NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project Manager has
accepted the following project as complete:
Project Name: Cohix Phase 1
City Project No.: 103287
Improvement Type(s): Water ❑x Sewer ❑x
Dev Costs City Costs
Total Cost
Original Contract Price: Water
$1,076,386.89
$60,234.31
$1,136,621.20
Original Contract Price: Sewer
$1,165,072.00
$0.00
$1,165,072.00
Original Contract Price Total
$2,241,458.89
$60,234.31
$2,301,693.20
Approved Change Order: Water
$2,000.00
$0.00
$2,000.00
Approved Change Order: Sewer
$1,490.00
$0.00
$1,490.00
Revised Contract Amount: Water
$1,078,386.89
$60,234.31
$1,138,621.20
Revised Contract Amount: Sewer
$1,166,562.00
$0.00
$1,166,562.00
Total Cost of Work Complete:
$2,244,948.89
$60,234.31
$2,305,183.20
M a r 28, 2024
Contractor
Date
Vice President
Title
Burnsco Construction INC
Company Name
--,'J�
Mar 28, 2024
William Fa uver(Mar28. 202411:14 CDT)
Project Inspector
Date
�� LAG P• �
Mar 28, 2024
K� Jaa ra ri P_F..��fi_7�7417J7 CDTI
Project Manager
Date
Mar 29, 2024
74�-111-A I01U12CDT)
CFA Manager
Date
Mar 29, 2024
TPW Director
Date
Cl�-
Apr 1, 2024
Asst. City Manager
Date
OFFICIAL RECORD
CITY SECRETARY Page 1 of 2
FT. WORTH, TX
Notice of Project Completion
Project Name: Cohix Phase 1
City Project No.: 103287
City's Attachments
Final Pay Estimate x❑
Change Order(s): ❑x Yes ❑ N/A
Pipe Report: x❑ Yes ❑ N/A
Contractor's Attachments
Affidavit of Bills Paid see attached
Consent of Surety see attached
Statement of Contract Time
Contract Time: 280 WD Days Charged: 369
Work Start Date: 6/13/2022 Work Complete Date: 1/31/2024
Completed number of Soil Lab Test: 750
Completed number of Water Test: 18
Page 2 of 2
FORT WO 1T H
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name COHIX PHASE 1
Contract Limits
Project Type WATER & SEWER
City Project Numbers 103287
DOE Number 3287
Estimate Number 1 Payment Number 1
City Secretary Contract Number
Contract Date 2/2/2022
For Period Ending 1/31/2024
WD
Contract Time 15WD
Days Charged to Date 369
Project Manager NA
Contractor BURNSCO CONSTRUCTION, INC.
6331 SOUTHWEST BLVD
FORT WORTH, TX 76132
Inspectors E. DAVILA / W. FAUVER
Contract is 100.00 Complete
Wednesday, March 27, 2024 Page 1 of 5
City Project Numbers 103287 DOE Number 3287
Contract Name COHIX PHASE 1 Estimate Number I
Contract Limits Payment Number 1
Project Type WATER & SEWER For Period Ending 1/31/2024
Project Funding
UNIT IA: WATER IMPROVEMENTS
Item
Description of Items
Estimated Unit
Unit Cost
Estimated
Completed
Completed
No.
Quanity
Total
Quanity
Total
1
8" PVC WATER PIPE
7044 LF
$59.70
020,526.80
7044
$420,526.80
2
FIRE HYDRANT W/GATE VALVE
7 EA
$5,020.00
$35,140.00
7
$35,140.00
3
1" WATER SERVICE
166 EA
$1,140.00
M9,240.00
166
$189,240.00
4
8" GATE VALVE & BOX
27 EA
$1,630.00
$44,010.00
27
$44,010.00
5
TRENCH SAFETY
7044 LF
$0.10
$704.40
7044
$704.40
6
CONNECTION TO EXISTING 36" WATER MAIN
1 EA
$1,800.00
$1,800.00
1
$1,800.00
7
DUCTILE IRON WATER FITTINGS
0.9 TN
$6,600.00
$5,940.00
0.9
$5,940.00
W/RESTRAINT
8
2" WATER SERVICE
1 EA
$2,760.00
$2,760.00
1
$2,760.00
9
1" IRRIGATION SERVICE
4 EA
$1,200.00
$4,800.00
4
$4,800.00
10
36" X 8" TAPPING SLEEVE & VALVE
1 EA
$9,000.00
$9,000.00
1
$9,000.00
11
8" WATERLINE LOWERING
20 EA
$4,220.00
$84,400.00
20
$84,400.00
12
1 1/2" IRRIGATION SERVICE (CO#1)
1 EA
$2,000.00
$2,000.00
1
$2,000.00
Sub -Total of Previous Unit
$800,321.20
$800,321.20
UNIT 111: 16" WATER IMPROVEMENTS (MCPHERSON
Item
Description of Items
Estimated Unit
Unit Cost
Estimated
Completed
Completed
No.
