HomeMy WebLinkAboutContract 39252-A5f
AMENDMENT NUMBER 5
STATE OF TEXAS 8 CITY SECRETARY CONTRACT NO.�Q
COUNTY OF TARRANT 8
WHEREAS, the City of Fort Worth (City) and Jacobs Engineering Group, Inc. (Engineer) made and
entered into City Secretary Contract No. 39252, (the Contract) which was authorized by the City Council by
M&C C-23735 on the 18th day of August 2010; and
WHEREAS, the Contract involves engineering services for the following project:
Alliance Runway Extension Phase 8
WHEREAS, it has become necessary to execute Amendment No. 5 to said Contract to include
an increased scope of work and revised maximum fee for additional program management
services, additional land acquisition services for BNSF Main Line and Connector Track and for
construction phase services for John Day and Keller Haslet Roads;
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their duly authorized
representatives, enter into the following agreement, which amends the Contract:
Article I of the Contract is amended to include the additional engineering services specified in
the proposal letter dated June 17, 2011, a copy of which is attached hereto and incorporated
herein. The cost to City for the additional services to be performed by ENGINEER total
$544,787.59.
2.
Article II of the Contract is amended to provide for an increase in the fee to be paid to
ENGINEER for all work and services performed under the Contract, as amended, so that the total
fee paid by the City for all work and services shall not exceed the sum of $3,304,871.92.
OFFICIAL RECORD
Page -1- CITY SECRETARY
FT. WORTH, TX
08-05-11 A10:38 IN
3.
All other provisions of the Contract, which are not expressly amended herein, shall remain in full
force and effect.
EXECUTED on this the day of k�)
APPROVAL RECOMMENDED:
kenneth L. Penney, Jr., A.A.E.
Aviation Director
, 2011 in Fort Worth, Tarrant County, Texas.
Jacobs Engine ' g rou , I ATTEST:
Engineer
By:
L---
Name: -kVirt e ISO n Authorization:
Title:
Date:
APPROVED AS TO FORM AND LEGALITY:
J�g-$lack P4 r« ,rq
Assistant City Attorney
— C- �nAs-
Contract AUthorizatiOR
I
Pot@
APPROVED:
Fernando Costa
Assistant City Manager
AttooW by:
M Hendrix,`Ci Sact+etf
�'h' City
Page -2-
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
I
June 17, 2011
Mr. Tim Ward
President
Alliance Air/Aviation Services
2221 Alliance Blvd, Suite 100
Fort Worth, TX 76177
Re: Alliance Airport Runway Extension Project
Phase VIII — Contract Amendment No. 5
Dear Mr. Ward:
The original Phase VIII contract included services for program management, design and land
acquisition. Construction management and construction support services for Earthwork Package
3 and John Day and Keller Haslet Roads were not included in the original scope of work because
the scope of work and fee for these services could not be accurately determined at that time. The
scope and cost of these services are dependent upon the duration of the construction contract.
This duration of the construction contract is usually determined during the end of design process.
A separate contract could have been issued for Earthwork Package 3 construction management
and construction support services instead of including them in Contract Amendment No. 3 and a
separate contract could have been issued for the John Day and Keller Haslet Road construction
support services instead of including them in Contract Amendment No. 5, however, the overall
cost would have been the same.
Therefore, I am requesting an amendment to the Alliance Airport Runway Extension Project -
Phase VIII contract for additional program management services, additional land acquisition
services for the BNSF Main Line and Connector Track and for construction phase services for
John Day and Keller Haslet Roads. A brief justification of these additional services is described
in the following paragraphs. A detailed scope of work and fee proposal is attached for your
consideration.
Program management services are a function of the duration of the contract. This amendment
will revise the completion date for land acquisition services from August 4, 2011 to December 9,
2011. This results in approximately 18 additional weeks of program management activities.
Additional land acquisition services are necessary to account for the changes to the BNSF right-
of-way and utility easements that have occurred since November 2010. Since the original
submittal of the BNSF Main Line and Connector Track alignment in November, there have been
five (5) major changes to the right of way and easements. Each major change has affected
approximately 60 tracts of land, resulting in the addition of parcels and easements and the re-
work of previously identified parcels and easements. Also included with the additional land
acquisition is the cost to prepare and submit to BNSF the due diligence packages for right of way
and easements associated the Main Line and Connector track, including the cost of ALTA
surveys. As mentioned above, these changes add approximately 18 weeks to the schedule.
We have successfully bid the John Day Road and Keller Haslet Road construction projects.
Construction is anticipated to begin in August of this year and will required engineering services
in support of the construction activities. These services will occur over the length of the
construction contract which is 300 calendar days.
There have also been some questions as to the number and timing of the last few contract
amendments and whether or not some of these contract amendments could have been
combined. Contract Amendment No. 3, for additional land acquisition services, was submitted to
the City of Fort Worth on January 26, 2011, approved by Council April 12, 2011 and fully
executed on May 5, 2011. During this time, the Jacobs' Team continued to advance the work
even though the contract amendment had not been approved. We incurred additional cost and
could not invoice for this work until the amendment was executed which took a total of 14 weeks.
Contract Amendment No. 4, for Earthwork Package 3 construction management services, was
submitted to the City of Fort Worth on April 1, 2011 and was approved at the May 17, 2011 City
Council Meeting. Combining Contract Amendment No. 3 and No. 4 would have further delayed
the approval of Contract Amendment No. 3.
Combining Contract Amendment No. 4 and Contract Amendment No. 5 is not practical due to
schedule issues related to the Earthwork Package 3 construction contact. The City Council
awarded the construction contract for Earthwork Package 3 on April 12, 2011. Contract
Amendment No. 4 for Earthwork Package 3 construction management services was approved at
the May 17, 2011 City Council Meeting. We needed Contract Amendment No. 4 approved to
issue the notice to proceed to the construction contractor. Combining Contract Amendments No.
4 and No. 5 would delay the start of the Earthwork Package 3 construction contract to late July.
A summary of the work items for Contract Amendment No. 5 is shown below. The detailed
scopes of work, fee proposals and schedule are attached for your information.
Jacobs — Program Management
Jacobs — Construction Support Services
TranSystems — Land Acquisition Services
ANA — Surveying and Legal Descriptions
Gorrondona — Surveying and Legal Descriptions
Total cost increase for Contract Amendment No. 5
DBE Participation for Contract Amendment No. 5
Original Contract Amount
Previous Amendments
Contract Amendment No. 5
New Contract Amount
$232,000.00 42.59%
DBE Participation Amount for New Contract Amount
DBE Participation % for New Contract Amount
$63,177.54
$80,121.05
$122,100.00
$232,000.00
$47,389.00
$544,787.59
$1,323,029.89
$1,437,054.44
$544.787.59
$3,304,871.92
$1,056,333.67
31.96%
Thank you for your attention to this request. Should you have any questions or comments
regarding this matter please feel free to contact me at 817-735-7004 or by email at
Jeff. Toner(a).Jacobs.corn .
