATION APPLICATION
Page 5 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS [Insert Project Number]
Revised August 13, 2021
8. In what other lines of business are you financially interested?
9. Have you ever performed any work for the City?
If so, when and to whom do you refer?
10. State names and detailed addresses of all producers fr om whom you have purchased principal
materials during the last three years.
NAME OF FIRM OR COMPANY DETAILED ADDRESS
11. Give the names of any affiliates or relatives currently debarred by the City. Indicate your relationship
to this person or firm.
12. What is the construction experience of the principal individuals in your organization?
NAME
PRESENT
POSITION OR
OFFICE
YEARS OF
EXPERIENCE
MAGNITUDE
AND TYPE OF
WORK
IN WHAT
CAPACITY
13. If any owner, of ficer, director, or stockholder of your firm is an employee of the City, or shares the same household with a City employee, please list the name of the City employee and the relationship. In
addition, list any City employee who is the spouse, child, or parent of an owner, officer, stockholder, or
director who does not live in the same household but who receives care and assistance from that person as
a direct result of a documented medical condition. This includes foster children or those related by
adoption or marriage.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
00 45 13 - 6
BIDDER PREQUALIFICATION APPLICATION
Page 6 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS [Insert Project Number]
Revised August 13, 2021
CORPORATION BLOCK PARTNERSHIP BLOCK
If a corporation: If a partnership:
Date of Incorporation State of Organization
Charter/File No. Date of organization
President Is partnership general, limited, or registered limited
lia bility partnership?
Vice Presidents
File No. (if Limited
Partnership)
General Partners/Officers
Secretary Limited Partners (if applicable)
Treasurer
LIMITED LIABILITY COMPANY BLOCK
If a corporation:
State of Incorporation
Date of organization
File No. Individuals authorized to sign for Partnership
Officers or Managers (with titles, if any)
Except for limited partners, the individuals listed in the blocks above are presumed to have full
signature authority for your firm unless otherwise advised. Should you wish to grant signature authority for additional individuals, please attach a certified copy of the corporate resolution,
corporate minutes, partnership agreement, power of attorney or other legal documentation which
grants this authority.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
00 45 13 - 7
BIDDER PREQUALIFICATION APPLICATION
Page 7 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS [Insert Project Number]
Revised August 13, 2021
14. Equipment $_______________
TOTAL
Similar types of equipment may be lumped together. If your firm has more than 30 types of equipment, you may show these 30 types and show the remainder as "various". The City, by allowing you to show
only 30 types of equipment, reserves the right to request a complete, detailed list of all your equipment.
The equipment list is a representation of equipment under the control of the firm and which is related to
the type of work for which the firm is seeking qualification. In the description include, the manufacturer,
model, and general common description of each.
ITEM QUANTITY ITEM DESCRIPTION BALANCE SHEET VALUE
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Various-
TOTAL
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
00 45 13 - 8
BIDDER PREQUALIFICATION APPLICATION
Page 8 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS [Insert Project Number]
Revised August 13, 2021
BIDDER PREQUALIFICATION AFFIDAVIT
STATE OF
COUNTY OF
The undersigned hereby declares that the foregoing is a true statement of the financial condition of the
entity herein first named, as of the date herein first given; that this statement is for the express purpose of
inducing the party to whom it is submitted to award the submitter a contract; and that the accountant who
prepared the balance sheet accompanying this report as w ell as any depository, vendor or any other
agency herein named is hereby authorized to supply each party with any information, while this statement
is in force, necessary to verify said statement.
_______________________________________________, being duly sworn, deposes and says that
he/she is the __________________________________ of ___________________________, the entity
described in and which executed the foregoing statement that he/she is familiar with the books of the said
entity showing its financial condition; that the foregoing financial statement taken from the books of the
said entity as of the date thereof and that the answers to the questions of the foregoing Bidder Prequalification Application are correct and true as of the date of this affidavit.
Firm Name:
Signature:
Sworn to before me this
day of ,
Notary Public
Notary Public must not be an officer, director, or stockholder or relative thereof.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
23rd
February 22
00 52 43 - 1
Developer Awarded Project Agreement
Page 1 of 4
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN:103920
Revised June 16, 2016
SECTION 00 52 43 1
AGREEMENT 2
3
THIS AGREEMENT, authorized on ______________is made by and between the Developer, 4
(Insert Full Legal Name of Developer), authorized to do business in Texas (“Developer”) , and 5
______________________________________________________________, authorized to do 6
business in Texas, acting by and through its duly authorized representative, (“Contractor”). 7
Developer and Contractor, in consideration of the mutual covenants hereinafter set forth, agree as 8
follows: 9
Article 1. WORK 10
Contractor shall complete all Work as specified or indicated in the Contract Documents for the 11
Project identified herein. 12
Article 2. PROJECT 13
The project for which the Work under the Contract Documents may be the whole or only a part is 14
generally described as follows: 15
Karis Phase 1 – CFW Sanitary Sewer Connection_____________________________________ 16
CPN: 103920__________________________________________________________________ 17
Article 3. CONTRACT TIME 18
3.1 Time is of the essence. 19
All time limits for Milestones, if any, and Final Acceptance as stated in the Contract 20
Documents are of the essence to this Contract. 21
3.2 Final Acceptance. 22
The Work will be complete for Final Acceptance within {_14_} working days after the date 23
when the Contract Time commences to run as provided in Paragraph 12.04 of the Standard 24
City Conditions of the Construction Contract for Developer Awarded Projects. 25
3.3 Liquidated damages 26
Contractor recognizes that time is of the essence of this Agreement and that Developer 27
will suffer financial loss if the Work is not completed within the times specified in 28
Paragraph 3.2 above, plus any extension thereof allowed in accordance with Article 10 of 29
the Standard City Conditions of the Construction Contract for Developer Awarded 30
Projects. The Contractor also recognizes the delays, expense and difficulties involved in 31
proving in a legal proceeding the actual loss suffered by the Developer if the Work is not 32
completed on time. Accordingly, instead of requiring any such proof , Contractor agrees 33
that as liquidated damages for delay (but not as a penalty), Contractor shall pay 34
Developer Zero Dollars ($0.00) for each day that expires after the time specified in 35
Paragraph 3.2 for Final Acceptance until the City issues the Final Letter of Acceptance. 36
CH TNC KARIS OWNER, LLC__________
2/23/2022
SYB Construction Co., Inc.
00 52 43 - 2
Developer Awarded Project Agreement
Page 2 of 4
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN:103920
Revised June 16, 2016
Article 4. CONTRACT PRICE 38
Developer agrees to pay Contractor for performance of the Work in accordance with the Contract 39
Documents an amount in current funds of __________________________________Dollars 40
($___________________). 41
Article 5. CONTRACT DOCUMENTS 42
5.1 CONTENTS: 43
A. The Contract Documents which comprise the entire agreement between Developer and 44
Contractor concerning the Work consist of the following: 45
1. This Agreement. 46
2. Attachments to this Agreement: 47
a. Bid Form (As provided by Developer) 48
1) Proposal Form (DAP Version) 49
2) Prequalification Statement 50
3) State and Federal documents (project specific) 51
b. Insurance ACORD Form(s) 52
c. Payment Bond (DAP Version) 53
d. Performance Bond (DAP Version) 54
e. Maintenance Bond (DAP Version) 55
f. Power of Attorney for the Bonds 56
g. Worker’s Compensation Affidavit 57
h. MBE and/or SBE Commitment Form (If required) 58
3. Standard City General Conditions of the Construction Contract for Developer 59
Awarded Projects. 60
4. Supplementary Conditions. 61
5. Specifications specifically made a part of the Contract Documents by attachment 62
or, if not attached, as incorporated by reference and described in the Table of 63
Contents of the Project’s Contract Documents. 64
6. Drawings. 65
7. Addenda. 66
8. Documentation submitted by Contractor prior to Notice of Award. 67
9. The following which may be delivered or issued after the Effective Date of the 68
Agreement and, if issued, become an incorporated part of the Contract Documents: 69
a. Notice to Proceed. 70
b. Field Orders. 71
c. Change Orders. 72
d. Letter of Final Acceptance. 73
74
75
TWENTY TWO THOUSAND AND EIGHT HUNDRED SEVENTY NINE
22,879.00
00 52 43 - 3
Developer Awarded Project Agreement
Page 3 of 4
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN:103920
Revised June 16, 2016
Article 6. INDEMNIFICATION 76
6.1 Contractor covenants and agrees to indemnify, hold harmless and defend, at its own 77
expense, the city, its officers, servants and employees, from and against any and all 78
claims arising out of, or alleged to arise out of, the work and services to be performed 79
by the contractor, its officers, agents, employees, subcontractors, licenses or invitees 80
under this contract. This indemnification provision is specifically intended to operate 81
and be effective even if it is alleged or proven that all or some of the damages being 82
sought were caused, in whole or in part, by any act, omission or negligence of the city. 83
This indemnity provision is intended to include, without limitation, indemnity for 84
costs, expenses and legal fees incurred by the city in defending against such claims and 85
causes of actions. 86
87
6.2 Contractor covenants and agrees to indemnify and hold harmless, at its own expense, 88
the city, its officers, servants and employees, from and against any and all loss, damage 89
or destruction of property of the city, arising out of, or alleged to arise out of, the work 90
and services to be performed by the contractor, its officers, agents, employees, 91
subcontractors, licensees or invitees under this contract. This indemnification 92
provision is specifically intended to operate and be effective even if it is alleged or 93
proven that all or some of the damages being sought were caused, in whole or in part, 94
by any act, omission or negligence of the city. 95
96
Article 7. MISCELLANEOUS 97
7.1 Terms. 98
Terms used in this Agreement are defined in Article 1 of the Standard City Conditions of 99
the Construction Contract for Developer Awarded Projects. 100
7.2 Assignment of Contract. 101
This Agreement, including all of the Contract Documents may not be assigned by the 102
Contractor without the advanced express written consent of the Developer. 103
7.3 Successors and Assigns. 104
Developer and Contractor each binds itself, its partners, successors, assigns and legal 105
representatives to the other party hereto, in respect to all covenants, agreements and 106
obligations contained in the Contract Documents. 107
7.4 Severability. 108
Any provision or part of the Contract Documents held to be unconstitutional, void or 109
unenforceable by a court of competent jurisdiction shall be deemed stricken, and all 110
remaining provisions shall continue to be valid and binding upon DEVELOPER and 111
CONTRACTOR. 112
7.5 Governing Law and Venue. 113
This Agreement, including all of the Contract Documents is performable in the State of 114
Texas. Venue shall be Tarrant County, Texas, or the United States District Court for the 115
Northern District of Texas, Fort Worth Division. 116
02/23/2022 02/23/2022
��
THE HANOVERINSURANCE COMPANY
MASSACHUSETTS BAYINSURANCE COMPANY
CITIZENS INSURANCE COMPANY OF AMERICA
POWER OF ATTORNEY
t" th manner and to the
�
�
I
THIS Power of Attorney limits the acts of those named herein, and they have no authority to bind the Company excep in e
extent herein stated.
KNOW ALL PERSONS BY THESE PRESENTS:
of the State of New Halmp hRe and CIOT Z NS INSURANCE COMPANY O AIMER CA, a corpoMat on organ zedn nd existin'g under the laws of the S ate of M cli gan,
(hereinafter Individually and collectively the "Compan�i') does hereby constitute and appoint,
Steven R. Foster, Jac6c M. Crowley, Laurrie P91ug , and Teuia Luri
Of Vlrllis Towers Watson insurance Services West, Inc of Dallas, TX each individuaily, if there be more than'one named, as its true and lawFui attorney(s)-in-
fact to sign, execute, seal, acknowledge and deliver for, and on its behalf, and as its act and deed any place within the United States, any and all surety bonds,
reesent ashall be asrbinding�upon the Co pany as, f they had been1duly signed by the president and attested by heksec retary of the ICompany, n thea own proper
p
persons. Provided however, that this power of attorney limits the acts of those named herein; and they have no authoriry to bind the Company except in t e manner
stated and to the extent of any limitation stated below:
Any such obligations in the United States, not to exceed Thirty Five Million and No1100 ($35,000,000) in any single instance
That this power ls made and executed pursuant to the authority of the following Resolutions passed by the Board of Directors of said Company, and said Resolutions
remain in full force and effect:
RESOLVED: That the President or any Vice President, in conjunction with any Vice President, be and they hereby are authorized and empowered to
appoint Attorneys-in-fact of the Company, In its name and as It acts, to execute and acknowledge for and on its behaif as surety,�any and all bonds,
recognizances, contracts of indemnity, waivers of citation and all other writings obligatory in the nature thereof, with power to attach thereto the seal of the
Company. Any such writings so executed by such Attorneys-In-fact shall be binding upon the Companyas if they had been duly executed and acknowledged
by the regularly elected officers of the Company in their own proper persons.
RESOLVED: That any and all Powers of Attorney and Certified Copies of such Powers of Attorney and certiflcation In respectthereto, granted and executed
by the President or Uce President In conjunction with any Vice President of the Company, shall be binding on the Company to the same extent as if all
signatures therein were manualiy affixed, even though one or more of any such signatures thereon may be facsimile. (Adopted October 7, 1981 — The
Hanover Insurance Company; Adopted April 14, 1982 — Massachusetts Bay Insurance Company; Adopted Sepfembar 7, 2001 — Citizens Insurance
Company of America and affirmed by each Company on March 24, 2014)
IN WITN ESS WH EREOF, THE HANOVER INSURANCE COMPANY, MASSACHUSETTS BAY INSURANCE COMPANYand CITIZENS INSURANCE COMPANY OF
AMERICA have caused these presents to be sealed with thelr respective corporate seals, duly att��s�t ��b� �o V�i'e��PUP��� G�����Yy of January, 2020.
i lH6 HAPlOV�:2 PIdSU � COt�lPf�N � f�9,4�S�kC�'�5��`i�a �AY fPi�URAN�� GCl1VIP6kiiaY
MAfiS#4GF]US�TT^a i' 1"s!lRAN�� �t3fdfF`�!'3Y C',1TI� Na i4s}�Ui�AN�� Gf�MFA►dY OP I�tPAE�C�
GI'�ITFIti$ i(��URAt�� ��RAP�NY OF l�N1ER4CA a i i � .
Presldent
r'a�r�-n•'
�'�"a`�
s S�.'1 a (3\�`,�,�; �£1
.n� �,�...
�� ,��
THE COMMONWEALTH OF MASSACHUSETTS )
COUNTYOF WORCESTER ) ss.
Massachu�setts Bay Insu ance ompanyand Cit zens Insurance Company of Ameri aeto me pers nally known to be the ndiv'duals and officersldescribed he�e n and
acknowledged Yhat the seals a�xed to the preceding instrument are the corporate seals of The Hanover insurance Company, Massachusetts Bay Insurance Company
and Citizens Insurance Company of America, respectively, and thatthe said corporate seals and their signatures as officers were duly affixedaand subscribed to said
instrument by the authority and direction of said Cornorations.
GIVEN under my hand and the seals of said Companies, at Worcester, Massachusetts, this day of
� ' • ----1—
nns� raoiQ� �� o
Arl�en V• Sim r r
li4y �ommis��on Expires June 15, 2A2�
June ,
I, the undersigned Vice President of The Hanover Insurance Company, Massachusetts Bay Insurance Companyand Cilizens Insurance Company of America, hereby
certify that the above and foregoing is a full, true and correct copy of the Original Power of Attorney issued by said Companies, and do hereby further certify that the
said Powars of Attorney are still in force and effect.
� A�il.�Efil V. 59i+hQRlS
¢_ Malafy Public
��CONiM9�v'rALTri 0F MASSACHUSEt7S
�qy CommissSqn Expires
'S5 2033
�ERTIFIE� ����
rv�e • .� . . .
SH� FtsMQVER 1615UPJ;NC� ��h7PA[dY
t�� aoHus� � rs e�av �ws►a�rac� con�P�Nv
IZ NS tNSURA _NCE C4MPMNY �F F+h7ERICA
% r� � �'• . ' . ._
�• -Carrielc A. B��9h� / 'sident
� '1he
� Hanover The Hanovee Insurance Compeny � A�10 Lincoln Streek Worcester, MA 01653
p Insurance Group° Gtiz�s Insurance Company of Ame�ica � 645 West Grand Rtver Avenue, Howell, MI 48843 Texas Compl�int Notice
IMPORiANT IVOTICE
io obtain information or make a complaint:
You may call ihe Hanover Insurance Company/Citizens
Insurance Company of America's toll-free telephone
number for information or to make a complaint at:
AVISO IMPORTANTE
Para obtener in#ormacian o para somefer uh� queja.:
Usted puede Ilamar al numero de telefono gratis de The
Hanover Insurance Company/Citizens Insurance Company
of America's para informacion o para someter una queja al:
1�800�60���141
You may also write to The Hanover Insurance Company/
Citizens Insurance Company of America at:
440 Lincoln Street
Worcester, MA 01615
You may contact the Texas Department of. Insurance to
obtain information on companies, coverages, rights or
complaints at:
1��00-252-3439
You may write the %xas Department of Insurance:
P. O. Box 149104
Austin, TX 78714-9104
Fax: (512) 475-1771
Web: http://www.tdi.texas.gov
E-mail: ConsumerProtection@tdi.state.tx.us
PREMIUM OR CLAIM DISPUTES:
Should you have a dispute conceming your premium or
about a claim you should contact the agent or the com-
pany �irst, If the dispute is not resolved, you may contact
the Texas Department of lnsurance,
q'IiACW THIS NOiICE i01POUR POLICY: This notice is
for information only and does not become a part or con-
dition of the attached document.
1-800�60��8141
Usted ta�nbien puede escribir a. The I�a.nc�,'er ��su� a.nce
Company/Citizens Insurance Company of America al:
440 Lincoln Street
Worcester, MA 01615
Puede comunicarse con el Departamento de Seguros de
Texas para obtener informacion acerca de companias,
coberturas, derechos o quejas al:
1 ��00�252�3439
Puede escribir al Departamento de Seguros de iexas:
P. O. Box 149104
Austin, TX 7�714-9104
Fax: (512) 475-1771
Web: http://www.tdi.texas.gov
E-mail: ConsumerProfiection@tdi.��a.te.tic.u5
DISPUTAS SO�RE PRIMAS O RECLAMOS:
Si tiene una disputa concemiente a su prima o a un reo-
lamo, debe comunicarse con el agente o la compania
primero. Si no se resuelve la disputa, puede entonces
comunicarse con el departamento (TDI).
UNA ESTE Ai/IS0 A S!J POLIZA: Este aviso es solo para
proposito de informacion y no se convierte en parte o
condicion del documento adjunto.
� Ai.1 dF] IF/1 �T
CFA22-0056
February 2224th
24th
February 22
�
2
3
4
5
6
7
10
11
12
� � .� C
Wit�iess as to Sarety
006213-3
PERFORMANCE BOND
Pnge 3 of 3
Telephone Number: 9�2'385-9800
*Note: If signed by an officer of the Surety Company, there must be on file a certified extract
from the by-laws showing that this person has authoriTy to sign such obligation. If
Surety's physical address is different from its mailing address, both must be provided,
The date of the bond shall not be prior to the date the Contract is awarded.
CI1'Y OF FORT WORTH Karis Phase I- CFW Sanl�a�y Seiver Connectlon
STANDARD CITY CONDITTONS — DEVELOPER AWARDED PROJECTS CPN.•103920
Revised Jenusry 31, 2012
CFA22-0056
24th February 22
February 22
24th
CFA22-0056
24th February 22
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
006219-2
MAINTENANCE BOND
Page 2 of 3
WHEREAS, Principal binds itself to repair or reconstruct the Work in whole or in part
upon receiving notice from the Developer and/or City of the need thereof at any time within the
Maintenance Period.
NOW THEREFORE, the condition of this obligation is such that if Principal shall
remedy any defective Work, for which timely notice was provided by Developer or City, to a
completion satisfactory to the City, then this obligation sha11 become null and void; otherwise to
remain in full force and effect.
PROVIDED, HOWEVER, if Priucipal shall fail so to repair or reconstnict any timely
noticed defective Work, it is agreed that the Developer or City may cause any and all such
defective Work to be repaired and/or reconstructed witli all associated costs thereof being borne
by the Principal and the Surety under this Maintenance Bond; and
PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in
Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort
Worth Division; and
PROVIDED FURTHER, that this obligation shall be continuous in nature and
successive recoveries may be had hereon for successive breaches.
CITY OF FORT W ORTH Karis Phase 1- CFW Sanitnry Sewer Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN:103920
Revised January 31, 2012
February 22
24th
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
STANDARD CITY CONDITIONS
OF THE CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
STANDARD CITY CONDITIONS OF THE
CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
TABLE OF CONTENTS
Page
Article 1 – Definitions and Terminology .......................................................................................................... 1
1.01 Defined Terms ............................................................................................................................... 1
1.02 Terminology .................................................................................................................................. 5
Article 2 – Preliminary Matters ......................................................................................................................... 6
2.01 Before Starting Construction ........................................................................................................ 6
2.02 Preconstruction Conference .......................................................................................................... 6
2.03 Public Meeting .............................................................................................................................. 6
Article 3 – Contract Documents and Amending ............................................................................................... 6
3.01 Reference Standards ..................................................................................................................... 6
3.02 Amending and Supplementing Contract Documents .................................................................. 6
Article 4 – Bonds and Insurance ....................................................................................................................... 7
4.01 Licensed Sureties and Insurers ..................................................................................................... 7
4.02 Performance, Payment, and Maintenance Bonds ........................................................................ 7
4.03 Certificates of Insurance ............................................................................................................... 7
4.04 Contractor’s Insurance .................................................................................................................. 9
4.05 Acceptance of Bonds and Insurance; Option to Replace ........................................................... 12
Article 5 – Contractor’s Responsibilities ........................................................................................................ 12
5.01 Supervision and Superintendent ................................................................................................. 12
5.02 Labor; Working Hours ................................................................................................................ 13
5.03 Services, Materials, and Equipment ........................................................................................... 13
5.04 Project Schedule .......................................................................................................................... 14
5.05 Substitutes and “Or-Equals” ....................................................................................................... 14
5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors) ..................................... 16
5.07 Concerning Subcontractors, Suppliers, and Others ................................................................... 16
5.08 Wage Rates.................................................................................................................................. 18
5.09 Patent Fees and Royalties ........................................................................................................... 19
5.10 Laws and Regulations ................................................................................................................. 19
5.11 Use of Site and Other Areas ....................................................................................................... 19
5.12 Record Documents ...................................................................................................................... 20
5.13 Safety and Protection .................................................................................................................. 21
5.14 Safety Representative ................................................................................................................. 21
5.15 Hazard Communication Programs ............................................................................................. 22
5.16 Submittals .................................................................................................................................... 22
5.17 Contractor’s General Warranty and Guarantee .......................................................................... 23
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
5.18 Indemnification ........................................................................................................................... 24
5.19 Delegation of Professional Design Services .............................................................................. 24
5.20 Right to Audit: ............................................................................................................................ 25
5.21 Nondiscrimination....................................................................................................................... 25
Article 6 – Other Work at the Site ................................................................................................................... 26
6.01 Related Work at Site ................................................................................................................... 26
Article 7 – City’s Responsibilities................................................................................................................... 26
7.01 Inspections, Tests, and Approvals .............................................................................................. 26
7.02 Limitations on City’s Responsibilities ....................................................................................... 26
7.03 Compliance with Safety Program ............................................................................................... 27
Article 8 – City’s Observation Status During Construction ........................................................................... 27
8.01 City’s Project Representative ..................................................................................................... 27
8.02 Authorized Variations in Work .................................................................................................. 27
8.03 Rejecting Defective Work .......................................................................................................... 27
8.04 Determinations for Work Performed .......................................................................................... 28
Article 9 – Changes in the Work ..................................................................................................................... 28
9.01 Authorized Changes in the Work ............................................................................................... 28
9.02 Notification to Surety .................................................................................................................. 28
Article 10 – Change of Contract Price; Change of Contract Time ................................................................ 28
10.01 Change of Contract Price ............................................................................................................ 28
10.02 Change of Contract Time............................................................................................................ 28
10.03 Delays .......................................................................................................................................... 28
Article 11 – Tests and Inspections; Correction, Removal or Acceptance of Defective Work ...................... 29
11.01 Notice of Defects ........................................................................................................................ 29
11.02 Access to Work ........................................................................................................................... 29
11.03 Tests and Inspections .................................................................................................................. 29
11.04 Uncovering Work ....................................................................................................................... 30
11.05 City May Stop the Work ............................................................................................................. 30
11.06 Correction or Removal of Defective Work ................................................................................ 30
11.07 Correction Period ........................................................................................................................ 30
11.08 City May Correct Defective Work ............................................................................................. 31
Article 12 – Completion .................................................................................................................................. 32
12.01 Contractor’s Warranty of Title ................................................................................................... 32
12.02 Partial Utilization ........................................................................................................................ 32
12.03 Final Inspection ........................................................................................................................... 32
12.04 Final Acceptance ......................................................................................................................... 33
Article 13 – Suspension of Work .................................................................................................................... 33
13.01 City May Suspend Work ............................................................................................................ 33
Article 14 – Miscellaneous .............................................................................................................................. 34
14.01 Giving Notice .............................................................................................................................. 34
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
14.02 Computation of Times ................................................................................................................ 34
14.03 Cumulative Remedies ................................................................................................................. 34
14.04 Survival of Obligations ............................................................................................................... 35
14.05 Headings ...................................................................................................................................... 35
00 73 10- 1
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 1 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 1 – DEFINITIONS AND TERMINOLOGY
1.01 Defined Terms
A. Wherever used in these General Conditions or in other Contract Documents, the terms listed
below have the meanings indicated which are applicable to both the singular and plural thereof,
and words denoting gender shall include the masculine, feminine and neuter. Said terms are
generally capitalized or written in italics, but not always. When used in a context consistent with
the definition of a listed-defined term, the term shall have a meaning as defined below whether
capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial
capital letters in the Contract Documents include references to identified articles and paragraphs,
and the titles of other documents or forms.
1. Agreement - The written instrument which is evidence of the agreement between Developer
and Contractor covering the Work
2. Asbestos—Any material that contains more than one percent asbestos and is friable or is
releasing asbestos fibers into the air above current action levels established by the United
States Occupational Safety and Health Administration.
3. Business Day – A business day is defined as a day that the City conducts normal business,
generally Monday through Friday, except for federal or state holidays observed by the City.
4. Buzzsaw – City’s on-line, electronic document management and collaboration system.
5. Calendar Day – A day consisting of 24 hours measured from midnight to the next midnight.
6. City— The City of Fort Worth, Texas, a Texas home-rule municipal corporation, acting by,
its governing body through its City Manager, his designee, or agents authorized pursuant to
its duly authorized charter on his behalf.
7. Community Facilities Agreement (CFA) -–A Contract between the Developer and the City
for the Construction of one or more following public facilities within the City public right-of-
way or easement: Water, Sanitary Sewer, Street, Storm Drain, Street Light, and Street Signs.
A CFA may include private facilities within the right-of-way dedicated as private right-of-
way or easement on a recorded plat.
8. Contract—The entire and integrated written document incorporating the Contract
Documents between the Developer, Contractor, and/or City concerning the Work. The
Contract supersedes prior negotiations, representations, or agreements, whether written or
oral.
9. Contract Documents—Those items that make up the contract and which must include the
Agreement, and it’s attachments such as standard construction specifications, standard City
Conditions, other general conditions of the Developer, including:
a. An Agreement
00 73 10- 2
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 2 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
b. Attachments to the Agreement
i. Bid Form
ii. Vendor Compliance with State Law Non-Resident Bidder
iii. Prequalification Statement
c. Current Prevailing Wage Rates Table (if required by City)
d. Insurance Accord Form
e. Payment Bond
f. Performance Bond
g. Maintenance Bond
h. Power of Attorney for Bonds
i. Workers Compensation Affidavit
j. MWBE Commitment Form( If required by City)
k. General Conditions
l. Supplementary Conditions
m. The Standard City Conditions
n. Specifications specifically made part of the Contract Documents by attachment, if
not attached, as incorporated by reference and described in the Table of Contents of
the Project’s Contract Documents
o. Drawings
p. Documentation submitted by contractor prior to Notice of Award.
q. The following which may be delivered or issued after the effective date if the
Agreement and, if issued become an incorporated part of the Contract Documents
i. Notice to Proceed
ii. Field Orders
iii. Change Orders
iv. Letters of Final Acceptance
r. Approved Submittals, other Contractor submittals, and the reports and drawings of
subsurface and physical conditions are not Contract Documents.
10. Contractor—The individual or entity with whom Developer has entered into the Agreement.
11. Day or day – A day, unless otherwise defined, shall mean a Calendar Day.
12. Developer – An individual or entity that desires to make certain improvements within the
City of Fort Worth
13. Drawings—That part of the Contract Documents prepared or approved by Engineer which
graphically shows the scope, extent, and character of the Work to be performed by
Contractor. Submittals are not Drawings as so defined.
14. Engineer—The licensed professional engineer or engineering firm registered in the State of
Texas performing professional services for the Developer.
15. Final Acceptance – The written notice given by the City to the Developer and/or Contractor
that the Work specified in the Contract Documents has been completed to the satisfaction of
the City.
00 73 10- 3
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 3 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
16. Final Inspection – Inspection carried out by the City to verify that the Contractor has
completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in
conformance with the Contract Documents.
17. General Requirements—A part of the Contract Documents between the Developer and a
Contractor.
18. Laws and Regulations—Any and all applicable laws, rules, regulations, ordinances, codes,
and orders of any and all governmental bodies, agencies, authorities, and courts having
jurisdiction.
19. Liens—Charges, security interests, or encumbrances upon Project funds, real property, or
personal property.
20. Milestone—A principal event specified in the Contract Documents relating to an
intermediate Contract Time prior to Final Acceptance of the Work.
21. Non-Participating Change Order—A document, which is prepared for and reviewed by the
City, which is signed by Contractor, and Developer, and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of the Agreement.
22. Participating Change Order—A document, which is prepared for and approved by the City,
which is signed by Contractor, Developer, and City and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of the Agreement.
23. Plans – See definition of Drawings.
24. Project Schedule—A schedule, prepared and maintained by Contractor, in accordance with
the General Requirements, describing the sequence and duration of the activities comprising
the Contractor’s plan to accomplish the Work within the Contract Time.
25. Project—The Work to be performed under the Contract Documents.
26. Project Representative—The authorized representative of the City who will be assigned to
the Site.
27. Public Meeting – An announced meeting conducted by the Developer to facilitate public
participation and to assist the public in gaining an informed view of the Project.
28. Regular Working Hours – Hours beginning at 7:00 a.m. and ending at 6:00 p.m., Monday
thru Friday (excluding legal holidays).
29. Samples—Physical examples of materials, equipment, or workmanship that are
representative of some portion of the Work and which establish the standards by which such
portion of the Work will be judged.
00 73 10- 4
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 4 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
30. Schedule of Submittals—A schedule, prepared and maintained by Contractor, of required
submittals and the time requirements to support scheduled performance of related
construction activities.
31. Site—Lands or areas indicated in the Contract Documents as being furnished by City or
Developer upon which the Work is to be performed, including rights-of-way, permits, and
easements for access thereto, and such other lands furnished by City or Developer which are
designated for the use of Contractor.
32. Specifications—That part of the Contract Documents consisting of written requirements for
materials, equipment, systems, standards and workmanship as applied to the Work, and
certain administrative requirements and procedural matters applicable thereto.
Specifications may be specifically made a part of the Contract Documents by attachment or,
if not attached, may be incorporated by reference as indicated in the Table of Contents
(Division 00 00 00) of each Project.
33. Standard City Conditions – That part of the Contract Documents setting forth requirements
of the City.
34. Subcontractor—An individual or entity having a direct contract with Contractor or with any
other Subcontractor for the performance of a part of the Work at the Site.
35. Submittals—All drawings, diagrams, illustrations, schedules, and other data or information
which are specifically prepared or assembled by or for Contractor and submitted by
Contractor to illustrate some portion of the Work.
36. Superintendent – The representative of the Contractor who is available at all times and able
to receive instructions from the City and/or Developer and to act for the Contractor.
37. Supplementary Conditions—That part of the Contract Documents which amends or
supplements the General Conditions.
38. Supplier—A manufacturer, fabricator, supplier, distributor, materialman, or vendor having
a direct contract with Contractor or with any Subcontractor to furnish materials or
equipment to be incorporated in the Work by Contractor or Subcontractor.
39. Underground Facilities—All underground pipelines, conduits, ducts, cables, wires,
manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any
encasements containing such facilities, including but not limited to, those that convey
electricity, gases, steam, liquid petroleum products, telephone or other communications,
cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or
other control systems.
40. Weekend Working Hours – Hours beginning at 9:00 a.m. and ending at 5:00 p.m., Saturday,
Sunday or legal holiday, as approved in advance by the City.
00 73 10- 5
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 5 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
41. Work—The entire construction or the various separately identifiable parts thereof required
to be provided under the Contract Documents. Work includes and is the result of performing
or providing all labor, services, and documentation necessary to produce such construction
including any Participating Change Order, Non-Participating Change Order, or Field
Order, and furnishing, installing, and incorporating all materials and equipment into such
construction, all as required by the Contract Documents.
42. Working Day – A working day is defined as a day, not including Saturdays, Sundays, or
legal holidays authorized by the City for contract purposes, in which weather or other
conditions not under the control of the Contractor will permit the performance of the
principal unit of work underway for a continuous period of not less than 7 hours between 7
a.m. and 6 p.m.
1.02 Terminology
A. The words and terms discussed in Paragraph 1.02.B through D are not defined but, when used in
the Bidding Requirements or Contract Documents, have the indicated meaning.
B. Defective:
1. The word “defective,” when modifying the word “Work,” refers to Work that is
unsatisfactory, faulty, or deficient in that it:
a. does not conform to the Contract Documents; or
b. does not meet the requirements of any applicable inspection, reference standard, test, or
approval referred to in the Contract Documents; or
c. has been damaged prior to City’s written acceptance.
C. Furnish, Install, Perform, Provide:
1. The word “Furnish” or the word “Install” or the word “Perform” or the word “Provide” or
the word “Supply,” or any combination or similar directive or usage thereof, shall mean
furnishing and incorporating in the Work including all necessary labor, materials, equipment,
and everything necessary to perform the Work indicated, unless specifically limited in the
context used.
D. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known
technical or construction industry or trade meaning are used in the Contract Documents in
accordance with such recognized meaning.
00 73 10- 6
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 6 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 2 – PRELIMINARY MATTERS
2.01 Before Starting Construction
Baseline Schedules: Submit to City in accordance with the Contract Documents, and prior to starting
the Work. New schedules will be submitted to City when Participating Change Orders or Non-
Participating Change Orders occur.
2.02 Preconstruction Conference
Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as
specified in the Contract Documents.
2.03 Public Meeting
Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor
attending the Public Meeting as scheduled by the City.
ARTICLE 3 – CONTRACT DOCUMENTS AND AMENDING
3.01 Reference Standards
A. Standards, Specifications, Codes, Laws, and Regulations
1. Reference to standards, specifications, manuals, or codes of any technical society,
organization, or association, or to Laws or Regulations, whether such reference be specific or
by implication, shall mean the standard, specification, manual, code, or Laws or Regulations
in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there
were no Bids), except as may be otherwise specifically stated in the Contract Documents.
2. No provision or instruction shall be effective to assign to City, or any of its officers,
directors, members, partners, employees, agents, consultants, or subcontractors, any duty or
authority to supervise or direct the performance of the Work or any duty or authority to
undertake responsibility inconsistent with the provisions of the Contract Documents.
3.02 Amending and Supplementing Contract Documents
A. The Contract Documents may be amended to provide for additions, deletions, and revisions in
the Work or to modify the terms and conditions thereof by a Participating Change Order or a
Non-Participating Change Order.
B. The requirements of the Contract Documents may be supplemented, and minor variations and
deviations in the Work not involving a change in Contract Price or Contract Time, may be
authorized, by one or more of the following ways:
1. A Field Order;
00 73 10- 7
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 7 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1. City’s or Engineer’s review of a Submittal (subject to the provisions of Paragraph 5.16.C); or
2. City’s written interpretation or clarification.
ARTICLE 4 – BONDS AND INSURANCE
4.01 Licensed Sureties and Insurers
All bonds and insurance required by the Contract Documents to be purchased and maintained by
Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized
in the State of Texas to issue bonds or insurance policies for the limits and coverage so required.
Such surety and insurance companies shall also meet such additional requirements and qualifications
as may be provided Section 4.04.
4.02 Performance, Payment, and Maintenance Bonds
A. Contractor shall furnish performance and payment bonds in the name of Developer and City, in
accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount
equal to the Contract Price as security for the faithful performance and payment of all of
Contractor’s obligations under the Contract Documents.
B. Contractor shall furnish maintenance bonds in the name of Developer and City in an amount
equal to the Contract Price as security to protect the City against any defects in any portion of the
Work described in the Contract Documents. Maintenance bonds shall remain in effect for two
(2) years after the date of Final Acceptance by the City.
C. All bonds shall be in the form prescribed by the Contract Documents except as provided
otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list
of “Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and
as Acceptable Reinsuring Companies” as published in Circular 570 (amended) by the Financial
Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed
by an agent or attorney-in-fact must be accompanied by a sealed and dated power of attorney
which shall show that it is effective on the date the agent or attorney-in-fact signed each bond.
D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or
its right to do business is terminated in the State of Texas or it ceases to meet the requirements of
Paragraph 4.02.C, Contractor shall promptly notify City and shall, within 30 days after the event
giving rise to such notification, provide another bond and surety, both of which shall comply
with the requirements of Paragraphs 4.01 and 4.02.C.
4.03 Certificates of Insurance
Contractor shall deliver to Developer and City, with copies to each additional insured and loss payee
identified in these Standard City Conditions certificates of insurance (and other evidence of
insurance requested by City or any other additional insured) which Contractor is required to
purchase and maintain.
00 73 10- 8
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 8 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1. The certificate of insurance shall document the City, an as “Additional Insured” on all
liability policies.
2. The Contractor’s general liability insurance shall include a, “per project” or “per location”,
endorsement, which shall be identified in the certificate of insurance provided to the City.
3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the
insured, be complete in its entirety, and show complete insurance carrier names as listed in
the current A.M. Best Property & Casualty Guide
4. The insurers for all policies must be licensed and/or approved to do business in the State of
Texas. Except for workers’ compensation, all insurers must have a minimum rating of A-:
VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial
strength and solvency to the satisfaction of Risk Management. If the rating is below that
required, written approval of City is required.
5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor
of the City. In addition, the Contractor agrees to waive all rights of subrogation against the
Engineer (if applicable), and each additional insured identified in these Standard City
Conditions. Failure of the City to demand such certificates or other evidence of full
compliance with the insurance requirements or failure of the City to identify a deficiency
from evidence that is provided shall not be construed as a waiver of Contractor’s obligation
to maintain such lines of insurance coverage.
6. If insurance policies are not written for specified coverage limits, an Umbrella or Excess
Liability insurance for any differences is required. Excess Liability shall follow form of the
primary coverage.
7. Unless otherwise stated, all required insurance shall be written on the “occurrence basis”. If
coverage is underwritten on a claims-made basis, the retroactive date shall be coincident with
or prior to the date of the effective date of the agreement and the certificate of insurance shall
state that the coverage is claims-made and the retroactive date. The insurance coverage shall
be maintained for the duration of the Contract and for three (3) years following Final
Acceptance provided under the Contract Documents or for the warranty period, whichever is
longer. An annual certificate of insurance submitted to the City shall evidence such
insurance coverage.
8. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the
required lines of coverage, nor decrease the limits of said coverage unless such endorsements
are approved in writing by the City. In the event a Contract has been bid or executed and the
exclusions are determined to be unacceptable or the City desires additional insurance
coverage, and the City desires the contractor/engineer to obtain such coverage, the contract
price shall be adjusted by the cost of the premium for such additional coverage plus 10%.
9. Any self-insured retention (SIR), in excess of $25,000.00, affecting required insurance
coverage shall be approved by the City in regards to asset value and stockholders' equity. In
00 73 10- 9
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 9 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
lieu of traditional insurance, alternative coverage maintained through insurance pools or risk
retention groups, must also be approved by City.
10. Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a
first-dollar basis, must be acceptable to and approved by the City.