Quanity
Total
Quanity
Total
1
16" WATER PIPE
1356 LF
$174.50
Q36,622.00
1356
$236,622.00
2
16" GATE VALVE & BOX
2 EA
$19,000.00
$38,000.00
2
$38,000.00
3
CONNECTION TO EXSING 36" WATER MAIN
1 EA
$1,800.00
$1,800.00
1
$1,800.00
4
DUCTILE IRON WATER FITTINGS
0.2 TN
$9,000.00
$1,800.00
0.2
$1,800.00
W/RESTRAINT
5
TREENCH SAFETY
1356 LF
$0.50
$678.00
1356
$678.00
6
TRAFFIC CONTROL
1 MO
$1,600.00
$1,600.00
1
$1,600.00
7
2" COMBINATION AIR RELEASE ASSEMBLY
1 EA
$10,100.00
$10,100.00
1
$10,100.00
FOR WATER
8
IMPORTED EMBEDMENT/BACKFILL CSS
100 LF
$24.00
$2,400.00
100
$2,400.00
9
36" X16" TAPPING SLEEVE & VALVE
I EA
$9,800.00
$9,800.00
1
$9,800.00
10
16" WATER LINE LOWERING
5 EA
$7,100.00
$35,500.00
5
$35,500.00
Sub -Total of Previous Unit
$338,300.00
$338,300.00
Wednesday, March 27, 2024 Page 2 of 5
City Project Numbers 103287 DOE Number 3287
Contract Name COHIX PHASE 1 Estimate Number I
Contract Limits Payment Number 1
Project Type WATER & SEWER For Period Ending 1/31/2024
Project Funding
UNIT II: SANITARY SEWER IMPROVEMENTS
Item
Description of Items
Estimated Unit
Unit Cost
Estimated
Completed Completed
No.
Quanity
Total
Quanity
Total
1
8": SEWER MAIN
8706 LF
$69.00
W0,714.00
8706
$600,714.00
2
10" SEWER PIPE
326 LF
$80.00
$26,080.00
326
$26,080.00
3
4' MANHOLE
32 EA
$3,900.00
W4,800.00
32
$124,800.00
4
EXTRA DEPT MANHOLE (> 6.0')
149 VF
$170.00
$25,330.00
149
$25,330.00
5
4" SEWER SERVICE (CO #1)
167 EA
$1,490.00
$248,830.00
167
$248,830.00
6
POST -CCTV INSPECTION
9032 LF
$3.00
$27,096.00
9032
$27,096.00
7
MANHOLE VACUUM TESTING
32 EA
$130.00
$4,160.00
32
$4,160.00
8
TRENCH SAFETY
9032 LF
$1.00
$9,032.00
9032
$9,032.00
9
TRAFFIC CONTROL
1 MO
$500.00
$500.00
1
$500.00
10
EPDXY MANHOLE LINER
153 VF
$350.00
$53,550.00
153
$53,550.00
11
IMPORTED EMBEDMENT/BACKFILL CSS
550 LF
$51.00
$28,050.00
550
$28,050.00
12
CONNECT TO EXISTING MANHOLE
1 EA
$2,100.00
$2,100.00
1
$2,100.00
13
8" SEWER PIPE SELECT BACKFILL
320 LF
$51.00
$16,320.00
320
$16,320.00
Sub -Total of
Previous Unit
$1,166,562.00
$1,166,562.00
Wednesday, March 27, 2024 Page 3 of 5
City Project Numbers 103287
Contract Name COHDC PHASE 1
Contract Limits
Project Type WATER & SEWER
Project Funding
Contract Information Summary
Original Contract Amount
Change Orders
Change Order Number 1
Change Order Number 1
DOE Number 3287
Estimate Number 1
Payment Number 1
For Period Ending 1/31/2024
$2,301,693.20
$2,000.00
$1,490.00
Total Contract Price $2,305,183.20
Total Cost of Work Completed $2,305,183.20
Less % Retained $0.00
Net Earned $2,305,183.20
Earned This Period $2,305,183.20
Retainage This Period $0.00
Less Liquidated Damages
Days @ / Day
LessPavement Deficiency
Less Penalty
Less Previous Payment
Plus Material on Hand Less 15%
Balance Due This Payment
$0.00
$0.00
$0.00
$0.00
$0.00
$2,305,183.20
Wednesday, March 27, 2024 Page 4 of 5
City Project Numbers 103287
Contract Name COHIX PHASE 1
Contract Limits
Project Type WATER & SEWER
Project Funding
Project Manager NA
Inspectors E. DAVILA / W. FAUVER
Contractor BURNSCO CONSTRUCTION, INC.
