HomeMy WebLinkAboutContract 60322-FP1FORT WORTH,,
City Secretary 60322-FP1
Contract No.
Date Received 03/20/2024
AT
NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Morningstar — Westpoint Blvd 12" Waterline
City Project No.: 105123
Improvement Type(s)
C r
Colton ToIlett (Mar20, 202412:50 1-
-Contractor
Vice President
Title
Water ❑x Sewer ❑
Original Contract Price:
$409,574.00
Amount of Approved Change Order(s):
$47,690.00
Revised Contract Amount:
$457,264.00
Total Cost of Work Complete:
$457,264.00
D T Utility Contractors Inc.
Company Name
Curtis Hol OnH orth(M a r20, 202413:24 CDT)
Project Inspector
Project Manager
M,I^
F,b—a Owen (Mar 20. 2024 14: 11 CDTi
CFA Manager
Lauren Prieur (Mar 20, 202414:12 CDT)
TPW Director
CW-L--
Asst. City Manager
Notice of Project Completion
M a r 20, 2024
Date
M a r 20, 2024
Mar 20, 2024
Date
Mar 20, 2024
Date
Mar 20, 2024
Date
Mar 20, 2024
Date
Mar 22, 2024
Date
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Page 1 of 2
Project Name: Morningstar — Westpoint Blvd 12" Waterline
City Project No.: 105123
City's Attachments
Final Pay Estimate ❑x
Change Order(s): ❑x Yes ❑ N/A
Pipe Report: ❑x Yes ❑ N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time: 30 WD Days Charged: 60
Work Start Date: 11/6/2023 Work Complete Date: 2/26/2024
Completed number of Soil Lab Test: 85
Completed number of Water Test: 6
Page 2of2
FORT WORT 11
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name MORNINGSTAR- WESTPOINT BLVD. 12" WATER LINE
Contract Limits
Project Type WATER
City Project Numbers 105123
DOE Number 5123
Estimate Number I Payment Number 1 For Period Ending 2/24/2024
WD
City Secretary Contract Number
Contract Date
Project Manager NA
Contractor D T UTILITY CONTRACTORS, INC.
2614 CAUSBIE RD
WEATHERFORD, TX 76087
Inspectors D. WATSON / HOLLINGSWO
Contract Time 3WD
Days Charged to Date 60
Contract is 100.00 Complete
Friday, March 1, 2024 Page 1 of 4
City Project Numbers 105123
Contract Name MORNINGSTAR- WESTPOINT BLVD. 12" WATERLINE
Contract Limits
Project Type WATER
Project Funding
UNIT I: WATER IMPROVEMENTS
Item Description of Items Estimated Unit
No. Quanity
1-39 8" DR-14 PVC WATER PIPE (ITEMS I-39 TO I-57 10 LF
SHTS. 16A TO 16C)
I-40
12" DR-14 PVC WATER PIPE
2155 LF
I-41
12" WATER PIPE W/ CONCRETE CASING
5 LF
I-42
12" DIP WATER PIPE
25 LF
I-43
12" DIP WATER PIPE W/24" STEEL CASING (CO
0 LF
#1)
I-44
12" DIP WATER PIPE W/24" STEEL CASING ON
35 LF
CONC. CRADLE
I-45
TRENCH SAFETY
2170 LF
I-46
8" GATE VALVE
1 EA
I-47
12" GATE VALVE (CO #1)
6 EA
I-48
4"-12" PRESSURE PLUGS (CO #1)
3 EA
I-49
CONNECT TO EXISTING 4"-12" WATER MAIN
1 EA
I-50
2" IRRIGATION SERVICE (MEDIANS OR POS)
2 EA
I-51
4" COMBINATION TURBINE MELTER VAULT
1 LS
INSTALLATION WITH BYPASS PER D- 119
I-52
MEDIUM STONE, RIPRAP, DRY
334 SY
I-53
REMOVE & REPLACE 7.5 PAVEMENT/LIME
19 SY
STABILIZATION PRESSURE PLUGS
I-54
REMOVE & REPLACE EXISTING RESIDENTIAL
860 SF
SIDEWALK (4" THICK)
I-55
REMOVE & REPLACE EXISTING R-I ADA RAMP
1 EA
I-56
REMOVE EXISTING 167 L.F. OF AN EXISTING
1 EA
8" WATERLINE, REMOVE AND SALVAGE
I-57
SLAVAGE & REINSTALL EXISTING WASH.