11. City, at its sole discretion, reserves the right to review the insurance requirements and to
make reasonable adjustments to insurance coverage’s and their limits when deemed
necessary and prudent by the City based upon changes in statutory law, court decision or the
claims history of the industry as well as of the contracting party to the City. The City shall
be required to provide prior notice of 90 days, and the insurance adjustments shall be
incorporated into the Work by Change Order.
12. City shall be entitled, upon written request and without expense, to receive copies of policies
and endorsements thereto and may make any reasonable requests for deletion or revision or
modifications of particular policy terms, conditions, limitations, or exclusions necessary to
conform the policy and endorsements to the requirements of the Contract. Deletions,
revisions, or modifications shall not be required where policy provisions are established by
law or regulations binding upon either party or the underwriter on any such policies.
13. City shall not be responsible for the direct payment of insurance premium costs for
Contractor’s insurance.
4.04 Contractor’s Insurance
A. Workers Compensation and Employers’ Liability. Contractor shall purchase and maintain such
insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers’
Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for
Employers’ Liability as is appropriate for the Work being performed and as will provide
protection from claims set forth below which may arise out of or result from Contractor’s
performance of the Work and Contractor’s other obligations under the Contract Documents,
whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly
or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts
any of them may be liable:
1. claims under workers’ compensation, disability benefits, and other similar employee benefit
acts;
2. claims for damages because of bodily injury, occupational sickness or disease, or death of
Contractor’s employees.
3. The limits of liability for the insurance shall provide the following coverages for not less
than the following amounts or greater where required by Laws and Regulations
a. Statutory limits
b. Employer's liability
00 73 10- 10
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 10 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1) $100,000 each accident/occurrence
2) $100,000 Disease - each employee
3) $500,000 Disease - policy limit
B. Commercial General Liability. Coverage shall include but not be limited to covering liability
(bodily injury or property damage) arising from: premises/operations, independent contractors,
products/completed operations, personal injury, and liability under an insured contract. Insurance
shall be provided on an occurrence basis, and as comprehensive as the current Insurance
Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to
any other insurance or self-insurance programs afforded to the City. The Commercial General
Liability policy, shall have no exclusions by endorsements that would alter of nullify
premises/operations, products/completed operations, contractual, personal injury, or advertising
injury, which are normally contained with the policy, unless the City approves such exclusions
in writing.
1. For construction projects that present a substantial completed operation exposure, the City
may require the contractor to maintain completed operations coverage for a minimum of no
less than three (3) years following the completion of the project
2. Contractor's Liability Insurance under this Section which shall be on a per project basis
covering the Contractor with minimum limits of:
a. $1,000,000 each occurrence
b. $2,000,000 aggregate limit
3. The policy must have an endorsement (Amendment – Aggregate Limits of Insurance)
making the General Aggregate Limits apply separately to each job site.
4. The Commercial General Liability Insurance policies shall provide “X”, “C”, and “U”
coverage’s. Verification of such coverage must be shown in the Remarks Article of the
Certificate of Insurance.
C. Automobile Liability. A commercial business auto policy shall provide coverage on “any auto”,
defined as autos owned, hired and non-owned and provide indemnity for claims for damages
because bodily injury or death of any person and or property damage arising out of the work,
maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by
anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone
for whose acts any of them may be liable.
1. Automobile Liability, Contractor’s Liability Insurance under this Section, which shall be in
an amount not less than the following amounts:
a. Automobile Liability - a commercial business policy shall provide coverage on "Any
Auto", defined as autos owned, hired and non-owned.
00 73 10- 11
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 11 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1) $1,000,000 each accident on a combined single limit basis. Split limits are
acceptable if limits are at least:
2) $250,000 Bodily Injury per person
3) $500,000 Bodily Injury per accident /
4) $100,000 Property Damage
D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of
railroad right-of-way, the Contractor shall comply with the following requirements:
1. The Contractor’s construction activities will require its employees, agents, subcontractors,
equipment, and material deliveries to cross railroad properties and tracks owned and
operated by: ____________________________________________________________
Write the name of the railroad company. (If none, then write none)
2. The Contractor shall conduct its operations on railroad properties in such a manner as not to
interfere with, hinder, or obstruct the railroad company in any manner whatsoever in the use
or operation of its/their trains or other property. Such operations on railroad properties may
require that Contractor to execute a “Right of Entry Agreement” with the particular railroad
company or companies involved, and to this end the Contractor should satisfy itself as to the
requirements of each railroad company and be prepared to execute the right-of-entry (if any)
required by a railroad company. The requirements specified herein likewise relate to the
Contractor’s use of private and/or construction access roads crossing said railroad company’s
properties.
3. The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions
shall provide coverage for not less than the following amounts, issued by companies
satisfactory to the City and to the Railroad Company for a term that continues for so long as
the Contractor’s operations and work cross, occupy, or touch railroad property:
a. General Aggregate: _____________________________________
Enter limits provided by Railroad Company (If none, write none)
b. Each Occurrence: : _____________________________________
Enter limits provided by Railroad Company (If none, write none)
4. With respect to the above outlined insurance requirements, the following shall govern:
a. Where a single railroad company is involved, the Contractor shall provide one insurance
policy in the name of the railroad company. However, if more than one grade separation
or at-grade crossing is affected by the Project at entirely separate locations on the line or
lines of the same railroad company, separate coverage may be required, each in the
amount stated above.
b. Where more than one railroad company is operating on the same right-of-way or where
several railroad companies are involved and operated on their own separate rights-of-
None
None
None
00 73 10- 12
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 12 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
way, the Contractor may be required to provide separate insurance policies in the name
of each railroad company.
c. If, in addition to a grade separation or an at-grade crossing, other work or activity is
proposed on a railroad company’s right-of-way at a location entirely separate from the
grade separation or at-grade crossing, insurance coverage for this work must be included
in the policy covering the grade separation.
d. If no grade separation is involved but other work is proposed on a railroad company’s
right-of-way, all such other work may be covered in a single policy for that railroad, even
though the work may be at two or more separate locations.
5. No work or activities on a railroad company’s property to be performed by the Contractor
shall be commenced until the Contractor has furnished the City with an original policy or
policies of the insurance for each railroad company named, as required above. All such
insurance must be approved by the City and each affected Railroad Company prior to the
Contractor’s beginning work.
6. The insurance specified above must be carried until all Work to be performed on the railroad
right-of-way has been completed and the grade crossing, if any, is no longer used by the
Contractor. In addition, insurance must be carried during all maintenance and/or repair work
performed in the railroad right-of-way. Such insurance must name the railroad company as
the insured, together with any tenant or lessee of the railroad company operating over tracks
involved in the Project.
E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation
or other loss of insurance coverage. Contractor shall stop work until replacement insurance has
been procured. There shall be no time credit for days not worked pursuant to this section.
4.05 Acceptance of Bonds and Insurance; Option to Replace
If City has any objection to the coverage afforded by or other provisions of the bonds or insurance
required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis
of non-conformance with the Contract Documents, the Developer and City shall so notify the
Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence
requested). Contractor shall provide to the City such additional information in respect of insurance
provided as the Developer or City may reasonably request. If Contractor does not purchase or
maintain all of the bonds and insurance required by the Contract Documents, the Developer or City
shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure
to maintain prior to any change in the required coverage.
ARTICLE 5 – CONTRACTOR’S RESPONSIBILITIES
5.01 Supervision and Superintendent
A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting
such attention thereto and applying such skills and expertise as may be necessary to perform the
00 73 10- 13
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 13 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Work in accordance with the Contract Documents. Contractor shall be solely responsible for the
means, methods, techniques, sequences, and procedures of construction.
B. At all times during the progress of the Work, Contractor shall assign a competent, English-
speaking, Superintendent who shall not be replaced without written notice to City. The
Superintendent will be Contractor’s representative at the Site and shall have authority to act on
behalf of Contractor. All communication given to or received from the Superintendent shall be
binding on Contractor.
C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of
construction.
5.02 Labor; Working Hours
A. Contractor shall provide competent, suitably qualified personnel to perform construction as
required by the Contract Documents. Contractor shall at all times maintain good discipline and
order at the Site.
B. Except as otherwise required for the safety or protection of persons or the Work or property at
the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work
at the Site shall be performed during Regular Working Hours. Contractor will not permit the
performance of Work beyond Regular Working Hours or for Weekend Working Hours without
City’s written consent (which will not be unreasonably withheld). Written request (by letter or
electronic communication) to perform Work:
1. for beyond Regular Working Hours request must be made by noon at least two (2) Business
Days prior
2. for Weekend Working Hours request must be made by noon of the preceding Thursday
3. for legal holidays request must be made by noon two Business Days prior to the legal
holiday.
5.03 Services, Materials, and Equipment
A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full
responsibility for all services, materials, equipment, labor, transportation, construction
equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary
facilities, temporary facilities, and all other facilities and incidentals necessary for the
performance, Contractor required testing, start-up, and completion of the Work.
B. All materials and equipment incorporated into the Work shall be as specified or, if not specified,
shall be of good quality and new, except as otherwise provided in the Contract Documents. All
special warranties and guarantees required by the Specifications shall expressly run to the benefit
of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of
required tests) as to the source, kind, and quality of materials and equipment.
00 73 10- 14
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 14 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed,
connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of
the applicable Supplier, except as otherwise may be provided in the Contract Documents.
5.04 Project Schedule
A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.01
and the General Requirements as it may be adjusted from time to time as provided below.
1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.01 and
the General Requirements) proposed adjustments in the Project Schedule.
2. Proposed adjustments in the Project Schedule that will change the Contract Time shall be
submitted in accordance with the requirements of Article 9. Adjustments in Contract Time
for projects with City participation shall be made by participating change orders.
5.05 Substitutes and “Or-Equals”
A. Whenever an item of material or equipment is specified or described in the Contract Documents
by using the name of a proprietary item or the name of a particular Supplier, the specification or
description is intended to establish the type, function, appearance, and quality required. Unless
the specification or description contains or is followed by words reading that no like, equivalent,
or “or-equal” item or no substitution is permitted, other items of material or equipment of other
Suppliers may be submitted to City for review under the circumstances described below.
1. “Or-Equal” Items: If in City’s sole discretion an item of material or equipment proposed by
Contractor is functionally equal to that named and sufficiently similar so that no change in
related Work will be required, it may be considered by City as an “or-equal” item, in which
case review and approval of the proposed item may, in City’s sole discretion, be
accomplished without compliance with some or all of the requirements for approval of
proposed substitute items. For the purposes of this Paragraph 5.05.A.1, a proposed item of
material or equipment will be considered functionally equal to an item so named if:
a. City determines that:
1) it is at least equal in materials of construction, quality, durability, appearance,
strength, and design characteristics;
2) it will reliably perform at least equally well the function and achieve the results
imposed by the design concept of the completed Project as a functioning whole; and
3) it has a proven record of performance and availability of responsive service; and
b. Contractor certifies that, if approved and incorporated into the Work:
1) there will be no increase in cost to the City or increase in Contract Time; and
00 73 10- 15
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 15 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
2) it will conform substantially to the detailed requirements of the item named in the
Contract Documents.
2. Substitute Items:
a. If in City’s sole discretion an item of material or equipment proposed by Contractor does
not qualify as an “or-equal” item under Paragraph 5.05.A.1, it may be submitted as a
proposed substitute item.
b. Contractor shall submit sufficient information as provided below to allow City to
determine if the item of material or equipment proposed is essentially equivalent to that
named and an acceptable substitute therefor. Requests for review of proposed substitute
items of material or equipment will not be accepted by City from anyone other than
Contractor.
c. Contractor shall make written application to City for review of a proposed substitute item
of material or equipment that Contractor seeks to furnish or use. The application shall
comply with Section 01 25 00 and:
1) shall certify that the proposed substitute item will:
i. perform adequately the functions and achieve the results called for by the general
design;
ii. be similar in substance to that specified;
iii. be suited to the same use as that specified; and
2) will state:
i. the extent, if any, to which the use of the proposed substitute item will prejudice
Contractor’s achievement of final completion on time;
ii. whether use of the proposed substitute item in the Work will require a change in
any of the Contract Documents (or in the provisions of any other direct contract
with City for other work on the Project) to adapt the design to the proposed
substitute item;
iii. whether incorporation or use of the proposed substitute item in connection with
the Work is subject to payment of any license fee or royalty; and
3) will identify:
i. all variations of the proposed substitute item from that specified;
ii. available engineering, sales, maintenance, repair, and replacement services; and
00 73 10- 16
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 16 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
4) shall contain an itemized estimate of all costs or credits that will result directly or
indirectly from use of such substitute item, including costs of redesign and Damage
Claims of other contractors affected by any resulting change.
B. Substitute Construction Methods or Procedures: If a specific means, method, technique,
sequence, or procedure of construction is expressly required by the Contract Documents,
Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure
of construction approved by City. Contractor shall submit sufficient information to allow City, in
City’s sole discretion, to determine that the substitute proposed is equivalent to that expressly
called for by the Contract Documents. Contractor shall make written application to City for
review in the same manner as those provided in Paragraph 5.05.A.2.
C. City’s Evaluation: City will be allowed a reasonable time within which to evaluate each
proposal or submittal made pursuant to Paragraphs 5.05.A and 5.05.B. City may require
Contractor to furnish additional data about the proposed substitute. City will be the sole judge of
acceptability. No “or-equal” or substitute will be ordered, installed or utilized until City’s review
is complete, which will be evidenced by a Change Order in the case of a substitute and an
accepted Submittal for an “or-equal.” City will advise Contractor in writing of its determination.
D. Special Guarantee: City may require Contractor to furnish at Contractor’s expense a special
performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall
indemnify and hold harmless City and anyone directly or indirectly employed by them from and
against any and all claims, damages, losses and expenses (including attorneys fees) arising out
of the use of substituted materials or equipment.
E. City’s Cost Reimbursement: City will record City’s costs in evaluating a substitute proposed or
submitted by Contractor pursuant to Paragraphs 5.05.A.2 and 5.05.B. Whether or not City
approves a substitute so proposed or submitted by Contractor, Contractor may be required to
reimburse City for evaluating each such proposed substitute. Contractor may also be required to
reimburse City for the charges for making changes in the Contract Documents.
F. Contractor’s Expense: Contractor shall provide all data in support of any proposed substitute or
“or-equal” at Contractor’s expense.
G. Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute
shall be incorporated to the Contract by Participating Change Order.
5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors)
A. The Contractor and any subcontractors are required to be prequalified for the work types
requiring pre-qualification
5.07 Concerning Subcontractors, Suppliers, and Others
A. Minority and Women Owned Business Enterprise Compliance:
00 73 10- 17
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 17 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Required for this Contract.
(Check this box if there is any City Participation)
Not Required for this Contract.
It is City policy to ensure the full and equitable participation by Minority and Women Business
Enterprises (MWBE) in the procurement of goods and services on a contractual basis. If the
Contract Documents provide for a MWBE goal, Contractor is required to comply with the intent
of the City’s MWBE Ordinance (as amended) by the following:
1. Contractor shall, upon request by City, provide complete and accurate information regarding
actual work performed by a MWBE on the Contract and payment therefor.
2. Contractor will not make additions, deletions, or substitutions of accepted MWBE without
written consent of the City. Any unjustified change or deletion shall be a material breach of
Contract and may result in debarment in accordance with the procedures outlined in the
Ordinance.
3. Contractor shall, upon request by City, allow an audit and/or examination of any books,
records, or files in the possession of the Contractor that will substantiate the actual work
performed by an MWBE. Material misrepresentation of any nature will be grounds for
termination of the Contract. Any such misrepresentation may be grounds for disqualification
of Contractor to bid on future contracts with the City for a period of not less than three years.
B. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors,
Suppliers, and other individuals or entities performing or furnishing any of the Work just as
Contractor is responsible for Contractor’s own acts and omissions. Nothing in the Contract
Documents:
1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity
any contractual relationship between City and any such Subcontractor, Supplier or other
individual or entity; nor
2. shall create any obligation on the part of City to pay or to see to the payment of any moneys
due any such Subcontractor, Supplier, or other individual or entity except as may otherwise
be required by Laws and Regulations.
C. Contractor shall be solely responsible for scheduling and coordinating the Work of
Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the
Work under a direct or indirect contract with Contractor.
D. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing
any of the Work shall communicate with City through Contractor.
E. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an
appropriate agreement between Contractor and the Subcontractor or Supplier which specifically
binds the Subcontractor or Supplier to the applicable terms and conditions of these Contract
X
00 73 10- 18
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 18 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Documents, Contractor shall provide City contract numbers and reference numbers to the
Subcontractors and/or Suppliers.
5.08 Wage Rates
Required for this Contract.
Not Required for this Contract.
A. Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of
Chapter 2258, Texas Government Code (as amended), including the payment of not less than the
rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in
accordance with Chapter 2258. Such prevailing wage rates are included in these Contract
Documents.
B. Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage
shall, upon demand made by the City, pay to the City $60 for each worker employed for each
calendar day or part of the day that the worker is paid less than the prevailing wage rates
stipulated in these contract documents. This penalty shall be retained by the City to offset its
administrative costs, pursuant to Texas Government Code 2258.023.
C. Complaints of Violations and City Determination of Good Cause. On receipt of information,
including a complaint by a worker, concerning an alleged violation of 2258.023, Texas
Government Code, by a Contractor or Subcontractor, the City shall make an initial
determination, before the 31st day after the date the City receives the information, as to whether
good cause exists to believe that the violation occurred. The City shall notify in writing the
Contractor or Subcontractor and any affected worker of its initial determination. Upon the
City’s determination that there is good cause to believe the Contractor or Subcontractor has
violated Chapter 2258, the City shall retain the full amounts claimed by the claimant or
claimants as the difference between wages paid and wages due under the prevailing wage rates,
such amounts being subtracted from successive progress payments pending a final determination
of the violation.
D. Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of
Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected
worker, shall be submitted to binding arbitration in accordance with the Texas General
Arbitration Act (Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any
affected worker does not resolve the issue by agreement before the 15th day after the date the
City makes its initial determination pursuant to Paragraph C above. If the persons required to
arbitrate under this section do not agree on an arbitrator before the 11th day after the date that
arbitration is required, a district court shall appoint an arbitrator on the petition of any of the
persons. The City is not a party in the arbitration. The decision and award of the arbitrator is
final and binding on all parties and may be enforced in any court of competent jurisdiction.
E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3)
years following the date of acceptance of the work, maintain records that show (i) the name and
X
00 73 10- 19
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 19 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
occupation of each worker employed by the Contractor in the construction of the Work provided
for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be
open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right
to Audit, shall pertain to this inspection.
F. Progress Payments. With each progress payment or payroll period, whichever is less, the
Contractor shall submit an affidavit stating that the Contractor has complied with the
requirements of Chapter 2258, Texas Government Code.
G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at
all times.
H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall
otherwise require all of its Subcontractors to comply with Paragraphs A through G above.
5.09 Patent Fees and Royalties
A. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold
harmless City, from and against all claims, costs, losses, and damages (including but not limited
to all fees and charges of engineers, architects, attorneys, and other professionals and all court
or arbitration or other dispute resolution costs) arising out of or relating to any infringement of
patent rights or copyrights incident to the use in the performance of the Work or resulting from
the incorporation in the Work of any invention, design, process, product, or device not specified
in the Contract Documents.
5.10 Laws and Regulations
A. Contractor shall give all notices required by and shall comply with all Laws and Regulations
applicable to the performance of the Work. Except where otherwise expressly required by
applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor’s
compliance with any Laws or Regulations.
B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws
or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such Work.
However, it shall not be Contractor’s responsibility to make certain that the Specifications and
Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of
Contractor’s obligations under Paragraph 3.01.
5.11 Use of Site and Other Areas
A. Limitation on Use of Site and Other Areas:
1. Contractor shall confine construction equipment, the storage of materials and equipment, and
the operations of workers to the Site and other areas permitted by Laws and Regulations, and
shall not unreasonably encumber the Site and other areas with construction equipment or
00 73 10- 20
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 20 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
other materials or equipment. Contractor shall assume full responsibility for any damage to
any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas
resulting from the performance of the Work.
2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is
carrying on operations in a portion of a street, right-of-way, or easement greater than is
necessary for proper execution of the Work, the City may require the Contractor to finish the
section on which operations are in progress before work is commenced on any additional
area of the Site.
3. Should any Damage Claim be made by any such owner or occupant because of the
performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim.
4. Pursuant to Paragraph 5.18, Contractor shall indemnify and hold harmless City, from and
against all claims, costs, losses, and damages arising out of or relating to any claim or
action, legal or equitable, brought by any such owner or occupant against City.
B. Removal of Debris During Performance of the Work: During the progress of the Work
Contractor shall keep the Site and other areas free from accumulations of waste materials,
rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other
debris shall conform to applicable Laws and Regulations.
C. Site Maintenance Cleaning: 24 hours after written notice is given to the Contractor that the
clean-up on the job site is proceeding in a manner unsatisfactory to the City or Developer, if the
Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as
the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the
written notice (by letter or electronic communication), and shall be entitled to recover its cost in
doing so. The City may withhold Final Acceptance until clean-up is complete and cost are
recovered.
D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and
the Work and make it ready for utilization by City or adjacent property owner. At the completion
of the Work Contractor shall remove from the Site all tools, appliances, construction equipment
and machinery, and surplus materials and shall restore to original condition or better all property
disturbed by the Work.
E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded
in any manner that will endanger the structure, nor shall Contractor subject any part of the Work
or adjacent property to stresses or pressures that will endanger it.
5.12 Record Documents
A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor
and approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change
Orders, Field Orders, and written interpretations and clarifications in good order and annotated
to show changes made during construction. These record documents together with all approved
00 73 10- 21
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 21 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Samples and a counterpart of all accepted Submittals will be available to City for reference.
Upon completion of the Work, these record documents, any operation and maintenance manuals,
and Submittals will be delivered to City prior to Final Inspection. Contractor shall include
accurate locations for buried and imbedded items.
5.13 Safety and Protection
A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety
precautions and programs in connection with the Work. Such responsibility does not relieve
Subcontractors of their responsibility for the safety of persons or property in the performance of
their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall
take all necessary precautions for the safety of, and shall provide the necessary protection to
prevent damage, injury or loss to:
1. all persons on the Site or who may be affected by the Work;
2. all the Work and materials and equipment to be incorporated therein, whether in storage on
or off the Site; and
3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks,
pavements, roadways, structures, utilities, and Underground Facilities not designated for
removal, relocation, or replacement in the course of construction.
B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of
persons or property, or to the protection of persons or property from damage, injury, or loss; and
shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall
notify owners of adjacent property and of Underground Facilities and other utility owners when
prosecution of the Work may affect them, and shall cooperate with them in the protection,
removal, relocation, and replacement of their property.
C. Contractor shall comply with the applicable requirements of City’s safety programs, if any.
D. Contractor shall inform City of the specific requirements of Contractor’s safety program, if any,
with which City’s employees and representatives must comply while at the Site.
E. All damage, injury, or loss to any property referred to in Paragraph 5.13.A.2 or 5.13.A.3 caused,
directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any
other individual or entity directly or indirectly employed by any of them to perform any of the
Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor.
F. Contractor’s duties and responsibilities for safety and for protection of the Work shall continue
until such time as all the Work is completed and City has accepted the Work.
5.14 Safety Representative
Contractor shall inform City in writing of Contractor’s designated safety representative at the Site.
00 73 10- 22
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 22 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
5.15 Hazard Communication Programs
Contractor shall be responsible for coordinating any exchange of material safety data sheets or other
hazard communication information required to be made available to or exchanged between or
among employers in accordance with Laws or Regulations.
5.16 Submittals
A. Contractor shall submit required Submittals to City for review and acceptance. Each submittal
will be identified as required by City.
1. Submit number of copies specified in the General Requirements.
2. Data shown on the Submittals will be complete with respect to quantities, dimensions,
specified performance and design criteria, materials, and similar data to show City the
services, materials, and equipment Contractor proposes to provide and to enable City to
review the information for the limited purposes required by Paragraph 5.16.C.
3. Submittals submitted as herein provided by Contractor and reviewed by City for
conformance with the design concept shall be executed in conformity with the Contract
Documents unless otherwise required by City.
4. When Submittals are submitted for the purpose of showing the installation in greater detail,
their review shall not excuse Contractor from requirements shown on the Drawings and
Specifications.
5. For-Information-Only submittals upon which the City is not expected to conduct review or
take responsive action may be so identified in the Contract Documents.
6. Submit required number of Samples specified in the Specifications.
7. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers,
the use for which intended and other data as City may require to enable City to review the
submittal for the limited purposes required by Paragraph 5.16.C.
B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any
related Work performed prior to City’s review and acceptance of the pertinent submittal will be
at the sole expense and responsibility of Contractor.
C. City’s Review:
1. City will provide timely review of required Submittals in accordance with the Schedule of
Submittals acceptable to City. City’s review and acceptance will be only to determine if the
items covered by the submittals will, after installation or incorporation in the Work, conform
to the information given in the Contract Documents and be compatible with the design
concept of the completed Project as a functioning whole as indicated by the Contract
Documents.
00 73 10- 23
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 23 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
2. City’s review and acceptance will not extend to means, methods, techniques, sequences, or
procedures of construction (except where a particular means, method, technique, sequence,
or procedure of construction is specifically and expressly called for by the Contract
Documents) or to safety precautions or programs incident thereto. The review and
acceptance of a separate item as such will not indicate approval of the assembly in which the
item functions.
3. City’s review and acceptance shall not relieve Contractor from responsibility for any
variation from the requirements of the Contract Documents unless Contractor has complied
with the requirements of Section 01 33 00 and City has given written acceptance of each
such variation by specific written notation thereof incorporated in or accompanying the
Submittal. City’s review and acceptance shall not relieve Contractor from responsibility for
complying with the requirements of the Contract Documents.
5.17 Contractor’s General Warranty and Guarantee
A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract
Documents and will not be defective. City and its officers, directors, members, partners,
employees, agents, consultants, and subcontractors shall be entitled to rely on representation of
Contractor’s warranty and guarantee.
B. Contractor’s warranty and guarantee hereunder excludes defects or damage caused by:
1. abuse, modification, or improper maintenance or operation by persons other than Contractor,
Subcontractors, Suppliers, or any other individual or entity for whom Contractor is
responsible; or
2. normal wear and tear under normal usage.
C. Contractor’s obligation to perform and complete the Work in accordance with the Contract
Documents shall be absolute. None of the following will constitute an acceptance of Work that is
not in accordance with the Contract Documents or a release of Contractor’s obligation to
perform the Work in accordance with the Contract Documents:
1. observations by City;
2. recommendation or payment by City or Developer of any progress or final payment;
3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by
City;
4. use or occupancy of the Work or any part thereof by City;
5. any review and acceptance of a Submittal by City;
6. any inspection, test, or approval by others; or
00 73 10- 24
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 24 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
7. any correction of defective Work by City.
D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to
other work or property resulting therefrom which shall appear within a period of two (2) years
from the date of Final Acceptance of the Work unless a longer period is specified and shall
furnish a good and sufficient maintenance bond, complying with the requirements of Article
4.02.B. The City will give notice of observed defects with reasonable promptness.
5.18 Indemnification
A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the
City, its officers, servants and employees, from and against any and all claims arising out of, or
alleged to arise out of, the work and services to be performed by the Contractor, its officers,
agents, employees, subcontractors, licenses or invitees under this Contract. THIS
INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE
AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME
OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY
ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. This indemnity provision is
intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by
the City in defending against such claims and causes of actions.
B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its
officers, servants and employees, from and against any and all loss, damage or destruction of
property of the City, arising out of, or alleged to arise out of, the work and services to be
performed by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees
under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY
INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR
PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE
CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF
THE CITY.
5.19 Delegation of Professional Design Services
A. Contractor will not be required to provide professional design services unless such services are
specifically required by the Contract Documents for a portion of the Work or unless such
services are required to carry out Contractor’s responsibilities for construction means, methods,
techniques, sequences and procedures.
B. If professional design services or certifications by a design professional related to systems,
materials or equipment are specifically required of Contractor by the Contract Documents, City
will specify all performance and design criteria that such services must satisfy. Contractor shall
cause such services or certifications to be provided by a properly licensed professional, whose
signature and seal shall appear on all drawings, calculations, specifications, certifications, and
Submittals prepared by such professional. Submittals related to the Work designed or certified
by such professional, if prepared by others, shall bear such professional’s written approval when
submitted to City.
00 73 10- 25
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 25 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services,
certifications or approvals performed by such design professionals, provided City has specified
to Contractor performance and design criteria that such services must satisfy.
D. Pursuant to this Paragraph 5.19, City’s review and acceptance of design calculations and design
drawings will be only for the limited purpose of checking for conformance with performance
and design criteria given and the design concept expressed in the Contract Documents. City’s
review and acceptance of Submittals (except design calculations and design drawings) will be
only for the purpose stated in Paragraph 5.16.C.
5.20 Right to Audit:
A. The City reserves the right to audit all projects utilizing City funds
B. The Contractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of the Contractor involving transactions relating
to this Contract. Contractor agrees that the City shall have access during Regular Working Hours
to all necessary Contractor facilities and shall be provided adequate and appropriate work space
in order to conduct audits in compliance with the provisions of this Paragraph. The City shall
give Contractor reasonable advance notice of intended audits.
C. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that
the subcontractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of such Subcontractor, involving transactions to
the subcontract, and further, that City shall have access during Regular Working Hours to all
Subcontractor facilities, and shall be provided adequate and appropriate work space in order to
conduct audits in compliance with the provisions of this Paragraph. The City shall give
Subcontractor reasonable advance notice of intended audits.
D. Contractor and Subcontractor agree to photocopy such documents as may be requested by the
City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate
published in the Texas Administrative Code in effect as of the time copying is performed.
5.21 Nondiscrimination
A. The City is responsible for operating Public Transportation Programs and implementing transit-
related projects, which are funded in part with Federal financial assistance awarded by the U.S.
Department of Transportation and the Federal Transit Administration (FTA), without
discriminating against any person in the United States on the basis of race, color, or national
origin.
B. Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of
the Act and the Regulations as further defined in the Supplementary Conditions for any project
receiving Federal assistance.
00 73 10- 26
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 26 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 6 – OTHER WORK AT THE SITE
6.01 Related Work at Site
A. City may perform other work related to the Project at the Site with City’s employees, or other
City contractors, or through other direct contracts therefor, or have other work performed by
utility owners. If such other work is not noted in the Contract Documents, then written notice
thereof will be given to Contractor prior to starting any such other work; and
B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility
owner, and City, if City is performing other work with City’s employees or other City
contractors, proper and safe access to the Site, provide a reasonable opportunity for the
introduction and storage of materials and equipment and the execution of such other work, and
properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of
the Work that may be required to properly connect or otherwise make its several parts come
together and properly integrate with such other work. Contractor shall not endanger any work of
others by cutting, excavating, or otherwise altering such work; provided, however, that
Contractor may cut or alter others' work with the written consent of City and the others whose
work will be affected.
C. If the proper execution or results of any part of Contractor’s Work depends upon work
performed by others under this Article 7, Contractor shall inspect such other work and promptly
report to City in writing any delays, defects, or deficiencies in such other work that render it
unavailable or unsuitable for the proper execution and results of Contractor’s Work. Contractor’s
failure to so report will constitute an acceptance of such other work as fit and proper for
integration with Contractor’s Work except for latent defects in the work provided by others.
ARTICLE 7 – CITY’S RESPONSIBILITIES
7.01 Inspections, Tests, and Approvals
City’s responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph
11.03.
7.02 Limitations on City’s Responsibilities
A. The City shall not supervise, direct, or have control or authority over, nor be responsible for,
Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety
precautions and programs incident thereto, or for any failure of Contractor to comply with Laws
and Regulations applicable to the performance of the Work. City will not be responsible for
Contractor’s failure to perform the Work in accordance with the Contract Documents.
B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 5.13.
00 73 10- 27
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 27 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
7.03 Compliance with Safety Program
While at the Site, City’s employees and representatives shall comply with the specific applicable
requirements of Contractor’s safety programs of which City has been informed pursuant to
Paragraph 5.13.
ARTICLE 8 – CITY’S OBSERVATION STATUS DURING CONSTRUCTION
8.01 City’s Project Representative
City will provide one or more Project Representative(s) during the construction period. The duties
and responsibilities and the limitations of authority of City’s representative during construction are
set forth in the Contract Documents.
A. City’s Project Representative will make visits to the Site at intervals appropriate to the various
stages of construction as City deems necessary in order to observe the progress that has been
made and the quality of the various aspects of Contractor’s executed Work. Based on
information obtained during such visits and observations, City’s Project Representative will
determine, in general, if the Work is proceeding in accordance with the Contract Documents.
City’s Project Representative will not be required to make exhaustive or continuous inspections
on the Site to check the quality or quantity of the Work. City’s Project Representative’s efforts
will be directed toward providing City a greater degree of confidence that the completed Work
will conform generally to the Contract Documents.
B. City’s Project Representative’s visits and observations are subject to all the limitations on
authority and responsibility in the Contract Documents.
8.02 Authorized Variations in Work
City’s Project Representative may authorize minor variations in the Work from the requirements of
the Contract Documents which do not involve an adjustment in the Contract Price or the Contract
Time and are compatible with the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. These may be accomplished by a Field Order and will be
binding on City Developer, and also on Contractor, who shall perform the Work involved promptly.
8.03 Rejecting Defective Work
City will have authority to reject Work which City’s Project Representative believes to be defective,
or will not produce a completed Project that conforms to the Contract Documents or that will
prejudice the integrity of the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. City will have authority to conduct special inspection or
testing of the Work as provided in Article 11, whether or not the Work is fabricated, installed, or
completed.
00 73 10- 28
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 28 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
8.04 Determinations for Work Performed
Contractor will determine the actual quantities and classifications of Work performed. City’s Project
Representative will review with Contractor the preliminary determinations on such matters before
rendering a written recommendation. City’s written decision will be final (except as modified to
reflect changed factual conditions or more accurate data).
ARTICLE 9 – CHANGES IN THE WORK
9.01 Authorized Changes in the Work
A. Without invalidating the Contract and without notice to any surety, City may, at any time or
from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall
promptly proceed with the Work involved which will be performed under the applicable
conditions of the Contract Documents (except as otherwise specifically provided). Extra Work
shall be memorialized by a Participating Change Order which may or may not precede an order
of Extra work.
B. For minor changes of Work not requiring changes to Contract Time or Contract Price on a
project with City participation, a Field Order may be issued by the City.
9.02 Notification to Surety
If the provisions of any bond require notice to be given to a surety of any change affecting the
general scope of the Work or the provisions of the Contract Documents (including, but not limited
to, Contract Price or Contract Time), the giving of any such notice will be Contractor’s
responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the
effect of any such change.
ARTICLE 10 – CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME
10.01 Change of Contract Price
A. The Contract Price may only be changed by a Participating Change Order for projects with City
participation.
10.02 Change of Contract Time
A. The Contract Time may only be changed by a Participating Change Order for projects with City
participation.
10.03 Delays
A. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or
damages (including but not limited to all fees and charges of engineers, architects, attorneys, and
other professionals and all court or arbitration or other dispute resolution costs) sustained by
Contractor on or in connection with any other project or anticipated project.
00 73 10- 29
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 29 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 11 – TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK
11.01 Notice of Defects
Notice of all defective Work of which City has actual knowledge will be given to Contractor.
Defective Work may be rejected, corrected, or accepted as provided in this Article 13.
11.02 Access to Work
City, independent testing laboratories, and governmental agencies with jurisdictional interests will
have access to the Site and the Work at reasonable times for their observation, inspection, and
testing. Contractor shall provide them proper and safe conditions for such access and advise them of
Contractor’s safety procedures and programs so that they may comply therewith as applicable.
11.03 Tests and Inspections
A. Contractor shall give City timely notice of readiness of the Work for all required inspections,
tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required
inspections or tests.
B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any
of the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full
responsibility for arranging and obtaining such independent inspections, tests, retests or
approvals, pay all costs in connection therewith, and furnish City the required certificates of
inspection or approval; excepting, however, those fees specifically identified in the
Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR)
inspections, which shall be paid as described in the Supplementary Conditions.
C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection
with any inspections, tests, re-tests, or approvals required for City’s acceptance of materials or
equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment
submitted for approval prior to Contractor’s purchase thereof for incorporation in the Work.
Such inspections, tests, re-tests, or approvals shall be performed by organizations approved by
City.
D. City may arrange for the services of an independent testing laboratory (“Testing Lab”) to
perform any inspections or tests (“Testing”) for any part of the Work, as determined solely by
City.
1. City will coordinate such Testing to the extent possible, with Contractor;
2. Should any Testing under this Section 11.03 D result in a “fail”, “did not pass” or other
similar negative result, the Contractor shall be responsible for paying for any and all retests.
Contractor’s cancellation without cause of City initiated Testing shall be deemed a negative
result and require a retest.
00 73 10- 30
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 30 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
3. Any amounts owed for any retest under this Section 11.03 D shall be paid directly to the
Testing Lab by Contractor. City will forward all invoices for retests to
Developer/Contractor.
4. If Contractor fails to pay the Testing Lab, City will not issue a letter of Final Acceptance
until the Testing Lab is Paid
E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by
Contractor without written concurrence of City, Contractor shall, if requested by City, uncover
such Work for observation.
11.04 Uncovering Work
A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it
must, if requested by City, be uncovered for City’s observation and replaced at Contractor’s
expense.
11.05 City May Stop the Work
If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials
or equipment, or fails to perform the Work in such a way that the completed Work will conform to
the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until
the cause for such order has been eliminated; however, this right of City to stop the Work shall not
give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any
Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent
of any of them.
11.06 Correction or Removal of Defective Work
A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to
an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has
been rejected by City, remove it from the Project and replace it with Work that is not defective.
Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such correction
or removal (including but not limited to all costs of repair or replacement of work of others).
Failure to require the removal of any defective Work shall not constitute acceptance of such
Work.
B. When correcting defective Work under the terms of this Paragraph 11.06 or Paragraph 11.07,
Contractor shall take no action that would void or otherwise impair City’s special warranty and
guarantee, if any, on said Work.
11.07 Correction Period
A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may
be prescribed by the terms of any applicable special guarantee required by the Contract
00 73 10- 31
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 31 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Documents), any Work is found to be defective, or if the repair of any damages to the land or
areas made available for Contractor’s use by City or permitted by Laws and Regulations as
contemplated in Paragraph 5.10.A is found to be defective, Contractor shall promptly, without
cost to City and in accordance with City’s written instructions:
1. repair such defective land or areas; or
2. correct such defective Work; or
3. if the defective Work has been rejected by City, remove it from the Project and replace it
with Work that is not defective, and
4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work
of others or other land or areas resulting therefrom.
B. If Contractor does not promptly comply with the terms of City’s written instructions, or in an
emergency where delay would cause serious risk of loss or damage, City may have the defective
Work corrected or repaired or may have the rejected Work removed and replaced. All claims,
costs, losses, and damages (including but not limited to all fees and charges of engineers,
architects, attorneys, and other professionals and all court or other dispute resolution costs)
arising out of or relating to such correction or repair or such removal and replacement (including
but not limited to all costs of repair or replacement of work of others) will be paid by Contractor.
C. Where defective Work (and damage to other Work resulting therefrom) has been corrected or
removed and replaced under this Paragraph 11.07, the correction period hereunder with respect
to such Work may be required to be extended for an additional period of one year after the end
of the initial correction period. City shall provide 30 days written notice to Contractor and
Developer should such additional warranty coverage be required. Contractor’s obligations under
this Paragraph 11.07 are in addition to any other obligation or warranty. The provisions of this
Paragraph 11.07 shall not be construed as a substitute for, or a waiver of, the provisions of any
applicable statute of limitation or repose.
11.08 City May Correct Defective Work
A. If Contractor fails within a reasonable time after written notice from City to correct defective
Work, or to remove and replace rejected Work as required by City in accordance with Paragraph
11.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents,
or if Contractor fails to comply with any other provision of the Contract Documents, City may,
after seven (7) days written notice to Contractor and the Developer, correct, or remedy any such
deficiency.
B. In exercising the rights and remedies under this Paragraph 11.09, City shall proceed
expeditiously. In connection with such corrective or remedial action, City may exclude
Contractor from all or part of the Site, take possession of all or part of the Work and suspend
Contractor’s services related thereto, and incorporate in the Work all materials and equipment
incorporated in the Work, stored at the Site or for which City has paid Contractor but which are
00 73 10- 32
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 32 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
stored elsewhere. Contractor shall allow City, City’s representatives, agents, consultants,
employees, and City’s other contractors, access to the Site to enable City to exercise the rights
and remedies under this Paragraph.