6331 SOUTHWEST BLVD
FORT WORTH, TX 76132
DOE Number 3287
Estimate Number I
Payment Number I
For Period Ending 1/31/2024
City Secretary Contract Number
Contract Date
2/2/2022
Contract Time
150 WD
Days Charged to Date
369 WD
Contract is .000000
Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
Total Cost of Work Completed $2,305,183.20
Less % Retained $0.00
Net Earned $2,305,183.20
Earned This Period $2,305,183.20
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty
$0.00
Less Previous Payment
$0.00
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$2,305,183.20
Wednesday, March 27, 2024 Page 5 of 5
PROJECT NAME:
CONTRACT:
CFA #
CITY PROJECT #
DOE #
FID #
FILE #
INSPECTOR:
PROJECT MANAGER:
ORIGINAL CONTRACT
EXTRAS TO DATE
CREDITS TO DATE
CONTRACT TO DATE
AMOUNT OF PROP. CHANGE ORDER
REVISED CONTRACT AMOUNT
TOTAL REVISED CONTRACT AMOUNT
PER UNIT
REVISED COST SHARE
TOTAL REVISED CONTRACT
DEVELOPER -AWARDED -PROJECT CHANGE ORDER
Cohix Ph 1
A - Water, Sewer, Drainage
B - Paving
C - Street Lights
21-0144
103287
30114-0200431-103287-EO7685
X-26892
Troy Gardner
Khal Jaafari
CITY PARTICIPATION: Yes
Phone No: 682-215-8720
Phone No: 817-392-7872
CHANGE
ORDER No:
Al, 131, C1
RECEIVED
By Khal Jaafari at 12:11 am, Aug 23, 2022
CONTRACT UNIT
WATER
I SEWER
I PAVING
I DRAINAGE
�evelo STREET LIGHTS
CONTRACT
er
DAYS
Developer Cost City Cost
Developer Cost I City Cost
(Developer Cost City Cost
(Developer Cost I City Cost
Cost City Cost
$1,076,386.89 $60,234.31
$1,165,072.00 I
I $1,393,061.40
I $1,216,275.00 I
$116,848.80
I 225 WD
$1,076,386.89 $60,234.31
$1,165,072.00 I $0.00
$1,393,061.40 $0.00
I $1,216,275.00 I $0.00
$116,848.80 $0.00
I 225 WD
$2,000.00
$1,490.00 I
$114,101.00
I I
$160.20
$1,078,386.89 $60,234.31
$1,166,562.00 I $0.00
$1,507,162.40 $0.00
I $1,216,275.00 I $0.00
$117,009.00 $0.00
I 225 WD
$1,138,621.20
$1,166,562.00
I $1,507,162.40
I $1,216,275.00
$117,009.00
Dev. Cost:
$5,085,395.29
City Cost:
$5,145,629.60
Revised: 10-12-2011 Page 1
You are directed to make the following changes in the contract docum nts
CITY BID ITEM
PAY ITEM #
#
QUANTITY
UNIT
12
9999.0000
1
EA
You are directed to make the following changes in the contract docum nts
CITY BID ITEM
PAY ITEM #
#
QUANTITY
UNIT
5
3331.3101
1
EA
You are directed to make the following changes in the contract docur"gnts
CITY BID ITEM
PAY ITEM #
#
QUANTITY
UNIT
3
3211.0501
-0.40
SY
4
3211.0502
0.40
SY
5
32 11 .0400
0.14
TON
6
3213.0301
0.015
SF
You are directed to make the following changes in the contract documents
CITY BID ITEM
PAY ITEM #
#
QUANTITY
UNIT
2
3211.0502
