NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: GTB South Commercial
City Project No.: 104495
Improvement Type(s): Water x❑ Sewer x❑
Original Contract Price: $150,421.50
Amount of Approved Change Order(s):
Revised Contract Amount:
Total Cost of Work Complete: $150,421.50
iimm ham blin (Jan 22,2024 14:06 CST) Jan 22, 2024
Contractor Date
Vice President
Title
Jimmv Hamblin
Company Name
1611e"1�a�
Jan 22, 2024
Roderick Baker (Jan 22, 202415:10 CST)
Project Inspector
Date
4.2002412:21
Jan 24, 2024
nnd1DAddik-i ( 2 SCST)
Project Manager
Date
n
Jan 24, 2024
Rebecca Diane Owen (Jan 24.202412:25 CST)
CFA Manager
Date
Lauren Prieur (Jan 24, 202413:05 CST)
Jan 24, 2024
TPW Director
Date
cl�
Jan 25, 2024
Asst. City Manager
Date
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Page 1 of 2
Notice of Project Completion
Project Name: GTB South Commercial
City Project No.: 104495
City's Attachments
Final Pay Estimate ❑x
Change Order(s): ❑ Yes ❑x N/A
Pipe Report: x❑ Yes ❑ N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time: 35 WD
Work Start Date: 10/17/2023
Completed number of Soil Lab Test: 14
Completed number of Water Test: 2
Days Charged: 40
Work Complete Date: 1/5/2024
Page 2of2
FoRTWORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name GTB SOUTH COMMERCIAL
Contract Limits
Project Type WATER & SEWER
City Project Numbers 104495
DOE Number 4495
Estimate Number 1 Payment Number 1 For Period Ending
City Secretary Contract Number
Contract Date
Project Manager NA
Contractor BCAC UNDERGROUND
5000 AIRPORT FRWY
HALTOM , TX 76117
Inspectors R.HORTON / R.BAKER
Contract Time
Days Charged to Date
Contract is 100.00
1/5/2024
WD
3WD
40
Complete
Monday, January 22, 2024 Page 1 of 5
City Project Numbers 104495
Contract Name GTB SOUTH COMMERCIAL
Contract Limits
Project Type WATER & SEWER
Project Funding
UNIT I: WATER IMPROVEMENT
Item Description of Items Estimated Unit
No. Quanity
1 6" PVC WATER PIPE 7 LF
2 8" PVC WATER PIPE 642 LF
3 6" GATE VALVE 1 EA
4 8" GATE VALVE 1 EA
5 12" CUT - IN GATE VAVLE 1 EA
6 CONNECTION TO EXISTING 4"-12" WATER 1 EA
MAIN
7 TRENCH SAFTEY
8 DUCTICLE IRON WATER FITTINGS W/
RESTRAINT
9 FIRE HYDRAT
10 2" WATER SERVICE
11 1" WATER SERVICE
12 REMOVE SIDEWALK
13 REMOVE FENCE
14 REMOVE CONC PVMT
15 4"-12" PRESSURE PLUG
16 9" CONC PVMT
17 4" CONC SIDEWALK
18 UTILITY SERVICESURFACE RESTORATION
SODDING
DOE Number 4495
Estimate Number 1
Payment Number 1
For Period Ending 1/5/2024
Unit Cost
Estimated
Completed
Completed
Total
Quanity
Total
$32.00
$224.00
7
$224.00
$58.00
$37,236.00
642
$37,236.00
$1,300.00
$1,300.00
1
$1,300.00
$2,290.00
$2,290.00
1
$2,290.00
$4,800.00
$4,800.00
1
$4,800.00
$500.00
$500.00
1
$500.00
649
LF
$2.50
$1,622.50
649
$1,622.50
0.91
TN
$4,700.00
$4,277.00
0.91
$4,277.00
1
EA
$4,800.00
$4,800.00
1
$4,800.00
1
EA
$3,200.00
$3,200.00
1
$3,200.00
1
EA
$2,300.00
$2,300.00
1
$2,300.00
50
SF
$2.50
$125.00
50
$125.00
20
LF
$2.00
$40.00
20
$40.00
69
SY
$5.00
$345.00
69
$345.00
1
EA
$325.00
$325.00
1
$325.00
69
SY
$60.00
$4,140.00
69
$4,140.00
50
SF
$11.00
$550.00
50
$550.00
1025
SY
$19.00
$19,475.00
1025
$19,475.00
Sub -Total of Previous Unit $87,549.50 $87,549.50
-------------
UNIT H: SANITORY IMPROVEMENT
Item
Description of Items
Estimated Unit
Unit Cost
Estimated
Completed
Completed
No.