C. All claims, costs, losses, and damages (including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals and all court or other dispute resolution
costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph
13.09 will be charged against Contractor, and a Change Order will be issued incorporating the
necessary revisions in the Contract Documents with respect to the Work; and City shall be
entitled to an appropriate decrease in the Contract Price.
D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the
performance of the Work attributable to the exercise of City’s rights and remedies under this
Paragraph 11.09.
ARTICLE 12 – COMPLETION
12.01 Contractor’s Warranty of Title
Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any
Application for Payment will pass to City no later than the time of Final Acceptance and shall be
free and clear of all Liens.
12.02 Partial Utilization
A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed
part of the Work which has specifically been identified in the Contract Documents, or which
City, determines constitutes a separately functioning and usable part of the Work that can be
used by City for its intended purpose without significant interference with Contractor’s
performance of the remainder of the Work. City at any time may notify Contractor in writing to
permit City to use or occupy any such part of the Work which City determines to be ready for its
intended use, subject to the following conditions:
1. Contractor at any time may notify City in writing that Contractor considers any such part of
the Work ready for its intended use.
2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and
Contractor shall make an inspection of that part of the Work to determine its status of
completion. If City does not consider that part of the Work to be substantially complete, City
will notify Contractor in writing giving the reasons therefor.
3. Partial Utilization will not constitute Final Acceptance by City.
12.03 Final Inspection
A. Upon written notice from Contractor that the entire Work is complete in accordance with the
Contract Documents:
00 73 10- 33
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 33 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1. within 10 days, City will schedule a Final Inspection with Contractor.
2. City will notify Contractor in writing of all particulars in which this inspection reveals that
the Work is incomplete or defective. Contractor shall immediately take such measures as are
necessary to complete such Work or remedy such deficiencies.
12.04 Final Acceptance
A. Upon completion by Contractor to City’s satisfaction, of any additional Work identified in the
Final Inspection, City will issue to Contractor a letter of Final Acceptance upon the satisfaction
of the following:
1. All documentation called for in the Contract Documents, including but not limited to the
evidence of insurance required by Paragraph 5.03;
2. consent of the surety, if any, to Final Acceptance;
3. a list of all pending or released Damage Claims against City that Contractor believes are
unsettled; and
4. affidavits of payments and complete and legally effective releases or waivers (satisfactory to
City) of all Lien rights arising out of or Liens filed in connection with the Work.
5. after all Damage Claims have been resolved:
a. directly by the Contractor or;
b. Contractor provides evidence that the Damage Claim has been reported to Contractor’s
insurance provider for resolution.
6. Issuing Final Acceptance by the City shall not relieve the Contractor of any guarantees or
other requirements of the Contract Documents which specifically continue thereafter.
ARTICLE 13 – SUSPENSION OF WORK
13.01 City May Suspend Work
A. At any time and without cause, City may suspend the Work or any portion thereof by written
notice to Contractor and which may fix the date on which Work will be resumed. Contractor
shall resume the Work on the date so fixed. During temporary suspension of the Work covered
by these Contract Documents, for any reason, the City will stop contract time on City
participation projects.
B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the
control of and without the fault or negligence of the Contractor, and should it be determined by
mutual consent of the Contractor and City that a solution to allow construction to proceed is not
00 73 10- 34
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 34 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
available within a reasonable period of time, Contractor may request an extension in Contract
Time, directly attributable to any such suspension.
C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall
store all materials in such a manner that they will not obstruct or impede the public unnecessarily
nor become damaged in any way, and he shall take every precaution to prevent damage or
deterioration of the work performed; he shall provide suitable drainage about the work, and erect
temporary structures where necessary.
ARTICLE 14 – MISCELLANEOUS
14.01 Giving Notice
A. Whenever any provision of the Contract Documents requires the giving of written notice, it will
be deemed to have been validly given if:
1. delivered in person to the individual or to a member of the firm or to an officer of the
corporation for whom it is intended; or
2. delivered at or sent by registered or certified mail, postage prepaid, to the last business
address known to the giver of the notice.
B. Business address changes must be promptly made in writing to the other party.
C. Whenever the Contract Documents specifies giving notice by electronic means such electronic
notice shall be deemed sufficient upon confirmation of receipt by the receiving party.
14.02 Computation of Times
When any period of time is referred to in the Contract Documents by days, it will be computed to
exclude the first and include the last day of such period. If the last day of any such period falls on a
Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last
day of the period.
14.03 Cumulative Remedies
The duties and obligations imposed by these General Conditions and the rights and remedies
available hereunder to the parties hereto are in addition to, and are not to be construed in any way as
a limitation of, any rights and remedies available to any or all of them which are otherwise imposed
or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the
Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically
in the Contract Documents in connection with each particular duty, obligation, right, and remedy to
which they apply.
00 73 10- 35
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 35 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
14.04 Survival of Obligations
All representations, indemnifications, warranties, and guarantees made in, required by, or given in
accordance with the Contract Documents, as well as all continuing obligations indicated in the
Contract Documents, will survive final payment, completion, and acceptance of the Work or
termination or completion of the Contract or termination of the services of Contractor.
14.05 Headings
Article and paragraph headings are inserted for convenience only and do not constitute parts of these
General Conditions.
01 11 00 - 1
DAP SUMMARY OF WORK
Page 1 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects [Insert Project Number]
Revised December 20, 2012
SECTION 01 11 00
SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Summary of Work to be performed in accordance with the Contract Documents
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract
2. Division 1 - General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Work Covered by Contract Documents
1. Work is to include furnishing all labor, materials, and equipment, and performing
all Work necessary for this construction project as detailed in the Drawings and
Specifications.
B. Subsidiary Work
1. Any and all Work specifically governed by documentary requirements for the
project, such as conditions imposed by the Drawings or Contract Documents in
which no specific item for bid has been provided for in the Proposal and the item is
not a typical unit bid item included on the standard bid item list, then the item shall
be considered as a subsidiary item of Work, the cost of which shall be included in
the price bid in the Proposal for various bid items.
C. Use of Premises
1. Coordinate uses of premises under direction of the City.
2. Assume full responsibility for protection and safekeeping of materials and
equipment stored on the Site.
3. Use and occupy only portions of the public streets and alleys, or other public places
or other rights-of-way as provided for in the ordinances of the City, as shown in the
Contract Documents, or as may be specifically authorized in writing by the City.
a. A reasonable amount of tools, materials, and equipment for construction
purposes may be stored in such space, but no more than is necessary to avoid
delay in the construction operations.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 11 00 - 2
DAP SUMMARY OF WORK
Page 2 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects [Insert Project Number]
Revised December 20, 2012
b. Excavated and waste materials shall be stored in such a way as not to interfere
with the use of spaces that may be designated to be left free and unobstructed
and so as not to inconvenience occupants of adjacent property.
c. If the street is occupied by railroad tracks, the Work shall be carried on in such
manner as not to interfere with the operation of the railroad.
1) All Work shall be in accordance with railroad requirements set forth in
Division 0 as well as the railroad permit.
D. Work within Easements
1. Do not enter upon private property for any purpose without having previously
obtained permission from the owner of such property.
2. Do not store equipment or material on private property unless and until the
specified approval of the property owner has been secured in writing by the
Contractor and a copy furnished to the City.
3. Unless specifically provided otherwise, clear all rights-of-way or easements of
obstructions which must be removed to make possible proper prosecution of the
Work as a part of the project construction operations.
4. Preserve and use every precaution to prevent damage to, all trees, shrubbery, plants,
lawns, fences, culverts, curbing, and all other types of structures or improvements,
to all water, sewer, and gas lines, to all conduits, overhead pole lines, or
appurtenances thereof, including the construction of temporary fences and to all
other public or private property adjacent to the Work.
5. Notify the proper representatives of the owners or occupants of the public or private
lands of interest in lands which might be affected by the Work.
a. Such notice shall be made at least 48 hours in advance of the beginning of the
Work.
b. Notices shall be applicable to both public and private utility companies and any
corporation, company, individual, or other, either as owners or occupants,
whose land or interest in land might be affected by the Work.
c. Be responsible for all damage or injury to property of any character resulting
from any act, omission, neglect, or misconduct in the manner or method or
execution of the Work, or at any time due to defective work, material, or
equipment.
6. Fence
a. Restore all fences encountered and removed during construction of the Project
to the original or a better than original condition.
b. Erect temporary fencing in place of the fencing removed whenever the Work is
not in progress and when the site is vacated overnight, and/or at all times to
provide site security.
c. The cost for all fence work within easements, including removal, temporary
closures and replacement, shall be subsidiary to the various items bid in the
project proposal, unless a bid item is specifically provided in the proposal.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 11 00 - 3
DAP SUMMARY OF WORK
Page 3 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects [Insert Project Number]
Revised December 20, 2012
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 25 00 - 1
DAP SUBSTITUTION PROCEDURES
Page 1 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
SECTION 01 25 00
SUBSTITUTION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. The procedure for requesting the approval of substitution of a product that is not
equivalent to a product which is specified by descriptive or performance criteria or
defined by reference to 1 or more of the following:
a. Name of manufacturer
b. Name of vendor
c. Trade name
d. Catalog number
2. Substitutions are not "or-equals".
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid. No
separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Request for Substitution - General
1. Within 30 days after award of Contract (unless noted otherwise), the City will
consider formal requests from Contractor for substitution of products in place of
those specified.
2. Certain types of equipment and kinds of material are described in Specifications by
means of references to names of manufacturers and vendors, trade names, or catalog
numbers.
a. When this method of specifying is used, it is not intended to exclude from
consideration other products bearing other manufacturer's or vendor's names,
trade names, or catalog numbers, provided said products are "or-equals," as
determined by City.
3. Other types of equipment and kinds of material may be acceptable substitutions
under the following conditions:
a. Or-equals are unavailable due to strike, discontinued production of products
meeting specified requirements, or other factors beyond control of Contractor;
or,
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 25 00 - 2
DAP SUBSTITUTION PROCEDURES
Page 2 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
b. Contractor proposes a cost and/or time reduction incentive to the City.
1.5 SUBMITTALS
A. See Request for Substitution Form (attached)
B. Procedure for Requesting Substitution
1. Substitution shall be considered only:
a. After award of Contract
b. Under the conditions stated herein
2. Submit 3 copies of each written request for substitution, including:
a. Documentation
1) Complete data substantiating compliance of proposed substitution with
Contract Documents
2) Data relating to changes in construction schedule, when a reduction is
proposed
3) Data relating to changes in cost
b. For products
1) Product identification
a) Manufacturer's name
b) Telephone number and representative contact name
c) Specification Section or Drawing reference of originally specified
product, including discrete name or tag number assigned to original
product in the Contract Documents
2) Manufacturer's literature clearly marked to show compliance of proposed
product with Contract Documents
3) Itemized comparison of original and proposed product addressing product
characteristics including, but not necessarily limited to:
a) Size
b) Composition or materials of construction
c) Weight
d) Electrical or mechanical requirements
4) Product experience
a) Location of past projects utilizing product
b) Name and telephone number of persons associated with referenced
projects knowledgeable concerning proposed product
c) Available field data and reports associated with proposed product
5) Samples
a) Provide at request of City.
b) Samples become the property of the City.
c. For construction methods:
1) Detailed description of proposed method
2) Illustration drawings
C. Approval or Rejection
1. Written approval or rejection of substitution given by the City
2. City reserves the right to require proposed product to comply with color and pattern
of specified product if necessary to secure design intent.
3. In the event the substitution is approved, if a reduction in cost or time results, it will
be documented by Change Order.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 25 00 - 3
DAP SUBSTITUTION PROCEDURES
Page 3 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
4. Substitution will be rejected if:
a. Submittal is not through the Contractor with his stamp of approval
b. Request is not made in accordance with this Specification Section
c. In the Developer’s opinion, acceptance will require substantial revision of the
original design
d. In the City’s or Developer’s opinion, substitution will not perform adequately
the function consistent with the design intent
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE
A. In making request for substitution or in using an approved product, the Contractor
represents that the Contractor:
1. Has investigated proposed product, and has determined that it is adequate or
superior in all respects to that specified, and that it will perform function for which it
is intended
2. Will provide same guarantee for substitute item as for product specified
3. Will coordinate installation of accepted substitution into Work, to include building
modifications if necessary, making such changes as may be required for Work to be
complete in all respects
4. Waives all claims for additional costs related to substitution which subsequently
arise
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 25 00 - 4
DAP SUBSTITUTION PROCEDURES
Page 4 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
EXHIBIT A
REQUEST FOR SUBSTITUTION FORM:
TO:
PROJECT: DATE:
We hereby submit for your consideration the following product instead of the specified item for
the above project:
SECTION PARAGRAPH SPECIFIED ITEM
Proposed Substitution:
Reason for Substitution:
Include complete information on changes to Drawings and/or Specifications which proposed
substitution will require for its proper installation.
Fill in Blanks Below:
A. Will the undersigned contractor pay for changes to the building design, including engineering
and detailing costs caused by the requested substitution?
B. What effect does substitution have on other trades?
C. Differences between proposed substitution and specified item?
D. Differences in product cost or product delivery time?
E. Manufacturer's guarantees of the proposed and specified items are:
Equal Better (explain on attachment)
The undersigned states that the function, appearance and quality are equivalent or superior to the
specified item.
Submitted By: For Use by City
Signature Recommended Recommended
as noted
Firm Not recommended Received late
Address By
Date
Date Remarks
Telephone
For Use by City:
Approved Rejected
City Date
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 31 19 - 1
DAP PRECONSTRUCTION MEETING
Page 1 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
SECTION 01 31 19
PRECONSTRUCTION MEETING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Provisions for the preconstruction meeting to be held prior to the start of Work to
clarify construction contract administration procedures
B. Deviations from this City of Fort Worth Standard Specification
1. No construction schedule required unless requested by the City.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Coordination
1. Attend preconstruction meeting.
2. Representatives of Contractor, subcontractors and suppliers attending meetings
shall be qualified and authorized to act on behalf of the entity each represents.
3. Meeting administered by City may be tape recorded.
a. If recorded, tapes will be used to prepare minutes and retained by City for
future reference.
B. Preconstruction Meeting
1. A preconstruction meeting will be held within 14 days after the delivery of the
distribution package to the City.
a. The meeting will be scheduled and administered by the City.
2. The Project Representative will preside at the meeting, prepare the notes of the
meeting and distribute copies of same to all participants who so request by fully
completing the attendance form to be circulated at the beginning of the meeting.
3. Attendance shall include:
a. Developer and Consultant
b. Contractor's project manager
c. Contractor's superintendent
d. Any subcontractor or supplier representatives whom the Contractor may desire
to invite or the City may request
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 31 19 - 2
DAP PRECONSTRUCTION MEETING
Page 2 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
e. Other City representatives
f. Others as appropriate
4. Preliminary Agenda may include:
a. Introduction of Project Personnel
b. General Description of Project
c. Status of right-of-way, utility clearances, easements or other pertinent permits
d. Contractor’s work plan and schedule
e. Contract Time
f. Notice to Proceed
g. Construction Staking
h. Progress Payments
i. Extra Work and Change Order Procedures
j. Field Orders
k. Disposal Site Letter for Waste Material
l. Insurance Renewals
m. Payroll Certification
n. Material Certifications and Quality Control Testing
o. Public Safety and Convenience
p. Documentation of Pre-Construction Conditions
q. Weekend Work Notification
r. Legal Holidays
s. Trench Safety Plans
t. Confined Space Entry Standards
u. Coordination with the City’s representative for operations of existing water
systems
v. Storm Water Pollution Prevention Plan
w. Coordination with other Contractors
x. Early Warning System
y. Contractor Evaluation
z. Special Conditions applicable to the project
aa. Damages Claims
bb. Submittal Procedures
cc. Substitution Procedures
dd. Correspondence Routing
ee. Record Drawings
ff. Temporary construction facilities
gg. MBE/SBE procedures
hh. Final Acceptance
ii. Final Payment
jj. Questions or Comments
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 31 19 - 3
DAP PRECONSTRUCTION MEETING
Page 3 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 32 16 - 1
DAP CONSTRUCTION PROGRESS SCHEDULE
Page 1 of 5
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised July 1, 2011
SECTION 01 32 16
CONSTRUCTION PROGRESS SCHEDULE
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. General requirements for the preparation, submittal, updating, status reporting and
management of the Construction Progress Schedule
2. Specific requirements are presented in the City of Fort Worth Schedule Guidance
Document
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES
A. Definitions
1. Schedule Tiers
a. Tier 1 - No schedule submittal required by contract. Small, brief duration
projects
b. Tier 2 - No schedule submittal required by contract, but will require some
milestone dates. Small, brief duration projects
c. Tier 3 - Schedule submittal required by contract as described in the
Specification and herein. Majority of City projects, including all bond program
projects
d. Tier 4 - Schedule submittal required by contract as described in the
Specification and herein. Large and/or complex projects with long durations
1) Examples: large water pump station project and associated pipeline with
interconnection to another governmental entity
e. Tier 5 - Schedule submittal required by contract as described in the
Specification and herein. Large and/or very complex projects with long
durations, high public visibility
1) Examples might include a water or wastewater treatment plant
2. Baseline Schedule - Initial schedule submitted before work begins that will serve
as the baseline for measuring progress and departures from the schedule.
3. Progress Schedule - Monthly submittal of a progress schedule documenting
progress on the project and any changes anticipated.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 32 16 - 2
DAP CONSTRUCTION PROGRESS SCHEDULE
Page 2 of 5
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised July 1, 2011
4. Schedule Narrative - Concise narrative of the schedule including schedule
changes, expected delays, key schedule issues, critical path items, etc
B. Reference Standards
1. City of Fort Worth Schedule Guidance Document
1.4 ADMINISTRATIVE REQUIREMENTS
A. Baseline Schedule
1. General
a. Prepare a cost-loaded baseline Schedule using approved software and the
Critical Path Method (CPM) as required in the City of Fort Worth Schedule
Guidance Document.
b. Review the draft cost-loaded baseline Schedule with the City to demonstrate
understanding of the work to be performed and known issues and constraints
related to the schedule.
c. Designate an authorized representative (Project Scheduler) responsible for
developing and updating the schedule and preparing reports.
B. Progress Schedule
1. Update the progress Schedule monthly as required in the City of Fort Worth
Schedule Guidance Document.
2. Prepare the Schedule Narrative to accompany the monthly progress Schedule.
3. Change Orders
a. Incorporate approved change orders, resulting in a change of contract time, in
the baseline Schedule in accordance with City of Fort Worth Schedule
Guidance Document.
C. Responsibility for Schedule Compliance
1. Whenever it becomes apparent from the current progress Schedule and CPM Status
Report that delays to the critical path have resulted and the Contract completion
date will not be met, or when so directed by the City, make some or all of the
following actions at no additional cost to the City
a. Submit a Recovery Plan to the City for approval revised baseline Schedule
outlining:
1) A written statement of the steps intended to take to remove or arrest the
delay to the critical path in the approved schedule
2) Increase construction manpower in such quantities and crafts as will
substantially eliminate the backlog of work and return current Schedule to
meet projected baseline completion dates
3) Increase the number of working hours per shift, shifts per day, working
days per week, the amount of construction equipment, or any combination
of the foregoing, sufficiently to substantially eliminate the backlog of work
4) Reschedule activities to achieve maximum practical concurrency of
accomplishment of activities, and comply with the revised schedule
2. If no written statement of the steps intended to take is submitted when so requested
by the City, the City may direct the Contractor to increase the level of effort in
manpower (trades), equipment and work schedule (overtime, weekend and holiday
work, etc.) to be employed by the Contractor in order to remove or arrest the delay
to the critical path in the approved schedule.
a. No additional cost for such work will be considered.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 32 16 - 3
DAP CONSTRUCTION PROGRESS SCHEDULE
Page 3 of 5
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised July 1, 2011
D. The Contract completion time will be adjusted only for causes specified in this
Contract.
a. Requests for an extension of any Contract completion date must be
supplemented with the following:
1) Furnish justification and supporting evidence as the City may deem
necessary to determine whether the requested extension of time is entitled
under the provisions of this Contract.
a) The City will, after receipt of such justification and supporting
evidence, make findings of fact and will advise the Contractor, in
writing thereof.
2) If the City finds that the requested extension of time is entitled, the City's
determination as to the total number of days allowed for the extensions
shall be based upon the approved total baseline schedule and on all data
relevant to the extension.
a) Such data shall be included in the next updating of the Progress
schedule.
b) Actual delays in activities which, according to the Baseline schedule,
do not affect any Contract completion date shown by the critical path in
the network will not be the basis for a change therein.
2. Submit each request for change in Contract completion date to the City within 30
days after the beginning of the delay for which a time extension is requested but
before the date of final payment under this Contract.
a. No time extension will be granted for requests which are not submitted within
the foregoing time limit.
b. From time to time, it may be necessary for the Contract schedule or completion
time to be adjusted by the City to reflect the effects of job conditions, weather,
technical difficulties, strikes, unavoidable delays on the part of the City or its
representatives, and other unforeseeable conditions which may indicate
schedule adjustments or completion time extensions.
1) Under such conditions, the City will direct the Contractor to reschedule the
work or Contract completion time to reflect the changed conditions and the
Contractor shall revise his schedule accordingly.
a) No additional compensation will be made to the Contractor for such
schedule changes except for unavoidable overall contract time
extensions beyond the actual completion of unaffected work, in which
case the Contractor shall take all possible action to minimize any time
extension and any additional cost to the City.
b) Available float time in the Baseline schedule may be used by the City
as well as by the Contractor.
3. Float or slack time is defined as the amount of time between the earliest start date
and the latest start date or between the earliest finish date and the latest finish date
of a chain of activities on the Baseline Schedule.
a. Float or slack time is not for the exclusive use or benefit of either the
Contractor or the City.
b. Proceed with work according to early start dates, and the City shall have the
right to reserve and apportion float time according to the needs of the project.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 32 16 - 4
DAP CONSTRUCTION PROGRESS SCHEDULE
Page 4 of 5
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised July 1, 2011
c. Acknowledge and agree that actual delays, affecting paths of activities
containing float time, will not have any effect upon contract completion times,
providing that the actual delay does not exceed the float time associated with
those activities.
E. Coordinating Schedule with Other Contract Schedules
1. Where work is to be performed under this Contract concurrently with or contingent
upon work performed on the same facilities or area under other contracts, the
Baseline Schedule shall be coordinated with the schedules of the other contracts.
a. Obtain the schedules of the other appropriate contracts from the City for the
preparation and updating of Baseline schedule and make the required changes
in his schedule when indicated by changes in corresponding schedules.
2. In case of interference between the operations of different contractors, the City will
determine the work priority of each contractor and the sequence of work necessary
to expedite the completion of the entire Project.
a. In such cases, the decision of the City shall be accepted as final.
b. The temporary delay of any work due to such circumstances shall not be
considered as justification for claims for additional compensation.
1.5 SUBMITTALS
A. Baseline Schedule
1. Submit Schedule in native file format and pdf format as required in the City of Fort
Worth Schedule Guidance Document.
a. Native file format includes:
1) Primavera (P6 or Primavera Contractor)
2. Submit draft baseline Schedule to City prior to the pre-construction meeting and
bring in hard copy to the meeting for review and discussion.
B. Progress Schedule
1. Submit progress Schedule in native file format and pdf format as required in the
City of Fort Worth Schedule Guidance Document.
2. Submit progress Schedule monthly no later than the last day of the month.
C. Schedule Narrative
1. Submit the schedule narrative in pdf format as required in the City of Fort Worth
Schedule Guidance Document.
2. Submit schedule narrative monthly no later than the last day of the month.
D. Submittal Process
1. The City administers and manages schedules through Buzzsaw.
2. Contractor shall submit documents as required in the City of Fort Worth Schedule
Guidance Document.
3. Once the project has been completed and Final Acceptance has been issued by the
City, no further progress schedules are required.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 32 16 - 5
DAP CONSTRUCTION PROGRESS SCHEDULE
Page 5 of 5
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised July 1, 2011
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE
A. The person preparing and revising the construction Progress Schedule shall be
experienced in the preparation of schedules of similar complexity.
B. Schedule and supporting documents addressed in this Specification shall be prepared,
updated and revised to accurately reflect the performance of the construction.
C. Contractor is responsible for the quality of all submittals in this section meeting the
standard of care for the construction industry for similar projects.
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 32 33 - 1
DAP PRECONSTRUCTION VIDEO
Page 1 of 2
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
SECTION 01 32 33
PRECONSTRUCTION VIDEO
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Administrative and procedural requirements for:
a. Preconstruction Videos
B. Deviations from this City of Fort Worth Standard Specification
1. Though not mandatory, it is highly recommended on infill developer projects.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Preconstruction Video
1. Produce a preconstruction video of the site/alignment, including all areas in the
vicinity of and to be affected by construction.
a. Provide digital copy of video upon request by the City.
2. Retain a copy of the preconstruction video until the end of the maintenance surety
period.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 32 33 - 2
DAP PRECONSTRUCTION VIDEO
Page 2 of 2
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 33 00 - 1
DAP SUBMITTALS
Page 1 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
SECTION 01 33 00
DAP SUBMITTALS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. General methods and requirements of submissions applicable to the following
Work-related submittals:
a. Shop Drawings
b. Product Data (including Standard Product List submittals)
c. Samples
d. Mock Ups
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Coordination
1. Notify the City in writing, at the time of submittal, of any deviations in the
submittals from the requirements of the Contract Documents.
2. Coordination of Submittal Times
a. Prepare, prioritize and transmit each submittal sufficiently in advance of
performing the related Work or other applicable activities, or within the time
specified in the individual Work Sections, of the Specifications.
b. Contractor is responsible such that the installation will not be delayed by
processing times including, but not limited to:
a) Disapproval and resubmittal (if required)
b) Coordination with other submittals
c) Testing
d) Purchasing
e) Fabrication
f) Delivery
g) Similar sequenced activities
c. No extension of time will be authorized because of the Contractor's failure to
transmit submittals sufficiently in advance of the Work.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 33 00 - 2
DAP SUBMITTALS
Page 2 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
d. Make submittals promptly in accordance with approved schedule, and in such
sequence as to cause no delay in the Work or in the work of any other
contractor.
B. Submittal Numbering
1. When submitting shop drawings or samples, utilize a 9-character submittal cross-
reference identification numbering system in the following manner:
a. Use the first 6 digits of the applicable Specification Section Number.
b. For the next 2 digits number use numbers 01-99 to sequentially number each
initial separate item or drawing submitted under each specific Section number.
c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e.
A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical
submittal number would be as follows:
03 30 00-08-B
1) 03 30 00 is the Specification Section for Concrete
2) 08 is the eighth initial submittal under this Specification Section
3) B is the third submission (second resubmission) of that particular shop
drawing
C. Contractor Certification
1. Review shop drawings, product data and samples, including those by
subcontractors, prior to submission to determine and verify the following:
a. Field measurements
b. Field construction criteria
c. Catalog numbers and similar data
d. Conformance with the Contract Documents
2. Provide each shop drawing, sample and product data submitted by the Contractor
with a Certification Statement affixed including:
a. The Contractor's Company name
b. Signature of submittal reviewer
c. Certification Statement
1) “By this submittal, I hereby represent that I have determined and verified
field measurements, field construction criteria, materials, dimensions,
catalog numbers and similar data and I have checked and coordinated each
item with other applicable approved shop drawings."
D. Submittal Format
1. Fold shop drawings larger than 8 ½ inches x 11 inches to 8 ½ inches x 11inches.
2. Bind shop drawings and product data sheets together.
3. Order
a. Cover Sheet
1) Description of Packet
2) Contractor Certification
b. List of items / Table of Contents
c. Product Data /Shop Drawings/Samples /Calculations
E. Submittal Content
1. The date of submission and the dates of any previous submissions
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 33 00 - 3
DAP SUBMITTALS
Page 3 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
2. The Project title and number
3. Contractor identification
4. The names of:
a. Contractor
b. Supplier
c. Manufacturer
5. Identification of the product, with the Specification Section number, page and
paragraph(s)
6. Field dimensions, clearly identified as such
7. Relation to adjacent or critical features of the Work or materials
8. Applicable standards, such as ASTM or Federal Specification numbers
9. Identification by highlighting of deviations from Contract Documents
10. Identification by highlighting of revisions on resubmittals
11. An 8-inch x 3-inch blank space for Contractor and City stamps
F. Shop Drawings
1. As specified in individual Work Sections includes, but is not necessarily limited to:
a. Custom-prepared data such as fabrication and erection/installation (working)
drawings
b. Scheduled information
c. Setting diagrams
d. Actual shopwork manufacturing instructions
e. Custom templates
f. Special wiring diagrams
g. Coordination drawings
h. Individual system or equipment inspection and test reports including:
1) Performance curves and certifications
i. As applicable to the Work
2. Details
a. Relation of the various parts to the main members and lines of the structure
b. Where correct fabrication of the Work depends upon field measurements
1) Provide such measurements and note on the drawings prior to submitting
for approval.
G. Product Data
1. For submittals of product data for products included on the City’s Standard Product
List, clearly identify each item selected for use on the Project.
2. For submittals of product data for products not included on the City’s Standard
Product List, submittal data may include, but is not necessarily limited to:
a. Standard prepared data for manufactured products (sometimes referred to as
catalog data)
1) Such as the manufacturer's product specification and installation
instructions
2) Availability of colors and patterns
3) Manufacturer's printed statements of compliances and applicability
4) Roughing-in diagrams and templates
5) Catalog cuts
6) Product photographs
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 33 00 - 4
DAP SUBMITTALS
Page 4 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
7) Standard wiring diagrams
8) Printed performance curves and operational-range diagrams
9) Production or quality control inspection and test reports and certifications
10) Mill reports
11) Product operating and maintenance instructions and recommended
spare-parts listing and printed product warranties
12) As applicable to the Work
H. Samples
1. As specified in individual Sections, include, but are not necessarily limited to:
a. Physical examples of the Work such as:
1) Sections of manufactured or fabricated Work
2) Small cuts or containers of materials
3) Complete units of repetitively used products color/texture/pattern swatches
and range sets
4) Specimens for coordination of visual effect
5) Graphic symbols and units of Work to be used by the City for independent
inspection and testing, as applicable to the Work
I. Do not start Work requiring a shop drawing, sample or product data nor any material to
be fabricated or installed prior to the approval or qualified approval of such item.
1. Fabrication performed, materials purchased or on-site construction accomplished
which does not conform to approved shop drawings and data is at the Contractor's
risk.
2. The City will not be liable for any expense or delay due to corrections or remedies
required to accomplish conformity.
3. Complete project Work, materials, fabrication, and installations in conformance
with approved shop drawings, applicable samples, and product data.
J. Submittal Distribution
1. Electronic Distribution
a. Confirm development of Project directory for electronic submittals to be
uploaded to City’s Buzzsaw site, or another external FTP site approved by the
City.
b. Shop Drawings
1) Upload submittal to designated project directory and notify appropriate
City representatives via email of submittal posting.
2) Hard Copies
a) 3 copies for all submittals
b) If Contractor requires more than 1 hard copy of Shop Drawings
returned, Contractor shall submit more than the number of copies listed
above.
c. Product Data
1) Upload submittal to designated project directory and notify appropriate
City representatives via email of submittal posting.
2) Hard Copies
a) 3 copies for all submittals
d. Samples
1) Distributed to the Project Representative
2. Hard Copy Distribution (if required in lieu of electronic distribution)
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 33 00 - 5
DAP SUBMITTALS
Page 5 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
a. Shop Drawings
1) Distributed to the City
2) Copies
a) 8 copies for mechanical submittals
b) 7 copies for all other submittals
c) If Contractor requires more than 3 copies of Shop Drawings returned,
Contractor shall submit more than the number of copies listed above.
b. Product Data
1) Distributed to the City
2) Copies
a) 4 copies
c. Samples
1) Distributed to the Project Representative
2) Copies
a) Submit the number stated in the respective Specification Sections.
3. Distribute reproductions of approved shop drawings and copies of approved
product data and samples, where required, to the job site file and elsewhere as
directed by the City.
a. Provide number of copies as directed by the City but not exceeding the number
previously specified.
K. Submittal Review
1. The review of shop drawings, data and samples will be for general conformance
with the design concept and Contract Documents. This is not to be construed as:
a. Permitting any departure from the Contract requirements
b. Relieving the Contractor of responsibility for any errors, including details,
dimensions, and materials
c. Approving departures from details furnished by the City, except as otherwise
provided herein
2. The review and approval of shop drawings, samples or product data by the City
does not relieve the Contractor from his/her responsibility with regard to the
fulfillment of the terms of the Contract.
a. All risks of error and omission are assumed by the Contractor, and the City will
have no responsibility therefore.
3. The Contractor remains responsible for details and accuracy, for coordinating the
Work with all other associated work and trades, for selecting fabrication processes,
for techniques of assembly and for performing Work in a safe manner.
4. If the shop drawings, data or samples as submitted describe variations and show a
departure from the Contract requirements which City finds to be in the interest of
the City and to be so minor as not to involve a change in Contract Price or time for
performance, the City may return the reviewed drawings without noting an
exception.
5. Submittals will be returned to the Contractor under 1 of the following codes:
a. Code 1
1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or
comments on the submittal.
a) When returned under this code the Contractor may release the
equipment and/or material for manufacture.
b. Code 2
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 33 00 - 6
DAP SUBMITTALS
Page 6 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of
the notations and comments IS NOT required by the Contractor.
a) The Contractor may release the equipment or material for manufacture;
however, all notations and comments must be incorporated into the
final product.
c. Code 3
1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is
assigned when notations and comments are extensive enough to require a
resubmittal of the package.
a) The Contractor may release the equipment or material for manufacture;
however, all notations and comments must be incorporated into the
final product.
b) This resubmittal is to address all comments, omissions and
non-conforming items that were noted.
c) Resubmittal is to be received by the City within 15 Calendar Days of
the date of the City's transmittal requiring the resubmittal.
d. Code 4
1) "NOT APPROVED" is assigned when the submittal does not meet the
intent of the Contract Documents.
a) The Contractor must resubmit the entire package revised to bring the
submittal into conformance.
b) It may be necessary to resubmit using a different manufacturer/vendor
to meet the Contract Documents.
6. Resubmittals
a. Handled in the same manner as first submittals
1) Corrections other than requested by the City
2) Marked with revision triangle or other similar method
a) At Contractor’s risk if not marked
b. Submittals for each item will be reviewed no more than twice at the City’s
expense.
1) All subsequent reviews will be performed at times convenient to the City
and at the Contractor's expense, based on the City's or City
Representative’s then prevailing rates.
2) Provide Contractor reimbursement to the City within 30 Calendar Days for
all such fees invoiced by the City.
c. The need for more than 1 resubmission or any other delay in obtaining City's
review of submittals, will not entitle the Contractor to an extension of Contract
Time.
7. Partial Submittals
a. City reserves the right to not review submittals deemed partial, at the City’s
discretion.
b. Submittals deemed by the City to be not complete will be returned to the
Contractor, and will be considered "Not Approved" until resubmitted.
c. The City may at its option provide a list or mark the submittal directing the
Contractor to the areas that are incomplete.
8. If the Contractor considers any correction indicated on the shop drawings to
constitute a change to the Contract Documents, then written notice must be
provided thereof to the Developer at least 7 Calendar Days prior to release for
manufacture.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 33 00 - 7
DAP SUBMITTALS
Page 7 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
9. When the shop drawings have been completed to the satisfaction of the City, the
Contractor may carry out the construction in accordance therewith and no further
changes therein except upon written instructions from the City.
10. Each submittal, appropriately coded, will be returned within 30 Calendar Days
following receipt of submittal by the City.
L. Mock ups
1. Mock Up units as specified in individual Sections, include, but are not necessarily
limited to, complete units of the standard of acceptance for that type of Work to be
used on the Project. Remove at the completion of the Work or when directed.
M. Qualifications
1. If specifically required in other Sections of these Specifications, submit a P.E.
Certification for each item required.
