CSC No. 56216-0O2
Attest: C ii
ddnn nezpsa4a
City Of Fort worth
Change Order Request
Facility and Project Diamond Hill Community Center Renovation
City Sec No. 56216
Description:
Funding (FID) No.(s) FID # 34018 0800450 5740010101652 004580
FID # 31002 0800450 5740010101652 000780
City Proj. No. 101652
Contractor: I Muckleroy & Falls Change Order #
0 Date: 1
1/17/2024
City Project Mgr.IAlfonso Meza City Inspector:
I Lisa Pyper
Phone Number: 1 (817) 392-8274 Phone Number:
1(817) 392-2391
Contract Time
(CD)
Original Contract Amount--------------------------------------------------------------------------------
58,219,906.80
390
Extras to Date-------------------------------•------------------------------------------------
$2,840.52
0
Creditsto Date•------------------------------------------------•---------------------------------------
0.00
0
Pending Change Orders (in M&C Process)-----------------------------------------------------------1
0.00
0
Contract Cost to Date------------------------------•------------------------------------------------
58,222,- 47.32
390
Amount of Proposed Change Order------------------------------------------------------------------I
0.00
311
Revised Contract Amount---------------------------------------------------------------------------------
1 58,222,747.32
701
Original Funds Available for Change Orders--------------------------------------------------------1
0.00
Remaining Funds Available for this CO ------------------------------------------------- -----------I
0.00
Additional Funding (if necessary)--------------------------------------------------------------------{
'0.00
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
0. 1
MAXALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%)
$10,274,883.50
JUSTIFICATION (REASONS) FOR CHANGE ORDER
The purpose of Change Order #2 is to add 311 days to the project duration. This will increase the project time to 701 total days for the completion of Diamond
Hill Community Center. Muckelroy and Falls did not request additional GC's nor is the CoFW assessing LD's for the additional time. This change order is at no
cost to the original contract amount ($8,219,906.80).
It is understood and agreed that the acceptance of this Change Order by the contractor consitutes an accord and satisfaction and represents payment in full (both
Contractor's Company Name Contractor Name Contractor Signature I Date
Muckleroy & Falls MAP N/(("-f1 r Jan 17, 2024
PMD Inspector
Date
Architecural Services Manager
Date
w
Jan 17, 2024
Jan 19, 2024
PMD Superintendent
Date
Director/Property Management Department
Date
Jan 17, 2024
Jan 24, 2024
Project M=Jlgr
Date
Assistant City Attorney
Date
Jan 18, 2024
-" stn4
Jan 29, 2024
Date
Assistant City Manager
Darte
. <<
Jan 18, 2024
Dana Sur hd%ff
,,,N�.a,�»,,.<„
Jan 29, 2024
M&C Number I N/A
M&C Date Approved
N/A
Contract Compliance Manager:
By signing I acknowledge that I am the person responsible OFFICIAL RECORD
for the monitoring and adminstration of this contract, including CITY SECRETARY Nikita Watts
ensuring all performance and reporting requirements. FT. WORTH, TX Architectural Services Manager
'M' MUCKLEROY & FALLS
Project Name: Diamond Hill Community Center
MF Job Number: 21667 Date: 01/09/24
PCO 85
To: City of Fort Worth
1 General Conditions
$
0.00
2 Self -Perform
$
0.00
3 Subcontractors, (Breakdowns Attached)
$
0.00
4 Builders Risk Insurance
$
0.00
5 General & Excess Liability Insurance
$
0.00
SUBTOTAL
$
0.00
6 Contractor Fee 10%
$
0.00
7 Payment & Performance Bonds
$
0.00
PROPOSED CHANGE TOTAL
$ 0.00
DESCRIPTION: Incorporate project delay days to contractual substantial completion date. Add 311 days
for a revised contractual substantial completion date of 10/31/2023.
This PC is issued to incorporate the revisions as specifically detailed on the attached cost summary and
supporting documents. If additional costs become apparent at a later date, or additional documents to
this scope of work become available, we reserve the right to price any additional costs and/or schedule
impacts as they become known.
Excludes any scope not listed above.
Please sign and return this PCO by January 10, 2024
HM & MF Ltd., dba Muckleroy & Falls
'W' MUCKLEROY & FALLS
January 9, 2024
Mr. Jackson Jones
Diamond Hill Community Center
1700 NE 37th Street
Fort Worth, TX 76106
Re: Diamond Hill Community Center
Summary of Documented Delays
Dear Mr. Jones,
3200 Riverfront Drive, Suite 200 Fort Worth, TX 76107
817.877.3510 1 www.MuckleroyFalls.com
This letter shall serve as written notification of documented lost days on the above referenced
project due to the reasons set forth below:
Contract Summary
➢ Project Award Date: 5/2021
➢ Contract Executed: 8/9/2021
➢ Permitting Delays from Project Award Date: Appx. 6 months
➢ NTP Date: 11/29/2021
➢ Permit Received: 11/19/2021
➢ Original Substantial Completion Date(390 days from NTP): 12/25/2022
➢ Actual and Revised Substantial Completion date:10/31/2023
Maior Delav Summarv:
• 311 "delay" days from original substantial completion date to actual substantial
completion date.
Critical Path delays:(please note some of these delays are concurrent with each other,
but are noted independently)
1. Market volatility/changes. General Contractor Pricing and material escalations and
reserve of materials, due to project award date vs NTP. PCO 01. (45d)
2. Earthwork Subcontractor Mobilization -Due to Permitting delays, early NTP. (35d)
3. PCO 08-Joist Change to WF Beams due to extended long lead duration of joists(28d)
4. Weather Days(weather log,105 day/22 claimable to critical path beyond allotted days in
contract) (22d)
5. Concrete Subcontractor Delays and Default.(60d)
6. Rework previous Concrete Subcontractor's deficiencies(30d)
7. Concrete Mix Availability during GB and slab pours due to changing market
conditions(10d)
8. Rock encountered during MEP Underground Rough in.(PCO 24) (15d)
9. Excavate for GB Void Clearance verifications and weather damage wash out(PCO
27)(5d)
L E A D E R S H I P I I L 0 Y A L T Y I W O R K E T H I C
11
MUCKLEROY & FALLS 3200 Riverfront Drive, Suite 200 Fort Worth, TX 76107
817.877.3510 1 www.MuckleroyFalls.com
10. PEMB Anchor Bolt Rework(7d)
11. PEMB-Structural Steel Design Coordination and Drawing Discrepancies(20d)
12. Glazing delays due to market lead time changes and PEMB discrepancies(10d)
13. Roofing Damage due to storm -Reinstallation. Impacted dry in(10d)
14. Waterproofing at Glazed block windows. Impacted dry in. PCO 38 and41, RFI 47)(15d)
15. Copper thefts(Electrical and Plumbing on 4-5 occasions) Plumbing rework (10d)
16.Add Wood Blocking substrate at roof gutters; impacted dry in.(5d)
17. MEP Rough in through PEMB Beams(PCO 43).(10d)
18. Additional Rough in for AV(PCO 51,60)(3d)
19. Furr out walls in Fitness. PCO 47 (5d)
Based on the above impacts and delays, Muckleroy & Falls seeks an additional 311 calendar
days. Please be advised this is only a summary of "major" delays encountered. Other delays
were experienced that ran concurrently with the above noted delays. M&F does not seek any
costs for noted delays since LD's are not being enforced.
Sincerely,
Muckleroy & Falls
Keith Melton
Project Director