-0.1
SY
3
3211.0400
0.358
TON
14
3292.0100
3695
SY
15
3291.0100
616
CY
You are directed to make the following changes in the contract docum nts
CITY BID ITEM
PAY ITEM #
#
QUANTITY
UNIT
1
2605.3015
9
LF
2
3441.1410
9
LF
RECEIVED
By Khal Jaafari
at 12:11 am, Aug 23, 2022
UNIT IA: WATER IMPROVEMENTS
ITEM DESCRIPTION
UNIT PRICE
TOTAL
1 1/2" Irrigation Service
$2,000.00
$2,000.00 I
TOTAL
$2,000.00 I
UNIT /I: SANITARY SEWER IMPROVEMENTS
ITEM DESCRIPTION
UNIT PRICE
TOTAL
4" Sewer Service
$1,490.00
$1,490.00 I
TOTAL
$1,490.00 I
UNIT IV., PAVING IMPROVEMENTS
ITEM DESCRIPTION
UNIT PRICE
TOTAL
6" Lime Treatment
$3.10
-$1.24
8" Lime Treatment
$3.65
$1.46 I
Hydrated Lime
$180.00
$25.20 I
4" Conc Sidewalk
$5.75
$0.09 I
TOTAL
$25.51
UNIT V. OFFSITE PAVING IMPROVEMENTS
ITEM DESCRIPTION
UNIT PRICE
TOTAL
8" Lime Treatment
$3.25
-$0.33 I
Hydrated Lime
$180.00
$64.44
Block Sod Placement
$16.38
$60,524.10 I
Topsoil
$86.83
$53,487.28 I
TOTAL
$114,075.50 I
UNIT VI., STREET LIGHTING IMPROVEMENTS
ITEM DESCRIPTION
UNIT PRICE
TOTAL
2" CONDT PVC SCH 80(T)
$13.68
$123.12
NO 10 Insulated Elec Condr
$4.12
$37.08 I
TOTAL
$160.20
REASONS FOR CHANGE ORDER
Added missing bid items, adjusted rounding error in paving quantities, shifted streetlight to avoid driveway.
Revised: 10-12-2011 Page 2
DocuSign Envelope ID: FF7E3867-E92B-491 E-9856-8D797C361 F42
RECOMMENDED:
By: Shield Engineering Group. PLLC
Name -
Title: UI4_0 Pj{9!5dpEw'r
RECEIVED
By Khal Jaafari at 12:12 am, Aug 23, 2022
APPROVED:
DocuSigned by:
By:
(
—F.,—.star tar SUSA Realstate Group, Inc.
Name: 4F0...
Tape: Vice Presi dent
APPROVED:
By: Bu sCq Construction, Inc
—
Name:
Tite:
Vice President
By:
Gitco Contracgng. Inc
Name:
V C �- ✓�`'��—
True:
1fi 9�S l
By:
Independent U01ity Construction, Inc
Name:
(Z� ilk t{�G
Title:
President
Revised: 10-12-2011 Page 3
il I G RY Wooui�,vr nL
TRANSPORTATION AND PUBLIC WORKS
PIPE REPORT FOR:
PROJECT NAME: Cohix Phase 1
CITY PROJECT NUMBER: CPN 103287
WATER
PIPE LAID SIZE TYPE OF PIPE LF
i
FIRE HYDRANTS: '7 VALVES (16" OR LARGER)
PIPE ABANDONED SIZE TYPE OF PIPE LF
N1
DENSITIES:
NEW SERVICES:
f
I Y Pvc
1 a 1 �� �
L6 L, dInti
�.
SEWER
1
PIPE LAID
SIZE
TYPE OF PIPE
LF
i'l 7-4
94`
„may
') 1.1 �•�." •�.��
� i,d tl
� .,•� �s ��. L.� 1',SA C'k_da
+�i � L1 i,,�'
PIPE ABANDONED
SIZE
TYPE OF PIPE
LF
DENSITIES: .A
NEW SERVICES:
TRANSPORTATION AND PUBLIC WORKS
The City of Fort Worth • 1000 Throckmorton Street • Fort Worth, TX 76012-6311
(817) 392 - 7941 • Fax: (817) 392 - 7845
FORTWORTH.
M,
TRANSPORTATION AND PUBLIC WORKS
February 8, 2024
Burnsco Construction INC INC.
6331 Southwest BLVD
Benbrook TX 76132
RE: Acceptance Letter
Project Name: Cohix Phase 1
Project Type: WATER,SEWER Drainage
City Project No.: 104075
To Whom It May Concern:
On February 8, 2024 a final inspection was made on the subject project. There were no punch list items
identified at that time. The final inspection indicates that the work meets the City of Fort Worth
specifications and is therefore accepted by the City. The warranty period will start on February 8, 2024,
which is the date of the final inspection and will extend of two (2) years in accordance with the Contract
Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at Khal
Jaafari. 817-392-7872.
Sincerely,
1CGc�G 9ag�G P. E.
KhaI Jaafari P.E. (Mar 28, 202412:22 CDT)
Khal Jaafari, Project Manager
Cc: William Favour, Inspector
Donald Watson, Inspection Supervisor
Aaron Ybarra, Senior Inspector
Andrew Goodman, Program Manager
Shield Engeering, Consultant
Burnsco Construction INC., Contractor
Forestar, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev. 08/20/19
AFFIDAVIT
STATE OF TEXAS
COUNTY OF TARRANT
Before me, the undersigned authority, a notary public in the state
and county aforesaid, on this day personally appeared Ab Grantges,
Contract Mgr, Of Burnsco Construction, known to me to be a credible
person, who being by ire duly sworn, upon his oath deposed and said;
That all persons, firms, associations, corporations, or other
organizations furnishing labor and/or materials have been paid in full;
That the wage scale established by the City Council in the City of
Fort Worth has been paid in full;
That there are no claims pending for personal injuiy and/or
property damages;
On Contract described as;
Cohix Phase 1 - Water, Sanitary Sewer and Storm Drain
BY qAr/ �antgesocontract Manager
Subscribed and sworn before me on this date 20th of February, 2024.
Notary Public
Tarrant County, Texas ,,.»V KASSAND9A CANALES
_ 0 L�Notary Public, State of Texas
moo:' .-
Comm, Expires 01-23.2027
'•'Fof�+ Notary ID 134158873
CONSENT OF
SURETY COMPANY
TO FINAL PAYMENT
Conforms with the American Institute of
Architects, AIA Document G707
OWNER
❑
ARCHITECT
❑
CONTRACTOR
❑
SURETY
❑
OTHER
Bond No 022232664
PROJECT:
(name, addresS)Cohix Phase 1 (Terra Trace) - Water, Sanitary Sewer and Drainage
TO (Owner)
Fort Worth TX
FORESTAR (USA) REAL ESTATE GROUP, INC. AND ARCHITECT'S PROJECT NO:
CITY OF FORT WORTH
CONTRACT FOR:
14755 Preston Road, Suite 130 Cohix Phase 1 (Terra Trace) - Water, Sanitary Sewer and Drainage
Improvements
Dallas TX 75254 CONTRACT DATE:
CONTRACTOR: BURNSCO CONSTRUCTION, INC.
In accordance with the provisions of the Contract between the Owner and the Contractor as indicated above, the
(here insert name and address of Surety Company)
LIBERTY MUTUAL INSURANCE COMPANY
175 Berkeley Street
Boston MA 02116 , SURETY COMPANY
on bond of (here insert name and address of Contractor)
BURNSCO CONSTRUCTION, INC.
6331 Southwest Boulevard
Benbrook TX 76132
,CONTRACTOR,
hereby approves of the final payment to the Contractor, and agrees that final payment to the Contractor shall not relieve
the Surety Company of any of its obligations to (here insert name and address of Owner)
FORESTAR (USA) REAL ESTATE GROUP, INC. AND CITY OF FORT WORTH
14755 Preston Road, Suite 130
Dallas TX 75254 , OWNER,
as set forth in the said Surety Company's bond.
IN WITNESS, WHEREOF,
the Surety Company has hereunto set its hand this
Attest: ", r'
.�%
(Seal):
20th day of February, 2024
LIBERTY MUTUAL INSURANCE COMPANY
Surety Company N,jjb,;�
Signature of Authorized Representative
Soohinie Hunter Attorney -in -Fact
Title
NOTE: This form is to be used as a companion document to AIA DOCUMENT G706, CONTRACTOR'S AFFIDAVIT OF PAYMENT OF DEBTS AND CLAIMS,
Current Edition
ONE PAGE
This Power of Attorney limits the acts of those named herein, and they have no authority to
bind the Company except in the manner and to the extent herein stated.
