Original Contract Amount
Contractor's Company Name
Circle C Construction Company
Contractor (Name)
Teresa Skelly
Contractor Signature
$59,500.00
$0.00
$120,000.00
$100,500.00
$3,119,428.70
$24,875.00
Revised Allowance Balance
$223,000.00
$0.00
$85,000.00
Current Contract Amount $4,053,030.20
Project and Contract Compliance Manager
Director, Contracting Department (Dept)
Date
$14,722,752.60
$19,500.00
JUSTIFICATION (REASONS) FOR CONSTRUCTION ALLOWANCE
Inspector/Inspection Supervisor
Date
DateAssistant City Attorney
Assistant Director (Dept)
Assistant City Manager
The purpose for this allowance is to add an additional construction item that was not included in a specific construction unit or not included in the
original bid. The items being added to to Westcliff Drainage Improvements, Unit 1 is to make repairs to a private irrigation line that is in public right-
of-way.We have deemed the price to be reasonable as we have compared to prices from TXDOT's average bid prices.
It is understood and agreed that the acceptance of this Construction Allowance Request by the contractor constitutes an accord and
satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Construction
Allowance Request. The Project/Program Manager signing below acknowledges that he/she is the person responsible for the monitoring and
administration of this contract, including ensuring all performance and reporting requirements.
$14,663,252.60
Allowance Funds Previously Allocated
$100,000.00 $150,000.00
$0.00
$37,500.00
$4,023,655.20
$29,375.00Extras to Date $5,250.00
$7,520,168.70
Credits to Date
City Sec #Westcliff Drainage Improvements Ph1 and Contract 91 Pt2
TPWUNIT or DEPT TotalsSewer UNIT 4 or DeptWater
Project
Description
TPW and Water Department partnership project constructing storm drain, water pipe, and sanitary sewer improvements in the westcliff
neighborhood.
CA #Circle C Construction Company
Mike Bennett, PE, PMP Brian McGillCity Inspector
$3,144,303.70
$370,000.00
$112,500.00
$613.22$0.00
$146,386.78
$613.22
Program Manager Date Senior Capital Project Officer
City of Fort Worth
Contractor
57280
Client Project #(s)C01669 & C01957
Date 1/2/2024
City Project Mgr.
Construction Allowance Request
2
Project Name
$14,386.78
Amount of Proposed Allocation
$7,525,418.70
Original Allowance Available to Allocation
Construction Allowance SUMMARY
Page 1 of 4
$613.22
$613.22
$0.00
$0.00
$0.00
Total Additions
TPW
Water
UNIT 4 or Dept
Sewer
Client Project #C01669 & C01957
2 1/2/2024
Mike Bennett, PE, PMP InspectorContractor
Construction Allowance Submittal #
Circle C Construction Company PM
City of Fort Worth
Construction Allowance Additions
Project Name Westcliff Drainage Improvements Ph1 and Contract 91 Pt2 City Sec #57280
ADDITIONS
Irrigaiton Repair 3700 Wyndale Ct 66 EA $613.22
TotalUnit Cost
$613.22
UnitQty
1.00000000
DEPTITEM DESCRIPTION
TPW
Date
Brian McGill
Westcliff Unit 3: Drainage Improvements (TPW)
Construction Allowance Additions
Page 2 of 4
$0.00
72 1.00 EA $613.22 $613.22
55 0.00 EA $1.00
Drainage Improvements Construction Allowance
Paving Construction Allowance
CONSTRUCTION ALLOWANCE VALUE BEING USED
$0.00
TotalQtyITEM Unit CostUnit
0.00 EA $1.00
DESCRIPTION
Water Construction Allowance 24
City of Fort Worth
Construction Allowance Value
Project Name Westcliff Drainage Improvements Ph1 and Contract 91 Pt2 City Sec #57280
Client Project #C01669 & C01957
2 1/2/2024Construction Allowance Submittal #
Contractor Circle C Construction Company PM Mike Bennett, PE,
PMP Inspector
Date
Brian McGill
Construction Allowance Value
3 of 4
CAR #DATE AMOUNT
M/SBE for this Construction Allowance Request
Previous Construction Allowance Requests
$0.00Total
Type of Service Amount for this CARM/SBE Sub
$0.00Total
Construction Allowance MSBE Data
Page 4 of 4
Routing and Transmittal Slip
Transportation & Public Works Department
DOCUMENT TITLE:Westcliff Drainage Improvements, Ph. 1,
Construction Allowance No. 2
M&C:N/A CPN:C01669 CSO:57280 DOC#:
Date:
To: Name Department Initials Date Out
1. Mike Bennett TPW
2.Teri Skelly
(t.skelly@circlecconstruction.com)Contractor
3. Brian McGill TPW
4. Linda Young TPW
5. Lissette Acevedo TPW
6. Patricia Wadsack TPW A/D
7. Lauren Prieur TPW/Dir
8. Doug Black Legal
9. Jesica McEachern CMO
10. Ronald Gonzales CSO
11. Jannette Goodall CSO
12. Allison Tidwell CSO
13. tpw_sw_contracts TPW
DOCUMENTS FOR CITY MANAGER’S SIGNATURE: All documents received from any and all
City Departments requesting City Manager’s signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, David will review
and take the next steps.
NEEDS TO BE NOTARIZED: YES No
RUSH:YES No SAME DAY:YES No NEXT DAY:YES No
ROUTING TO CSO: YES No
Action Required: Attach Signature, Initial and Notary Tabs
As Requested
For Your Information
Signature/Routing and or Recording
Comment
File
Return to: tpw_sw_contracts@fortworthtexas.gov Call 817-229-3283 with questions. Thank you!