Sincerely
Xd J. Toner, P.E.
Program Manager
cc: Patrick Buckley — City of Fort Worth
Ruseena Johnson — City of Fort Worth
Aya Ealy — City of Fort Worth
JACOBS'
Alliance Airport Runway Extension Project: - Phase Vill
Contract Amendment No. 5
.......................
14-Jun:,�
Task List and Summary of Fees
Program Management
'Construction Phass, Sorvices -John Day 8 Keller Haslet
'Land Acquistion
Land AcqqIs#qrj& Phase 1 Environmental Services
, _
Field Surveys,-L-9e, a1 Descriptions and Exhibits
_
Field Surveys, Legal Descriptions and Exhibits
Total Foe
DBE Partfiqlpatin
.. . . . . .....
Consultant Task Amount I_DBE Amount
Jacobs 63.177.54 f
Jacobs- $ 80,121.05
TranSyStems
$ 122,100.00
&N.A S 232.000.00 3 232,000.00
1
Gomxidona Z—47`389.00
5 ",787.59 L
42.59%
JACOBS
June 14, 2011
Alliance Airport Runway Extension Project - Phase Vill
Contract Amendment No. 5
Program Management
Scope of Work
The schedule for the land acquisition will extend beyond the scheduled completion
date, revised in Contract Amendment No. 3, due to changes for the BNSF Main
Line and Connector Track right-of-way and easements. Jacobs will provide
additional program management services during this time, estimated to be an
additional 18 weeks. During this time Jacobs will:
• Conduct bi-weekly project coordination meetings
• Conduct additional stake holder meetings
• Prepare and distribute meeting minutes
• Monitor and adjust the program schedule
• Monitor and adjust the program budget
• Maintain the document control system
• Administer the prime and subcontract agreements
• Provide technical and graphic support for the program
• Provide technical reviews of the land acquisition documents
• Coordinate with BNSF, FAA, Alliance Airport and City of Fort Worth
Jacobs will also provide program management services associated with tasks
identified in City of Fort Worth / Burlington Northern Santa Fe Relocation
Agreement. The work identified below is for reporting requirements for the BNSF
Main Line Relocation and Connector Track. During this time Jacobs will:
• Prepare monthly status reports
• Review BNSF monthly status reports
• Review BNSF monthly pay request
Jacobs Fee Proposal
Alliance Airport Runway Extension Project - Phase Vill
Contract Amendment No. 5 144un-11
Program Management Services
Labor Hour Estimate
Program Deputy
Senior Project
CADD Technical Admin
Manager Program Mgr
Engineer Controls Mgr.
Tech Assistant Assistant
ProgQram Management
Conduct Bi-Weekly Progress Meetings
18
18
18
[Conduct Stakeholder Coordination Meetings
18
�Preyy�: & Distribute Meeting Minutes
I 9 l
18
IMalntain Project Schedules
1 91 I
41
1 Update Project Budgets
I 91
4
I
Maintain Document Control System
I 1
18
Administer Contracts & Sub -Contracts
f 91
4
18
Technical & Graphic Suppprt
I
20 20
%chnicel Review - RO uisition
72
1
Coordinate with BNSF
18
Coordinate with FAA. Alliance. Ft. Worth
18
COFW / BNSF Agreement
I (
I
Prep Monthly Status Report
I 91
I
8
Review BNSF Monthly Status Report
I 9
I
8
(Review BNSF Monthly Pay Request
+j
I 9
f
8I
j
I Total Hours
I i
I I
I 1351 01
I
901 12
I
20 1161 01
Fee Proposal
Program Manager
Deputy Program Manager
Senior Engineer
Project Controls Manager
CADD Technician
Technical Assistant
Administrative Assistant
JEG Labor Cost
Expenses
Mileage
Courier/Express Mail
Printing & Plotting
Reproduction
Total Expenses
Hourly
Rate
$
112.00
$
63.00
$
55.00
$
30.00
$
31.00
$
24,00
$
19.00
Salary Cost
Overhead Rate Q 126.85%
Sub - Total
Profit @ 15%
Hours Labor
Cost
135 $ 15.120.00
0 $ -
90 $ 4,950.00
12 $ 360.00
20 $ 620.00
116 $ 2,784.00
0 $ -
$ 23,834.00
$ 30.233.43
$ 54,067.43
$ 8,110.11
$ 62.177.54
$ 250.00
$ 50.00
$ 200.00
$ 500.00
$ 1,000.00
Total Program Management Cost $ 63,177.54
A •,,
.,,- ,%iin Streo
F or= i'r :E t:t. 'TX h l try 11.
June 14, 2011
Alliance Airport Runway Extension Project - Phase VIII
Contract Amendment No. 5
Construction Phase Services — John Day & Keller Haslet Roads
Scope of Work
The scope of work for construction phase services is summarized below. The labor hour
estimate for these services is based upon a three hundred (300) calendar day
construction contract.
• Attend the Pre — Construction Meeting
• Attend the Public Meeting
• Conduct a Monthly Site Visit and Prepare Observation Report (estimated at 12
meetings)
• Respond to Requests for Information
• Review Shop Drawings and Submittals
• Participate in the Final Walk Through and Prepare Punch List
• Prepare Record Drawings
• Project Administration Activities
Jacobs Fee Proposal
Alliance Airport Runway Extension Project - Phase VIII
Contract Amendment No. 5
14,1un-11
Construction Phase Services -John Day & Keller
Haslet Roads
Labor Hour Estimate
Program
Project Project Project
CADD Technical Admin
Manager
Manager Engineer Controls Mgr.
Tech Assistant Assistant
Construction Phase Services
i
IAttend Pre-ConslructionConference
4 4
lAttend Public Meeting 1
4 4
Project Site Visits & Report Preparation (12)
96
96
36
Review Submittals
16
40
Respond to Requests fqr Information
16
80
Pre,Qpre Change Order Documents
24 80
80
Final Walk Through & Punch List Preparation
8 8
6
Prepare Record brawings 1
8 24
60
Project Administration
20
10
1
I Total Hours 1
01
i
1961 3361 101
I
1401 0 42
Fee Proposal
Hourly
Hours Labor
Rate
Cost
Program Manager
$ 112.00
0 $
Project Manager
$ 55.00
196 S 10,780.00
Project Engineer
$ 40A0
336 $ 13,440.00
Project Controls Manager
$ 30.00
10 $ 300.00
CADD Technician
$ 31.00
140 S 4,340.00
Technical Assistant
$ 24.00
0 $ -
Administrative Assistant
$ 19.00
42 $ 798.00
Salary Cost
$ 29,658.00
Overhead Rate Q
126.85%
$ 37,621.17
Sub - Total
$ 67,279.17
Profit
15%
$ 10,091.83
JEG Labor Cost
$ 77,371.05
Expenses
Mileage
$ 500.00
Courier/Express Mail
$ 50.00
Printing & Plotting
$ 200.00
Record Drawing (Mylars)
S 2,000.00
Total Expenses
$ 2,760.00
Total Program Management Cost
$ 80,121.05
TranSystems
500 West Seventh Street
Suite 1100
Fort Worth, TX 76102
Tel 817.339-8950
Fax 817-336-2247
www.transystems.com
April 12, 2011
Jeff Toner
Jacobs Engineering
777 Main Street
Fort Worth, Texas 76102
Re: WFXJ2000 Alliance Airport Runway Extension Project Phase Vill
Contract Modification Request #4
Dear Mr. Toner:
Please let this serve as request for a modification to contract for Right of Way acquisition and Phase I Environmental.
This amendment is for work outside the scope of the original contract. This work will be considered 'Additional
Services".
Acquisition
Acquisition on two (2) additional parcels on BNSF Mainline Relocation .......... $4,250 each = $8,500
Significant and multiple changes in field notes and non -Alta surveys that requires extensive coordinating with
appraisers, title company and surveyors, as well as numerous discussions with attorney.
Seventy-seven (77) parcels..................................................................... $525 per parcel = $40,425
Corrections or changes to field notes
Any occurrence after date of this request (4/12/11)................................................. $400 per parcel
Due Diligence Package to BNSF for Mainline Relocation and Connector Track
This scope of work was not included in original contract.
Sixty-six (66) parcels.............................................................................. $750 per parcel = $49,500
Appraisal
Appraisals on two (2) additional parcels......................................................... $2,500 each = $5,000
Updates due to minor revisions in field notes (minor changes in area)............ $500 each as necessary
Updates due to major revisions in field notes (i.e., change in damages, highest and best use
or take now affects improvements) .................. .................. .............. $650 as necessary
On Hold Fee for reports assigned (as requested); then put on hold for six (6) months. Work done prior to parcels
being put on hold will now have to be updated and revised.
Fee is for work done to date and will be in addition to normal appraisal fee.
Parcels included in this request to date are P1, P3A, 3B, 4 and 12
Five (5) parcels............................................................................................... $1,475 each = $7,375
F11111"..
Appraisal Review
Reviews on two (2) additional parcels.......................................................................... $650 = $1,300
Updates — minor revisions..........................................................................$450 each as necessary
Updates — major revisions..........................................................................$600 each as necessary
"As necessary" fees will be in addition on a case by case scenario; unknown at this time.
Environmental
Alterations, start -stops and delays have resulted in changed focus, priorities, schedules to be re -worked, delays and
project flow alterations. This resulted in additional site visits, rescheduling of site interview appointments; as well as
alterations to partially completed reports. This has caused inefficiency by switching study from one parcel or group to
a different parcel or group mid-stream.......................................................... ................ $10,000
Total known contract modification request at this time ................................................. $122,100
Sincerely,
cf�
Brad Penn
Assistant Vice President
Senior Project Manager
4
5.
EtlG�N�ERS+
SURVEYQR$�
P.n NNER$'„
1331 Airport Freeway
$uite 410
Euless, Texas 76040
(817)335-9900
Fax (8 17) 335-9955
AUTHORIZATION FOR PROFESSIONAL SERVICES
PROJECT NAME: Alliance Runway Extension — BNSF Mainline Relocation
PROJECT No.: 10-0370.03 MOD #3
CLIENT: Jeff Toner, P.E.
Jacobs Engineering
ADDRESS: 777 Main St.
Fort Worth, Texas76102
SCOPE OF SERVICES:
See attached Exhibit 'A' and layouts for detail Scope of Services.
COMPENSATION:
PROFESSIONAL SERVICES
Prepare property acquisition Documents in ALTA Survey Format and
Requirements (60 ROW, 40 Utility Easements, and 10 Temporary Construction
$ 110,000
Easement documents per the original contract and contract MOD No. 2)
Additional Utility Coordination (John Day Road and Keller -Haslet Road)
additional compensation to coordinate the utilities temporary and permanent for
$ 22,000
Keller -Haslet Road and John Day Road.
Additional Permanent Utility Easement Document per Revised BNSF Mainline
Plans dated May 11, 2011per ALTA Survey requirements (not to exceed and
$ 79,000
additional 30 documents)
Additional Temporary Construction Easement Document per Revised BNSF
Mainline Plans dated May 11, 2011per ALTA Survey requirements (not to
$ 13,00
exceed and additional 10 documents)
Boundary Survey for Briscoe Clark Company per City of Fort Worth
$ 8,000
Requirements
Total
$232,000.00
TOTAL ENGINEERING COMPENSATION: $232,000.00 Lump Sum
Additional services not covered in this authorization and its attachments will be provided
on an hourly basis per Exhibit'B'.
Services covered by this authorization shall be performed in accordance with
PROVISIONS stated on the attached form.
Approved for CLIENT Accepted for A N.A. Consultants, L.L.C. By: By:f%.
�AWa'ad, P.E �—
Title: Title: Vice President
Date: Date: 06/12/2011
CLIENT SATISFACTION IS OUR BUSINESS
ANA Scope - Phase 8 - MOD 3-Original Job No 090590.doc
A.N.A. Consultants, L.L.C.
Exhibit A — Scope of Services
A.N.A. Consultants, L.L.C. (herein referred to as ANA) is prepared to provide specific
civil engineering services for the Alliance Runwav Extension — BNSF Mainline
Relocation -Mod No. 3 (herein refer to as PROJECT) for Jacobs
Enqineerinq (herein called JACOBS).
1.0 INTRODUCTION
The purpose of this scope of work (SOW) is to provide engineering services, technical
manpower, and deliverables for the preparation of Right -of -Way Documents to be
implemented for the PROJECT.
1.1 Project Summary
This modification is to address increase scope of work from the original
contract and contract MOD No. 2 for the following items:
• Additional preparation requirements needed for 2005 ALTA
survey requirements for the 60 ROW, 40 Permanent Utility
Easements, and 10 Temporary Easements per the original
contract and contract MOD No. 2.
• Additional time required for utility coordination services on John
Day Road and Keller Haslet Road.
• Preparation of an additional 30 Permanent Utility Easements
per 2005 ALTA survey requirements.
■ Boundary Survey for Briscoe Clark Company property.
1.2 Information to be Provided by JACOBS
Upon receiving a notice to proceed (NTP), JACOBS shall furnish the
necessary hardcopy and electronic copy of the PROJECT CADD files
necessary for or incidental to the performance of work set forth herein for
the completion of the Right -of -Way Parcel Documents. These files
include but are not limited to the following:
• Project Border Sheet
• Project CADD Standards
• Overall alignment and aerial photo with alignment layout
• Existing and Proposed BNSF Rail Plan and Profile plan sheets
including drainage. (All phases during the construction plan
preparation)
• All Design Sheets (Plan -Plan Sheets and/or Plan -Profile sheets; ie.
cut sheets) as required by the client to prepare signing and striping
sheets with all necessary reference files attached for reference use.
(All phases during the construction plan preparation)
• Any property documents including right-of-way, deed sketch, field
notes, title research, etc. previously used on any projects
associated with the Alliance Airport Runway Extension. (Ali phases
during the construction plan preparation)
ANA No. 10-370.03 Alliance Runway Ext. — BNSF Reloc. —MOD 3
Confidential Page 2 5/12/2011
A.N.A. Consultants, L.L.C.
Exhibit A — Scope of Services
All Right -of -Way and property map electronic files in MicroStation
format related to any project associated with the Alliance Runway
Extension project. (All phases during the construction plan
preparation)
All field notes, field sketches, MicroStation CADD files, ASCII files,
electronic files related to the project benchmarks and project control
points. (All phases during the construction plan preparation)
All information needed to establish GPS equipment on appropriate
project coordinate base.
2.0 SCOPE
ENGINEER will support and perform activities related to ROW and land as outlined
below, per direction and guidance from the JACOB's Project Manager.
Task 1: ALTA Survey (2005) Right -of -Way Document Preparation
• The JACOBS shall determine rights -of -way areas needed for construction of
the project. ANA is not responsible for determining right-of-way parcel size or
area. Right -of -Way areas that are altered after giving ANA notice to proceed
with right-of-way document preparation will require additional compensation
to modify said right-of-way documents.
• ANA shall prepare documents to be used to obtain right-of-way required to
construct the improvements.
• ANA shall submit the right-of-way acquisition documents to JACOBS PM for
real property acquisition. ANA will not perform any services related properly
acquisition.
• The documentation shall be provided in conformance with the checklists and
templates available per Table A of the 2005 ALTA Survey Requirements, with
the exception of items 1, 5, 6, 7(b), 7(c), 10, 11(a), 12, 14, 15, 16, 17, 18, and
19.
• The documentation on the ALTA survey for the topographic survey and
identifying existing utilities on properties will be provided by Multatech's
survey and engineering data used to prepare engineering design for the
BNSF Mainline track.
Task 2: ALTA Survey (2005) Permanent Utility Easement Document Preparation
• The JACOBS shall determine utility easement areas needed for construction
of the project. ANA is not responsible for determining utility easement parcel
size or area. Easement areas that are altered after giving ANA notice to
proceed with easement document preparation will require additional
compensation to modify said easement documents.
ANA No. 10-370.03 Alliance Runway Ext. — BNSF Reloc. —MOD 3
Confidential Page 3 5/12/2011
A.N.A. Consultants, L.L.C.
Exhibit A -- Scope of Services
ANA shall prepare documents to be used to obtain permanent utility
easement required to construct the improvements.
• ANA shall submit the permanent utility easement documents to JACOBS PM
for real property acquisition. ANA will not perform any services related
property acquisition.
• The documentation shall be provided in conformance with the checklists and
templates available per Table A of the 2005 ALTA Survey Requirements, with
the exception of items 1, 5, 6, 7(b), 7(c), 10, 11(a), 12, 14, 15, 16, 17, 18, and
19.
• The documentation on the ALTA survey for the topographic survey and
identifying existing utilities on properties will be provided by Multatech's
survey and engineering data used to prepare engineering design for the
BNSF Mainline track.
Task 3: ALTA Survey (2005) Temporary Construction Easement Document
Preparation
• The JACOBS shall determine temporary construction easement areas
needed for construction of the project. ANA is not responsible for determining
utility easement parcel size or area. Easement areas that are altered after
giving ANA notice to proceed with easement document preparation will
require additional compensation to modify said easement documents.
• ANA shall prepare documents to be used to obtain temporary construction
easement required to construct the improvements.
• ANA shall submit the permanent utility easement documents to JACOBS PM
for real property acquisition. ANA will not perform any services related
property acquisition.
• The documentation shall be provided in conformance with the checklists and
templates available per Table A of the 2005 ALTA Survey Requirements, with
the exception of items 1, 5, 6, 7(b), 7(c), 10, 11(a), 12, 14, 15, 16, 17, 18, and
19.
• The documentation on the ALTA survey for the topographic survey and
identifying existing utilities on properties will be provided by Multatech's
survey and engineering data used to prepare engineering design for the
BNSF Mainline track.
3.0 ADDITIONAL SERVICES
If authorized by JACOBS to perform any other services not included in the basic
services listed above, ANA may perform Optional services for additional
compensation on a reimbursable hourly basis or by amendment to current
contract. Providing Utility Coordination for BNSF Mainline relocation, Subsurface
Utility Engineering, and Topographic Survey services are not included in the
ANA No. 10-370.03 Alliance Runway Ext. — BNSF Reloc. —MOD 3
Confidential Page 4 5/12/2011
A.N.A. Consultants, L.L.C.
Exhibit A — Scope of Services
scope of work and will require additional compensation if required by the City of
Fort Worth or BNSF.
Deliverables
❖ Convert original contract and contract Mod. 1 Right -Of -Way and Easement
documents to meet 2005 ALTA Survey Requirements listed above (60 ROW,
40 Utility Easements, and 10 Temporary Construction Easement documents
per the original contract and contract MOD No. 2). Field monuments for Right
of Way Acquisition ONLY will be 5/8 inch iron rod with cap.
❖ Prepare additional Permanent Utility Easement Documents per 2005 ALTA
Survey requirements listed above (not to exceed 30 documents).
❖ Temporary Construction Easement Documents per 2005 ALTA Survey
requirements listed above (not to exceed 10 documents).
❖ Boundary Survey for Briscoe Clark Company property.
3. COMPENSATION
Lump Sum Fee
The ENGINEER will accomplish the Basic Services for a lump sum fee of
$232,000.00 , plus "Additional: Expenses not included in Fee
Proposal' and required sales taxes on certain related services (if any).
The following "Additional Expenses not included in Fee Proposal' will be billed at
our cost plus 10%; for both Basic and Optional Services:
a) Platting, application, inspection, filing, review or other fees paid directly by
ANA on behalf of JACOBS at the prerogative of ANA so as to expedite
submittals, rather than waiting for JACOBS to provide check for these fees
prior to the time of submittal.
b) Any cost related to purchasing and maintaining additional insurance
requirements required by railroad in order to enter and work on railroad
property to complete the project.
c) Any cost related to permits in order to enter and work on railroad or city
property to complete the project.
d) Any costs related to preparing Temporary Right -of -Entry Documents for
surveying or construction purposes.
e) All courier delivery including but not limited to local couriers, FedEX, UPS,
and Express US postal Mail. (This will be billed at Direct Cost)
f) All Reproduction costs, excluding in house plotting and data processing
ANA No. 10-370.03 Alliance Runway Ext. — BNSF Reioc. —MOD 3
Confidential Page 5 5/12/2011
A.N.A. Consultants, L.L.C. Exhibit A — Scope of Services
g) Any costs related to installing field monuments using concrete and brass
disks.
h) Any cost related to Subsurface Utility Engineering.
i) Any cost related to Topographic Surveying.
Billing for Basic and/or Optional Services: will be made monthly on a "percent
complete" basis for fees listed as lump sums, or on an hourly reimbursable basis
for other Optional Additional Services. Payment of each invoice will be due within
15 days of receipt by JACOBS of invoice from ANA. Compensation and payment
thereof is not contingent upon the consummation of any closing, loan, real estate
transaction, zoning, plat or plans approval, or any other permit or condition. An
interest charge at the rate of 1.5% per month will be assessed to any amounts
outstanding more than 30 days from the invoice date. ANA may suspend its
services without liability for consequential or other damages if payment is not
received within 30 days of any billing.
ANA No. 10-370.03 Alliance Runway Ext. — BNSF Reloc. —MOD 3
Confidential Page 6 5/12/2011
A.N.A. Consultants, L.L.C.
Attachment B-1
Hourly Rate Schedule
Work Title
Principal
Controller
Quality Control Manager
Project Manager / Project Engineer
f Project Manager / Project Surveyor
En ineer Intern / Survey Intern
Engineering Desipnor / Survey Teghnician
24Man Survey Crew
GPS Survey Crew
Specification Writer
Reproduction
f Word Processor / Secretary
Exhibit B — Hourly Rates
Hourly Rate
$205.00
$165.00
$175.00
$150.00
$150.00
$115.00
$105.00
$135.00
$160.00
$60.00
$30.00
$38.00
Any extra work that is not in the Scope of Work, the Consultant fees will be based
on the above hourly rates schedule.
ANA No. 10-370.03 Alliance Runway Ext. — BNSF Reloc. —MOD 3
Confidential Page 7 5/12/2011
A.N.A. Consultants, L.L.C.
Contract Provisions
PROVISIONS
AUTHORIZATION TO PROCEED
Signing this form shall be construed as authorization by CLIENT for A.N.A.
to proceed with the work, unless otherwise provided for in the
authorization.
LABOR COSTS
A.N.A.'s Labor Cost shall be the amount of salaries paid A.N.A.'s
employees for the work performed on CLIENTS Project plus a stipulated
percentage of such salaries to cover all payroll -related taxes, payments,
premiums, and benefits.
DIRECT EXPENSES
A.N.A's Direct Expense shall be those costs incurred on or directly for the
CLIENT'S Project including but not limited to necessary transportation
costs including milage at A.N.A.'s current rate when its automobiles are
used, meals and lodging, laboratory test and analyses, computer services,
word processing services, telephone, printing and binding charges.
Reimbursement for these EXPENSES shall be on the basis of actual
charges when furnished by A.N.A. Consultants, L.L.C.
OUTSIDE SERVICES
When technical or professional services are fumished by an outside
source, when approved by the CLIENT, an additional amount of 10% shall
be added to the cost of these services for A.N.A's administrative cost.
COST ESTIMATES
Any cost estimates provided by A.N.A. will be on a basis of experience and
judgement, but since it has no control over market conditions or bidding
procedures A.N.A. cannot warrant that bids or ultimate construction costs
will not vary from these cost estimates.
PROFESSIONAL STANDARDS
A.NA. shall perform its professional services pursuant to the standard of
care which would be applied by a reasonable and prudent registered
professional engineer in the State of Texas providing services under the
same or similar scope of service for the same or similar types of projects.
WARRANTY
A.N_A.'s services are professional services limited to the exercise of
judgment and the rendering of advice and opinions and, as such, A.N.A.
makes no warranty, express or implied.
TERMINATION
Either CLIENT or A.N.A. may terminate this authorization by giving 30
days written notice to the other party. In such event CLIENT shall forthwith
pay A.N.A. in full for all work previously authorized and performed prior to
effective date of termination. If at any time the CLIENT suspends the work
of the project for any reason, the contract shall be terminated after 90 days
of notice to suspend work. If no notice of termination is given, relationships
and obligations created by this Authorization shall be terminated upon
completion of all applicable requirements of this Authorization.
ARBITRATION
All claims, disputes, and other matters in question arising out of, or
relating to, this Authorization or the breach thereof may be decided by
arbitration in accordance with the rules of the American Arbitration
Association then obtaining. Either CLIENT or A.N.A. may initiate a
request for such arbitration, but consent of the other party to such
procedure shall be mandatory. No arbitration arising out of, or relating to
this Authorization may include, by consolidation, joiner, or in any other
manner, any additional party not a party to this Authorization.
LEGAL EXPENSES
In the event legal action is brought by CLIENT or A.N.A. against the other
to enforce any of the obligations hereunder or arising out of any dispute
concerning the terms and conditions hereby created, the losing party
shall pay the prevailing party such reasonable amounts for fees, cost and
expenses as may be set by the court.
PAYMENT TO A.N.A., LLC.
Monthly invoices will be issued by A.N.A. for all work performed under the
terms of this agreement. Invoices are due and payable on receipt.
Interest at the rate of 1.5% per month wig be charged on all past -due
amounts, unless not permitted by law, in which case, interest will be
charged at the highest amount permitted by law.
LIMITATION OF LIABILITY
A.N.A's liability to the CLIENT for any cause or combination of causes is
in the aggregate, limited to an amount no greater than the fee earned
under this agreement.
ADDITIONAL SERVICES
Services In addition to those specified in Scope will be provided by A.N.A.
if authorized in writing by CLIENT. Additional services will be paid for by
CLIENT as indicated in attached Basis of Compensation or as negotiated.
SALES TAX
In accordance with the State Sales Tax Codes, certain surveying i services
are taxable. Applicable sales tax is n included in the above proposed
fee. Sales tax at an applicable rate will be indicated on invoice
statements.
SURVEYING SERVICES
in accordance with the Professional Land Surveying Practices Act of
1989, the client is informed that any complaints about surveying services
may be forwarded to the Texas Board of Professional Land Surveying,
7701 North Lamar, Suite 400, Austin, Texas 78752, (512) 452-9427,
In case any one or more of the provisions contained in this
Agreement shall be held illegal, the enforceability of the remaining
provisions contained herein shall not be Impaired thereby.
AUGUST 2006
ANA No. 10-370.03 Alliance Runway Ext. — BNSF Reloc. —MOD 3
Confidential Page 8 5/12/2011
Gorrondona & Associates, Inc.
May 11, 2011
Jacobs
Attn: Ms. Christine Graygor
777 Main Street
Fort Worth, Texas 76102
Re: Revisions to ALTA Surveys for Keller -Haslet Road, Alliance Runway Ext Ph III,
Tarrant County, Texas
Dear Ms. Graygor,
Gorrondona & Associates, Inc. (G&Ai) is pleased to submit this proposal for professional
land surveying services for the above referenced project. The following itemized
surveying services are to be provided by G&AI:
ATLA SURVEYS
Revised ALTA Surveys — Revise four (4) ALTA Boundary Surveys on four (4)
proposed easements, designated Parcels 1 UE-Pti , 1 UE-Pt2, 1 DE and 1 AE, on the
west side of Keller -Haslet Road. The revised surveys will conform to the 2011
Minimum Standard Detail Requirements for ALTA/ACSM Land Title Surveys, and will
include items 2, 3, 4, 7a, 8, 9, 11 b and 13 of Table A thereof.