Liberty Liberty Mutual Insurance Company
Mutual The Ohio Casualty Insurance Company Certificate No: 8205467-022020
SURETY West American Insurance Company
POWER OF ATTORNEY
KNOWN ALL PERSONS BY THESE PRESENTS: That The Ohio Casualty Insurance Company is a corporation duly organized under the laws of the State of New Hampshire, that
Liberty Mutual Insurance Company is a corporation duly organized under the laws of the State of Massachusetts, and West American Insurance Company is a corporation duly organized
under the laws of the State of Indiana (herein collectively called the "Companies"), pursuant to and by authority herein set forth, does hereby name, constitute and appoint, Don E.
Cornell, Joshua Saunders; Kelly A. Westbrook; Mikaela Peppers; Ricardo J. Reyna; Robbi Morales; Sophinie Hunter; Tina McEwan; Tone, Petranek
all of the city of Dallas state of TX each individually if there be more than one named, its true and lawful attorney -in -fact to make,
execute, seal, acknowledge and deliver, for and on its behalf as surety and as its act and deed, any and all undertakings, bonds, recognizances and other surety obligations, in pursuance
of these presents and shall be as binding upon the Companies as if they have been duly signed by the president and attested by the secretary of the Companies in their own proper
persons.
IN WITNESS WHEREOF, this Power of Attorney has been subscribed by an authorized officer or official of the Companies and the corporate seals of the Companies have been affixed
thereto this 23rd day of April 2021
Liberty Mutual Insurance Company
Ns The Ohio
asualty Insurance Company
g/?JPoo>uo R9n sogcaPagWest Insurance Comany
3 Fo u� 3 Fo m W 3 Fo
1912 o y1919�o s 1991 0
/j to 0
d�9sSACHUs��.da yp HAMPSdD� '!s vNDIANP da GCr �nCi1�l r !` 'r_ U
y.
David M. Carey, Assistant Secretary Cr
m State of PENNSYLVANIA ss
m County of MONTGOMERY o E
- On this 23rd day of April 2021 before me personally appeared David M. Carey, who acknowledged himself to be the Assistant Secretary of Liberty Mutual Insurance
o > Company, The Ohio Casualty Company, and West American Insurance Company, and that he, as such, being authorized so to do, execute the foregoing instrument for the purposes
alatherein contained bsigning on behalf thecorporationsbhimself dauthorized
i y gg ehaof y mseas a duly auorzeofficer. >
IN WITNESS WHEREOF, I have hereunto subscribed my name and affixed my notarial seal at King of Prussia, Pennsylvania, on the day and year first above written. ; =
07 N 0-0
2
L '°� �F` Commonwealth of Penns Ivania - Nota Seal
.E�t1N�<.n;;� Teresa pastels, Not Public ry
O N 1F' Montgomery County ler
�, ,,^-' �{/;//I ` E
O +-� My commission expires March 28, 2025 By.,(.,tcpc..� �.t�.� O N
Paz Commission number 1126044
Y4.`+�C Member, Pennsylvania Association of Notaries sa Pastella, Notary Public Q O
Co
a? This Power of Attorney is made and executed pursuant to and by authority of the following By-laws and Authorizations of The Ohio Casualty Insurance Company, Liberty Mutual 3
E •� Insurance Company, and West American Insurance Company which resolutions are now in full force and effect reading as follows: a M
00
ARTICLE IV- OFFICERS: Section 12. Power of Attorney. o 0
Any officer or other official of the Corporation authorized for that purpose in writing by the Chairman or the President, and subject to such limitation as the Chairman or the -a
President may prescribe, shall appoint such attorneys -in -fact, as may be necessary to act in behalf of the Corporation to make, execute, seal, acknowledge and deliver as surety C°
any and all undertakings, bonds, recognizances and other surety obligations. Such attorneys -in -fact, subject to the limitations set forth in their respective powers of attorney, shall aMo
have full power to bind the Corporation by their signature and execution of any such instruments and to attach thereto the seal of the Corporation. When so executed, such o m
Zinstruments shall be as binding as if signed by the President and attested to by the Secretary. Any power or authority granted to any representative or attorney -in -fact under the f m
provisions of this article may be revoked at any time by the Board, the Chairman, the President or by the officer or officers granting such power or authority. ti ?
CL
ARTICLE XIII - Execution of Contracts: Section 5. Surety Bonds and Undertakings.
