HomeMy WebLinkAboutContract 59004-PM1CSC No. 59004-PMI PROJECT MANUAL FOR THE CONSTRUCTION OF WATER AND SANITARY SEWER IMPROVEMENTS TO SERVE WICHITA INDUSTRIAL IPRC Record No. 22-0104 City Project No. 104140 FID No.30114-0200431-104140-EO7685 X File No. 27384 Mattie Parker David Cooke Mayor City Manager Christopher P. Harder, P.E. Director, Water Department Lauren Prieur, P.E. Director, Transportation and Public Works Department Prepared for The City of Fort Worth APRIL 2024 RUNAWAY DUNAWAY ASSOCIATES, L.P. 550 Bailey Avenue, Suite 400 Ft. Worth, TX 76107 Office: 817-335-1121 / Fax: 817-429-1370 TX REG. F-1114 www.dunaway.com DA Project#B006085.002 OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 1 of 5 SECTION 00 00 10 TABLE OF CONTENTS DEVELOPER AWARDED PROJECTS Division 00 - General Conditions Last Revised 00 11 13 irviia4io to Bidders 03/20/2020 0021 13 lastFuetions to Bidde :s 03/20/2020 00 41 00 Bid Fe 04/02/2014 00 42 43 Proposal Form Unit Price 05/22/2019 0043 13 Bid Ben 04/02/2014 0045 11 Bidders Pf:eq, alifie tief's 04/02/2014 0045 12 Prequalification Statement 09/01/2015 0045 13 Bidde . Pfegtta1 i;,,a4ien kWiaz.,ian 03/09/2020 00 45 26 Contractor Compliance with Workers' Compensation Law 04/02/2014 00 45 40 r, iner-;ty Business E tefpr- se Goa 08/21/2018 00 52 43 Agreement 06/16/2016 00 61 25 Certificate of Insurance 07/01/2011 00 62 13 Performance Bond 01/31/2012 00 62 14 Payment Bond 01/31/2012 00 62 19 Maintenance Bond 01/31/2012 00 72 00 General Conditions 11/15/2017 00 73 00 r"„„leme tary Conditions 07/01/2011 0073 10 Standard City Conditions of the Construction Contract for Developer 01/10/2013 Awarded Projects Division 01- General Requirements Last Revised 01 1100 Summary of Work 12/20/2012 01 25 00 Substitution Procedures 08/30/2013 01 31 19 Preconstruction Meeting 08/30/2013 013120 D-ejeetMeet;ngs 07/01/2011 01 32 33 Preconstruction Video 08/30/2013 01 33 00 Submittals 08/30/2013 01 35 13 Special Project Procedures 08/30/2013 01 45 23 Testing and Inspection Services 03/20/2020 01 50 00 Temporary Facilities and Controls 07/01/2011 01 5526 Street Use Permit and Modifications to Traffic Control 07/01/2011 01 57 13 Storm Water Pollution Prevention Plan 07/01/2011 01 60 00 Product Requirements 03/20/2020 01 66 00 Product Storage and Handling Requirements 04/07/2014 01 70 00 04/07/2014 01 71 23 Geastfitetiorl E"teaking 04/07/2014 01 74 23 Cleaning 04/07/2014 0177 19 Closeout Requirements 04/07/2014 01 78 23 Operation and Maintenance Data 04/07/2014 01 78 39 Project Record Documents 04/07/2014 City of Fort Worth Water Department Standard Product List 11/08/2021 CITY OF FORT WORTH Water & Sanitary Sewer Wichita Industrial STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104140 Revised March 20, 2020 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 2 of 5 Technical Specifications which have been modified by the Engineer specifically for this Project; hard copies are included in the Project's Contract Documents NONE Technical Specifications listed below are included for this Project by reference and can be viewed/downloaded from the City's website at: htti):Hfortworthtexas.aov/tvw/contractors/ or httus:Hauus.fortworthtexas.2ov/Proi ectResources/ Division 02 - Existing Conditions Last Revised 0241 13 Seleetio U.'Si Jaen 12/20/2012 0241 14 Utility Removal/Abandonment 12/20/2012 0241 15 Paving Removal 02/02/2016 Division 03 - Concrete 03 30 00 Cast -In -Place Concrete 12/20/2012 0334 13 Controlled Low Strength Material (CLSM) 12/20/2012 0334 16 C nef:ete Base Ma4er-;^i for- T -efie Repair- 12/20/2012 03 80 00 raedifiea4i as t E*istiag Genefete ctruetffes 12/20/2012 Division 26 - Electrical 26 05 00 room"" WedE Results f r Eleetr4eal 11/22/2013 2605 10 Demolition f Y EleetfiM Systems 12/20/2012 26 05 33 Raee a-ys a -a Bees for- B'eetfie ' cyst 12/20/2012 26 05 43 Undergr-eun a Dtiets a -a Raee a-ys f f Electriaal E"iy,� 07/01/2011 26 05 50 Eo.m,,'mumi^^tions Multi Duet Conduit 02/26/2016 Division 31- Earthwork 31 1000 Site r� 12/20/2012 3123 16 Unclassified Excavation 01/28/2013 31 23 23 Borrow 01/28/2013 31 24 00 Embankments 01/28/2013 31 25 00 Erosion and Sediment Control 12/20/2012 31 36 00 Gabions 12/20/2012 31 37 00 Riprap 12/20/2012 Division 32 - Exterior Improvements 3201 17 n^... a-ne"t Asphalt t Pa-vi g Repair- 12/20/2012 3201 18 To.. pef:^ ... A ^. hak Pa-yi g n epai . 12/20/2012 3201 29 Conefete Paving Repa , 12/20/2012 32 1123 Fle* ble Base Gets see- 12/20/2012 32 1129 Lime Treated Base C.Aeu see 12/20/2012 32 11 33 GamoRt Treated Base G ^^^ 12/20/2012 32 1137 Liquid ,;a Treated Seil ctabil ,^, 08/21/2015 32 1216 A spha t Paying 12/20/2012 32 1273 A*halt A-4- n r aek Sea1af t^ 12/20/2012 CITY OF FORT WORTH Water & Sanitary Sewer Wichita Industrial STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104140 Revised March 20, 2020 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 3 of 5 32 13 13 r'^^^r^te Paving 12/20/2012 32 1320 C fef:ete Sidewalks, Driveways and BafFieF Fro^ Ramps 06/05/2018 32 1373 Genefete Pa-vi g joint C'o.,l 12/20/2012 32 1416 B-63k- Urtitpa-vifig 12/20/2012 32 16 13 C f^.^te ruFb and QdReFS ^"a Valley r„tteFS 10/05/2016 32 1723 Pa-ve e t Mar4i figs 11/22/2013 32 1725 CurbAdozz lhi.:skr,g 11/04/2013 3231 13 C!nr. Forzoas ^ 12/20/2012 32 31 26 W -e Fenees and rates 12/20/2012 32 31 29 Weed Fences and rates 12/20/2012 3232 13 Cast i Plate C f^.ote D:fn,.-�ing `ems 06/05/2018 3291 19 Topsoil Placement and Finishing of Parkways 12/20/2012 32 92 13 Hydro -Mulching, Seeding, and Sodding 12/20/2012 32 93 43 Trees 3 arubc 12/20/2012 Division 33 - Utilities 33 01 30 Sewer and Manhole Testing 12/20/2012 33 01 31 Closed Circuit Television (CCTV) Inspection 03/03/2016 3303 10 Bypass Pumping of Existing Sewer Systems 12/20/2012 3304 10 r,,;rt Beading ^"a Qeet iea lsela4ie 12/20/2012 33 04 11 Ceffesion Cetitfel -rest Stetiefis 12/20/2012 33 04 12 r agaesitff Anode r^thedie Pfeteetie S ysteffl 12/20/2012 33 04 30 T^m....,-ary Water- Sefviees 07/01/2011 33 04 40 Cleaning and Acceptance Testing of Water Mains 02/06/2013 33 04 50 Cleaning of Sewer Mains 12/20/2012 3305 10 Utility Trench Excavation, Embedment, and Backfill 12/12/2016 3305 12 Water Line Lowering 12/20/2012 3305 13 Frame, Cover and Grade Rings — Cast Iron 01/22/2016 3305 13.10 Frame, Coyef:�'a* Credo Ri:�z z 01/22/2016 33 OS 14 Adjusting Tv kil t^Valve Boxes, Sti 12/20/2012 l� aFAieles, and detl�'cste Gfade 3305 16 Genefete W tef Vaults 12/20/2012 33 05 17 Concrete Collars 12/20/2012 33 05 20 Auger Boring 12/20/2012 33 05 21 Turr-rjl l.inar- Pla4e 12/20/2012 33 05 22 Steel Casing Pipe 12/20/2012 33 05 23 Hand Tu ewliMg 12/20/2012 33 05 24 Installation of Carrier Pipe in Casing or Tunnel Liner Plate 06/19/2013 33 05 26 Utility Markers/Locators 12/20/2012 33 05 30 Location of Existing Utilities 12/20/2012 33 1105 Bolts, Nuts, and Gaskets 12/20/2012 33 11 10 Ductile Iron Pipe 12/20/2012 33 11 11 Ductile Iron Fittings 12/20/2012 33 11 12 Polyvinyl Chloride (PVC) Pressure Pipe 11/16/2018 33 11 13 Eexefet3 Pr000uro Piro, Bar Wfapped, Steei Cyli def Type 12/20/2012 33 11 14 Buried Steel Pipe and Fittings 12/20/2012 33 1210 Water Services 1-inch to 2-inch 02/14/2017 33 1211 r ^ e Wa4e. mote,.^ 12/20/2012 33 1220 Resilient Seated Gate Valve 12/20/2012 CITY OF FORT WORTH Water & Sanitary Sewer Wichita Industrial STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104140 Revised March 20, 2020 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 4 of 5 33 1221 AWWA Rubber -Seated Butterfly Valves 12/20/2012 33 1225 Connection to Existing Water Mains 02/06/2013 33 1230 r,..,..bin io it v i.,o A0ooniWks for- Potable Water- Syste , � 12/20/2012 33 1240 Fire Hydrants 01/03/2014 33 1250 Water Sample Stations 12/20/2012 33 1260 Sta-nd ra Blow eff Valve ve n sseff b!) 06/19/2013 3331 12 Cur-ed in Dlaee Pipe (CIDDI 12/20/2012 3331 13 Fibefg1wo P_ocfer-ee Pipe for- r -a-v t EG.Aita? -Sewer$ 12/20/2012 3331 15 High Deal t-y D l.,ethylene (HDPE4 Pipe fe f Sanitary Sewef 12/20/2012 33 31 20 Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe 06/19/2013 33 31 21 Polyvinyl Chlef:ide Closed Profile Gr-avity Sa*iiafy Sewef 12/20/2012 (PVC) Pipe 33 31 22 ra~' Par F)i* li&rng 12/20/2012 33 31 23 Safiit y Sewe, T' pj Bally cement 12/20/2012 33 31 50 Sanitary Sewer Service Connections and Service Line 04/26/2013 33 31 70 Combi xida if: Valve f3F BGnitwy Sewer Fef:ee Mains 12/20/2012 33 39 10 Cast -in -Place Concrete Manholes 12/20/2012 33 39 20 Precast Concrete Manholes 12/20/2012 33 39 30 F-ibcrglxr_ Manholes 12/20/2012 33 39 40 Wastewater- n eeess Chaff bee: �W n C4 12/20/2012 33 39 60 Epoxy Liners for Sanitary Sewer Structures 12/20/2012 3341 10 Reinforced Concrete Storm Sewer Pipe/Culverts 07/01/2011 3341 11 High Density Polyethylene (HDPE4 Dire for- St.-,.- 12/20/2012 3341 12 Reinf reed Pelyet lene E) Dina 11/13/2015 33 46 00 e„l� 12/20/2012 33 46 01 warm Diuin-. 07/01/2011 33 46 02 T r-,-,mk ��� 07/01/2011 33 49 10 Ccol, k: Plyze Manholes and I„n f e Be*es 12/20/2012 33 49 20 Curl' and T'"^" blots 12/20/2012 33 49 40 Stor. DId-nsa^e 14ead ^ells and Wingwells 07/01/2011 Division 34 - Transportation 3441 10 'T'r^rfi^ Sigga is 10/12/2015 3441 10.01 ARaehmef4 ACptreller Cabinet 12/18/2015 3441 10.02 Attaehmeat B C-eatfallzr fro men 02/2012 3441 10.03 Attaehment G Se€twafespeei£eatien 01/2012 3441 11 Temper^Y" Tr-affie Signals 11/22/2013 3441 13 Removing ' 'T r-aff e Signals 12/20/2012 3441 15 Reetangulx Ram d FlwJhxg Been 11/22/2013 3441 16 gedoo*�aA I-I;brid Signal 11/22/2013 34 41 20 Read Illurncyatia Assemblies 12/20/2012 34 41 20.01 ArtolVJ. 06/15/2015 34 41 20.02 Free ay LED Read ' 06/15/2015 34 41 20.03 Residential LED Readw" ' Dan. irswi-es 06/15/2015 34 41 30 Aluminum E"igns 11/12/2013 34 41 50 Single e r lode Fiber- artie r 1.1 0 02/26/2016 3471 13 Traffic Control 11/22/2013 CITY OF FORT WORTH Water & Sanitary Sewer Wichita Industrial STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS CPN 104140 Revised March 20, 2020 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Appendix Page 5 of 5 FG4,91 Availulit-y' ,.P GG 4.02 Fi.-./arr e . a a Physie i r n a; iefi Fib-406 IhzGrI etis Enyi efff ,en4a Condition , 4 Site GG 6.07 W GG-6-M f\ar iitvax.a r T 1 1`T�ac�atian GR-01 60 00 Product Requirements END OF SECTION CITY OF FORT WORTH Water & Sanitary Sewer Wichita Industrial STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 104140 Revised March 20, 2020 UNIT PRICE BID Bidlist Item No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 Wichita Industrial - CPN: 104140 SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM Project Item Infonuation Description Specification Section Unit of No. Measure UNIT I: WATER IMPROVEMEN—S 3311.0441 12" Water Pipe 3311 12 LF 3311.0241 8" Water Pipe 3311 12 LF 3311.0451 12" DIP Water 3311 10 LF 9999.0001 24" Steel Encasement 99 99 99 LF 3312.0117 Connection to Ex. 4"-12" Water Main 33 12 25 EA 3312.3005 12" Gate Valve 33 12 20 EA 3312.3003 8" Gate Valve 33 12 20 EA 3312.0001 Fire Hydrant 33 12 20 EA 3311.0001 Ductile Iron Water Fittings w/ Restraint 3311 11 TON 0241.1118 4" - 12" Pressure Plug 0241 14 EA 3305.0109 Trench Safety 34 05 10 LF 3312.2203 2" Water Service (Domestic) 33 12 10 EA 3312.2203 2" Water Service (Irrigation) 33 12 10 EA 3312.4211 24"X12" Tapping Sleeve and Valve 33 12 25 EA 3305.0005 12" Waterline Lowering 33 05 12 EA 9999.0002 Rip Rap 99 99 99 SF 3305.0203 Imported Embed ment/Backfill, CLSM 33 05 10 CY 00 42 43 DAP - BID PROPOSAL Page 1 of4 Bidder's Application Bid Quantity 1613 105 175 175 1 4 3 3 2.25 4 1893 3 3 1 2 4200 78 TOTAL UNIT I: WATER IMPROVEMENTS Bidder's Proposal Unit Price I Bid Value $110.00 $78.00 $200.00 $300.00 $7,500.00 $4,150.00 $2,150.00 $4,500.00 $12,500.00 $1, 000.00 $1.50 $5,000.00 $3,000.00 $33,500.00 $6,600.00 $1.25 $100.00 1 $177,430.00 1 $8,190.00 1 $35,000.00 1 $52,500.00 1 $7,500.00 1 $16,600.00 1 $6,450.00 1 $13,500.00 1 $28,125.00 1 $4,000.00 1 $2,839.50 1 $15,000.00 1 $9,000.00 1 $33,500.00 1 $13,200.00 1 $5,250.00 1 $7,800.00 1 $435,884.50 1 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS Form Version May 22, 2019 Copy of 00 42 43_Bid Proposal_DAP - 2022.11.16 UNIT PRICE BID Bidlist Item No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 Wichita Industrial - CPN: 104140 SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM Project Item Infonuation Description I Specification Section Unit of No. Measure UNIT II: SANITARY SEWER IMPROVEMENTS 3339.1001 4' Sewer Manhole 0241 14 EA 3339.1101 5' Sewer Manhole 33 39 10 EA 9999.0003 5' Sewer Manhole w/ Watertight Gaskets & 99 99 99 EA Covers 9999.0004 4' Sewer Manhole w/ Watertight Gaskets & 99 99 99 EA Covers 3331.4115 8" Sewer Pipe 3311 10 LF 3331.4225 18" Sewer Pipe 3311 10 LF 3331.4229 18" DIP Sewer 3311 10 LF 3331.4226 18" Sewer Pipe, CSS Backfill 3311 10 LF 3305.0109 Trench Safety 33 05 10 LF 3339.0001 Epoxy Manhole Liner 33 39 60 VF 3301.0002 Post -CCTV Inspection 3301 31 LF 3301.0101 Manhole Vacuum Testing 3301 30 EA 3331.5756 18" Sewer Pipe, CLSM Backfill 3311 10 LF 9999.0004 Rip Rap 99 99 99 SF 3331.4227 18" Sewer Pipe, Select Backfill 3311 10 LF 0241.2015 Remove 12" Sewer Line 0241 14 LF 0241.2201 Remove 4' Sewer Manhole 0241 14 EA 9999.0005 36" Steel Encasement 99 99 99 LF 00 42 43 DAP - BID PROPOSAL Page 2 of 4 Bidder's Application Bidder's Proposal Bid Unit Price Bid Value Quantity 3 $9,250.00 6 $11,500.00 1 $17,000.00 1 $15,700.00 355 $100.00 1587 $200.00 443 $440.00 20 $380.00 1942 $1.50 130 $15.00 1942 $3.00 1942 $2.00 280 $195.00 12720 $1.25 120 $80.00 1393 $30.00 5 $1,250.00 290 $478.00 TOTAL UNIT II: SANITARY SEWER IMPROVEMENTS 1 $27,750.00 1 $69,000.00 1 $17,000.00 $15,700.001 $35,500.00 1 $317,400.00 1 $194,920.00 1 $7,600.00 1 $2,913.00 1 $1,950.00 1 $5,826.00 1 $3,884.00 1 $54,600.00 1 $15,900.00 1 $9,600.00 1 $41,790.001 $6,250.00 1 $138,620.00 1 $966,203.00 1 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS Form Version May 22, 2019 Copy of 00 42 43_13id Proposal_DAP - 2022.11.16 Wichita Industrial - CPN: 104140 SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM UNIT PRICE BID 00 42 43 DAP - BID PROPOSAL Page 3 of 4 Bidder's Application Project Item Information Bidder's Proposal Bidlist Item I Specification Section Unit of Bid Description Unit Price Bid Value No. No. Measure Quantity Bid Summary UNIT I: WATER IMPROVEMENTS $435,884.501 UNIT II: SANITARY SEWER IMPROVEMENTS $966,203.001 1 Total Construction Bid $1,402,087.50 1 This Bid is submitted by the entity named below: BIDDER: Bratjen Construction Company 1701 E Lamar Blvd. Suite 290 Arlington, TX 76006 Contractor agrees to complete WORK for FINAL ACCEPTANCE within CONTRACT commences to run as provided in the General Conditions. BY: Benjamin Bratcher Ben Bratcher TITLE: CEO DATE: 11 /16/2022 END OF SECTION 1 180 working days after the date when the CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS Form Version May 22, 2019 Copy of 00 42 43_Bid Proposal DAP - 2022.11.16 0045 12 DAP PREQUALIFICATION STATEMENT Page 1 of 1 SECTION 00 45 12 DAP — PREQUALIFICATION STATEMENT Each Bidder is required to complete the information below by identifying the prequalified contractors and/or subcontractors whom they intend to utilize for the major work type(s) listed. In the "Maior Work Tvpe" box provide the complete maior work tvpe and actual description as _provided by the Water Department for water and sewer and TPW for paving. Major Work Type Water New Development, Rehabilitation, and Redevelopment Open Cut (42" and Under) Wastewater New Development, Rehabilitation, and Redevelopment Open Cut (42" and Under) Contractor/Subcontractor Company Name Venus Construction Company Venus Construction Company Prequalification Expiration Date 5/31/2024 5/31/2024 The undersigned hereby certifies that the contractors and/or subcontractors described in the table above are currently prequalified for the work types listed. BIDDER: Bratjen Construction Company BY 1701 E Lamar Blvd., Suite 290 Arlington, TX 76006 TIT CEO DA'i t: 2/16/2024 END OF SECTION CITY OF FORT WORTH Water & Sanitary Sewer to Serve Wichita Industrial STANDARD CONSTRUCTION PREQUALIFICATION STATEMENT— DEVELOPER AWARDED PROJECTS 0045 12_Prequalification Statement 2015_DAP.docx Form Version September 1, 2015 CPN 104140 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 00 45 26 - 1 CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW Page 1 of 1 SECTION 00 45 26 CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW Pursuant to Texas Labor Code Section 406.096(a), as amended, Contractor certifies that it provides worker's compensation insurance coverage for all of its employees employed on City Project No.104140 Contractor further certifies that, pursuant to Texas Labor Code, Section 406.096(b), as amended, it will provide to City its subcontractor's certificates of compliance with worker's compensation coverage. CONTRACTOR: Bratien Construction Company 1701 E Lamar Blvd., Suite 290 Address Arlington. TX 76006 City/State/Zip THE STATE OF TEXAS § COUNTY OF TARRANT § By: Benj - -- - ^ ^--�-�-- Signature: Title: CE( (Please Print) BEFORE ME, the undersigned authority, on this day personally appeared Beniamin C. Bratcher , known to me to be the person whose name is subscribed to the foregoing instrument, and acknowledged to me that he/she executed the same as the act and deed of Bratien Construction Comaanv for the purposes and consideration therein expressed and in the capacity therein stated. GIVEN UNDER MY HAND AND SEAL OF OFFICE this 16th day of February , 2024 MELONIE LOWRIE� , ^ ` ,s Notary Public '•'�• STATE OF TEXAS 1 Notary Public in and for the State of Texas iD# 13063723-9 My Comm. Exo. Apr. 26, 2024 1 END OF SECTION CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised April 2, 2014 Water & Sanitary Sewer to Serve Wichita Industrial CPN.•104140 1 SECTION 00 52 43 005243-1 Developer Awarded Project Agreement Page 1 of 4 2 AGREEMENT 3 THIS AGREEMENT, authorized on 4/1 /2024 is made by and between the Developer, 4 PRIH/HLCI WICHITA STREET. L.P. authorized to do business in Texas ("Developer") , and 5 SRATJEN CONSTRUCTION COMPANY. authorized to do business in Texas, acting by and 6 through its duly authorized representative, ("Contractor"). 7 Developer and Contractor, in consideration of the mutual covenants hereinafter set forth, agree as 8 follows: 9 Article I. WORK 10 Contractor shall complete all Work as specified or indicated in the Contract Documents for the 11 Project identified herein. 12 Article 2. PROJECT 13 The project for which the Work under the Contract Documents may be the whole or only a part is 14 generally described as follows: 15 WICHITA INDUSTRIAL 16 CITY PROJECT NO. I04140 17 Article 3. CONTRACT TIME 18 3.1 Time is of the essence. 19 All titne limits for Milestones, if any, and Final Acceptance as stated in the Contract 20 Documents are of the essence to this Contract. 21 3.2 Final Acceptance. 22 The Work will be complete for Final Acceptance within 180 working days after the date 23 when the Contract Time commences to run as provided in Paragraph 12.04 of the Standard 24 City Conditions of the Construction Contract for Developer Awarded Projects. 25 3.3 Liquidated damages 26 Contractor recognizes that time is of the essence of this Agreement and that Developer 27 will suffer financial loss if the Work is not completed within the times specified in 28 Paragraph 3.2 above, plus any extension thereof allowed in accordance with Article 10 of 29 the Standard City Conditions of the Construction Contract for Developer Awarded 30 Projects. The Contractor also recognizes the delays, expense and difficulties involved in 31 proving in a legal proceeding the actual loss suffered by the Developer if the Work is not 32 completed on time. Accordingly, instead of requiring any such proof , Contractor agrees 33 that as liquidated damages for delay (but not as a penalty), Contractor shall pay 34 Developer ZERO Dollars $0.00 for each day that expires after the time specified in 35 Paragraph 3.2 for Final Acceptance until the City issues the Final Letter of Acceptance. CITY OF FORT WORTH Water & Sanitary Sewer to Serve Wichita Industrial STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN: 104140 Revised June 16, 2016 005243 -2 Developer Awarded Project Agreement Page 2 of 4 36 Article 4. CONTRACT PRICE 37 Developer agrees to pay Contractor for performance of the Work in accordance with the Contract 38 Documents an amount in current funds of ONE MILLION FOUR HUNDRED TWO 39 THOUASAND EIGHTY-SEVEN DOLLARS AND FIFTY CENTS ($1.402.087.50). 40 Article 5. CONTRACT DOCUMENTS 41 5.1 CONTENTS: 42 A. The Contract Documents which comprise the entire agreement between Developer and 43 Contractor concerning the Work consist of the following: 44 1. This Agreement. 45 2. Attachments to this Agreement: 46 a. Bid Form (As provided by Developer) 47 1) Proposal Form (DAP Version) 48 2) Prequalification Statement 49 3) State and Federal documents (project specific) 50 b. Insurance ACORD Form(s) 51 c. Payment Bond (DAP Version) 52 d. Performance Bond (DAP Version) 53 e. Maintenance Bond (DAP Version) 54 f. Power of Attorney for the Bonds 55 g. Worker's Compensation Affidavit 56 h. MBE and/or SBE Commitment Form (If required) 57 3. Standard City General Conditions of the Construction Contract for Developer 58 Awarded Projects. 59 4. Supplementary Conditions. 60 5. Specifications specifically made a part of the Contract Documents by attachment 61 or, if not attached, as incorporated by reference and described in the Table of 62 Contents of the Project's Contract Documents. 63 6. Drawings. 64 7. Addenda. 65 8. Documentation submitted by Contractor prior to Notice of Award. 66 9. The following which may be delivered or issued after the Effective Date of the 67 Agreement and, if issued, become an incorporated part of the Contract Documents: 68 a. Notice to Proceed. 69 b. Field Orders. 70 c. Change Orders. 71 d. Letter of Final Acceptance. 72 73 CITY OF FORT WORTH Water & SeaiWy Sewer to Serve Wichita Industrial STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS— DEVELOPER AWARDED PROJECTS CPN: 104140 Revised Jme 16, 2016 005243-3 Developer Awarded Project Agreement Page 3 of 74 Article 6. INDEMNIFICATION 75 6.1 Contractor covenants and agrees to indemnify, hold harmless and defend, at its own 76 expense, the city, its officers, servants and employees, from and against any and all 77 claims arising out of, or alleged to arise out of, the work and services to be 78 performed by the contractor, its officers, agents, employees, subcontractors, licenses 79 or invitees under this contract. This indemnification Drovision is svecifically 80 intended to operate and be effective even if it is alleged or Droven that all or some of 81 the damages being sought were caused, in whole or in Dart, by anv act, omission or 82 negligence of the citv. This indemnity provision is intended to include, without 83 limitation, indemnity for costs, expenses and legal fees incurred by the city in 84 defending against such claims and causes of actions. 85 86 6.2 Contractor covenants and agrees to indemnify and hold harmless, at its own expense, 87 the city, its officers, servants and employees, from and against any and all loss, damage 88 or destruction of property of the city, arising out of, or alleged to arise out of, the work 89 and services to be performed by the contractor, its officers, agents, employees, 90 subcontractors, licensees or invitees under this contract. This indemnification 91 Drovision is suecificallv intended to overate and be effective even if it is alleged or 92 Droven that all or some of the damages being sought were caused. in whole or in Dart. 93 by anv act. omission or negligence of the citv. 94 95 Article 7. MISCELLANEOUS 96 7.1 Terms. 97 Terms used in this Agreement are defined in Article 1 of the Standard City Conditions of 98 the Construction Contract for Developer Awarded Projects. 99 7.2 Assignment of Contract. 100 This Agreement, including all of the Contract Documents may not be assigned by the 101 Contractor without the advanced express written consent of the Developer. 102 7.3 Successors and Assigns. 103 Developer and Contractor each binds itself, its partners, successors, assigns and legal 104 representatives to the other party hereto, in respect to all covenants, agreements and 105 obligations contained in the Contract Documents. 106 7.4 Severability. 107 Any provision or part of the Contract Documents held to be unconstitutional, void or 108 unenforceable by a court of competent jurisdiction shall be deemed stricken, and all 109 remaining provisions shall continue to be valid and binding upon DEVELOPER and 110 CONTRACTOR - ill 7.5 Governing Law and Venue. 112 This Agreement, including all of the Contract Documents is performable in the State of 113 Texas. Venue shall be Tarrant County, Texas, or the United States District Court for the 114 Northern District of Texas, Fort Worth Division. CITY OF FORT WORTH Water & Sanitary Sewer to Serve Winldta Industrial STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS— DEVELOPER AWARDED PROJECTS CPN: 104140 Revised Jane 16, 2016 005243-4 Developer Awarded Project Agreement Page 4 of 4 115 116 7.6 Authority to Sign. 117 Contractor shall attach evidence of authority to sign Agreement, if other than duly 118 authorized signatory of the Contractor. 119 120 IN WITNESS WHEREOF, Developer and Contractor have executed this Agreement in multiple 121 counterparts. 122 123 This Agreement is effective as of the last date signed by the Parties ("Effective Date'). 124 125 Contractor: Bratjen Construction Company By: j (Signature) Beniamin C. Bratcher - -- (Printed Name) Developer: r< B Or1 !A Jgnature RUTTCN W NS FuKo (Printed Name) Title: CEO Title: VP OF GFA/CRAL PAKTNrtt Company Name: Bratjen Construction Company name:PK IIt/RLC1 WICHIrA STp.FCT, LT. Address: 1701 E. Lamar Blvd. Address:5g5o 6kP FSHIRE LN Suite 290 SUITC qoo City/state/Zip: Arlington, TX 76006 2/16/2024 Date City/State/Zip: PA -Lk, Tx 7522S Li/i /ZoZy Date CITY OF FORT WORTH Water& Sanitary Sewer W serve Wichita Indws l STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS —DEVELOPER AWARDED PROJECTS CPN: 104140 Revised June 16, 2016 EXECUTED IN TRIPLICATE 006219-1 MAINTENANCE BOND Page 1 of 3 Bond No.107969751 1 SECTION 00 62 19 2 MAINTENANCE BOND 3 4 THE STATE OF TEXAS § 5 § KNOW ALL BY THESE PRESENTS: 6 COUNTY OF TARRANT § 7 That we Bratien Construction Comganv , known as 8 "Principal" herein and Travelers Casualty and Suretv Company of America a corporate surety 9 (sureties, if more than one) duly authorized to do business in the State of Texas, known as 10 "Surety" herein (whether one or more), are held and firmly bound unto the Developer, 11 (PRIII/HLCI WICHITA STREET, L.P.I authorized to do business in Texas ("Developer") and 12 the City of Fort Worth, a Texas municipal corporation ("City"), in the sum of ONE MILLION 13 FOUR HUNDRED TWO THOUSAND EIGHTY-SEVEN DOLLARS AND FIFTY CENTS 14 (S1,402,087.50), lawful money of the United States, to be paid in Fort Worth, Tarrant County, 15 Texas, for payment of which sum well and truly be made jointly unto the Developer and the City 16 as dual obligees and their successors, we bind ourselves, our heirs, executors, administrators, 17 successors and assigns, jointly and severally, firmly by these presents. 18 19 WHEREAS, Developer and City have entered into an Agreement for the construction of 20 community facilities in the City of Fort Worth by and through a Community Facilities 21 Agreement, CFA Number CFA22-0169 and 22 WHEREAS, the Principal has entered into a certain written contract with the Developer 23 awarded the 1 st day of ADrll . 2024, which Contract is hereby referred to and made a 24 part hereof for all purposes as if fully set forth herein, to furnish all materials, equipment labor 25 and other accessories as defined by law, in the prosecution of the Work, including any Work 26 resulting from a duly authorized Change Order (collectively herein, the "Work") as provided for 27 in said Contract and designated as WICHITA INDUSTRIAL. 104140; and 28 29 WHEREAS, Principal binds itself to use such materials and to so construct the Work in 30 accordance with the plans, specifications and Contract Documents that the Work is and will 31 remain free from defects in materials or workmanship for and during the period of two (2) years 32 after the date of Final Acceptance of the Work by the City ("Maintenance Period"); and 33 CITY OF FORT WORTH Water & Sanitary Sewer to Serve Wichita Industrial STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN:104140 Revised January 31, 2012 006219-2 MAINTENANCE BOND Page 2 of 3 1 WHEREAS, Principal binds itself to repair or reconstruct the Work in whole or in part 2 upon receiving notice from the Developer and/or City of the need thereof at any time within the 3 Maintenance Period. 4 5 NOW THEREFORE, the condition of this obligation is such that if Principal shall 6 remedy any defective Work, for which timely notice was provided by Developer or City, to a 7 completion satisfactory to the City, then this obligation shall become null and void; otherwise to 8 remain in full force and effect. 9 10 PROVIDED, HOWEVER, if Principal shall fail so to repair or reconstruct any timely 11 noticed defective Work, it is agreed that the Developer or City may cause any and all such 12 defective Work to be repaired and/or reconstructed with all associated costs thereof being borne 13 by the Principal and the Surety under this Maintenance Bond; and 14 15 PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in 16 Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort 17 Worth Division; and 18 19 PROVIDED FURTHER, that this obligation shall be continuous in nature and 20 successive recoveries may be had hereon for successive breaches. 21 22 23 CITY OF FORT WORTH Water & Sanitary Sewer to Serve Wichita Industrial STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN:104140 Revised January 31, 2012 006219-3 MAINTENANCE BOND Page 3 of 3 1 IN WITNESS WHEREOF, the Principal and the Surety have each SIGNED and SEALED this 2 instrument by duly authorized agents and officers on this the 1 St day of 3 April 2094. 4 5 6 7 8 9 10 11 ATTEST: 12 13:__- 14 (Pipal)2wa_ � 15 16 17 18 19 20 Witness as to Principal 21 22 23 24 25 26 27 28 29 ATTEST: 31 J, 3(wit 32 (S s yn Simchik, Witness 33 34 35 ess as to Surety Alex Rausch, Witness 36 Dn TXTrTn e T Benjamin C. Bratcher. CEO Name and Title Address: 1701 E Lamar Blvd. Arlington TX 76006 SURETY: Travelers Casualty and Surety Company of America BY: Signature Sean J McCauley, Jr., Attomey-in-Fact Name and Title Address: One Tower Square Hartford, CT 06183 Telephone Number: (860) 277-0111 37 *Note: If signed by an officer of the Surety Company, there must be on file a certified extract 38 from the by-laws showing that this person has authority to sign such obligation. If 39 Surety's physical address is different from its mailing address, both must be provided. 40 41 The date of the bond shall not be prior to the date the Contract is awarded. 42 CITY OF FORT WORTH Water & Sanitary Sewer to Serve Wichita Industrial STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN.•104140 Revised January 31, 2012 EXECUTED IN TRIPLICATE 006213-1 PERFORMANCE BOND Page 1 of 3 Bond No.107969751 1 SECTION 00 62 13 2 PERFORMANCE BOND 3 4 THE STATE OF TEXAS § 5 § KNOW ALL BY THESE PRESENTS: 6 COUNTY OF TARRANT § 7 That we, Bratjen Construction Company , known as 8 "Principal" herein and Travelers Casualty and Surety Company of America , a corporate 9 surety(sureties, if more than one) duly authorized to do business in the State of Texas, known as 10 "Surety" herein (whether one or more), are held and firmly bound unto the Developer, 11 PRIH/HLCI WICHITA STREET. L.P. authorized to do business in Texas ("Developer") and 12 the City of Fort Worth, a Texas municipal corporation ("City"), in the penal sum of, ONE 13 MILLION FOUR HUNDRED TWO THOUSAND EIGHTY-SEVEN DOLLARS AND 14 FIFTY CENTS ($1.402,087.50), lawful money of the United States, to be paid in Fort Worth, 15 Tarrant County, Texas for the payment of which sum well and truly to be made jointly unto the 16 Developer and the City as dual obligees, we bind ourselves, our heirs, executors, administrators, 17 successors and assigns, jointly and severally, firmly by these presents. 