Gorrondona & Associates, Inc. can provide the above professional land surveying
services for a lump sum fee of $ 1,552.00. If you have any questions or require
additional information please contact me at (817) 496-1424.
Sincerely,
GORRONDONA & ASSOCIkfff&,-TNC,.
Richard Kennedy, R.P.L.S.
Project Manager
Page 1ofI
7524 Jack Neweit Blvd. So • Fort Worth, Texas 76118 - 817.496.1424 • Fax 817 496 1768 - www.ga-inc-net
Gorrondona & Associates, Inc.
March 10, 2011
Jacobs
Attn: Ms. Christine Graygor
777 Main Street
Fort Worth, Texas 76102
Re: ALTA Surveys for (Seller -Haslet Road, Alliance Runway Ext Ph III, Tarrant
County, Texas
Dear Ms. Graygor,
Gorrondona & Associates, Inc. (G&AI) is pleased to submit this proposal for professional
land surveying and subsurface utility services for the above referenced project. The
following itemized surveying services are to be provided by G&AI:
ATLA SURVEYS
1.) ALTA Surveys — Prepare five (5) ALTA Boundary Surveys on one (1) fee simple
tract, designated Parcel 3A, and four (4) proposed easements, designated
Parcels 1UE-Pt1, 1UE-Pt2, 1DE and 1AE, on the west side of Keller -Haslet Road.
The surveys will conform to the 2011 Minimum Standard Detail Requirements for
ALTA/ACSM Land Title Surveys, and will include items 2, 3, 4, 7a, 8, 9, 11 b and
13 of Table A thereof.
AMOUNT $ 5,600.00
2.) Subsurface Utility — Locate subsurface utilities, marked by G&AI, within ten (10)
feet of the five (5) above referenced surveys as required in Table A, Item 11 b of
the 2011 Minimum Standard Detail Requirements for ALTA/ACSM Land Title
Surveys.
AMOUNT $ 5,500.00
Gorrondona & Associates, Inc. can provide the above professional land surveying and
subsurface utility services for a lump sum fee of $ 11,100.00. If you have any questions
or require additional information please contact me at (817) 496-1424.
Sincerely,
GORRONDONA & ASSOCJAT€S, INC.
Richard Kennedy, R.P.L.S.
Project Manager
Page 1 of I
7524 Jack Newell Blvd. So. • Fort Worth, Texas 76118.817 496.1424 - Fax 817 496.1768 • www.ga-anc.net
p r{ QGt/e 4r!-r,4
Gorrondona & Associates, Inc.
u
G
JA
Jacobs
Attn: Ms. Christine Graygor
777 Main Street
Fort Worth, Texas 76102
May 6, 2011
Re: Revision of Parcel 8DE to Parcel 8A, Alliance Runway Ext Ph III, Tarrant
County, Texas
Dear Ms. Graygor,
Gorrondona & Associates, Inc. (G&AI) is pleased to submit this proposal for professional
land surveying services for the above referenced project. The following itemized
surveying services are to be provided by G&AI:
Revision of Parcel 8DE to 8A
Revise Parcel 8DE Parts 1 through 9 (Permanent Drainage Easement) to Parcel 8A
Parts 1 through 9 (Right -of -Way Acquisition). After right-of-way documents have been
approved, set new right-of-way monumentation. Right-of-way takings will be on a per
parcel basis for a fee of $1,800.00 per document less the fee of $1000.00 per
document as previously invoiced leaving a net total fee of $800.00 per document.
Gorrondona & Associates, Inc. can provide the above professional land surveying
services for a lump sum fee of $ 7,200.00. If you have any questions or require
additional information please contact me at (817) 496-1424.
Sincerely,
GORRONDONA & ASSOCIATES
Richard Kennedy, ^R.P.L.S.
Project Manager
Page I of I
7524 Jack Newell Blvd. So. - Fort Worth. Texas 76118 - 817 496,1424 - Fax 817 496 1768 - www.ga-fic.net
-00 ,_, i,..
Gorrondona & Associates, Inc.
G
A
Jacobs
Attn: Ms. Christine Graygor, P.E.
777 Main Street
Fort Worth, Texas 76102
June 13, 2011
Re: Alliance Runway Extension Phase III Project
Final Plat for John Day Road / Barnwood Drive Right -of -Way
Annexation Document for the City of Fort Worth
Additional ALTA Surveys for BNSF
Dear Ms. Graygor:
Gorrondona $ Associates, Inc. (G&AI) is pleased to submit this proposal for
professional land surveying services for the above referenced project. The
following itemized surveying services are to be provided by Gorrondona &
Associates, Inc.:
I. Right-of-Wav Plat
A.) Prepare a Final Plat to City of Fort Worth platting standards of
approximately 8,700 feet of John Day Road and approximately 1,100 feet
of Barnwood Drive. After review make the necessary changes to the plat
and prepare the plat for final submittal to the City of Fort Worth. All ROW
Markers have been set during acquisition of the right-of-way.
Amount $8,500.00
II. Citv of Fort Worth Annexation Document
A.) Prepare an annexation document to City of Fort Worth standards of
approximately 145 acres between existing John Day Road and proposed
John Day Road/Barnwood Drive, including legal description and exhibit.
The proposed John Day Road/ Barnwood Drive to be purchased and
platted previous to the annexation.
Amount $7,500.00
Page 1 of 2
7524 Jack Newell Blvd. So - Fort Worth, Texas 76118 • 817.496 1424 • Fax 817.496 1768 • www.ga-inc net
Ill. Additional ALTA Surveys for Parcel No. 1
A.)Prepare three (3) additional ALTA Boundary Surveys on three (3) proposed
easements, designated Parcels 1UE-Pt3, 1TE-Pt1 and 1TE-Pt2, on the
west side of Keller -Haslet Road. The surveys will conform to the 2011
Minimum Standard Detail Requirements for ALTA/ACSM Land Title
Surveys, and will include items 2, 3, 4, 7a, 8, 9, 11 b and 13 of Table A
thereof.
Amount
IV. Additional ALTA Survevs for Parcel No. 12
$3,400.00
A.) Prepare three (3) ALTA Boundary Surveys on three (3) proposed
easements, designated Parcels 12UE-Pt1, 12UE-Pt2 and 12TE-Pt3 across
the BNSF Property and Keller -Haslet Road. The surveys will conform to the
2011 Minimum Standard Detail Requirements for ALTA/ACSM Land Title
Surveys, and will include items 2, 3, 4, 7a, 8, 9, 11 b and 13 of Table A
thereof.
Amount
$ 4,200.00
Gorrondona & Associates, Inc. can provide the above professional land
surveying services for a lump sum fee of $23,600.00, plus sales tax (8.25%) of
$1,947.00 (not required with Sales Tax Exemption Form), plus $1,990.00 for
applicable platting fees. The Total fee of this proposal is $27,537.00. if you have
any questions or require additional information please contact me at (817) 496-
1424.
