Loading...
HomeMy WebLinkAboutContract 52102-CO3FORT WOn-ir City of Fort Worth Change Order Request Project Name: Upper Big Fossil Creek Drainage Basin Parallel Relief Interceptor Project No.(s):I 56016 0700430 5740010 CO2515 I DOE No. I N/A CSC No. 52102-0O3 City Sec No.: 52102 City Proj. No.: 02515 Project Description: Construct Parallel Relief Interceptor in Upper Big Fossil Basin and Rehabilitate Existing M-347 and M-386 Contractor:I William J. Schultz, Inc. dba Circle C Const. Co. City Project Mgr.1 Walter Norwood I Phone Number: (817) 392-5026 Dept. Original Contract Amount Extras to Date Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date Amount of Proposed Change Order Revised Contract Amount Original Funds Available for Change Orders Remaining Funds Available for this CO Additional Funding (if necessary) Change Order # 3 1 Date: City Inspector: I John Robinson I Phone Number: (817) 392-8452 I 1 /22/2024 Water Sewer I $13,006,286.25 $89,305.00 Totals $13,006,286.25 Contract Time (Calender days) 546 0360 $13 095.59115 $13,095,591.25 816 395.00 $395.00 480 $1 ,095,986.25 $13,095,986.25 1,296 $260,125.00 $260,125.00 $170,820.00 $170.820,00 CHANGE ORDERS to DATE (I MAX ALLOWABLE CON JUSTIFICATION (REASONS) FOR CHANGE ORDER (INCLUDING Change Order No. 3 provides for the folllowing: • Rehabilitation of existing manholes since the existing pipeline is being rehabilitated via CIPP and the manholes are in good condition. • Epoxy lining in existing manholes (250 mil Thickness). • The deletion of pay item quantities that are no longer needed on the project. Staff recommends the addition of 480 calendar days to the project for the additional work and delays resulting from repeated failure during heavy rain events of a temporary creek crossing that required replacement. No work could be done on the other side of the creek until the creek crossing was restored subsequent to the rin events. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. aCtDftCompany N Contractor N3rt� _ (�t,, sr;ictor Signature Date William J. SOO?, Inc dba Circla C �nsl Cc � Teri Skelly � .�r � J � /— Z3 -2 Mans er Date 1 ^?1, Zvi nstructiori Supervisor a%r ep11 Date ]hrrs"21- ' Feb 2, 2024 +=s,!stanl ;ity Manager Date Feb 7, 2024 �G Feb 7, 2024 ugla M&C Number I NIA M&C Date Approved I N/A I OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX FORT WO RTH City of Fort Worth Change Order Additions Project Name Upper Big Fossil Creek Drainage Basin Parallel Relief Interceptor City Sec No.: 1 52102 Project No,(s): 56016 0700430 5740010 CO2515 , DOE No.1 N/A I City Proj, No.: 1 02515 Project Construct Parallel Relief Interceptor in Upper Big Fossil Basin and Rehabilitate Existing M-347 and M-386. Description Contractor William J. Schultz, Inc. dba Circle C Const. Co. Change Order: l 3 J Date: j 11/13/2022 City Project Mgr. j Walter Norwood City Inspector I John Robinson ADDITIONS HEM EM - UhbL;KIP I IUN DEPT 116 MFI AdIust/MH Repair including New Ring/Cover & 250 mil epoxy liner Sewer 117 250 mil Epoxy Liner in MH Extra Depth Sewer 118 250 mil Epoxy Liner In MH in Beach Sta. 370+92 Sewer Unit Unit Cost 1 Total 13.00 EA $9,300.00 $120,900.00 181.00 VF $350.00 $63,350.00 8.00 VF $350.00 $2,800.00 lwater Sewer $187,050,00 0 Page i oi' 1 jAdditions Sub Total $187,050.00 FORT WORTH City of Fort Worth -� Change Order Deletions Project Name Upper Big Fossil Creek Drainage Basin Parallel Relief Interceptor I City Sec No.: 52102 Project No.(s): 56016 0700430 5740010 CO2515 I DOE No. I N/A City Proj. No.: 02515 Project Description I Construct Parallel Relief Interceptor in Upper Big Fossil Basin and Rehabilitate Existing M-347 and M-386. Contractor I William J. Schultz, Inc. dba Circle C Const. Co. I Change Order: FT] Date I 11/13/2022 City Project Mgr. Walter Norwood City Inspector: I John Robinson DELETIONS ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total 6 48" Fiberglass Sewer Pipe, CLSM Backfill Sewer 13.00 LF $535.00 $6,955.00 22 5' Manhole Sewer 13.00 EA $7,500,00 $97.500.00 23 5' Extra Depth MH Sewer 168.00 VF $250.00 $42,000.00 101 Conshield Antimicrobial in 5' Manhole Extra Depth Sewer 13.00 EA $1,800.00 $23,400.00 102 Conshield Antimicrobial in 5' Extra Depth Manhole Sewer 168.00 VF $100,00 $16,800.00 Water Sewer $186,655.00 I Page 1 of 1 IDeletions Sub Total $186,655.00 MIWBE Breakdown for this Change Order MWBE Sub I Type of Service _( Amount for this CO Total $0.00 Previous Change Orders co tt DATE I AMOUNT Total $0.00 Page 1 of 1 1/22/2024 Upper Big Fossil Creek Drainage Basin Parallel Relief Interceptor Project CPN CO2515 Change Order 3 Notes Staff has reviewed the requested prices and considers them to be fair and reasonable. Contract Compliance Manager By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. Signature Walter Norwood Name of Employee Project Manager Title a4�nan� �� �000000000 Y p �`o $4 ATTEST: pv8 o= 0 o 0o f 4r, rEX C/, ��da444 Jannette Goodall City Secretary OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX