HomeMy WebLinkAboutContract 39252-A3AMENDMENT NUMBER 3
STATE OF TEXAS 6 CITY SECRETARY CONTRACT NO.3 {os�m
COUNTY OF TARRANT 6
WHEREAS, the City of Fort Worth (City) and Jacobs Engineering Group, Inc. (Engineer) made and
entered into City Secretary Contract No. 39252, (the Contract) which was authorized by the City Council by
MSC C-23944 on the 8th day of December 2009 and amended by City Secretary Contract No. 39252-A1 on
the 180 day of May, 2010; and
WHEREAS, the Contract involves engineering services for the following project:
Alliance Runway Extension Phase 8, Project No. 00960
WHEREAS, it has become necessary to execute Amendment No. 3 to said Contract to include
an increased scope of work and revised maximum fee for professional services for the acquisition
of land necessary for the Burlington Northern Santa Fe Railroad connector track and relocation
of their main line;
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their duly authorized
representatives, enter into the following agreement, which amends the Contract:
1.
Article I of the Contract is amended to include the additional engineering services specified in
the proposal letter dated January 26, 2011, a copy of which is attached hereto and incorporated
herein. The cost to City for the additional services to be performed by ENGINEER; total
$546,621.29.
2.
Article II of the Contract is amended to provide for an increase in the fee to be paid to
ENGINEER for all work and services performed under the Contract, as amended, so that the total
fee paid by the City for all work and services shall not exceed the sum of $2,390,539.51.
Page 1-
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
3.
I
All other provisions of the Contract, which are not expressly amended herein, shall remain in full
force and effect.
EXECUTED on this the day of � , 2011 in Fort Worth, Tarrant County, Texas.
APPROVAL RECOMMENDED: APPROVED:
/enneth L. nney, Jr., A.A.E. Fernando Costa
Aviation Director Assistant City Manager
Jacobs Engin ri kGrup Inc. �QIt'i�� /•�
Enginee Y (�
By:
Name: Xev in T. t�je (Sort, j? E Authorization: pa°'-ORT a�
°°°°°
Title: VjLe''r es id-e n+ ` a 0 °° °°o
Date: 1 �I Zq l 1 PA-40 OA
° °3
p Fo 0
O 00 ° o
o°�C
o °
APPROV S TO FORM AND LEGALITY: ��� °°°00000°°° a
i
Dou Black 0:-449,5-
Assistant City Attorney - I
Contract Authorization
D�it_=
Page -2 - OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
ii
Nov
ffff
January 26, 2011
Mr. Tim Ward
Alliance Air Services
2221 Alliance Blvd, Suite 100
Fort Worth, TX 76177
Re: Alliance Airport Runway Extension Project, Phase VIII
Amendment No. 3
Dear Mr. Ward:
I am requesting an amendment to the Alliance Airport Runway Extension Project Phase VIII contract. This
amendment is for additional work that was not part of the original contract. We received the BNSF Main
Line and Connector Track alignment in November of 2010. This alignment was to establish the right-of-
way and easement requirements for the Main Line and Connector Track. The alignment submitted by
BNSF is different than the alignment shown in our February 2010 Preliminary Engineering Report. The
BNSF alignment requires an additional 30 parcels and 40 easements to be acquired. The additional work
will also add additional 20 weeks to the schedule. A summary of the additional work items are shown
below. The detailed scope of work, fee proposals and schedule are attached for your information.
Jacobs ... Program Management
Transystem - Right -of -Way Acquisition and Phase I Environmental Site Assessment
ANA Additional Right -of -Way Survey and Utility Easements (DBE)
Total cost increase for Contract Amendment #3
DBE Participation for Contract Amendment #3
Original Contract Amount
Previous Amendments
Contract Amendment # 3
New Contract Amount
DBE Participation Amount for New Contract Amount
DBE Participation % for New Contract Amount
$80,873.29
$ 266,748.00
$199,000.00
$546,621.29
36.41 %
$1,323,029.89
$520,888.33
$546.621.29
$2,390,539.51
$608,177.48
25.44%
Thank you for your attention to this request. Should you have any questions or comments regarding this
matter please feel free to contact me at 817-735-7004 or by email at Jeff;Toncrq Jacob...s,.coni .
