HomeMy WebLinkAboutOrdinance 26779-03-2024Ordinance No. 26779-03-2024
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER AND SEWER CAPITAL PROJECTS FUND
IN THE AMOUNT OF $10,186,221.00, TRANSFERRED FROM AVAILABLE
FUNDS IN THE WATER AND SEWER FUND, FOR THE PURPOSE OF FUNDING
THE WATER AND SANITARY SEWER REPLACEMENT, CONTRACT 2021
WSM-C PROJECT (CITY PROJECT NO. 103500); PROVIDING FOR A
SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF
PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT
HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2023-2024 in the
Budget of the City Manager, there shall also be increased estimated receipts and appropriations in the Water
and Sewer Capital Projects Fund in the amount of $10,186,221,00, transferred from available funds in the
Water and Sewer Fund, for the purpose of funding the Water and Sanitary Sewer Replacement, Contract 2021
WSM-C project (City Project No. 103500).
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 26453-09-2023 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Douglas Black (Mar 29, 202410:14 COT)
Douglas W. Black
Senior Assistant City Attorney
ADOPTED AND EFFECTIVE: MARCH 19, 2024
CITY SECRETARY
—is
V
Jannette S. Goodall
City Secretary
100
jo"...00
,�►
a oo
oiJ
D
r O O *d
O00
0Op000 P4
MAYOR AND COUNCIL COMMUNICATION MAP
60WSS21 WSMC-CIRCLE
41
4 y� ONTptVE � O
EM 9'A
R�1r,
4 9
r p
goo
I� co
RIDGI
L
6
y`--SUMACRb
O-'
ti
1~STDR
-ram,EDG
WORTIJ
e
-GEDDESAVEE '
NIILBURN S7
u
' I Fit
`1,HOUR NAVE
„ WELLESL.FYAVE!
cy
r FL'ETCHERAVE' 1�
' _ELLAVE �amot cn
W
o
KIL'PATRICKAVE
z
a oo�NAVE _
I Li.
t.
L I
LIBBEYAVE -
�O
MCKM
� B REAVE C-
HUMBERI
FARNSWORUj
THAVE i
z ,A
T
HELMICKAVE LIJ
q
rti
r
�>
0
i Via. Zf. j
r I
W f O
.� IE R W D s'"" H Z L
vA��-EY V-
7-7
City of Fort Worth,
Mayor and
DATE: 03/19/24
Texas
Council Communication
LOG NAME; 60WSSC21WSMC-CIRCLEC
SUBJECT
M&C FILE NUMBER: M&C 24-0227
(CD 3) Authorize Execution of a Contract with William J. Schultz, Inc. dba Circle C Construction Company, in the Amount of $10,357,458.00, for
Water and Sanitary Sewer Replacement, Contract 2021 WSM-C Project, Amend Transportation & Public Works Department's Fiscal Years 2024-
2028 Capital Improvement Program and Adopt Appropriation Ordinances to Effect a Portion of Water's Contribution to the Fiscal Years 2024-
2028 Capital Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of a contract with William J. Schultz, Inc. dba Circle C Construction Company, in the amount of $10,357,458.00 for Water
and Sanitary Sewer Replacement, Contract 2021 WSM-C project;
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water and Sewer Capital Projects Fund
in the amount of $10,186,221.00, transferred from available funds within the Water and Sewer Fund, for the purpose of funding the Water and
Sanitary Sewer Replacement, Contract 2021 WSM-C project (City Project No. 103500) and to effect a portion of Water's contribution to the
Fiscal Years 2024-2028 Capital Improvement Program;
3. Adopt the attached appropriation ordinance adjusting estimated receipts and appropriations in the General Capital Projects Fund by
increasing estimated receipts and appropriations in Water and Sanitary Sewer Replacement, Contract 2021 WSM-C project (City Project
No. 103500) in the amount of $1,165,561.00, and decreasing estimated receipts and appropriations in the Contract Street Maintenance
programmable project (City Project No. P00020) by the same amount; and
4. Amend the Transportation & Public Works Department's Fiscal Years 2024-2028 Capital Improvement Program.
DISCUSSION:
This Mayor & Council Communication (M&C) is to authorize execution of a construction contract for the replacement of cast iron water and
deteriorated sanitary sewer mains as indicated on the following streets and easements:
Street
From
To
Scope of
Work
Westridge
Avenue
Camp Bowie Boulevard
Vckery
Boulevard
Water/Sewer
Edgehill Road
Sealands Lane
Westridge
Water/Sewer
Avenue
Ridgeway
Westridge Avenue
Winthrop
Water
Street
E.