18 WHEREAS, Developer and City have entered into an Agreement for the construction of 19 community facilities in the City of Fort Worth by and through a Community Facilities 20 Agreement, CFA Number CFA22-0169 and 21 WHEREAS, the Principal has entered into a certain written contract with the Developer awarded 22 the 1 St day of April , 2024, which Contract is hereby referred to and made a 23 part hereof for all purposes as if fully set forth herein, to furnish all materials, equipment labor 24 and other accessories defined by law, in the prosecution of the Work, including any Change 25 Orders, as provided for in said Contract designated as WICHITA INDUSTRIAL. 26 NOW, THEREFORE, the condition of this obligation is such that if the said Principal 27 shall faithfully perform it obligations under the Contract and shall in all respects duly and 28 faithfully perform the Work, including Change Orders, under the Contract, according to the plans, 29 specifications, and contract documents therein referred to, and as well during any period of 30 extension of the Contract that may be granted on the part of the Developer and/or City, then this 31 obligation shall be and become null and void, otherwise to remain in full force and effect. CITY OF FORT WORTH Water & Sanitary Sewer to Serve Wichita Industrial STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN: 104140 Revised January 31, 2012 006213-2 PERFORMANCE BOND Page 2 of 3 1 PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in 2 Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort 3 Worth Division. 4 This bond is made and executed in compliance with the provisions of Chapter 2253 of the 5 Texas Government Code, as amended, and all liabilities on this bond shall be determined in 6 accordance with the provisions of said statue. 7 IN WITNESS WHEREOF, the Principal and the Surety have SIGNED and SEALED 8 this instrument by duly authorized agents and officers on this the 1 St day of 9 April 2o24. 10 11 12 13 14 15 16 16 ATTES'I': 17 r 19 (Yrtlacipal) Secretaft Q _ �; t�� 20 21 22 23 24 25 Witness as to Principal 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 Witness as to Surety -flex Rausch, Witness 41 42 43 DD TAT(`TD AT . Benjamin C. Bratcher. CFO Name and Title Address: 1701 E Lamar Blvd. Arlinaton TX 76006 SURETY: Travelers Casualtv and Suretv Companv of America 4 l _ BY: Signature Sean J McCauley, Jr., Attorney -in -Fact Name and Title Address: One Tower Square Hartford. CT 06183 Telephone Number: (860) 277-0111 44 *Note: If signed by an officer of the Surety Company, there must be on file a certified extract 45 from the by-laws showing that this person has authority to sign such obligation. If 46 Surety's physical address is different from its mailing address, both must be provided. 47 CITY OF FORT WORTH Water & Sanitary Sewer to Serve Wichita Industrial STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN: 104140 Revised January 31, 2012 0062 13 -3 PERFORMANCE BOND Page 3 of 3 The date of the bond shall not be prior to the date the Contract is awarded. CITY OF FORT WORTH Water & Sanitary Sewer to Serve Wichita Industrial STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN: 104140 Revised January 31, 2012 EXECUTED IN TRIPLICATE 006214-1 PAYMENTBOND Page 1 of 2 Bond No.107969751 1 SECTION 00 62 14 2 PAYMENT BOND 3 4 THE STATE OF TEXAS § 5 § KNOW ALL BY THESE PRESENTS: 6 COUNTY OF TARRANT § 7 That we, Bratjen Construction Company known as 8 "Principal" herein, and Travelers Casualtv and Surety Companv of America a 9 corporate surety ( or sureties if more than one), duly authorized to do business in the State of 10 Texas, known as "Surety" herein (whether one or more), are held and firmly bound unto the 11 Developer, PRHI/HLCI WICHITA STREET. L.P. authorized to do business in Texas 12 "(Developer"), and the City of Fort Worth, a Texas municipal corporation ("City"), in the penal 13 sum of ONE MILLION FOUR HUNDRED TWO THOUSAND EIGHTY-SEVEN, 14 DOLLARS AND FIFTY CENTS ($1,402.087.50), lawful money of the United States, to be 15 paid in Fort Worth, Tarrant County, Texas, for the payment of which sum well and truly be made 16 jointly unto the Developer and the City as dual obligees, we bind ourselves, our heirs, executors, 17 administrators, successors and assigns, jointly and severally, firmly by these presents: 18 WHEREAS, Developer and City have entered into an Agreement for the construction of 19 community facilities in the City of Fort Worth, by and through a Community Facilities 20 Agreement, CFA Number CFA22-0169 and 21 WHEREAS, Principal has entered into a certain written Contract with Developer, 22 awarded the 1 St day of April , 20 24 , which Contract is hereby 23 referred to and made a part hereof for all purposes as if fully set forth herein, to furnish all 24 materials, equipment, labor and other accessories as defined by law, in the prosecution of the 25 Work as provided for in said Contract and designated as WICHITA INDUSTRIAL. 26 NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if 27 Principal shall pay all monies owing to any (and all) payment bond beneficiary (as defined in 28 Chapter 2253 of the Texas Government Code, as amended) in the prosecution of the Work under 29 the Contract, then this obligation shall be and become null and void; otherwise to remain in full 30 force and effect. CITY OF FORT WORTH Water & Sanitary Sewer to Serve Wichita Industrial STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN: 104140 Revised January 31, 2012 1 2 3 4 5 6 7 8 9 10 11 12 13 14 006214-2 PAYMENT BOND Page 2 of 2 This bond is made and executed in compliance with the provisions of Chapter 2253 of the Texas Government Code, as amended, and all liabilities on this bond shall be determined in accordance with the provisions of said statute. IN WITNESS WHEREOF, the Principal and Surety have each SIGNED and SEALED this instrument by duly authorized agents and officers on this the 1 St day of April 2024 1Ntpal) �.OrdL Witness as to Principal ATTEST: �i�� (S rety) �,ynshlSimchik, Witness at_, /--- Witness as to Surety Alex Rausch, Witness PRINCIPAL: I Benjamin C. Bratcher, CEO Name and Title Address: 1701 E Lamar Blvd. Arlinqton TX 76006 SURETY: Travelers Casualtv and Suretv Companv of America BY: Signature Sean J McCauley, Jr., Attornev-in-Fact Name and Title Address: One Tower Square Hartford, CT 06183 Telephone Number: (860) 277-0111 Note: If signed by an officer of the Surety, there must be on file a certified extract from the bylaws showing that this person has authority to sign such obligation. If Surety's physical address is different from its mailing address, both must be provided. The date of the bond shall not be prior to the date the Contract is awarded. END OF SECTION CITY OF FORT WORTH Water & Sanitary Sewer to Serve Wichita Industrial STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN: 104140 Revised January 31, 2012 Travelers Casualty and Surety Company of America CAW Travelers Casualty and Surety Company TRAVELERS St. Paul Fire and Marine Insurance Company POWER OF ATTORNEY KNOW ALL MEN BY THESE PRESENTS: That Travelers Casualty and Surety Company of America, Travelers Casualty and Surety Company, and St. Paul Fire and Marine Insurance Company are corporations duly organized under the laws of the State of Connecticut (herein collectively called the "Companies"), and that the Companies do hereby make, constitute and appoint SEAN J MCCAULEY JR of DALLAS , Texas their true and lawful Attorney(s)-in-Fact to sign, execute, seal and acknowledge any and all bonds, recognizances, conditional undertakings and other writings obligatory in the nature thereof on behalf of the Companies in their business of guaranteeing the fidelity of persons, guaranteeing the performance of contracts and executing or guaranteeing bonds and undertakings required or permitted in any actions or proceedings allowed by law. IN WITNESS WHEREOF, the Companies have caused this instrument to be signed, and their corporate seals to be hereto affixed, this 21st day of April, 2021. OX' 7iF �Jp4TY Ay�.� HAMM N. 'CON G State of Connecticut City of Hartford ss. By: rR*bertRane enior Vice President On this the 21st day of April, 2021, before me personally appeared Robert L. Raney, who acknowledged himself to be the Senior Vice President of each of the Companies, and that he, as such, being authorized so to do, executed the foregoing instrument for the purposes therein contained by signing on behalf of said Companies by himself as a duly authorized officer. IN WITNESS WHEREOF, I hereunto set my hand and official seal. My Commission expires the 30th day of June, 2026 MWO Anna P. Nowik, Notary Public This Power of Attorney is granted under and by the authority of the following resolutions adopted by the Boards of Directors of each of the Companies, which resolutions are now in full force and effect, reading as follows: RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President, any Vice President, any Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary may appoint Attorneys -in -Fact and Agents to act for and on behalf of the Company and may give such appointee such authority as his or her certificate of authority may prescribe to sign with the Company's name and seal with the Company's seal bonds, recognizances, contracts of indemnity, and other writings obligatory in the nature of a bond, recognizance, or conditional undertaking, and any of said officers or the Board of Directors at any time may remove any such appointee and revoke the power given him or her; and it is FURTHER RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or any Vice President may delegate all or any part of the foregoing authority to one or more officers or employees of this Company, provided that each such delegation is in writing and a copy thereof is filed in the office of the Secretary; and it is FURTHER RESOLVED, that any bond, recognizance, contract of indemnity, or writing obligatory in the nature of a bond, recognizance, or conditional undertaking shall be valid and binding upon the Company when (a) signed by the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or any Vice President, any Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary and duly attested and sealed with the Company's seal by a Secretary or Assistant Secretary; or (b) duly executed (under seal, if required) by one or more Attorneys -in -Fact and Agents pursuant to the power prescribed in his or her certificate or their certificates of authority or by one or more Company officers pursuant to a written delegation of authority; and it is FURTHER RESOLVED, that the signature of each of the following officers: President, any Executive Vice President, any Senior Vice President, any Vice President, any Assistant Vice President, any Secretary, any Assistant Secretary, and the seal of the Company may be affixed by facsimile to any Power of Attorney or to any certificate relating thereto appointing Resident Vice Presidents, Resident Assistant Secretaries or Attorneys -in - Fact for purposes only of executing and attesting bonds and undertakings and other writings obligatory in the nature thereof, and any such Power of Attorney or certificate bearing such facsimile signature or facsimile seal shall be valid and binding upon the Company and any such power so executed and certified by such facsimile signature and facsimile seal shall be valid and binding on the Company in the future with respect to any bond or understanding to which it is attached. I, Kevin E. Hughes, the undersigned, Assistant Secretary of each of the Companies, do hereby certify that the above and foregoing is a true and correct copy of the Power of Attorney executed by said Companies, which remains in full force and effect. Dated this day of ®rflp� J�44Y —W4 IN aq, W ONN. 4 FM Hughes, Assi tant Secretary To verify the authenticity of this Fower oft ftorn&y, please call us at 1-800-411-3880. Please refer to the above -named Attorneys) -in -Fact and the det,yils of the bond to which this Power ofAttorney is attached. 'nil IfRMC-111 z :e* Certificate of Authority c=pI with the laws of the Sty of Texas applicable thereto and Is hereby auftrized to transact tbe busing of Fire: Allied Coverages; Hail —growing crops only: i nInland Marine; Ocean Marine; Aircraft --Liability & Physical Damage; workers' CQmpensation & Employers' Liability, Liability Automobile --Liability Physical D ag ; Liability other than Automobile; Fidelity & Surety; Mass; Burglary "Theft; Forgery; Boiler & Machinery; Credit; Livestock and Reinsurance on all limes authorized to he written on A dit-6dt b,ssts insurance within the stares of T+cxas. This Certificate of Autberity shall be in full farce and effect until it is revoked, canceled or suspended according to law. IN TESTIMONY HOMP. wimess my hand and seal of offcc at Austin, Texss, tMs list day of my A.D. 1"' ELTON 50bWA COMMISSIONER OF INSLMANCE l BY A. Wilcox Director Insurer Ser iO IMPORTANT NOTICE To obtain information or make a complaint: You may call Travelers Casualty and Surety Company of America and its affiliates' toll -free telephone number for information or to make a complaint at: 1-800-328-2189 You may contact the Texas Department of Insurance to obtain information on companies, coverages, rights or complaints at: 1-800-252-3439 You may write the Texas Department of Insurance: P. O. Box 149104 Austin, TX 78714-9104 Fax: (512) 475-1771 Web: httr)://www.tdi.state.tx.us E-mail: ConsumerProtection(d)tdi.state.tx.us PREMIUM OR CLAIM DISPUTES: Should you have a dispute concerning your premium or about a claim you should contact your Agent or Travelers first. if the dispute is not resolved, you may contact the Texas Department of Insurance. ATTACH THIS NOTICE TO YOUR BOND: This notice is for information only and does not become a part or condition of the attached document and is given to comply with Texas legal and regulatory requirements. (PN-042-B) Ed.10.18.07 STANDARD CITY CONDITIONS OF THE CONSTRUCTION CONTRACT FOR DEVELOPER AWARDED PROJECTS CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 STANDARD CITY CONDITIONS OF THE CONSTRUCTION CONTRACT FOR DEVELOPER AWARDED PROJECTS TABLE OF CONTENTS Article 1 — Definitions and Terminology.......... 1.01 Defined Terms ............................... 1.02 Terminology .................................. Article 2 — Preliminary Matters ....................... 2.01 Before Starting Construction...... 2.02 Preconstruction Conference........ 2.03 Public Meeting ............................ Page .............................................1 .............................................1 ............................................. 5 ....................................................... 6 ....................................................... 6 ....................................................... 6 ....................................................... 6 Article 3 — Contract Documents and Amending............................................................................................... 6 3.01 Reference Standards..................................................................................................................... 6 3.02 Amending and Supplementing Contract Documents.................................................................. 6 Article 4 — Bonds and Insurance....................................................................................................................... 7 4.01 Licensed Sureties and Insurers..................................................................................................... 7 4.02 Performance, Payment, and Maintenance Bonds........................................................................ 7 4.03 Certificates of Insurance............................................................................................................... 7 4.04 Contractor's Insurance.................................................................................................................. 9 4.05 Acceptance of Bonds and Insurance; Option to Replace...........................................................12 Article 5 — Contractor's Responsibilities........................................................................................................12 5.01 Supervision and Superintendent.................................................................................................12 5.02 Labor; Working Hours................................................................................................................13 5.03 Services, Materials, and Equipment...........................................................................................13 5.04 Project Schedule..........................................................................................................................14 5.05 Substitutes and "Or-Equals".......................................................................................................14 5.06 Pre -Qualification of Bidders (Prime Contractors and Subcontractors).....................................16 5.07 Concerning Subcontractors, Suppliers, and Others...................................................................16 5.08 Wage Rates..................................................................................................................................18 5.09 Patent Fees and Royalties...........................................................................................................19 5.10 Laws and Regulations.................................................................................................................19 5.11 Use of Site and Other Areas.......................................................................................................19 5.12 Record Documents......................................................................................................................20 5.13 Safety and Protection.................................................................................................................. 21 5.14 Safety Representative.................................................................................................................21 5.15 Hazard Communication Programs.............................................................................................22 5.16 Submittals....................................................................................................................................22 5.17 Contractor's General Warranty and Guarantee..........................................................................23 CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 5.18 Indemnification ............................................ 5.19 Delegation of Professional Design Services 5.20 Right to Audit: ............................................. 5.21 Nondiscrimination ........................................ Article 6 - Other Work at the Site....... 6.01 Related Work at Site ....... Article 7 - City's Responsibilities ............................................ 7.01 Inspections, Tests, and Approvals ....................... 7.02 Limitations on City's Responsibilities ................ 7.03 Compliance with Safety Program ........................ Article 8 - City's Observation Status During Construction....... 8.01 City's Project Representative ................................. 8.02 Authorized Variations in Work .............................. 8.03 Rejecting Defective Work ...................................... 8.04 Determinations for Work Performed ...................... Article 9 - Changes in the Work ...................... 9.01 Authorized Changes in the Work 9.02 Notification to Surety ................... Article 10 - Change of Contract Price; Change of Contract Time 10.01 Change of Contract Price ........................................... 10.02 Change of Contract Time ........................................... 10.03 Delays......................................................................... Article 11 - Tests and Inspections; Correction, Removal or Acceptance of Defective Work ............ 11.01 Notice of Defects.............................................................................................................. 11.02 Access to Work................................................................................................................. 11.03 Tests and Inspections........................................................................................................ 11.04 Uncovering Work............................................................................................................. 11.05 City May Stop the Work................................................................................................... 11.06 Correction or Removal of Defective Work...................................................................... 11.07 Correction Period.............................................................................................................. 11.08 City May Correct Defective Work................................................................................... Article 12 - Completion ........................................... 12.01 Contractor's Warranty of Title ............ 12.02 Partial Utilization ................................. 12.03 Final Inspection .................................... 12.04 Final Acceptance .................................. Article 13 - Suspension of Work ..................................... 13.01 City May Suspend Work ............................. Article 14 - Miscellaneous ......................................... 14.01 Giving Notice ......................................... CITY OF FORT WORTH STANDARD CITY CONDITIONS - DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 24 24 25 25 26 26 26 26 26 27 a a ... 29 ... 29 ... 29 ... 29 ... 30 ... 30 ... 30 ... 30 ... 31 ................................. 32 ................................. 32 ................................. 32 ................................. 32 ................................. 33 ............................................................. 33 ............................................................. 33 34 34 14.02 Computation of Times................................................................................................................ 34 14.03 Cumulative Remedies................................................................................................................. 34 14.04 Survival of Obligations...............................................................................................................35 14.05 Headings......................................................................................................................................35 CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10- 1 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 1 of 35 ARTICLE 1— DEFINITIONS AND TERMINOLOGY 1.01 Defined Terms A. Wherever used in these General Conditions or in other Contract Documents, the terms listed below have the meanings indicated which are applicable to both the singular and plural thereof, and words denoting gender shall include the masculine, feminine and neuter. Said terms are generally capitalized or written in italics, but not always. When used in a context consistent with the definition of a listed -defined term, the term shall have a meaning as defined below whether capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial capital letters in the Contract Documents include references to identified articles and paragraphs, and the titles of other documents or forms. 1. Agreement - The written instrument which is evidence of the agreement between Developer and Contractor covering the Work 2. Asbestos —Any material that contains more than one percent asbestos and is friable or is releasing asbestos fibers into the air above current action levels established by the United States Occupational Safety and Health Administration. 3. Business Day — A business day is defined as a day that the City conducts normal business, generally Monday through Friday, except for federal or state holidays observed by the City. 4. Buzzsaw — City's on-line, electronic document management and collaboration system. 5. Calendar Day — A day consisting of 24 hours measured from midnight to the next midnight. 6. City— The City of Fort Worth, Texas, a Texas home -rule municipal corporation, acting by, its governing body through its City Manager, his designee, or agents authorized pursuant to its duly authorized charter on his behalf. 7. Community Facilities Agreement (CFA) A Contract between the Developer and the City for the Construction of one or more following public facilities within the City public right-of- way or easement: Water, Sanitary Sewer, Street, Storm Drain, Street Light, and Street Signs. A CFA may include private facilities within the right-of-way dedicated as private right-of- way or easement on a recorded plat. 8. Contract —The entire and integrated written document incorporating the Contract Documents between the Developer, Contractor, and/or City concerning the Work. The Contract supersedes prior negotiations, representations, or agreements, whether written or oral. 9. Contract Documents —Those items that make up the contract and which must include the Agreement, and it's attachments such as standard construction specifications, standard City Conditions, other general conditions of the Developer, including: a. An Agreement CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10-2 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 2 of 35 b. Attachments to the Agreement i. Bid Form ii. Vendor Compliance with State Law Non -Resident Bidder iii. Prequalification Statement C. Current Prevailing Wage Rates Table (if required by City) d. Insurance Accord Form e. Payment Bond f. Performance Bond g. Maintenance Bond h. Power of Attorney for Bonds i. Workers Compensation Affidavit j. MWBE Commitment Form( If required by City) k. General Conditions 1. Supplementary Conditions in. The Standard City Conditions n. Specifications specifically made part of the Contract Documents by attachment, if not attached, as incorporated by reference and described in the Table of Contents of the Project's Contract Documents o. Drawings P. Documentation submitted by contractor prior to Notice of Award. q. The following which may be delivered or issued after the effective date if the Agreement and, if issued become an incorporated part of the Contract Documents i. Notice to Proceed ii. Field Orders iii. Change Orders iv. Letters of Final Acceptance r. Approved Submittals, other Contractor submittals, and the reports and drawings of subsurface and physical conditions are not Contract Documents. 10. Contractor —The individual or entity with whom Developer has entered into the Agreement. 11. Day or day —A day, unless otherwise defined, shall mean a Calendar Day. 12. Developer — An individual or entity that desires to make certain improvements within the City of Fort Worth 13. Drawings —That part of the Contract Documents prepared or approved by Engineer which graphically shows the scope, extent, and character of the Work to be performed by Contractor. Submittals are not Drawings as so defined. 14. Engineer —The licensed professional engineer or engineering firm registered in the State of Texas performing professional services for the Developer. 15. Final Acceptance — The written notice given by the City to the Developer and/or Contractor that the Work specified in the Contract Documents has been completed to the satisfaction of the City. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10- 3 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 3 of 35 16. Final Inspection — Inspection carried out by the City to verify that the Contractor has completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in conformance with the Contract Documents. 17. General Requirements —A part of the Contract Documents between the Developer and a Contractor. 18. Laws and Regulations Any and all applicable laws, rules, regulations, ordinances, codes, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction. 19. Liens —Charges, security interests, or encumbrances upon Project funds, real property, or personal property. 20. Milestone —A principal event specified in the Contract Documents relating to an intermediate Contract Time prior to Final Acceptance of the Work. 21. Non -Participating Change Order —A document, which is prepared for and reviewed by the City, which is signed by Contractor, and Developer, and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on or after the Effective Date of the Agreement. 22. Participating Change Order —A document, which is prepared for and approved by the City, which is signed by Contractor, Developer, and City and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on or after the Effective Date of the Agreement. 23. Plans — See definition of Drawings. 24. Project Schedule —A schedule, prepared and maintained by Contractor, in accordance with the General Requirements, describing the sequence and duration of the activities comprising the Contractor's plan to accomplish the Work within the Contract Time. 25. Project —The Work to be performed under the Contract Documents. 26. Project Representative —The authorized representative of the City who will be assigned to the Site. 27. Public Meeting — An announced meeting conducted by the Developer to facilitate public participation and to assist the public in gaining an informed view of the Project. 28. Regular Working Hours — Hours beginning at 7: 00 a.m. and ending at 6:00 p.m., Monday thru Friday (excluding legal holidays). 29. Samples Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and which establish the standards by which such portion of the Work will be judged. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10- 4 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 4 of 35 30. Schedule of Submittals —A schedule, prepared and maintained by Contractor, of required submittals and the time requirements to support scheduled performance of related construction activities. 31. Site —Lands or areas indicated in the Contract Documents as being furnished by City or Developer upon which the Work is to be performed, including rights -of -way, permits, and easements for access thereto, and such other lands furnished by City or Developer which are designated for the use of Contractor. 32. Specifications —That part of the Contract Documents consisting of written requirements for materials, equipment, systems, standards and workmanship as applied to the Work, and certain administrative requirements and procedural matters applicable thereto. Specifications may be specifically made a part of the Contract Documents by attachment or, if not attached, may be incorporated by reference as indicated in the Table of Contents (Division 00 00 00) of each Project. 33. Standard City Conditions — That part of the Contract Documents setting forth requirements of the City. 34. Subcontractor —An individual or entity having a direct contract with Contractor or with any other Subcontractor for the performance of apart of the Work at the Site. 35. Submittals All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for Contractor and submitted by Contractor to illustrate some portion of the Work. 36. Superintendent — The representative of the Contractor who is available at all times and able to receive instructions from the City and/or Developer and to act for the Contractor. 37. Supplementary Conditions —That part of the Contract Documents which amends or supplements the General Conditions. 38. Supplier —A manufacturer, fabricator, supplier, distributor, materialman, or vendor having a direct contract with Contractor or with any Subcontractor to furnish materials or equipment to be incorporated in the Work by Contractor or Subcontractor. 39. Underground Facilities All underground pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including but not limited to, those that convey electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or other control systems. 40. Weekend Working Hours — Hours beginning at 9: 00 a. in. and ending at 5: 00 p.m., Saturday, Sunday or legal holiday, as approved in advance by the City. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10- 5 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 5 of 35 41. Work —The entire construction or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction including any Participating Change Order, Non -Participating Change Order, or Field Order, and furnishing, installing, and incorporating all materials and equipment into such construction, all as required by the Contract Documents. 42. Working Day — A working day is defined as a day, not including Saturdays, Sundays, or legal holidays authorized by the City for contract purposes, in which weather or other conditions not under the control of the Contractor will permit the performance of the principal unit of work underway for a continuous period of not less than 7 hours between 7 a.m. and 6 p. m. 1.02 Terminology A. The words and terms discussed in Paragraph 1.02.13 through D are not defined but, when used in the Bidding Requirements or Contract Documents, have the indicated meaning. B. Defective: 1. The word "defective," when modifying the word "Work," refers to Work that is unsatisfactory, faulty, or deficient in that it: a. does not conform to the Contract Documents; or b. does not meet the requirements of any applicable inspection, reference standard, test, or approval referred to in the Contract Documents; or c. has been damaged prior to City's written acceptance. C. Furnish, Install, Perform, Provide: 1. The word "Furnish" or the word "Install" or the word "Perform" or the word "Provide" or the word "Supply," or any combination or similar directive or usage thereof, shall mean furnishing and incorporating in the Work including all necessary labor, materials, equipment, and everything necessary to perform the Work indicated, unless specifically limited in the context used. D. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known technical or construction industry or trade meaning are used in the Contract Documents in accordance with such recognized meaning. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10- 6 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 6 of 35 ARTICLE 2 — PRELIMINARY MATTERS 2.01 Before Starting Construction Baseline Schedules: Submit to City in accordance with the Contract Documents, and prior to starting the Work. New schedules will be submitted to City when Participating Change Orders or Non - Participating Change Orders occur. 2.02 Preconstruction Conference Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as specified in the Contract Documents. 2.03 Public Meeting Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor attending the Public Meeting as scheduled by the City. ARTICLE 3 — CONTRACT DOCUMENTS AND AMENDING 3.01 Reference Standards A. Standards, Specifications, Codes, Laws, and Regulations 1. Reference to standards, specifications, manuals, or codes of any technical society, organization, or association, or to Laws or Regulations, whether such reference be specific or by implication, shall mean the standard, specification, manual, code, or Laws or Regulations in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there were no Bids), except as may be otherwise specifically stated in the Contract Documents. 2. No provision or instruction shall be effective to assign to City, or any of its officers, directors, members, partners, employees, agents, consultants, or subcontractors, any duty or authority to supervise or direct the performance of the Work or any duty or authority to undertake responsibility inconsistent with the provisions of the Contract Documents. 3.02 Amending and Supplementing Contract Documents A. The Contract Documents may be amended to provide for additions, deletions, and revisions in the Work or to modify the terms and conditions thereof by a Participating Change Order or a Non -Participating Change Order. B. The requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work not involving a change in Contract Price or Contract Time, may be authorized, by one or more of the following ways: 1. A Field Order; CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10- 7 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 7 of 35 1. City's or Engineer's review of a Submittal (subject to the provisions of Paragraph 5.16.C); or 2. City's written interpretation or clarification. ARTICLE 4 — BONDS AND INSURANCE 4.01 Licensed Sureties and Insurers All bonds and insurance required by the Contract Documents to be purchased and maintained by Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized in the State of Texas to issue bonds or insurance policies for the limits and coverage so required. Such surety and insurance companies shall also meet such additional requirements and qualifications as may be provided Section 4.04. 4.02 Performance, Payment, and Maintenance Bonds A. Contractor shall furnish performance and payment bonds in the name of Developer and City, in accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount equal to the Contract Price as security for the faithful performance and payment of all of Contractor's obligations under the Contract Documents. B. Contractor shall furnish maintenance bonds in the name of Developer and City in an amount equal to the Contract Price as security to protect the City against any defects in any portion of the Work described in the Contract Documents. Maintenance bonds shall remain in effect for two (2) years after the date of Final Acceptance by the City. C. All bonds shall be in the form prescribed by the Contract Documents except as provided otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list of "Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies" as published in Circular 570 (amended) by the Financial Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed by an agent or attorney -in -fact must be accompanied by a sealed and dated power of attorney which shall show that it is effective on the date the agent or attorney -in -fact signed each bond. D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or its right to do business is terminated in the State of Texas or it ceases to meet the requirements of Paragraph 4.02.C, Contractor shall promptly notify City and shall, within 30 days after the event giving rise to such notification, provide another bond and surety, both of which shall comply with the requirements of Paragraphs 4.01 and 4.02.C. 4.03 Certificates of Insurance Contractor shall deliver to Developer and City, with copies to each additional insured and loss payee identified in these Standard City Conditions certificates of insurance (and other evidence of insurance requested by City or any other additional insured) which Contractor is required to purchase and maintain. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10- 8 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 8 of 35 1. The certificate of insurance shall document the City, an as "Additional Insured" on all liability policies. 2. The Contractor's general liability insurance shall include a, "per project" or "per location", endorsement, which shall be identified in the certificate of insurance provided to the City. 3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the insured, be complete in its entirety, and show complete insurance carrier names as listed in the current A.M. Best Property & Casualty Guide 4. The insurers for all policies must be licensed and/or approved to do business in the State of Texas. Except for workers' compensation, all insurers must have a minimum rating of A-: VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial strength and solvency to the satisfaction of Risk Management. If the rating is below that required, written approval of City is required. 5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor of the City. In addition, the Contractor agrees to waive all rights of subrogation against the Engineer (if applicable), and each additional insured identified in these Standard City Conditions. Failure of the City to demand such certificates or other evidence of full compliance with the insurance requirements or failure of the City to identify a deficiency from evidence that is provided shall not be construed as a waiver of Contractor's obligation to maintain such lines of insurance coverage. 6. If insurance policies are not written for specified coverage limits, an Umbrella or Excess Liability insurance for any differences is required. Excess Liability shall follow form of the primary coverage. 7. Unless otherwise stated, all required insurance shall be written on the "occurrence basis". If coverage is underwritten on a claims -made basis, the retroactive date shall be coincident with or prior to the date of the effective date of the agreement and the certificate of insurance shall state that the coverage is claims -made and the retroactive date. The insurance coverage shall be maintained for the duration of the Contract and for three (3) years following Final Acceptance provided under the Contract Documents or for the warranty period, whichever is longer. An annual certificate of insurance submitted to the City shall evidence such insurance coverage. 8. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the required lines of coverage, nor decrease the limits of said coverage unless such endorsements are approved in writing by the City. In the event a Contract has been bid or executed and the exclusions are determined to be unacceptable or the City desires additional insurance coverage, and the City desires the contractor/engineer to obtain such coverage, the contract price shall be adjusted by the cost of the premium for such additional coverage plus 10%. 9. Any self -insured retention (SIR), in excess of $25,000.00, affecting required insurance coverage shall be approved by the City in regards to asset value and stockholders' equity. In CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 0073 10-9 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 9 of 35 lieu of traditional insurance, alternative coverage maintained through insurance pools or risk retention groups, must also be approved by City. 10. Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a first -dollar basis, must be acceptable to and approved by the City. 11. City, at its sole discretion, reserves the right to review the insurance requirements and to make reasonable adjustments to insurance coverage's and their limits when deemed necessary and prudent by the City based upon changes in statutory law, court decision or the claims history of the industry as well as of the contracting party to the City. The City shall be required to provide prior notice of 90 days, and the insurance adjustments shall be incorporated into the Work by Change Order. 12. City shall be entitled, upon written request and without expense, to receive copies of policies and endorsements thereto and may make any reasonable requests for deletion or revision or modifications of particular policy terms, conditions, limitations, or exclusions necessary to conform the policy and endorsements to the requirements of the Contract. Deletions, revisions, or modifications shall not be required where policy provisions are established by law or regulations binding upon either parry or the underwriter on any such policies. 13. City shall not be responsible for the direct payment of insurance premium costs for Contractor's insurance. 4.04 Contractor's Insurance A. Workers Compensation and Employers' Liability. Contractor shall purchase and maintain such insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers' Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for Employers' Liability as is appropriate for the Work being performed and as will provide protection from claims set forth below which may arise out of or result from Contractor's performance of the Work and Contractor's other obligations under the Contract Documents, whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable: 1. claims under workers' compensation, disability benefits, and other similar employee benefit acts; 2. claims for damages because of bodily injury, occupational sickness or disease, or death of Contractor's employees. 3. The limits of liability for the insurance shall provide the following coverages for not less than the following amounts or greater where required by Laws and Regulations a. Statutory limits b. Employer's liability CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 10 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 10 of 35 1) $100,000 each accident/occurrence 2) $100,000 Disease - each employee 3) $500,000 Disease - policy limit B. Commercial General Liability. Coverage shall include but not be limited to covering liability (bodily injury or property damage) arising from: premises/operations, independent contractors, products/completed operations, personal injury, and liability under an insured contract. Insurance shall be provided on an occurrence basis, and as comprehensive as the current Insurance Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to any other insurance or self-insurance programs afforded to the City. The Commercial General Liability policy, shall have no exclusions by endorsements that would alter of nullify premises/operations, products/completed operations, contractual, personal injury, or advertising injury, which are normally contained with the policy, unless the City approves such exclusions in writing. 1. For construction projects that present a substantial completed operation exposure, the City may require the contractor to maintain completed operations coverage for a minimum of no less than three (3) years following the completion of the project 2. Contractor's Liability Insurance under this Section which shall be on a per project basis covering the Contractor with minimum limits of: a. $1,000,000 each occurrence b. $2,000,000 aggregate limit 3. The policy must have an endorsement (Amendment — Aggregate Limits of Insurance) making the General Aggregate Limits apply separately to each job site. 4. The Commercial General Liability Insurance policies shall provide "X", "C", and "U" coverage's. Verification of such coverage must be shown in the Remarks Article of the Certificate of Insurance. C. Automobile Liability. A commercial business auto policy shall provide coverage on "any auto", defined as autos owned, hired and non -owned and provide indemnity for claims for damages because bodily injury or death of any person and or property damage arising out of the work, maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable. 1. Automobile Liability, Contractor's Liability Insurance under this Section, which shall be in an amount not less than the following amounts: a. Automobile Liability - a commercial business policy shall provide coverage on "Any Auto", defined as autos owned, hired and non -owned. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 11 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 11 of 35 1) $1, 000, 000 each accident on a combined single limit basis. Split limits are acceptable if limits are at least: 2) $250,000 Bodily Injury per person 3) $500,000 Bodily Injury per accident / 4) $100,000 Property Damage D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of railroad right-of-way, the Contractor shall comply with the following requirements: 1. The Contractor's construction activities will require its employees, agents, subcontractors, equipment, and material deliveries to cross railroad properties and tracks owned and operated by: Write the name of the railroad company. (If none, then write none) 2. The Contractor shall conduct its operations on railroad properties in such a manner as not to interfere with, hinder, or obstruct the railroad company in any manner whatsoever in the use or operation of its/their trains or other property. Such operations on railroad properties may require that Contractor to execute a "Right of Entry Agreement" with the particular railroad company or companies involved, and to this end the Contractor should satisfy itself as to the requirements of each railroad company and be prepared to execute the right -of -entry (if any) required by a railroad company. The requirements specified herein likewise relate to the Contractor's use of private and/or construction access roads crossing said railroad company's properties. 3. The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions shall provide coverage for not less than the following amounts, issued by companies satisfactory to the City and to the Railroad Company for a term that continues for so long as the Contractor's operations and work cross, occupy, or touch railroad property: a. General Aggregate: b. Each Occurrence: : Enter limits provided by Railroad Company (If none, write none) Enter limits provided by Railroad Company (If none, write none) 4. With respect to the above outlined insurance requirements, the following shall govern: a. Where a single railroad company is involved, the Contractor shall provide one insurance policy in the name of the railroad company. However, if more than one grade separation or at -grade crossing is affected by the Project at entirely separate locations on the line or lines of the same railroad company, separate coverage may be required, each in the amount stated above. b. Where more than one railroad company is operating on the same right-of-way or where several railroad companies are involved and operated on their own separate rights -of - CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 12 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 12 of 35 way, the Contractor may be required to provide separate insurance policies in the name of each railroad company. c. If, in addition to a grade separation or an at -grade crossing, other work or activity is proposed on a railroad company's right-of-way at a location entirely separate from the grade separation or at -grade crossing, insurance coverage for this work must be included in the policy covering the grade separation. d. If no grade separation is involved but other work is proposed on a railroad company's right-of-way, all such other work may be covered in a single policy for that railroad, even though the work may be at two or more separate locations. 5. No work or activities on a railroad company's property to be performed by the Contractor shall be commenced until the Contractor has furnished the City with an original policy or policies of the insurance for each railroad company named, as required above. All such insurance must be approved by the City and each affected Railroad Company prior to the Contractor's beginning work. 6. The insurance specified above must be carried until all Work to be performed on the railroad right-of-way has been completed and the grade crossing, if any, is no longer used by the Contractor. In addition, insurance must be carried during all maintenance and/or repair work performed in the railroad right-of-way. Such insurance must name the railroad company as the insured, together with any tenant or lessee of the railroad company operating over tracks involved in the Project. E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation or other loss of insurance coverage. Contractor shall stop work until replacement insurance has been procured. There shall be no time credit for days not worked pursuant to this section. 4.05 Acceptance of Bonds and Insurance; Option to Replace If City has any objection to the coverage afforded by or other provisions of the bonds or insurance required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis of non-conformance with the Contract Documents, the Developer and City shall so notify the Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence requested). Contractor shall provide to the City such additional information in respect of insurance provided as the Developer or City may reasonably request. If Contractor does not purchase or maintain all of the bonds and insurance required by the Contract Documents, the Developer or City shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure to maintain prior to any change in the required coverage. ARTICLE 5 — CONTRACTOR'S RESPONSIBILITIES 5.01 Supervision and Superintendent A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 13 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 13 of 35 Work in accordance with the Contract Documents. Contractor shall be solely responsible for the means, methods, techniques, sequences, and procedures of construction. B. At all times during the progress of the Work, Contractor shall assign a competent, English- speaking, Superintendent who shall not be replaced without written notice to City. The Superintendent will be Contractor's representative at the Site and shall have authority to act on behalf of Contractor. All communication given to or received from the Superintendent shall be binding on Contractor. C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of construction. 5.02 Labor; Working Hours A. Contractor shall provide competent, suitably qualified personnel to perform construction as required by the Contract Documents. Contractor shall at all times maintain good discipline and order at the Site. B. Except as otherwise required for the safety or protection of persons or the Work or property at the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work at the Site shall be performed during Regular Working Hours. Contractor will not permit the performance of Work beyond Regular Working Hours or for Weekend Working Hours without City's written consent (which will not be unreasonably withheld). Written request (by letter or electronic communication) to perform Work: 1. for beyond Regular Working Hours request must be made by noon at least two (2) Business Days prior 2. for Weekend Working Hours request must be made by noon of the preceding Thursday 3. for legal holidays request must be made by noon two Business Days prior to the legal holiday. 5.03 Services, Materials, and Equipment A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full responsibility for all services, materials, equipment, labor, transportation, construction equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary facilities, temporary facilities, and all other facilities and incidentals necessary for the performance, Contractor required testing, start-up, and completion of the Work. B. All materials and equipment incorporated into the Work shall be as specified or, if not specified, shall be of good quality and new, except as otherwise provided in the Contract Documents. All special warranties and guarantees required by the Specifications shall expressly run to the benefit of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of required tests) as to the source, kind, and quality of materials and equipment. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 14 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 14 of 35 C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed, connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of the applicable Supplier, except as otherwise may be provided in the Contract Documents. 5.04 Project Schedule A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.01 and the General Requirements as it may be adjusted from time to time as provided below. 1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.01 and the General Requirements) proposed adjustments in the Project Schedule. 2. Proposed adjustments in the Project Schedule that will change the Contract Time shall be submitted in accordance with the requirements of Article 9. Adjustments in Contract Time for projects with City participation shall be made by participating change orders. 5.05 Substitutes and "Or -Equals " A. Whenever an item of material or equipment is specified or described in the Contract Documents by using the name of a proprietary item or the name of a particular Supplier, the specification or description is intended to establish the type, function, appearance, and quality required. Unless the specification or description contains or is followed by words reading that no like, equivalent, or "or -equal" item or no substitution is permitted, other items of material or equipment of other Suppliers may be submitted to City for review under the circumstances described below. 1. "Or -Equal" Items: If in City's sole discretion an item of material or equipment proposed by Contractor is functionally equal to that named and sufficiently similar so that no change in related Work will be required, it may be considered by City as an "or -equal" item, in which case review and approval of the proposed item may, in City's sole discretion, be accomplished without compliance with some or all of the requirements for approval of proposed substitute items. For the purposes of this Paragraph 5.05.A.1, a proposed item of material or equipment will be considered functionally equal to an item so named if: a. City determines that: 1) it is at least equal in materials of construction, quality, durability, appearance, strength, and design characteristics; 2) it will reliably perform at least equally well the function and achieve the results imposed by the design concept of the completed Project as a functioning whole; and 3) it has a proven record of performance and availability of responsive service; and b. Contractor certifies that, if approved and incorporated into the Work: 1) there will be no increase in cost to the City or increase in Contract Time; and CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 15 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 15 of 35 2) it will conform substantially to the detailed requirements of the item named in the Contract Documents. 2. Substitute Items: a. If in City's sole discretion an item of material or equipment proposed by Contractor does not qualify as an "or -equal" item under Paragraph 5.05.A.1, it may be submitted as a proposed substitute item. b. Contractor shall submit sufficient information as provided below to allow City to determine if the item of material or equipment proposed is essentially equivalent to that named and an acceptable substitute therefor. Requests for review of proposed substitute items of material or equipment will not be accepted by City from anyone other than Contractor. c. Contractor shall make written application to City for review of a proposed substitute item of material or equipment that Contractor seeks to furnish or use. The application shall comply with Section 0125 00 and: 1) shall certify that the proposed substitute item will: i. perform adequately the functions and achieve the results called for by the general design; ii. be similar in substance to that specified; iii. be suited to the same use as that specified; and 2) will state: i. the extent, if any, to which the use of the proposed substitute item will prejudice Contractor's achievement of final completion on time; ii. whether use of the proposed substitute item in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with City for other work on the Project) to adapt the design to the proposed substitute item; iii. whether incorporation or use of the proposed substitute item in connection with the Work is subject to payment of any license fee or royalty; and 3) will identify: i. all variations of the proposed substitute item from that specified; ii. available engineering, sales, maintenance, repair, and replacement services; and CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 16 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 16 of 35 4) shall contain an itemized estimate of all costs or credits that will result directly or indirectly from use of such substitute item, including costs of redesign and Damage Claims of other contractors affected by any resulting change. B. Substitute Construction Methods or Procedures: If a specific means, method, technique, sequence, or procedure of construction is expressly required by the Contract Documents, Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure of construction approved by City. Contractor shall submit sufficient information to allow City, in City's sole discretion, to determine that the substitute proposed is equivalent to that expressly called for by the Contract Documents. Contractor shall make written application to City for review in the same manner as those provided in Paragraph 5.05.A.2. C. City's Evaluation: City will be allowed a reasonable time within which to evaluate each proposal or submittal made pursuant to Paragraphs 5.05.A and 5.05.13. City may require Contractor to furnish additional data about the proposed substitute. City will be the sole judge of acceptability. No "or -equal" or substitute will be ordered, installed or utilized until City's review is complete, which will be evidenced by a Change Order in the case of a substitute and an accepted Submittal for an "or -equal." City will advise Contractor in writing of its determination. D. Special Guarantee: City may require Contractor to furnish at Contractor's expense a special performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall indemnify and hold harmless City and anyone directly or indirectly employed by them from and against any and all claims, damages, losses and expenses (including attorneys fees) arising out of the use of substituted materials or equipment. E. City's Cost Reimbursement: City will record City's costs in evaluating a substitute proposed or submitted by Contractor pursuant to Paragraphs 5.05.A.2 and 5.05.B. Whether or not City approves a substitute so proposed or submitted by Contractor, Contractor may be required to reimburse City for evaluating each such proposed substitute. Contractor may also be required to reimburse City for the charges for making changes in the Contract Documents. F. Contractor's Expense: Contractor shall provide all data in support of any proposed substitute or "or -equal" at Contractor's expense. G. Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute shall be incorporated to the Contract by Participating Change Order. 5.06 Pre -Qualification of Bidders (Prime Contractors and Subcontractors) A. The Contractor and any subcontractors are required to be prequalified for the work types requiring pre -qualification 5.07 Concerning Subcontractors, Suppliers, and Others A. Minority and Women Owned Business Enterprise Compliance: CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 17 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 17 of 35 ❑ Required for this Contract. (Check this box if there is any City Participation) ❑ Not Required for this Contract. It is City policy to ensure the full and equitable participation by Minority and Women Business Enterprises (MWBE) in the procurement of goods and services on a contractual basis. If the Contract Documents provide for a MWBE goal, Contractor is required to comply with the intent of the City's MWBE Ordinance (as amended) by the following: 1. Contractor shall, upon request by City, provide complete and accurate information regarding actual work performed by a MWBE on the Contract and payment therefor. 2. Contractor will not make additions, deletions, or substitutions of accepted MWBE without written consent of the City. Any unjustified change or deletion shall be a material breach of Contract and may result in debarment in accordance with the procedures outlined in the Ordinance. 3. Contractor shall, upon request by City, allow an audit and/or examination of any books, records, or files in the possession of the Contractor that will substantiate the actual work performed by an MWBE. Material misrepresentation of any nature will be grounds for termination of the Contract. Any such misrepresentation may be grounds for disqualification of Contractor to bid on future contracts with the City for a period of not less than three years. B. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work just as Contractor is responsible for Contractor's own acts and omissions. Nothing in the Contract Documents: 1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity any contractual relationship between City and any such Subcontractor, Supplier or other individual or entity; nor 2. shall create any obligation on the part of City to pay or to see to the payment of any moneys due any such Subcontractor, Supplier, or other individual or entity except as may otherwise be required by Laws and Regulations. C. Contractor shall be solely responsible for scheduling and coordinating the Work of Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work under a direct or indirect contract with Contractor. D. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing any of the Work shall communicate with City through Contractor. E. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an appropriate agreement between Contractor and the Subcontractor or Supplier which specifically binds the Subcontractor or Supplier to the applicable terms and conditions of these Contract CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 18 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 18 of 35 Documents, Contractor shall provide City contract numbers and reference numbers to the Subcontractors and/or Suppliers. 5.08 Wage Rates ❑ Required for this Contract. ❑ Not Required for this Contract. A. Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of Chapter 2258, Texas Government Code (as amended), including the payment of not less than the rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in accordance with Chapter 2258. Such prevailing wage rates are included in these Contract Documents. B. Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage shall, upon demand made by the City, pay to the City $60 for each worker employed for each calendar day or part of the day that the worker is paid less than the prevailing wage rates stipulated in these contract documents. This penalty shall be retained by the City to offset its administrative costs, pursuant to Texas Government Code 2258.023. C. Complaints of Violations and City Determination of Good Cause. On receipt of information, including a complaint by a worker, concerning an alleged violation of 2258.023, Texas Government Code, by a Contractor or Subcontractor, the City shall make an initial determination, before the 31 st day after the date the City receives the information, as to whether good cause exists to believe that the violation occurred. The City shall notify in writing the Contractor or Subcontractor and any affected worker of its initial determination. Upon the City's determination that there is good cause to believe the Contractor or Subcontractor has violated Chapter 2258, the City shall retain the full amounts claimed by the claimant or claimants as the difference between wages paid and wages due under the prevailing wage rates, such amounts being subtracted from successive progress payments pending a final determination of the violation. D. Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected worker, shall be submitted to binding arbitration in accordance with the Texas General Arbitration Act (Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any affected worker does not resolve the issue by agreement before the 15th day after the date the City makes its initial determination pursuant to Paragraph C above. If the persons required to arbitrate under this section do not agree on an arbitrator before the 1 Ith day after the date that arbitration is required, a district court shall appoint an arbitrator on the petition of any of the persons. The City is not a party in the arbitration. The decision and award of the arbitrator is final and binding on all parties and may be enforced in any court of competent jurisdiction. E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3) years following the date of acceptance of the work, maintain records that show (i) the name and CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 19 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 19 of 35 occupation of each worker employed by the Contractor in the construction of the Work provided for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right to Audit, shall pertain to this inspection. F. Progress Payments. With each progress payment or payroll period, whichever is less, the Contractor shall submit an affidavit stating that the Contractor has complied with the requirements of Chapter 2258, Texas Government Code. G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at all times. H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall otherwise require all of its Subcontractors to comply with Paragraphs A through G above. 5.09 Patent Fees and Royalties A. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless City, from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to any infringement of patent rights or copyrights incident to the use in the performance of the Work or resulting from the incorporation in the Work of any invention, design, process, product, or device not specified in the Contract Documents. 5.10 Laws and Regulations A. Contractor shall give all notices required by and shall comply with all Laws and Regulations applicable to the performance of the Work. Except where otherwise expressly required by applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor's compliance with any Laws or Regulations. B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such Work. However, it shall not be Contractor's responsibility to make certain that the Specifications and Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of Contractor's obligations under Paragraph 3.01. 5.11 Use of Site and Other Areas A. Limitation on Use of Site and Other Areas: 1. Contractor shall confine construction equipment, the storage of materials and equipment, and the operations of workers to the Site and other areas permitted by Laws and Regulations, and shall not unreasonably encumber the Site and other areas with construction equipment or CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 20 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 20 of 35 other materials or equipment. Contractor shall assume full responsibility for any damage to any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas resulting from the performance of the Work. 2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is carrying on operations in a portion of a street, right-of-way, or easement greater than is necessary for proper execution of the Work, the City may require the Contractor to finish the section on which operations are in progress before work is commenced on any additional area of the Site. 3. Should any Damage Claim be made by any such owner or occupant because of the performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim. 4. Pursuant to Paragraph 5.18, Contractor shall indemnify and hold harmless City, from and against all claims, costs, losses, and damages arising out of or relating to any claim or action, legal or equitable, brought by any such owner or occupant against City. B. Removal of Debris During Performance of the Work: During the progress of the Work Contractor shall keep the Site and other areas free from accumulations of waste materials, rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other debris shall conform to applicable Laws and Regulations. C. Site Maintenance Cleaning: 24 hours after written notice is given to the Contractor that the clean-up on the job site is proceeding in a manner unsatisfactory to the City or Developer, if the Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the written notice (by letter or electronic communication), and shall be entitled to recover its cost in doing so. The City may withhold Final Acceptance until clean-up is complete and cost are recovered. D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and the Work and make it ready for utilization by City or adjacent property owner. At the completion of the Work Contractor shall remove from the Site all tools, appliances, construction equipment and machinery, and surplus materials and shall restore to original condition or better all property disturbed by the Work. E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded in any manner that will endanger the structure, nor shall Contractor subject any part of the Work or adjacent property to stresses or pressures that will endanger it. 5.12 Record Documents A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor and approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change Orders, Field Orders, and written interpretations and clarifications in good order and annotated to show changes made during construction. These record documents together with all approved CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 21 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 21 of 35 Samples and a counterpart of all accepted Submittals will be available to City for reference. Upon completion of the Work, these record documents, any operation and maintenance manuals, and Submittals will be delivered to City prior to Final Inspection. Contractor shall include accurate locations for buried and imbedded items. 5.13 Safety and Protection A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work. Such responsibility does not relieve Subcontractors of their responsibility for the safety of persons or property in the performance of their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury or loss to: 1. all persons on the Site or who may be affected by the Work; 2. all the Work and materials and equipment to be incorporated therein, whether in storage on or off the Site; and 3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures, utilities, and Underground Facilities not designated for removal, relocation, or replacement in the course of construction. B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of persons or property, or to the protection of persons or property from damage, injury, or loss; and shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall notify owners of adjacent property and of Underground Facilities and other utility owners when prosecution of the Work may affect them, and shall cooperate with them in the protection, removal, relocation, and replacement of their property. C. Contractor shall comply with the applicable requirements of City's safety programs, if any. D. Contractor shall inform City of the specific requirements of Contractor's safety program, if any, with which City's employees and representatives must comply while at the Site. E. All damage, injury, or loss to any property referred to in Paragraph 5.13.A.2 or 5.13.A.3 caused, directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any other individual or entity directly or indirectly employed by any of them to perform any of the Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor. F. Contractor's duties and responsibilities for safety and for protection of the Work shall continue until such time as all the Work is completed and City has accepted the Work. 5.14 Safety Representative Contractor shall inform City in writing of Contractor's designated safety representative at the Site. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 22 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 22 of 35 5.15 Hazard Communication Programs Contractor shall be responsible for coordinating any exchange of material safety data sheets or other hazard communication information required to be made available to or exchanged between or among employers in accordance with Laws or Regulations. 5.16 Submittals A. Contractor shall submit required Submittals to City for review and acceptance. Each submittal will be identified as required by City. 1. Submit number of copies specified in the General Requirements. 2. Data shown on the Submittals will be complete with respect to quantities, dimensions, specified performance and design criteria, materials, and similar data to show City the services, materials, and equipment Contractor proposes to provide and to enable City to review the information for the limited purposes required by Paragraph 5.16.C. 3. Submittals submitted as herein provided by Contractor and reviewed by City for conformance with the design concept shall be executed in conformity with the Contract Documents unless otherwise required by City. 4. When Submittals are submitted for the purpose of showing the installation in greater detail, their review shall not excuse Contractor from requirements shown on the Drawings and Specifications. 5. For -Information -Only submittals upon which the City is not expected to conduct review or take responsive action may be so identified in the Contract Documents. 6. Submit required number of Samples specified in the Specifications. 7. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers, the use for which intended and other data as City may require to enable City to review the submittal for the limited purposes required by Paragraph 5.16.C. B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any related Work performed prior to City's review and acceptance of the pertinent submittal will be at the sole expense and responsibility of Contractor. C. City's Review: 1. City will provide timely review of required Submittals in accordance with the Schedule of Submittals acceptable to City. City's review and acceptance will be only to determine if the items covered by the submittals will, after installation or incorporation in the Work, conform to the information given in the Contract Documents and be compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 23 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 23 of 35 2. City's review and acceptance will not extend to means, methods, techniques, sequences, or procedures of construction (except where a particular means, method, technique, sequence, or procedure of construction is specifically and expressly called for by the Contract Documents) or to safety precautions or programs incident thereto. The review and acceptance of a separate item as such will not indicate approval of the assembly in which the item functions. 3. City's review and acceptance shall not relieve Contractor from responsibility for any variation from the requirements of the Contract Documents unless Contractor has complied with the requirements of Section 01 33 00 and City has given written acceptance of each such variation by specific written notation thereof incorporated in or accompanying the Submittal. City's review and acceptance shall not relieve Contractor from responsibility for complying with the requirements of the Contract Documents. 5.17 Contractor's General Warranty and Guarantee A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract Documents and will not be defective. City and its officers, directors, members, partners, employees, agents, consultants, and subcontractors shall be entitled to rely on representation of Contractor's warranty and guarantee. B. Contractor's warranty and guarantee hereunder excludes defects or damage caused by: 1. abuse, modification, or improper maintenance or operation by persons other than Contractor, Subcontractors, Suppliers, or any other individual or entity for whom Contractor is responsible; or 2. normal wear and tear under normal usage. C. Contractor's obligation to perform and complete the Work in accordance with the Contract Documents shall be absolute. None of the following will constitute an acceptance of Work that is not in accordance with the Contract Documents or a release of Contractor's obligation to perform the Work in accordance with the Contract Documents: 1. observations by City; 2. recommendation or payment by City or Developer of any progress or final payment; 3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by City; 4. use or occupancy of the Work or any part thereof by City; 5. any review and acceptance of a Submittal by City; 6. any inspection, test, or approval by others; or CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 24 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 24 of 35 7. any correction of defective Work by City. D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to other work or property resulting therefrom which shall appear within a period of two (2) years from the date of Final Acceptance of the Work unless a longer period is specified and shall furnish a good and sufficient maintenance bond, complying with the requirements of Article 4.02.13. The City will give notice of observed defects with reasonable promptness. 5.18 Indemnification A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the City, its officers, servants and employees, from and against any and all claims arising out of, or alleged to arise out of, the work and services to be performed by the Contractor, its officers, agents, employees, subcontractors, licenses or invitees under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. This indemnity provision is intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by the City in defending against such claims and causes of actions. B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its officers, servants and employees, from and against any and all loss, damage or destruction of property of the City, arising out of, or alleged to arise out of, the work and services to be performed by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. 5.19 Delegation of Professional Design Services A. Contractor will not be required to provide professional design services unless such services are specifically required by the Contract Documents for a portion of the Work or unless such services are required to carry out Contractor's responsibilities for construction means, methods, techniques, sequences and procedures. B. If professional design services or certifications by a design professional related to systems, materials or equipment are specifically required of Contractor by the Contract Documents, City will specify all performance and design criteria that such services must satisfy. Contractor shall cause such services or certifications to be provided by a properly licensed professional, whose signature and seal shall appear on all drawings, calculations, specifications, certifications, and Submittals prepared by such professional. Submittals related to the Work designed or certified by such professional, if prepared by others, shall bear such professional's written approval when submitted to City. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 25 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 25 of 35 C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services, certifications or approvals performed by such design professionals, provided City has specified to Contractor performance and design criteria that such services must satisfy. D. Pursuant to this Paragraph 5.19, City's review and acceptance of design calculations and design drawings will be only for the limited purpose of checking for conformance with performance and design criteria given and the design concept expressed in the Contract Documents. City's review and acceptance of Submittals (except design calculations and design drawings) will be only for the purpose stated in Paragraph 5.16.C. 5.20 Right to Audit: A. The City reserves the right to audit all projects utilizing City funds B. The Contractor agrees that the City shall, until the expiration of three (3) years after final payment under this Contract, have access to and the right to examine and photocopy any directly pertinent books, documents, papers, and records of the Contractor involving transactions relating to this Contract. Contractor agrees that the City shall have access during Regular Working Hours to all necessary Contractor facilities and shall be provided adequate and appropriate work space in order to conduct audits in compliance with the provisions of this Paragraph. The City shall give Contractor reasonable advance notice of intended audits. C. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that the subcontractor agrees that the City shall, until the expiration of three (3) years after final payment under this Contract, have access to and the right to examine and photocopy any directly pertinent books, documents, papers, and records of such Subcontractor, involving transactions to the subcontract, and further, that City shall have access during Regular Working Hours to all Subcontractor facilities, and shall be provided adequate and appropriate work space in order to conduct audits in compliance with the provisions of this Paragraph. The City shall give Subcontractor reasonable advance notice of intended audits. D. Contractor and Subcontractor agree to photocopy such documents as may be requested by the City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate published in the Texas Administrative Code in effect as of the time copying is performed. 5.21 Nondiscrimination A. The City is responsible for operating Public Transportation Programs and implementing transit - related projects, which are funded in part with Federal financial assistance awarded by the U.S. Department of Transportation and the Federal Transit Administration (FTA), without discriminating against any person in the United States on the basis of race, color, or national origin. B. Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of the Act and the Regulations as further defined in the Supplementary Conditions for any project receiving Federal assistance. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 26 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 26 of 35 ARTICLE 6 — OTHER WORK AT THE SITE 6.01 Related Work at Site A. City may perform other work related to the Project at the Site with City's employees, or other City contractors, or through other direct contracts therefor, or have other work performed by utility owners. If such other work is not noted in the Contract Documents, then written notice thereof will be given to Contractor prior to starting any such other work; and B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility owner, and City, if City is performing other work with City's employees or other City contractors, proper and safe access to the Site, provide a reasonable opportunity for the introduction and storage of materials and equipment and the execution of such other work, and properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of the Work that may be required to properly connect or otherwise make its several parts come together and properly integrate with such other work. Contractor shall not endanger any work of others by cutting, excavating, or otherwise altering such work; provided, however, that Contractor may cut or alter others' work with the written consent of City and the others whose work will be affected. C. If the proper execution or results of any part of Contractor's Work depends upon work performed by others under this Article 7, Contractor shall inspect such other work and promptly report to City in writing any delays, defects, or deficiencies in such other work that render it unavailable or unsuitable for the proper execution and results of Contractor's Work. Contractor's failure to so report will constitute an acceptance of such other work as fit and proper for integration with Contractor's Work except for latent defects in the work provided by others. ARTICLE 7 — CITY'S RESPONSIBILITIES 7.01 Inspections, Tests, and Approvals City's responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph 11.03. 7.02 Limitations on City's Responsibilities A. The City shall not supervise, direct, or have control or authority over, nor be responsible for, Contractor's means, methods, techniques, sequences, or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of Contractor to comply with Laws and Regulations applicable to the performance of the Work. City will not be responsible for Contractor's failure to perform the Work in accordance with the Contract Documents. B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 5.13. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 27 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 27 of 35 7.03 Compliance with Safety Program While at the Site, City's employees and representatives shall comply with the specific applicable requirements of Contractor's safety programs of which City has been informed pursuant to Paragraph 5.13. ARTICLE 8 — CITY'S OBSERVATION STATUS DURING CONSTRUCTION 8.01 City's Project Representative City will provide one or more Project Representative(s) during the construction period. The duties and responsibilities and the limitations of authority of City's representative during construction are set forth in the Contract Documents. A. City's Project Representative will make visits to the Site at intervals appropriate to the various stages of construction as City deems necessary in order to observe the progress that has been made and the quality of the various aspects of Contractor's executed Work. Based on information obtained during such visits and observations, City's Project Representative will determine, in general, if the Work is proceeding in accordance with the Contract Documents. City's Project Representative will not be required to make exhaustive or continuous inspections on the Site to check the quality or quantity of the Work. City's Project Representative's efforts will be directed toward providing City a greater degree of confidence that the completed Work will conform generally to the Contract Documents. B. City's Project Representative's visits and observations are subject to all the limitations on authority and responsibility in the Contract Documents. 8.02 Authorized Variations in Work City's Project Representative may authorize minor variations in the Work from the requirements of the Contract Documents which do not involve an adjustment in the Contract Price or the Contract Time and are compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. These may be accomplished by a Field Order and will be binding on City Developer, and also on Contractor, who shall perform the Work involved promptly. 8.03 Rejecting Defective Work City will have authority to reject Work which City's Project Representative believes to be defective, or will not produce a completed Project that conforms to the Contract Documents or that will prejudice the integrity of the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. City will have authority to conduct special inspection or testing of the Work as provided in Article 11, whether or not the Work is fabricated, installed, or completed. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 28 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 28 of 35 8.04 Determinations for Work Performed Contractor will determine the actual quantities and classifications of Work performed. City's Project Representative will review with Contractor the preliminary determinations on such matters before rendering a written recommendation. City's written decision will be final (except as modified to reflect changed factual conditions or more accurate data). ARTICLE 9 — CHANGES IN THE WORK 9.01 Authorized Changes in the Work A. Without invalidating the Contract and without notice to any surety, City may, at any time or from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall promptly proceed with the Work involved which will be performed under the applicable conditions of the Contract Documents (except as otherwise specifically provided). Extra Work shall be memorialized by a Participating Change Order which may or may not precede an order of Extra work. B. For minor changes of Work not requiring changes to Contract Time or Contract Price on a project with City participation, a Field Order may be issued by the City. 9.02 Notification to Surety If the provisions of any bond require notice to be given to a surety of any change affecting the general scope of the Work or the provisions of the Contract Documents (including, but not limited to, Contract Price or Contract Time), the giving of any such notice will be Contractor's responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the effect of any such change. ARTICLE 10 — CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME 10.01 Change of Contract Price A. The Contract Price may only be changed by a Participating Change Order for projects with City participation. 10.02 Change of Contract Time A. The Contract Time may only be changed by a Participating Change Order for projects with City participation. 10.03 Delays A. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) sustained by Contractor on or in connection with any other project or anticipated project. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 29 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 29 of 35 ARTICLE 11— TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK 11.01 Notice of Defects Notice of all defective Work of which City has actual knowledge will be given to Contractor. Defective Work may be rejected, corrected, or accepted as provided in this Article 13. 11.02 Access to Work City, independent testing laboratories, and governmental agencies with jurisdictional interests will have access to the Site and the Work at reasonable times for their observation, inspection, and testing. Contractor shall provide them proper and safe conditions for such access and advise them of Contractor's safety procedures and programs so that they may comply therewith as applicable. 11.03 Tests and Inspections A. Contractor shall give City timely notice of readiness of the Work for all required inspections, tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required inspections or tests. B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any of the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full responsibility for arranging and obtaining such independent inspections, tests, retests or approvals, pay all costs in connection therewith, and furnish City the required certificates of inspection or approval; excepting, however, those fees specifically identified in the Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR) inspections, which shall be paid as described in the Supplementary Conditions. C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection with any inspections, tests, re -tests, or approvals required for City's acceptance of materials or equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment submitted for approval prior to Contractor's purchase thereof for incorporation in the Work. Such inspections, tests, re -tests, or approvals shall be performed by organizations approved by City. D. City may arrange for the services of an independent testing laboratory ("Testing Lab") to perform any inspections or tests ("Testing") for any part of the Work, as determined solely by City. 1. City will coordinate such Testing to the extent possible, with Contractor; 2. Should any Testing under this Section 11.03 D result in a "fail", "did not pass" or other similar negative result, the Contractor shall be responsible for paying for any and all retests. Contractor's cancellation without cause of City initiated Testing shall be deemed a negative result and require a retest. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 30 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 30 of 35 3. Any amounts owed for any retest under this Section 11.03 D shall be paid directly to the Testing Lab by Contractor. Developer/Contractor. City will forward all invoices for retests to 4. If Contractor fails to pay the Testing Lab, City will not issue a letter of Final Acceptance until the Testing Lab is Paid E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by Contractor without written concurrence of City, Contractor shall, if requested by City, uncover such Work for observation. 11.04 Uncovering Work A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it must, if requested by City, be uncovered for City's observation and replaced at Contractor's expense. 11.05 City May Stop the Work If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials or equipment, or fails to perform the Work in such a way that the completed Work will conform to the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, this right of City to stop the Work shall not give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent of any of them. 11.06 Correction or Removal of Defective Work A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has been rejected by City, remove it from the Project and replace it with Work that is not defective. Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such correction or removal (including but not limited to all costs of repair or replacement of work of others). Failure to require the removal of any defective Work shall not constitute acceptance of such Work. B. When correcting defective Work under the terms of this Paragraph 11.06 or Paragraph 11.07, Contractor shall take no action that would void or otherwise impair City's special warranty and guarantee, if any, on said Work. 11.07 Correction Period A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may be prescribed by the terms of any applicable special guarantee required by the Contract CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 31 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 31 of 35 Documents), any Work is found to be defective, or if the repair of any damages to the land or areas made available for Contractor's use by City or permitted by Laws and Regulations as contemplated in Paragraph 5.10.A is found to be defective, Contractor shall promptly, without cost to City and in accordance with City's written instructions: 1. repair such defective land or areas; or 2. correct such defective Work; or 3. if the defective Work has been rejected by City, remove it from the Project and replace it with Work that is not defective, and 4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work of others or other land or areas resulting therefrom. B. If Contractor does not promptly comply with the terms of City's written instructions, or in an emergency where delay would cause serious risk of loss or damage, City may have the defective Work corrected or repaired or may have the rejected Work removed and replaced. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) arising out of or relating to such correction or repair or such removal and replacement (including but not limited to all costs of repair or replacement of work of others) will be paid by Contractor. C. Where defective Work (and damage to other Work resulting therefrom) has been corrected or removed and replaced under this Paragraph 11.07, the correction period hereunder with respect to such Work may be required to be extended for an additional period of one year after the end of the initial correction period. City shall provide 30 days written notice to Contractor and Developer should such additional warranty coverage be required. Contractor's obligations under this Paragraph 11.07 are in addition to any other obligation or warranty. The provisions of this Paragraph 11.07 shall not be construed as a substitute for, or a waiver of, the provisions of any applicable statute of limitation or repose. 11.08 City May Correct Defective Work A. If Contractor fails within a reasonable time after written notice from City to correct defective Work, or to remove and replace rejected Work as required by City in accordance with Paragraph 11.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents, or if Contractor fails to comply with any other provision of the Contract Documents, City may, after seven (7) days written notice to Contractor and the Developer, correct, or remedy any such deficiency. B. In exercising the rights and remedies under this Paragraph 11.09, City shall proceed expeditiously. In connection with such corrective or remedial action, City may exclude Contractor from all or part of the Site, take possession of all or part of the Work and suspend Contractor's services related thereto, and incorporate in the Work all materials and equipment incorporated in the Work, stored at the Site or for which City has paid Contractor but which are CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 32 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 32 of 35 stored elsewhere. Contractor shall allow City, City's representatives, agents, consultants, employees, and City's other contractors, access to the Site to enable City to exercise the rights and remedies under this Paragraph. C. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph 13.09 will be charged against Contractor, and a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work; and City shall be entitled to an appropriate decrease in the Contract Price. D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the performance of the Work attributable to the exercise of City's rights and remedies under this Paragraph 11.09. ARTICLE 12 — COMPLETION 12.01 Contractor's Warranty of Title Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any Application for Payment will pass to City no later than the time of Final Acceptance and shall be free and clear of all Liens. 12.02 Partial Utilization A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed part of the Work which has specifically been identified in the Contract Documents, or which City, determines constitutes a separately functioning and usable part of the Work that can be used by City for its intended purpose without significant interference with Contractor's performance of the remainder of the Work. City at any time may notify Contractor in writing to permit City to use or occupy any such part of the Work which City determines to be ready for its intended use, subject to the following conditions: 1. Contractor at any time may notify City in writing that Contractor considers any such part of the Work ready for its intended use. 2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and Contractor shall make an inspection of that part of the Work to determine its status of completion. If City does not consider that part of the Work to be substantially complete, City will notify Contractor in writing giving the reasons therefor. 3. Partial Utilization will not constitute Final Acceptance by City. 12.03 Final Inspection A. Upon written notice from Contractor that the entire Work is complete in accordance with the Contract Documents: CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 33 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 33 of 35 1. within 10 days, City will schedule a Final Inspection with Contractor. 2. City will notify Contractor in writing of all particulars in which this inspection reveals that the Work is incomplete or defective. Contractor shall immediately take such measures as are necessary to complete such Work or remedy such deficiencies. 12.04 Final Acceptance A. Upon completion by Contractor to City's satisfaction, of any additional Work identified in the Final Inspection, City will issue to Contractor a letter of Final Acceptance upon the satisfaction of the following: 1. All documentation called for in the Contract Documents, including but not limited to the evidence of insurance required by Paragraph 5.03; 2. consent of the surety, if any, to Final Acceptance; 3. a list of all pending or released Damage Claims against City that Contractor believes are unsettled; and 4. affidavits of payments and complete and legally effective releases or waivers (satisfactory to City) of all Lien rights arising out of or Liens filed in connection with the Work. 5. after all Damage Claims have been resolved: a. directly by the Contractor or; b. Contractor provides evidence that the Damage Claim has been reported to Contractor's insurance provider for resolution. 6. Issuing Final Acceptance by the City shall not relieve the Contractor of any guarantees or other requirements of the Contract Documents which specifically continue thereafter. ARTICLE 13 — SUSPENSION OF WORK 13.01 City May Suspend Work A. At any time and without cause, City may suspend the Work or any portion thereof by written notice to Contractor and which may fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. During temporary suspension of the Work covered by these Contract Documents, for any reason, the City will stop contract time on City participation projects. B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the control of and without the fault or negligence of the Contractor, and should it be determined by mutual consent of the Contractor and City that a solution to allow construction to proceed is not CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 34 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 34 of 35 available within a reasonable period of time, Contractor may request an extension in Contract Time, directly attributable to any such suspension. C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall store all materials in such a manner that they will not obstruct or impede the public unnecessarily nor become damaged in any way, and he shall take every precaution to prevent damage or deterioration of the work performed; he shall provide suitable drainage about the work, and erect temporary structures where necessary. ARTICLE 14 — MISCELLANEOUS 14.01 Giving Notice A. Whenever any provision of the Contract Documents requires the giving of written notice, it will be deemed to have been validly given i£ 1. delivered in person to the individual or to a member of the firm or to an officer of the corporation for whom it is intended; or 2. delivered at or sent by registered or certified mail, postage prepaid, to the last business address known to the giver of the notice. B. Business address changes must be promptly made in writing to the other party. C. Whenever the Contract Documents specifies giving notice by electronic means such electronic notice shall be deemed sufficient upon confirmation of receipt by the receiving party. 14.02 Computation of Times When any period of time is referred to in the Contract Documents by days, it will be computed to exclude the first and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last day of the period. 14.03 Cumulative Remedies The duties and obligations imposed by these General Conditions and the rights and remedies available hereunder to the parties hereto are in addition to, and are not to be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically in the Contract Documents in connection with each particular duty, obligation, right, and remedy to which they apply. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 00 73 10- 35 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 35 of 35 14.04 Survival of Obligations All representations, indemnifications, warranties, and guarantees made in, required by, or given in accordance with the Contract Documents, as well as all continuing obligations indicated in the Contract Documents, will survive final payment, completion, and acceptance of the Work or termination or completion of the Contract or termination of the services of Contractor. 14.05 Headings Article and paragraph headings are inserted for convenience only and do not constitute parts of these General Conditions. CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1 2 3 PART1- GENERAL 4 1.1 SUMMARY SECTION 01 11 00 SUMMARY OF WORK 011100-1 DAP SUMMARY OF WORK Pagel of 3 5 A. Section Includes: 6 1. Summary of Work to be performed in accordance with the Contract Documents 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract 11 2. Division 1 - General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered subsidiary to the various items bid. 15 No separate payment will be allowed for this Item. 16 1.3 REFERENCES [NOT USED] 17 1.4 ADMINISTRATIVE REQUIREMENTS 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 A. Work Covered by Contract Documents 1. Work is to include furnishing all labor, materials, and equipment, and performing all Work necessary for this construction project as detailed in the Drawings and Specifications. B. Subsidiary Work 1. Any and all Work specifically governed by documentary requirements for the project, such as conditions imposed by the Drawings or Contract Documents in which no specific item for bid has been provided for in the Proposal and the item is not a typical unit bid item included on the standard bid item list, then the item shall be considered as a subsidiary item of Work, the cost of which shall be included in the price bid in the Proposal for various bid items. C. Use of Premises 1. Coordinate uses of premises under direction of the City. 2. Assume full responsibility for protection and safekeeping of materials and equipment stored on the Site. 3. Use and occupy only portions of the public streets and alleys, or other public places or other rights -of -way as provided for in the ordinances of the City, as shown in the Contract Documents, or as may be specifically authorized in writing by the City. a. A reasonable amount of tools, materials, and equipment for construction purposes may be stored in such space, but no more than is necessary to avoid delay in the construction operations. CITY OF FORT WORTH Water & Sanitary Sewer to Serve Wichita Industrial STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 104140 Revised December 20, 2012 011100-2 DAP SUMMARY OF WORK Page 2 of 3 1 b. Excavated and waste materials shall be stored in such a way as not to interfere 2 with the use of spaces that may be designated to be left free and unobstructed 3 and so as not to inconvenience occupants of adjacent property. 4 c. If the street is occupied by railroad tracks, the Work shall be carried on in such 5 manner as not to interfere with the operation of the railroad. 6 1) All Work shall be in accordance with railroad requirements set forth in 7 Division 0 as well as the railroad permit. 8 D. Work within Easements 9 1. Do not enter upon private property for any purpose without having previously 10 obtained permission from the owner of such property. 11 2. Do not store equipment or material on private property unless and until the 12 specified approval of the property owner has been secured in writing by the 13 Contractor and a copy furnished to the City. 14 3. Unless specifically provided otherwise, clear all rights -of -way or easements of 15 obstructions which must be removed to make possible proper prosecution of the 16 Work as a part of the project construction operations. 17 4. Preserve and use every precaution to prevent damage to, all trees, shrubbery, plants, 18 lawns, fences, culverts, curbing, and all other types of structures or improvements, 19 to all water, sewer, and gas lines, to all conduits, overhead pole lines, or 20 appurtenances thereof, including the construction of temporary fences and to all 21 other public or private property adjacent to the Work. 22 5. Notify the proper representatives of the owners or occupants of the public or private 23 lands of interest in lands which might be affected by the Work. 24 a. Such notice shall be made at least 48 hours in advance of the beginning of the 25 Work. 26 b. Notices shall be applicable to both public and private utility companies and any 27 corporation, company, individual, or other, either as owners or occupants, 28 whose land or interest in land might be affected by the Work. 29 c. Be responsible for all damage or injury to property of any character resulting 30 from any act, omission, neglect, or misconduct in the manner or method or 31 execution of the Work, or at any time due to defective work, material, or 32 equipment. 33 6. Fence 34 a. Restore all fences encountered and removed during construction of the Project 35 to the original or a better than original condition. 36 b. Erect temporary fencing in place of the fencing removed whenever the Work is 37 not in progress and when the site is vacated overnight, and/or at all times to 38 provide site security. 39 c. The cost for all fence work within easements, including removal, temporary 40 closures and replacement, shall be subsidiary to the various items bid in the 41 project proposal, unless a bid item is specifically provided in the proposal. CITY OF FORT WORTH Water & Sanitary Sewer to Serve Wichita Industrial STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 104140 Revised December 20, 2012 011100-3 DAP SUMMARY OF WORK Page 3 of 3 1 1.5 SUBMITTALS [NOT USED] 2 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED] 3 1.7 CLOSEOUT SUBMITTALS [NOT USED] 4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 5 1.9 QUALITY ASSURANCE [NOT USED] 6 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 7 1.11 FIELD [SITE] CONDITIONS [NOT USED] 8 1.12 WARRANTY [NOT USED] 9 PART 2 - PRODUCTS [NOT USED] 10 PART 3 - EXECUTION [NOT USED] 11 END OF SECTION 12 13 Revision Log DATE NAME SUMMARY OF CHANGE CITY OF FORT WORTH Water & Sanitary Sewer to Serve Wichita Industrial STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects 104140 Revised December 20, 2012 012500-1 DAP SUBSTITUTION PROCEDURES SECTION 0125 00 SUBSTITUTION PROCEDURES PART1- GENERAL 1.1 SUMMARY A. Section Includes: Page 1 of 4 The procedure for requesting the approval of substitution of a product that is not equivalent to a product which is specified by descriptive or performance criteria or defined by reference to 1 or more of the following: a. Name of manufacturer b. Name of vendor c. Trade name d. Catalog number 2. Substitutions are not "or -equals". B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 — General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Request for Substitution - General 1. Within 30 days after award of Contract (unless noted otherwise), the City will consider formal requests from Contractor for substitution of products in place of those specified. 2. Certain types of equipment and kinds of material are described in Specifications by means of references to names of manufacturers and vendors, trade names, or catalog numbers. a. When this method of specifying is used, it is not intended to exclude from consideration other products bearing other manufacturer's or vendor's names, trade names, or catalog numbers, provided said products are "or -equals," as determined by City. 3. Other types of equipment and kinds of material may be acceptable substitutions under the following conditions: a. Or -equals are unavailable due to strike, discontinued production of products meeting specified requirements, or other factors beyond control of Contractor; or, CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 012500-2 DAP SUBSTITUTION PROCEDURES Page 2 of 4 b. Contractor proposes a cost and/or time reduction incentive to the City. 1.5 SUBMITTALS A. See Request for Substitution Form (attached) B. Procedure for Requesting Substitution 1. Substitution shall be considered only: a. After award of Contract b. Under the conditions stated herein 2. Submit 3 copies of each written request for substitution, including: a. Documentation 1) Complete data substantiating compliance of proposed substitution with Contract Documents 2) Data relating to changes in construction schedule, when a reduction is proposed 3) Data relating to changes in cost b. For products 1) Product identification a) Manufacturer's name b) Telephone number and representative contact name c) Specification Section or Drawing reference of originally specified product, including discrete name or tag number assigned to original product in the Contract Documents 2) Manufacturer's literature clearly marked to show compliance of proposed product with Contract Documents 3) Itemized comparison of original and proposed product addressing product characteristics including, but not necessarily limited to: a) Size b) Composition or materials of construction c) Weight d) Electrical or mechanical requirements 4) Product experience a) Location of past projects utilizing product b) Name and telephone number of persons associated with referenced projects knowledgeable concerning proposed product c) Available field data and reports associated with proposed product 5) Samples a) Provide at request of City. b) Samples become the property of the City. c. For construction methods: 1) Detailed description of proposed method 2) Illustration drawings C. Approval or Rejection 1. Written approval or rejection of substitution given by the City 2. City reserves the right to require proposed product to comply with color and pattern of specified product if necessary to secure design intent. 3. In the event the substitution is approved, if a reduction in cost or time results, it will be documented by Change Order. CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 012500-3 DAP SUBSTITUTION PROCEDURES Page 3 of 4 4. Substitution will be rejected if. a. Submittal is not through the Contractor with his stamp of approval b. Request is not made in accordance with this Specification Section c. In the Developer's opinion, acceptance will require substantial revision of the original design d. In the City's or Developer's opinion, substitution will not perform adequately the function consistent with the design intent 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE A. In making request for substitution or in using an approved product, the Contractor represents that the Contractor: 1. Has investigated proposed product, and has determined that it is adequate or superior in all respects to that specified, and that it will perform function for which it is intended 2. Will provide same guarantee for substitute item as for product specified 3. Will coordinate installation of accepted substitution into Work, to include building modifications if necessary, making such changes as may be required for Work to be complete in all respects 4. Waives all claims for additional costs related to substitution which subsequently arise 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 012500-4 DAP SUBSTITUTION PROCEDURES Page 4 of 4 EXHIBIT A REQUEST FOR SUBSTITUTION FORM: PROJECT: DATE: We hereby submit for your consideration the following product instead of the specified item for the above project: SECTION PARAGRAPH SPECIFIED ITEM Proposed Substitution: Reason for Substitution: Include complete information on changes to Drawings and/or Specifications which proposed substitution will require for its proper installation. Fill in Blanks Below: A. Will the undersigned contractor pay for changes to the building design, including engineering and detailing costs caused by the requested substitution? B. What effect does substitution have on other trades? C. Differences between proposed substitution and specified item? D. Differences in product cost or product delivery time? E. Manufacturer's guarantees of the proposed and specified items are: Equal Better (explain on attachment) The undersigned states that the function, appearance and quality are equivalent or superior to the specified item. Submitted By: For Use by City Signature Recommended as noted Firm Not recommended Address By Date Date Remarks Telephone For Use by City: Approved Rejected City Date Recommended Received late CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 013119-1 DAP PRECONSTRUCTION MEETING SECTION 01 31 19 PRECONSTRUCTION MEETING PART1- GENERAL 1.1 SUMMARY A. Section Includes: Page 1 of 3 1. Provisions for the preconstruction meeting to be held prior to the start of Work to clarify construction contract administration procedures B. Deviations from this City of Fort Worth Standard Specification 1. No construction schedule required unless requested by the City. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 — General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Coordination 1. Attend preconstruction meeting. 2. Representatives of Contractor, subcontractors and suppliers attending meetings shall be qualified and authorized to act on behalf of the entity each represents. 3. Meeting administered by City may be tape recorded. a. If recorded, tapes will be used to prepare minutes and retained by City for future reference. B. Preconstruction Meeting 1. A preconstruction meeting will be held within 14 days after the delivery of the distribution package to the City. a. The meeting will be scheduled and administered by the City. 2. The Project Representative will preside at the meeting, prepare the notes of the meeting and distribute copies of same to all participants who so request by fully completing the attendance form to be circulated at the beginning of the meeting. 3. Attendance shall include: a. Developer and Consultant b. Contractor's project manager c. Contractor's superintendent d. Any subcontractor or supplier representatives whom the Contractor may desire to invite or the City may request CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 01 31 19 - 2 DAP PRECONSTRUCTION MEETING Page 2 of 3 e. Other City representatives f. Others as appropriate 4. Preliminary Agenda may include: a. Introduction of Project Personnel b. General Description of Project c. Status of right-of-way, utility clearances, easements or other pertinent permits d. Contractor's work plan and schedule e. Contract Time f. Notice to Proceed g. Construction Staking h. Progress Payments i. Extra Work and Change Order Procedures j. Field Orders k. Disposal Site Letter for Waste Material 1. Insurance Renewals m. Payroll Certification n. Material Certifications and Quality Control Testing o. Public Safety and Convenience p. Documentation of Pre -Construction Conditions q. Weekend Work Notification r. Legal Holidays s. Trench Safety Plans t. Confined Space Entry Standards u. Coordination with the City's representative for operations of existing water systems v. Storm Water Pollution Prevention Plan w. Coordination with other Contractors x. Early Warning System y. Contractor Evaluation z. Special Conditions applicable to the project aa. Damages Claims bb. Submittal Procedures cc. Substitution Procedures dd. Correspondence Routing ee. Record Drawings ff. Temporary construction facilities gg. MBE/SBE procedures hh. Final Acceptance ii. Final Payment J. Questions or Comments CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 013119-3 DAP PRECONSTRUCTION MEETING Page 3 of 3 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 013216-1 DAP CONSTRUCTION PROGRESS SCHEDULE Page 1 of 5 SECTION 0132 16 CONSTRUCTION PROGRESS SCHEDULE PART1- GENERAL 1.1 SUMMARY A. Section Includes: 1. General requirements for the preparation, submittal, updating, status reporting and management of the Construction Progress Schedule 2. Specific requirements are presented in the City of Fort Worth Schedule Guidance Document B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 — General Requirements IWAKUW41W.Iel7Z%140IBlel89ZIZy011117V A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES A. Definitions 1. Schedule Tiers a. Tier 1 - No schedule submittal required by contract. Small, brief duration projects b. Tier 2 - No schedule submittal required by contract, but will require some milestone dates. Small, brief duration projects c. Tier 3 - Schedule submittal required by contract as described in the Specification and herein. Majority of City projects, including all bond program projects d. Tier 4 - Schedule submittal required by contract as described in the Specification and herein. Large and/or complex projects with long durations 1) Examples: large water pump station project and associated pipeline with interconnection to another governmental entity e. Tier 5 - Schedule submittal required by contract as described in the Specification and herein. Large and/or very complex projects with long durations, high public visibility 1) Examples might include a water or wastewater treatment plant 2. Baseline Schedule - Initial schedule submitted before work begins that will serve as the baseline for measuring progress and departures from the schedule. 3. Progress Schedule - Monthly submittal of a progress schedule documenting progress on the project and any changes anticipated. CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 013216-2 DAP CONSTRUCTION PROGRESS SCHEDULE Page 2 of 5 4. Schedule Narrative - Concise narrative of the schedule including schedule changes, expected delays, key schedule issues, critical path items, etc B. Reference Standards 1. City of Fort Worth Schedule Guidance Document 1.4 ADMINISTRATIVE REQUIREMENTS A. Baseline Schedule 1. General a. Prepare a cost -loaded baseline Schedule using approved software and the Critical Path Method (CPM) as required in the City of Fort Worth Schedule Guidance Document. b. Review the draft cost -loaded baseline Schedule with the City to demonstrate understanding of the work to be performed and known issues and constraints related to the schedule. c. Designate an authorized representative (Project Scheduler) responsible for developing and updating the schedule and preparing reports. B. Progress Schedule 1. Update the progress Schedule monthly as required in the City of Fort Worth Schedule Guidance Document. 2. Prepare the Schedule Narrative to accompany the monthly progress Schedule. 3. Change Orders a. Incorporate approved change orders, resulting in a change of contract time, in the baseline Schedule in accordance with City of Fort Worth Schedule Guidance Document. C. Responsibility for Schedule Compliance 1. Whenever it becomes apparent from the current progress Schedule and CPM Status Report that delays to the critical path have resulted and the Contract completion date will not be met, or when so directed by the City, make some or all of the following actions at no additional cost to the City a. Submit a Recovery Plan to the City for approval revised baseline Schedule outlining: 1) A written statement of the steps intended to take to remove or arrest the delay to the critical path in the approved schedule 2) Increase construction manpower in such quantities and crafts as will substantially eliminate the backlog of work and return current Schedule to meet projected baseline completion dates 3) Increase the number of working hours per shift, shifts per day, working days per week, the amount of construction equipment, or any combination of the foregoing, sufficiently to substantially eliminate the backlog of work 4) Reschedule activities to achieve maximum practical concurrency of accomplishment of activities, and comply with the revised schedule 2. If no written statement of the steps intended to take is submitted when so requested by the City, the City may direct the Contractor to increase the level of effort in manpower (trades), equipment and work schedule (overtime, weekend and holiday work, etc.) to be employed by the Contractor in order to remove or arrest the delay to the critical path in the approved schedule. a. No additional cost for such work will be considered. CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 013216-3 DAP CONSTRUCTION PROGRESS SCHEDULE Page 3 of 5 D. The Contract completion time will be adjusted only for causes specified in this Contract. a. Requests for an extension of any Contract completion date must be supplemented with the following: 1) Furnish justification and supporting evidence as the City may deem necessary to determine whether the requested extension of time is entitled under the provisions of this Contract. a) The City will, after receipt of such justification and supporting evidence, make findings of fact and will advise the Contractor, in writing thereof. 2) If the City finds that the requested extension of time is entitled, the City's determination as to the total number of days allowed for the extensions shall be based upon the approved total baseline schedule and on all data relevant to the extension. a) Such data shall be included in the next updating of the Progress schedule. b) Actual delays in activities which, according to the Baseline schedule, do not affect any Contract completion date shown by the critical path in the network will not be the basis for a change therein. 2. Submit each request for change in Contract completion date to the City within 30 days after the beginning of the delay for which a time extension is requested but before the date of final payment under this Contract. a. No time extension will be granted for requests which are not submitted within the foregoing time limit. b. From time to time, it may be necessary for the Contract schedule or completion time to be adjusted by the City to reflect the effects of job conditions, weather, technical difficulties, strikes, unavoidable delays on the part of the City or its representatives, and other unforeseeable conditions which may indicate schedule adjustments or completion time extensions. 1) Under such conditions, the City will direct the Contractor to reschedule the work or Contract completion time to reflect the changed conditions and the Contractor shall revise his schedule accordingly. a) No additional compensation will be made to the Contractor for such schedule changes except for unavoidable overall contract time extensions beyond the actual completion of unaffected work, in which case the Contractor shall take all possible action to minimize any time extension and any additional cost to the City. b) Available float time in the Baseline schedule may be used by the City as well as by the Contractor. 3. Float or slack time is defined as the amount of time between the earliest start date and the latest start date or between the earliest finish date and the latest finish date of a chain of activities on the Baseline Schedule. a. Float or slack time is not for the exclusive use or benefit of either the Contractor or the City. b. Proceed with work according to early start dates, and the City shall have the right to reserve and apportion float time according to the needs of the project. CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 013216-4 DAP CONSTRUCTION PROGRESS SCHEDULE Page 4 of 5 c. Acknowledge and agree that actual delays, affecting paths of activities containing float time, will not have any effect upon contract completion times, providing that the actual delay does not exceed the float time associated with those activities. E. Coordinating Schedule with Other Contract Schedules 1. Where work is to be performed under this Contract concurrently with or contingent upon work performed on the same facilities or area under other contracts, the Baseline Schedule shall be coordinated with the schedules of the other contracts. a. Obtain the schedules of the other appropriate contracts from the City for the preparation and updating of Baseline schedule and make the required changes in his schedule when indicated by changes in corresponding schedules. 