*neJ. Toner, P.E.
m Manager
JJT,°ss
cc: Patrick Buckley City of Fort Worth
Ruseena Johnson - City of Fort Worth
Aya Ealy City of Fort Worth
--
January 26, 2011
Alliance Runway Extension Project - Phase VIII
Amendment No. 3
Program Management
Scope of Work
The schedule for the land acquisition extends beyond the scheduled completion date of the
original scope of work for Phase VIII. Therefore, Jacobs will provide additional program
management activities from the completion of the original Phase VIII work to the
completion of the land acquisition. The estimated duration for these services is an
additional 20 weeks. During this time Jacobs will:
• Conduct bi-weekly project coordination meetings
• Conduct additional stake holder meetings
• Prepare and distribute meeting minutes
• Monitor and adjust the program schedule
• Monitor and adjust the program budget
• Maintain the document control system
• Administer the prime and subcontract agreements
• Provide technical and graphic support for the program
• Provide technical reviews of the land acquisition documents
• Coordinate with BNSF, FAA, Alliance Airport and City of Fort Worth
Jacobs will also provide program management services associated with tasks identified in
City of Fort Worth / Burlington Northern Santa Fe Relocation Agreement. The work
identified below is for reporting requirements for the BNSF Main Line Relocation and
Connector Track. During this time Jacobs will:
• Prepare monthly status reports
• Review BNSF monthly status reports
• Review BNSF monthly pay request
Jacobs Fee Proposal
Alliance Airport Runway Extension Project
Professional Services for Additional Land Acquisition & Environmental Site Assessment 26-Jan-11
Amendment 03
Program Management Services
Labor Hour Estimate
Program Deputy
Senior Project CADD
Technical Admin
Manager Program Mgr
Engineer Controls Mgr. Tech
Assistant Assistant
f Program Management
Conduct Bi-Weekfq Progress Meetirt
IConduct Stakeholder Coordination Meetings
18
18
18 18
IPeepare & Distribute Meeting Minutes
9
18
(Maintain Proiect Schedules
4
18
U date Project Bud Is
9
18
Maintain Document Control System
34
Administer Contracts & Sub -Contracts
9
18
20
Technical & Graphic Su ort
Technical Review - ROW Acquisition 40
Coordinate with BNSF 36
(Coordinate with FAA, Alliance, Ft. Worth 36
I
COFW / BNSF Agreement
Prepare Monthly Status Report 16
�Review BNSF Lthly Status Report 16
Rev:ew BNSF Monthly Pay Request 16
I
I Total Hours
Fee Proposal
Program Manager
Deputy Program Manager
Senior Engineer
Project Controls Manager
CADD Technician
Technical Assistant
Administrative Assistant
JEG Labor Cost
Expenses
Mileage
Courier/Express Mail
Printing & Plotting
Reproduction
Total Expenses
187
Hourly
Rate
$ 112.00
$ 63.00
$ 57,00
$ 30.00
$ 31.00
$ 24.00
$ 19.00
Salary Cost
(Overhead Rate ® 126.85' �,
Sub - Total
Profit a 15%
0 40
Hours Labor
Cost
187 $ 20,944.00
0 $
40 $ 2,280.00
54 $ 1,620.00
40 $ 1,240.00
170 $ 4,080.00
1® $ 342.00
$ 30,506,00
$ 38,696 86
S 69,202.66
$ 10.380.43
S 79,583.29
$ 500.00
$ 90.00
$ 200.00
$ 500,00
$ 1,290.00
Total Program Management Cost S 80,873.29
40 20
24
18
18
54 40 170 18
1331 Airport Freeway
Suite 410
F,uless, Texas 76040
(817)335-9900
Fax (817) 335-9955
AUTHORIZATION FOR PROFESSIONAL SERVICES
PROJECT NAME:
Alliance Runway Extension — BNSF Mainline Relocation —
Property Map Survey
PROJECT No.:
10-0370.01 Amendment #2
CLIENT:
Jeff Toner, P.E.
Jacobs Engineering
ADDRESS:
777 Main St.
Fort Worth, Texas76102
SCOPE OF SERVICES:
See attached Exhibit `A' and layouts for detail Scope of Services.
COMPENSATION:
PROFESSIONAL SERVICES
Task 1: Deed Research and Task 2: Property Corner Location j
1 ' (not to exceed an additional 100 properties) $45,000.00
2 Right -of -Way Document Preparation $82,000.00
(not to exceed an additional 30 parcels)
3 Utility Easement Documentation $62,000.00
(not to exceed 40 parcels)
4 ; Temporary Construction Easement Documentation $10,000.00
(not to exceed 10 parcels)
Total $199,000.00
TOTAL ENGINEERING COMPENSATION: 0 $199,000.00 (Lump Sum
Additional services not covered in this authorization and its attachments will be provided
on an hourly basis per Exhibit `S'.
Services covered by this authorization shall be performed in accordance with
PROVISIONS stated on the attached form.
Approved for CLIENT Accepted for A.N.A. Consultants, L.L.C.
By: By
Mark Assaad, P.E.