N. Request for Information (RFI)
1. Contractor Request for additional information
a. Clarification or interpretation of the contract documents
b. When the Contractor believes there is a conflict between Contract Documents
c. When the Contractor believes there is a conflict between the Drawings and
Specifications
1) Identify the conflict and request clarification
2. Sufficient information shall be attached to permit a written response without further
information.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 33 00 - 8
DAP SUBMITTALS
Page 8 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
12/20/2012 D. Johnson 1.4.K.8. Working Days modified to Calendar Days
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 35 13 - 1
DAP SPECIAL PROJECT PROCEDURES
Page 1 of 7
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN:103920
Revised August, 30, 2013
SECTION 01 35 13 1
SPECIAL PROJECT PROCEDURES 2
3
PART 1 - GENERAL 4
1.1 SUMMARY 5
A. Section Includes: 6
1. The procedures for special project circumstances that includes, but is not limited to: 7
a. Coordination with the Texas Department of Transportation 8
b. Work near High Voltage Lines 9
c. Confined Space Entry Program 10
d. Air Pollution Watch Days 11
e. Use of Explosives, Drop Weight, Etc. 12
f. Water Department Notification 13
g. Public Notification Prior to Beginning Construction 14
h. Coordination with United States Army Corps of Engineers 15
i. Coordination within Railroad permits areas 16
j. Dust Control 17
k. Employee Parking 18
l. Coordination with North Central Texas Council of Governments Clean 19
Construction Specification 20
B. Deviations from this City of Fort Worth Standard Specification 21
1. None. 22
C. Related Specification Sections include, but are not necessarily limited to: 23
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 24
2. Division 1 – General Requirements 25
3. Section 33 12 25 – Connection to Existing Water Mains 26
27
1.2 REFERENCES 28
A. Reference Standards 29
1. Reference standards cited in this Specification refer to the current reference 30
standard published at the time of the latest revision date logged at the end of this 31
Specification, unless a date is specifically cited. 32
2. Health and Safety Code, Title 9. Safety, Subtitle A. Public Safety, Chapter 752. 33
High Voltage Overhead Lines. 34
3. North Central Texas Council of Governments (NCTCOG) – Clean Construction 35
Specification 36
1.3 ADMINISTRATIVE REQUIREMENTS 37
A. Coordination with the Texas Department of Transportation 38
1. When work in the right-of-way which is under the jurisdiction of the Texas 39
Department of Transportation (TxDOT): 40
01 35 13 - 2
DAP SPECIAL PROJECT PROCEDURES
Page 2 of 7
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN:103920
Revised August, 30, 2013
a. Notify the Texas Department of Transportation prior to commencing any work 1
therein in accordance with the provisions of the permit 2
b. All work performed in the TxDOT right-of-way shall be performed in 3
compliance with and subject to approval from the Texas Department of 4
Transportation 5
B. Work near High Voltage Lines 6
1. Regulatory Requirements 7
a. All Work near High Voltage Lines (more than 600 volts measured between 8
conductors or between a conductor and the ground) shall be in accordance with 9
Health and Safety Code, Title 9, Subtitle A, Chapter 752. 10
2. Warning sign 11
a. Provide sign of sufficient size meeting all OSHA requirements. 12
3. Equipment operating within 10 feet of high voltage lines will require the following 13
safety features 14
a. Insulating cage-type of guard about the boom or arm 15
b. Insulator links on the lift hook connections for back hoes or dippers 16
c. Equipment must meet the safety requirements as set forth by OSHA and the 17
safety requirements of the owner of the high voltage lines 18
4. Work within 6 feet of high voltage electric lines 19
a. Notification shall be given to: 20
1) The power company (example: ONCOR) 21
a) Maintain an accurate log of all such calls to power company and record 22
action taken in each case. 23
b. Coordination with power company 24
1) After notification coordinate with the power company to: 25
a) Erect temporary mechanical barriers, de-energize the lines, or raise or 26
lower the lines 27
c. No personnel may work within 6 feet of a high voltage line before the above 28
requirements have been met. 29
C. Confined Space Entry Program 30
1. Provide and follow approved Confined Space Entry Program in accordance with 31
OSHA requirements. 32
2. Confined Spaces include: 33
a. Manholes 34
b. All other confined spaces in accordance with OSHA’s Permit Required for 35
Confined Spaces 36
D. Use of Explosives, Drop Weight, Etc. 37
1. When Contract Documents permit on the project the following will apply: 38
a. Public Notification 39
1) Submit notice to City and proof of adequate insurance coverage, 24 hours 40
prior to commencing. 41
2) Minimum 24 hour public notification in accordance with Section 01 31 13 42
E. Water Department Coordination 43
01 35 13 - 3
DAP SPECIAL PROJECT PROCEDURES
Page 3 of 7
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN:103920
Revised August, 30, 2013
1. During the construction of this project, it will be necessary to deactivate, for a 1
period of time, existing lines. The Contractor shall be required to coordinate with 2
the Water Department to determine the best times for deactivating and activating 3
those lines. 4
2. Coordinate any event that will require connecting to or the operation of an existing 5
City water line system with the City’s representative. 6
a. Coordination shall be in accordance with Section 33 12 25. 7
b. If needed, obtain a hydrant water meter from the Water Department for use 8
during the life of named project. 9
c. In the event that a water valve on an existing live system be turned off and on 10
to accommodate the construction of the project is required, coordinate this 11
activity through the appropriate City representative. 12
1) Do not operate water line valves of existing water system. 13
a) Failure to comply will render the Contractor in violation of Texas Penal 14
Code Title 7, Chapter 28.03 (Criminal Mischief) and the Contractor 15
will be prosecuted to the full extent of the law. 16
b) In addition, the Contractor will assume all liabilities and 17
responsibilities as a result of these actions. 18
F. Public Notification Prior to Beginning Construction 19
1. Prior to beginning construction on any block in the project, on a block by block 20
basis, prepare and deliver a notice or flyer of the pending construction to the front 21
door of each residence or business that will be impacted by construction. The notice 22
shall be prepared as follows: 23
a. Post notice or flyer 7 days prior to beginning any construction activity on each 24
block in the project area. 25
1) Prepare flyer on the Contractor’s letterhead and include the following 26
information: 27
a) Name of Project 28
b) City Project No (CPN) 29
c) Scope of Project (i.e. type of construction activity) 30
d) Actual construction duration within the block 31
e) Name of the contractor’s foreman and phone number 32
f) Name of the City’s inspector and phone number 33
g) City’s after-hours phone number 34
2) A sample of the ‘pre-construction notification’ flyer is attached as Exhibit 35
A. 36
3) Submit schedule showing the construction start and finish time for each 37
block of the project to the inspector. 38
4) Deliver flyer to the City Inspector for review prior to distribution. 39
b. No construction will be allowed to begin on any block until the flyer is 40
delivered to all residents of the block. 41
G. Public Notification of Temporary Water Service Interruption during Construction 42
1. In the event it becomes necessary to temporarily shut down water service to 43
residents or businesses during construction, prepare and deliver a notice or flyer of 44
the pending interruption to the front door of each affected resident. 45
2. Prepared notice as follows: 46
a. The notification or flyer shall be posted 24 hours prior to the temporary 47
interruption. 48
01 35 13 - 4
DAP SPECIAL PROJECT PROCEDURES
Page 4 of 7
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN:103920
Revised August, 30, 2013
b. Prepare flyer on the contractor’s letterhead and include the following 1
information: 2
1) Name of the project 3
2) City Project Number 4
3) Date of the interruption of service 5
4) Period the interruption will take place 6
5) Name of the contractor’s foreman and phone number 7
6) Name of the City’s inspector and phone number 8
c. A sample of the temporary water service interruption notification is attached as 9
Exhibit B. 10
d. Deliver a copy of the temporary interruption notification to the City inspector 11
for review prior to being distributed. 12
e. No interruption of water service can occur until the flyer has been delivered to 13
all affected residents and businesses. 14
f. Electronic versions of the sample flyers can be obtained from the Project 15
Construction Inspector. 16
H. Coordination with United States Army Corps of Engineers (USACE) 17
1. At locations in the Project where construction activities occur in areas where 18
USACE permits are required, meet all requirements set forth in each designated 19
permit. 20
I. Coordination within Railroad Permit Areas 21
1. At locations in the project where construction activities occur in areas where 22
railroad permits are required, meet all requirements set forth in each designated 23
railroad permit. This includes, but is not limited to, provisions for: 24
a. Flagmen 25
b. Inspectors 26
c. Safety training 27
d. Additional insurance 28
e. Insurance certificates 29
f. Other employees required to protect the right-of-way and property of the 30
Railroad Company from damage arising out of and/or from the construction of 31
the project. Proper utility clearance procedures shall be used in accordance 32
with the permit guidelines. 33
2. Obtain any supplemental information needed to comply with the railroad’s 34
requirements. 35
J. Dust Control 36
1. Use acceptable measures to control dust at the Site. 37
a. If water is used to control dust, capture and properly dispose of waste water. 38
b. If wet saw cutting is performed, capture and properly dispose of slurry. 39
K. Employee Parking 40
1. Provide parking for employees at locations approved by the City. 41
L. Coordination with North Central Texas Council of Governments (NCTCOG) Clean 42
Construction Specification [if required for the project] 43
1. Comply with equipment, operational, reporting and enforcement requirements set 44
forth in NCTCOG’s Clean Construction Specification. 45
01 35 13 - 5
DAP SPECIAL PROJECT PROCEDURES
Page 5 of 7
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN:103920
Revised August, 30, 2013
1.4 SUBMITTALS [NOT USED] 1
1.5 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 2
1.6 CLOSEOUT SUBMITTALS [NOT USED] 3
1.7 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 4
1.8 QUALITY ASSURANCE [NOT USED] 5
1.9 DELIVERY, STORAGE, AND HANDLING [NOT USED] 6
1.10 FIELD [SITE] CONDITIONS [NOT USED] 7
1.11 WARRANTY [NOT USED] 8
PART 2 - PRODUCTS [NOT USED] 9
PART 3 - EXECUTION [NOT USED] 10
END OF SECTION 11
12
Revision Log
DATE NAME SUMMARY OF CHANGE
8/31/2012 D. Johnson
1.3.B – Added requirement of compliance with Health and Safety Code, Title 9.
Safety, Subtitle A. Public Safety, Chapter 752. High Voltage Overhead Lines.
13
01 35 13 - 6
DAP SPECIAL PROJECT PROCEDURES
Page 6 of 7
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN:103920
Revised August, 30, 2013
EXHIBIT A 1
(To be printed on Contractor’s Letterhead) 2
3
4
5
Date: 6
7
CPN No.: 8
Project Name: 9
Mapsco Location: 10
Limits of Construction: 11
12
13
14
15
16
THIS IS TO INFORM YOU THAT UNDER A CONTRACT WITH THE CITY OF FORT 17
WORTH, OUR COMPANY WILL WORK ON UTILITY LINES ON OR AROUND YOUR 18
PROPERTY. 19
20
CONSTRUCTION WILL BEGIN APPROXIMATELY SEVEN DAYS FROM THE DATE 21
OF THIS NOTICE. 22
23
IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SAFETY OR ANY OTHER 24
ISSUE, PLEASE CALL: 25
26
27
Mr. <CONTRACTOR’S SUPERINTENDENT> AT <TELEPHONE NO.> 28
29
OR 30
31
Mr. <CITY INSPECTOR> AT < TELEPHONE NO.> 32
33
AFTER 4:30 PM OR ON WEEKENDS, PLEASE CALL (817) 392 8306 34
35
PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL 36
37
01 35 13 - 7
DAP SPECIAL PROJECT PROCEDURES
Page 7 of 7
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN:103920
Revised August, 30, 2013
EXHIBIT B 1
2
3
4
01 45 23
DAP TESTING AND INSPECTION SERVICES
Page 1 of 2
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised March 20, 2020
SECTION 01 45 23
TESTING AND INSPECTION SERVICES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Testing and inspection services procedures and coordination
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
a. Contractor is responsible for performing, coordinating, and payment of all
Quality Control testing.
b. City is responsible for performing and payment for first set of Quality
Assurance testing.
1) If the first Quality Assurance test performed by the City fails, the
Contractor is responsible for payment of subsequent Quality Assurance
testing until a passing test occurs.
a) Final acceptance will not be issued by City until all required payments
for testing by Contractor have been paid in full.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Testing
1. Complete testing in accordance with the Contract Documents.
2. Coordination
a. When testing is required to be performed by the City, notify City, sufficiently
in advance, when testing is needed.
b. When testing is required to be completed by the Contractor, notify City,
sufficiently in advance, that testing will be performed.
3. Distribution of Testing Reports
a. Electronic Distribution
1) Confirm development of Project directory for electronic submittals to be
uploaded to the City’s document management system, or another form of
distribution approved by the City.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 45 23
DAP TESTING AND INSPECTION SERVICES
Page 2 of 2
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised March 20, 2020
2) Upload test reports to designated project directory and notify appropriate
City representatives via email of submittal posting.
3) Hard Copies
a) 1 copy for all submittals submitted to the Project Representative
b. Hard Copy Distribution (if required in lieu of electronic distribution)
1) Tests performed by City
a) Distribute 1 hard copy to the Contractor
2) Tests performed by the Contractor
a) Distribute 3 hard copies to City’s Project Representative
4. Provide City’s Project Representative with trip tickets for each delivered load of
Concrete or Lime material including the following information:
a. Name of pit
b. Date of delivery
c. Material delivered
B. Inspection
1. Inspection or lack of inspection does not relieve the Contractor from obligation to
perform work in accordance with the Contract Documents.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
03/20/2020 D.V. Magaña Removed reference to Buzzsaw and noted that electronic submittals be uploaded
through the City’s document management system.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 50 00 - 1
DAP TEMPORARY FACILITIES AND CONTROLS
Page 1 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised JULY 1, 2011
SECTION 01 50 00
TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Provide temporary facilities and controls needed for the Work including, but not
necessarily limited to:
a. Temporary utilities
b. Sanitary facilities
c. Storage Sheds and Buildings
d. Dust control
e. Temporary fencing of the construction site
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Temporary Utilities
1. Obtaining Temporary Service
a. Make arrangements with utility service companies for temporary services.
b. Abide by rules and regulations of utility service companies or authorities
having jurisdiction.
c. Be responsible for utility service costs until Work is approved for Final
Acceptance.
1) Included are fuel, power, light, heat and other utility services necessary for
execution, completion, testing and initial operation of Work.
2. Water
a. Contractor to provide water required for and in connection with Work to be
performed and for specified tests of piping, equipment, devices or other use as
required for the completion of the Work.
b. Provide and maintain adequate supply of potable water for domestic
consumption by Contractor personnel and City’s Project Representatives.
c. Coordination
1) Contact City 1 week before water for construction is desired
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 50 00 - 2
DAP TEMPORARY FACILITIES AND CONTROLS
Page 2 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised JULY 1, 2011
d. Contractor Payment for Construction Water
1) Obtain construction water meter from City for payment as billed by City’s
established rates.
3. Electricity and Lighting
a. Provide and pay for electric powered service as required for Work, including
testing of Work.
1) Provide power for lighting, operation of equipment, or other use.
b. Electric power service includes temporary power service or generator to
maintain operations during scheduled shutdown.
4. Telephone
a. Provide emergency telephone service at Site for use by Contractor personnel
and others performing work or furnishing services at Site.
5. Temporary Heat and Ventilation
a. Provide temporary heat as necessary for protection or completion of Work.
b. Provide temporary heat and ventilation to assure safe working conditions.
B. Sanitary Facilities
1. Provide and maintain sanitary facilities for persons on Site.
a. Comply with regulations of State and local departments of health.
2. Enforce use of sanitary facilities by construction personnel at job site.
a. Enclose and anchor sanitary facilities.
b. No discharge will be allowed from these facilities.
c. Collect and store sewage and waste so as not to cause nuisance or health
problem.
d. Haul sewage and waste off-site at no less than weekly intervals and properly
dispose in accordance with applicable regulation.
3. Locate facilities near Work Site and keep clean and maintained throughout Project.
4. Remove facilities at completion of Project
C. Storage Sheds and Buildings
1. Provide adequately ventilated, watertight, weatherproof storage facilities with floor
above ground level for materials and equipment susceptible to weather damage.
2. Storage of materials not susceptible to weather damage may be on blocks off
ground.
3. Store materials in a neat and orderly manner.
a. Place materials and equipment to permit easy access for identification,
inspection and inventory.
4. Equip building with lockable doors and lighting, and provide electrical service for
equipment space heaters and heating or ventilation as necessary to provide storage
environments acceptable to specified manufacturers.
5. Fill and grade site for temporary structures to provide drainage away from
temporary and existing buildings.
6. Remove building from site prior to Final Acceptance.
D. Temporary Fencing
1. Provide and maintain for the duration or construction when required in contract
documents
E. Dust Control
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 50 00 - 3
DAP TEMPORARY FACILITIES AND CONTROLS
Page 3 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised JULY 1, 2011
1. Contractor is responsible for maintaining dust control through the duration of the
project.
a. Contractor remains on-call at all times
b. Must respond in a timely manner
F. Temporary Protection of Construction
1. Contractor or subcontractors are responsible for protecting Work from damage due
to weather.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 INSTALLATION
A. Temporary Facilities
1. Maintain all temporary facilities for duration of construction activities as needed.
3.5 [REPAIR] / [RESTORATION]
3.6 RE-INSTALLATION
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES
A. Temporary Facilities
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 50 00 - 4
DAP TEMPORARY FACILITIES AND CONTROLS
Page 4 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised JULY 1, 2011
1. Remove all temporary facilities and restore area after completion of the Work, to a
condition equal to or better than prior to start of Work.
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 55 26 - 1
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 1 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised July 1, 2011
SECTION 01 55 26
STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Administrative procedures for:
a. Street Use Permit
b. Modification of approved traffic control
c. Removal of Street Signs
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
3. Section 34 71 13 – Traffic Control
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES
A. Reference Standards
1. Reference standards cited in this specification refer to the current reference standard
published at the time of the latest revision date logged at the end of this
specification, unless a date is specifically cited.
2. Texas Manual on Uniform Traffic Control Devices (TMUTCD).
1.4 ADMINISTRATIVE REQUIREMENTS
A. Traffic Control
1. General
a. When traffic control plans are included in the Drawings, provide Traffic
Control in accordance with Drawings and Section 34 71 13.
b. When traffic control plans are not included in the Drawings, prepare traffic
control plans in accordance with Section 34 71 13 and submit to City for
review.
1) Allow minimum 10 working days for review of proposed Traffic Control.
B. Street Use Permit
1. Prior to installation of Traffic Control, a City Street Use Permit is required.
a. To obtain Street Use Permit, submit Traffic Control Plans to City
Transportation and Public Works Department.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 55 26 - 2
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 2 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised July 1, 2011
1) Allow a minimum of 5 working days for permit review.
2) Contractor’s responsibility to coordinate review of Traffic Control plans for
Street Use Permit, such that construction is not delayed.
C. Modification to Approved Traffic Control
1. Prior to installation traffic control:
a. Submit revised traffic control plans to City Department Transportation and
Public Works Department.
1) Revise Traffic Control plans in accordance with Section 34 71 13.
2) Allow minimum 5 working days for review of revised Traffic Control.
3) It is the Contractor’s responsibility to coordinate review of Traffic Control
plans for Street Use Permit, such that construction is not delayed.
D. Removal of Street Sign
1. If it is determined that a street sign must be removed for construction, then contact
City Transportation and Public Works Department, Signs and Markings Division to
remove the sign.
E. Temporary Signage
1. In the case of regulatory signs, replace permanent sign with temporary sign meeting
requirements of the latest edition of the Texas Manual on Uniform Traffic Control
Devices (MUTCD).
2. Install temporary sign before the removal of permanent sign.
3. When construction is complete, to the extent that the permanent sign can be
reinstalled, contact the City Transportation and Public Works Department, Signs
and Markings Division, to reinstall the permanent sign.
F. Traffic Control Standards
1. Traffic Control Standards can be found on the City’s Buzzsaw website.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 55 26 - 3
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 3 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised July 1, 2011
Revision Log
DATE NAME SUMMARY OF CHANGE
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 57 13 - 1
DAP STORM WATER POLLUTION PREVENTION
Page 1 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised July 1, 2011
SECTION 01 57 13
STORM WATER POLLUTION PREVENTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Procedures for Storm Water Pollution Prevention Plans
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the
Contract
2. Division 1 – General Requirements
3. Section 31 25 00 – Erosion and Sediment Control
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Construction Activities resulting in less than 1 acre of disturbance
a. Work associated with this Item is considered subsidiary to the various Items
bid. No separate payment will be allowed for this Item.
2. Construction Activities resulting in greater than 1 acre of disturbance
a. Measurement and Payment shall be in accordance with Section 31 25 00.
1.3 REFERENCES
A. Abbreviations and Acronyms
1. Notice of Intent: NOI
2. Notice of Termination: NOT
3. Storm Water Pollution Prevention Plan: SWPPP
4. Texas Commission on Environmental Quality: TCEQ
5. Notice of Change: NOC
A. Reference Standards
1. Reference standards cited in this Specification refer to the current reference
standard published at the time of the latest revision date logged at the end of this
Specification, unless a date is specifically cited.
2. Integrated Storm Management (iSWM) Technical Manual for Construction
Controls
1.4 ADMINISTRATIVE REQUIREMENTS
A. General
1. Contractor is responsible for resolution and payment of any fines issued associated
with compliance to Stormwater Pollution Prevention Plan.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 57 13 - 2
DAP STORM WATER POLLUTION PREVENTION
Page 2 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised July 1, 2011
B. Construction Activities resulting in:
1. Less than 1 acre of disturbance
a. Provide erosion and sediment control in accordance with Section 31 25 00 and
Drawings.
2. 1 to less than 5 acres of disturbance
a. Texas Pollutant Discharge Elimination System (TPDES) General Construction
Permit is required
b. Complete SWPPP in accordance with TCEQ requirements
1) TCEQ Small Construction Site Notice Required under general permit
TXR150000
a) Sign and post at job site
b) Prior to Preconstruction Meeting, send 1 copy to City Department of
Transportation and Public Works, Environmental Division, (817) 392-
6088.
2) Provide erosion and sediment control in accordance with:
a) Section 31 25 00
b) The Drawings
c) TXR150000 General Permit
d) SWPPP
e) TCEQ requirements
3. 5 acres or more of Disturbance
a. Texas Pollutant Discharge Elimination System (TPDES) General Construction
Permit is required
b. Complete SWPPP in accordance with TCEQ requirements
1) Prepare a TCEQ NOI form and submit to TCEQ along with required fee
a) Sign and post at job site
b) Send copy to City Department of Transportation and Public Works,
Environmental Division, (817) 392-6088.
2) TCEQ Notice of Change required if making changes or updates to NOI
3) Provide erosion and sediment control in accordance with:
a) Section 31 25 00
b) The Drawings
c) TXR150000 General Permit
d) SWPPP
e) TCEQ requirements
4) Once the project has been completed and all the closeout requirements of
TCEQ have been met a TCEQ Notice of Termination can be submitted.
a) Send copy to City Department of Transportation and Public Works,
Environmental Division, (817) 392-6088.
1.5 SUBMITTALS
A. SWPPP
1. Submit in accordance with Section 01 33 00, except as stated herein.
a. Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City
as follows:
1) 1 copy to the City Project Manager
a) City Project Manager will forward to the City Department of
Transportation and Public Works, Environmental Division for review
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 57 13 - 3
DAP STORM WATER POLLUTION PREVENTION
Page 3 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised July 1, 2011
B. Modified SWPPP
1. If the SWPPP is revised during construction, resubmit modified SWPPP to the City
in accordance with Section 01 33 00.
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 60 00
DAP PRODUCT REQUIREMENTS
Page 1 of 2
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised March 20, 2020
SECTION 01 60 00
PRODUCT REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. References for Product Requirements and City Standard Products List
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES [NOT USED]
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A list of City approved products for use is available through the City’s website at:
https://apps.fortworthtexas.gov/ProjectResources/ and following the directory
path: 02 - Construction Documents\Standard Products List
A. Only products specifically included on City’s Standard Product List in these Contract
Documents shall be allowed for use on the Project.
1. Any subsequently approved products will only be allowed for use upon specific
approval by the City.
B. Any specific product requirements in the Contract Documents supersede similar
products included on the City’s Standard Product List.
1. The City reserves the right to not allow products to be used for certain projects even
though the product is listed on the City’s Standard Product List.
C. Although a specific product is included on City’s Standard Product List, not all
products from that manufacturer are approved for use, including but not limited to, that
manufacturer’s standard product.
D. See Section 01 33 00 for submittal requirements of Product Data included on City’s
Standard Product List.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 60 00
DAP PRODUCT REQUIREMENTS
Page 2 of 2
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised March 20, 2020
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
10/12/12 D. Johnson Modified Location of City’s Standard Product List
4/7/2014 M.Domenech Revised for DAP application
03/20/2020 D.V. Magaña Removed reference to Buzzsaw and noted that the City approved products list is
accessible through the City’s website.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 66 00 - 1
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 1 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
SECTION 01 66 00
PRODUCT STORAGE AND HANDLING REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Scheduling of product delivery
2. Packaging of products for delivery
3. Protection of products against damage from:
a. Handling
b. Exposure to elements or harsh environments
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY AND HANDLING
A. Delivery Requirements
1. Schedule delivery of products or equipment as required to allow timely installation
and to avoid prolonged storage.
2. Provide appropriate personnel and equipment to receive deliveries.
3. Delivery trucks will not be permitted to wait extended periods of time on the Site
for personnel or equipment to receive the delivery.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 66 00 - 2
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 2 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
4. Deliver products or equipment in manufacturer's original unbroken cartons or other
containers designed and constructed to protect the contents from physical or
environmental damage.
5. Clearly and fully mark and identify as to manufacturer, item and installation
location.
6. Provide manufacturer's instructions for storage and handling.
B. Handling Requirements
1. Handle products or equipment in accordance with these Contract Documents and
manufacturer’s recommendations and instructions.
C. Storage Requirements
1. Store materials in accordance with manufacturer’s recommendations and
requirements of these Specifications.
2. Make necessary provisions for safe storage of materials and equipment.
a. Place loose soil materials and materials to be incorporated into Work to prevent
damage to any part of Work or existing facilities and to maintain free access at
all times to all parts of Work and to utility service company installations in
vicinity of Work.
3. Keep materials and equipment neatly and compactly stored in locations that will
cause minimum inconvenience to other contractors, public travel, adjoining owners,
tenants and occupants.
a. Arrange storage to provide easy access for inspection.
4. Restrict storage to areas available on construction site for storage of material and
equipment as shown on Drawings, or approved by City’s Project Representative.
5. Provide off-site storage and protection when on-site storage is not adequate.
a. Provide addresses of and access to off-site storage locations for inspection by
City’s Project Representative.
6. Do not use lawns, grass plots or other private property for storage purposes without
written permission of owner or other person in possession or control of premises.
7. Store in manufacturers’ unopened containers.
8. Neatly, safely and compactly stack materials delivered and stored along line of
Work to avoid inconvenience and damage to property owners and general public
and maintain at least 3 feet from fire hydrant.
9. Keep public and private driveways and street crossings open.
10. Repair or replace damaged lawns, sidewalks, streets or other improvements to
satisfaction of City’s Project Representative.
a. Total length which materials may be distributed along route of construction at
one time is 1,000 linear feet, unless otherwise approved in writing by City’s
Project Representative.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 66 00 - 3
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 3 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 ERECTION [NOT USED]
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE-INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL
A. Tests and Inspections
1. Inspect all products or equipment delivered to the site prior to unloading.
B. Non-Conforming Work
1. Reject all products or equipment that are damaged, used or in any other way
unsatisfactory for use on the project.
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION
A. Protect all products or equipment in accordance with manufacturer's written directions.
B. Store products or equipment in location to avoid physical damage to items while in
storage.
C. Protect equipment from exposure to elements and keep thoroughly dry if required by
the manufacturer.
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 66 00 - 4
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 4 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 70 00 - 1
DAP MOBILIZATION AND REMOBILIZATION
Page 1 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
SECTION 01 70 00
MOBILIZATION AND REMOBILIZATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Mobilization and Demobilization
a. Mobilization
1) Transportation of Contractor’s personnel, equipment, and operating supplies
to the Site
2) Establishment of necessary general facilities for the Contractor’s operation
at the Site
3) Premiums paid for performance and payment bonds
4) Transportation of Contractor’s personnel, equipment, and operating supplies
to another location within the designated Site
5) Relocation of necessary general facilities for the Contractor’s operation
from 1 location to another location on the Site.
b. Demobilization
1) Transportation of Contractor’s personnel, equipment, and operating supplies
away from the Site including disassembly
2) Site Clean-up
3) Removal of all buildings and/or other facilities assembled at the Site for this
Contract
c. Mobilization and Demobilization do not include activities for specific items of
work that are for which payment is provided elsewhere in the contract.
2. Remobilization
a. Remobilization for Suspension of Work specifically required in the Contract
Documents or as required by City includes:
1) Demobilization
a) Transportation of Contractor’s personnel, equipment, and operating
supplies from the Site including disassembly or temporarily securing
equipment, supplies, and other facilities as designated by the Contract
Documents necessary to suspend the Work.
b) Site Clean-up as designated in the Contract Documents
2) Remobilization
a) Transportation of Contractor’s personnel, equipment, and operating
supplies to the Site necessary to resume the Work.
b) Establishment of necessary general facilities for the Contractor’s
operation at the Site necessary to resume the Work.
3) No Payments will be made for:
a) Mobilization and Demobilization from one location to another on the
Site in the normal progress of performing the Work.
b) Stand-by or idle time
c) Lost profits
3. Mobilizations and Demobilization for Miscellaneous Projects
a. Mobilization and Demobilization
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 70 00 - 2
DAP MOBILIZATION AND REMOBILIZATION
Page 2 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
1) Mobilization shall consist of the activities and cost on a Work Order basis
necessary for:
a) Transportation of Contractor’s personnel, equipment, and operating
supplies to the Site for the issued Work Order.
b) Establishment of necessary general facilities for the Contractor’s
operation at the Site for the issued Work Order
2) Demobilization shall consist of the activities and cost necessary for:
a) Transportation of Contractor’s personnel, equipment, and operating
supplies from the Site including disassembly for each issued Work
Order
b) Site Clean-up for each issued Work Order
c) Removal of all buildings or other facilities assembled at the Site for
each Work Oder
b. Mobilization and Demobilization do not include activities for specific items of
work for which payment is provided elsewhere in the contract.
4. Emergency Mobilizations and Demobilization for Miscellaneous Projects
a. A Mobilization for Miscellaneous Projects when directed by the City and the
mobilization occurs within 24 hours of the issuance of the Work Order.
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Mobilization and Demobilization
a. Measure
1) This Item is considered subsidiary to the various Items bid.
b. Payment
1) The work performed and materials furnished in accordance with this Item
are subsidiary to the various Items bid and no other compensation will be
allowed.
2. Remobilization for suspension of Work as specifically required in the Contract
Documents
a. Measurement
1) Measurement for this Item shall be per each remobilization performed.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under “Measurement” will be paid for at the unit
price per each “Specified Remobilization” in accordance with Contract
Documents.
c. The price shall include:
1) Demobilization as described in Section 1.1.A.2.a.1)
2) Remobilization as described in Section 1.1.A.2.a.2)
d. No payments will be made for standby, idle time, or lost profits associated this
Item.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 70 00 - 3
DAP MOBILIZATION AND REMOBILIZATION
Page 3 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
3. Remobilization for suspension of Work as required by City
a. Measurement and Payment
1) This shall be submitted as a Contract Claim in accordance with Article 10
of Section 00 72 00.
2) No payments will be made for standby, idle time, or lost profits associated
with this Item.
4. Mobilizations and Demobilizations for Miscellaneous Projects
a. Measurement
1) Measurement for this Item shall be for each Mobilization and
Demobilization required by the Contract Documents
b. Payment
1) The Work performed and materials furnished in accordance with this Item
and measured as provided under “Measurement” will be paid for at the unit
price per each “Work Order Mobilization” in accordance with Contract
Documents. Demobilization shall be considered subsidiary to mobilization
and shall not be paid for separately.
c. The price shall include:
1) Mobilization as described in Section 1.1.A.3.a.1)
2) Demobilization as described in Section 1.1.A.3.a.2)
d. No payments will be made for standby, idle time, or lost profits associated this
Item.
5. Emergency Mobilizations and Demobilizations for Miscellaneous Projects
a. Measurement
1) Measurement for this Item shall be for each Mobilization and
Demobilization required by the Contract Documents
b. Payment
1) The Work performed and materials furnished in accordance with this Item
and measured as provided under “Measurement” will be paid for at the unit
price per each “Work Order Emergency Mobilization” in accordance with
Contract Documents. Demobilization shall be considered subsidiary to
mobilization and shall not be paid for separately.
c. The price shall include
1) Mobilization as described in Section 1.1.A.4.a)
2) Demobilization as described in Section 1.1.A.3.a.2)
d. No payments will be made for standby, idle time, or lost profits associated this
Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
1.5 SUBMITTALS [NOT USED]
1.6 INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 70 00 - 4
DAP MOBILIZATION AND REMOBILIZATION
Page 4 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 71 23 - 1
CONSTRUCTION STAKING AND SURVEY
Page 1 of 7
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN: 103920
Revised February 14, 2018
SECTION 01 71 23 1
CONSTRUCTION STAKING AND SURVEY 2
PART 1 - GENERAL 3
1.1 SUMMARY 4
A. Section Includes: 5
1. Requirements for construction staking and construction survey 6
B. Deviations from this City of Fort Worth Standard Specification 7
1. See Changes (Highlighted in Yellow). 8
C. Related Specification Sections include, but are not necessarily limited to: 9
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 10
2. Division 1 – General Requirements 11
1.2 PRICE AND PAYMENT PROCEDURES 12
A. Measurement and Payment 13
1. Construction Staking 14
a. Measurement 15
1) This Item is considered subsidiary to the various Items bid. 16
b. Payment 17
1) The work performed and the materials furnished in accordance with this 18
Item are subsidiary to the various Items bid and no other compensation will 19
be allowed. 20
2. Construction Survey 21
a. Measurement 22
1) This Item is considered subsidiary to the various Items bid. 23
b. Payment 24
1) The work performed and the materials furnished in accordance with this 25
Item are subsidiary to the various Items bid and no other compensation will be 26
allowed. 27
3. As-Built Survey 28
a. Measurement 29
1) This Item is considered subsidiary to the various Items bid. 30
b. Payment 31
1) The work performed and the materials furnished in accordance with this 32
Item are subsidiary to the various Items bid and no other compensation will be 33
allowed. 34
1.3 REFERENCES 35
A. Definitions 36
1. Construction Survey - The survey measurements made prior to or while 37
construction is in progress to control elevation, horizontal position, dimensions and 38
configuration of structures/improvements included in the Project Drawings. 39
01 71 23 - 2
CONSTRUCTION STAKING AND SURVEY
Page 2 of 7
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN: 103920
Revised February 14, 2018
2. As-built Survey –The measurements made after the construction of the 1
improvement features are complete to provide position coordinates for the features 2
of a project. 3
3. Construction Staking – The placement of stakes and markings to provide offsets 4
and elevations to cut and fill in order to locate on the ground the designed 5
structures/improvements included in the Project Drawings. Construction staking 6
shall include staking easements and/or right of way if indicated on the plans. 7
4. Survey “Field Checks” – Measurements made after construction staking is 8
completed and before construction work begins to ensure that structures marked on 9
the ground are accurately located per Project Drawings. 10
B. Technical References 11
1. City of Fort Worth – Construction Staking Standards (available on City’s Buzzsaw 12
website) – 01 71 23.16.01_ Attachment A_Survey Staking Standards 13
2. City of Fort Worth - Standard Survey Data Collector Library (fxl) files (available 14
on City’s Buzzsaw website). 15
3. Texas Department of Transportation (TxDOT) Survey Manual, latest revision 16
4. Texas Society of Professional Land Surveyors (TSPS), Manual of Practice for Land 17
Surveying in the State of Texas, Category 5 18
19
1.4 ADMINISTRATIVE REQUIREMENTS 20
A. The Contractor’s selection of a surveyor must comply with Texas Government 21
Code 2254 (qualifications based selection) for this project. 22
1.5 SUBMITTALS 23
A. Submittals, if required, shall be in accordance with Section 01 33 00. 24
B. All submittals shall be received and reviewed by the City prior to delivery of work. 25
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 26
A. Field Quality Control Submittals 27
1. Documentation verifying accuracy of field engineering work, including coordinate 28
conversions if plans do not indicate grid or ground coordinates. 29
2. Submit “Cut-Sheets” conforming to the standard template provided by the City 30
(refer to 01 71 23.16.01 – Attachment A – Survey Staking Standards). 31
1.7 CLOSEOUT SUBMITTALS 32
B. As-built Redline Drawing Submittal 33
1. Submit As-Built Survey Redline Drawings documenting the locations/elevations of 34
constructed improvements signed and sealed by Registered Professional Land 35
Surveyor (RPLS) responsible for the work (refer to 01 71 23.16.01 – Attachment A 36
– Survey Staking Standards) . 37
2. Contractor shall submit the proposed as-built and completed redline drawing 38
submittal one (1) week prior to scheduling the project final inspection for City 39
review and comment. Revisions, if necessary, shall be made to the as-built redline 40
drawings and resubmitted to the City prior to scheduling the construction final 41
inspection. 42
01 71 23 - 3
CONSTRUCTION STAKING AND SURVEY
Page 3 of 7
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN: 103920
Revised February 14, 2018
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1
1.9 QUALITY ASSURANCE 2
A. Construction Staking 3
1. Construction staking will be performed by the Contractor. 4
2. Coordination 5
a. Contact City and Developer’s Project Representative at least one week in 6
advance notifying the City of when Construction Staking is scheduled. 7
b. It is the Contractor’s responsibility to coordinate staking such that 8
construction activities are not delayed or negatively impacted. 9
3. General 10
a. Contractor is responsible for preserving and maintaining stakes. If 11
Developer’s Project Representative is required to re-stake for any reason, the 12
Contractor will be responsible for costs to perform staking. If in the opinion of 13
the City, a sufficient number of stakes or markings have been lost, destroyed 14
disturbed or omitted that the contracted Work cannot take place then the 15
Contractor will be required to stake or re-stake the deficient areas. 16
B. Construction Survey 17
1. Construction Survey will be performed by the Contractor. 18
2. Coordination 19
a. Contractor to verify that horizontal and vertical control data established in the 20
design survey and required for construction survey is available and in place. 21
3. General 22
a. Construction survey will be performed in order to construct the work shown 23
on the Construction Drawings and specified in the Contract Documents. 24
b. For construction methods other than open cut, the Contractor shall perform 25
construction survey and verify control data including, but not limited to, the 26
following: 27
1) Verification that established benchmarks and control are accurate. 28
2) Use of Benchmarks to furnish and maintain all reference lines and grades 29
for tunneling. 30
3) Use of line and grades to establish the location of the pipe. 31
4) Submit to the City copies of field notes used to establish all lines and 32
grades, if requested, and allow the City to check guidance system setup prior 33
to beginning each tunneling drive. 34
5) Provide access for the City, if requested, to verify the guidance system and 35
the line and grade of the carrier pipe. 36
6) The Contractor remains fully responsible for the accuracy of the work and 37
correction of it, as required. 38
7) Monitor line and grade continuously during construction. 39
8) Record deviation with respect to design line and grade once at each pipe 40
joint and submit daily records to the City. 41
9) If the installation does not meet the specified tolerances (as outlined in 42
Sections 33 05 23 and/or 33 05 24), immediately notify the City and correct 43
the installation in accordance with the Contract Documents. 44
C. As-Built Survey 45
1. Required As-Built Survey will be performed by the Contractor. 46
01 71 23 - 4
CONSTRUCTION STAKING AND SURVEY
Page 4 of 7
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN: 103920
Revised February 14, 2018
2. Coordination 1
a. Contractor is to coordinate with City to confirm which features require as-2
built surveying. 3
b. It is the Contractor’s responsibility to coordinate the as-built survey and 4
required measurements for items that are to be buried such that construction 5
activities are not delayed or negatively impacted. 6
c. For sewer mains and water mains 12” and under in diameter, it is acceptable 7
to physically measure depth and mark the location during the progress of 8
construction and take as-built survey after the facility has been buried. The 9
Contractor is responsible for the quality control needed to ensure accuracy. 10
3. General 11
a. The Contractor shall provide as-built survey including the elevation and 12
location (and provide written documentation to the City) of construction 13
features during the progress of the construction including the following: 14
1) Water Lines 15
a) Top of pipe elevations and coordinates for waterlines at the following 16
locations: 17
(1) Minimum every 250 linear feet, including 18
(2) Horizontal and vertical points of inflection, curvature, 19
etc. 20
(3) Fire line tee 21
(4) Plugs, stub-outs, dead-end lines 22
(5) Casing pipe (each end) and all buried fittings 23
2) Sanitary Sewer 24
a) Top of pipe elevations and coordinates for force mains and siphon 25
sanitary sewer lines (non-gravity facilities) at the following locations: 26
(1) Minimum every 250 linear feet and any buried fittings 27
(2) Horizontal and vertical points of inflection, curvature, 28
etc. 29
3) Stormwater – Not Applicable 30
b. The Contractor shall provide as-built survey including the elevation and 31
location (and provide written documentation to the City) of construction 32
features after the construction is completed including the following: 33
1) Manholes 34
a) Rim and flowline elevations and coordinates for each manhole 35
2) Water Lines 36
a) Cathodic protection test stations 37
b) Sampling stations 38
c) Meter boxes/vaults (All sizes) 39
d) Fire hydrants 40
e) Valves (gate, butterfly, etc.) 41
f) Air Release valves (Manhole rim and vent pipe) 42
g) Blow off valves (Manhole rim and valve lid) 43
h) Pressure plane valves 44
i) Underground Vaults 45
(1) Rim and flowline elevations and coordinates for each 46
Underground Vault. 47
3) Sanitary Sewer 48
a) Cleanouts 49
(1) Rim and flowline elevations and coordinates for each 50
01 71 23 - 5
CONSTRUCTION STAKING AND SURVEY
Page 5 of 7
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN: 103920
Revised February 14, 2018
b) Manholes and Junction Structures 1
(1) Rim and flowline elevations and coordinates for each 2
manhole and junction structure. 3
4) Stormwater – Not Applicable 4
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 5
1.11 FIELD [SITE] CONDITIONS [NOT USED] 6
1.12 WARRANTY 7
PART 2 - PRODUCTS 8
A. A construction survey will produce, but will not be limited to: 9
1. Recovery of relevant control points, points of curvature and points of intersection. 10
2. Establish temporary horizontal and vertical control elevations (benchmarks) 11
sufficiently permanent and located in a manner to be used throughout construction. 12
3. The location of planned facilities, easements and improvements. 13
a. Establishing final line and grade stakes for piers, floors, grade beams, parking 14
areas, utilities, streets, highways, tunnels, and other construction. 15
b. A record of revisions or corrections noted in an orderly manner for reference. 16
c. A drawing, when required by the client, indicating the horizontal and vertical 17
location of facilities, easements and improvements, as built. 18
4. Cut sheets shall be provided to the City inspector and Survey Superintendent for all 19
construction staking projects. These cut sheets shall be on the standard city template 20
which can be obtained from the Survey Superintendent (817-392-7925). 21
5. Digital survey files in the following formats shall be acceptable: 22
a. AutoCAD (.dwg) 23
b. ESRI Shapefile (.shp) 24
c. CSV file (.csv), formatted with X and Y coordinates in separate columns (use 25
standard templates, if available) 26
6. Survey files shall include vertical and horizontal data tied to original project 27
control and benchmarks, and shall include feature descriptions 28
PART 3 - EXECUTION 29
3.1 INSTALLERS 30
A. Tolerances: 31
1. The staked location of any improvement or facility should be as accurate as 32
practical and necessary. The degree of precision required is dependent on many 33
factors all of which must remain judgmental. The tolerances listed hereafter are 34
based on generalities and, under certain circumstances, shall yield to specific 35
requirements. The surveyor shall assess any situation by review of the overall plans 36
and through consultation with responsible parties as to the need for specific 37
tolerances. 38
a. Earthwork: Grades for earthwork or rough cut should not exceed 0.1 ft. vertical 39
tolerance. Horizontal alignment for earthwork and rough cut should not exceed 40
1.0 ft. tolerance. 41
01 71 23 - 6
CONSTRUCTION STAKING AND SURVEY
Page 6 of 7
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN: 103920
Revised February 14, 2018
b. Horizontal alignment on a structure shall be within .0.1ft tolerance. 1
c. Paving or concrete for streets, curbs, gutters, parking areas, drives, alleys and 2
walkways shall be located within the confines of the site boundaries and, 3
occasionally, along a boundary or any other restrictive line. Away from any 4
restrictive line, these facilities should be staked with an accuracy producing no 5
more than 0.05ft. tolerance from their specified locations. 6
d. Underground and overhead utilities, such as sewers, gas, water, telephone and 7
electric lines, shall be located horizontally within their prescribed areas or 8
easements. Within assigned areas, these utilities should be staked with an 9
accuracy producing no more than 0.1 ft tolerance from a specified location. 10
e. The accuracy required for the vertical location of utilities varies widely. Many 11
underground utilities require only a minimum cover and a tolerance of 0.1 ft. 12
should be maintained. Underground and overhead utilities on planned profile, 13
but not depending on gravity flow for performance, should not exceed 0.1 ft. 14
tolerance. 15
B. Surveying instruments shall be kept in close adjustment according to manufacturer’s 16
specifications or in compliance to standards. The City reserves the right to request a 17
calibration report at any time and recommends regular maintenance schedule be 18
performed by a certified technician every 6 months. 19
1. Field measurements of angles and distances shall be done in such fashion as to 20
satisfy the closures and tolerances expressed in Part 3.1.A. 21
2. Vertical locations shall be established from a pre-established benchmark and 22
checked by closing to a different bench mark on the same datum. 23
3. Construction survey field work shall correspond to the client’s plans. Irregularities 24
or conflicts found shall be reported promptly to the City. 25
4. Revisions, corrections and other pertinent data shall be logged for future reference. 26
27
3.2 EXAMINATION [NOT USED] 28
3.3 PREPARATION [NOT USED] 29
3.4 APPLICATION 30
3.5 REPAIR / RESTORATION 31
A. If the Contractor’s work damages or destroys one or more of the control 32
monuments/points set by the Developer’s Project Representative, the monuments shall be 33
adequately referenced for expedient restoration. 34
1. Notify City or Developer’s Project Representative if any control data needs to be 35
restored or replaced due to damage caused during construction operations. 36
a. Contractor shall perform replacements and/or restorations. 37
b. The City or Developer’s Project Representative may require at any time a 38
survey “Field Check” of any monument or benchmarks that are set be verified 39
by the Developer’s Project Representative before further associated work can 40
move forward. 41
01 71 23 - 7
CONSTRUCTION STAKING AND SURVEY
Page 7 of 7
CITY OF FORT WORTH Karis Phase 1 - CFW Sanitary Sewer Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN: 103920
Revised February 14, 2018
3.6 RE-INSTALLATION [NOT USED] 1
3.7 FIELD [OR] SITE QUALITY CONTROL 2
A. It is the Contractor’s responsibility to maintain all stakes and control data placed by the 3
Developer’s Project Representative in accordance with this Specification. This includes 4
easements and right of way, if noted on the plans. 5
B. Do not change or relocate stakes or control data without approval from the City. 6
3.8 SYSTEM STARTUP 7
A. Survey Checks 8
1. The City reserves the right to perform a Survey Check at any time deemed 9
necessary. 10
2. Checks by City personnel or 3rd party contracted surveyor are not intended to 11
relieve the contractor of his/her responsibility for accuracy. 12
13
3.9 ADJUSTING [NOT USED] 14
3.10 CLEANING [NOT USED] 15
3.11 CLOSEOUT ACTIVITIES [NOT USED] 16
3.12 PROTECTION [NOT USED] 17
3.13 MAINTENANCE [NOT USED] 18
3.14 ATTACHMENTS [NOT USED] 19
END OF SECTION 20
21
Revision Log
DATE NAME SUMMARY OF CHANGE
8/31/2012 D. Johnson
8/31/2017 M. Owen
Added instruction and modified measurement & payment under 1.2; added
definitions and references under 1.3; modified 1.6; added 1.7 closeout submittal
requirements; modified 1.9 Quality Assurance; added PART 2 – PRODUCTS ;
Added 3.1 Installers; added 3.5 Repair/Restoration; and added 3.8 System Startup.