2. In case of interference between the operations of different contractors, the City will determine the work priority of each contractor and the sequence of work necessary to expedite the completion of the entire Project. a. In such cases, the decision of the City shall be accepted as final. b. The temporary delay of any work due to such circumstances shall not be considered as justification for claims for additional compensation. 1.5 SUBMITTALS A. Baseline Schedule 1. Submit Schedule in native file format and pdf format as required in the City of Fort Worth Schedule Guidance Document. a. Native file format includes: 1) Primavera (P6 or Primavera Contractor) 2. Submit draft baseline Schedule to City prior to the pre -construction meeting and bring in hard copy to the meeting for review and discussion. B. Progress Schedule 1. Submit progress Schedule in native file format and pdf format as required in the City of Fort Worth Schedule Guidance Document. 2. Submit progress Schedule monthly no later than the last day of the month. C. Schedule Narrative 1. Submit the schedule narrative in pdf format as required in the City of Fort Worth Schedule Guidance Document. 2. Submit schedule narrative monthly no later than the last day of the month. D. Submittal Process 1. The City administers and manages schedules through Buzzsaw. 2. Contractor shall submit documents as required in the City of Fort Worth Schedule Guidance Document. 3. Once the project has been completed and Final Acceptance has been issued by the City, no further progress schedules are required. CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 013216-5 DAP CONSTRUCTION PROGRESS SCHEDULE Page 5 of 5 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE A. The person preparing and revising the construction Progress Schedule shall be experienced in the preparation of schedules of similar complexity. B. Schedule and supporting documents addressed in this Specification shall be prepared, updated and revised to accurately reflect the performance of the construction. C. Contractor is responsible for the quality of all submittals in this section meeting the standard of care for the construction industry for similar projects. 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 013233-1 DAP PRECONSTRUCTION VIDEO Page 1 of 2 SECTION 0132 33 PRECONSTRUCTION VIDEO PART1- GENERAL 1.1 SUMMARY A. Section Includes: 1. Administrative and procedural requirements for: a. Preconstruction Videos B. Deviations from this City of Fort Worth Standard Specification 1. Though not mandatory, it is highly recommended on infill developer projects. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 — General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Preconstruction Video 1. Produce a preconstruction video of the site/alignment, including all areas in the vicinity of and to be affected by construction. a. Provide digital copy of video upon request by the City. 2. Retain a copy of the preconstruction video until the end of the maintenance surety period. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 01 32 33 - 2 DAP PRECONSTRUCTION VIDEO Page 2 of 2 PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 SECTION 0133 00 DAP SUBMITTALS PART1- GENERAL 1.1 SUMMARY A. Section Includes: 013300-1 DAP SUBMITTALS Page 1 of 8 General methods and requirements of submissions applicable to the following Work -related submittals: a. Shop Drawings b. Product Data (including Standard Product List submittals) c. Samples d. Mock Ups B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 — General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Coordination 1. Notify the City in writing, at the time of submittal, of any deviations in the submittals from the requirements of the Contract Documents. 2. Coordination of Submittal Times a. Prepare, prioritize and transmit each submittal sufficiently in advance of performing the related Work or other applicable activities, or within the time specified in the individual Work Sections, of the Specifications. b. Contractor is responsible such that the installation will not be delayed by processing times including, but not limited to: a) Disapproval and resubmittal (if required) b) Coordination with other submittals c) Testing d) Purchasing e) Fabrication f) Delivery g) Similar sequenced activities c. No extension of time will be authorized because of the Contractor's failure to transmit submittals sufficiently in advance of the Work. CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 013300-2 DAP SUBMITTALS Page 2 of 8 d. Make submittals promptly in accordance with approved schedule, and in such sequence as to cause no delay in the Work or in the work of any other contractor. B. Submittal Numbering When submitting shop drawings or samples, utilize a 9-character submittal cross- reference identification numbering system in the following manner: a. Use the first 6 digits of the applicable Specification Section Number. b. For the next 2 digits number use numbers 01-99 to sequentially number each initial separate item or drawing submitted under each specific Section number. c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e. A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical submittal number would be as follows: 03 30 00-08-B 1) 03 30 00 is the Specification Section for Concrete 2) 08 is the eighth initial submittal under this Specification Section 3) B is the third submission (second resubmission) of that particular shop drawing C. Contractor Certification Review shop drawings, product data and samples, including those by subcontractors, prior to submission to determine and verify the following: a. Field measurements b. Field construction criteria c. Catalog numbers and similar data d. Conformance with the Contract Documents 2. Provide each shop drawing, sample and product data submitted by the Contractor with a Certification Statement affixed including: a. The Contractor's Company name b. Signature of submittal reviewer c. Certification Statement 1) `By this submittal, I hereby represent that I have determined and verified field measurements, field construction criteria, materials, dimensions, catalog numbers and similar data and I have checked and coordinated each item with other applicable approved shop drawings." D. Submittal Format 1. Fold shop drawings larger than 8 '/2 inches x 11 inches to 8 '/2 inches x 11 inches. 2. Bind shop drawings and product data sheets together. 3. Order a. Cover Sheet 1) Description of Packet 2) Contractor Certification b. List of items / Table of Contents c. Product Data /Shop Drawings/Samples /Calculations E. Submittal Content 1. The date of submission and the dates of any previous submissions CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 013300-3 DAP SUBMITTALS Page 3 of 8 2. The Project title and number 3. Contractor identification 4. The names of: a. Contractor b. Supplier c. Manufacturer 5. Identification of the product, with the Specification Section number, page and paragraph(s) 6. Field dimensions, clearly identified as such 7. Relation to adjacent or critical features of the Work or materials 8. Applicable standards, such as ASTM or Federal Specification numbers 9. Identification by highlighting of deviations from Contract Documents 10. Identification by highlighting of revisions on resubmittals 11. An 8-inch x 3-inch blank space for Contractor and City stamps F. Shop Drawings 1. As specified in individual Work Sections includes, but is not necessarily limited to: a. Custom -prepared data such as fabrication and erection/installation (working) drawings b. Scheduled information c. Setting diagrams d. Actual shopwork manufacturing instructions e. Custom templates f. Special wiring diagrams g. Coordination drawings h. Individual system or equipment inspection and test reports including: 1) Performance curves and certifications i. As applicable to the Work 2. Details a. Relation of the various parts to the main members and lines of the structure b. Where correct fabrication of the Work depends upon field measurements 1) Provide such measurements and note on the drawings prior to submitting for approval. G. Product Data 1. For submittals of product data for products included on the City's Standard Product List, clearly identify each item selected for use on the Project. 2. For submittals of product data for products not included on the City's Standard Product List, submittal data may include, but is not necessarily limited to: a. Standard prepared data for manufactured products (sometimes referred to as catalog data) 1) Such as the manufacturer's product specification and installation instructions 2) Availability of colors and patterns 3) Manufacturer's printed statements of compliances and applicability 4) Roughing -in diagrams and templates 5) Catalog cuts 6) Product photographs CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 013300-4 DAP SUBMITTALS Page 4 of 8 7) Standard wiring diagrams 8) Printed performance curves and operational -range diagrams 9) Production or quality control inspection and test reports and certifications 10) Mill reports 11) Product operating and maintenance instructions and recommended spare -parts listing and printed product warranties 12) As applicable to the Work H. Samples As specified in individual Sections, include, but are not necessarily limited to: a. Physical examples of the Work such as: 1) Sections of manufactured or fabricated Work 2) Small cuts or containers of materials 3) Complete units of repetitively used products color/texture/pattern swatches and range sets 4) Specimens for coordination of visual effect 5) Graphic symbols and units of Work to be used by the City for independent inspection and testing, as applicable to the Work I. Do not start Work requiring a shop drawing, sample or product data nor any material to be fabricated or installed prior to the approval or qualified approval of such item. 1. Fabrication performed, materials purchased or on -site construction accomplished which does not conform to approved shop drawings and data is at the Contractor's risk. 2. The City will not be liable for any expense or delay due to corrections or remedies required to accomplish conformity. 3. Complete project Work, materials, fabrication, and installations in conformance with approved shop drawings, applicable samples, and product data. J. Submittal Distribution Electronic Distribution a. Confirm development of Project directory for electronic submittals to be uploaded to City's Buzzsaw site, or another external FTP site approved by the City. b. Shop Drawings 1) Upload submittal to designated project directory and notify appropriate City representatives via email of submittal posting. 2) Hard Copies a) 3 copies for all submittals b) If Contractor requires more than 1 hard copy of Shop Drawings returned, Contractor shall submit more than the number of copies listed above. c. Product Data 1) Upload submittal to designated project directory and notify appropriate City representatives via email of submittal posting. 2) Hard Copies a) 3 copies for all submittals d. Samples 1) Distributed to the Project Representative 2. Hard Copy Distribution (if required in lieu of electronic distribution) CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 013300-5 DAP SUBMITTALS Page 5 of 8 a. Shop Drawings 1) Distributed to the City 2) Copies a) 8 copies for mechanical submittals b) 7 copies for all other submittals c) If Contractor requires more than 3 copies of Shop Drawings returned, Contractor shall submit more than the number of copies listed above. b. Product Data 1) Distributed to the City 2) Copies a) 4 copies c. Samples 1) Distributed to the Project Representative 2) Copies a) Submit the number stated in the respective Specification Sections. Distribute reproductions of approved shop drawings and copies of approved product data and samples, where required, to the job site file and elsewhere as directed by the City. a. Provide number of copies as directed by the City but not exceeding the number previously specified. K. Submittal Review 1. The review of shop drawings, data and samples will be for general conformance with the design concept and Contract Documents. This is not to be construed as: a. Permitting any departure from the Contract requirements b. Relieving the Contractor of responsibility for any errors, including details, dimensions, and materials c. Approving departures from details furnished by the City, except as otherwise provided herein 2. The review and approval of shop drawings, samples or product data by the City does not relieve the Contractor from his/her responsibility with regard to the fulfillment of the terms of the Contract. a. All risks of error and omission are assumed by the Contractor, and the City will have no responsibility therefore. 3. The Contractor remains responsible for details and accuracy, for coordinating the Work with all other associated work and trades, for selecting fabrication processes, for techniques of assembly and for performing Work in a safe manner. 4. If the shop drawings, data or samples as submitted describe variations and show a departure from the Contract requirements which City finds to be in the interest of the City and to be so minor as not to involve a change in Contract Price or time for performance, the City may return the reviewed drawings without noting an exception. 5. Submittals will be returned to the Contractor under 1 of the following codes: a. Code 1 1) "NO EXCEPTIONS TAKEN' is assigned when there are no notations or comments on the submittal. a) When returned under this code the Contractor may release the equipment and/or material for manufacture. b. Code 2 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 013300-6 DAP SUBMITTALS Page 6 of 8 1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of the notations and comments IS NOT required by the Contractor. a) The Contractor may release the equipment or material for manufacture; however, all notations and comments must be incorporated into the final product. c. Code 3 1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is assigned when notations and comments are extensive enough to require a resubmittal of the package. a) The Contractor may release the equipment or material for manufacture; however, all notations and comments must be incorporated into the final product. b) This resubmittal is to address all comments, omissions and non -conforming items that were noted. c) Resubmittal is to be received by the City within 15 Calendar Days of the date of the City's transmittal requiring the resubmittal. d. Code 4 1) "NOT APPROVED" is assigned when the submittal does not meet the intent of the Contract Documents. a) The Contractor must resubmit the entire package revised to bring the submittal into conformance. b) It may be necessary to resubmit using a different manufacturer/vendor to meet the Contract Documents. 6. Resubmittals a. Handled in the same manner as first submittals 1) Corrections other than requested by the City 2) Marked with revision triangle or other similar method a) At Contractor's risk if not marked b. Submittals for each item will be reviewed no more than twice at the City's expense. 1) All subsequent reviews will be performed at times convenient to the City and at the Contractor's expense, based on the City's or City Representative's then prevailing rates. 2) Provide Contractor reimbursement to the City within 30 Calendar Days for all such fees invoiced by the City. c. The need for more than 1 resubmission or any other delay in obtaining City's review of submittals, will not entitle the Contractor to an extension of Contract Time. 7. Partial Submittals a. City reserves the right to not review submittals deemed partial, at the City's discretion. b. Submittals deemed by the City to be not complete will be returned to the Contractor, and will be considered "Not Approved" until resubmitted. c. The City may at its option provide a list or mark the submittal directing the Contractor to the areas that are incomplete. 8. If the Contractor considers any correction indicated on the shop drawings to constitute a change to the Contract Documents, then written notice must be provided thereof to the Developer at least 7 Calendar Days prior to release for manufacture. CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 013300-7 DAP SUBMITTALS Page 7 of 8 9. When the shop drawings have been completed to the satisfaction of the City, the Contractor may carry out the construction in accordance therewith and no further changes therein except upon written instructions from the City. 10. Each submittal, appropriately coded, will be returned within 30 Calendar Days following receipt of submittal by the City. L. Mock ups 1. Mock Up units as specified in individual Sections, include, but are not necessarily limited to, complete units of the standard of acceptance for that type of Work to be used on the Project. Remove at the completion of the Work or when directed. M. Qualifications 1. If specifically required in other Sections of these Specifications, submit a P.E. Certification for each item required. N. Request for Information (RFI) 1. Contractor Request for additional information a. Clarification or interpretation of the contract documents b. When the Contractor believes there is a conflict between Contract Documents c. When the Contractor believes there is a conflict between the Drawings and Specifications 1) Identify the conflict and request clarification 2. Sufficient information shall be attached to permit a written response without further information. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 013300-8 DAP SUBMITTALS Page 8 of 8 PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] D 31111=1x4011130 Revision Log DATE NAME SUMMARY OF CHANGE 12/20/2012 D. Johnson 1.4.K.8. Working Days modified to Calendar Days CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 0135 13- 1 DAP SPECIAL PROJECT PROCEDURES Page 1 of 7 1 SECTION 0135 13 2 SPECIAL PROJECT PROCEDURES 3 PART1- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. The procedures for special project circumstances that includes, but is not limited to: 7 a. Coordination with the Texas Department of Transportation 8 b. Work near High Voltage Lines 9 c. Confined Space Entry Program 10 d. Air Pollution Watch Days 11 e. Use of Explosives, Drop Weight, Etc. 12 £ Water Department Notification 13 g. Public Notification Prior to Beginning Construction 14 h. Coordination with United States Army Corps of Engineers 15 i. Coordination within Railroad permits areas 16 j. Dust Control 17 k. Employee Parking 18 B. Deviations from this City of Fort Worth Standard Specification 19 1. None. 20 C. Related Specification Sections include, but are not necessarily limited to: 21 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract 22 2. Division 1 — General Requirements 23 3. Section 33 12 25 — Connection to Existing Water Mains 24 25 1.2 REFERENCES 26 A. Reference Standards 27 1. Reference standards cited in this Specification refer to the current reference 28 standard published at the time of the latest revision date logged at the end of this 29 Specification, unless a date is specifically cited. 30 2. Health and Safety Code, Title 9. Safety, Subtitle A. Public Safety, Chapter 752. 31 High Voltage Overhead Lines. 32 3. North Central Texas Council of Governments (NCTCOG) — Clean Construction 33 Specification 34 1.3 ADMINISTRATIVE REQUIREMENTS 35 A. Coordination with the Texas Department of Transportation 36 1. When work in the right-of-way which is under the jurisdiction of the Texas 37 Department of Transportation (TxDOT): 38 a. Notify the Texas Department of Transportation prior to commencing any work 39 therein in accordance with the provisions of the permit CITY OF FORT WORTH Water & Sewer to Serve Wichita Industrial STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN: 104140 Revised August, 30, 2013 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 013513-2 DAP SPECIAL PROJECT PROCEDURES Page 2 of 7 b. All work performed in the TxDOT right-of-way shall be performed in compliance with and subject to approval from the Texas Department of Transportation B. Work near High Voltage Lines 1. Regulatory Requirements a. All Work near High Voltage Lines (more than 600 volts measured between conductors or between a conductor and the ground) shall be in accordance with Health and Safety Code, Title 9, Subtitle A, Chapter 752. 2. Warning sign a. Provide sign of sufficient size meeting all OSHA requirements. 3. Equipment operating within 10 feet of high voltage lines will require the following safety features a. Insulating cage -type of guard about the boom or arm b. Insulator links on the lift hook connections for back hoes or dippers c. Equipment must meet the safety requirements as set forth by OSHA and the safety requirements of the owner of the high voltage lines 4. Work within 6 feet of high voltage electric lines a. Notification shall be given to: 1) The power company (example: ONCOR) a) Maintain an accurate log of all such calls to power company and record action taken in each case. b. Coordination with power company 1) After notification coordinate with the power company to: a) Erect temporary mechanical barriers, de -energize the lines, or raise or lower the lines c. No personnel may work within 6 feet of a high voltage line before the above requirements have been met. C. Confined Space Entry Program 1. Provide and follow approved Confined Space Entry Program in accordance with OSHA requirements. 2. Confined Spaces include: a. Manholes b. All other confined spaces in accordance with OSHA's Permit Required for Confined Spaces D. Use of Explosives, Drop Weight, Etc. 1. When Contract Documents permit on the project the following will apply: a. Public Notification 1) Submit notice to City and proof of adequate insurance coverage, 24 hours prior to commencing. 2) Minimum 24 hour public notification in accordance with Section 0131 13 E. Water Department Coordination 1. During the construction of this project, it will be necessary to deactivate, for a period of time, existing lines. The Contractor shall be required to coordinate with the Water Department to determine the best times for deactivating and activating those lines. CITY OF FORT WORTH Water & Sewer to Serve Wichita Industrial STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN: 104140 Revised August, 30, 2013 013513-3 DAP SPECIAL PROJECT PROCEDURES Page 3 of 7 1 2. Coordinate any event that will require connecting to or the operation of an existing 2 City water line system with the City's representative. 3 a. Coordination shall be in accordance with Section 33 12 25. 4 b. If needed, obtain a hydrant water meter from the Water Department for use 5 during the life of named project. 6 c. In the event that a water valve on an existing live system be turned off and on 7 to accommodate the construction of the project is required, coordinate this 8 activity through the appropriate City representative. 9 1) Do not operate water line valves of existing water system. 10 a) Failure to comply will render the Contractor in violation of Texas Penal 11 Code Title 7, Chapter 28.03 (Criminal Mischief) and the Contractor 12 will be prosecuted to the full extent of the law. 13 b) In addition, the Contractor will assume all liabilities and 14 responsibilities as a result of these actions. 15 F. Public Notification Prior to Beginning Construction 16 1. Prior to beginning construction on any block in the project, on a block by block 17 basis, prepare and deliver a notice or flyer of the pending construction to the front 18 door of each residence or business that will be impacted by construction. The notice 19 shall be prepared as follows: 20 a. Post notice or flyer 7 days prior to beginning any construction activity on each 21 block in the project area. 22 1) Prepare flyer on the Contractor's letterhead and include the following 23 information: 24 a) Name of Project 25 b) City Project No (CPN) 26 c) Scope of Project (i.e. type of construction activity) 27 d) Actual construction duration within the block 28 e) Name of the contractor's foreman and phone number 29 f) Name of the City's inspector and phone number 30 g) City's after-hours phone number 31 2) A sample of the `pre -construction notification' flyer is attached as Exhibit 32 A. 33 3) Submit schedule showing the construction start and finish time for each 34 block of the project to the inspector. 35 4) Deliver flyer to the City Inspector for review prior to distribution. 36 b. No construction will be allowed to begin on any block until the flyer is 37 delivered to all residents of the block. 38 G. Public Notification of Temporary Water Service Interruption during Construction 39 1. In the event it becomes necessary to temporarily shut down water service to 40 residents or businesses during construction, prepare and deliver a notice or flyer of 41 the pending interruption to the front door of each affected resident. 42 2. Prepared notice as follows: 43 a. The notification or flyer shall be posted 24 hours prior to the temporary 44 interruption. 45 b. Prepare flyer on the contractor's letterhead and include the following 46 information: 47 1) Name of the project 48 2) City Project Number CITY OF FORT WORTH Water & Sewer to Serve Wichita Industrial STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN: 104140 Revised August, 30, 2013 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 01 35 13 - 4 DAP SPECIAL PROJECT PROCEDURES Page 4 of 7 3) Date of the interruption of service 4) Period the interruption will take place 5) Name of the contractor's foreman and phone number 6) Name of the City's inspector and phone number c. A sample of the temporary water service interruption notification is attached as Exhibit B. d. Deliver a copy of the temporary interruption notification to the City inspector for review prior to being distributed. e. No interruption of water service can occur until the flyer has been delivered to all affected residents and businesses. f. Electronic versions of the sample flyers can be obtained from the Project Construction Inspector. H. Coordination with United States Army Corps of Engineers (USACE) 1. At locations in the Project where construction activities occur in areas where USACE permits are required, meet all requirements set forth in each designated permit. I. Coordination within Railroad Permit Areas 1. At locations in the project where construction activities occur in areas where railroad permits are required, meet all requirements set forth in each designated railroad permit. This includes, but is not limited to, provisions for: a. Flagmen b. Inspectors c. Safety training d. Additional insurance e. Insurance certificates f. Other employees required to protect the right-of-way and property of the Railroad Company from damage arising out of and/or from the construction of the project. Proper utility clearance procedures shall be used in accordance with the permit guidelines. 2. Obtain any supplemental information needed to comply with the railroad's requirements. J. Dust Control 1. Use acceptable measures to control dust at the Site. a. If water is used to control dust, capture and properly dispose of waste water. b. If wet saw cutting is performed, capture and properly dispose of slurry. K. Employee Parking 1. Provide parking for employees at locations approved by the City. CITY OF FORT WORTH Water & Sewer to Serve Wichita Industrial STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN: 104140 Revised August, 30, 2013 013513-5 DAP SPECIAL PROJECT PROCEDURES Page 5 of 7 1 1.4 SUBMITTALS [NOT USED] 2 1.5 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED] 3 1.6 CLOSEOUT SUBMITTALS [NOT USED] 4 1.7 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 5 1.8 QUALITY ASSURANCE [NOT USED] 6 1.9 DELIVERY, STORAGE, AND HANDLING [NOT USED] 7 1.10 FIELD [SITE] CONDITIONS [NOT USED] 8 1.11 WARRANTY [NOT USED] 9 PART 2 - PRODUCTS [NOT USED] 10 PART 3 - EXECUTION [NOT USED] 11 END OF SECTION 12 13 Revision Log DATE NAME SUMMARY OF CHANGE 1.3.13— Added requirement of compliance with Health and Safety Code, Title 9. 8/31/2012 D. Johnson Safety, Subtitle A. Public Safety, Chapter 752. High Voltage Overhead Lines. CITY OF FORT WORTH Water & Sewer to Serve Wichita Industrial STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN: 104140 Revised August, 30, 2013 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 01 35 13 - 6 DAP SPECIAL PROJECT PROCEDURES Page 6 of 7 EXHIBIT A (To be printed on Contractor's Letterhead) Date: CPN No.: Project Name: Mapsco Location: Limits of Construction: THIS IS TO INFORM YOU THAT UNDER A CONTRACT WITH THE CITY OF FORT WORTH, OUR COMPANY WILL WORK ON UTILITY LINES ON OR AROUND YOUR PROPERTY. CONSTRUCTION WILL BEGIN APPROXIMATELY SEVEN DAYS FROM THE DATE OF THIS NOTICE. IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SAFETY OR ANY OTHER ISSUE, PLEASE CALL: Mr. <CONTRACTOR'S SUPERINTENDENT> AT <TELEPHONE NO.> OR Mr. <CITY INSPECTOR> AT < TELEPHONE NO.> AFTER 4:30 PM OR ON WEEKENDS, PLEASE CALL (817) 392 8306 PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL CITY OF FORT WORTH Water & Sewer to Serve Wichita Industrial STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN: 104140 Revised August, 30, 2013 2 3 4 Date: EXHIBIT B FORT WORTH DOE NO. xxxx Project Name: 013513-7 DAP SPECIAL PROJECT PROCEDURES Page 7 of 7 NOTICE OF TEMPORARY WATER SERVICE INTERRUPTION DUE TO UTILITY IMPROVEMENTS IN YOUR NEIGHBORHOOD, YOUR WATER SERVICE WILL BE INTERRUPTED ON BETWEEN THE HOURS OF AND IF YOU HAVE QUESTIONS ABOUT THIS SHUT -OUT, PLEASE CALL: MR. AT (CONTRACTORS SUPERINTENDENT) (TELEPHONE NUMBER) OR MR. AT (CITY INSPECTOR) (TELEPHONE NUMBER) THIS INCONVENIENCE WILL BE AS SHORT AS POSSIBLE. THANK YOU, CONTRACTOR CITY OF FORT WORTH Water & Sewer to Serve Wichita Industrial STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN: 104140 Revised August, 30, 2013 01 45 23 DAP TESTING AND INSPECTION SERVICES Page 1 of 2 SECTION 0145 23 TESTING AND INSPECTION SERVICES PART1- GENERAL 1.1 SUMMARY A. Section Includes: 1. Testing and inspection services procedures and coordination B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 — General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. a. Contractor is responsible for performing, coordinating, and payment of all Quality Control testing. b. City is responsible for performing and payment for first set of Quality Assurance testing. 1) If the first Quality Assurance test performed by the City fails, the Contractor is responsible for payment of subsequent Quality Assurance testing until a passing test occurs. a) Final acceptance will not be issued by City until all required payments for testing by Contractor have been paid in full. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Testing 1. Complete testing in accordance with the Contract Documents. 2. Coordination a. When testing is required to be performed by the City, notify City, sufficiently in advance, when testing is needed. b. When testing is required to be completed by the Contractor, notify City, sufficiently in advance, that testing will be performed. 3. Distribution of Testing Reports a. Electronic Distribution 1) Confirm development of Project directory for electronic submittals to be uploaded to the City's document management system, or another form of distribution approved by the City. CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised March 20, 2020 01 45 23 DAP TESTING AND INSPECTION SERVICES Page 2 of 2 2) Upload test reports to designated project directory and notify appropriate City representatives via email of submittal posting. 