Any officer of the Company authorized for that purpose in writing by the chairman or the president, and subject to such limitations as the chairman or the president may prescribe,
shall appoint such attorneys -in -fact, as may be necessary to act in behalf of the Company to make, execute, seal, acknowledge and deliver as surety any and all undertakings,
bonds, recognizances and other surety obligations. Such attorneys -in -fact subject to the limitations set forth in their respective powers of attorney, shall have full power to bind the
Company by their signature and execution of any such instruments and to attach thereto the seal of the Company. When so executed such instruments shall be as binding as if
signed by the president and attested by the secretary.
Certificate of Designation - The President of the Company, acting pursuant to the Bylaws of the Company, authorizes David M. Carey, Assistant Secretary to appoint such attorneys -in -
fact as may be necessary to act on behalf of the Company to make, execute, seal, acknowledge and deliver as surety any and all undertakings, bonds, recognizances and other surety
obligations.
Authorization - By unanimous consent of the Company's Board of Directors, the Company consents that facsimile or mechanically reproduced signature of any assistant secretary of the
Company, wherever appearing upon a certified copy of any power of attorney issued by the Company in connection with surety bonds, shall be valid and binding upon the Company with
the same force and effect as though manually affixed.
I, Renee C. Llewellyn, the undersigned, Assistant Secretary, The Ohio Casualty Insurance Company, Liberty Mutual Insurance Company, and West American Insurance Company do
hereby certify that the original power of attorney of which the foregoing is a full, true and correct copy of the Power of Attorney executed by said Companies, is in full force and effect and
has not been revoked.
IN TESTIMONY WHEREOF, I have hereunto set my hand and affixed the seals of said Companies this 20th day of February 2023
P� %Nsu,. P'ZV INS& a %Nsuoi
J b'4p0.P0/�TOy�tn d0Co- O gTQ'9y� \VP=ovkpo gr�y0
o
1912 0 oy1919�o Q 1991 0
SO �NA MPS�`� a Y vNDIANP D By.
Renee C. Llewellyn, Assistant Secretary
,t
LMS-12873 LMIC OCIC WAIC Multi Co 02/21
TEXAS
IMPORTANT NOTICE
To obtain information or make a complaint:
You may call toll -free for information or to
make a complaint at
1-877-751-2640
You may also write to:
2200 Renaissance Blvd., Ste. 400
King of Prussia, PA 19406-2755
You may contact the Texas Department of
Insurance to obtain information on companies,
coverages, rights or complaints at
1-800-252-3439
You may write the Texas Department of Insurance
Consumer Protection (I I I-1A)
P. O. Box 149091
Austin, TX 78714-9091
FAX: (512) 490-1007
Web: htta://www.tdi.texas.V.ov
E-mail: ConsumerProtection4,tdi.texas.gov
PREMIUM OR CLAIM DISPUTES:
Should you have a dispute concerning your
premium or about a claim you should first
contact the agent or call 1-800-843-6446.
If the dispute is not resolved, you may contact the
Texas Department of Insurance.
ATTACH THIS NOTICE TO YOUR
POLICY:
This notice is for information only and does not
become a part or condition of the attached
document.
NP 70 68 09 01
LMS-15292 10/15
TEXAS
AVISO IMPORTANTE
Para obtener informacion o para someter una
queja:
Usted puede llamar al numero de telefono gratis
para informacion o para someter una queja al
1-877-751-2640
Usted tambien puede escribir a:
2200 Renaissance Blvd., Ste. 400
King of Prussia, PA 19406-2755
Puede comunicarse con el Departamento de
Seguros de Texas para obtener information
acerca de companies, coberturas, derechos o
quejas al
1-800-252-3439
Puede escribir al Departamento de Seguros
de Texas Consumer Protection (I I I A A)
P. O. Box 149091
Austin, TX 78714-9091
FAX # (512) 490-1007
Web: htta://www.tdi.texas.aov
E-mail: ConsumerProtection�tdi.texas.gov
DISPUTAS SOBRE PRIMAS O RECLAMOS:
Si tiena una disputa concerniente a su prima o a
un reclamo, debe comunicarse con el agente o
primero. Si no se resuelve la disputa, puede
entonces comunicarse con el departamento (TDI)
UNA ESTE AVISO A SU POLIZA:
Este aviso es solo para proposito de informacion
y no se convierte en parte o condicion del
documento adjunto.