Title: Title: Vice President
Date: Date: 01/13/2011
CLIENT SATISFACTION IS OUR BUSINESS
ANA Scope - Phase 8 - MOD 2-Original Job No 090590.dre
A.N.A. Consultants, L.L.C. Exhibit A — Scope of Services
A.N.A. Consultants, L.L.C. (herein referred to as ANA) is prepared to provide specific
civil engineering services for the Alliance Runwav Extension — BNSF Mainline
Relocation -Mod No. 2 (herein refer to as PROJECT) for Jacobs
Enqineerinq (herein called JACOBS).
1.0 INTRODUCTION
The purpose of this scope of work (SOW) is to provide engineering services, technical
manpower, and deliverables for the preparation of Right -of -Way Documents to be
implemented for the PROJECT.
1.1 Project Summary
ANA will provide survey services for the preparation of additional Right -of -
Way and Utility Easement documents along the proposed 11 mile BNSF
Mainline relocation. The scope also includes limited miscellaneous survey
services on an as -needed basis. The basis of this proposal is the BNSF
Mainline Relocation Alignment provided by Multatech dated November
2010.
The BNSF Mainline Relocation adjacent to the Fort Worth Alliance Airpoit
will be relocated for the proposed runway extension.
1.2 Information to be Provided by JACOBS
Upon receiving a notice to proceed (NTP), JACOBS shall fumish the
necessary hardcopy and electronic copy of the PROJECT CADD files
necessary for or incidental to the performance of work set forth herein for
the completion of the Right -of -Way Parcel Documents. These files
include but are not limited to the following:
• Project Border Sheet
• Project CADD Standards
• Overall alignment and aerial photo with alignment layout
• Existing and Proposed BNSF Rail Plan and Profile plan sheets
including drainage. (All phases during the construction plan
preparation)
• All Design Sheets (Plan -Plan Sheets and/or Plan -Profile sheets; ie.
cut sheets) as required by the client to prepare signing and striping
sheets with all necessary reference files attached for reference use.
(All phases during the construction plan preparation)
• Any property documents including right-of-way, deed sketch, field
notes, title research, etc. previously used on any projects
associated with the Alliance Airport Runway Extension. (All phases
during the construction plan preparation)
• All Right -of -Way and property map electronic files in MicroStation
format related to any project associated with the Alliance Runway
ANA No. 10-370.01 Alliance Runway Ext, — BNSF Reloc. --MOD 2
Confidential Page 2 1126/2011
A.N.A. Consultants, L.L,C.
Exhibit A — Scope of Services
Extension project. (All phases during the construction pla
preparation)
All field notes, field sketches, MicroStation CADD files, ASCII files,
electronic files related to the project benchmarks and project control
points. (All phases during the construction plan preparation)
All information needed to establish GPS equipment on appropriate
project coordinate base.
2.0 SCOPE
ENGINEER will support and perform activities related to ROW and land as outlined
below, per direction and guidance from the JACOB's Project Manager.
Task 1: Deed Research
Deed research and mapping includes review of property/right-of-way records
based on current intemet based Tarrant Appraisal District (TAD) and Denton
County Appraisal District (DCAD) information available at the start of the
project and available on -ground property information (i.e. iron rods, fences,
stakes, etc.) for the right-of-way acquisition of proposed BNSF mainline
relocation (not to exceed and additional 100 properties).
It does not include effort for chain of title research, parent track research,
additional research for easements not included in the TAD or DCAD data
base, right-of-way takings, easement vacations and abandonments, right-of-
way vacations, and street closures. Any requirement to provide the
aforementioned services will require additional compensation and will be
performed on a time and material basis per the man-hour rates provided in
Attachment B-1.
Task 2: Field Location of Property Corners
ANA will perform field investigation to locate and survey readily available
property corners for an additional 100 properties. ANA will not provide
services to reestablishing missing property corners unless need for the
preparation of the right-of-way acquisition documents.
Task 3: Right -of -Way Document Preparation
The JACOBS shall determine rights -of -way areas needed for construction of
the project. ANA is not responsible for determining right-of-way parcel size or
area. Right -of -Way areas that are altered after giving ANA notice to proceed
with right-of-way document preparation will require additional compensation
to modify said right-of-way documents.
ANA shall prepare documents to be used to obtain right-of-way required to
construct the improvements.
ANA shall submit the right-of-way acquisition documents to JACOBS PM for
real property acquisition. ANA will not perform any services related property
acquisition.
ANA No. 10-370.01 Alliance Runway Ext. — BNSF Reloc. —MOD 2
Confidential Page 3 1/26/2011
A.N.A. Consultants, L.L.C. Exhibit A — Scope of Services
• The documentation shall be provided in conformance with the checklists and
templates available on the City of Fort Worth's Buzzsaw site as of the NTP.