Quanity
Total
Quanity
Total
---------------------------------------
19
REMOVE SIDEWALK
50 SF
$2.50
$125.00
50
$125.00
20
REMOVE CONC PVMT
88 SY
$5.00
$440.00
88
$440.00
21
4" SEWER ABANDOMENT PLUG
3 EA
$150.00
$450.00
3
$450.00
22
9" CONC PVMY
88 SY
$60.00
$5,280.00
88
$5,280.00
23
4" CONC SIDEWALK
50 SF
$11.00
$550.00
50
$550.00
24
UTILITY SERVICE SURFACE RESTORTION
319 SY
$19.00
$6,061.00
319
$6,061.00
SODDING
Monday, January 22, 2024 Page 2 of 5
City Project Numbers 104495 DOE Number 4495
Contract Name GTB SOUTH COMMERCIAL Estimate Number I
Contract Limits Payment Number 1
Project Type SANTTORY For Period Ending 1/5/2024
Project Funding
25 POST -CCTV INSPECTION
278 LF
$4.00
$1,112.00
278
$1,112.00
26 MANHOLE VACUUM TESTING
2 EA
$200.00
$400.00
2
$400.00
27 TRENCH SAFETY
278 LF
$3.00
$834.00
278
$834.00
28 TRENCH WATER STOPS
I EA
$750.00
$750.00
1
$750.00
29 4" SEWER PIPE
18 LF
$40.00
$720.00
18
$720.00
30 6" SEWER PIPE
10 LF
$52.50
$525.00
10
$525.00
31 8" SEWER PIPE
210 LF
$67.00
$14,070.00
210
$14,070.00
32 8" SEWER PIPE, CLASS CSS BACKFILL
40 LF
$71.00
$2,840.00
40
$2,840.00
33 EPOZY MANHOLE LINER
20 VF
$438.00
$8,760.00
20
$8,760.00
34 4' MANHOLE
2 EA
$4,900.00
$9,800.00
2
$9,800.00
35 4' EXTRA DEPTH MANHOLE
7 VF
$165.00
$1,155.00
7
$1,155.00
36 4' DROP MANHOLE
1 EA
$4,500.00
$4,500.00
1
$4,500.00
37 TRAFFIC CONTRAL
3 MO
$1,500.00
$4,500.00
3
$4,500.00
Sub -Total of Previous Unit
$62,872.00
$62,872.00
Monday, January 22, 2024 Page 3 of 5
City Project Numbers 104495
Contract Name GTB SOUTH COMMERCIAL
Contract Limits
Project Type SANTTORY
Project Funding
Contract Information Summary
Original Contract Amount
Chanhe Orders
Total Contract Price
DOE Number 4495
Estimate Number 1
Payment Number 1
For Period Ending 1/5/2024
$150,421.50
$150,421.50
Total Cost of Work Completed $150,421.50
Less % Retained $0.00
Net Earned $150,421.50
Earned This Period $150,421.50
Retainage This Period $0.00
Less Liquidated Damages
Days @ / Day
LessPavement Deficiency
Less Penalty
Less Previous Payment
Plus Material on Hand Less 15%
Balance Due This Payment
$0.00
$0.00
$0.00
$0.00
$0.00
$150,421.50
Monday, January 22, 2024 Page 4 of 5
City Project Numbers 104495
Contract Name GTB SOUTH COMMERCIAL
Contract Limits
Project Type SANTTORY
Project Funding
Project Manager NA
Inspectors R.HORTON / R.BAKER
Contractor BCAC UNDERGROUND
5000 AIRPORT FRWY
HALTOM , TX 76117
DOE Number 4495
Estimate Number 1
Payment Number 1
For Period Ending 1/5/2024
City Secretary Contract Number
Contract Date
Contract Time 35 WD
Days Charged to Date 40 WD
Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
Total Cost of Work Completed $150,421.50
Less % Retained $0.00
Net Earned $150,421.50
Earned This Period $150,421.50
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty
$0.00
Less Previous Payment
$0.00
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$150,421.50
Monday, January 22, 2024 Page 5 of 5
FORTWORTH
TRANSPORTATION AND PUBLIC WORKS
PIPE REPORT FOR:
PROJECT NAME: GTB South Commercial Lot 1,2 & 3, Block 1
CITY PROJECT NUMBER: 104495
WATER
PIPE LAID SIZE TYPE OF PIPE
WATER 6" PVC C-900
WATER 8" PVC C-900
LF
FIRE HYDRANTS: 1 VALVES (16" OR LARGER)
PIPE ABANDONED SIZE TYPE OF PIPE LF
7
642
DENSITIES:
Yes
NEW SERVICES:
2"
Copper
1 EA
1"
Copper
1 EA
SEWER
PIPE LAID
SIZE
TYPE OF PIPE
LF
SEWER
4"
SDR-26
18
SEWER
6"
SDR-26
10
SEWER
8"
SDR-26
210
PIPE ABANDONED
SIZE TYPE OF PIPE
DENSITIES: Yes
NEW SERVICES:
TRANSPORTATION AND PUBLIC WORKS
The City of Fort Worth • 1000 Throckmorton Street • Fort Worth, TX 76012-6311
LF
FORTWORTH.