2/14/2018 M Owen
Removed “blue text”; revised measurement and payment sections for Construction
Staking and As-Built Survey; added reference to selection compliance with TGC
2254; revised action and Closeout submittal requirements; added acceptable depth
measurement criteria; revised list of items requiring as-built survey “during” and
“after” construction; and revised acceptable digital survey file format
22
01 74 23 - 1
DAP CLEANING
Page 1 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
SECTION 01 74 23
CLEANING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Intermediate and final cleaning for Work not including special cleaning of closed
systems specified elsewhere
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
3. Section 32 92 13 – Hydro-Mulching, Seeding and Sodding
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Scheduling
1. Schedule cleaning operations so that dust and other contaminants disturbed by
cleaning process will not fall on newly painted surfaces.
2. Schedule final cleaning upon completion of Work and immediately prior to final
inspection.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 STORAGE, AND HANDLING
A. Storage and Handling Requirements
1. Store cleaning products and cleaning wastes in containers specifically designed for
those materials.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 74 23 - 2
DAP CLEANING
Page 2 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS
2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED]
2.2 MATERIALS
A. Cleaning Agents
1. Compatible with surface being cleaned
2. New and uncontaminated
3. For manufactured surfaces
a. Material recommended by manufacturer
2.3 ACCESSORIES [NOT USED]
2.4 SOURCE QUALITY CONTROL [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 APPLICATION [NOT USED]
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE-INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING
A. General
1. Prevent accumulation of wastes that create hazardous conditions.
2. Conduct cleaning and disposal operations to comply with laws and safety orders of
governing authorities.
3. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in
storm or sanitary drains or sewers.
4. Dispose of degradable debris at an approved solid waste disposal site.
5. Dispose of nondegradable debris at an approved solid waste disposal site or in an
alternate manner approved by City and regulatory agencies.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 74 23 - 3
DAP CLEANING
Page 3 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
6. Handle materials in a controlled manner with as few handlings as possible.
7. Thoroughly clean, sweep, wash and polish all Work and equipment associated with
this project.
8. Remove all signs of temporary construction and activities incidental to construction
of required permanent Work.
9. If project is not cleaned to the satisfaction of the City, the City reserves the right to
have the cleaning completed at the expense of the Contractor.
10. Do not burn on-site.
B. Intermediate Cleaning during Construction
1. Keep Work areas clean so as not to hinder health, safety or convenience of
personnel in existing facility operations.
2. At maximum weekly intervals, dispose of waste materials, debris and rubbish.
3. Confine construction debris daily in strategically located container(s):
a. Cover to prevent blowing by wind
b. Store debris away from construction or operational activities
c. Haul from site at a minimum of once per week
4. Vacuum clean interior areas when ready to receive finish painting.
a. Continue vacuum cleaning on an as-needed basis, until Final Acceptance.
5. Prior to storm events, thoroughly clean site of all loose or unsecured items, which
may become airborne or transported by flowing water during the storm.
C. Exterior (Site or Right of Way) Final Cleaning
1. Remove trash and debris containers from site.
a. Re-seed areas disturbed by location of trash and debris containers in accordance
with Section 32 92 13.
2. Sweep roadway to remove all rocks, pieces of asphalt, concrete or any other object
that may hinder or disrupt the flow of traffic along the roadway.
3. Clean any interior areas including, but not limited to, vaults, manholes, structures,
junction boxes and inlets.
4. If no longer required for maintenance of erosion facilities, and upon approval by
City, remove erosion control from site.
5. Clean signs, lights, signals, etc.
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 74 23 - 4
DAP CLEANING
Page 4 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 77 19 - 1
DAP CLOSEOUT REQUIREMENTS
Page 1 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
SECTION 01 77 19
CLOSEOUT REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. The procedure for closing out a contract
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Guarantees, Bonds and Affidavits
1. No application for final payment will be accepted until all guarantees, bonds,
certificates, licenses and affidavits required for Work or equipment as specified are
satisfactorily filed with the City.
B. Release of Liens or Claims
1. No application for final payment will be accepted until satisfactory evidence of
release of liens has been submitted to the City.
1.5 SUBMITTALS
A. Submit all required documentation to City’s Project Representative.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 77 19 - 2
DAP CLOSEOUT REQUIREMENTS
Page 2 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
1.6 INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 CLOSEOUT PROCEDURE
A. Prior to requesting Final Inspection, submit:
1. Project Record Documents in accordance with Section 01 78 39
2. Operation and Maintenance Data, if required, in accordance with Section 01 78 23
B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section
01 74 23.
C. Final Inspection
1. After final cleaning, provide notice to the City Project Representative that the Work
is completed.
a. The City will make an initial Final Inspection with the Contractor present.
b. Upon completion of this inspection, the City will notify the Contractor, in
writing within 10 business days, of any particulars in which this inspection
reveals that the Work is defective or incomplete.
2. Upon receiving written notice from the City, immediately undertake the Work
required to remedy deficiencies and complete the Work to the satisfaction of the
City.
3. Upon completion of Work associated with the items listed in the City's written
notice, inform the City, that the required Work has been completed. Upon receipt
of this notice, the City, in the presence of the Contractor, will make a subsequent
Final Inspection of the project.
4. Provide all special accessories required to place each item of equipment in full
operation. These special accessory items include, but are not limited to:
a. Specified spare parts
b. Adequate oil and grease as required for the first lubrication of the equipment
c. Initial fill up of all chemical tanks and fuel tanks
d. Light bulbs
e. Fuses
f. Vault keys
g. Handwheels
h. Other expendable items as required for initial start-up and operation of all
equipment
D. Notice of Project Completion
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 77 19 - 3
DAP CLOSEOUT REQUIREMENTS
Page 3 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
1. Once the City Project Representative finds the Work subsequent to Final Inspection
to be satisfactory, the City will issue a Notice of Project Completion (Green Sheet).
E. Supporting Documentation
1. Coordinate with the City Project Representative to complete the following
additional forms:
a. Final Payment Request
b. Statement of Contract Time
c. Affidavit of Payment and Release of Liens
d. Consent of Surety to Final Payment
e. Pipe Report (if required)
f. Contractor’s Evaluation of City
g. Performance Evaluation of Contractor
F. Letter of Final Acceptance
1. Upon review and acceptance of Notice of Project Completion and Supporting
Documentation, in accordance with General Conditions, City will issue Letter of
Final Acceptance and release the Final Payment Request for payment.
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE-INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 78 23 - 1
DAP OPERATION AND MAINTENANCE DATA
Page 1 of 5
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
SECTION 01 78 23
OPERATION AND MAINTENANCE DATA
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Product data and related information appropriate for City's maintenance and
operation of products furnished under Contract
2. Such products may include, but are not limited to:
a. Traffic Controllers
b. Irrigation Controllers (to be operated by the City)
c. Butterfly Valves
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Schedule
1. Submit manuals in final form to the City within 30 calendar days of product
shipment to the project site.
1.5 SUBMITTALS
A. Submittals shall be in accordance with Section 01 33 00. All submittals shall be
approved by the City prior to delivery.
1.6 INFORMATIONAL SUBMITTALS
A. Submittal Form
1. Prepare data in form of an instructional manual for use by City personnel.
2. Format
a. Size: 8 ½ inches x 11 inches
b. Paper
1) 40 pound minimum, white, for typed pages
2) Holes reinforced with plastic, cloth or metal
c. Text: Manufacturer’s printed data, or neatly typewritten
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 78 23 - 2
DAP OPERATION AND MAINTENANCE DATA
Page 2 of 5
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
d. Drawings
1) Provide reinforced punched binder tab, bind in with text
2) Reduce larger drawings and fold to size of text pages.
e. Provide fly-leaf for each separate product, or each piece of operating
equipment.
1) Provide typed description of product, and major component parts of
equipment.
2) Provide indexed tabs.
f. Cover
1) Identify each volume with typed or printed title "OPERATING AND
MAINTENANCE INSTRUCTIONS".
2) List:
a) Title of Project
b) Identity of separate structure as applicable
c) Identity of general subject matter covered in the manual
3. Binders
a. Commercial quality 3-ring binders with durable and cleanable plastic covers
b. When multiple binders are used, correlate the data into related consistent
groupings.
4. If available, provide an electronic form of the O&M Manual.
B. Manual Content
1. Neatly typewritten table of contents for each volume, arranged in systematic order
a. Contractor, name of responsible principal, address and telephone number
b. A list of each product required to be included, indexed to content of the volume
c. List, with each product:
1) The name, address and telephone number of the subcontractor or installer
2) A list of each product required to be included, indexed to content of the
volume
3) Identify area of responsibility of each
4) Local source of supply for parts and replacement
d. Identify each product by product name and other identifying symbols as set
forth in Contract Documents.
2. Product Data
a. Include only those sheets which are pertinent to the specific product.
b. Annotate each sheet to:
1) Clearly identify specific product or part installed
2) Clearly identify data applicable to installation
3) Delete references to inapplicable information
3. Drawings
a. Supplement product data with drawings as necessary to clearly illustrate:
1) Relations of component parts of equipment and systems
2) Control and flow diagrams
b. Coordinate drawings with information in Project Record Documents to assure
correct illustration of completed installation.
c. Do not use Project Record Drawings as maintenance drawings.
4. Written text, as required to supplement product data for the particular installation:
a. Organize in consistent format under separate headings for different procedures.
b. Provide logical sequence of instructions of each procedure.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 78 23 - 3
DAP OPERATION AND MAINTENANCE DATA
Page 3 of 5
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
5. Copy of each warranty, bond and service contract issued
a. Provide information sheet for City personnel giving:
1) Proper procedures in event of failure
2) Instances which might affect validity of warranties or bonds
C. Manual for Materials and Finishes
1. Submit 5 copies of complete manual in final form.
2. Content, for architectural products, applied materials and finishes:
a. Manufacturer's data, giving full information on products
1) Catalog number, size, composition
2) Color and texture designations
3) Information required for reordering special manufactured products
b. Instructions for care and maintenance
1) Manufacturer's recommendation for types of cleaning agents and methods
2) Cautions against cleaning agents and methods which are detrimental to
product
3) Recommended schedule for cleaning and maintenance
3. Content, for moisture protection and weather exposure products:
a. Manufacturer's data, giving full information on products
1) Applicable standards
2) Chemical composition
3) Details of installation
b. Instructions for inspection, maintenance and repair
D. Manual for Equipment and Systems
1. Submit 5 copies of complete manual in final form.
2. Content, for each unit of equipment and system, as appropriate:
a. Description of unit and component parts
1) Function, normal operating characteristics and limiting conditions
2) Performance curves, engineering data and tests
3) Complete nomenclature and commercial number of replaceable parts
b. Operating procedures
1) Start-up, break-in, routine and normal operating instructions
2) Regulation, control, stopping, shut-down and emergency instructions
3) Summer and winter operating instructions
4) Special operating instructions
c. Maintenance procedures
1) Routine operations
2) Guide to "trouble shooting"
3) Disassembly, repair and reassembly
4) Alignment, adjusting and checking
d. Servicing and lubrication schedule
1) List of lubricants required
e. Manufacturer's printed operating and maintenance instructions
f. Description of sequence of operation by control manufacturer
1) Predicted life of parts subject to wear
2) Items recommended to be stocked as spare parts
g. As installed control diagrams by controls manufacturer
h. Each contractor's coordination drawings
1) As installed color coded piping diagrams
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 78 23 - 4
DAP OPERATION AND MAINTENANCE DATA
Page 4 of 5
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
i. Charts of valve tag numbers, with location and function of each valve
j. List of original manufacturer's spare parts, manufacturer's current prices, and
recommended quantities to be maintained in storage
k. Other data as required under pertinent Sections of Specifications
3. Content, for each electric and electronic system, as appropriate:
a. Description of system and component parts
1) Function, normal operating characteristics, and limiting conditions
2) Performance curves, engineering data and tests
3) Complete nomenclature and commercial number of replaceable parts
b. Circuit directories of panelboards
1) Electrical service
2) Controls
3) Communications
c. As installed color coded wiring diagrams
d. Operating procedures
1) Routine and normal operating instructions
2) Sequences required
3) Special operating instructions
e. Maintenance procedures
1) Routine operations
2) Guide to "trouble shooting"
3) Disassembly, repair and reassembly
4) Adjustment and checking
f. Manufacturer's printed operating and maintenance instructions
g. List of original manufacturer's spare parts, manufacturer's current prices, and
recommended quantities to be maintained in storage
h. Other data as required under pertinent Sections of Specifications
4. Prepare and include additional data when the need for such data becomes apparent
during instruction of City's personnel.
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE
A. Provide operation and maintenance data by personnel with the following criteria:
1. Trained and experienced in maintenance and operation of described products
2. Skilled as technical writer to the extent required to communicate essential data
3. Skilled as draftsman competent to prepare required drawings
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 78 23 - 5
DAP OPERATION AND MAINTENANCE DATA
Page 5 of 5
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
8/31/2012 D. Johnson 1.5.A.1 – title of section removed
4/7/2014 M.Domenech Revised for DAP Application
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 78 39 - 1
DAP PROJECT RECORD DOCUMENTS
Page 1 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
SECTION 01 78 39
PROJECT RECORD DOCUMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Work associated with the documenting the project and recording changes to project
documents, including:
a. Record Drawings
b. Water Meter Service Reports
c. Sanitary Sewer Service Reports
d. Large Water Meter Reports
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
1.5 SUBMITTALS
A. Prior to submitting a request for Final Inspection, deliver Project Record Documents to
City’s Project Representative.
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE
A. Accuracy of Records
1. Thoroughly coordinate changes within the Record Documents, making adequate
and proper entries on each page of Specifications and each sheet of Drawings and
other Documents where such entry is required to show the change properly.
2. Accuracy of records shall be such that future search for items shown in the Contract
Documents may rely reasonably on information obtained from the approved Project
Record Documents.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 78 39 - 2
DAP PROJECT RECORD DOCUMENTS
Page 2 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
3. To facilitate accuracy of records, make entries within 24 hours after receipt of
information that the change has occurred.
4. Provide factual information regarding all aspects of the Work, both concealed and
visible, to enable future modification of the Work to proceed without lengthy and
expensive site measurement, investigation and examination.
1.10 STORAGE AND HANDLING
A. Storage and Handling Requirements
1. Maintain the job set of Record Documents completely protected from deterioration
and from loss and damage until completion of the Work and transfer of all recorded
data to the final Project Record Documents.
2. In the event of loss of recorded data, use means necessary to again secure the data
to the City's approval.
a. In such case, provide replacements to the standards originally required by the
Contract Documents.
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS
2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIED PRODUCTS [NOT USED]
2.2 RECORD DOCUMENTS
A. Job set
1. Promptly following receipt of the Notice to Proceed, secure from the City, at no
charge to the Contractor, 1 complete set of all Documents comprising the Contract.
B. Final Record Documents
1. At a time nearing the completion of the Work and prior to Final Inspection, provide
the City 1 complete set of all Final Record Drawings in the Contract.
2.3 ACCESSORIES [NOT USED]
2.4 SOURCE QUALITY CONTROL [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 MAINTENANCE DOCUMENTS
A. Maintenance of Job Set
1. Immediately upon receipt of the job set, identify each of the Documents with the
title, "RECORD DOCUMENTS - JOB SET".
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 78 39 - 3
DAP PROJECT RECORD DOCUMENTS
Page 3 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
2. Preservation
a. Considering the Contract completion time, the probable number of occasions
upon which the job set must be taken out for new entries and for examination,
and the conditions under which these activities will be performed, devise a
suitable method for protecting the job set.
b. Do not use the job set for any purpose except entry of new data and for review
by the City, until start of transfer of data to final Project Record Documents.
c. Maintain the job set at the site of work.
3. Coordination with Construction Survey
a. At a minimum clearly mark any deviations from Contract Documents
associated with installation of the infrastructure.
4. Making entries on Drawings
a. Record any deviations from Contract Documents.
b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the
change by graphic line and note as required.
c. Date all entries.
d. Call attention to the entry by a "cloud" drawn around the area or areas affected.
e. In the event of overlapping changes, use different colors for the overlapping
changes.
5. Conversion of schematic layouts
a. In some cases on the Drawings, arrangements of conduits, circuits, piping,
ducts, and similar items, are shown schematically and are not intended to
portray precise physical layout.
1) Final physical arrangement is determined by the Contractor, subject to the
City's approval.
2) However, design of future modifications of the facility may require
accurate information as to the final physical layout of items which are
shown only schematically on the Drawings.
b. Show on the job set of Record Drawings, by dimension accurate to within 1
inch, the centerline of each run of items.
1) Final physical arrangement is determined by the Contractor, subject to the
City's approval.
2) Show, by symbol or note, the vertical location of the Item ("under slab", "in
ceiling plenum", "exposed", and the like).
3) Make all identification sufficiently descriptive that it may be related
reliably to the Specifications.
c. The City may waive the requirements for conversion of schematic layouts
where, in the City's judgment, conversion serves no useful purpose. However,
do not rely upon waivers being issued except as specifically issued in writing
by the City.
B. Final Project Record Documents
1. Transfer of data to Drawings
a. Carefully transfer change data shown on the job set of Record Drawings to the
corresponding final documents, coordinating the changes as required.
b. Clearly indicate at each affected detail and other Drawing a full description of
changes made during construction, and the actual location of items.
c. Call attention to each entry by drawing a "cloud" around the area or areas
affected.
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
01 78 39 - 4
DAP PROJECT RECORD DOCUMENTS
Page 4 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
d. Make changes neatly, consistently and with the proper media to assure
longevity and clear reproduction.
2. Transfer of data to other Documents
a. If the Documents, other than Drawings, have been kept clean during progress of
the Work, and if entries thereon have been orderly to the approval of the City,
the job set of those Documents, other than Drawings, will be accepted as final
Record Documents.
b. If any such Document is not so approved by the City, secure a new copy of that
Document from the City at the City's usual charge for reproduction and
handling, and carefully transfer the change data to the new copy to the approval
of the City.
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE-INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP Application
Karis Phase 1 - CFW Sanitary Sewer Connection
CPN:103920
KARIS - PHASE 1, SECTIONS A, B & C
CROWLEY, TEXAS
SUBMITTED TO:
PROJECT NO.
SUBMITTED DATE:
THE NEHEMIAH COMPANY, LLC
0521-3082
September 14, 2021
Geotechnical & Environmental Engineering
Construction Materials Testing
L aboratory Testing
LANDTEC ENGINEERS, LLC 3906 W IH-20 Suite 100 Arlington, Texas 76017 / 817.572.2818
Arlington I The Colony
September 14, 2021
Report No. 0521-3082
John Jordan | Senior Project Manager
The Nehemiah Company | Real Estate Development
2201 E. Lamar Blvd. Ste. 115
Arlington, TX 76006
RE: Geotechnical Engineering Exploration & Report
Karis - Phase 1, Sections A, B & C
Crowley, Texas
Dear John:
The results of our geotechnical study for the referenced project are presented in the
following engineering report. The study has been conducted in general agreement with our
proposal and your subsequent authorization to proceed.
Thank you for this opportunity to provide engineering services on this project. If you have
any questions, please let us know.
Sincerely,
LANDTEC ENGINEERS, LLC
September 14, 2021 September 14, 2021
G. Scott Graves, P.E., M.Eng. Thomas D. Baker, P.E., RPLS
Project Engineer Sr. Geotechnical Engineer & Principal
Texas Board of Professional Engineers and Land Surveyors
PE Firm No. F-000329 / RPLS Firm No. 100956-00
Distribution by PDF: John Jordan
Rachel Coward
Howard Porteus
Caryn Erskine
Chris Conners
Scott Koehler
LANDT E C ENGINEER S
3082 Karis- Phase 1-Geot-Sept2021.doc i
TABLE OF CONTENTS
________________________________________________________________
Section Page No.
Executive Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ii
1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.1 Project Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.2 Purpose and Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.3 Prior Geotechnical Explorations and Reports . . . . . . . . . . . . 2
2 Subsurface Conditions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
3 Analysis and Recommendations . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
3.1 Geotechnical Considerations . . . . . . . . . . . . . . . . . . . . . . . . 4
3.2 Potential Soil Movements . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
3.3 Slab-on-Grade Foundation . . . . . . . . . . . . . . . . . . . . . . . . . . 7
3.4 Moisture Conditioning to Reduce PVM . . . . . . . . . . . . . . . . . 8
4 Moisture Control – Site Grading and Landscaping . . . . . . . . . . . . . . 9
5 General Site Grading . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
5.1 General Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
5.2 Subgrade Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
5.3 Placing of Material . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
5.4 Moisture and Density Control . . . . . . . . . . . . . . . . . . . . . . . . 13
5.5 Excavations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
5.6 Acceptance of Imported Fill . . . . . . . . . . . . . . . . . . . . . . . . . . 17
6 General Comments and Conditions . . . . . . . . . . . . . . . . . . . . . . . . 17
______________________________________________________________
APPENDIX A –Plan of Borings, Boring Logs & General Notes, Description of Field
Exploration
APPENDIX B – Summary of Laboratory Results, Description of Laboratory Testing
APPENDIX C – Moisture Conditioning (MC) Recommendations
APPENDIX D – Drainage Illustrations
APPENDIX E – Important Information about Your Geotechnical Engineering Repor
LANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc ii
EXECUTIVE SUMMARY
Karis
Phase 1, Sections A, B, and C
Crowley, Texas
September 14, 2021
The following information presents a summary of the principal findings in the geotechnical
engineering exploration and report prepared for Phase 1, Sections A, B and C of the Karis
Development in Crowley, Texas.
Based on the results of new borings performed in Phase 1 in late August 2021 along
with several backhoe excavation test pits, this report presents the results of
additional site exploration and laboratory tests. The additional information was used
to develop recommendations for lots requiring moisture conditioning and
recommendations for post-tension, slab-on-grade foundations.
Twenty (20) new borings were drilled at the site to depths of approximately 10 to 30
feet below existing grade on August 23 and 31, 2021 and 15 backhoe test pits were
made by the utility contractor on August 23, 2021. The field work was performed
after the grading contractor had cleared the Phase 1 area of trees, brush, and grass.
Actual site grading work, including the beginning of cutting and filling was initiated
by Mario Sinacola & Sons on September 2, 2021.
Subsurface conditions consist of various depths of clay, calcareous (limy) clay,
severely weathered limestone, weathered limestone, and limestone. See Section
1.0, Item 1.3 of this report and see GeoReport Numbers 2770-A and 2770-B for
descriptions of subsurface conditions across the site.
Based on the information developed from our borings, tests, site observations, and
analysis of data, Potential Vertical Movement (PVM) values on the order of
approximately 2 to 3 inches have been determined for most of Phase 1. Exceptions
include areas where the PVM is over 4½ inches as identified on the Plan of Borings
in Appendix A, Drawing A1. Lots outlined in blue color are recommended for
Moisture Conditioning to a depth of 6 feet and the lots with red color are
recommended for 4 feet of Moisture Conditioning as described in detail in the text
and Appendix C. The recommended depths are below existing (original) grade
before the beginning of site grading. Any fill material placed on the lots should also
be moisture conditioned.
An estimated total of 49 lots should be Moisture Conditioned in Phase 1, Sections A
and B. Section C, north of the electrical transmission line, does not have lots that
need to be moisture conditioned based on current information from borings and test
pits. The proposed Amenity Center site will not be moisture conditioned at this time.
LANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc iii
During moisture conditioning work, some lots could be added to the moisture
conditioning list and/or some lots may not require moisture conditioning and will be
deleted.
Geotechnical recommendations for design of post-tensioned, slab-on-grade
foundations are provided herein.
Recommendations for street pavement subgrade preparation were provided in the
original geotechnical report. See GeoReport No. 2770-A. Additional paving
subgrade recommendations may be required as the grading contractor establishes
final street grade (especially with the subgrade is limestone rock) and as the utility
contractor excavates for utilities along the street.
Earthwork and site grading recommendations are provided for stripping vegetation,
subgrade preparation, proof rolling, compaction, moisture, lift thickness and testing.
Site drainage is always a key element for house pads and the long-term
performance of slab-on-ground foundations will be dependent on providing drainage
swales for positive drainage around and between house foundations, both during
and after construction.
The “Executive Summary” is intended to be a brief overview and, therefore, the text of the
entire report should be followed for specific geotechnical recommendations. The section
titled General Comments and Conditions should be read for an understanding of the report
limitations.
LANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc 1
1.0 INTRODUCTION
1.1 Project Description
The following geotechnical engineering report presents the results of additional
geotechnical exploration, testing and analysis for Phase 1, Sections A, B, and C of the
Karis Development in Crowley, Texas.
A copy of the latest site plan showing the proposed streets, and lots was provided by
Graham Associates. We understand homes in Phase 1 will be one and two story in height
and will not have basements. Future grading (cuts and fills) is anticipated to be in the range
of 1 to 3 feet of cut and approximately 1 to 7 feet of fill in some locations.
Loading conditions for houses with up to two stories are anticipated to be approximately
1,200 pounds per linear foot or less for grade beams supporting masonry walls.
At the time of the recent test borings and backhoe test pits, Phase 1 of the site had just
been cleared of trees, brush, and grass. Site grading for internal utilities, streets and house
pads started a few days after the borings and test pits were made.
1.2 Purpose and Scope
The purpose of these services is to provide information and geotechnical engineering
recommendations for homes in the proposed development. Our scope of services included
the following.
Explore subsurface conditions and obtain soil samples.
Obtain physical soil properties by laboratory testing including classification, strength,
dry unit weight and particularly to determine current soil moisture content and swell
potential.
Provide an estimate of the Potential Soil Movement (PVM) values using both Tex-
124-E calculations and swell test data.
Determine the need for remediation of lots and if Moisture Conditioning is required.
Provide foundation recommendations and allowable soil bearing capacity.
Provide recommendations for general earthwork and fill placement including
compaction and moisture requirements.
LANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc 2
The geotechnical recommendations presented in this report are based on the available
information provided by the client and subsurface conditions described in this report. If any
of the stated information is incorrect, please inform LandTec Engineers in writing so that we
may amend the recommendations presented in this report if appropriate.
It is recommended that LandTec be retained to review those portions of the plans and
specifications for this project that pertain to geotechnical recommendations contained in this
report to determine whether the recommendations have been interpreted as intended. This
is typically done when the plans are at the 50 to 75 percent design level. Additionally, the
site grading plan should be provided to LandTec in PDF and AutoCAD format.
The scope of services did not include any slope stability analysis for embankments, cut-fill
slopes, excavations or retaining walls. These services can be provided under a separate
proposal, if requested by the client.
The scope of services did not include an environmental assessment for determining the
presence or absence of wetlands, or hazardous or toxic materials in the soil, bedrock,
surface water, groundwater, or air on or below, or around this site. Any statements in this
report or on the boring logs regarding odors, colors, and unusual or suspicious items or
conditions are strictly for informational purposes.
1.3 Prior Geotechnical Explorations and Reports
The following information presents a chronological order of the geotechnical explorations
and reports prepared for the Karis Development.
First GeoReport: LandTec performed the initial geotechnical exploration of the planned
development in April of 2019 and Report No. 2770-A was issued on May 14, 2019. Borings
made for this report were drilled in areas of the large tract of land accessible to truck
mounted and all-terrain drill rigs. Wooded areas of the tract were not explored at that time.
A total of 43 widely spaced borings were made during this time. Graham Associates staked
the boring locations and provided LandTec with elevations and coordinates which are
included on the boring logs.
Subsurface soil and rock conditions along with geologic formations and alluvial soils
encountered in the initial 43 borings were described in the original report. Boring location
maps, boring logs, subsurface soil and rock profiles, soil tests and recommendations for
earthwork were included in the report. The report was provided to the client and civil
engineer and a meeting was held in July 2019 at The Nehemiah Company office off N.
Collins Street with representatives of Graham Associates, Nehemiah and LandTec to
review the GeoReport and discuss soil and rock conditions, areas of shallow soils over hard
to very hard limestone rock, laboratory test results, the need for additional borings once the
site is cleared, and other general items typical of a site development project.
LANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc 3
Second GeoReport: LandTec performed additional borings at Karis in August 2019 and
issued a factual report called Addendum No. 1 (Report No. 2770-B) on September 11,
2019. Sixteen (16) new borings were made in accessible areas. The site had not been
cleared when these borings were made. The purpose for these additional borings and
report was to explore tracts south of Deer Creek and north of the electrical / gas line
easement. Information in the addendum included color coded maps indicating areas of clay
and areas of shallow limestone rock, as best could be determined at that time, since the
site had not been cleared for access to all planned boring locations.
Tables were provided in the text describing the subsurface conditions in the different
Phases, percent of area with estimated clay soils or shallow limestone rock, rock hardness,
and estimated Potential Vertical Movement (PVM) values were provided for the various
phases in Karis.
Third GeoReport: The report presented herein includes new borings and backhoe test pits
made in late August 2021 following the clearing of Phase 1, Sections A, B, and C. The
Report No. is 3082 submitted September 14, 2021. A total of 20 new borings and 15
backhoe test pits were made in Phase 1 to further explore the areas of anticipated deep
clay soils, areas of shallow hard to very hard limestone rock, obtain soil samples for
laboratory tests, and provide the utility contractor the opportunity to explore the hardness of
the limestone rock in advance of utility installation. Selected boring logs made previously for
the First and Second GeoReports which apply to Phase 1, Sections A, B, and C are
included in this report for reference. This includes B-51, B-59, B-62, B-85, B-86, and B-131.
The report presents geotechnical information for design of post-tension slab-on-grade
foundations, earthwork recommendations, Potential Vertical Movement (PVM) values
based on the use of Method Tex-124-E and swell tests, and recommendations for Moisture
Conditioning of specific lots are provided.
2.0 SUBSURFACE CONDITIONS
The new borings and backhoe test pits made in late August 2021 for Karis, Phase 1
indicate subsurface soil and rock conditions as encountered and described in the two
previous subsurface explorations. See Report No’s 2770-A and 2770-B submitted in May
and September 2019, respectively.
Subsurface seepage was not observed in the borings and backhoe test pits made in late
August 2021. Subsequent checks for seepage water made after the completion of drilling
and test pit excavation did not indicate the presence of shallow seepage.
LANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc 4
The site has been classified with respect to seismic design criteria contained in the 2015
International Building Code (IBC), Section 1613 1. The criteria require characterization of
the upper 100 feet of subsurface materials. Based on the IBC criteria, the site is classified
as Site Class “C” for the borings as per Table 1613.5.2 for the upper 20 to 30 feet. Note the
IBC requires a site soil profile determination extending a depth of 100 feet for seismic site
classification. However, our scope of services did not include a boring to 100 feet. The
deepest borings extended to 30 feet, and it can only be estimated that the soils/rocks
encountered continues to a depth of 100 feet.
3.0 ANALYSIS AND RECOMMENDATIONS
3.1 Geotechnical Considerations
Subsurface conditions at this site consist of a wide range of soils including clays and sandy
calcareous (limy) clays. The clays have the potential for some volume change (shrink and
swell) movements with variations in soil moisture content. Where the clay soils are deeper,
they can subject shallow foundations, slabs, flatwork, sidewalks, and paving placed on the
soil to differential post construction movements due to moisture fluctuations in the soils.
Differential movement within the foundation can be prevented by using a pier and beam
foundation. This type of foundation consists of drilled piers placed below the zone of
seasonal moisture change and/or to a specific bearing depth or material. If slab
movements must be limited to less than one inch, structurally suspended slabs and grade
beams are recommended for areas of deeper clay soils. The slab and grade beams are
structurally supported above the ground by the drilled pier foundation. If a pier and beam
foundation system is needed, additional geotechnical information will be required on a lot-
by-lot basis to design this type of foundation.
We understand proposed one- and two-story homes planned for this phase will be
supported by slab-on-grade, post-tensioned foundations. This type of soil supported slab-
on-grade will have some level of risk. Soil supported slab-on-grade foundations are not
designed to resist soil and foundation movements resulting from climate anomalies,
sewer/plumbing leaks, excessive landscape irrigation, lack of irrigation, poor drainage, lack
of proper maintenance of drainage swells and roof downspouts, and/or surface and
subsurface water ponding around and below the foundation. Additionally, plumbing
trenches and/or other types of trenches should not be a conduit to allow storm water and/or
any other sources of water to flow from the perimeter of the foundation to the area below
the house.
1 International Building Code (2015). Section 1613, Earthquake Loads
L ANDTEC E NGINEER S
3082 Karis- Phase 1-Geot-Sept2021.doc 5
Since lot drainage is one of the most important items to the success of slab-on-grade
foundations on potentially expansive clay soils, the builder and homeowner should not
change or block drainage swales around and between houses. The swales were designed
by the civil engineer and installed by the developer to allow storm water and other water to
quickly flow away from the house pad to prevent ponding of water around and/or below the
house.
Geotechnical design information for shallow slab-on-grade foundations is included in the
following paragraphs. If the Post Tensioned Institute (PTI) design methodology is utilized
by the structural engineer, both climatically controlled and non-climatically controlled
variables should be accounted for in the overall design.
3.2 Potential Soil Movements
Clay soils encountered at this site can undergo shrink and swell as the soil moisture content
fluctuates during seasonal wet and dry cycles. The potential magnitude of soil movements
can only be estimated, due to factors influenced by specific soil properties such as moisture
and density, overburden pressure, moisture attraction within the clay mass, site drainage,
ponding of surface water, and the overall soil moisture contents at various times during and
post foundation installation. The methods used to estimate soil movement include the
following.
One of the methods used to estimate soil movement includes the Texas Department of
Transportation (TxDOT) Method 124-E for determining Potential Vertical Rise (PVR). Using
this method as a guide only, the procedure can be used to determine a value or range of
values for predicted movements of expansive clay soils when they change from “dry” to
“wet” soil moisture conditions.
Swell tests are also used to estimate the amount of soil movement and a significant number
of swell tests were performed on representative soil samples from the borings. They were
used to determine the amount of soil movement and were compared to the Method Tex-
124-E values obtained. In some cases, the obtained soil movement values were similar
and in other cases the numbers obtained using swell tests exceeded the Method Tex-124-E
values.
Residential developments, where potentially expansive clay soils are present, will typically
have variable soil and climatically controlled soil moisture conditions, especially with the
ever-changing North Texas weather, ranging from wet, rainy years to other years with
extreme drought. Subsurface conditions consisting of expansive clay fills with variable
moisture, density and plasticity also impact the design of slab-on-grade foundations. The
slab designer must choose from a range of possible design assumptions used in each of
L ANDTEC E N GINEE R S
3082 Karis- Phase 1-Geot-Sept2021.doc 6
the geotechnical engineer’s models to conscientiously choose the proper set of conditions
that are applicable at the time of construction and location of each slab-on-grade
foundation.
The term Potential Vertical Movement (PVM) is often considered as a measurement of the
change in height of a building slab or pavement from its original constructed elevation. The
acronym PVM is used in this report to represent the amount of movement.
Based on the information developed from our field and laboratory programs, Method Tex-
124-E, swell tests, and our experience with similar soil conditions, we estimate the
subgrade soils could subject the proposed structures to PVM values of approximately 2 to
3 inches.
However, the exception is the area where the PVM is over 4½ inches and outlined on the
Plan of Borings included on Drawing A1 in Appendix A. Lots adjacent to the identified lots
could also have PVM’s greater than 4½ inches.
The clay soils encountered at the proposed Amenity Center site should also be moisture
conditioned to a depth of at least 6 feet below existing grade before any fill is placed on the
site. All fill should be moisture conditioned as well. We understand as of September 9,
2021, moisture conditioning the Amenity Center site in Phase 1, Section A will be
postponed until the final site-specific location of the Amenity Center is determined.
PVM SUMMARY:
Requirement for PVM: Maximum of 4½ inches.
See Drawing A1 for the areas outlined where estimated PVM values over 4½ inches
are located. The blue color outline requires 6 feet of moisture conditioning, and the
red color outline requires 4 feet of moisture conditioning. The recommended
moisture conditioning depths are below existing (original) grade before any fill is
placed. All fill placed on the lots throughout Phase 1 will also need to be moisture
conditioned and covered with poly.
An estimated total of 49 lots are recommended for Moisture Conditioning. During the
moisture conditioning process, LandTec should be contracted to observe the work
and determine if the number of lots can be reduced depending on the soil conditions
found during excavation.
L ANDTEC ENGIN EERS
3082 Karis- Phase 1-Geot-Sept2021.doc 7
3.3 Slab-On-Grade Foundations
Stiffened, monolithically placed slab-on-grade foundations, either rebar or post-tensioned,
should be designed by the structural slab design engineer to resist the estimated differential
movements as provided herein. Note the PTI design methodology only accounts for
climatically controlled variables. Non-climatically controlled variables include, but are not
limited to pre-existing vegetation, slopes, cut and fill sections, landscaping, irrigation,
installation of post-construction trees and droughts. The final design of the foundation
system should also consider the anticipated PVM which has been estimated.