Task 4: Permanent Utility Easement Document Preparation
• The JACOBS shall determine utility easement areas needed for construction
of the project. ANA is not responsible for determining utility easement parcel
size or area. Easement areas that are altered after giving ANA notice to
proceed with easement document preparation will require additional
compensation to modify said easement documents.
• ANA shall prepare documents to be used to obtain permanent utility
easement required to construct the improvements.
• ANA shall submit the permanent utility easement documents to JACOBS PM
for real property acquisition. ANA will not perform any services related
property acquisition.
• The documentation shall be provided in conformance with the checklists and
templates available on the City of Fort Worth's Buzzsaw site as of the NTP.
Task 5: Temporary Construction Easement Document Preparation
• The JACOBS shall determine temporary construction easement areas
needed for construction of the project. ANA is not responsible for determining
utility easement parcel size or area. Easement areas that are altered after
giving ANA notice to proceed with easement document preparation will
require additional compensation to modify said easement documents.
• ANA shall prepare documents to be used to obtain temporary construction
easement required to construct the improvements.
• ANA shall submit the permanent utility easement documents to JACOBS PM
for real property acquisition. ANA will not perform any services related
property acquisition.
• The documentation shall be provided in conformance with the checklists and
templates available on the City of Fort Worth's Buzzsaw site as of the NTP.
3.0 MEETINGS
The ANA members will attend one kickoff meeting with the JACOBS to review
project requirements, design criteria, communication procedures, project
scheduling, personnel, and other pertinent matters that may impact the project.
ANA will provide one member to attend bi-monthly meetings associated with tine
Project, not to exceed an additional 10 meetings.
4.0 ADDITIONAL SERVICES
If authorized by JACOBS to perform any other services not included in the basic
services listed above, ANA may perform Optional services for additional
ANA No. 10-370.01 Alliance Runway Ext. -.. BNSF Reloc. —MOB
Confidential Page 4 1/26/201
A.N.A. Consultants, L.L.C. Exhibit A — Scope of Services
compensation on a reimbursable hourly basis or by amendment to current
contract.
Deliverables
❖ Right -Of -Way documents per City of Forth Worth Buzzsaw site as of the NTP
(not to exceed an additional 30 documents). Field monuments will be 5/8 inch
iron rod with cap.
❖ Permanent Utility Easement Documents per City of Fort Worth Buzzsaw site
as of the NTP (not to exceed 40 documents).
❖ Temporary Construction Easement Documents per City of Fort Worth
Buzzsaw site as of the NTP (not to exceed 10 documents).
Time Schedule
ANA shall commence its services when JACOBS provides a NTP for the
additional work per this contract modification as such the document preparation
is expected to be completed by March 25, 2011. Placement of field monuments
to mark new ROW will commence following approval by CITY after property
acquisition, which should take approximately 3 weeks to complete.
3. COMPENSATION
Lump Sum Fee
The ENGINEER will accomplish the Basic Services for a lump sum fee of
$199,000.00 , plus "Additional Expenses not included in Fee
Proposal" and required sales taxes on certain related services (if any).
The following "Additional Expenses not included in Fee Proposal" will be billed at
our cost plus 10%; for both Basic and Optional Services:
a) Platting, application, inspection, filing, review or other fees paid directly by
ANA on behalf of JACOBS at the prerogative of ANA so as to expedite
submittals, rather than waiting for JACOBS to provide check for these fees
prior to the time of submittal.
b) Any cost related to purchasing and maintaining additional insurance
requirements required by railroad in order to enter and work on railroad
property to complete the project.
c) Any cost related to permits in order to enter and work on railroad or city
property to complete the project.
d) Any costs related to preparing Temporary Right -of -Entry Documents for
surveying or construction purposes.
ANA No, 10-370.01 Alliance Runway Ext. -- BNSF Reloc. —MOD 2
Confidential Page 5 1/26/201 1
A.N.A. Consultants, L.L.C.
Exhibit A — Scope of Services
e) All courier delivery including but not limited to local couriers, FedEX, UPS,
and Express US postal Mail. (This will be billed at Direct Cost)
f) All Reproduction costs, excluding in house plotting and data processing.
g) Any costs related to installing field monuments using concrete and brass
disks.
Billing for Basic and/or Optional Services: will be made monthly on a "percent
complete" basis for fees listed as lump sums, or on an hourly reimbursable basis
for other Optional Additional Services. Payment of each invoice will be due within
15 days of receipt by JACOBS of invoice from ANA. Compensation and payment
thereof is not contingent upon the consummation of any closing, loan, real estate
transaction, zoning, plat or plans approval, or any other permit or condition. An
interest charge at the rate of 1.5% per month will be assessed to any amounts
outstanding more than 30 days from the invoice date. ANA may suspend its
services without liability for consequential or other damages if payment is not
received within 30 days of any billing.