TRANSPORTATION AND PUBLIC WORKS
January 8, 2024
BCAC Underground, LLC
5000 Airport Freeway
Haltom City, Texas 76117
RE: Acceptance Letter
Project Name: GTB South Commercial
Project Type: Water, Sanitary Sewer
City Project No.: 104495
To Whom It May Concern:
On January 8, 2024 a final inspection was made on the subject project. There were no punch list items
identified at that time. The final inspection indicates that the work meets the City of Fort Worth
specifications and is therefore accepted by the City. The warranty period will start on January 8, 2024,
which is the date of the final inspection and will extend of two (2) years in accordance with the Contract
Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at 817-
392-8424.
Sincerely,
S,,,4 Aa*,Pft.? E
Sandi Adhikari (Jan 24, 202412:21 CST)
Sandip Adhikari, Project Manager
Cc: Roderick Baker, Inspector
Mike Glover, Inspection Supervisor
Randy Horton, Senior Inspector
Andrew Goodman, Program Manager
Peloton Land Solutions, Consultant
BCAC Underground, Contractor
Hillwood Alliance Services, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev. 08/20/19
NOTICE:
THIS DOCUMENT WAIVES RIGHTS UNCONDITIONALLY AND STATES
THAT YOU HAVE BEEN PAID FOR GIVING UP THOSE RIGHTS. IT IS PROHIBITED
FOR A PERSON TO REQUIRE YOU TO SIGN THIS DOCUMENT IF YOU HAVE NOT
BEEN PAID THE PAYMENT AMOUNT SET FORTH BELOW. IF YOU HAVE NOT
BEEN PAID, USE A CONDITIONAL RELEASE FORM.
UNCONDITIONAL WAIVER AND RELEASE ON PROGRESS PAYMENT
Project: GTB South Commercial
Job No. 23006
The signer of this document has been paid and has received a progress payment in the sum
of $140,247.05 for all labor, services, equipment, or materials furnished to the property minus
Retainage to BCAC Utilities LLC (person with whom signer contracted) on the property of
Hillwood Alliance Services (owner) located at Fort Worth, Texas (location) to the following
extent: Utilities (job description). The signer therefore waives and releases any mechanic's lien
right, any right arising from a payment bond that complies with a state or federal statute, any
common law payment bond right, any claim for payment, and any rights under any similar
ordinance, rule, or statute related to claim or payment rights for persons in the signer's position
that the signer has on the above referenced project to the following extent:
This release covers a progress payment for all labor, services, equipment, or materials
furnished to the property or to BCAC Utilities LLC (person with whom signer contracted) as
indicated in the attached statement(s) or progress payment request(s), except for unpaid
retention, pending modifications and changes, or other items furnished.
The signer warrants that the signer has already paid or will use the funds received from this
progress payment to promptly pay in full all of the signer's laborers, subcontractors, materialmen,
and suppliers for all work, materials, equipment, or services provided for or to the above referenced
i
project in regard to the attached statement(s) or progress payment request(s).
Date:
BCAC Underground, LLC
;0 4�—
Ben Goodall, CEO
Lindsey S Grier
M7 � ornmistion
111131202 7 xpins
1 }' J ✓ —
Notary ID130323782
0
FF
100=6—
CONSENT OF SURETY
TO FINAL PAYMENT
Conforms with the American Institute of
Architects, AIA Document G707
TO OWNER:
(Name and address)
Hillwood Alliance Services LLC
9800 Hillwood parkway, Ste. 300
Fort Worth, TX 76177
PROJECT:
(Name and address)
CFA Number - CFA22-0180 - GT13 South Commercial
City Project No. 104495
CONTRACT FOR: OCP: $150,42 L'
FCP: $150,421.`
CONTRACT DATED: 7/12/2023
iii Wd1'iieh& Uith the provisions of the Contract between the Owner and the Contractor as indicated above, the
(Insert name and address ofSurery)
The Hanover Insurance Company
440 Lincoln Street
Worcester, MA 01653-0002
on bond of
(Insert name and address of Contractor)
BCAC Underground, LLC
5000 Airport Freeway
Haltom City, TX 79117
hereby approves of the final payment to the Contractor, and agrees that final payment to the Contractor shall n,
of its obligations to
(Insert name and address of Owner)
Hillwood Alliance Services LLC
9800 Hillwood parkway, Ste. 300
Fort Worth, TX 76177
as set forth in said Surety's bond.
IN WITNESS WHEREOF, the Surety has hereunto set its hand on this date: January 10, 2024
(Insert in writing the month followed by the numeric date and year.)
Attest: 1,
Bridget Truxillo, itness
The Hanover Insurance Company
(Surety)
(Signature of authori=ed representative)
Sean McCauley, Jr, Attorney -in -Fact
(Printed name and title)