Sincerely,
GORRONDONA & ASSOCIATES, INC.
Richard Kennedy, R.P.L.S.
Project Manager
Page 2 of 2
JACOBS
M 156
M 156 North Conatructlon
M 156 South COnshNCllen
NSF Main LIM 6 Connector Track
BNSF Prelim DoR9n 6 Eramirmaremat
Prepare BNSF R.location Agreement
C—CH Approves BNSF Agreement
Agreement Executed by COFW 6 BNSF
BNSF Reviews Nagn4nary Ewarermg Radon
COFW Rewads 1. BNSF Review Comments
Comment Ciose Out Mewing
BNSF60% D.W
ROW Acquisition MOD
BNSF Final Design
COFW Review of BNSF Fhal O1,19,
' BNSF Marai.h. Bid 6 Avrerd
BNSF Main Nne Conau orb..
l5-
FAA Raknburaable AgraNmenl.
Juba Day A K.H r-He det Road
65%Desgn
ROW Aodu1s uon MOD 5
Final Design
Ed sad AwarC
Conetfuction MOD 5
16 Parkway
E.gW Parkway ROW AcWisitim
Iw.y 6 T.siw.y E.W.W.
Early Earthwork Package
Ea.brear. k Package 2
Alliance Airport Runway Extension Project Schedule
T i ^, ��� �,. 1. i �„ , i �„ ,,, Is
sun 1
1460 day. U. Fri MY/Of
150 day. Bat 620 B Mon 1124108
501 days Tue 11125108 Fri 4/9/10 N
15920,y, Mon 2/23M
Wad W3
t. rin 11.1.
330 days Man W3N9
Mon 1/16.10
184 days Mon 11009
M'^
Tue 514110 .+. iw. Mrrnil
'
0 daya Too 5/4/10
Tue 514/10 c..xrarrowr ..w^.w
'.
13 days Wed.SS/10
Mon 5/17/10 sew.+ abM
aJ.MT%w.ww..•.^
30 days Tue S/1Oil 0
WWWIS110 easra.rlaa
IS days Thu 6117110
Thu 711110 coeA a.rww.l. eLLsrl...k. com^wx.
0 tlays Mon 7'19110
Mon 7119110 canm.m im
109 tlays Mon 7/19/10
Thu 111A10 n.
400 days Fri 1IWO
Fa 1MII
,ow a.rrmMW,
195 days Fr111,5110
Wed 5118111
30 days Thu 5119/11
Fri 6117,11
co.wa 'N10➢NYi• 1 ..e
90 days Wad 1W,
Man 112112
0
"
548 days Tue IM12
Wad 7/3113
586 tlays Thu 8/26/10
Mon 412/12
an
903 day, Thu t/7/10
Wed SWI12
4o+or,aax«.aa Aua
98 tlays Thu 1/7110
Wed 4/14/1D rsx o.
.n.
505 days Thu 4/15/10
Thu 211/11 ow a.a .,.n
_._. 'BR'','TVIF1r11P®R9!',-,
-
was
1!PWW\--
383 days Thu 4/15/10
Man 52/11 morn
120 days Thu 54111
Thu 911111
.
v
no days --Fri 9/2AI
Wetl&27/12
.uun 'too,
""•_wa +Mp�9WeNutvB
- 90 day, Man 21C13
Sal W4113
90 days Mon 2/4/13
Sat SVN3
5104d.ya Sun4/21102 W.d6129/16
12936aya Sun4/21/02 Thu111L06
631 d.y. bun 327105 Sun 12/17/04
Earthwork 6 WIWI,- Package 3
690 d.y,
Thu 117/10 Sun 11/27/11 m..e..•u+i..•a.r.v.a un
Eanhwod. B mill- - Package 3 Design
261 days
Thu 117/10
Fn9124110 a ,uaw. r++rao.Wn w.mmwmme;;' as
Earthwork 6 UOIiMc-Package 3 BM 8 Award
139 days
Thu 1R3/11
Too 531111 e—a a raw.-wu
Eanhwan,8 U0kties- Package 3 Consllutlion MOD
180 days
Wad 61111
Sun 11117,11 r••w. �.=�r.,.� rlloos
5
fie.
E,rtbw'9rk Package 4. Eagle Parkway 9 Try A
1492 days
Wed 1211/f0
Wed 12131/14
u
Design
379 days
Mon k2rlZ
Mon 4/15/13
Bid Is Award
90 tlays.
Wed IV1110
Mon 2/2WIt .w4awrro yea -
Canalruclion
5460ay,
Thu 7/4/13
Wed 12/31A4
Shen l Rary 1fiR 6 fury 16L
1550 daya
Wn 4/2/12
Wad 6129/16
Design
925 days
Mon 4IV12
Mon 10/13114
Bid 6 Award
90 days
Fri 1013/14
Thu 111,15
ConMruchan
546 days
Thu ii1115
Wed 6,29,16
M&C - Council Agenda Page 1 of 2
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 7/19/2011
DATE: Tuesday, July 19, 2011 REFERENCE NO.: **C-25025
LOG NAME: 55AFW RWY EXT P8 AMD 5 - JDR/KHR
SUBJECT:
Authorize Execution of Amendment No. 5 to City Secretary Contract No. 39252 in the Amount of
$544,787.59 with Jacobs Engineering Group, Inc., for Construction Support Services, Additional Land
Acquisition Services and ALTA Surveying Associated with the Relocation of John Day Road and Keller
Haslet Road and the Relocation of the Burlington Northern Santa Fe Railroad Mainline for the Alliance
Runway Extension Project (COUNCIL DISTRICT 2)
RECOMMENDATION:
It is recommended that the City Council authorize the City Manager to execute amendment No. 5 to City
Secretary Contract No. 39252 in the amount of $544,787.59 with Jacobs Engineering Group, Inc., for
construction support services, additional land acquisition services, and ALTA surveying associated with
the relocation of John Day Road and Keller Haslet Road and the relocation of the Burlington Northern
Santa Fe Railroad Mainline for the Alliance Runway Extension project. The total fee paid by the City for all
work and services under this contract shall not exceed the sum of $3,304,871.92.
DISCUSSION:
Jacobs has identified the following additional services that were not in earlier agreements: additional
construction support services, additional land acquisition services and ALTA surveying associated with the
relocation of John Day Road and Keller Haslet Road and relocation of the Burlington Northern Santa Fe
Railroad (BNSF) Mainline for the Alliance Runway Extension project. Staff has determined that the
services and fees proposed are reasonable for the project.
On March 28, 2001, (M&C C-18528) the City Council approved hiring Carter and Burgess, Inc. (now
Jacobs Engineering Group, Inc.) for Phase I program management services for the Runway Extension
Project at Fort Worth Alliance Airport. Subsequently, similar services have been performed in multiple
phases under individual agreements as funds became available.