Grade beam and footing excavations should be observed to determine that all excessively
loose, soft, or otherwise undesirable materials are removed and that foundations will bear
on satisfactory material. Soil exposed in the bases of all satisfactory grade beam
excavations should be protected against detrimental change in condition such as from
disturbance, rain, or excessive drying. Surface runoff should be drained away from the
excavations and not allowed to pond. See Section 4.0 Moisture Control, for
recommended site grading and landscaping requirements.
Beams may be designed based on an allowable soil bearing pressure of 1,500 pounds per
square foot or less within the shallow soils. The beams should extend eighteen (18) inches
into natural undisturbed soil or compacted and tested fill. The beam depth is given
regarding bearing capacity and is not intended to be a structural recommendation regarding
stiffness. The beam width should be 10 inches minimum. A moisture barrier material should
be used beneath the slab to limit moisture migration.
Grade beam and footing excavations should be observed to determine that all excessively
loose, soft, or otherwise undesirable materials are removed and that foundations will bear
on satisfactory material. Soil exposed in the bases of all satisfactory grade beam
excavations should be protected against detrimental change in condition such as from
disturbance, rain, or excessive drying. Surface runoff should be drained away from the
excavations and not allowed to pond.
These values should be utilized by the structural engineer to design a foundation system
which can accommodate anticipated climatically and non-climatically controlled
movements. Accordingly, while PTI values for climatically driven conditions are provided,
estimates of non-climatically controlled movements are also provided and intended for
incorporation into the final structural design.
LANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc 8
Table 3-1
Estimated Slab-On-Grade Design Parameters
EEddggee MMooiissttuurree VVaarriiaattiioonn,, eemm DDiiffffeerreennttiiaall SSwweellll,, yymm
CCeenntteerr LLiifftt,, fftt.. EEddggee LLiifftt,, fftt.. CCeenntteerr LLiifftt,, iinncchheess EEddggee LLiifftt,, iinncchheess
77..00 33..88 22..00 22..77
NNootteess::
1 Values based on VOLFLOW Version 1.5 and Design of Post Tension Slabs-on-Grade, Third
Addition.
2 The original research which forms the basis for the PTI design method extended only to Ym
values of 4 inches. Alternatively, for Ym values over 4 inches a different type of foundation
design method, such as finite elements, may be used. Consideration should be given to
using methods other than PTI for design to resist the estimated large differential soil
movements.
3.4 Moisture Conditioning to Reduce PVM
To reduce the PVM to less than 4½ inches, we recommend the soils be moisture
conditioned to a depth of 6 feet for lots outlined in blue and for lots outlined in red to a
depth of 4 feet deep as shown on Drawing A1 in Appendix A. The proposed Amenity
Center site will not be moisture conditioned at this time.
The recommended moisture conditioning depths are below existing (original) grade before
any fill is placed. All fill placed on the lots throughout Phase 1 will also need to be moisture
conditioned and covered with polyethylene sheeting.
We recommend a pre-construction Moisture Conditioning meeting be held, preferably
at the jobsite, and attended by representatives of the owner, contractor, project
superintendent, earthwork equipment operator and geotechnical engineer of record. The
purpose of the site meeting is to discuss the moisture conditioning depths, compaction,
watering and testing requirements, and preparation the final house pads wrapped in poly.
The intent of moisture conditioning is to construct a uniform building pad below the
foundation to reduce (to an acceptable level) the potential for slab movement associated
with volumetric changes within the soils due to moisture variations to an acceptable level.
The actual movements could be greater if poor drainage conditions allow ponded water
and/or other sources of moisture are allowed to infiltrate beneath the foundation after
construction.
LANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc 9
Building pad preparation should include the following to provide a uniform pad to place the
slab. See Appendix C for complete Moisture Conditioning recommendations.
A minimum of 5 feet outside the building line is recommended. Additional areas to
be considered for moisture conditioning, depending on the risk level and the desired
reduction in soil movement includes sidewalks, drives, porches, patios, and any
other areas where it is desired to reduce the soil movement.
Once the excavation is made, scarify the bottom of the excavation a minimum of 12-
inches deep with dozer or loader ripper teeth and rip at least two different directions
approximately 90 degrees to each other, adjust the soils moisture in the bottom of
the excavation, re-compact and test as referenced herein.
Place the excavated soil back in the excavation in 8-inch loose lifts and compact to
a uniform density ranging from 93 to 98 percent of standard Proctor (ASTM D698) at
a minimum moisture content of plus four percentage points above optimum (+4 and
above).
Moisture conditioned lots should be covered with minimum 10-mil polyethylene
plastic sheeting that is covered with 8 to 10-inches of soil.
See the complete Moisture Conditioning requirements listed in Appendix C.
4.0 MOISTURE CONTROL – SITE GRADING AND LANDSCAPING
To reduce the potential for moisture induced soil movement (uplift) as well as shrinkage
(settlement), it is very important that measures be taken to control moisture changes
around and below the structure. The following recommendations/comments should be
incorporated into the overall project design.
1. Site grading should be designed to provide surface drainage so that water does not
pond during or after construction. A minimum slope of 10 percent should be
provided, such that the ground surface slopes away from the structure 10 feet or to
paving. This consists of one (1) foot of drop for the first 10 feet of the ground
surface away from the slab. The slab should be higher than the outside surrounding
flatwork, sidewalks, entries, paving and curbs. Low areas caused by landscaping
features (which also include irrigation) should be drained and/or sloped to drain so
that water (irrigation or storm water) does not pond. Ponding water next to the
building will cause sidewalks, entries, and any other type of flatwork to undergo
differential movement, usually upward. All ADA requirements must be followed.
2. A complete gutter and downspout system is recommended. Water from roof gutters
should be collected and transmitted to the storm drain system, a paved area, a
drainage swale, or sufficient distance from the foundation (approximately 10 to 15
LANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc 10
feet). If downspouts discharge next to the structure onto flatwork or paved areas,
the area should be watertight to eliminate infiltration next to the foundation and
below flatwork. Joints should be sealed against moisture penetration and planned
maintenance checks should repair and replace damaged joint sealer.
3. Utility ditches should be backfilled so that they do not become conduits that allow
surface water to flow adjacent to or below the foundation. This can be
accomplished using clay or concrete plugs placed within the trench backfill.
Plugs should have a minimum length of three (3) feet along the trench above and
below the utility pipe. The gravel embedment should be removed in this 3-foot
section to prevent water from flowing through the backfill. A positive cut-off at the
building line is required to prevent water from migrating along the trench and
through the utility backfill. Utility trenches should not be left open for extended
periods.
4. Landscape irrigation systems should be designed and located to prevent excessive
moisture adjacent to the foundation. Systems should not be located where water
will be sprayed onto building walls and subsequently drain downward and flow into
the soils beneath foundations.
5. Utilities which project through floor slabs, particularly where expansive soils or soils
subject to settlement are present, should be designed with some degree of flexibility
and/or with a sleeve to reduce the potential for damage to the utilities should
movement occur.
6. Contraction, control, or expansion joints should be designed and placed throughout
the structure. Properly planned placement of these joints will assist in controlling
the degree and location of material cracking which normally occurs due to material
shrinkage, thermal effects, soil movements and other related structural conditions.
7. Landscape borders consisting of metal, wood, stone, or other types of edging must
not prevent water from flowing away from the slab and/or cause water to pond.
Water must be able to flow freely away from the slab and enter a drainage swale
and flow away from the slab. If any grades prevent the quick removal of water, an
under-drain must be installed to collect the water and cause it to flow to an outfall
point so that the water flows into a storm drain, paved surface or at least 25 feet
away from the slab. Check local city codes to determine where French drains can
outfall and ADA compliance requirements for slopes.
8. Trees should not be planted next to the foundation. A distance equal to the mature
tree height from the foundation is suggested. A vertical moisture barrier can be
used between the tree and the foundation. Tree root systems extend out from the
tree to find moisture, especially in times of drought, and planting the tree the
recommended distance from the slab will help prevent drying and shrinkage of the
soil next to and below the foundation. This drying out and shrinkage of the soil can
cause settlement of the foundation grade beam and slab.
LANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc 11
9. The key is to maintain uniform moisture around and below the foundation on a year
around basis. The soil must not dry out nor become too wet. This will require
deliberate effort on the part of the homeowner and should be explained to the
homeowner in a document and in regular homeowner association meetings.
10. The homeowner should maintain the drainage around the foundation slab as
provided when the pad was originally graded to design grades. The homeowner
must not change drainage patterns and cause ponding of surface or subsurface
water.
11. The builder and/or homeowner must not install landscape beds, plant shrubs or
trees, construct patios, concrete pads, place gravel beds and A/C units within the
designed drainage swale which was installed by the developer. Fence panels
should not be placed into the ground and prevent storm water flow and change
drainage patterns. The drainage swale between houses must be free of all objects
that would block the design intent of the swale itself and that is to provide a drainage
swale to quickly remove storm water or other sources of water.
12. The home builder should specify the concrete strength for slabs; perform
temperature, slump, and compressive strength tests as well as Quality Assurance
observation during concrete placement by an independent Construction Materials
Engineering and Testing company. Prior to pouring the foundation concrete, the
beam depth and width, beam spacing, and sloughed soil and mud are removed from
the beam excavation.
13. Post tension cables should be installed per the Post Tension slab design and
checked by an independent inspector prior to concrete placement. Tendon
stressing must be monitored and recorded by an independent inspector. The
independent inspector can be an independent Construction Materials Engineering
and Testing company, or the inspection can be provided by the structural engineer
that performed the foundation design.
14. Flatwork and pavement will be subject to post construction movement. Maximum
grades practical should be used for paving and flatwork to help prevent areas where
water can pond. Where paving or flatwork abuts the structures, care should be
taken that the joints are properly sealed and maintained to prevent the infiltration of
surface water. All ADA requirements must be followed.
15. Homeowners should be advised that it is important to maintain relatively uniform
ground moisture conditions throughout the life of the house to decrease shrinkage of
the soils around the perimeter of the structure and reduce related foundation
distress.
L ANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc 12
5.0 GENERAL SITE GRADING
5.1 General Information
This section of the report provides recommendations for cutting and filling across the site.
These recommendations are intended to provide guidance to the civil engineer designing
the final site grading across this site. Mass grading has already been accomplished and
only some minor cut and fill remains as the streets, and lots are final graded. Specific
recommendations for Moisture Conditioned soils are provided in Appendix C.
Recommendations are provided for grading including vegetation stripping, preparation of
subgrade, scarifying, placement methods for fill based on what will be constructed in a
particular area. Recommendations for lift thickness, moisture and density, processing,
compaction methods, observation and testing the subgrade and fill are also provided. The
following paragraphs apply to general earthwork at the project site.
5.2 Subgrade Preparation
Stripping should consist of the removal of roots, vegetation and rubbish not removed by the
clearing and grubbing operation. The actual stripping depth should be based on field
observations with particular attention given to old drainage areas, uneven topography, and
excessively wet soils. The stripped areas should be observed by LandTec to determine
if additional excavation is required to remove weak or otherwise objectionable materials that
would adversely affect the fill placement.
The subgrade should be firm and able to support the construction equipment without
displacement. Soft or yielding subgrade should be corrected and made stable before
construction proceeds. The subgrade should be proof rolled to detect soft spots, which if
exist, should be reworked. Proof rolling should be performed using a heavy loaded dump
truck, water tanker truck, loaded scraper or similar equipment weighing approximately 20
tons. The proof rolling operations should be observed by the project geotechnical engineer
or his field representative.
In areas of the subgrade which, in the opinion of the project geotechnical engineer, are too
soft, wet, or otherwise unstable to allow fill construction to begin, the use of thicker initial
layers (lifts) may be required.
The traffic of heavy equipment, including heavy compaction equipment, may create
pumping and general deterioration of the soil. Occasionally some soils must be excavated,
mixed and dried, and replaced. At times, excavating and replacing with selected soils is
required before an adequate subgrade can be achieved. Therefore, it should be
anticipated that some construction difficulties will be encountered during periods when
these soils are saturated.
L ANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc 13
5.3 Placing of Material
Fill material should be placed on a properly prepared subgrade as specified. The combined
excavation, placing, and spreading operation should be done in such a manner to obtain
blending of material, and to provide that the materials, when compacted will have the most
practicable degree of compaction and stability. Materials excavated from cut sections
and/or borrow sources and hauled to construct fills must be mixed and not segregated,
except where such segregated soil zones are required. All fill should be placed in
horizontal lifts. Filling along (parallel to) slopes should not be permitted. In areas where
slopes will be constructed using fill, the fill should extend beyond finished contours and cut
back to grade.
If the surface of the fill is too smooth and hard to bond properly with a succeeding layer, the
surface should be roughened and loosened by disking before the succeeding layer is
placed. Where fill is to be placed next to existing fill, that fill should be removed to un-
weathered, dense material. Each layer should be benched and disked as adjoining lifts are
placed. Material hauling equipment should be so routed over the fill surface to distribute the
added compaction afforded by the rolling equipment, and to prevent the formation of ruts on
the surface.
The surface of the fill should be graded to drain freely and maintained throughout
construction. During the dumping and spreading process, the contractor should always
maintain a force of personnel adequate to remove all roots and debris and all rocks greater
than about six (6) inches in maximum dimension from the fill materials. No rocks should be
allowed within the final 18 inches of subgrade. Where other rock like materials are placed
as fill, the material must be broken down to manageable sizes. This will be accomplished
by large dozers, Cat 815 compactors or other suitable equipment that is acceptable to the
project geotechnical engineer of record.
In the event of slides in any part of the fill prior to final acceptance of the work, the
contractor should remove material from the slide area and should rebuild such portion of
the fill as requested by the project geotechnical engineer.
5.4 Moisture and Density Control
Following the spreading and mixing of the soil, it should be processed to break up and
provide additional blending of materials. Disking or ripping could be necessary to
accomplish breaking up and blending the fill. If the grading contractor dumps large blocks
of soil from earth moving equipment, the soil should be worked with a dozer to break the
blocks into sizes that can then be further broken down and blended by ripping or disking.
Prior to placing the next layer of fill, the previously processed, compacted, and tested lift
should be lightly watered to created bond with subsequent lifts.
LANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc 14
The recommended loose lift thickness is nine (9) inches. The moisture content of the soil
should be adjusted, if necessary, by either aeration or the addition of water to bring the
moisture content within the specified range. Water required for sprinkling to bring the fill
material to the proper moisture content should be applied evenly through each layer.
Any layers which become damaged by weather conditions should be reprocessed to meet
specification requirements. The compacted surface of a layer of fill should be lightly
loosened by disking before the succeeding layer is placed.
When the moisture content and the condition of the fill layer are satisfactory, compaction
should be made with appropriate compaction equipment.
The recommended compactor should be a Caterpillar 815 or similar compactor approved
by the project geotechnical engineer. The tamping-foot length should be a minimum of
eight (8) inches. Vibratory tamping rollers may be required for compacting some types of fill
material.
Clay fill material with a Plasticity Index (PI) equal to or greater than 25 should be
compacted to 93 to 98 percent of the maximum dry density as determined by the moisture-
density relations test method ASTM Designation D 698 for standard Proctor. The moisture
content for the clay fill should be at least four (4) percentage points above optimum. In
some cases, the geotechnical engineer may require a different moisture and density
requirement depending on the soil type and the area within that phase of the development.
The moisture content ranges specified are to be considered as allowable ranges. The
contractor may have to maintain a narrower range (within the maximum allowable) to
consistently achieve the specified density for some soils or under some conditions. The
moisture content and density of all fill material should be maintained at the specified range
of moisture and density.
Where fill depths including utility excavations exceed 10 feet, the compaction should be 100
percent as a minimum with a moisture content of -2 to +2; but will depend upon the site-
specific area in question and the intended use of the fill area as well as overlying structures.
Field density tests should be taken as each lift of fill material is placed. One field density
test per lift for approximately each 5,000 square feet of compacted area is generally
recommended. The project geotechnical engineer maintains the right to adjust the
frequency of compaction tests, moisture content and density based on actual field
conditions and the contractor’s performance. The earthwork operations should be
observed and tested on a continuing basis by an experienced engineering soil technician
working in conjunction with the project geotechnical engineer. The contractor is responsible
for notifying the testing agency’s on-site field representative when an area is ready for
compaction testing.
L ANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc 15
The contractor should assist the engineering technician in taking tests to the extent of
furnishing labor and equipment to prepare the areas for testing and curtailing operations in
the vicinity of the test area during testing. Where compaction tests do not comply with the
specifications, the contractor will rework the area and then inform the area is ready for re-
tests.
Each lift should be compacted, tested, and approved before another lift is added. The
purpose of the field density tests is to provide some indication that uniform and adequate
compaction is being obtained.
Trench backfill for utilities should be properly placed and compacted. Dense or dry backfill
can swell and create a mound along the ditch line. Loose or wet backfill can settle and form
a depression along the ditch line. Distress to overlying structures, pavements, sidewalks,
etc. can occur if heaving or settling happens. A granular bedding material is recommended
for pipe bedding. Clean coarse sand or well graded crushed rock make good bedding
materials. In all cases the city requirements for utility line embedment material should be
followed.
Care should be taken to prevent the backfilled trench throughout the subdivision
development from becoming French Drains and piping surface or subsurface water beneath
structures or pavements or from draining the shallow perched water from the site resulting
in increasing the slab-on-grade design swell potential estimates of both PVR and PVM.
The use of numerous concrete cut-off collars or clay plugs will likely be required to prevent
this from occurring.
Trench backfill should be placed and compacted in uniform lifts of 8 to 12 inches and be
tested for moisture and density. We recommend that each lift be tested with spacing of 150
to 300 feet along the trench. Compaction should be to a minimum of 95 percent of
standard Proctor density (ASTM D 698) at a moisture content ranging from one percentage
point below optimum to four percentage points above optimum (-1 to +4). Where trench
depths exceed 10 feet, compaction of the backfill should be to a minimum of 98% of
standard Proctor, for that portion of the trench backfill below 10 feet and as determined by
the geotechnical engineer.
5.5 Excavations
Excavations should consider the stability of adjacent structures, street pavement,
underground utilities, etc. Unstable soils include, but are not necessarily limited to, (1)
jointed, fissured, and slickensided materials (2) soils with pockets or layers of sand or
gravel, and (3) soils with groundwater seepage occurring. Slopes in these types of soils
may become unstable during periods of wet weather or as loads are applied to the top
and/or along the slope. The stability is also affected by weather conditions, excavation
depth, adjacent structures, construction equipment, and the length of time the excavation
will remain open.
L ANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc 16
Surcharge loads, either static or dynamic, should not be applied to the slope, particularly at
the top of slope. Construction equipment should be prevented from traveling along or near
the top of the excavation slope. Monitoring of temporary slopes, trenches, and dewatering
during construction should be undertaken by the contractor to detect early warnings of
movement within slopes, structures, pavements, etc.
Excavations should be shored to provide stability up-slope and to protect construction
workers. In all cases, the requirements of the Occupational Safety and Health
Administration (OSHA) must be followed. It is important for the contractor to monitor the
slope stability by observation and measurement, and to prevent excessive loads (especially
heavy vibratory loads) from being applied to the slope. The contractor should be
responsible for maintaining the slopes in a safe condition during construction and the use of
slope stability monitoring equipment is recommended. Inclinometers are one means of
measuring slope movement. This report has not been prepared for trench safety design
and slope angle design.
In the Federal Register, Volume 54, No. 209 (October 1989), the United States Department
of Labor, Occupational Safety and Health Administration (OSHA) amended its
“Construction Standards for Excavations, 29 CFR, part 1926, Subpart P”. This document
was issued to better ensure the safety of workmen entering trenches or excavations. It is
mandated by this federal regulation that excavations, whether they be utility trenches,
basement excavation or footing excavations, be constructed in accordance with the new
OSHA guidelines. It is our understanding that these regulations will be strictly enforced and
if they are not closely followed, the owner and the contractor could be liable for substantial
penalties.
The contractor is solely responsible for designing and constructing stable, temporary
excavations and should shore, slope, or bench the sides of the excavations as required to
maintain stability of both the excavation sides and bottom. The contractor’s “responsible
person”, as defined in 29 CFR Part 1926, should evaluate the soil exposed in the
excavations as part of the contractor’s safety procedures. In no case should slope height,
slope inclination, or excavation depth, including utility trench excavation depth, exceed
those specified in local, state, and federal safety regulations.
We are providing this information solely as a service to our client. LandTec Engineers does
not assume responsibility for construction site safety or the contractor’s or other parties’
compliance with the local, state, and federal safety or other regulations.
Fill or cut slopes constructed in the soils at the site should generally be maintained on
slopes no steeper than 5 horizontal to 1 vertical (5H:1V) for slopes up to 6 feet. Some
slopes in this geological formation could require flatter slopes. Slopes over 6 feet in height
should be designed based on site specific geometry and soil strength parameters. This
report has not been prepared for slope angle design.
LA N D TEC E NGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc 17
All slopes, whether temporary construction slopes or permanent fill slopes should be
designed to allow drainage at planned areas where erosion protection can be provided,
instead of allowing surface water to flow down unprotected slopes. Vegetative ground
cover should be provided as soon as practical to completed slopes.
5.6 Acceptance of Imported Fill
The owner must approve any soil hauled onto this project from off-site sources. The
contractor must obtain a written, notarized certification from the landowner of each
proposed off-site soil borrow source stating that to the best of the landowner's knowledge
and belief there has never been contamination of the borrow source site with hazardous or
toxic materials. The certification must be furnished to the owner prior to proceeding to
furnish soils to the site. Soil materials derived from the excavation of underground
petroleum storage tanks shall not be used as fill on this project.
6.0 GENERAL COMMENTS AND CONDITIONS
In any geotechnical study, the design recommendations are based on a limited amount of
information about the subsurface conditions. In the analysis, the geotechnical engineer
must assume the subsurface conditions are like the conditions encountered in the boring.
However, during construction, anomalies in the subsurface conditions are quite often
revealed.
Confirmation-Dependent Recommendations: Do not rely on these recommendations until
the Geotechnical Engineer of Record (GER) confirms through field observation that the
inferred conditions on which the recommendations are based are the conditions that exist.
If observation suggests otherwise, your GER will develop the necessary modifications.
The project geotechnical engineer of record should be retained to observe earthwork and
foundation installation and perform materials evaluation during the construction phase of
the project. This enables the project geotechnical engineer to stay abreast with the project
and to be readily available to evaluate unanticipated conditions, to conduct additional tests
if required and, when necessary, to recommend alternative solutions to unanticipated
conditions.
It is proposed that construction observation commence at the outset of the project.
Experience has shown that the most suitable method for procuring these services is for the
owner to contract directly with the geotechnical / materials engineer. This results in a clear,
direct line of communication between the owner or his representative and the geotechnical /
materials engineer.
L ANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc 18
The services described in this report were performed consistent with generally accepted
geotechnical engineering principles and practices. No other warranty, expressed or implied,
is made. These services were performed in agreement with our client. This report is solely
for the use and information of our client unless otherwise noted. Any reliance on this report
by a third party is at such party's sole risk.
Opinions and recommendations contained in this report apply to conditions existing when
services were performed and are intended only for the client, purposes, locations, time
frames, and project parameters indicated. We do not warrant the accuracy of information
supplied by others, or the use of segregated portions of this report.
The conclusions and recommendations in this report are invalid if:
the report is used for adjacent or other property or buildings.
grades, shallow perched seepage water levels, or both, change between the
issuance of this report and construction.
any other change is implemented that materially alters the project from that
proposed when this report was prepared
The boring logs do not provide a warranty of the conditions that may exist at the entire site.
The extent and nature of subsurface soil and groundwater variations may not become
evident until construction begins. Variations in soil conditions between borings could
possibly exist between or beyond the points of exploration or groundwater elevations may
change, both of which may require additional studies, consultation, and possible design
revisions. Any person associated with this project who observes conditions or features of
the site or surrounding areas that are different from those described in this report should
report the differences immediately for consideration and evaluation. This report was
prepared solely for the use of our client and should be reviewed in its entirety.
It is recommended that LANDTEC be retained to review those portions of the plans and
specifications for this project that pertain to geotechnical recommendations contained in this
report to determine whether the recommendations have been interpreted as intended. This
is typically done when the plans are at the 50 to 75 percent design level.
APPENDIX A
Plan of Borings, Boring Logs, General Notes
& Description of Field Exploration
LEGEND
� BORING LOCATION
1A-1 (DRILLED 2021)
16-1
1C-1
� TEST PIT LOCATION
TP-1
(DUG 2021)
BORING LOCATION
� (FUTURE AMENITY CENTER SITE
AC-1 DRILLED 2021)
� BORING LOCATION
(DRILLED 2019)
B-41
Q MOISTURE CONDITION TO 6 FEET
� MOISTURE CONDITION TO 4 FEET
� NO MOISTURE CONDITIONING AT
� THIS TIME
NOTE: BORING LOCATIONS ARE APPROXIMATE.
�
� � � � �
�TJ < o
m D
� < � O I,+�,1
z �� o0
� g � ; �
D m � i o
o �
�
N
�
TP-1 �
B-131
� /
/
�� TP-3 i I �
`.TP-2
� I �
�, j I I i� ' ��, .�
�� jTP I$ �I �I -- ,I - . �-7 ;��- �\y�s � TP-5
�
---- � 1 C- ��TP-1
NTS
B-42
B-41 �
B 66
�'" 1A-8 !I Iltt-54 � �55 � � i �--7 � ,
TP-3 8-67 B-74 B-75 Ilg-80 �
TP-2 � � � � B-81 \
� — - 1A-7 B-65 B-68� -73 � � �
� � TP-7 B-76 B-83
8-44 1A-6 � � � � � - �
B-69 B-72 8-77 "
� B-79 B-82
B'51� �1A-4 � � �
8-70 8-71 8-78
�-s
1A-3 � Q
� 1A-2 TP-10 �_ � 16-9 �
16-8�
TP-9 ��B-85 �B-6 �
1A-1 � /� o '� , � L-I■
�/ ,
� 18-5 18-7
�-2 ..
AC-1
' �. B-86 �16-4
TP-12 � 1B-2
FUTURE AMENITY J �B-� � _
CENTER SITE 1B-3
PLAN OF BORINGS & TEST PITS
KARIS DEVELOPMENT PHASE 1
CROWLEY, TEXAS
Q:\Projects\Karis Develapment\3082 - Phase 1, Section A,B,C (2021)\DRAWINGS\POB2021 8.SX11.dwg
L�►�VDT� ���-
ENGINEERS
TBPE REGISTRATION N0. F-329
TBPLS REGISTRATION N0. 100956-00
3906 W IH-20, STE 100 817-572-2818
ARLINGTON. TX 76017 WWW.LANDTECENG.COM
54
32
53
31
17
28
6.0
17.0
20.0
23
15
25
85
65
66
15.8
15.7
16.8
21.2
13.6
22.2
105.9
103.7
4.5+
4.5+
4.5+
4.5+
4.5+
4.5+
3.0
1.0
4.5+
4.5+
7.4
1.4
CLAY (CH), dark brown to grayish
brown, very stiff & w/calcareous nodules
SANDY LEAN CLAY (CL), calcareous,
tan & gray, stiff w/limestone fragments
CLAY (CH), grayish brown, very stiff,
blocky
737.0
726.0
723.0
FIGURE A2
Remarks: Dry @ completion.RQDLocation: See Plan of Borings
Surface El.: 743.0
5
10
15
20
25
30
35Depth, feetSheet 1 of 1
Northing: 6899368.6
Easting: 2318943.3 PenetrationBlows / Foot3082
Project:
Project Number:% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRecovery %Hand Penetrometer,tsfBORING LOG
1A-1
MoistureContent, %Liquid LimitPlastic LimitUnc. CompressiveStrength, tsfSymbol / USCSKaris DevelopmentPhase 1Crowley, Texas
Unit Dry Weight,pcfSoil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The
stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 20 ft
Date: 8/23/2021
Driller: Texplor
BORING LOG W/FIGURE (ELEVATIONS & DEPTH) 3082 KARIS DEVELOPMENT.GPJ LANDTEC.GDT 9/14/21
59
42
33
18
6.0
12.0
18.0
20.0
26
24
98
84
19.8
20.0
19.7
17.9
15.7
17.5
104.9
108.9
4.5+
4.5+
4.5+
4.5+
4.5+
4.5+
4.5+
4.5+
4.5+
4.5+
7.0
4.2
CLAY (CH), dark brown to grayish
brown, very stiff w/calcareous nodules
SANDY LEAN CLAY (CL), tan & gray,
very stiff w/calcareous nodules & lean clay
layers
CLAY (CH), brown & gray, very stiff,
blocky w/slickenside joints
CLAY (CH), reddish brown & gray, very
stiff, blocky & shaly w/slickenside joints
737.1
731.1
725.1
723.1
FIGURE A3
Remarks: Dry @ completion.RQDLocation: See Plan of Borings
Surface El.: 743.1
5
10
15
20
25
30
35Depth, feetSheet 1 of 1
Northing: 6899428.9
Easting: 2319224.9 PenetrationBlows / Foot3082
Project:
Project Number:% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRecovery %Hand Penetrometer,tsfBORING LOG
1A-2
MoistureContent, %Liquid LimitPlastic LimitUnc. CompressiveStrength, tsfSymbol / USCSKaris DevelopmentPhase 1Crowley, Texas
Unit Dry Weight,pcfSoil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The
stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 20 ft
Date: 8/23/2021
Driller: Texplor
BORING LOG W/FIGURE (ELEVATIONS & DEPTH) 3082 KARIS DEVELOPMENT.GPJ LANDTEC.GDT 9/14/21
72
49
71
45
30
42
5.0
18.0
20.0
27
19
29
82
82
98
20.5
21.4
23.0
17.1
17.3
10.8
25.6
100.7
109.3
4.5+
4.5+
4.5+
4.5+
4.5+
4.5+
4.5+
3.5
4.5+
4.5+
5.1
5.4
CLAY (CH), dark brown, very stiff
w/calcareous nodules
LEAN CLAY & CLAY (CL-CH), tan &
gray, very stiff w/calcareous material &
limestone fragments
CLAY (CH), light reddish brown, very
stiff, blocky
741.0
728.0
726.0
FIGURE A4
Remarks: Dry @ completion.RQDLocation: See Plan of Borings
Surface El.: 746.0
5
10
15
20
25
30
35Depth, feetSheet 1 of 1
Northing: 6899621.8
Easting: 2318917.4 PenetrationBlows / Foot3082
Project:
Project Number:% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRecovery %Hand Penetrometer,tsfBORING LOG
1A-3
MoistureContent, %Liquid LimitPlastic LimitUnc. CompressiveStrength, tsfSymbol / USCSKaris DevelopmentPhase 1Crowley, Texas
Unit Dry Weight,pcfSoil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The
stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 20 ft
Date: 8/23/2021
Driller: Texplor
BORING LOG W/FIGURE (ELEVATIONS & DEPTH) 3082 KARIS DEVELOPMENT.GPJ LANDTEC.GDT 9/14/21
63
100/
4.5"
56 32
2.5
10.0
24 8219.3
17.3
4.5+
4.5+
CLAY (CH), dark brown, very stiff
w/calcareous nodules
WEATHERED LIMESTONE, light tan,
hard to very hard (ROCK) w/clay seams
745.4
737.9
FIGURE A5
Remarks: Dry @ completion.RQDLocation: See Plan of Borings
Surface El.: 747.9
5
10
15
20
25
30
35Depth, feetSheet 1 of 1
Northing: 6899737.7
Easting: 2319064.4 PenetrationBlows / Foot3082
Project:
Project Number:% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRecovery %Hand Penetrometer,tsfBORING LOG
1A-4
MoistureContent, %Liquid LimitPlastic LimitUnc. CompressiveStrength, tsfSymbol / USCSKaris DevelopmentPhase 1Crowley, Texas
Unit Dry Weight,pcfSoil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The
stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 10 ft
Date: 8/23/2021
Driller: Texplor
BORING LOG W/FIGURE (ELEVATIONS & DEPTH) 3082 KARIS DEVELOPMENT.GPJ LANDTEC.GDT 9/14/21
Boring Not Drilled
(See Backhoe Test Pit Excavation)
FIGURE A6
Remarks: None RQDLocation: See Plan of Borings
Surface El.: Unknown
5
10
15
20
25
30
35Depth, feetSheet 1 of 1
PenetrationBlows / Foot3082
Project:
Project Number:% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRecovery %Hand Penetrometer,tsfBORING LOG
1A-5
MoistureContent, %Liquid LimitPlastic LimitUnc. CompressiveStrength, tsfSymbol / USCSKaris DevelopmentPhase 1Crowley, Texas
Unit Dry Weight,pcfSoil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The
stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 0 ft
Date:
Driller: Texplor
BORING LOG W/FIGURE (ELEVATIONS & DEPTH) 3082 KARIS DEVELOPMENT.GPJ LANDTEC.GDT 9/14/21
100/
0.5"
55
32
31
16
4.0
6.0
10.0
24
16 78
21.0
17.8
12.6
11.1
4.5+
4.5+
4.5+
4.5+
4.5+
4.5+
CLAY (CH), dark brown, very stiff
w/calcareous nodules
SANDY LEAN CLAY (CL), tan, very
stiff w/calcareous material & limestone
fragments
WEATHERED LIMESTONE, tan, hard
to very hard (ROCK) w/clay seams
748.1
746.1
742.1
FIGURE A7
Remarks: Dry @ completion.RQDLocation: See Plan of Borings
Surface El.: 752.1
5
10
15
20
25
30
35Depth, feetSheet 1 of 1
Northing: 6900003.9
Easting: 2319057.8 PenetrationBlows / Foot3082
Project:
Project Number:% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRecovery %Hand Penetrometer,tsfBORING LOG
1A-6
MoistureContent, %Liquid LimitPlastic LimitUnc. CompressiveStrength, tsfSymbol / USCSKaris DevelopmentPhase 1Crowley, Texas
Unit Dry Weight,pcfSoil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The
stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 10 ft
Date: 8/23/2021
Driller: Texplor
BORING LOG W/FIGURE (ELEVATIONS & DEPTH) 3082 KARIS DEVELOPMENT.GPJ LANDTEC.GDT 9/14/21
100/
1.25"
54 343.5
10.0
20 63
25.6
20.1
16.4
4.5+
4.5+
4.5+
4.5+
CLAY (CH), dark brown, very stiff
w/calcareous nodules
WEATHERED LIMESTONE, tan, hard
to very hard (ROCK) w/interbedded tan
clay seams & layers
751.0
744.5
FIGURE A8
Remarks: Dry @ completion.RQDLocation: See Plan of Borings
Surface El.: 754.5
5
10
15
20
25
30
35Depth, feetSheet 1 of 1
Northing: 6900182.4
Easting: 2319080.9 PenetrationBlows / Foot3082
Project:
Project Number:% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRecovery %Hand Penetrometer,tsfBORING LOG
1A-7
MoistureContent, %Liquid LimitPlastic LimitUnc. CompressiveStrength, tsfSymbol / USCSKaris DevelopmentPhase 1Crowley, Texas
Unit Dry Weight,pcfSoil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The
stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 10 ft
Date: 8/23/2021
Driller: Texplor
BORING LOG W/FIGURE (ELEVATIONS & DEPTH) 3082 KARIS DEVELOPMENT.GPJ LANDTEC.GDT 9/14/21
50/
4.0",
33
2.0
10.0
19.3
19.6
4.7
4.5+
4.5+
CLAY (CH), dark brown, very stiff
w/calcareous nodules
WEATHERED LIMESTONE, tan, hard
to very hard (ROCK) w/interbedded tan
clay seams & layers
752.8
744.8
FIGURE A9
Remarks: Dry @ completion.RQDLocation: See Plan of Borings
Surface El.: 754.8
5
10
15
20
25
30
35Depth, feetSheet 1 of 1
Northing: 6900236.9
Easting: 2318657.8 PenetrationBlows / Foot3082
Project:
Project Number:% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRecovery %Hand Penetrometer,tsfBORING LOG
1A-8
MoistureContent, %Liquid LimitPlastic LimitUnc. CompressiveStrength, tsfSymbol / USCSKaris DevelopmentPhase 1Crowley, Texas
Unit Dry Weight,pcfSoil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The
stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 10 ft
Date: 8/23/2021
Driller: Texplor
BORING LOG W/FIGURE (ELEVATIONS & DEPTH) 3082 KARIS DEVELOPMENT.GPJ LANDTEC.GDT 9/14/21
100/
1.0"
100/
0.5"
24
53
12
30
0.5
7.0
14.0
20.0
12
23 94
6.0
22.9 114.5
4.5+
4.5+
3.5 2.6
SANDY LEAN CLAY (CL), brown
w/limestone fragments
SANDY LEAN CLAY & CLAYEY
SAND (SC-CL), tan, very stiff w/gravel
CLAY (CH), reddish brown, tan & gray,
very stiff, blocky w/slickensided joints
LIMESTONE, gray, hard (ROCK)
w/some shale seams
731.6
725.1
718.1
712.1
FIGURE A10
Remarks: Dry @ completion.RQDLocation: See Plan of Borings
Surface El.: 732.1
5
10
15
20
25
30
35Depth, feetSheet 1 of 1
Northing: 6898978.6
Easting: 2319570.9 PenetrationBlows / Foot3082
Project:
Project Number:% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRecovery %Hand Penetrometer,tsfBORING LOG
1B-1
MoistureContent, %Liquid LimitPlastic LimitUnc. CompressiveStrength, tsfSymbol / USCSKaris DevelopmentPhase 1Crowley, Texas
Unit Dry Weight,pcfSoil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The
stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 20 ft
Date: 8/31/2021
Driller: Texplor
BORING LOG W/FIGURE (ELEVATIONS & DEPTH) 3082 KARIS DEVELOPMENT.GPJ LANDTEC.GDT 9/14/21
51
43
27
27
4.0
17.0
20.0
24
16
73
70
37
19.1
18.0
15.2
16.9
10.6
20.3
116.74.5+
4.5+
4.5+
4.5+
4.5+
4.5+
7.8
CLAY (CH), dark brown to brown, very
stiff
SANDY LEAN CLAY (CL), calcareous,
tan, very stiff w/gravel seams & layers
CLAY (CH), reddish brown, tan & gray,
very stiff, blocky w/slickensided joints
732.5
719.5
716.5
FIGURE A11
Remarks: Dry @ completion.RQDLocation: See Plan of Borings
Surface El.: 736.5
5
10
15
20
25
30
35Depth, feetSheet 1 of 1
Northing: 6898952.9
Easting: 2319983.9 PenetrationBlows / Foot3082
Project:
Project Number:% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRecovery %Hand Penetrometer,tsfBORING LOG
1B-2
MoistureContent, %Liquid LimitPlastic LimitUnc. CompressiveStrength, tsfSymbol / USCSKaris DevelopmentPhase 1Crowley, Texas
Unit Dry Weight,pcfSoil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The
stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 20 ft
Date: 8/31/2021
Driller: Texplor
BORING LOG W/FIGURE (ELEVATIONS & DEPTH) 3082 KARIS DEVELOPMENT.GPJ LANDTEC.GDT 9/14/21
62
34
47
37
17
28
4.0
8.0
14.0
20.0
25
17
19
74
80
76
20.0
19.5
13.0
19.8
21.9
21.4
4.5+
4.5+
4.5+
3.5
3.5
4.5+
4.5+
CLAY (CH), dark brown to brown, very
stiff
SANDY LEAN CLAY (CL), calcareous,
tan, very stiff w/gravel seams & layers
SANDY LEAN CLAY & CLAYEY
SAND (SC-CL), calcareous, silty &
sandy, very stiff w/gravel
CLAY (CH), reddish brown, tan & gray,
very stiff, blocky w/slickensided joints
731.7
727.7
721.7
715.7
FIGURE A12
Remarks: Dry @ completion.RQDLocation: See Plan of Borings
Surface El.: 735.7
5
10
15
20
25
30
35Depth, feetSheet 1 of 1
Northing: 6898904.1
Easting: 2320329.6 PenetrationBlows / Foot3082
Project:
Project Number:% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRecovery %Hand Penetrometer,tsfBORING LOG
1B-3
MoistureContent, %Liquid LimitPlastic LimitUnc. CompressiveStrength, tsfSymbol / USCSKaris DevelopmentPhase 1Crowley, Texas
Unit Dry Weight,pcfSoil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The
stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 20 ft
Date: 8/31/2021
Driller: Texplor
BORING LOG W/FIGURE (ELEVATIONS & DEPTH) 3082 KARIS DEVELOPMENT.GPJ LANDTEC.GDT 9/14/21
65
56
63
39
32
38
2.0
3.0
7.0
13.0
20.0
26
24
25
73
87
25.0
11.1
19.7
20.6
98.8
106.7
4.5+
4.5+
4.5+
4.5+
9.3
3.5
CLAY (CH), dark brown to brown, very
stiff
WEATHERED LIMESTONE, tan, hard
to very hard (ROCK), fractured w/some
interbedded clay seams & layers
SANDY LEAN CLAY (CL), calcareous,
tan, very stiff w/gravel seams & layers
CLAY (CH), tan, brown & gray, very
stiff, block w/slickenside joints
CLAY (CH), reddish brown, tan & gray,
very stiff, blocky w/slickensided joints
737.9
736.9
732.9
726.9
719.9
FIGURE A13
Remarks: Dry @ completion.RQDLocation: See Plan of Borings
Surface El.: 739.9
5
10
15
20
25
30
35Depth, feetSheet 1 of 1
Northing: 6899097.4
Easting: 2320405.3 PenetrationBlows / Foot3082
Project:
Project Number:% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRecovery %Hand Penetrometer,tsfBORING LOG
1B-4
MoistureContent, %Liquid LimitPlastic LimitUnc. CompressiveStrength, tsfSymbol / USCSKaris DevelopmentPhase 1Crowley, Texas
Unit Dry Weight,pcfSoil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The
stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 20 ft
Date: 8/31/2021
Driller: Texplor
BORING LOG W/FIGURE (ELEVATIONS & DEPTH) 3082 KARIS DEVELOPMENT.GPJ LANDTEC.GDT 9/14/21
56
54
47
32
33
28
5.0
12.0
17.0
20.0
24
21
19
83
77
88
23.6
17.3
17.7
15.0
14.3
26.4
18.5
4.5+
4.5+
4.5+
4.5+
4.5+
2.0
4.5+
CLAY (CH), dark brown to brown, very
stiff
CLAY (CH), calcareous, tan, very stiff
w/gravel seams & layers
CLAY (CH), tan to reddish tan, very stiff
w/silty sand seams & calcareous material
CLAY (CH), olive gray w/tan & gray,
very stiff, shaly, blocky
733.6
726.6
721.6
718.6
FIGURE A14
Remarks: Dry @ completion.RQDLocation: See Plan of Borings
Surface El.: 738.6
5
10
15
20
25
30
35Depth, feetSheet 1 of 1
Northing: 6899162.0
Easting: 2319754.2 PenetrationBlows / Foot3082
Project:
Project Number:% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRecovery %Hand Penetrometer,tsfBORING LOG
1B-5
MoistureContent, %Liquid LimitPlastic LimitUnc. CompressiveStrength, tsfSymbol / USCSKaris DevelopmentPhase 1Crowley, Texas
Unit Dry Weight,pcfSoil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The
stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 20 ft
Date: 8/31/2021
Driller: Texplor
BORING LOG W/FIGURE (ELEVATIONS & DEPTH) 3082 KARIS DEVELOPMENT.GPJ LANDTEC.GDT 9/14/21
100/
2.0"
1.5
10.0
19.54.5+
SANDY LEAN CLAY (CL), brown
w/limestone fragments
WEATHERED LIMESTONE, tan, hard
to very hard (ROCK), fractured w/some
interbedded clay seams & layers
741.9
733.4
FIGURE A15
Remarks: Dry @ completion.RQDLocation: See Plan of Borings
Surface El.: 743.4
5
10
15
20
25
30
35Depth, feetSheet 1 of 1
Northing: 6899333.1
Easting: 2320046.5 PenetrationBlows / Foot3082
Project:
Project Number:% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRecovery %Hand Penetrometer,tsfBORING LOG
1B-6
MoistureContent, %Liquid LimitPlastic LimitUnc. CompressiveStrength, tsfSymbol / USCSKaris DevelopmentPhase 1Crowley, Texas
Unit Dry Weight,pcfSoil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The
stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 10 ft
Date: 8/31/2021
Driller: Texplor
BORING LOG W/FIGURE (ELEVATIONS & DEPTH) 3082 KARIS DEVELOPMENT.GPJ LANDTEC.GDT 9/14/21
100/
0.5"
100/
0.5"
1.5
10.0
12.54.5+
SANDY LEAN CLAY (CL), brown
w/limestone fragments
WEATHERED LIMESTONE, tan, hard
to very hard (ROCK), fractured w/some
interbedded clay seams & layers
742.9
734.4
FIGURE A16
Remarks: Dry @ completion.RQDLocation: See Plan of Borings
Surface El.: 744.4
5
10
15
20
25
30
35Depth, feetSheet 1 of 1
Northing: 6899291.4
Easting: 2320449.4 PenetrationBlows / Foot3082
Project:
Project Number:% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRecovery %Hand Penetrometer,tsfBORING LOG
1B-7
MoistureContent, %Liquid LimitPlastic LimitUnc. CompressiveStrength, tsfSymbol / USCSKaris DevelopmentPhase 1Crowley, Texas
Unit Dry Weight,pcfSoil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The
stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 10 ft
Date: 8/31/2021
Driller: Texplor
BORING LOG W/FIGURE (ELEVATIONS & DEPTH) 3082 KARIS DEVELOPMENT.GPJ LANDTEC.GDT 9/14/21
100/
0.75"
100/
0.5"
42 19
2.0
10.0
2318.44.5+
SANDY LEAN CLAY (CL), brown
w/limestone fragments
WEATHERED LIMESTONE, tan, hard
to very hard (ROCK), fractured w/some
interbedded clay seams & layers
744.8
736.8
FIGURE A17
Remarks: Dry @ completion.RQDLocation: See Plan of Borings
Surface El.: 746.8
5
10
15
20
25
30
35Depth, feetSheet 1 of 1
Northing: 6899511.4
Easting: 2320275.7 PenetrationBlows / Foot3082
Project:
Project Number:% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRecovery %Hand Penetrometer,tsfBORING LOG
1B-8
MoistureContent, %Liquid LimitPlastic LimitUnc. CompressiveStrength, tsfSymbol / USCSKaris DevelopmentPhase 1Crowley, Texas
Unit Dry Weight,pcfSoil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The
stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 10 ft
Date: 8/31/2021
Driller: Texplor
BORING LOG W/FIGURE (ELEVATIONS & DEPTH) 3082 KARIS DEVELOPMENT.GPJ LANDTEC.GDT 9/14/21
100/
0.5"
100/
0.5"
1.0
2.0
10.0
12.0
4.5+
SANDY LEAN CLAY (CL), brown
w/limestone fragments
WEATHERED & BROKEN
LIMESTONE, tan & white, hard
WEATHERED LIMESTONE, tan, hard
to very hard (ROCK), fractured w/some
interbedded clay seams & layers
746.5
745.5
737.5
FIGURE A18
Remarks: Dry @ completion.RQDLocation: See Plan of Borings
Surface El.: 747.5
5
10
15
20
25
30
35Depth, feetSheet 1 of 1
Northing: 6899502.6
Easting: 2319926.7 PenetrationBlows / Foot3082
Project:
Project Number:% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRecovery %Hand Penetrometer,tsfBORING LOG
1B-9
MoistureContent, %Liquid LimitPlastic LimitUnc. CompressiveStrength, tsfSymbol / USCSKaris DevelopmentPhase 1Crowley, Texas
Unit Dry Weight,pcfSoil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The
stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 10 ft
Date: 8/31/2021
Driller: Texplor
BORING LOG W/FIGURE (ELEVATIONS & DEPTH) 3082 KARIS DEVELOPMENT.GPJ LANDTEC.GDT 9/14/21
34,
50/
4.0"
100/
1.25"
45
23
22
11
2.5
18.0
20.0
23
12
87
57
14.8
5.8
5.9
7.7
4.5+
4.5+
4.5+
LEAN CLAY (CL), reddish brown, very
stiff w/calcareous material
WEATHERED LIMESTONE, tan, hard
to very hard (ROCK) w/some interbedded
clay seams & layers
LIMESTONE, gray, hard to very hard
(ROCK)
762.5
747.0
745.0
FIGURE A19
Remarks: Dry @ completion.RQDLocation: See Plan of Borings
Surface El.: 765.0
5
10
15
20
25
30
35Depth, feetSheet 1 of 1
Northing: 6900644.9
Easting: 2319279.6 PenetrationBlows / Foot3082
Project:
Project Number:% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRecovery %Hand Penetrometer,tsfBORING LOG
1C-6
MoistureContent, %Liquid LimitPlastic LimitUnc. CompressiveStrength, tsfSymbol / USCSKaris DevelopmentPhase 1Crowley, Texas
Unit Dry Weight,pcfSoil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The
stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 20 ft
Date: 8/23/2021
Driller: Texplor
BORING LOG W/FIGURE (ELEVATIONS & DEPTH) 3082 KARIS DEVELOPMENT.GPJ LANDTEC.GDT 9/14/21
100/
1.0
67
40
60
42
24
36
6.0
9.0
13.0
19.5
23.0
30.0
25
16
24
66
77
89
22.8
21.1
19.5
13.5
13.5
16.5
10.9
26.6
20.7
13.0
98.8
116.8
99.5
105.3
4.5+
4.5+
4.5+
4.5+
4.5+
4.5+
4
4.5+
3.5
4.5+
6.7
3.4
2.8
2.1
CLAY (CH), dark brown, very stiff
w/calcareous nodules
SANDY LEAN CLAY (CL), calcareous,
tan & gray, very stiff w/calcareous
material
SANDY LEAN CLAY (CL), calcareous,
tan & gray, very stiff w/gravel & sand
seams
CLAY (CH), reddish tan, stiff to very
stiff, blocky & w/slickenside fractures
CLAY (CH), shaly, dark gray &
brownish gray, very stiff w/clayey shale
seams
LIMESTONE, gray, hard to very hard
(ROCK) w/some shale seams & layers
733.6
730.6
726.6
720.1
716.6
709.6
FIGURE A20
Remarks: Seepage observed @ 10' during drilling. Dry after 24 hours.