ANA No. 10-370.01 Alliance Runway Ext. — BNSF Reloc. —MOD 2
Confidential Page 6 1/26/2011
A.N.A. Consultants, L.L.C.
TV VAU7
Attachment B-1
Hourly Rate Schedule
Work Title
Principal
Controller
Quality Control Manager
Project Manager / Project Engineer
Project Manager / Project Surveyor
Engineer Intern /Survey Intern
Engineering Designer / Survey Technician
2-Man Survey Crew
GPS Survey Crew
Specification Writer
Reproduction
Word Processor / Secretary
Exhibit B — Hourly Rates
Hourly Rate
$205.00
$165.00
$175.00
$150.00
$150.00
$115.00
$105.00
$135.00
$160.00
$60.00
$30.00
$38.00
Any extra work that is not in the Scope of Work, the Consultant fees will be based
on the above hourly rates schedule.
ANA No. 10-370.01 Alliance Runway Ext. — BNSF Reloc. —MOD 2
Confidential Page 7 1 /26/2011
A.N.A. Consultants, L.L.C.
Contract Provisions
PROVISIONS
AUTHORIZATION TO PROCEED
Signing this form shall be construed as authorization by CLIENT for A.N.A.
to proceed with the work, unless otherwise provided for in the
authorization.
LABOR COSTS
A.N.A:s Labor Cost shall be the amount of salaries paid A.N.A's
employees for the work performed on CLIENTS Project plus a stipulated
percentage of such salaries to cover all payroll -related taxes, payments,
premiums, and benefits.
DIRECT EXPENSES
A.N.A's Direct Expense shall be those costs incurred on or directly for the
CLIENT'S Project including but not limited to necessary transportation
costs including milage at A.N.A.'s current rate when its automobiles are
used, meals and lodging, laboratory test and analyses, computer services,
word processing services, telephone, printing and binding charges.
Reimbursement for these EXPENSES shall be on the basis of actual
charges when furnished by A.N.A. Consultants, L.L.C.
OUTSIDE SERVICES
When technical or professional services are furnished by an outside
source, when approved by the CLIENT, an additional amount of 10% shall
be added to the cost of these services for A. II administrative cost.
COST ESTIMATES
Any cost estimates provided by A.N.A. will be on a basis of experience and
judgement, but since it has no control over market conditions or bidding
procedures A.N.A. cannot warrant that bids or ultimate construction costs
will not vary from these cost estimates.
PROFESSIONAL STANDARDS
A.N.A, shalt perform its professional services pursuant to the standard of
care which would be applied by a reasonable and prudent registered
professional engineer in the State of Texas providing services under the
same or similar scope of service for the same or similar types of projects.
WARRANTY
A.N.A.'s services are professional services limited to the exercise of
judgment and the rendering of advice and opinions and, as such, A.N.A.
makes no warranty, express or implied.
TERMINATION
Either CLIENT or A.N.A. may terminate this authorization by giving 30
days written notice to the other party. In such event CLIENT shall forthwith
pay A.N.A. in full for all work previously authorized and performed prior to
effective date of termination. If at any time the CLIENT suspends the work
of the project for any reason, the contract shall be terminated after 90 days
of notice to suspend work. if no notice of termination is given, relationships
and obligations created by this Authorization shall be terminated upon
completion of ail applicable requirements of this Authorization.
ARBITRATION
All claims, disputes, and other matters in question arising out of, or
relating to, this Authorization or the breach thereof may be decided by
arbitration in accordance with the rules of the American Arbitration
Association then obtaining. Either CLIENT or A.N.A. may initiate a
request for such arbitration, but consent of the other party to such
procedure shall be mandatory. No arbitration arising out of, or relating to
this Authorization may include, by consolidation, joiner, or in any other
manner, any additional party not a party to this Authorization.
LEGAL EXPENSES
In the event legal action is brought by CLIENT or A.N.A. against the other
to enforce any of the obligations hereunder or arising out of any dispute
concerning the terms and conditions hereby created, the losing party
shall pay the prevailing party such reasonable amounts for fees, cost and
expenses as may be set by the court.
PAYMENT TO A.N.A., L.L.C.
Monthly invoices will be issued by A.N.A. for all work performed under the
terms of this agreement. Invoices are due and payable on receipt.
Interest at the rate of 1.5% per month will be charged on all past -due
amounts, unless not permitted by law, in which case, interest will be
charged at the highest amount permitted by law.