Easement north
160 feet south of the
550 feet
of Ridgeway
Ridgeway Street 1 Westridge
southeast
Water
Street
Avenue Intersection
Additionally, asphalt pavement rehabilitation will be conducted on all the roadways subsequent to the water and sanitary sewer main replacement.
The Water Department's share of this contract is $9,308,253.00, and the Transportation & Public Works Department's share of the contract is
$1,049,205.00.
The project was advertised for bids on November 30, 2023 and December 7, 2023, in the Fort Worth Star -Telegram. On January 11, 2024, the
following bids were received:
Bidder
Amount
Time of
Completion
690
William J. SchuItz, Inc. dba Circle C
,357,458.00
Fs,
Calendar
Construction Company, Inc.
Days
Jackson Construction, Ltd.
$11,444,338.00
Western Municipal Construction of
$12,926,036.33
Texas, LLC
Venus Construction, Inc. _�$15,001,351.69L ........ J
In addition to the contract amount, $632,473.00 (Water: $445,932.00; Sewer. $122,645.00; Paving: $63,896.00) is required for project
management, material testing and inspection, and $361,851,00 (Water: $234,033.00; Sewer: $75,358.00; Paving: $52,460.00) is provided for
project contingencies. The sanitary sewer component of this project is part of the Water Department's Sanitary Sewer Overflow Initiative Program.
Approximately 10,037 linear feet of cast iron water pipe will be removed and replaced as part of this project.
This project will have no impact on the Transportation & Public Works' or the Water Department's operating budgets when completed.
Funding for this project was not included in the FY2024-2028 Capital Improvement Program (CIP) because Transporatfon & Public Works
Department amounts for the project were unknown at the time of CIP development. The action in this M&C will amend the FY2024-2028 Capital
Improvement Program as approved in connection with Ordinance 26453-09-2023 as follows:
60WSSC21 WSMC-CIRCLEC
Capital
Fund
Project
Name
FY2024 CIP
Appropriations
Authority
Budget Adjustment
Revised
PY2024
Name
Bud et
9
30100 -
P00020 -
General
Contract
Capital
$9,126,492.00
This M&C
$(1,165,561.00)
$7,960,931.00
Projects
Maintenance
Fund
It is the practice of the Water Department to appropriate its CIP plan throughout the Fiscal Year, instead of within the annual budget ordinance, as
projects commence, additional funding needs are identified, and to complywith bond covenants. The actions in the M&C will appropriate funds in
support of the Water's portion of the City of Fort Worth's Fiscal Years 2024-2028 Capital Improvement Program, as follows:
60WSSC21 WSMC-CIRCLEC
Capital
Fund
Project
FY2024 CIP
Authority
Budget Change
Revised
FY2024
Name
Name
Appropriations
(increase/Decrease)
Bud et
9
W&S
103500-
Capital
W/SS
Projects —
Repl.
$0.00
This M&C
$10,186,221.00
$10,186,221.00
Fund
Contract
56002
2021
WSM-G
Funding is budgeted in the Contract Street Maintenance programmable project within the General Capital Projects Fund and in the Transfer to
Water/Sewer account of the Water and Sewer operating budget for the purpose of funding the WISS Repl Contract 2021 WSM-C project within the
Water & Sewer Capital Projects Fund.
Appropriations for the Water and Sanitary Sewer Replacement, Contract 2021 WSM-C project are as depicted below:
Existing
Additional
[::::Fund
Appropriations
Appropriations
Project Total`
Water & Sewer
Capital Projects
$630,403.00
$10,186,221.00
$10,816,624.00
Fund 56002
General Capital
Projects Fund
$0.00
$1,165,561.00
$1,165.561.00
30100
Project Total
$630,403.00
$11,351,782.00
$11,982,185.00
"Numbers rounded for presentation purposes.
Business Equity: William J. Schultz, Inc. dba Circle C Construction Company, is in compliance with the City's Business Equity Ordinance by
committing to 14 percent MWBE participation on this project. The City's MWBE goal on this project is 14 percent.
The project is located in COUNCIL DISTRICT 3.
A Form 1295 is not required because: This M&C does not request approval of a contract with a business entity.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Contract Street Maintenance programmable project within the General
Capital Projects Fund and in the Water & Sewer Fund, and upon approval of the above recommendations and adoption of the attached
appropriation ordinances, funds will be available in the W&S Capital Projects Fund and the General Capital Projects Fund for the WISS
Repl Contract 2021 WSM-C project to support execution of the contract. Prior to any expenditure being incurred, the Water and Transportation &
Public Works Departments have the responsibility of verifying the availability of funds.
Submitted for City Managers Office b . Fernando Costa 6122
Originating Business Unit Head: Chris Harder 5020
Additional Information Contact: Dena Johnson 7866