Area of future amenity center RQDLocation: See Plan of Borings
Surface El.: 739.6
5
10
15
20
25
30
35Depth, feetSheet 1 of 1
Northing: 6899291.8
Easting: 2319291.6 PenetrationBlows / Foot3082
Project:
Project Number:% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRecovery %Hand Penetrometer,tsfBORING LOG
AC-1
MoistureContent, %Liquid LimitPlastic LimitUnc. CompressiveStrength, tsfSymbol / USCSKaris DevelopmentArea of Future Amenity CenterCrowley, Texas
Unit Dry Weight,pcfSoil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The
stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 30 ft
Date: 8/23/2021
Driller:BORING LOG W/FIGURE (ELEVATIONS & DEPTH) 3082 KARIS DEVELOPMENT AMENITY CENTER.GPJ LANDTEC.GDT 9/14/21
13
100/
1.0
100/
0.5
37
53
24
29
2.5
8.0
19.5
30.0
13
24
25
93
19.3
9.6
24.7
28.8
7.5
127.4
94.5
4.5+
4.5+
4.5+
4.5+
3.5
1.8
2.2
CLAY (CH), dark brown, very stiff
w/limestone fragments
SANDY LEAN CLAY (CL), brown &
tan, calcareous, very stiff w/sand seams,
limestone fragments & gravel
CLAY (CH), tan, stiff to very stiff,
blocky w/tan sand seams & w/slickenside
fractures
LIMESTONE, gray, hard to very hard
(ROCK) w/some shale seams
735.0
729.5
718.0
707.5
FIGURE A21
Remarks: Dry @ completion. Dry after 24 hours.
Area of future amenity center RQDLocation: See Plan of Borings
Surface El.: 737.5
5
10
15
20
25
30
35Depth, feetSheet 1 of 1
Northing: 6899121.9
Easting: 2319088.2 PenetrationBlows / Foot3082
Project:
Project Number:% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRecovery %Hand Penetrometer,tsfBORING LOG
AC-2
MoistureContent, %Liquid LimitPlastic LimitUnc. CompressiveStrength, tsfSymbol / USCSKaris DevelopmentArea of Future Amenity CenterCrowley, Texas
Unit Dry Weight,pcfSoil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The
stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 30 ft
Date: 8/23/2021
Driller:BORING LOG W/FIGURE (ELEVATIONS & DEPTH) 3082 KARIS DEVELOPMENT AMENITY CENTER.GPJ LANDTEC.GDT 9/14/21
Figure A22
GENERAL NOTES
DRILLING AND SAMPLING SYMBOLS:
Thin-Walled Shelby Tube
:Split Spoon - 2” O.D., unless otherwise noted
:TxDOT Cone Penetrometer (TCP)
:Auger
RELATIVE DENSITY
OF COARSE-GRAINED SOILS:
CONSISTENCY
OF FINE-GRAINED SOILS:
Penetration Resistance
Blows/foot
Relative
Density
Unconfined
Compressive
Strength, Qu, tsf
Consistency
0-4 Very Loose Less than 0.25 Very Soft
4-10 Loose 0.25 to 0.50 Soft
10-30 Medium Dense 0.50 to 1.00 Firm
30-50 Dense 1.00 to 2.00 Stiff
over 50 Very Dense 2.00 to 4.00 Very Stiff
4.00 and higher Hard
TERMS CHARACTERIZING SOIL STRUCTURE:
Slickensided : Having inclined planes of weakness that are slick and glossy in appearance.
Fissured : Containing shrinkage cracks, frequently filled with fine sand or silt; usually more
or less vertical.
Laminated : Composed of thin layers of varying color and texture.
Interbedded : Composed of alternate layers of different soil types.
Calcareous : Containing appreciable quantities of calcium carbonate.
Well graded : Having wide range in grain sizes and substantial amounts of all intermediate
particle sizes.
Poorly graded : Predominantly of one grain size or having a range of sizes with some
intermediate size missing.
NOTE: Slickensided and fissured clays may have lower unconfined compressive strengths because of
planes of weakness or cracks in the soil. The consistency rating of such soils is based on penetrometer
readings.
DEGREE OF WEATHERING:
Unweathered : Rock in its natural state before being exposed to atmospheric agents.
Slightly Weathered : Noted predominantly by color change with no disintegrated zones.
Weathered/Severely Weathered: Complete color change with consistency, texture, and general
appearance approaching soil.
SUBSURFACE CONDITIONS:
Soil and rock descriptions on the boring logs are a compilation of field data as well as from laboratory testing
of samples. The stratification lines represent the approximate boundary between materials and the
transition can be gradual.
Water level observations have been made in the borings at the times indicated. It must be noted that
fluctuations in the groundwater level may occur due to variations in rainfall, hydraulic conductivity of soil
strata, construction activity, and other factors.
Hardness terms for soil and rock are for relative comparison of the various samples and are not intended to
be used as an indication of the ease or difficulty of excavation or of excavation stability. Hardness terms on
the logs may be based upon a combination of the test and observation methods listed above, and upon field
observations.
Water Level
(Level where first
observed)
Water Level
(Level after exploration
completed)
Figure A23
CLASSIFICATION OF SOILS
Criteria for Assigning Group Symbols and Group Names Using
Laboratory Tests
Soil Classification
Group
Symbol
Group Name
GRAVELS
More than 50%
of coarse
fraction
retained on
No. 4 sieve
CLEAN
GRAVELS
Less than 5%
fines
CU ≥ 4 and 1 ≤ Cc ≤ 3 GW Well-graded
Gravel
CU ≤ 4 and 1 ≥ Cc ≥ 3 GP Poorly-graded
Gravel
GRAVELS
WITH FINES
More than
12% of fines
Fines classify as ML or MH GM Silty Gravel
Fines classify as CL or CH GC Clayey Gravel
SANDS
50% or more of
coarse fraction
retained on
No. 4 sieve
CLEAN
SANDS
Less than 5%
fines
CU ≥ 6 and 1 ≤ Cc ≤ 3 SW Well-graded Sand
CU ≤ 6 and 1 ≥ Cc ≥ 3 SP Poorly-graded
Sand
SANDS
WITH FINES
More than
12% fines
Fines classify as ML or MH SM Silty Sand
Fines classify as CL or CH SC Clayey Sand
SILTS AND
CLAYS
Liquid limit less
than 50%
Inorganic PI ˃ 7 and plots on or above “A”
line
CL Lean Clay
PI ˂ 4 and plots below “A” line ML Silt
Organic Liquid limit – ovendried
Liquid limit – not dried ˂ 0.75 OL Organic Clay
Organic Silt
SILTS AND
CLAYS
Liquid limit
more than 50%
Inorganic PI plots on or above “A” line CH Fat Clay
PI plots below “A” line MH Elastic Silt
Organic Liquid limit – ovendried
Liquid limit – not dried ˂ 0.75 OH Organic Silt
Organic Silt
Highly fibrous
organic soils
Primary organic matter, dark in color, and organic
odor
Pt Peat
LA NDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc A24
Description of Field Exploration
Subsurface materials at the project site were explored by a total of 20 borings drilled to
depths of approximately 10 to 30 feet in late August 2021, at the locations staked by
Graham Associates, Inc. and as shown on the Plan of Borings in Appendix A. Borings were
advanced with CME 55 and 75 truck mounted drill rigs using thin-walled Shelby tube
samplers and continuous flight augers. The boring logs and a key to terms and
descriptions on the logs are provided in Appendix A. Backhoe test pits were also made by
the utility contractor during the same timeframe as the borings were drilled. The test pit
locations were also staked by Graham Associates.
Soil descriptions on the boring logs are a compilation of field log data as well as from
laboratory testing of samples. The stratification lines represent the approximate boundary
between soil types and the transition can be gradual. The boring logs presented in this
report represent the engineer’s interpretation of the field logs, visual observation of the
samples as well as results of laboratory tests.
Relatively undisturbed samples of cohesive soils encountered in the borings were obtained
with a Shelby tube sampler. Depths at which these samples were taken are indicated in the
"Sample" column of the boring log. Estimates of the consistency of the cohesive soil
samples were obtained in the field using a hand penetrometer. The result of a hand
penetrometer reading is recorded at a corresponding depth in the "Penetrometer, TSF"
column of the boring log. When the capacity of the hand penetrometer is exceeded, the
value of 4.5+ is recorded.
The hard materials were evaluated in place by the Texas Department of Transportation
(TxDOT) Texas Cone Penetrometer (TCP) Test. Either the number of blows required to
produce 12 inches of penetration, or the inches of penetration due to 100 blows of the
hammer are noted on the boring log designated "V" in the "Penetration Resistance" column.
Short term observations were made in the borings to observe for shallow subsurface
seepage. Water level observations made during drilling and shortly after completion of the
borings are noted on the respective logs. Water level measurements refer only to those
observed at the times and places indicated, and can vary with time, geologic condition,
construction activity, rainfall, and other factors.
APPENDIX B
Summary of Laboratory Results, Test Reports &
Description of Laboratory Testing
1A-1 1.5 54 23 31 85 15.8 105.9 7.4
1A-1 3.5 15.7
1A-1 5.5 16.8
1A-1 9.0 32 15 17 65 21.2 103.7 1.4
1A-1 14.5 13.6
1A-1 19.5 53 25 28 66 22.2
1A-2 2.5 59 26 33 98 19.8 104.9 7.0
1A-2 4.5 20.0
1A-2 5.5 19.7
1A-2 7.0 42 24 18 84 17.9 108.9 4.2
1A-2 14.5 15.7
1A-2 19.0 17.5
1A-3 1.5 20.5
1A-3 3.5 72 27 45 82 21.4 100.7 5.1
1A-3 5.5 23.0
1A-3 7.0 49 19 30 82 17.1 109.3 5.4
1A-3 9.0 17.3
1A-3 14.5 10.8
1A-3 19.5 71 29 42 98 25.6
1A-4 1.5 56 24 32 82 19.3
1A-4 2.5 17.3
1A-6 1.5 55 24 31 21.0
1A-6 3.5 17.8
1A-6 4.5 32 16 16 78 12.6
1A-6 9.5 11.1
1A-7 1.5 25.6
1A-7 2.5 20.1
1A-7 3.3 54 20 34 63 16.4
1A-8 0.5 19.3
1A-8 1.5 19.6
1A-8 4.5 4.7
1B-1 4.5 24 12 12 6.0
1B-1 9.0 53 23 30 94 22.9 114.5 2.6
1B-2 1.0 19.1 116.7 7.8
1B-2 3.0 51 24 27 73 18.0
1B-2 5.0 15.2
1B-2 7.0 43 16 27 70 16.9
1B-2 14.0 37 10.6
1B-2 19.0 20.3
1B-3 1.0 20.0
1B-3 3.0 62 25 37 74 19.5
1B-3 5.0 34 17 17 80 13.0
%<#200
Sieve
Water
Content
(%)
Dry
Density
(pcf)
Unconfined
Compressive
Strength
tsf
Summary of Laboratory Results
Sheet 1 of 2
Liquid
LimitDepth Plastic
Limit
Plasticity
IndexBorehole
Karis Development
Phase 1
Crowley, Texas
3082
Project:
Number: Date:8/23/2021US_LAB_SUMMARY_LANDTEC 3082 KARIS DEVELOPMENT.GPJ LANDTEC.GDT 9/14/21
1B-3 7.0 19.8
1B-3 9.0 47 19 28 76 21.9
1B-3 14.0 21.4
1B-4 1.0 65 26 39 73 25.0 98.8 9.3
1B-4 5.5 11.1
1B-4 9.5 56 24 32 87 19.7 106.7 3.5
1B-4 14.0 63 25 38 20.6
1B-5 1.0 23.6
1B-5 3.0 56 24 32 83 17.3
1B-5 5.0 17.7
1B-5 7.0 54 21 33 77 15.0
1B-5 9.0 14.3
1B-5 14.0 47 19 28 88 26.4
1B-5 19.0 18.5
1B-6 0.5 19.5
1B-7 0.8 12.5
1B-8 1.0 42 23 19 18.4
1B-9 0.5 12.0
1C-6 1.5 45 23 22 87 14.8
1C-6 2.5 5.8
1C-6 4.5 23 12 11 57 5.9
1C-6 9.5 7.7
%<#200
Sieve
Water
Content
(%)
Dry
Density
(pcf)
Unconfined
Compressive
Strength
tsf
Summary of Laboratory Results
Sheet 2 of 2
Liquid
LimitDepth Plastic
Limit
Plasticity
IndexBorehole
Karis Development
Phase 1
Crowley, Texas
3082
Project:
Number: Date:8/23/2021US_LAB_SUMMARY_LANDTEC 3082 KARIS DEVELOPMENT.GPJ LANDTEC.GDT 9/14/21
AC-1 1.5 67 25 42 66 22.8 98.8 6.7
AC-1 2.5 21.1
AC-1 3.5 19.5
AC-1 4.5 13.5
AC-1 5.5 13.5
AC-1 7.0 40 16 24 77 16.5 116.8 3.4
AC-1 9.0 10.9
AC-1 14.5 60 24 36 89 26.6 99.5 2.8
AC-1 19.5 20.7 105.3 2.1
AC-1 24.5 13.0
AC-2 1.5 19.3
AC-2 5.5 37 13 24 25 9.6 127.4 1.8
AC-2 9.3 24.7
AC-2 14.5 53 24 29 93 28.8 94.5 2.2
AC-2 24.5 7.5
%<#200
Sieve
Water
Content
(%)
Dry
Density
(pcf)
Unconfined
Compressive
Strength
tsf
Summary of Laboratory Results
Sheet 1 of 1
Liquid
LimitDepth Plastic
Limit
Plasticity
IndexBorehole
Karis Development
Area of Future Amenity Center
Crowley, Texas
3082
Project:
Number: Date:8/23/2021US_LAB_SUMMARY_LANDTEC 3082 KARIS DEVELOPMENT AMENITY CENTER.GPJ LANDTEC.GDT 9/14/21
LANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc B4
SUMMARY OF RESULTS
SWELL TESTS
Karis Development
Phase 1, Section A, B, C and Amenity Center Area
Crowley, Texas
Project No. 0821-3082
September 2021
Boring
No.
Sample
Depth,
Ft.
Unit dry
Weight,
pcf
Initial
Moisture
Content,
%
Final
Moisture
Content,
%
Applied
Surcharge
Pressure,
psf
Vertical
Swell,
%
AC-1 1-2 105.8 21.5 26.1 200 5.5
AC-1 6-8 116.5 16.2 17.9 900 0.2
1A-1 1-2 111.6 16.4 24.6 100 9.4
1A-1 8-10 102.8 23.4 24.1 1150 -0.1
1A-2 2-3 100.4 20.3 28.3 300 4.5
1A-2 6-8 109.6 18.6 22.4 900 1.0
1A-3 3-4 105.2 20.9 26.8 450 5.4
1A-3 6-8 113.3 17.4 20.7 650 2.0
1B-2 2-4 104.1 18.8 26.0 400 4.6
1B-3 2-4 98.3 27.2 28.0 400 4.8
1B-3 4-6 109.3 14.2 21.3 650 2.3
1B-5 2-4 105.1 20.1 24.0 400 5.0
1B-5 6-8 119.7 13.5 17.6 900 5.2
L ANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc B5
Description of Laboratory Testing
Representative samples of the soils were tested in our geotechnical soil’s laboratory.
Liquid limit and plastic limit tests (Atterberg limits) and percent passing No. 200 sieve were
performed on soil samples from the borings to classify them according to the Unified Soil
Classification (USC) System.
Strength properties of the soil were evaluated by performing unconfined compression tests.
The results of these tests are reported as Qu values (in tons per square foot). Moisture
content and density determinations were also made on samples to determine the in-situ
conditions. These tests were performed in general accordance with the American Society
for Testing and Materials (ASTM) Procedures.
Selected samples of clay soils were subjected to swell tests. The results are reported as
the percent swell, with initial and final moisture content, and overburden pressure. The
overburden pressure (or confinement) simulates the pressure experienced by the soil
sample for a specific depth under in-situ conditions.
Results of the laboratory tests including classification, strength, unit dry weight and
moisture content are presented on each respective boring log in Appendix A. A summary
of Laboratory Results along with the swell tests are provided in Appendix B.
APPENDIX C
Moisture Conditioning (MC) Recommendations
LANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc C1
MOISTURE CONDITIONING (MC) RECOMMENDATIONS
Karis Development – Phase 1
Crowley, Texas
September 2021
Over-Excavation, Moisture Conditioning and Replacement
To reduce the PVM to less than 4½ inches, we recommend the soils be moisture
conditioned for the lots outlined in blue (6 feet deep) and outlined in red (4 feet deep)
as shown on Drawing A1 in Appendix A. The proposed Amenity Center Site will not be
moisture conditioned at this time.
The moisture conditioning depth is from existing (original) grade when the recent borings
were made and before any cut or fill. All fill material placed on the lots will also need to be
moisture conditioned. Recommendations are made based on calculations assuming the
“Fill” placed over the Moisture Conditioned soil will be moisture conditioned as per the
specifications.
The intent is to construct a uniform building pad below the foundation to reduce (to an
acceptable level) the potential for slab movement associated with volumetric changes within
the soils due to moisture variations to an acceptable level. The actual movements could be
greater if poor drainage conditions allow ponded water and/or other sources of moisture are
allowed to infiltrate beneath the foundation after construction.
Building pad preparation should include the following to provide a uniform pad to place the
slab.
A minimum of 5 feet outside the building line is recommended. Additional areas to
be considered for moisture conditioning, depending on the risk level and the desired
reduction in soil movement includes sidewalks, drives, porches, patios, and any
other areas where it is desired to reduce the soil movement.
Once the excavation is made, scarify the bottom of the excavation a minimum of 12-
inches deep with dozer or loader ripper teeth and rip at least two different directions
approximately 90 degrees to each other, adjust the soils moisture in the bottom of
the excavation, re-compact and test as referenced herein.
Place the excavated soil back in the excavation in 8-inch loose lifts and compact to
a uniform density ranging from 93 to 98 percent of standard Proctor (ASTM D698) at
a minimum moisture content of plus four percentage points above optimum (+4 and
above).
LANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc C2
For some soils and under some conditions, the earthwork contractor in consultation
with the project geotechnical engineer may have to adjust the moisture content up
or down to consistently achieve the recommended density.
Polyethylene sheeting (minimum 10-mil thickness) should be placed over the
moisture conditioned soils to limit loss of moisture within the conditioned soils. The
sheeting should be covered with approximately 8 to 10 inches of compacted soil to
prevent UV deterioration from sunlight. The polyethylene sheeting must be installed
within 48 hours or less of completion of the moisture conditioned pad.
All fill material placed on lots will need to be moisture conditioned following the
moisture conditioning procedures described herein.
With respect to the building pad, we recommend the contractor take survey shots at
4 or 5 locations on the pad to make sure the pad is not heaving from the moisture
conditioning. Since moisture conditioning is typically performed in a short time
frame, the pad could still be undergoing upward movement due to the moisture
added to the soil. The contractor should not place the slab until sure the pad is not
moving upward. Therefore, the building contractor should check the pad at multiple
locations by surveying on a regular basis.
The contractor is responsible for surveying the building pad location; that the pad
has been moisture conditioned the recommended distance past the building line
(including sidewalks, porches, flatwork, etc. if required), that the moisture
conditioning is to the recommended depth and the pad is wrapped in polyethylene
sheeting to the limits determined by the developer. These items are typically
controlled by the contractor’s surveyor and site superintendent.
The slab designer and slab contractor should consider use of a vapor retarder
beneath the slab to limit moisture migration. Consider ACI 302 and/or ACI 360 for
procedures and cautions regarding the use and placement of a vapor retarder.
Following completion of the moisture conditioned pad, every attempt should be
made to keep the pad moist to prevent drying. Utility trench and grade beam
excavations made into the pads moisture conditioned soils should be prevented
from drying out and should be backfilled to similar compaction conditions as the
moisture conditioned soil.
Compaction tests on the moisture conditioned soil should be taken at the rate of one test
per 2,500 to 5,000 square feet per lift. A minimum of two (2) compaction tests per lift
should be required. Tests indicating low moisture and/or high density will require re-
working that lift. The earthwork operations should be observed and tested on a continuing
basis by an experienced engineering technician working in conjunction with the project
geotechnical engineer.
LANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc C3
Each lift should be compacted, tested, and approved before another lift is added. The
purpose of the field density tests is to provide some indication that uniform and adequate
compaction is being obtained. The actual quality of the fill, as compacted, should be the
responsibility of the contractor and satisfactory results from the tests should not be
considered as a guarantee of the quality of the contractor's filling operations.
Swell tests should be performed on samples of the re-compacted clay soils as the clay is
replaced in the excavation to determine the swell potential of the re-compacted soil. In
general, the average swell of one (1) percent or less with no swell test over two (2) percent
should be used for the acceptance criteria.
The moisture conditioning process should be observed and tested on a continuing basis by
a LandTec Engineers field representative working in conjunction with the project
geotechnical engineer.
APPENDIX D
Drainage Illustrations
LANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc D1
Recommended drainage swale slope between house foundations.
Recommended drainage slope from house to street.
LANDTEC ENGINEERS
3082 Karis- Phase 1-Geot-Sept2021.doc D2
Ideal drainage condition between houses where drainage swale is open and not blocked
by AC Unit, fence, landscaping, rock wall, etc.
Unacceptable drainage conditions between houses should not be allowed. Drainage
swale is blocked by fence & AC unit.
APPENDIX E
GBA Statement
Geotechnical-Engineering Report
Important Information about This
Subsurface problems are a principal cause of construction delays, cost overruns, claims, and disputes.
While you cannot eliminate all such risks, you can manage them. The following information is provided to help.
The Geoprofessional Business Association (GBA)
has prepared this advisory to help you – assumedly
a client representative – interpret and apply this
geotechnical-engineering report as effectively
as possible. In that way, clients can benefit from
a lowered exposure to the subsurface problems
that, for decades, have been a principal cause of
construction delays, cost overruns, claims, and
disputes. If you have questions or want more
information about any of the issues discussed below,
contact your GBA-member geotechnical engineer.
Active involvement in the Geoprofessional Business
Association exposes geotechnical engineers to a
wide array of risk-confrontation techniques that can
be of genuine benefit for everyone involved with a
construction project.
Geotechnical-Engineering Services Are Performed for
Specific Purposes, Persons, and Projects
Geotechnical engineers structure their services to meet the specific
needs of their clients. A geotechnical-engineering study conducted
for a given civil engineer will not likely meet the needs of a civil-
works constructor or even a different civil engineer. Because each
geotechnical-engineering study is unique, each geotechnical-
engineering report is unique, prepared solely for the client. Those who
rely on a geotechnical-engineering report prepared for a different client
can be seriously misled. No one except authorized client representatives
should rely on this geotechnical-engineering report without first
conferring with the geotechnical engineer who prepared it. And no one
– not even you – should apply this report for any purpose or project except
the one originally contemplated.
Read this Report in Full
Costly problems have occurred because those relying on a geotechnical-
engineering report did not read it in its entirety. Do not rely on an
executive summary. Do not read selected elements only. Read this report
in full.
You Need to Inform Your Geotechnical Engineer
about Change
Your geotechnical engineer considered unique, project-specific factors
when designing the study behind this report and developing the
confirmation-dependent recommendations the report conveys. A few
typical factors include:
• the client’s goals, objectives, budget, schedule, and
risk-management preferences;
• the general nature of the structure involved, its size,
configuration, and performance criteria;
• the structure’s location and orientation on the site; and
• other planned or existing site improvements, such as
retaining walls, access roads, parking lots, and
underground utilities.
Typical changes that could erode the reliability of this report include
those that affect:
• the site’s size or shape;
• the function of the proposed structure, as when it’s
changed from a parking garage to an office building, or
from a light-industrial plant to a refrigerated warehouse;
• the elevation, configuration, location, orientation, or
weight of the proposed structure;
• the composition of the design team; or
• project ownership.
As a general rule, always inform your geotechnical engineer of project
changes – even minor ones – and request an assessment of their
impact. The geotechnical engineer who prepared this report cannot accept
responsibility or liability for problems that arise because the geotechnical
engineer was not informed about developments the engineer otherwise
would have considered.
This Report May Not Be Reliable
Do not rely on this report if your geotechnical engineer prepared it:
• for a different client;
• for a different project;
• for a different site (that may or may not include all or a
portion of the original site); or
• before important events occurred at the site or adjacent
to it; e.g., man-made events like construction or
environmental remediation, or natural events like floods,
droughts, earthquakes, or groundwater fluctuations.
Note, too, that it could be unwise to rely on a geotechnical-engineering
report whose reliability may have been affected by the passage of time,
because of factors like changed subsurface conditions; new or modified
codes, standards, or regulations; or new techniques or tools. If your
geotechnical engineer has not indicated an “apply-by” date on the report,
ask what it should be, and, in general, if you are the least bit uncertain
about the continued reliability of this report, contact your geotechnical
engineer before applying it. A minor amount of additional testing or
analysis – if any is required at all – could prevent major problems.
Most of the “Findings” Related in This Report Are
Professional Opinions
Before construction begins, geotechnical engineers explore a site’s
subsurface through various sampling and testing procedures.
Geotechnical engineers can observe actual subsurface conditions only at
those specific locations where sampling and testing were performed. The
data derived from that sampling and testing were reviewed by your
geotechnical engineer, who then applied professional judgment to
form opinions about subsurface conditions throughout the site. Actual
sitewide-subsurface conditions may differ – maybe significantly – from
those indicated in this report. Confront that risk by retaining your
geotechnical engineer to serve on the design team from project start to
project finish, so the individual can provide informed guidance quickly,
whenever needed.
This Report’s Recommendations Are
Confirmation-Dependent
The recommendations included in this report – including any options
or alternatives – are confirmation-dependent. In other words, they are
not final, because the geotechnical engineer who developed them relied
heavily on judgment and opinion to do so. Your geotechnical engineer
can finalize the recommendations only after observing actual subsurface
conditions revealed during construction. If through observation your
geotechnical engineer confirms that the conditions assumed to exist
actually do exist, the recommendations can be relied upon, assuming
no other changes have occurred. The geotechnical engineer who prepared
this report cannot assume responsibility or liability for confirmation-
dependent recommendations if you fail to retain that engineer to perform
construction observation.
This Report Could Be Misinterpreted
Other design professionals’ misinterpretation of geotechnical-
engineering reports has resulted in costly problems. Confront that risk
by having your geotechnical engineer serve as a full-time member of the
design team, to:
• confer with other design-team members,
• help develop specifications,
• review pertinent elements of other design professionals’
plans and specifications, and
• be on hand quickly whenever geotechnical-engineering
guidance is needed.
You should also confront the risk of constructors misinterpreting this
report. Do so by retaining your geotechnical engineer to participate in
prebid and preconstruction conferences and to perform construction
observation.
Give Constructors a Complete Report and Guidance
Some owners and design professionals mistakenly believe they can shift
unanticipated-subsurface-conditions liability to constructors by limiting
the information they provide for bid preparation. To help prevent
the costly, contentious problems this practice has caused, include the
complete geotechnical-engineering report, along with any attachments
or appendices, with your contract documents, but be certain to note
conspicuously that you’ve included the material for informational
purposes only. To avoid misunderstanding, you may also want to note
that “informational purposes” means constructors have no right to rely
on the interpretations, opinions, conclusions, or recommendations in
the report, but they may rely on the factual data relative to the specific
times, locations, and depths/elevations referenced. Be certain that
constructors know they may learn about specific project requirements,
including options selected from the report, only from the design
drawings and specifications. Remind constructors that they may
perform their own studies if they want to, and be sure to allow enough
time to permit them to do so. Only then might you be in a position
to give constructors the information available to you, while requiring
them to at least share some of the financial responsibilities stemming
from unanticipated conditions. Conducting prebid and preconstruction
conferences can also be valuable in this respect.
Read Responsibility Provisions Closely
Some client representatives, design professionals, and constructors do
not realize that geotechnical engineering is far less exact than other
engineering disciplines. That lack of understanding has nurtured
unrealistic expectations that have resulted in disappointments, delays,
cost overruns, claims, and disputes. To confront that risk, geotechnical
engineers commonly include explanatory provisions in their reports.
Sometimes labeled “limitations,” many of these provisions indicate
where geotechnical engineers’ responsibilities begin and end, to help
others recognize their own responsibilities and risks. Read these
provisions closely. Ask questions. Your geotechnical engineer should
respond fully and frankly.
Geoenvironmental Concerns Are Not Covered
The personnel, equipment, and techniques used to perform an
environmental study – e.g., a “phase-one” or “phase-two” environmental
site assessment – differ significantly from those used to perform
a geotechnical-engineering study. For that reason, a geotechnical-
engineering report does not usually relate any environmental findings,
conclusions, or recommendations; e.g., about the likelihood of
encountering underground storage tanks or regulated contaminants.
Unanticipated subsurface environmental problems have led to project
failures. If you have not yet obtained your own environmental
information, ask your geotechnical consultant for risk-management
guidance. As a general rule, do not rely on an environmental report
prepared for a different client, site, or project, or that is more than six
months old.
Obtain Professional Assistance to Deal with Moisture
Infiltration and Mold
While your geotechnical engineer may have addressed groundwater,
water infiltration, or similar issues in this report, none of the engineer’s
services were designed, conducted, or intended to prevent uncontrolled
migration of moisture – including water vapor – from the soil through
building slabs and walls and into the building interior, where it can
cause mold growth and material-performance deficiencies. Accordingly,
proper implementation of the geotechnical engineer’s recommendations
will not of itself be sufficient to prevent moisture infiltration. Confront
the risk of moisture infiltration by including building-envelope or mold
specialists on the design team. Geotechnical engineers are not building-
envelope or mold specialists.