3) Hard Copies a) 1 copy for all submittals submitted to the Project Representative b. Hard Copy Distribution (if required in lieu of electronic distribution) 1) Tests performed by City a) Distribute 1 hard copy to the Contractor 2) Tests performed by the Contractor a) Distribute 3 hard copies to City's Project Representative 4. Provide City's Project Representative with trip tickets for each delivered load of Concrete or Lime material including the following information: a. Name of pit b. Date of delivery c. Material delivered B. Inspection 1. Inspection or lack of inspection does not relieve the Contractor from obligation to perform work in accordance with the Contract Documents. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 03/20/2020 D.V. Magana Removed reference to Buzzsaw and noted that electronic submittals be uploaded through the City's document management system. CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised March 20, 2020 015000-1 DAP TEMPORARY FACILITIES AND CONTROLS Page 1 of 4 SECTION 0150 00 TEMPORARY FACILITIES AND CONTROLS PART1- GENERAL 1.1 SUMMARY A. Section Includes: Provide temporary facilities and controls needed for the Work including, but not necessarily limited to: a. Temporary utilities b. Sanitary facilities c. Storage Sheds and Buildings d. Dust control e. Temporary fencing of the construction site B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 — General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Temporary Utilities 1. Obtaining Temporary Service a. Make arrangements with utility service companies for temporary services. b. Abide by rules and regulations of utility service companies or authorities having jurisdiction. c. Be responsible for utility service costs until Work is approved for Final Acceptance. 1) Included are fuel, power, light, heat and other utility services necessary for execution, completion, testing and initial operation of Work. 2. Water a. Contractor to provide water required for and in connection with Work to be performed and for specified tests of piping, equipment, devices or other use as required for the completion of the Work. b. Provide and maintain adequate supply of potable water for domestic consumption by Contractor personnel and City's Project Representatives. c. Coordination 1) Contact City 1 week before water for construction is desired CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised JULY 1, 2011 01 50 00 - 2 DAP TEMPORARY FACILITIES AND CONTROLS Page 2 of 4 d. Contractor Payment for Construction Water 1) Obtain construction water meter from City for payment as billed by City's established rates. 3. Electricity and Lighting a. Provide and pay for electric powered service as required for Work, including testing of Work. 1) Provide power for lighting, operation of equipment, or other use. b. Electric power service includes temporary power service or generator to maintain operations during scheduled shutdown. 4. Telephone a. Provide emergency telephone service at Site for use by Contractor personnel and others performing work or furnishing services at Site. 5. Temporary Heat and Ventilation a. Provide temporary heat as necessary for protection or completion of Work. b. Provide temporary heat and ventilation to assure safe working conditions. B. Sanitary Facilities 1. Provide and maintain sanitary facilities for persons on Site. a. Comply with regulations of State and local departments of health. 2. Enforce use of sanitary facilities by construction personnel at job site. a. Enclose and anchor sanitary facilities. b. No discharge will be allowed from these facilities. c. Collect and store sewage and waste so as not to cause nuisance or health problem. d. Haul sewage and waste off -site at no less than weekly intervals and properly dispose in accordance with applicable regulation. 3. Locate facilities near Work Site and keep clean and maintained throughout Project. 4. Remove facilities at completion of Project C. Storage Sheds and Buildings 1. Provide adequately ventilated, watertight, weatherproof storage facilities with floor above ground level for materials and equipment susceptible to weather damage. 2. Storage of materials not susceptible to weather damage may be on blocks off ground. 3. Store materials in a neat and orderly manner. a. Place materials and equipment to permit easy access for identification, inspection and inventory. 4. Equip building with lockable doors and lighting, and provide electrical service for equipment space heaters and heating or ventilation as necessary to provide storage environments acceptable to specified manufacturers. 5. Fill and grade site for temporary structures to provide drainage away from temporary and existing buildings. 6. Remove building from site prior to Final Acceptance. D. Temporary Fencing Provide and maintain for the duration or construction when required in contract documents E. Dust Control CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised JULY 1, 2011 01 50 00 - 3 DAP TEMPORARY FACILITIES AND CONTROLS Page 3 of 4 1. Contractor is responsible for maintaining dust control through the duration of the project. a. Contractor remains on -call at all times b. Must respond in a timely manner F. Temporary Protection of Construction 1. Contractor or subcontractors are responsible for protecting Work from damage due to weather. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 INSTALLATION A. Temporary Facilities 1. Maintain all temporary facilities for duration of construction activities as needed. 3.5 [REPAIR] / [RESTORATION] 3.6 RE -INSTALLATION 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES A. Temporary Facilities CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised JULY 1, 2011 01 50 00 - 4 DAP TEMPORARY FACILITIES AND CONTROLS Page 4 of 4 1. Remove all temporary facilities and restore area after completion of the Work, to a condition equal to or better than prior to start of Work. 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised JULY 1, 2011 015526-1 DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 1 of 3 SECTION 0155 26 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL PART1- GENERAL 1.1 SUMMARY A. Section Includes: 1. Administrative procedures for: a. Street Use Permit b. Modification of approved traffic control c. Removal of Street Signs B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 — General Requirements 3. Section 34 71 13 — Traffic Control 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES A. Reference Standards 1. Reference standards cited in this specification refer to the current reference standard published at the time of the latest revision date logged at the end of this specification, unless a date is specifically cited. 2. Texas Manual on Uniform Traffic Control Devices (TMUTCD). 1.4 ADMINISTRATIVE REQUIREMENTS A. Traffic Control 1. General a. When traffic control plans are included in the Drawings, provide Traffic Control in accordance with Drawings and Section 34 71 13. b. When traffic control plans are not included in the Drawings, prepare traffic control plans in accordance with Section 34 71 13 and submit to City for review. 1) Allow minimum 10 working days for review of proposed Traffic Control. B. Street Use Permit 1. Prior to installation of Traffic Control, a City Street Use Permit is required. a. To obtain Street Use Permit, submit Traffic Control Plans to City Transportation and Public Works Department. CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 015526-2 DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 2 of 3 1) Allow a minimum of 5 working days for permit review. 2) Contractor's responsibility to coordinate review of Traffic Control plans for Street Use Permit, such that construction is not delayed. C. Modification to Approved Traffic Control Prior to installation traffic control: a. Submit revised traffic control plans to City Department Transportation and Public Works Department. 1) Revise Traffic Control plans in accordance with Section 34 71 13. 2) Allow minimum 5 working days for review of revised Traffic Control. 3) It is the Contractor's responsibility to coordinate review of Traffic Control plans for Street Use Permit, such that construction is not delayed. D. Removal of Street Sign 1. If it is determined that a street sign must be removed for construction, then contact City Transportation and Public Works Department, Signs and Markings Division to remove the sign. E. Temporary Signage 1. In the case of regulatory signs, replace permanent sign with temporary sign meeting requirements of the latest edition of the Texas Manual on Uniform Traffic Control Devices (MUTCD). 2. Install temporary sign before the removal of permanent sign. 3. When construction is complete, to the extent that the permanent sign can be reinstalled, contact the City Transportation and Public Works Department, Signs and Markings Division, to reinstall the permanent sign. F. Traffic Control Standards 1. Traffic Control Standards can be found on the City's Buzzsaw website. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 015526-3 DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 3 of 3 Revision Log DATE NAME SUMMARY OF CHANGE CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 015713-1 DAP STORM WATER POLLUTION PREVENTION Page 1 of 3 SECTION 0157 13 STORM WATER POLLUTION PREVENTION PART1- GENERAL 1.1 SUMMARY A. Section Includes: 1. Procedures for Storm Water Pollution Prevention Plans B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 — General Requirements 3. Section 3125 00 — Erosion and Sediment Control 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Construction Activities resulting in less than 1 acre of disturbance a. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 2. Construction Activities resulting in greater than 1 acre of disturbance a. Measurement and Payment shall be in accordance with Section 3125 00. 1.3 REFERENCES A. Abbreviations and Acronyms 1. Notice of Intent: NOI 2. Notice of Termination: NOT 3. Storm Water Pollution Prevention Plan: SWPPP 4. Texas Commission on Environmental Quality: TCEQ 5. Notice of Change: NOC A. Reference Standards 1. Reference standards cited in this Specification refer to the current reference standard published at the time of the latest revision date logged at the end of this Specification, unless a date is specifically cited. 2. Integrated Storm Management (iSWM) Technical Manual for Construction Controls 1.4 ADMINISTRATIVE REQUIREMENTS A. General 1. Contractor is responsible for resolution and payment of any fines issued associated with compliance to Stormwater Pollution Prevention Plan. CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 01 57 13 - 2 DAP STORM WATER POLLUTION PREVENTION Page 2 of 3 B. Construction Activities resulting in: 1. Less than 1 acre of disturbance a. Provide erosion and sediment control in accordance with Section 3125 00 and Drawings. 2. 1 to less than 5 acres of disturbance a. Texas Pollutant Discharge Elimination System (TPDES) General Construction Permit is required b. Complete SWPPP in accordance with TCEQ requirements 1) TCEQ Small Construction Site Notice Required under general permit TXR150000 a) Sign and post at job site b) Prior to Preconstruction Meeting, send 1 copy to City Department of Transportation and Public Works, Environmental Division, (817) 392- 6088. 2) Provide erosion and sediment control in accordance with: a) Section 3125 00 b) The Drawings c) TXR150000 General Permit d) SWPPP e) TCEQ requirements 5 acres or more of Disturbance a. Texas Pollutant Discharge Elimination System (TPDES) General Construction Permit is required b. Complete SWPPP in accordance with TCEQ requirements 1) Prepare a TCEQ NOI form and submit to TCEQ along with required fee a) Sign and post at job site b) Send copy to City Department of Transportation and Public Works, Environmental Division, (817) 392-6088. 2) TCEQ Notice of Change required if making changes or updates to NOI 3) Provide erosion and sediment control in accordance with: a) Section 3125 00 b) The Drawings c) TXR150000 General Permit d) SWPPP e) TCEQ requirements 4) Once the project has been completed and all the closeout requirements of TCEQ have been met a TCEQ Notice of Termination can be submitted. a) Send copy to City Department of Transportation and Public Works, Environmental Division, (817) 392-6088. 1.5 SUBMITTALS A. SWPPP Submit in accordance with Section 0133 00, except as stated herein. a. Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City as follows: 1) 1 copy to the City Project Manager a) City Project Manager will forward to the City Department of Transportation and Public Works, Environmental Division for review CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 0157 13 -3 DAP STORM WATER POLLUTION PREVENTION Page 3 of 3 B. Modified SWPPP 1. If the SWPPP is revised during construction, resubmit modified SWPPP to the City in accordance with Section 0133 00. 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 015813-1 DAP TEMPORARY PROJECT SIGNAGE Page 1 of 3 SECTION 0158 13 TEMPORARY PROJECT SIGNAGE PART1- GENERAL 1.1 SUMMARY A. Section Includes: 1. Temporary Project Signage Requirements B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 — General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART2- PRODUCTS 2.1 OWNER -FURNISHED [oR] OWNER-SUPPLIEDPRODUCTS [NOT USEDI 2.2 EQUIPMENT, PRODUCT TYPES, AND MATERIALS A. Design Criteria 1. Provide free standing Project Designation Sign in accordance with City's Standard Details for project signs. CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 01 58 13 - 2 DAP TEMPORARY PROJECT SIGNAGE Page 2 of 3 B. Materials 1. Sign a. Constructed of 3/4-inch fir plywood, grade A-C (exterior) or better 2.3 ACCESSORIES [NOT USED] 2.4 SOURCE QUALITY CONTROL [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 INSTALLATION A. General 1. Provide vertical installation at extents of project. 2. Relocate sign as needed, upon request of the City. B. Mounting options a. Skids b. Posts c. Barricade 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE -INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE A. General 1. Maintenance will include painting and repairs as needed or directed by the City. 3.14 ATTACHMENTS [NOT USED] END OF SECTION CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 0158 13 -3 DAP TEMPORARY PROJECT SIGNAGE DATE NAME 4/7/2014 M. Domenech Revision Log SUMMARY OF CHANGE Revised for DAP application Page 3 of 3 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 SECTION 0160 00 PRODUCT REQUIREMENTS PART1- GENERAL 1.1 SUMMARY A. Section Includes: 01 60 00 DAP PRODUCT REQUIREMENTS Page 1 of 2 1. References for Product Requirements and City Standard Products List B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 — General Requirements 1.2 PRICE AND PAYMENT PROCEDURES [NOT USED] 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A list of City approved products for use is available through the City's website at: httDs://apps.fortworthtexas.2ov/ProiectResources/ and following the directory path: 02 - Construction Documents\Standard Products List A. Only products specifically included on City's Standard Product List in these Contract Documents shall be allowed for use on the Project. 1. Any subsequently approved products will only be allowed for use upon specific approval by the City. B. Any specific product requirements in the Contract Documents supersede similar products included on the City's Standard Product List. 1. The City reserves the right to not allow products to be used for certain projects even though the product is listed on the City's Standard Product List. C. Although a specific product is included on City's Standard Product List, not all products from that manufacturer are approved for use, including but not limited to, that manufacturer's standard product. D. See Section 0133 00 for submittal requirements of Product Data included on City's Standard Product List. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised March 20, 2020 01 60 00 DAP PRODUCT REQUIREMENTS Page 2 of 2 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 10/12/12 D. Johnson Modified Location of City's Standard Product List 4/7/2014 M.Domenech Revised for DAP application 03/20/2020 D.V. Magafia Removed reference to Buzzsaw and noted that the City approved products list is accessible through the City's website. CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised March 20, 2020 016600-1 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 1 of 4 SECTION 0166 00 PRODUCT STORAGE AND HANDLING REQUIREMENTS PART1- GENERAL 1.1 SUMMARY A. Section Includes: 1. Scheduling of product delivery 2. Packaging of products for delivery 3. Protection of products against damage from: a. Handling b. Exposure to elements or harsh environments B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 — General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY AND HANDLING A. Delivery Requirements 1. Schedule delivery of products or equipment as required to allow timely installation and to avoid prolonged storage. 2. Provide appropriate personnel and equipment to receive deliveries. 3. Delivery trucks will not be permitted to wait extended periods of time on the Site for personnel or equipment to receive the delivery. CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 01 66 00 - 2 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 2 of 4 4. Deliver products or equipment in manufacturer's original unbroken cartons or other containers designed and constructed to protect the contents from physical or environmental damage. 5. Clearly and fully mark and identify as to manufacturer, item and installation location. 6. Provide manufacturer's instructions for storage and handling. B. Handling Requirements 1. Handle products or equipment in accordance with these Contract Documents and manufacturer's recommendations and instructions. C. Storage Requirements 1. Store materials in accordance with manufacturer's recommendations and requirements of these Specifications. 2. Make necessary provisions for safe storage of materials and equipment. a. Place loose soil materials and materials to be incorporated into Work to prevent damage to any part of Work or existing facilities and to maintain free access at all times to all parts of Work and to utility service company installations in vicinity of Work. 3. Keep materials and equipment neatly and compactly stored in locations that will cause minimum inconvenience to other contractors, public travel, adjoining owners, tenants and occupants. a. Arrange storage to provide easy access for inspection. 4. Restrict storage to areas available on construction site for storage of material and equipment as shown on Drawings, or approved by City's Project Representative. 5. Provide off -site storage and protection when on -site storage is not adequate. a. Provide addresses of and access to off -site storage locations for inspection by City's Project Representative. 6. Do not use lawns, grass plots or other private property for storage purposes without written permission of owner or other person in possession or control of premises. 7. Store in manufacturers' unopened containers. 8. Neatly, safely and compactly stack materials delivered and stored along line of Work to avoid inconvenience and damage to property owners and general public and maintain at least 3 feet from fire hydrant. 9. Keep public and private driveways and street crossings open. 10. Repair or replace damaged lawns, sidewalks, streets or other improvements to satisfaction of City's Project Representative. a. Total length which materials may be distributed along route of construction at one time is 1,000 linear feet, unless otherwise approved in writing by City's Project Representative. CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 016600-3 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 3 of 4 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 ERECTION [NOT USED] 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE -INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL A. Tests and Inspections 1. Inspect all products or equipment delivered to the site prior to unloading. B. Non -Conforming Work 1. Reject all products or equipment that are damaged, used or in any other way unsatisfactory for use on the project. 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION A. Protect all products or equipment in accordance with manufacturer's written directions. B. Store products or equipment in location to avoid physical damage to items while in storage. C. Protect equipment from exposure to elements and keep thoroughly dry if required by the manufacturer. 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] END OF SECTION CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 01 66 00 - 4 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 4 of 4 Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 SECTION 0174 23 CLEANING PART1- GENERAL 1.1 SUMMARY 017423-1 DAP CLEANING Page 1 of 4 A. Section Includes: 1. Intermediate and final cleaning for Work not including special cleaning of closed systems specified elsewhere B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 — General Requirements 3. Section 32 92 13 — Hydro -Mulching, Seeding and Sodding 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Scheduling 1. Schedule cleaning operations so that dust and other contaminants disturbed by cleaning process will not fall on newly painted surfaces. 2. Schedule final cleaning upon completion of Work and immediately prior to final inspection. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 STORAGE, AND HANDLING A. Storage and Handling Requirements 1. Store cleaning products and cleaning wastes in containers specifically designed for those materials. CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 01 74 23 - 2 DAP CLEANING Page 2 of 4 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART2- PRODUCTS 2.1 OWNER -FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED] 2.2 MATERIALS A. Cleaning Agents 1. Compatible with surface being cleaned 2. New and uncontaminated 3. For manufactured surfaces a. Material recommended by manufacturer 2.3 ACCESSORIES [NOT USED] 2.4 SOURCE QUALITY CONTROL [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 APPLICATION [NOT USED] 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE -INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING A. General 1. Prevent accumulation of wastes that create hazardous conditions. 2. Conduct cleaning and disposal operations to comply with laws and safety orders of governing authorities. 3. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in storm or sanitary drains or sewers. 4. Dispose of degradable debris at an approved solid waste disposal site. 5. Dispose of nondegradable debris at an approved solid waste disposal site or in an alternate manner approved by City and regulatory agencies. CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 01 74 23 - 3 DAP CLEANING Page 3 of 4 6. Handle materials in a controlled manner with as few handlings as possible. 7. Thoroughly clean, sweep, wash and polish all Work and equipment associated with this project. 8. Remove all signs of temporary construction and activities incidental to construction of required permanent Work. 9. If project is not cleaned to the satisfaction of the City, the City reserves the right to have the cleaning completed at the expense of the Contractor. 10. Do not burn on -site. B. Intermediate Cleaning during Construction 1. Keep Work areas clean so as not to hinder health, safety or convenience of personnel in existing facility operations. 2. At maximum weekly intervals, dispose of waste materials, debris and rubbish. 3. Confine construction debris daily in strategically located container(s): a. Cover to prevent blowing by wind b. Store debris away from construction or operational activities c. Haul from site at a minimum of once per week 4. Vacuum clean interior areas when ready to receive finish painting. a. Continue vacuum cleaning on an as -needed basis, until Final Acceptance. 5. Prior to storm events, thoroughly clean site of all loose or unsecured items, which may become airborne or transported by flowing water during the storm. C. Exterior (Site or Right of Way) Final Cleaning 1. Remove trash and debris containers from site. a. Re -seed areas disturbed by location of trash and debris containers in accordance with Section 32 92 13. 2. Sweep roadway to remove all rocks, pieces of asphalt, concrete or any other object that may hinder or disrupt the flow of traffic along the roadway. 3. Clean any interior areas including, but not limited to, vaults, manholes, structures, junction boxes and inlets. 4. If no longer required for maintenance of erosion facilities, and upon approval by City, remove erosion control from site. 5. Clean signs, lights, signals, etc. 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 DATE NAME 4/7/2014 M.Domenech END OF SECTION Revision Log SUMMARY OF CHANGE Revised for DAP application 01 74 23 - 4 DAP CLEANING Page 4 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 SECTION 0177 19 CLOSEOUT REQUIREMENTS PART1- GENERAL 1.1 SUMMARY 017719-1 DAP CLOSEOUT REQUIREMENTS Page 1 of 3 A. Section Includes: 1. The procedure for closing out a contract B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 — General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Guarantees, Bonds and Affidavits 1. No application for final payment will be accepted until all guarantees, bonds, certificates, licenses and affidavits required for Work or equipment as specified are satisfactorily filed with the City. B. Release of Liens or Claims 1. No application for final payment will be accepted until satisfactory evidence of release of liens has been submitted to the City. 1.5 SUBMITTALS A. Submit all required documentation to City's Project Representative. CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 017719-2 DAP CLOSEOUT REQUIREMENTS Page 2 of 3 1.6 INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 CLOSEOUT PROCEDURE A. Prior to requesting Final Inspection, submit: 1. Project Record Documents in accordance with Section 0178 39 2. Operation and Maintenance Data, if required, in accordance with Section 0178 23 B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section 01 74 23. C. Final Inspection 1. After final cleaning, provide notice to the City Project Representative that the Work is completed. a. The City will make an initial Final Inspection with the Contractor present. b. Upon completion of this inspection, the City will notify the Contractor, in writing within 10 business days, of any particulars in which this inspection reveals that the Work is defective or incomplete. 2. Upon receiving written notice from the City, immediately undertake the Work required to remedy deficiencies and complete the Work to the satisfaction of the City. 3. Upon completion of Work associated with the items listed in the City's written notice, inform the City, that the required Work has been completed. Upon receipt of this notice, the City, in the presence of the Contractor, will make a subsequent Final Inspection of the project. 4. Provide all special accessories required to place each item of equipment in full operation. These special accessory items include, but are not limited to: a. Specified spare parts b. Adequate oil and grease as required for the first lubrication of the equipment c. Initial fill up of all chemical tanks and fuel tanks d. Light bulbs e. Fuses f. Vault keys g. Handwheels h. Other expendable items as required for initial start-up and operation of all equipment D. Notice of Project Completion CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 017719-3 DAP CLOSEOUT REQUIREMENTS Page 3 of 3 1. Once the City Project Representative finds the Work subsequent to Final Inspection to be satisfactory, the City will issue a Notice of Project Completion (Green Sheet). E. Supporting Documentation 1. Coordinate with the City Project Representative to complete the following additional forms: a. Final Payment Request b. Statement of Contract Time c. Affidavit of Payment and Release of Liens d. Consent of Surety to Final Payment e. Pipe Report (if required) £ Contractor's Evaluation of City g. Performance Evaluation of Contractor F. Letter of Final Acceptance 1. Upon review and acceptance of Notice of Project Completion and Supporting Documentation, in accordance with General Conditions, City will issue Letter of Final Acceptance and release the Final Payment Request for payment. 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE -INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] DATE NAME 4/7/2014 M.Domenech END OF SECTION Revision Log SUMMARY OF CHANGE Revised for DAP application CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 017839-1 DAP PROJECT RECORD DOCUMENTS Page 1 of 4 SECTION 0178 39 PROJECT RECORD DOCUMENTS PART1- GENERAL 1.1 SUMMARY A. Section Includes: 1. Work associated with the documenting the project and recording changes to project documents, including: a. Record Drawings b. Water Meter Service Reports c. Sanitary Sewer Service Reports d. Large Water Meter Reports B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 — General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 1.5 SUBMITTALS A. Prior to submitting a request for Final Inspection, deliver Project Record Documents to City's Project Representative. 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE A. Accuracy of Records 1. Thoroughly coordinate changes within the Record Documents, making adequate and proper entries on each page of Specifications and each sheet of Drawings and other Documents where such entry is required to show the change properly. 2. Accuracy of records shall be such that future search for items shown in the Contract Documents may rely reasonably on information obtained from the approved Project Record Documents. CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 01 78 39 - 2 DAP PROJECT RECORD DOCUMENTS Page 2 of 4 3. To facilitate accuracy of records, make entries within 24 hours after receipt of information that the change has occurred. 4. Provide factual information regarding all aspects of the Work, both concealed and visible, to enable future modification of the Work to proceed without lengthy and expensive site measurement, investigation and examination. 1.10 STORAGE AND HANDLING A. Storage and Handling Requirements 1. Maintain the job set of Record Documents completely protected from deterioration and from loss and damage until completion of the Work and transfer of all recorded data to the final Project Record Documents. 2. In the event of loss of recorded data, use means necessary to again secure the data to the City's approval. a. In such case, provide replacements to the standards originally required by the Contract Documents. 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART2- PRODUCTS 2.1 OWNER -FURNISHED [OR] OWNER -SUPPLIED PRODUCTS [NOT USED] 2.2 RECORD DOCUMENTS A. Job set 1. Promptly following receipt of the Notice to Proceed, secure from the City, at no charge to the Contractor, 1 complete set of all Documents comprising the Contract. B. Final Record Documents 1. At a time nearing the completion of the Work and prior to Final Inspection, provide the City 1 complete set of all Final Record Drawings in the Contract. 2.3 ACCESSORIES [NOT USED] 2.4 SOURCE QUALITY CONTROL [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 MAINTENANCE DOCUMENTS A. Maintenance of Job Set 1. Immediately upon receipt of the job set, identify each of the Documents with the title, "RECORD DOCUMENTS - JOB SET". CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 017839-3 DAP PROJECT RECORD DOCUMENTS Page 3 of 4 2. Preservation a. Considering the Contract completion time, the probable number of occasions upon which the job set must be taken out for new entries and for examination, and the conditions under which these activities will be performed, devise a suitable method for protecting the job set. b. Do not use the job set for any purpose except entry of new data and for review by the City, until start of transfer of data to final Project Record Documents. c. Maintain the job set at the site of work. 3. Coordination with Construction Survey a. At a minimum clearly mark any deviations from Contract Documents associated with installation of the infrastructure. 