0 EA
STYLE ST. LIGHT WITH TYPE 7 (CO #1)
I-58
24" CASING BY OPEN CUT (CO #1)
80 LF
I-59
2" AIR VALVE ASSEMBLY (CO #1)
1 EA
I-60
DIP FITTINGS W/ RESTRAINT (CO #1)
1 TN
1-61
16"X12" TAPPING SLEEVE & VALVE (CO #1)
1 EA
Sub -Total of Previous Unit
DOE Number 5123
Estimate Number I
Payment Number 1
For Period Ending 2/24/2024
Unit Cost Estimated Completed Completed
Total Quanity Total
$65.00 $650.00 10 $650.00
$95.00
$204,725.00
2155
$204,725.00
$125.00
$625.00
5
$625.00
$125.00
$3,125.00
25
$3,125.00
$310.00
$0.00
0
$0.00
$150.00
$5,250.00
35
$5,250.00
$1.00
$2,170.00
2170
$2,170.00
$2,100.00
$2,100.00
1
$2,100.00
$4,250.00
$25,500.00
6
$25,500.00
$500.00
$1,500.00
3
$1,500.00
$1,500.00
$1,500.00
1
$1,500.00
$3,400.00
$6,800.00
2
$6,800.00
$65,000.00
$65,000.00
1
$65,000.00
$125.00
$41,750.00
334
$41,750.00
$261.00
$4,959.00
19
$4,959.00
$26.00
$22,360.00
860
$22,360.00
$4,200.00
$4,200.00
1
$4,200.00
$9,500.00
$9,500.00
1
$9,500.00
$15,000.00
$0.00
0
$0.00
$310.00
$24,800.00
80
$24,800.00
$7,500.00
$7,500.00
1
$7,500.00
$12,000.00
$12,000.00
1
$12,000.00
$11,250.00
$11,250.00
1
$11,250.00
$457,264.00
$457,264.00
Friday, March 1, 2024 Page 2 of 4
City Project Numbers 105123
Contract Name MORNINGSTAR- WESTPOINT BLVD. 12" WATERLINE
Contract Limits
Project Type WATER
Project Funding
Contract Information Summary
Original Contract Amount
Change Orders
Change Order Number 1
Total Contract Price
DOE Number 5123
Estimate Number 1
Payment Number 1
For Period Ending 2/24/2024
$409,574.00
$457,264.00
$457,264.00
Total Cost of Work Completed $457,264.00
Less % Retained $0.00
Net Earned $457,264.00
Earned This Period $457,264.00
Retainage This Period $0.00
Less Liquidated Damages
Days @ / Day
LessPavement Deficiency
Less Penalty
Less Previous Payment
Plus Material on Hand Less 15%
Balance Due This Payment
$0.00
$0.00
$0.00
$0.00
$0.00
$457,264.00
Friday, March 1, 2024 Page 3 of 4
City Project Numbers 105123
Contract Name MORNINGSTAR- WESTPOINT BLVD. 12" WATERLINE
Contract Limits
Project Type WATER
Project Funding
Project Manager NA
Inspectors D. WATSON / HOLLINGSWO
Contractor D T UTILITY CONTRACTORS, INC.
2614 CAUSBIE RD
WEATHERFORD, TX 76087
DOE Number 5123
Estimate Number I
Payment Number 1
For Period Ending 2/24/2024
City Secretary Contract Number
Contract Date
Contract Time 30 WD
Days Charged to Date 60 WD
Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
Total Cost of Work Completed $457,264.00
Less % Retained $0.00
Net Earned $457,264.00
Earned This Period $457,264.00
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty
$0.00
Less Previous Payment
$0.00
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$457,264.00
Friday, March 1, 2024 Page 4 of 4
02/19120242
IPROJECT NAME:
I CONTRACT:
ICFA #
ICITY PROJECT #
IDOE #
IWATER PROJECT#
ISEWER PROJECT #
IFILE #
INSPECTOR:
PROJECT MANAGER:
DEVELOPER -AWARDED -PROJECT CHANGE ORDER
MORNINGSTAR - WESTPOINT BLVD. 12" WATER LINE
12" WATER LINE
23-0133 I
CITY PARTICIPATION:( NO
105123
N/A
30114-0200431-105123-EO7685
N/A
N/A
CURTIS HOLLINGSWORTH
817-584-4535
Phone No:
GEORGE MARQUEZ, P.E.