Copyright 2016 by Geoprofessional Business Association (GBA). Duplication, reproduction, or copying of this document, in whole or in part, by any means whatsoever, is strictly
prohibited, except with GBA’s specific written permission. Excerpting, quoting, or otherwise extracting wording from this document is permitted only with the express written permission
of GBA, and only for purposes of scholarly research or book review. Only members of GBA may use this document or its wording as a complement to or as an element of a report of any
kind. Any other firm, individual, or other entity that so uses this document without being a GBA member could be committing negligent
Telephone: 301/565-2733
e-mail: info@geoprofessional.org www.geoprofessional.org
LANDTEC ENGINEERS, LLC
ARLINGTON | THE COLONY
3906 W. IH-20, Suite 100 | Arlington, Texas 76017
(w) 817-572-2818 | www.landteceng.com
geotechnical engineering
environmental engineering
construction materials testing
laboratory testing
SERVICES
DR-01 60 00
Water Department
Standard Product List
Approval Spec No. Classsification Manufacturer Model No. National Spec Size
Water & Sewer - Manholes & Bases/Components 33-39-10 (Rev 2/3/16)
07/23/97 33 05 13 Urethane Hydrophilic Waterstop Asahi Kogyo K.K. Adeka Ultra-Seal P-201 ASTM D2240/D412/D792
04/26/00 33 05 13 Offset Joint for 4' Diam. MH Hanson Concrete Products Drawing No. 35-0048-001
04/26/00 33 05 13 Profile Gasket for 4' Diam. MH. Press-Seal Gasket Corp. 250-4G Gasket ASTM C-443/C-361 SS MH
1/26/99 33 05 13 HDPE Manhole Adjustment Rings Ladtech, Inc HDPE Adjustment Ring Traffic and Non-traffic area
5/13/05 33 05 13 Manhole External Wrap Canusa - CPS WrapidSeal Manhole Encapsulation System
Water & Sewer - Manholes & Bases/Fiberglass 33-39-13 (1/8/13)
1/26/99 33 39 13 Fiberglass Manhole Fluid Containment, Inc. Flowtite ASTM 3753 Non-traffic area
08/30/06 33 39 13 Fiberglass Manhole L.F. Manufacturing Non-traffic area
Water & Sewer - Manholes & Bases/Frames & Covers/Rectangular 33-05-13 (Rev 2/3/16)
* 33 05 13 Manhole Frames and Covers Western Iron Works, Bass & Hays Foundry 1001 24"x40" WD
Water & Sewer - Manholes & Bases/Frames & Covers/Standard (Round) 33-05-13 (Rev 2/3/16)
* 33 05 13 Manhole Frames and Covers Western Iron Works, Bass & Hays Foundry 30024 24" Dia.
* 33 05 13 Manhole Frames and Covers McKinley Iron Works Inc. A 24 AM 24" Dia.
08/24/18 33 05 13 Manhole Frames and Covers Neenah Foundry R-1272 ASTM A48 & AASHTO M306 24" Dia.
08/24/18 33 05 13 Manhole Frames and Covers Neenah Foundry R- 165-LM (Hinged) ASTM A48 & AASHTO M306 24" Dia.
08/24/18 33 05 13 Manhole Frames and Covers Neenah Foundry NF 1274 ASTM A48 & AASHTO M306 30" Dia.
08/24/18 33 05 13 Manhole Frames and Covers Neenah Foundry R-1743-LM (Hinged) ASTM A48 & AASHTO M306 30" dia.
33 05 13 Manhole Frames and Covers Sigma Corporation MH-144N
33 05 13 Manhole Frames and Covers Sigma Corporation MH-143N
33 05 13 Manhole Frames and Covers Pont-A-Mousson GTS-STD 24" dia.
33 05 13 Manhole Frames and Covers Neenah Casting 24" dia.
10/31/06 33 05 13 Manhole Frames and Covers (Hinged) Powerseal Hinged Ductile Iron Manhole ASTM A536 24" Dia.
7/25/03 33 05 13 Manhole Frames and Covers Saint-Gobain Pipelines (Pamrex/rexus) RE32-R8FS 30" Dia.
01/31/06 33 05 13 30" Dia. MH Ring and Cover East Jordan Iron Works V1432-2 and V1483 Designs AASHTO M306-04 30" Dia.
11/02/10 33 05 13 30" Dia. MH Ring and Cover Sigma Corporation MH1651FWN & MH16502 30" Dia
07/19/11 33 05 13 30" Dia. MH Ring and Cover Star Pipe Products MH32FTWSS-DC 30" Dia
08/10/11 33 05 13 30" Dia. MH Ring and Cover Accucast 220700 Heavy Duty with Gasket Ring 30" Dia
10/14/13 33 05 13 30" Dia. MH Ring and Cover (Hinged & Lockable) East Jordan Iron Works
30" ERGO XL Assembly
with Cam Lock/MPIC/T-Gasket ASSHTO M105 & ASTM A536 30" Dia
06/01/17 34 05 13 30" Dia. MH Ring and Cover (Hinged & Lockable) CI SIP Industries 2280 (32") ASTM A 48 30" Dia.
09/16/19 33 05 13 30" Dia. MH Ring and Cover Composite Access Products, L.P.
CAP-ONE-30-FTW, Composite, w/ Lock
w/o Hing 30" Dia.
10/07/21 34 05 13 30" Dia. MH Ring and Cover Trumbull Manufacturing 32"(30") Frame and Cover 30" Dia.
Water & Sewer - Manholes & Bases/Frames & Covers/Water Tight & Pressure Tight 33-05-13 (Rev 2/3/16)
* 33 05 13 Manhole Frames and Covers Pont-A-Mousson Pamtight 24" Dia.
* 33 05 13 Manhole Frames and Covers Neenah Casting 24" Dia.
* 33 05 13 Manhole Frames and Covers Western Iron Works,Bass & Hays Foundry 300-24P 24" Dia.
* 33 05 13 Manhole Frames and Covers McKinley Iron Works Inc. WPA24AM 24" Dia.
03/08/00 33 05 13 Manhole Frames and Covers Accucast RC-2100 ASTM A 48 24" Dia.
04/20/01 33 05 13 Manhole Frames and Covers (SIP)Serampore Industries Private Ltd. 300-24-23.75 Ring and Cover ASTM A 48 24" Dia.
Water & Sewer - Manholes & Bases/Precast Concrete (Rev 1/8/13)
* 33 39 10 Manhole, Precast Concrete Hydro Conduit Corp SPL Item #49 ASTM C 478 48"
* 33 39 10 Manhole, Precast Concrete Wall Concrete Pipe Co. Inc. ASTM C-443 48"
09/23/96 33 39 10 Manhole, Precast Concrete Concrete Product Inc. 48" I.D. Manhole w/ 32" Cone ASTM C 478 48" w/32" cone
05/08/18 33 39 10 Manhole, Precast Concrete The Turner Company 48", 60" I.D. Manhole w/ 32" Cone ASTM C 478 48", 60"
10/27/06 33 39 10 Manhole, Precast Concrete Oldcastle Precast Inc. 48" I.D. Manhole w/ 24" Cone ASTM C 478 48" Diam w 24" Ring
06/09/10 33 39 10 Manhole, Precast (Reinforced Polymer)Concrete US Composite Pipe Reinforced Polymer Concrete ASTM C-76 48" to 72"
09/06/19 33 39 20 Manhole, Precast Concrete Forterra Pipe and Precast 60" & 72" I.D. Manhole w/32" Cone ASTM C-76 60" & 72"
10/07/21 32 39 20 Manhole, Precast Concrete Forterra Pipe and Precast 48" I.D. Manhole w/32" Cone ASTM C-77 48"
10/07/21 33 39 20 Manhole, Precast (Reinforced Polymer) Concrete Armorock 48" & 60" I.D. Manhole w/32" Cone 48" & 60"
10/07/21 33 39 20 Manhole, Precast (Hybrid) Polymer & PVC Predl Systems 48" & 60" I.D. Manhole w/32" Cone 48" & 60"
Water & Sewer - Manholes & Bases/Rehab Systems/Cementitious
* E1-14 Manhole Rehab Systems Quadex
04/23/01 E1-14 Manhole Rehab Systems Standard Cement Materials, Inc. Reliner MSP
E1-14 Manhole Rehab Systems AP/M Permaform
4/20/01 E1-14 Manhole Rehab System Strong Company Strong Seal MS2A Rehab System
5/12/03 E1-14 Manhole Rehab System (Liner) Poly-triplex Technologies MH repair product to stop infiltration ASTM D5813
08/30/06 General Concrete Repair FlexKrete Technologies Vinyl Polyester Repair Product Misc. Use
Water & Sewer - Manholes & Bases/Rehab Systems/NonCementitious
05/20/96 E1-14 Manhole Rehab Systems Sprayroq, Spray Wall Polyurethane Coating ASTM D639/D790
* E1-14 Manhole Rehab Systems Sun Coast
12/14/01 Coating for Corrosion protection(Exterior) ERTECH Series 20230 and 2100 (Asphatic Emulsion)
For Exterior Coating of Concrete
Structures Only
01/31/06 Coatings for Corrosion Protection Chesterton Arc 791, S1HB, S1, S2 Acid Resistance Test Sewer Applications
8/28/2006 Coatings for Corrosion Protection Warren Environmental S-301 and M-301 Sewer Applications
08/30/06 Coatings for Corrosion Protection Citadel SLS-30 Solids Epoxy Sewer Applications
03/19/18
33 05 16, 33 39 10,
33 39 20 Coating for Corrosion protection(Exterior) Sherwin Williams
RR&C Dampproofing Non-Fibered Spray
Grade (Asphatic Emulsion)
For Exterior Coating of Concrete
Structures Only
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
Note: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.
Updated: 11/08/2021
* From Original Standard Products List 1
Approval Spec No. Classsification Manufacturer Model No. National Spec Size
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
Note: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.
Updated: 11/08/2021
Water & Sewer - Manhole Inserts - Field Operations Use Only (Rev 2/3/16)
* 33 05 13 Manhole Insert Knutson Enterprises Made to Order - Plastic ASTM D 1248 For 24" dia.
* 33 05 13 Manhole Insert South Western Packaging Made to Order - Plastic ASTM D 1248 For 24" dia.
* 33 05 13 Manhole Insert Noflow-Inflow Made to Order - Plastic ASTM D 1248 For 24" dia.
09/23/96 33 05 13 Manhole Insert Southwestern Packing & Seals, Inc. LifeSaver - Stainless Steel For 24" dia.
09/23/96 33 05 13 Manhole Insert Southwestern Packing & Seals, Inc. TetherLok - Stainless Steel For 24" dia
Water & Sewer - Pipe Casing Spacers 33-05-24 (07/01/13)
11/04/02 Steel Band Casing Spacers Advanced Products and Systems, Inc. Carbon Steel Spacers, Model SI
02/02/93 Stainless Steel Casing Spacer Advanced Products and Systems, Inc. Stainless Steel Spacer, Model SSI
04/22/87 Casing Spacers Cascade Waterworks Manufacturing Casing Spacers
09/14/10 Stainless Steel Casing Spacer Pipeline Seal and Insulator Stainless Steel Casing Spacer Up to 48"
09/14/10 Coated Steel Casin Spacers Pipeline Seal and Insulator Coated Steel Casin Spacers Up to 48"
05/10/11 Stainless Steel Casing Spacer Powerseal 4810 Powerchock Up to 48"
03/19/18 Casing Spacers BWM SS-12 Casing Spacer(Stainless Steel)
03/19/18 Casing Spacers BWM
FB-12 Casing Spacer (Coated Carbon Steel)
for Non_pressure Pipe and Grouted Casing
Water & Sewer - Pipes/Ductile Iron 33-11-10(1/8/13)
* 33 11 10 Ductile Iron Pipe Griffin Pipe Products, Co. Super Bell-Tite Ductile Iron Pressure Pipe, AWWA C150, C151 3" thru 24"
08/24/18 33 11 10 Ductile Iron Pipe American Ductile Iron Pipe Co. American Fastite Pipe (Bell Spigot) AWWA C150, C151 4" thru 30"
08/24/18 33 11 10 Ductile Iron Pipe American Ductile Iron Pipe Co. American Flex Ring (Restrained Joint) AWWA C150, C151 4" thru 30"
* 33 11 10 Ductile Iron Pipe U.S. Pipe and Foundry Co. AWWA C150, C151
* 33 11 10 Ductile Iron Pipe McWane Cast Iron Pipe Co. AWWA C150, C151
Water & Sewer - Utility Line Marker (08/24/2018)
Sewer - Coatings/Epoxy 33-39-60 (01/08/13)
02/25/02 Epoxy Lining System Sauereisen, Inc SewerGard 210RS LA County #210-1.33
12/14/01 Epoxy Lining System Ertech Technical Coatings Ertech 2030 and 2100 Series
04/14/05 Interior Ductile Iron Pipe Coating Induron Protecto 401 ASTM B-117 Ductile Iron Pipe Only
01/31/06 Coatings for Corrosion Protection Chesterton Arc 791, S1HB, S1, S2 Acid Resistance Test Sewer Applications
8/28/2006 Coatings for Corrosion Protection Warren Environmental S-301 and M-301 Sewer Applications
Sewer - Coatings/Polyurethane
Sewer - Combination Air Valves
05/25/18 33-31-70 Air Release Valve A.R.I. USA, Inc. D025LTP02(Composite Body) 2"
Sewer - Pipes/Concrete
* E1-04 Conc. Pipe, Reinforced Wall Concrete Pipe Co. Inc. ASTM C 76
* E1-04 Conc. Pipe, Reinforced Hydro Conduit Corporation Class III T&G, SPL Item #77 ASTM C 76
* E1-04 Conc. Pipe, Reinforced Hanson Concrete Products SPL Item #95-Manhole, #98- Pipe ASTM C 76
* E1-04 Conc. Pipe, Reinforced Concrete Pipe & Products Co. Inc. ASTM C 76
Sewer - Pipe Enlargment System (Method)33-31-23 (01/18/13)
PIM System PIM Corporation Polyethylene PIM Corp., Piscata Way, N.J. Approved Previously
McConnell Systems McLat Construction Polyethylene Houston, Texas Approved Previously
TRS Systems Trenchless Replacement System Polyethylene Calgary, Canada Approved Previously
Sewer - Pipe/Fiberglass Reinforced Pipe 33-31-13(1/8/13)
7/21/97 33 31 13 Cent. Cast Fiberglass (FRP) Hobas Pipe USA, Inc. Hobas Pipe (Non-Pressure) ASTM D3262/D3754
03/22/10 33 31 13 Fiberglass Pipe (FRP) Ameron Bondstrand RPMP Pipe ASTM D3262/D3754
04/09/21 Glass-Fiber Reinforced Polymer Pipe (FRP) Thompson Pipe Group Thompson Pipe (Flowtite) ASTM D3262/D3754
4/14/05 Polymer Modified Concrete Pipe Amitech USA Meyer Polycrete Pipe ASTM C33, A276, F477 8" to 102", Class V
06/09/10 E1-9 Reinforced Polymer Concrete Pipe US Composite Pipe Reinforced Polymer Concrete Pipe ASTM C-76
Sewer - Pipes/HDPE 33-31-23(1/8/13)
* High-density polyethylene pipe Phillips Driscopipe, Inc. Opticore Ductile Polyethylene Pipe ASTM D 1248 8"
* High-density polyethylene pipe Plexco Inc. ASTM D 1248 8"
* High-density polyethylene pipe Polly Pipe, Inc. ASTM D 1248 8"
High-density polyethylene pipe CSR Hydro Conduit/Pipeline Systems McConnell Pipe Enlargement ASTM D 1248
Sewer - Pipes/PVC (Pressure Sewer) 33-11-12 (4/1/13)
12/02/11 33-11-12 DR-14 PVC Pressure Pipe Pipelife Jetstream PVC Pressure Pipe AWWA C900 4" thru 12"
10/22/14 33-11-12 DR-14 PVC Pressure Pipe Royal Building Products Royal Seal PVC Pressure Pipe AWWA C900 4" thru 12"
* From Original Standard Products List 2
Approval Spec No. Classsification Manufacturer Model No. National Spec Size
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
Note: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.
Updated: 11/08/2021
Sewer - Pipes/PVC* 33-31-20 (7/1/13)
* 33-31-20 PVC Sewer Pipe J-M Manufacturing Co., Inc. (JM Eagle) SDR-26 ASTM D 3034 4" - 15"
12/23/97* 33-31-20 PVC Sewer Pipe Diamond Plastics Corporation SDR-26
ASTM D 3034 4" thru 15"
* 33-31-20 PVC Sewer Pipe Lamson Vylon Pipe ASTM F 789 4" thru 15"
01/18/18 33-31-20 PVC Sewer Pipe Vinyltech PVC Pipe Gravity Sewer ASTM D3034 4" thru 15"
11/11/98 33-31-20 PVC Sewer Pipe Diamond Plastics Corporation "S" Gravity Sewer Pipe ASTM F 679 18" to 27"
* 33-31-20 PVC Sewer Pipe J-M Manufacturing Co, Inc. (JM Eagle) SDR 26/35 PS 115/46 ASTM F 679 18" - 28"
09/11/12 33-31-20 PVC Sewer Pipe Pipelife Jet Stream SDR-26 and SDR-35 ASTM F-679 18"
05/06/05 33-31-20 PVC Solid Wall Pipe Diamond Plastics Corporation SDR 26/35 PS 115/46 ASTM F-679 18" to 48"
04/27/06 33-31-20 PVC Sewer Fittings Harco SDR-26 and SDR-35 Gasket Fittings ASTM D-3034, D-1784, etc 4" - 15"
*33-31-20 PVC Sewer Fittings Plastic Trends, In.c Gasketed PVC Sewer Main Fittings ASTM D 3034
3/19/2018 33 31 20 PVC Sewer Pipe Pipelife Jet Stream SDR 35 ASTM F679 18"- 24"
3/19/2018 33 31 20 PVC Sewer Pipe Pipelife Jet Stream SDR 26 ASTM D3034 4"- 15"
3/29/2019 33 31 20
Gasketed Fittings (PVC)GPK Products, Inc. SDR 26 ASTM D3034/F-679 4"- 15"
10/21/2020 33 31 20 PVC Sewer Pipe NAPCO SDR 26 ASTM D3034 4" - 15"
10/22/2020 33 31 20 PVC Sewer Pipe Sanderson Pipe Corp. SDR 26 ASTM D3034 4"- 15"
10/21/2020 33 31 20 PVC Sewer Pipe NAPCO SDR 26/35 PS 115/46 ASTM F-679 18"- 36"
Sewer - Pipes/Rehab/CIPP 33-31-12 (01/18/13)
* Cured in Place Pipe Insituform Texark, Inc ASTM F 1216
05/03/99 Cured in Place Pipe National Envirotech Group National Liner, (SPL) Item #27 ASTM F-1216/D-5813
05/29/96 Cured in Place Pipe Reynolds Inc/Inliner Technolgy (Inliner USA) Inliner Technology ASTM F 1216
Sewer - Pipes/Rehab/Fold & Form
* Fold and Form Pipe Cullum Pipe Systems, Inc.
11/03/98 Fold and Form Pipe Insituform Technologies, Inc. Insituform "NuPIpe" ASTM F-1504
Fold and Form Pipe American Pipe & Plastics, Inc.Demo. Purpose Only
12/04/00 Fold and Form Pipe Ultraliner Ultraliner PVC Alloy Pipeliner ASTM F-1504, 1871, 1867
06/09/03 Fold and Form Pipe Miller Pipeline Corp. EX Method ASTM F-1504, F-1947 Up to 18" diameter
Sewer - Pipes/Open Profile Large Diameter
09/26/91 E100-2 PVC Sewer Pipe, Ribbed Lamson Vylon Pipe Carlon Vylon H.C. Closed Profile Pipe, ASTM F 679 18" to 48"
09/26/91 E100-2 PVC Sewer Pipe, Ribbed Extrusion Technologies, Inc. Ultra-Rib Open Profile Sewer Pipe ASTM F 679 18" to 48"
E100-2 PVC Sewer Pipe, Ribbed Uponor ETI Company
11/10/10 (E100-2) Polypropylene (PP) Sewer Pipe, Double Wall Advanced Drainage Systems (ADS) SaniTite HP Double Wall (Corrugated) ASTM F 2736 24"-30"
11/10/10 (E100-2) Polypropylene (PP) Sewer Pipe, Triple Wall Advanced Drainage Systems (ADS) SaniTite HP Triple Wall Pipe ASTM F 2764 30" to 60"
05/16/11 Steel Reinforced Polyethylene Pipe ConTech Construction Products Durmaxx ASTM F 2562 24" to 72"
Water - Appurtenances 33-12-10 (07/01/13)
01/18/18 33-12-10 Double Strap Saddle Romac 202NS Nylon Coated AWWA C800 1"-2" SVC, up to 24" Pipe
08/28/02 Double Strap Saddle Smith Blair #317 Nylon Coated Double Strap Saddle
07/23/12 33-12-10 Double Strap Service Saddle Mueller Company DR2S Double (SS) Strap DI Saddle AWWA C800 1"-2" SVC, up to 24" Pipe
10/27/87 Curb Stops-Ball Meter Valves McDonald 6100M,6100MT & 610MT 3/4" and 1"
10/27/87 Curb Stops-Ball Meter Valves McDonald 4603B, 4604B, 6100M, 6100TM and 6101M 1½" and 2"
5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Ford Meter Box Co., Inc.
FB600-7NL, FB1600-7-NL, FV23-777-W-NL,
L22-77NL AWWA C800 2"
5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Ford Meter Box Co., Inc.
FB600-6-NL, FB1600-6-NL, FV23-666-W-
NL, L22-66NL AWWA C800 1-1/2"
5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Ford Meter Box Co., Inc.
FB600-4-NL, FB1600-4-NL, B11-444-WR-
NL, B22444-WR-NL, L28-44NL AWWA C800 1"
5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Mueller Co., Ltd.
B-25000N, B-24277N-3, B-20200N-3, H-
15000N, , H-1552N, H142276N
AWWA C800, ANSF 61,
ANSI/NSF 372 2"
5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Mueller Co., Ltd.
B-25000N, B-20200N-3, B-24277N-3,H-
15000N, H-14276N, H-15525N
AWWA C800, ANSF 61,
ANSI/NSF 372 1-1/2"
5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Mueller Co., Ltd.
B-25000N, B-20200N-3,H-15000N, H-
15530N
AWWA C800, ANSF 61,
ANSI/NSF 372 1"
01/26/00 Coated Tapping Saddle with Double SS Straps JCM Industries, Inc. #406 Double Band SS Saddle 1"-2" Taps on up to 12"
0/5/21/12 33-12-25 Tapping Sleeve (Coated Steel) JCM Industries, Inc. 412 Tapping Sleeve ESS AWWA C-223 Up to 30" w/12" Out
05/10/11 Tapping Sleeve (Stainless Steel) Powerseal 3490AS (Flange) & 3490MJ 4"-8" and 16"
02/29/12 33-12-25 Tapping Sleeve (Coated Steel) Romac FTS 420 AWWA C-223 U p to 42" w/24" Out
02/29/12 33-12-25 Tapping Sleeve (Stainless Steel) Romac SST Stainless Steel AWWA C-223 Up to 24" w/12" Out
02/29/12 33-12-25 Tapping Sleeve (Stainless Steel) Romac SST III Stainless Steel AWWA C-223 Up to 30" w/12" Out
05/10/11 Joint Repair Clamp Powerseal 3232 Bell Joint Repair Clamp 4" to 30"
Plastic Meter Box w/Composite Lid DFW Plastics Inc. DFW37C-12-1EPAF FTW
Plastic Meter Box w/Composite Lid DFW Plastics Inc. DFW39C-12-1EPAF FTW
08/30/06 Plastic Meter Box w/Composite Lid DFW Plastics Inc. DFW65C-14-1EPAF FTW Class "A"
Concrete Meter Box Bass & Hays CMB37-B12 1118 LID-9
Concrete Meter Box Bass & Hays CMB-18-Dual 1416 LID-9
Concrete Meter Box Bass & Hays CMB65-B65 1527 LID-9
Water - Bolts, Nuts, and Gaskets 33-11-05 (01/08/13)
* From Original Standard Products List 3
Approval Spec No. Classsification Manufacturer Model No. National Spec Size
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
Note: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.
Updated: 11/08/2021
Water - Combination Air Release 33-31-70 (01/08/13)
* E1-11 Combination Air Release Valve GA Industries, Inc. Empire Air and Vacuum Valve, Model 935 ASTM A 126 Class B, ASTM A
240 - float, ASTM A 307 - Cover
Bolts
1" & 2"
* E1-11 Combination Air Release Valve Multiplex Manufacturing Co.
Crispin Air and Vacuum Valves, Model No. 1/2", 1" & 2"
* E1-11 Combination Air Release Valve Valve and Primer Corp. APCO #143C, #145C and #147C 1", 2" & 3"
Water - Dry Barrel Fire Hydrants 33-12-40 (01/15/14)
10/01/87 E-1-12 Dry Barrel Fire Hydrant American-Darling Valve Drawing Nos. 90-18608, 94-18560 AWWA C-502
03/31/88 E-1-12 Dry Barrel Fire Hydrant American Darling Valve Shop Drawing No. 94-18791 AWWA C-502
09/30/87 E-1-12 Dry Barrel Fire Hydrant Clow Corporation Shop Drawing No. D-19895 AWWA C-502
01/12/93 E-1-12 Dry Barrel Fire Hydrant American AVK Company Model 2700 AWWA C-502
08/24/88 E-1-12 Dry Barrel Fire Hydrant Clow Corporation Drawings D20435, D20436, B20506 AWWA C-502
E-1-12 Dry Barrel Fire Hydrant ITT Kennedy Valve Shop Drawing No. D-80783FW AWWA C-502
09/24/87 E-1-12 Dry Barrel Fire Hydrant M&H Valve Company Shop Drawing No. 13476 AWWA C-502
10/14/87 E-1-12 Dry Barrel Fire Hydrant Mueller Company
Shop Drawings No. 6461
A-423 Centurion AWWA C-502
01/15/88 E1-12 Dry Barrel Fire Hydrant Mueller Company
Shop Drawing FH-12
A-423 Super Centurion 200 AWWA C-502
10/09/87 E-1-12 Dry Barrel Fire Hydrant U.S. Pipe & Foundry Shop Drawing No. 960250 AWWA C-502
09/16/87 E-1-12 Dry Barrel Fire Hydrant Waterous Company Shop Drawing No. SK740803 AWWA C-502
08/12/16 33-12-40 Dry Barrel Fire Hydrant EJ (East Jordan Iron Works) WaterMaster 5CD250
Water - Meters
02/05/93 E101-5 Detector Check Meter Ames Company Model 1000 Detector Check Valve AWWA C550 4" - 10"
08/05/04 Magnetic Drive Vertical Turbine Hersey Magnetic Drive Vertical AWWA C701, Class 1 3/4" - 6"
Water - Pipes/PVC (Pressure Water) 33-31-70 (01/08/13)
01/18/18 33-11-12 PVC Pressure Pipe Vinyltech PVC Pipe DR14
AWWA C900, AWWA C605,
ASTM D1784 4"-12"
3/19/2018 33 11 12 PVC Pressure Pipe Pipelife Jet Stream DR14 AWWA C900 4"-12"
3/19/2018 33 11 12 PVC Pressure Pipe Pipelife Jet Stream DR18 AWWA C900 16"-24"
5/25/2018 33 11 12 PVC Pressure Pipe Diamond Plastics Corporation DR 14 AWWA C900 4"-12"
5/25/2018 33 11 12 PVC Pressure Pipe Diamond Plastics Corporation DR 18 AWWA C900 16"-24"
12/6/2018 33 11 12 PVC Pressure Pipe J-M Manufacturing Co., Inc d/b/a JM Eagle DR 14
AWWA C900-16
UL 1285
ANSI/NSF 61
FM 1612
4"-28"
12/6/2018 33 11 12 PVC Pressure Pipe J-M Manufacturing Co., Inc d/b/a JM Eagle DR 18
AWWA C900-16
UL 1285
ANSI/NSF 61
FM 1612
16"-24"
9/6/2019 33 11 12 PVC Pressure Pipe Underground Solutions Inc. DR14 Fusible PVC AWWA C900 4" - 8"
9/6/2019 33 11 12 PVC Pressure Pipe NAPCO DR18 AWWA C900 16" - 24"
9/6/2019 33 11 12 PVC Pressure Pipe NAPCO DR14 AWWA C900 4"- 12"
9/6/2019 33 11 12 PVC Pressure Pipe Sanderson Pipe Corp. DR14 AWWA C900 4"- 12"
Water - Pipes/Valves & Fittings/Ductile Iron Fittings 33-11-11 (01/08/13)
07/23/92 E1-07 Ductile Iron Fittings Star Pipe Products, Inc. Mechanical Joint Fittings AWWA C153 & C110
* E1-07 Ductile Iron Fittings Griffin Pipe Products, Co. Mechanical Joint Fittings AWWA C 110
* E1-07 Ductile Iron Fittings McWane/Tyler Pipe/ Union Utilities Division
Mechanical Joint Fittings, SSB Class 350 AWWA C 153, C 110, C 111
08/11/98 E1-07 Ductile Iron Fittings Sigma, Co.
Mechanical Joint Fittings, SSB Class 351 AWWA C 153, C 110, C 112
02/26/14 E1-07 MJ Fittings Accucast
Class 350 C-153 MJ Fittings AWWA C153 4"-12"
05/14/98 E1-07 Ductile Iron Joint Restraints Ford Meter Box Co./Uni-Flange
Uni-Flange Series 1400 AWWA C111/C153 4" to 36"
05/14/98 E1-24 PVC Joint Restraints Ford Meter Box Co./Uni-Flange
Uni-Flange Series 1500 Circle-Lock AWWA C111/C153 4" to 24"
11/09/04 E1-07 Ductile Iron Joint Restraints One Bolt, Inc.
One Bolt Restrained Joint Fitting AWWA C111/C116/C153 4" to 12"
02/29/12 33-11-11 Ductile Iron Pipe Mechanical Joint Restraint EBAA Iron, Inc.
Megalug Series 1100 (for DI Pipe)AWWA C111/C116/C153 4" to 42"
02/29/12 33-11-11 PVC Pipe Mechanical Joint Restraint EBAA Iron, Inc.
Megalug Series 2000 (for PVC Pipe)AWWA C111/C116/C153 4" to 24"
08/05/04 E1-07 Mechanical Joint Retainer Glands(PVC) Sigma, Co.
Sigma One-Lok SLC4 - SLC10 AWWA C111/C153 4" to 10"
03/06/19 33-11-11 Mechanical Joint Retainer Glands(PVC) Sigma, Co.
Sigma One-Lok SLCS4 - SLCS12 AWWA C111/C153 4" to 12"
08/05/04 E1-07 Mechanical Joint Retainer Glands(PVC) Sigma, Co.
Sigma One-Lok SLCE AWWA C111/C153 12" to 24"
08/10/98 E1-07 MJ Fittings(DIP) Sigma, Co.
Sigma One-Lok SLDE AWWA C153 4" - 24"
10/12/10 E1-24 Interior Restrained Joint System S & B Techncial Products
Bulldog System ( Diamond Lok 21 & JM ASTM F-1624 4" to 12"
08/16/06 E1-07 Mechanical Joint Fittings SIP Industries(Serampore)
Mechanical Joint Fittings AWWA C153 4" to 24"
11/07/16 33-11-11 Mechanical Joint Retainer Glands Star Pipe Products, Inc.
PVC Stargrip Series 4000 ASTM A536 AWWA C111
11/07/16 33-11-11 Mechanical Joint Retainer Glands Star Pipe Products, Inc.
DIP Stargrip Series 3000 ASTM A536 AWWA C111
03/19/18 33-11-11 Mechanical Joint Retainer Glands SIP Industries(Serampore)
EZ Grip Joint Restraint (EZD) Black For DIP ASTM A536 AWWA C111 3"-48"
03/19/18 33-11-11 Mechanical Joint Retainer Glands SIP Industries(Serampore)
EZ Grip Joint Restraint (EZD) Red for C900
DR14 PVC Pipe ASTM A536 AWWA C111 4"-12"
03/19/18 33-11-11 Mechanical Joint Retainer Glands SIP Industries(Serampore)
EZ Grip Joint Restraint (EZD) Red for C900
DR18 PVC Pipe ASTM A536 AWWA C111 16"-24"
* From Original Standard Products List 4
Approval Spec No. Classsification Manufacturer Model No. National Spec Size
Water & Sewer - Manholes & Bases/Components 33-39-10 (Rev 2/3/16)
07/23/97 33 05 13 Urethane Hydrophilic Waterstop Asahi Kogyo K.K. Adeka Ultra-Seal P-201 ASTM D2240/D412/D792
04/26/00 33 05 13 Offset Joint for 4' Diam. MH Hanson Concrete Products Drawing No. 35-0048-001
04/26/00 33 05 13 Profile Gasket for 4' Diam. MH. Press-Seal Gasket Corp. 250-4G Gasket ASTM C-443/C-361 SS MH
1/26/99 33 05 13 HDPE Manhole Adjustment Rings Ladtech, Inc HDPE Adjustment Ring Traffic and Non-traffic area
5/13/05 33 05 13 Manhole External Wrap Canusa - CPS WrapidSeal Manhole Encapsulation System
Water & Sewer - Manholes & Bases/Fiberglass 33-39-13 (1/8/13)
1/26/99 33 39 13 Fiberglass Manhole Fluid Containment, Inc. Flowtite ASTM 3753 Non-traffic area
08/30/06 33 39 13 Fiberglass Manhole L.F. Manufacturing Non-traffic area
Water & Sewer - Manholes & Bases/Frames & Covers/Rectangular 33-05-13 (Rev 2/3/16)
* 33 05 13 Manhole Frames and Covers Western Iron Works, Bass & Hays Foundry 1001 24"x40" WD
Water & Sewer - Manholes & Bases/Frames & Covers/Standard (Round) 33-05-13 (Rev 2/3/16)
* 33 05 13 Manhole Frames and Covers Western Iron Works, Bass & Hays Foundry 30024 24" Dia.
* 33 05 13 Manhole Frames and Covers McKinley Iron Works Inc. A 24 AM 24" Dia.
08/24/18 33 05 13 Manhole Frames and Covers Neenah Foundry R-1272 ASTM A48 & AASHTO M306 24" Dia.
08/24/18 33 05 13 Manhole Frames and Covers Neenah Foundry R- 165-LM (Hinged) ASTM A48 & AASHTO M306 24" Dia.
08/24/18 33 05 13 Manhole Frames and Covers Neenah Foundry NF 1274 ASTM A48 & AASHTO M306 30" Dia.
08/24/18 33 05 13 Manhole Frames and Covers Neenah Foundry R-1743-LM (Hinged) ASTM A48 & AASHTO M306 30" dia.
33 05 13 Manhole Frames and Covers Sigma Corporation MH-144N
33 05 13 Manhole Frames and Covers Sigma Corporation MH-143N
33 05 13 Manhole Frames and Covers Pont-A-Mousson GTS-STD 24" dia.
33 05 13 Manhole Frames and Covers Neenah Casting 24" dia.
10/31/06 33 05 13 Manhole Frames and Covers (Hinged) Powerseal Hinged Ductile Iron Manhole ASTM A536 24" Dia.
7/25/03 33 05 13 Manhole Frames and Covers Saint-Gobain Pipelines (Pamrex/rexus) RE32-R8FS 30" Dia.
01/31/06 33 05 13 30" Dia. MH Ring and Cover East Jordan Iron Works V1432-2 and V1483 Designs AASHTO M306-04 30" Dia.
11/02/10 33 05 13 30" Dia. MH Ring and Cover Sigma Corporation MH1651FWN & MH16502 30" Dia
07/19/11 33 05 13 30" Dia. MH Ring and Cover Star Pipe Products MH32FTWSS-DC 30" Dia
08/10/11 33 05 13 30" Dia. MH Ring and Cover Accucast 220700 Heavy Duty with Gasket Ring 30" Dia
10/14/13 33 05 13 30" Dia. MH Ring and Cover (Hinged & Lockable) East Jordan Iron Works
30" ERGO XL Assembly
with Cam Lock/MPIC/T-Gasket ASSHTO M105 & ASTM A536 30" Dia
06/01/17 34 05 13 30" Dia. MH Ring and Cover (Hinged & Lockable) CI SIP Industries 2280 (32") ASTM A 48 30" Dia.
09/16/19 33 05 13 30" Dia. MH Ring and Cover Composite Access Products, L.P.
CAP-ONE-30-FTW, Composite, w/ Lock
w/o Hing 30" Dia.
10/07/21 34 05 13 30" Dia. MH Ring and Cover Trumbull Manufacturing 32"(30") Frame and Cover 30" Dia.
Water & Sewer - Manholes & Bases/Frames & Covers/Water Tight & Pressure Tight 33-05-13 (Rev 2/3/16)
* 33 05 13 Manhole Frames and Covers Pont-A-Mousson Pamtight 24" Dia.
* 33 05 13 Manhole Frames and Covers Neenah Casting 24" Dia.
* 33 05 13 Manhole Frames and Covers Western Iron Works,Bass & Hays Foundry 300-24P 24" Dia.
* 33 05 13 Manhole Frames and Covers McKinley Iron Works Inc. WPA24AM 24" Dia.
03/08/00 33 05 13 Manhole Frames and Covers Accucast RC-2100 ASTM A 48 24" Dia.
04/20/01 33 05 13 Manhole Frames and Covers (SIP)Serampore Industries Private Ltd. 300-24-23.75 Ring and Cover ASTM A 48 24" Dia.
Water & Sewer - Manholes & Bases/Precast Concrete (Rev 1/8/13)
* 33 39 10 Manhole, Precast Concrete Hydro Conduit Corp SPL Item #49 ASTM C 478 48"
* 33 39 10 Manhole, Precast Concrete Wall Concrete Pipe Co. Inc. ASTM C-443 48"
09/23/96 33 39 10 Manhole, Precast Concrete Concrete Product Inc. 48" I.D. Manhole w/ 32" Cone ASTM C 478 48" w/32" cone
05/08/18 33 39 10 Manhole, Precast Concrete The Turner Company 48", 60" I.D. Manhole w/ 32" Cone ASTM C 478 48", 60"
10/27/06 33 39 10 Manhole, Precast Concrete Oldcastle Precast Inc.48" I.D. Manhole w/ 24" Cone ASTM C 478 48" Diam w 24" Ring
06/09/10 33 39 10 Manhole, Precast (Reinforced Polymer)Concrete US Composite Pipe Reinforced Polymer Concrete ASTM C-76 48" to 72"
09/06/19 33 39 20 Manhole, Precast Concrete Forterra Pipe and Precast 60" & 72" I.D. Manhole w/32" Cone ASTM C-76 60" & 72"
10/07/21 32 39 20 Manhole, Precast Concrete Forterra Pipe and Precast 48" I.D. Manhole w/32" Cone ASTM C-77 48"
10/07/21 33 39 20 Manhole, Precast (Reinforced Polymer) Concrete Armorock 48" & 60" I.D. Manhole w/32" Cone 48" & 60"
10/07/21 33 39 20 Manhole, Precast (Hybrid) Polymer & PVC Predl Systems 48" & 60" I.D. Manhole w/32" Cone 48" & 60" Non Traffic Areas
Water & Sewer - Manholes & Bases/Rehab Systems/Cementitious
* E1-14 Manhole Rehab Systems Quadex
04/23/01 E1-14 Manhole Rehab Systems Standard Cement Materials, Inc. Reliner MSP
E1-14 Manhole Rehab Systems AP/M Permaform
4/20/01 E1-14 Manhole Rehab System Strong Company Strong Seal MS2A Rehab System
5/12/03 E1-14 Manhole Rehab System (Liner) Poly-triplex Technologies MH repair product to stop infiltration ASTM D5813
08/30/06 General Concrete Repair FlexKrete Technologies Vinyl Polyester Repair Product Misc. Use
Water & Sewer - Manholes & Bases/Rehab Systems/NonCementitious
05/20/96 E1-14 Manhole Rehab Systems Sprayroq, Spray Wall Polyurethane Coating ASTM D639/D790
* E1-14 Manhole Rehab Systems Sun Coast
12/14/01 Coating for Corrosion protection(Exterior) ERTECH Series 20230 and 2100 (Asphatic Emulsion)
For Exterior Coating of Concrete
Structures Only
01/31/06 Coatings for Corrosion Protection Chesterton Arc 791, S1HB, S1, S2 Acid Resistance Test Sewer Applications
8/28/2006 Coatings for Corrosion Protection Warren Environmental S-301 and M-301 Sewer Applications
08/30/06 Coatings for Corrosion Protection Citadel SLS-30 Solids Epoxy Sewer Applications
03/19/18
33 05 16, 33 39 10,
33 39 20 Coating for Corrosion protection(Exterior) Sherwin Williams
RR&C Dampproofing Non-Fibered Spray
Grade (Asphatic Emulsion)
For Exterior Coating of Concrete
Structures Only
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
Note: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.
Updated: 03/29/2022
* From Original Standard Products List 1