Change Order Request CONTRACT NO.
Change Order No. Date TPW Project No. Funding (FAC)
1 (one) 7/6/12 GG04-539120
0246000
Facility and Project Description City Secretary Contract No.
Roof Repairs at Will Rogers Memorial Center CS-43302
ORIGINAL CONTRACT AMOUNT................................................................ $1,182,491
EXTRAS TO DATE..................................................................... $ 0
CREDITS TO DATE.................................................................... $ 0
CONTRACT COST TO DATE.................................................................................................. $ 1,182,491
AMOUNT OF PROPOSED CHANGE ORDER............................................................................ $ 13,350
REVISED CONTRACT AMOUNT ..................................................... •OFFICIAtitECORD...... $1,195,841
ORIGINAL FUNDS AVAILABLE FOR CHANGE ORDERS ..................... ..CIT .NCRE.TARX....... $ 75,000
REMAINING FUNDS AVAILABLE FOR CHANGE ORDERS ...................... F.M.WORTHIIX,......... $ 61,650
ADDITIONAL FUNDING (IF NECESSARY).. ..............................................................................
IN ACCORDANCE WITH THIS CHANGE ORDER, THE CONTRACTOR SHALL;
Furnish all labor and material as per the attached Propose Change Request:
PCR 1 — Furnish and install 5 new copper scuppers to match existing
Add $ 1,780
PCR 2- Install NP-2 caulking at coping bed joint at Exhibit Hall Add $ 11,570
------------------------------------------------------------------------------------------------------------------------------
ADD $ 13,350
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time
and money) for all costs arising out of, or incidental to, the above Change Order
Contractor's Name
Jeff Eubank Roofing Co. Inc.
Original Contract Time Additional Approved Time To Date I Approved Contract Time To Date Additional Time For This Change Order
90 cd 0 cd
Contract6d— Jeff Eubank Reofing Co. Inc.
ArcKite!d I Services Manager
O& hmh' V'J
Project Architect — N//U
Distribution:
File
Construction Manager
Project Manager
Contractor
PO4:01
90 cd I 0 cd
Date WTrans
r
a-- & -/L ---
Daten and Public Works
W - C� -'-
vatdr
Date Council Action (If Required)
❑ Approved ❑ Disapproved
. I Z ❑Other �
A b "MA 0 0 �o��,a�a
�y` op° 000
0
00
M J, r, City S a Zr
°° ° * .a
A°oO0000°° cr
TPW Facilities Management Division �a41r �y�a
Change Order Form (01/31/12) ���"p-��
Date
Date j
Date
bate I
A- J
EFF
EUBANK
ROOFING
CO., INC.
July 5, 2012
City of Fort Worth
Transportation and Public Works Dept.
1000 Throckmorton St.
Fort Worth, Texas 76102
Attn: Jack Durham
Re: Roof Repairs at Will Rogers Memorial Center
PCR #1
Per your request we respectfully submit the following Project Change Request:
The copper scuppers on the Tower roofs are not in a condition to be reused as was
specified. We respectfully submit a change order in the amount of $1,780.00 to furnish
and install five new copper through -wall scuppers to match existing.
To clean, repair and reuse:
To replace with new:
NET CHANGE
If you have any questions please call.
nk Jr., LEED AP
nk Roofing Co., Inc.
LABOR MATERIALS TOTAL
$ 475.00 $ 150.00 $ 625.00
$ 1,283.00 $ 1,122.00 $ 2,405.00
$ 1,780.00
- Commerical Roofing and Sheet Metal A
A P.O. Box 4309 A Fort Worth, TX 76164-3090 A (817) 334-0161 A Toll Free (877) 220-6236 A Fax (817) 336-1811 A
www.eubankroofing.com A Licensed in FL, LA and NM
A� JEFF
EUBANK
ROOFING
CO., INC.
July 5, 2012
City of Fort Worth
Transportation and Public Works Dept.
1000 Throckmorton St.
Fort Worth, Texas 76102
Attn: lack Durham
Re: Roof Repairs at Will Rogers Memorial Center
PCR #2
Per your request we respectfully submit the following Project Change Request:
On the Exhibit Hall where the stone coping meets the brick it is our opinion that the
majority of this detail will need to be repointed. We were instructed to include only 10
linear feet and anything beyond that would be based on the submitted unit price.
• Entire Exhibit Hall per previously submitted unit price:
168.2 (10 linear foot units) @ $315.00 = $52,983.00
Option A— Install NP2 sealant at coping bed joint (1,682 linear feet), add $11,570.00
Labor
$ 9,256.00
Materials
$ 2.231.00
Total
$11,570.00
Option B — Re -point mortar at coping bed joint (1,682 linear feet), add $12,630.00
If you have any questions please call.
Jr., LEED AP
Roofing Co., Inc.
A Commerical Roofing and Sheet Metal A
A P.O. Box 4309 A Fort Worth, TX 76164-3090 A (817) 334-0161 A Toll Free (877) 220-6236 A Fax (817) 336-1811 A
www.cubankroofing.com A Licensed in FL, LA and NM