On August 18, 2009, (M&C C-23735) the City Council approved a contract in the amount of $1,323,029.89
with Jacobs Engineering Group, Inc., for phase VIII for the runway extension project which included
program management for the design of Earthwork Package No. 3, John Day Road relocation, Keller
Haslet Road relocation and ALP Update at Fort Worth Alliance Airport.
On April 20, 2010, (M&C C-24187) Amendment No. 1 in the amount of $471,179.70 was to add additional
program management and land acquisition services associated with the relocation of the BNSF mainline
and connector track which was not included in the original contract.
On June 23, 2010, (no M&C required) Amendment No. 2 in the amount of $49,708.63 was approved to
increase funding for Phase I Environmental Site Assessment associated with the relocation of the BNSF
mainline due to the need to change the alignment to separate the rail line from an existing natural gas well
pad site.
On April 12, 2011, (M&C C-24855) Amendment No. 3 in the amount of $546,621.29 was approved for
additional program management and land acquisition services for the relocation of the BNSF connector
track and mainline. The amendment was necessary to account for the additional parcels and changes in
http://apps.cfwnet.org/ecouncil/printmc.asp?id=l 5549&print=true&DocType=Print 8/4/2011
M&C - Council Agenda Page 2 of 2
the right-of-way requirements due to two changes in the alignment.
On May 17, 2011, (M&C C-24909) Amendment No. 4 in the amount of $369,544.82 was approved for
construction support services, material testing and surveying associated with the construction of the
Earthworks Package No. 3 for the Alliance Runway Extension.
This Amendment No. 5 in the amount of $544,787.59 has been proposed for construction support
services, ALTA surveys and additional land acquisition services required for the Fort Worth Alliance
Airport Runway Extension. The initial scope of the project included boundary surveys only. Later in the
project, the consultant learned that the BNSF would only accept ALTA surveys for the relocation of the
BNSF rail lines. The construction support services included are for the construction phase of the relocation
of John Day Road and Keller Haslet Road which has recently been awarded. The additional land
acquisition is required to cover the costs to the project management team for three other changes to the
BNSF mainline alignment which occurred after Amendment 3 was agreed upon.
The total fee paid by the City for all work and services under this contract shall not exceed the sum of
$3,304,871.92.
Federal Aviation Association funds from Runway Extension Grant 3-48-0296-43-2011 will be used for this
project. Existing land credits that remain from the original land donation for Alliance Airport will be used for
the City's five percent in -kind match.
Jacobs Engineering Group, Inc. agrees to maintain its initial MWWBE commitment of 20 percent that it
made on the original agreement and extend and maintain that same MWWBE commitment of 20 percent to
all prior amendments up to and inclusive of this Amendment No. 5. Therefore Jacobs Engineering Group,
Inc., remains in compliance with the City's MWWBE Ordinance and attests to its commitment by its
signature on the Acceptance of Previous MWWBE Commitment form executed by an authorized
representative of its company.
This project is located in COUNCIL DISTRICT 2, Mapsco 7P.
FISCAL INFORMATION / CERTIFICATION:
The Financial Management Services Director certifies that funds are available in the current capital
budget, as appropriated, of the Airport Grants Fund.
FUND CENTERS:
TO F u nd/Accou nt/C enters FROM Fund/Account/Centers
GR14 541200 055218517800 $544.787.59
CERTIFICATIONS:
Submitted for Citv Manager's Office bv: Fernando Costa (6122)
Oriqinatinq Department Head: Kent Penney (5403)
Ruseena Johnson (5407)
Additional Information Contact: Patrick Buckley (2443)
ATTACHMENTS
1. 55AFW RWY EXT PBAMD 5_00960 Proiect Man.pdf (Public)
2. 960 FAR - P8A5.pdf (CFW Internal)
3. 960 MWBE APC-P8A5.pdf (CFW Internal)
4. AFW MOD 5 exolanation.odf (CFW Internal)
5. Available funds_218517.doc (CFW Internal)
http://apps.cfwnet.org/ecouncil/printmc.asp?id=l 5549&print=true&DocType=Print 8/4/2011
M&C - Council Agenda
Page 2 of 2
the right-of-way requirements due to two changes in the alignment.
On May 17, 2011, (M&C C-24909) Amendment No. 4 in the amount of $369,544.82 was approved for
construction support services, material testing and surveying associated with the construction of the
Earthworks Package No. 3 for the Alliance Runway Extension.
This Amendment No. 5 in the amount of $544,787.59 has been proposed for construction support
services, ALTA surveys and additional land acquisition services required for the Fort Worth Alliance
Airport Runway Extension. The initial scope of the project included boundary surveys only. Later in the
project, the consultant learned that the BNSF would only accept ALTA surveys for the relocation of the
BNSF rail lines. The construction support services included are for the construction phase of the relocation
of John Day Road and Keller Haslet Road which has recently been awarded. The additional land
acquisition Is required to cover the costs to the project management team for three other changes to the
BNSF mainline alignment which occurred after Amendment 3 was agreed upon.
The total fee paid by the City for all work and services under this contract shall not exceed the sum o�
$3,304,871.92.
Federal Aviation Association funds from Runway Extension Grant 3-48-0296-43-2011 will be used for this
project. Existing land credits that remain from the original land donation for Alliance Airport will be used for
the City's five percent in -kind match.
Jacobs Engineering Group, Inc. agrees to maintain its initial MWWBE commitment of 20 percent that it
made on the original agreement and extend and maintain that same MWWBE commitment of 20 percent to
all prior amendments up to and inclusive of this Amendment No. 5. Therefore Jacobs Engineering Group,
Inc., remains in compliance with the City's MWWBE Ordinance and attests to its commitment by its
signature on the Acceptance of Previous MWWBE Commitment form executed by an authorized
representative of its company.
This project is located in COUNCIL DISTRICT 2, Mapsco 7P.
FISCAL INFORMATION / CERTIFICATION:
The Financial Management Services Director certifies that funds are available in the current capital
budget, as appropriated, of the Airport Grants Fund.
FUND CENTERS:
TO Fund/Account/Centers
.1..... ..... ............ ._..................... ......_..
CERTIFICATIONS:
FROM Fund/Account/Centers
GR14 541200 055218517800 $544.787.59
Submitted for City Manaaer's Office by: Fernando Costa (6122)
Originatinq Department Head: Kent Penney (5403)
Ruseena Johnson (5407)
Additional Information Contact: Patrick Buckley (2443)
ATTACHMENTS
1. 55AFW RWY EXT P8AMD 5 00960 Proiect MaD.odf (Public)
2. 960 FAR - P8A5.Ddf (CFW Internal)
3. 960 MWBE APC-P8A5.Ddf (CFW Internal)
4. AFW MOD 5 exr)lanation.Ddf (CFW Internal)
5. Available funds 218517.doc (CFW Internal)
http://apps.cfwnet.orglecouncillprintmc.asp?id=15549&print=true&DocType=Print 8/4/2011