LIMITATION OF LIABILITY
A.N.A."s liability to the CLIENT for any cause or combination of causes is
in the aggregate, limited to an amount no greater than the fee earned
under this agreement.
ADDITIONAL SERVICES
Services in addition to those specified in Scope will be provided by A.N.A.
if authorized in writing by CLIENT. Additional services will be paid for by
CLIENT as indicated in attached Basis of Compensation or as negotiated.
SALES TAX
In accordance with the State Sales Tax Codes, certain surveying services
are taxable. Applicable sales tax is not included in the above proposed
fee. Sales tax at an applicable rate will be indicated on invoice
statements.
SURVEYING SERVICES
In accordance with the Professional Land Surveying Practices Act of
1989, the client is informed that any complaints about surveying services
may be forwarded to the Texas Board of Professional Land Surveying,
7701 North Lamar, Suite 400, Austin, Texas 78752, (512) 452-9427.
In case any one or more of the provisions contained in this
Agreement shall be held illegal, the enforceability of the remaining
provisions contained herein shall not be impaired thereby.
AUGUST 2005
ANA No. 10-370.01 Alliance RUnWay Ext. — BNSF Reloc. —MOD 2
Confidential Page 8 -1 /26/2011
TranSystems
i pv.C'1 ti'E I.",,?i
`�
4 "AVvl' 1,X r'610-1
December 14, 2010
Jeff Toner
Jacobs Engineering
777 Main Street
Fort Worth, Texas 76102
Re: WFXJ2000 Alliance Airport Runway Extension Project Phase Vlll
Contract Modification #3 — Addition of 1 parcel (John Day/Keller-Haslet)
Addition of 28 parcels (BNSF Mainline Relocation)
Addition of 2 parcels (Railroad Connector Track)
Addition of 34 parcels (BNSF Mainline Phase I Environmental)
Dear Mr. Toner:
I am requesting a modification to this contract for Right of Way acquisition and Phase I Environmental,. This
amendment is for additional work that was not part of original contract.
John Dav/Keller Haslet Road Segment - ROW
Acquisition —1 Parcel @ $4,450/Parcel.......................................................................................... $4,450
Appraisals —1 Parcel @ $3,000/Parcel.............................................. $3,000
Appraisal Review —1 Parcel @ $650/Parcel......... ............................. ......... ..._ $650
This request includes Parcels 5 & 7 BNSF being combined and Parcel 12 BNSF being added.
BNSF Mainline Relocation Segment - ROW
Acquisition -- 28 Parcels @ $4,250/Parcel.......................................................................................... $119,000
Appraisals —28 Parcels @ $2,500/Parcel ............................ $70,000
....................................................
Appraisal Review -- 28 Parcels @ $650/Parcel................................ $18,200
Railroad Connector Track
Acquisition — 2 Parcels @ $4,250/Parcel........................................................................................... $8,500
Appraisals —2 Parcels @ $2,5001Parcel................................. . . .............................. . ................ . $5,000
Appraisal Review-- 2 Parcels @ $650/Parcel.................................................................................... $1,300
This request is based on ROW Parcel Takings list received November 23, 2010.
*Note. Per parcel fee schedule and initial appraisal fees are different on the BNSF Mainline Segment than the John
DaylKeller Road Segments
Relocation (if applicable) $4,600 per parcel
Condemnation support Hourly (per rate schedule attached)
Appraisal revisions and updates (when requested) will be billed as follows:
Minor revisions. - —.................................................................................. $750
..........
Majorrevisions... .............. ........ ..................................... ... .................................. ... $1,450
AppraisalUpdates........................................................................................................... $750
The revision and update fees apply to John Day Road, Keller -Haslet Road and BNSF Mainline Relocation Segments.
Schedule:
Appraisals completed in two to three weeks; if field notes delivered in batch of six to eight.
Appraisal reviews completed in one to two weeks after appraisal reports delivered.
Acquisition completed in twenty weeks. This does not include time required to condemn, if necessary
Relocation (if applicable) will be completed in thirteen weeks.
Relocation was included in contract fee and schedule in the event it becomes necessary. Based on review of the
exhibits provided, it does not appear relocation will be required.
Scope:
The scope for these services remains the same as in the John Day and Keller -Haslet Road Projects Contract,
Phase I Environmental
Additional 34 Parcels Added to Scope of Work for Project Tasks
1.0 Understanding of Additional Task
It is TranSystems understanding the proposed task of a Phase I Environmental Site Assessment (ESA) for the linear
transportation project consisting of the Burlington Northern and Santa Fe Railway (BNSF) track realignment has an
additional 34 parcels to be added. The ongoing Phase I Environmental is to be expanded to include an additional 34
parcels for a total of 61 parcels.
