HomeMy WebLinkAboutContract 59514-CO1CSC No. 59514-COI FORT WORTH® City of Fort Worth Change Order Request Project Namel Improvements at Thomas Place Park, Edgewood Park, Parkwood East Park, & Trail Lake Estates Park I City Sec # I 59514 Client Project#(s)l 101631, 102325, 102963, 102964 Project Description) Major construction work required at not each, but several of the parks will consist of the following: playground equipment, shelters, parking lots, site lighting, sidewalks, benches, picnic tables, trash receptacles, sodding, trees, grading, and dumpster enclosures. Contractorl Cole Construction Inc. Change Order #I 1 I Date) 2/5/2024 City Project Mgr.I Robert Kevin Rodriguez City Inspectorl Patrick Jones / Travis Strang Dept. Park & Recreation Contract Time Totals (CD� Original Contract Amount $1,003,319.71 $1,003,319.71 00 Extras to Date $0.00 Credits to Date $0.00 Pending Change Orders (in M&C Process) $0.00 Contract Cost to Date $1,003,319.71 200 Amount o Proposed hange Order i 11 56 Revised Contract Amount �'r 28,0 7.92 Original Funds Available for Change Orders :1!1!= $0.00 i Remaining Funds Available for this CO Additional Funding (if necessary) 24,69821 CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) JUSTIFICATION (REASONS) FOR CHANGE ORDER ► During construction, it was determined that a change order #1 would be needed due to the following: • Additional design modifications were requested by the City specifically in relation to Thomas Place • These changes called for an additional sidewalk along the existing basketball court, additional demoliton of existing sidewalk, and additional concrete flumes • Changes to grading to fit the new drawing changes as well as additional concrete thickness added in lieu of lime stabilization Bench and table concrete pad as well additional bermuda sod Modifications at Edgewood, Parkwood East, and Trail Lake Estates were also requested to include ADA cast in place tile for playground ramps ► The additional scope of work will increase the contract time from 200 calendar days to 256 calendar days. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. Contractor's Company Name Contractor Name Date Cole Construction Inc. Kenneth Thorne Feb 6, 2024 ector/Ins ection Supervisor Project and Contract Compliance Manager Date '7"kL Xeu«, Jiac�r4aer_ Feb 5, 2024 ro at Mana er E8,2024 Senior Capital Project Officer Date �°���'° Feb8,2024 sistant Director De t Director, Contracting Department (Dept) Date Feb 10, 2024 1 Feb 12, 2024 me Date Assistant CityManager Date Feb 13, 2024 < ,Atip Feb 13, 2024 Council Action if required) g ":w M&C Number I 23 0344 M&C Date Approved I 4/25/2023I 7 ATTEST: KC Jannette Goodall, City Secretary OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX FORT W RTH -W, - City of Fort Worth Change Order Additions Project Name Improvements at Thomas Place Park, Edgewood Park, Parkwood East Park, & Trail Lake Estates Park CitySec # 59514 Client Project# 101631, 102325,102963,102964 Contractorl Cole Construction Inc. PMJ Robert Kevin Rodriguez I Ins ectorl '°°"JO11J l Change Order Submittal # O1 Dale 1 215/2024 ADDITIONS IIEM DhS;UKIP I ION UENI Oty Unit Unit lost total 1 Additional concrete sldewalK Ihomes Fla Ce VarK&Recreation bUU.000UUUUU 5F $2/.b`1' $1b,b14.UU1 2 Additional concrete parking homes Placet Park & Recreation 80.00000000 SF $26.15 $2,092.001 3 Additional grading (Thomas lace Park & Recreation 60.00000000 CY $107.16 $6,429.601 4 Additional bermuda sod Thomas lace) Park & Recreation 300.00000000 SF $2.46 $738.001 5 ADA Cast in Place Tile fo Playgrounds tramps Park & Recreation 3.00000001) EA $250.00 $750.001 Park & Recreation $26,623.60 1 1 1 1 Sub Total Additions $26,623.601 Change Order Additions Page 2 of 4 FORT WORTH City of Fort Worth Change Order Deletions Project Name I Improvements at Thomas Place Park, Edqewood Park, Parkwood East Park, & Trail Lake Estates Park I City Sec # 1 59514 1 Client Project # 1 101631,102325, 102963,102964 1 Contractorl Cole Construction Inc. I PMI Robert Kevin Rodriguez I Inspector rain Change Order Submittal # 0 Date 1 21512024 1 11 EM 6 Delete gravel channel DELETIONS UESI:KINI IUN UEF'I Uly Unit Unit host total 1 Park & Kecreatibn 1.uuuuuuuu LS $1,925.39 $1,925.391 Park & Ilacreation $1,925.391 1 1 1 Sub total Deletions $1,925.391 Change Order Deletions Page 3 of 4 M/SBE for this Change Order M/SBE Sub Type of Service Amount for this CO Maintaining commitment on original agreement of 15% Total I $0.00 I Previous Change Orders CO# DATE I AMOUNT Total I $0.00 1