Phone No: 817-392-6826
CONTRACT UNIT
WATER SEWER PAVING
Cost City Cost
IORIGINAL CONTRACT
$409,574.00
(EXTRAS TO DATE
ICREDITS TO DATE
ICONTRACT TO DATE
$409,574.00
(AMOUNT OF PROP. CHANGE ORDER
$47,690.00
IREVISED CONTRACT AMOUNT
$457,264.00
TOTAL REVISED CONTRACT AMOUNT
PER UNIT
$457,264.00
REVISED COST SHARE
Dev. Cost:
TOTAL REVISED CONTRACT
oper Developer
City Cost Cost City Cost
n/a I n/a
$0.00
$0.00
$0.00
$457,264.00
$0.00
$0.00
$0.00
City Cost:
$457,264.00
REVIEWED
By George Marqeuez, P.E. at 4:10 pm, Feb 21, 2024
CHANGE
ORDER No:
CHANGE
ORDER
No: 1
Georae.MaraueZ(aFortWorthTexas.aov
DRAINAGE STREET LIGHTS CONTRACT
oper Developer DAYS
City Cost Cost City Cost
n/a I n/a k 1 30
$0.00 $0.00
$0.00 $0.00 30
0
$0.00 $0.00
$0.00 $0.00 I 30
$0.00
$0.00
$0.00
Page 1
You are directed to make the following changes in the contract documents
CITY BID ITEM
CONTRACT
PAY ITEM #
#
QUANTITY
(WATER LINE
Adjustments
1-43
9999.0112
-6
1-47
3312.3005
2
1-48
0241.1118
1
1-57
9999.0117
-1
New Adds
1-58
3305.1004
80
1-59
3312.1002
1
1-60
3311.0001
1
1-61
3312.4114
1
UNIT
ITEM DESCRIPTION
UNIT PRICE TOTAL
LF
12" DIP Water Pipe w/24" Steel Casing
$310.00
-$1,860.00
EA
12" Gate Valve
$4,250.00
$8,500.00
EA
4"-12" Pressure Plugs
$500.00
$500.00
EA
Salvage and Reinstall existing Washington Style Street Light with Type 7 foundation.
$15,000.00
-$15,000.00
LF
24" Casing by Open Cut
$310.00
$24,800.00
EA
2" Air Valve Assembly
$7,500.00
$7,500.00
TN
DIP Fittings w/Restraint
$12,000.00
$12,000.00
EA
16" x 12" Tapping Sleeve & Valve
$11,250.00
$11,250.00
I'OTAL - WATER IMPROVEMENTS
$47,690.00
REASONS FOR CHANGE ORDER:
Pay items 1-43, 1-47, 1-48 and 1-57 and 18 are based on adjustments in the field. Items 1-58 to 1-61 are due to the relocation of the water line from the Church Property to Mornningstar prop(
RECOMMENDED:
WELCH ENGINEERING, INC.
APPROVED:
F.G. ALEDO DEVELOPMENT, LLC.
APPROVED:
D.T. UTILITY CONTRACTORS, INC.
By: �cy�� s%/�z By: t/e C� By: �zera s
Name: Timothy J. Welch, P.E. Name: Kim Gill Name: Dennis Toilet
Title: President Title: President Title: President
FORT WORTH,
TRANSPORTATION AND PUBLIC WORKS
PIPE REPORT FOR:
PROJECT NAME: Morningstar Westpoint 12" Waterline
CITY PROJECT NUMBER: 105123
WATER
PIPE LAID SIZE TYPE OF PIPE
OPEN CUT 12" PVC
OPEN CUT 12" DIP
OPEN CUT 8" PVC
LF
2160
66
10
FIRE HYDRANTS: NONE VALVES (16" OR LARGER) NONE
PIPE ABANDONED SIZE TYPE OF PIPE LF
DENSITIES: PASSED
NEW SERVICES: 2" COPPER 10
I SEWER
PIPE LAID SIZE TYPE OF PIPE LF
PIPE ABANDONED SIZE TYPE OF PIPE LF
DENSITIES:
NEW SERVICES:
TRANSPORTATION AND PUBLIC WORKS
The City of Fort Worth • 1000 Throckmorton Street • Fort Worth, TX 76012-6311
(817) 392 - 7941 • Fax: (817) 392 - 7845
FORT WORTH,,
TRANSPORTATION AND PUBLIC WORKS
March 1, 2024
D.T. Utility Contractors, INC
2614 Causbie Rd
Weatherford, TX 76087
RE: Acceptance Letter
Project Name: Morningstar Westpoint-12" Waterline
Project Type: Water and Paving
City Project No.: 105123
To Whom It May Concern:
On February 14, 2024 a final inspection was made on the subject project. There were punch list items
identified at that time. The punch list items were completed on February 26, 2024. The final inspection
and the corrected punch list items indicate that the work meets the City of Fort Worth specifications and
is therefore accepted by the City. The warranty period will start on February 26, 2024, which is the date
of the punch list completion and will extend of two (2) years in accordance with the Contract
Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at 817-
392-6826.
Sincerely,
George Marquez P.E., Project Manager
Cc: Curtis Hollingsworth, Inspector
Donald Watson, Inspection Supervisor
Aaron Ybarra, Senior Inspector
Andrew Goodman P.E., Program Manager
Welch Engineering, Consultant
D.T. Utilities, Contractor
FG Aledo Development, LLC, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev. 8/20/19