2.0 Scope of Services
Phase I
An initial draft Phase I ESA will continue to be developed for the first set of parcels under study.
A second draft Phase I ESA will be developed subsequently, by including the additional 34 parcels.
BNSF Addendum
The Addendum to original Phase I ESA report to be developed within 60 days of property transfer to BNSF to update
visual and ASTM/AAI Database of original report will also be updated to include the additional 34 parcels.
3.0 Fees Scope of services
Based on the additional scope of services outlined above, discussions with Jacobs Engineering, Brad Penn and Dr.
Ernest Crosby, TranSystems offers the following additional fee proposai to add the 34 parcels for a total of 61
parcels.
A
ESA . PHASE I Cost Total
Phase I
Records Review (US and ST)
$0
Records Review (Local)
$2,960
Site Reconnaissance
$5,430
Interview Process
$5,000
Report
$3,540
Qa/QC
$370 $17,300
Phase I Addendum:
Site Reconnaissance $4,440
Report $3,620
Qa/QC $185 $8,245
Misc Supplies and Reproduction $350 $350
Records Search Acquisition (Banks)
ASTM/AAI Database Report
$0
ASTM/AAI Database Report update
$0
Historical Aerial Photos
$0
Historical Topos
$0
City Directory for Haslet, Tx
$0
Fire Insurance Maps
$0
Chain of Title/Environmental Lien
$10,753 $10,753
(34 Properties)
Total $36,648
If the chain of title search revels more properties are impacted or that some of the properties in history area split and
require additional property searches, then additional chain of title searches required will be billed per search.
Mileage will be billed at Current IRS rates.
4.0 Schedules
TranSystems will deliver the first draft Phase I ESA within 60 working days of the initial authorization to proceed and
will coordinate with the CFW for site visits.
TranSystems will deliver the second draft Phase I within 30 working days of the authorization to proceed and will
coordinate with the CFW for site visits.
TranSystems will deliver the Phase I Addendum after the second draft Phase I is finished and within 15 working clays
after receiving authorization from both CFW and BNSF to proceed with the Addendum, in order to facilitate the 60
day BNSF requirement for closing.
5.0 Deliverables
TranSystems will provide five copies of the first draft and second draft Phase I ESA report, including necessary
drawings and photographs.
TranSystems will provide five copies of the Addendum to the Phase I ESA report, including necessary drawings and
photographs:
Total Modification request
Contract total after this modification
Sincerely,
Assent Vice President
Senior Project Manager
$266,748.00
$621,973.00
ALLIANCE AIRPORT as"u�rvz",`""
RUNWAY EXTENTION PROJECT
i
PHASE VIII
I
AMENDMENT #3
DVa4M
jtad +-----F
_
—.._._.._.__._..
l.is. F•Dtwh Natdx a RsaY ,ida• Juy °W++ret Saptf PC _
t
^ -
it
!en r•D My _ !pf Mai ,Nn hl Iaq Up cie,
p, p
HOW Acquisition Main Line 8
253 dare
Yon 12nY80
Nw PRb'99
i Ganno;lar Track YD0 /3
pwpea�n Wnu7amen
a53 date
Fn;AT5t,9
ww y,'If:i3
Rcp;ew
I
�«,..r ...,, ... _.as2,
3Ji FfMdSwaY
i::pta
AAa, li/i1'3il
faL?:.,i
•.. ...•.............................................................................�,.....,.....,..
FYItl SVYtl/
�'<
.......... ... _..,..... artt
A,agaat•le�a�kosctmtraraEdamµ
b:x,
T/y t:i3,t
'dcn3,sa:tt
pefp•sa Lep•iC1NcP 4kan6ms
bla
Mx,,l2utf
714L,,.:f,
,tpp,r.s.
� E ,iyryu,/matHn+ew
to Gaya
i+x,pae�„
Fn<a?rt9
A�emsMi R®vw,a
~
�..—.t
Lre1' %Cs'�:Mfx vtitN
i1 dYl
T14)11[V,1
J$-t f
Z°;Y bpcar• Y•,W
Sa daYs
Fe;yit(,t
Fir iPJtt
lidf•giref
..M......� ••,
j L w NreyDik�c+u 8+ekein
i4 wave
afm aiftiff
fn �„'kti
.'>cer+�w MpclnlioroiAeaepB
I-.1Q..••R i.WWIh1WY ja +:
i
tn;Kam
Wlb 5f14„5-
i st P,mye„Y51•a•g
+a;; •.lam
Wd Slt,ii,
wad 92a.11
Ciic
€ µ Sb4iy
_paq•ny
.__.____- .................... .. ......................... ,......... ...........,.........................
r"YVl$ICti,i'ni%nalKYtiiA+:,DLeu,[>,aaa ,{li f::u;;w,:a:>m.: ,�riY fivlCMt705'MDO r7d.WSt➢^c>
M&C - Council Agenda Page 1 of 2
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 4/12/2011
DATE: Tuesday, April 12, 2011 REFERENCE NO.: **C-24855
LOG NAME: 55AFW RWY EXT PHASE VIII AMD 3
SUBJECT:
Authorize Amendment No. 3 to City Secretary Contract No. 39252 with Jacobs Engineering Group Inc., for
Phase Vlll of the Program Management Services for the Fort Worth Alliance Airport Runway Extension in
the Amount of $546,621.29 for Professional Services for the Acquisition of Land Necessary for the
Burlington Northern Santa Fe Railroad Connector Track and Relocation of their Main Line (COUNCIL
DISTRICT 2)
RECOMMENDATION:
It is recommended that the City Council Council authorize Amendment No. 3 to City Secretary Contract
No. 39252 with Jacobs Engineering Group, Inc., for Phase VIII of the program management services for
the Fort Worth Alliance Airport Runway Extension in the amount of $546,621.29 for professional services
for the acquisition of land necessary for the Burlington Northern Santa Fe Railroad connector track and
relocation of their main line.
DISCUSSION:
On March 27, 2001, (M&C C-18528) the City Council approved an agreement with Carter and Burgess,
Inc. (now Jacobs Engineering Group Inc.) for Phase I program management services for the Runway
Extension Project at Fort Worth Alliance Airport. Subsequently, similar services have been performed in
multiple phases under individual agreements as funds became available.
On December 8, 2009, (M&C C-23944) the City Council approved a contract in the amount of
$1,323,029.89 with Jacobs Engineering Group Inc., for phase VIII of the program management services
for the runway extension project which included program management Design Earthwork Package No. 3,
Design John Day Road, Design Keller Haslet Road and ALP Update at Fort Worth Alliance Airport.
On May 18, 2010, (M&C C-24187), the City Council approved a contract with Jacobs Engineering Group
Inc., for Amendment 1 in the amount of $471,179.70 in order to add additional program management and
land acquisition services associated with the Burlington Northern Santa Fe Railroad (BNSF) main line and
connector track for additional work not included in the original contract .
On June 23, 2010, (no M&C required), Amendment 2 in the amount of $49,708.63, was approved to
increase funding to this project for Phase I Environmental Site Assessment associated with the relocation
of the BNSF main line.
This Amendment No. 3 in the amount of $546,621.29 has been proposed to accomplish professional
services for the acquisition of land necessary for the Burlington Northern Santa Fe Railroad connector
track and relocation of their main line in conjunction with the Fort Worth Alliance Airport Runway Extension
Project. The total fee paid by the City for all work and services shall not exceed the sum of $2,390,539.51.
http://apps.cfwnet.org/ecouncil/printme.asp?id=l 5067&print=true&DocType=Print 4/28/2011
M&C - Council Agenda
Page 2 of 2
FAA funds from Runway Extension Grant 3-48-0296-34-2008 will be used for this project. Existing land
credits that remain from the original land donation for Alliance Airport will be used for the City's five
percent in -kind match.
M/WBE — Jacobs Engineering Group Inc. f/k/a Carter and Burgess, is in compliance with the City's DBE
Program by committing to an additional 36 percent DBE participation on this Amendment No. 3. The City's
goal on this amendment is 36 percent.
This project is located in COUNCIL DISTRICT 2, Mapsco 7P.
FISCAL INFORMATION / CERTIFICATION:
The Financial Management Services Director certifies that funds are available in the current capital
budget, as appropriated, of the Airport Grants Fund.
FUND CENTERS:
TO Fund/Account/Centers FROM Fund/Account/Centers
GR14 539120 055218265300
CERTIFICATIONS:
Submitted for Citv Manager's Office bv:
Originating Department Head:
Fernando Costa (6122)
Kent Penney (5403)
Ruseena Johnson (5407)
Additional Information Contact: Patrick Buckley (2443)
ATTACHMENTS
1. 960 P8 A3 MWBE Comp.pdf (CFW Internal)
2. Alliance Proiect Overall MAYOR AND COUNCIL COMMUNICATION MAP 20110406.pdf (Public)
3. GR14 539120 055218265300 as of 3-25-11.odf (CFW Internal)
$546,621.29
http://apps.cfwnet.org/ecouncil/printmc.asp?id=15067&print=true&DocType=Print 4/28/2011