4. Making entries on Drawings a. Record any deviations from Contract Documents. b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the change by graphic line and note as required. c. Date all entries. d. Call attention to the entry by a "cloud" drawn around the area or areas affected. e. In the event of overlapping changes, use different colors for the overlapping changes. Conversion of schematic layouts a. In some cases on the Drawings, arrangements of conduits, circuits, piping, ducts, and similar items, are shown schematically and are not intended to portray precise physical layout. 1) Final physical arrangement is determined by the Contractor, subject to the City's approval. 2) However, design of future modifications of the facility may require accurate information as to the final physical layout of items which are shown only schematically on the Drawings. b. Show on the job set of Record Drawings, by dimension accurate to within 1 inch, the centerline of each run of items. 1) Final physical arrangement is determined by the Contractor, subject to the City's approval. 2) Show, by symbol or note, the vertical location of the Item ("under slab", "in ceiling plenum", "exposed", and the like). 3) Make all identification sufficiently descriptive that it may be related reliably to the Specifications. c. The City may waive the requirements for conversion of schematic layouts where, in the City's judgment, conversion serves no useful purpose. However, do not rely upon waivers being issued except as specifically issued in writing by the City. B. Final Project Record Documents Transfer of data to Drawings a. Carefully transfer change data shown on the job set of Record Drawings to the corresponding final documents, coordinating the changes as required. b. Clearly indicate at each affected detail and other Drawing a full description of changes made during construction, and the actual location of items. c. Call attention to each entry by drawing a "cloud" around the area or areas affected. CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 01 78 39 - 4 DAP PROJECT RECORD DOCUMENTS Page 4 of 4 d. Make changes neatly, consistently and with the proper media to assure longevity and clear reproduction. 2. Transfer of data to other Documents a. If the Documents, other than Drawings, have been kept clean during progress of the Work, and if entries thereon have been orderly to the approval of the City, the job set of those Documents, other than Drawings, will be accepted as final Record Documents. b. If any such Document is not so approved by the City, secure a new copy of that Document from the City at the City's usual charge for reproduction and handling, and carefully transfer the change data to the new copy to the approval of the City. 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE -INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] DATE NAME 4/7/2014 M.Domenech END OF SECTION Revision Log SUMMARY OF CHANGE Revised for DAP Application CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 SECTION 34 4120 - LED PILOT PROGRAM CFW LED Residential 100 - 150W Replacement Specification December 2013 City of Fort Worth Specification for Residential LED Roadway Luminaires PART 1— GENERAL 1.1. REFERENCES The publications listed below form a part of this specification to the extent referenced. Publications are referenced within the text by their basic designation only. Versions listed shall be superseded by updated versions as they become available. A. American National Standards Institute (ANSI) 1. C136.2-2004 (or latest), American National Standard for Roadway and Area Lighting Equipment—Luminaire Voltage Classification 2. C136.10-2010 (or latest), American National Standard for Roadway and Area Lighting Equipment - Locking -Type Photocontrol Devices and Mating Receptacle Physical and Electrical Interchangeability and Testing 3. C136.15-2011 (or latest), American National Standard for Roadway and Area Lighting Equipment— Luminaire Field Identification 4. C136.22-2004 (R2009 or latest), American National Standard for Roadway and Area Lighting Equipment — Internal Labeling of Luminaires 5. C136.25-2009 (or latest), American National Standard for Roadway and Area Lighting Equipment— Ingress Protection (Resistance to Dust, Solid Objects and Moisture) for Luminaire Enclosures 6. C136.31-2010 (or latest), American National Standard for Roadway Lighting Equipment— Luminaire Vibration 7. C136.37-2011 (or latest), American National Standard for Roadway and Area Lighting Equipment - Solid State Light Sources Used in Roadway and Area Lighting B. American Society for Testing and Materials International (ASTM) 1. B117-09 (or latest), Standard Practice for Operating Salt Spray (Fog) Apparatus 2. D1654-08 (or latest), Standard Test Method for Evaluation of Painted or Coated Specimens Subjected to Corrosive Environments 3. D523-08 (or latest), Standard Test Method for Specular Gloss 4. G154-06 (or latest), Standard Practice for Operating Fluorescent Light Apparatus for UV Exposure of Nonmetallic Materials C. Council of the European Union (EC) 1. RoHS Directive 2002/95/EC, on the restriction of the use of certain hazardous substances in electrical and electronic equipment D. Federal Trade Commission (FTC) 1. Green Guides, 16 CFR Part 260, Guides for the Use of Environmental Marketing Claims E. Illuminating Engineering Society of North America (IESNA or IES) 1. DG-4-03 (or latest), Design Guide for Roadway Lighting Maintenance 2. HB-10-11 (or latest), IES Lighting Handbook, 10th Edition 3. LM-50-99 (or latest), IESNA Guide for Photometric Measurement of Roadway Lighting Installations 4. LM-61-06 (or latest), IESNA Approved Guide for Identifying Operating Factors Influencing Measured Vs. Predicted Performance for Installed Outdoor High Intensity Discharge (HID) Luminaires 5. LM-79-08 (or latest), IESNA Approved Method for the Electrical and Photometric Measurements of Solid -Sate Lighting Products Adapted from the DOE MSSLC Model Specification for LED Roadway Luminaires, Version 1.0 P a g e I 1 City of Fort Worth Specification for Residential LED Roadway Luminaires 6. LM-80-08 (or latest), IESNA Approved Method for Measuring Lumen Maintenance of LED Light Sources 7. RP-8-00 (or latest), ANSI / IESNA American National Standard Practice for Roadway Lighting 8. RP-16-10 (or latest), ANSI/IES Nomenclature and Definitions for Illuminating Engineering 9. TM-3-95 (or latest), A Discussion of Appendix E - "Classification of Luminaire Lighting Distribution," from ANSI/IESNA RP-8-83 10. TM-15-11 (or latest), Luminaire Classification System for Outdoor Luminaires 11. TM-21-11 (or latest), Projecting Long Term Lumen Maintenance of LED Light Sources F. Institute of Electrical and Electronics Engineers (IEEE) 1. IEEE C62.41.2-2002 (or latest), IEEE Recommended Practice on Characterization of Surges in Low -Voltage (1000 V and less) AC Power Circuits 2. ANSI/IEEE C62.45-2002 (or latest), IEEE Recommended Practice on Surge Testing for Equipment Connected to Low -Voltage (1000 V and Less) AC Power Circuits G. National Electrical Manufacturers Association (NEMA) 1. ANSI/NEMA/ANSLG C78.377-2008 (or latest), American National Standard for the Chromaticity of Solid State Lighting Products H. National Fire Protection Association (NFPA) 1. 70— National Electrical Code (NEC) I. Underwriters Laboratories (UL) 1. 1449, Surge Protective Devices 2. 1598, Luminaires 3. 8750, Light Emitting Diode (LED) Equipment for Use in Lighting Products 1.2. RELATED DOCUMENTS A. Contract Drawings and conditions of Contract (including General Conditions, Addendum to the General Conditions, Special Conditions, Division 01 Specifications Sections and all other Contract Documents) apply to the work of this section. a. See the separate Specification for Adaptive Control and Remote Monitoring of LED Roadway Luminaires for additional driver performance and interface requirements. 1.3. DEFINITIONS A. Lighting terminology used herein is defined in IES RP-16. See referenced documents for additional definitions. Exception: The term "driver" is used herein to broadly cover both drivers and power supplies, where applicable. Clarification: The term "LED light source(s)" is used herein per IES LM-80 to broadly cover LED package(s), module(s), and array(s). 1.4. QUALITY ASSURANCE A. Before approval and purchase, Owner may request luminaire sample(s) identical to product configuration(s) submitted for inspection. Owner may request IES LM-79 testing of luminaire sample(s) to verify performance is within manufacturer -reported tolerances. Adapted from the DOE MSSLC Model Specification for LED Roadway Luminaires, Version 1.0 P a g e 12 City of Fort Worth Specification for Residential LED Roadway Luminaires B. After installation, Owner may perform IES LM-50 field measurements to verify performance requirements outlined in Appendix A, giving consideration to measurement uncertainties outlined in IES LM-61. 1.5. LIGHTING SYSTEM PERFORMANCE A. Energy Conservation 1. Connected Load a. Luminaires shall have maximum nominal luminaire input wattage as specified for each luminaire type in Appendix A. 2. Lighting Controls a. See separate controls specification identified in section 1.2 above, if applicable. b. See section 2.1-13 below for driver control interface and performance requirements. c. See section 2.1-K below for photocontrol receptacle requirements. B. Photometric Requirements 1. Luminaires shall meet the general criteria provided in the body of this specification and the particular criteria for each luminaire type defined in Appendix A. 1.6. REQUIRED SUBMITTALS FOR EACH LUMINAIRE TYPE DEFINED IN APPENDIX A A. General submittal content shall include 1. Completed Appendix E submittal form 2. Luminaire cutsheets 3. Cutsheets for LED light sources 4. Cutsheets for LED driver(s) a. If dimmable LED driver is specified, provide diagrams illustrating light output and input power as a function of control signal. 5. Cutsheets for surge protection device, if applicable 6. Instructions for installation and maintenance 7. Summary of luminaire recycled content and recyclability per the FTC Green Guides, expressed by percentage of luminaire weight B. LM-79 luminaire photometric report(s) shall be produced by the test laboratory and include 1. Name of test laboratory a. The test laboratory must hold National Voluntary Laboratory Accreditation Program (NVLAP) accreditation for the IES LM-79 test procedure or must be qualified, verified, and recognized through the U.S. Department of Energy's CALIPER program. For more information, see httr)://ts.nist.gov/standards/scopes/eelit.htm or www.ssl.enerRv.Rov/test labs.html. 2. Report number 3. Date 4. Complete luminaire catalog number a. Provide explanation if catalog number in test report(s) does not match catalog number of luminaire submitted i. Clarify whether discrepancy does not affect performance, e.g., in the case of differing luminaire housing color. Adapted from the DOE MSSLC Model Specification for LED Roadway Luminaires, Version 1.0 P a g e 13 City of Fort Worth Specification for Residential LED Roadway Luminaires ii. If nominal performance of submitted and tested products differ, submit additional LM-79 report(s) and derivation as indicated in Appendix C. 5. Description of luminaire, LED light source(s), and LED driver(s) 6. Goniophotometry C. Calculations and supporting test data per Appendix B indicating a lumen maintenance life of not less than 36,000 operating hours D. Computer -generated point -by -point photometric analysis of maintained photopic light levels as per Appendix A 1. Calculations shall be for maintained values, i.e. Light Loss Factor (LLF) < 1.0, where LLF = LLD x LDD x LATF, and a. Lamp Lumen Depreciation (LLD) i. Shall be 0.95. ii. Shall be the percentage of initial output calculated in section 1.6-C. b. Luminaire Dirt Depreciation (LDD) = 0.90, as per IES DG-4 for an enclosed and gasketed roadway luminaire installed in an environment with less than 150 µg/m3 airborne particulate matter and cleaned every four years. c. Luminaire Ambient Temperature Factor (LATF) = 1.00 2. Calculation/measurement points shall be per IES RP-8. E. Summary of reliability testing performed for LED driver(s) F. Written product warranty as per section 1.7 below G. Safety certification and file number 1. Applicable testing bodies are determined by the US Occupational Safety Health Administration (OSHA) as Nationally Recognized Testing Laboratories (NRTL) and include: CSA (Canadian Standards Association), ETL (Edison Testing Laboratory), and UL (Underwriters Laboratory). H. Buy American documentation 1. Manufacturers listed on the current NEMA Listing of Companies Offering Outdoor Luminaires Manufactured in U.S.A. for Recovery Act Projects need only provide a copy of the document. 2. Other manufacturers shall submit documentation as per the DOE Guidance on Documenting Compliance with the Recovery Act Buy American Provisions (http://wwwl.eere.enerizv.jzov/recoverv/buv american provision.html). 1.7. WARRANTY A. Provide a minimum ten-year warranty covering maintained integrity and functionality of 1. Luminaire housing, wiring, and connections 2. LED light source(s) a. Negligible light output from more than 10 percent of the LED packages constitutes luminaire failure. 3. LED driver(s) B. Warranty period shall begin 90 days after date of invoice, or as negotiated by owner such as in the case of an auditable asset management system. PART 2 — PRODUCTS 2.1. LUMINAIRE REQUIREMENTS Adapted from the DOE MSSLC Model Specification for LED Roadway Luminaires, Version 1.0 P a g e 14 City of Fort Worth Specification for Residential LED Roadway Luminaires A. General Requirements 1. Luminaires shall be as specified for each type in Appendix A. 2. Luminaire shall have an external label per ANSI C136.15 3. Luminaire shall have an internal label per ANSI C136.22. 4. Luminaire to have internal label of manufactured date visible when drive compartment opened. 5. Nominal luminaire input wattage shall account for nominal applied voltage and any reduction in driver efficiency due to sub -optimal driver loading. 6. Luminaires shall start and operate in -20°C to +40°C ambient. 7. Electrically test fully assembled luminaires before shipment from factory. 8. Effective Projected Area (EPA) and weight of the luminaire shall not exceed the values indicated in Appendix A. 9. Luminaires shall be designed for ease of component replacement and end -of -life disassembly. 10. Luminaires shall have tool -less entry for access to driver compartment 11. Luminaires shall be a minimum of IP65 rated 12. Luminaires must be available in 4000 K and 3000 K options 13. Luminaires shall be rated for the ANSI C136.31 Vibration Level indicated in Appendix A. 14. LED light source(s) and driver(s) shall be RoHS compliant. 15. Transmissive optical components shall be applied in accordance with OEM design guidelines to ensure suitability for the thermal/mechanical/chemical environment. B. Driver 1. Rated case temperature shall be suitable for operation in the luminaire operating in the ambient temperatures indicated in section 2.1-A above. 2. Shall have a drive current no higher than 700mA 3. Shall accept the voltage or voltage range indicated in Appendix A at 50/60 Hz, and shall operate normally for input voltage fluctuations of plus or minus 10 percent. 4. Shall have a minimum Power Factor (PF) of 0.90 at full input power and across specified voltage range. 5. Control signal interface a. Luminaire types indicated "Required" in Appendix A shall accept a control signal as specified via separate controls specification referenced in section 1.2 above, e.g., for dimming. b. Luminaire types indicated "Not Required" in Appendix A need not accept a control signal. C. Electrical immunity Luminaire shall meet the "Basic" requirements in Appendix D. Manufacturer shall indicate on submittal form (Appendix E) whether failure of the electrical immunity system can possibly result in disconnect of power to luminaire. Luminaire shall meet the "Elevated" requirements in Appendix D. Manufacturer shall indicate on submittal form (Appendix E) whether failure of the electrical immunity system can possibly result in disconnect of power to luminaire. D. Electromagnetic interference 1. Shall have a maximum Total Harmonic Distortion (THD) of 20% at full input power and across specified voltage range. 2. Shall comply with FCC 47 CFR part 15 non -consumer RFI/EMI standards. Adapted from the DOE MSSLC Model Specification for LED Roadway Luminaires, Version 1.0 Page 15 City of Fort Worth Specification for Residential LED Roadway Luminaires E. Electrical safety testing 1. Luminaire shall be listed for wet locations by an OSHA NRTL. 2. Luminaires shall have locality -appropriate governing mark and certification. F. Painted or finished luminaire components exposed to the environment 1. Shall exceed a rating of six per ASTM D1654 after 1000hrs of testing per ASTM B117. 2. The coating shall exhibit no greater than 30% reduction of gloss per ASTM D523, after 500 hours of QUV testing at ASTM G154 Cycle 6. G. Thermal management 1. Mechanical design of protruding external surfaces (heat sink fins) for shall facilitate hose -down cleaning and discourage debris accumulation. 2. Liquids or other moving parts shall be clearly indicated in submittals, shall be consistent with product testing, and shall be subject to review by Owner. H. IES TM-15 limits for Backlight, Uplight, and Glare (BUG Ratings) shall be as specified for each luminaire type in Appendix A. 1. Calculation of BUG Ratings shall be for initial (worst -case) values, i.e., Light Loss Factor (LLF) = 1.0. 2. If luminaires are tilted upward for calculations in section 1.6-D, BUG Ratings shall be calculated for the same angle(s) of tilt. I. Minimum Color Rendering Index (CRI): 70. J. Correlated Color Temperature (CCT) 1. If nominal CCT specified in Appendix A is listed in Table 1 below, measured CCT and Duv shall be as listed in Table 1. Table 1. Allowable CCT and Duv (adapted from NEMA C78.377) Manufacturer -Rated Allowable LM-79 Chromaticity Values Nominal CCT (K) Measured CCT (K) =Measured Duv 2700 2580 to 2870 -0.006 to 0.006 3000 2870 to 3220 -0.006 to 0.006 3500 3220 to 3710 -0.006 to 0.006 4000 3710 to 4260 -0.005 to 0.007 4500 4260 to 4746 -0.005 to 0.007 5000 4745 to 5311 -0.004 to 0.008 5700 5310 to 6020 -0.004 to 0.008 6500 6020 to 7040 -0.003 to 0.009 2. If nominal CCT specified in Appendix A is not listed in Table 1, measured CCT and Duv shall be as per the criteria for Flexible CCT defined in NEMA C78.377. K. The following shall be in accordance with corresponding sections of ANSI C136.37 1. Wiring and grounding a. All internal components shall be assembled and pre -wired using modular electrical connections. 2. Mounting provisions a. Specific configurations are indicated in Appendix A 3. Terminal blocks for incoming AC lines 4. Photocontrol receptacle 5. Latching and hinging 6. Ingress protection Adapted from the DOE MSSLC Model Specification for LED Roadway Luminaires, Version 1.0 P a g e 16 City of Fort Worth Specification for Residential LED Roadway Luminaires 2.2. PRODUCT MANUFACTURERS A. Any manufacturer offering products that comply with the required product performance and operation criteria may be considered. 2.3. MANUFACTURER SERVICES A. Manufacturer or local sales representative shall provide installation and troubleshooting support via telephone and/or email. END OF SECTION Adapted from the DOE MSSLC Model Specification for LED Roadway Luminaires, Version 1.0 P a g e 17 City of Fort Worth Specification for Residential LED Roadway Luminaires APPENDIX A MATERIAL SPECIFICATION LUMINAIRE TYPE "A" EXISTING LUMINAIRE TO BE REPLACED (FOR REFERENCE ONLY) BENCHMARK LUMINAIRE: Lamp wattage and type 100 W HPS/ 150W MH Initial downward luminaire output (lumens below horizontal) -- 0.80 Light loss factor LENS: ❑ Flat ("cutoff' style) 0 Sag/drop IES' FORWARD TYPE: ❑ I ❑ II 2111 ❑ IV ❑ V ❑ VS IES1 LATERAL TYPE: ❑ Very short ❑ Short 0 Medium ❑ Long ❑ Very long PERFORMANCE CRITERIA: LED LUMINAIRE INPUT POWER: Max. nominal luminaire input power 105 W NOMINAL CCT: Rated correlated color temperature 3000 K PHOTOPICZ DOWNWARD Minimum maintained luminaire output below horizontal LUMINAIRE OUTPUT: CUTOFF CLASSIFICATION Full Cutoff Only VOLTAGE: Nominal luminaire input voltage 120/208/240 V FINISH: Luminaire housing finish color Gray WEIGHT: Maximum luminaire weight 30 lb EPA: Maximum effective projected area 0.7 ftz MOUNTING: Mtg. method ❑ Post -top 0 Side -arm ❑ Trunnion/yoke ❑ Swivel -tenon Tenon nominal pipe size (NPS) 1-1/4" to 2-3/8" VIBRATION: ANSI test level 0 Level 1 (normal) ❑ Level 2 (bridge/overpass) DRIVER: Control signal interface 0 Not required ❑ Required Adapted from the DOE MSSLC Model Specification for LED Roadway Luminaires, Version 1.0 P a g e 18 Appendix B Estimating LED Lumen Maintenance IES TM-21 allows for extrapolation of expected lumen maintenance from available test data. The extent of such extrapolation is limited by the duration of testing completed and the number of samples used in the testing. The TM-21 methodology shall be used by the manufacturer to determine lamp lumen depreciation (LLD) at end of lumen maintenance life per section 1.6-C. The applicant may estimate lumen maintenance in one of two ways: Option 1: Component Performance Under this compliance path, the applicant must submit calculations per TM-21 predicting lumen maintenance at the luminaire level using In Situ Temperature Measurement Testing (ISTMT) and LM-80 data. To be eligible for the Component Performance option, ALL of the conditions below must be met. If ANY of the conditions is not met, the component performance option may not be used and the applicant must use Option 2 for compliance. 1. The LED light source(s) have been tested according to LM-80. 2. The LED drive current specified by the luminaire manufacturer is less than or equal to the drive current specified in the LM-80 test report. 3. The LED light source(s) manufacturer prescribes/indicates a temperature measurement point (Ts) on the light source(s). 4. The Ts is accessible to allow temporary attachment of a thermocouple for measurement of in situ temperature. Access via a temporary hole in the housing, tightly resealed during testing with putty or other flexible sealant is allowable. 5. For the hottest LED light source in the luminaire, the temperature measured at the Ts during ISTMT is less than or equal to the temperature specified in the LM-80 test report for the corresponding drive current or higher, within the manufacturer's specified operating current range. a. The ISTMT laboratory must be approved by OSHA as a Nationally Recognized Testing Lab (NRTL), must be qualified, verified, and recognized through DOE's CALIPER program, or must be recognized through UL's Data Acceptance Program. b. The ISTMT must be conducted with the luminaire installed in the appropriate application as defined by ANSI/UL 1598 (hardwired luminaires), with bird -fouling appropriately simulated (and documented by photograph) as determined by the manufacturer. Option 2: Luminaire Performance Under this compliance path, the applicant must submit TM-21 calculations based on LM-79 photometric test data for no less than three samples of the entire luminaire. Duration of operation and interval between photometric tests shall conform to the TM-21 criteria for LED light sources. For example, testing solely at 0 and 6000 hours of operation would not be adequate for the purposes of extrapolation. Between LM-79 tests, the luminaire test samples must be operated long-term in the appropriate application as defined by ANSI/UL 1598 (hardwired luminaires). The test laboratory must hold Adapted from the DOE MSSLC Model Specification for LED Roadway Luminaires P a g e I B-1 NVLAP accreditation for the LM-79 test procedure or must be qualified, verified, and recognized through the U.S. Department of Energy (DOE)'s CALIPER program. The extent of allowable extrapolation (either 5.5 or 6 times the test duration) depends on the total number of LED light sources (no less than 10 and preferably more than 19) installed in the luminaire samples, as per TM-21. This compliance path poses a greater testing burden to luminaire manufacturers but incorporates long-term testing of other components in the system, such as drivers. Under either compliance path, values used for extrapolation shall be summarized per TM-21 Tables 1 and 2. Submitted values for lumen maintenance lifetime and the associated percentage lumen maintenance shall be "reported" rather than "projected" as defined by TM-21. Supporting diagrams are requested to facilitate interpretation by Owner. Adapted from the DOE MSSLC Model Specification for LED Roadway Luminaires P a g e I B-2 APPENDIX C PRODUCT FAMILY TESTING LM-79 AND ISTMT It is recognized that due to the time and cost required for product testing, it would not be realistic to expect manufacturers offering a multitude of unique luminaire configurations to test every possible configuration. Therefore, the "product families" method may be utilized for LM-79 and ISTMT, whereby manufacturers identify a set of representative products for which test data can be used to demonstrate the accuracy of interpolated or extrapolated performance of product configurations lacking test data. Precedent for this approach can be found in LM-80. If the particular luminaire configuration submitted has not been tested, the performance may be conservatively represented by test data for another luminaire configuration having: • The same intensity distribution (typically only applies to LM-79) • The same or lower nominal CCT • The same or higher nominal drive current • The same or greater number of LED light source(s) • The same or lower percentage driver loading and efficiency • The same or smaller size luminaire housing. A more accurate estimate of performance can be obtained by linear interpolation between two or more tests differing in terms of the six parameters listed above. For example, consider a hypothetical luminaire offered in a single size housing, and having the following parameters: • Three intensity distributions: IES Type II, III, or IV • Three CCTs: 4000, 5000, and 6000K • Three drive currents: 350, 525, and 700 mA • Four LED quantities: 20, 40, 60, or 80 LEDs. Table CA illustrates a set of tests which could allow for accurate interpolation between tested configurations, given a single luminaire housing size and essentially constant driver efficiency; these 10 tests may provide representative data for the 108 possible product configurations. Note that normalized intensity distribution must not be affected by the other three parameters. Table C.I. Representative testing of a single luminaire housing size Tests Intensity distribution (I ES Type) CCT (K) Drive current (mA) # of LEDs 4,5 6,7 8, 9, 10 II, III, IV IV IV IV 4000 5000, 6000 4000 4000 700 700 325,525 700 80 80 80 20, 40, 60 For example, the manufacturer could detail interpolation as shown in Table C.2, applying the following multipliers to the base test #2 to model a configuration with Type III intensity distribution, 5000K CCT, 525 mA drive current, and 40 LEDs: • Ratio of test #4 lumens to test #3 lumens • Ratio of test #7 lumens to test #3 lumens • Ratio of test #9 lumens to test #3 lumens. Adapted from the DOE MSSLC Model Specification for LED Roadway Luminaires P a g e I C-1 Table C.2. Multipliers for Test #2 to yield: Type III , 5000K, 525mA, 40 LEDs Test # Intensity distribution (I ES Type) CCT (K) Drive current (mA) # of LEDs Multiplier (lumens ratio) 2 III 4000 700 80 n/a 3 IV 4000 700 80 n/a 4 IV I 5000 700 80 #4 / #3 7 IV I 525 80 #7 / #3 4000 9 IV 4000 700 40 #9 / #3 Interpolation between minimal LM-79 and ISTMT data is more difficult if housing size increases with increasing wattage; it may not be clear whether the lowest -wattage configuration would be expected to "run cooler" than the highest -wattage configuration. In these circumstances, the adequacy of submitted data is subject to Owner approval. At this time, the "successor" method cannot be used; luminaires tested must utilize the LED light source(s) characterized by the submitted LM-80 report. Adapted from the DOE MSSLC Model Specification for LED Roadway Luminaires P a g e I C-2 APPENDIX D ELECTRICAL IMMUNITY Test Procedure • Electrical Immunity Tests 1, 2 and 3, as defined by their Test Specifications, shall be performed on an entire powered and connected luminaire, including any control modules housed within the luminaire, but excluding any control modules mounted externally, such as a NEMA socket connected photo -control. A shorting cap should be placed across any such exterior connector. • The luminaire shall be connected to an AC power source with a configuration appropriate for nominal operation. The AC power source shall have a minimum available short-circuit current of 200A. The luminaire shall be tested at the nominal input voltage specified in Appendix A, or at the highest input voltage in the input voltage range specified in Appendix A. • Electrical Immunity test waveforms shall be superimposed on the input AC power line at a point within 6 inches (15cm) of entry into the luminaire using appropriate high -voltage probes and a series coupler/decoupler network (CDN) appropriate for each coupling mode, as defined by ANSI/IEEE C62.45-2002. The test area for all tests shall be set up according to ANSI/IEEE C62.45- 2002, as appropriate. • Prior to electrical immunity testing a set of diagnostic measurements shall be performed, and the results recorded to note the pre -test function of the luminaire after it has reached thermal equilibrium. These measurements should include at a minimum: a) For all luminaires, Real Power, Input RMS Current, Power Factor and THD at full power/light output b) For luminaires specified as dimmable, Real Power, Input RMS Current, Power Factor and THD at a minimum of 4 additional dimmed levels, including the rated minimum dimmed level • Tests shall be applied in sequential order (Test 1, followed by Test 2, followed by Test 3). If a failure occurs during Test 3, then Test 3 shall be re -applied to a secondary luminaire of identical construction. • Following the completion of Tests 1, 2, and 3, the same set of diagnostic measurements performed pre -test should be repeated for all tested luminaires, and the results recorded to note the post-test function of the luminaire(s). • A luminaire must function normally and show no evidence of failure following the completion of Test 1 + Test 2 + Test 3 (for a single tested luminaire), or the completion of Test 1 + Test 2 on a primary luminaire and Test 3 on a secondary luminaire. Abnormal behavior during testing is acceptable. • A luminaire failure will be deemed to have occurred if any of the following conditions exists following the completion of testing: a) A hard power reset is required to return to normal operation b) A noticeable reduction in full light output (e.g. one or more LEDs fail to produce light, or become unstable) is observed c) Any of the post-test diagnostic measurements exceeds by ±5% the corresponding pre -test diagnostic measurement. d) The luminaire, or any component in the luminaire (including but not limited to an electrical connector, a driver, a protection component or module) has ignited or shows evidence of Adapted from the DOE MSSLC Model Specification for LED Roadway Luminaires P a g e I D-1 melting or other heat -induced damage. Evidence of cracking, splitting, rupturing, or smoke damage on any component is acceptable. Test Specifications NOTE: L1 is typically "HOT", L2 is typically "NEUTRAL" and PE = Protective Earth. Test 1) Ring Wave: The luminaire shall be subjected to repetitive strikes of a "C Low Ring Wave" as defined in IEEE C62.41.2-2002, Scenario 1, Location Category C. The test strikes shall be applied as specified by Table D.I. Prior to testing, the ring wave generator shall be calibrated to simultaneously meet BOTH the specified short circuit current peak and open circuit voltage peak MINIMUM requirements. Note that this may require that the generator charging voltage be raised above the specified level to obtain the specified current peak. Calibrated current probes/transformers designed for measuring high -frequency currents shall be used to measure test waveform currents. Test waveform current shapes and peaks for all strikes shall be compared to ensure uniformity throughout each set (coupling mode + polarity/phase angle) of test strikes, and the average peak current shall be calculated and recorded. If any individual peak current in a set exceeds by ±10% the average, the test setup shall be checked, and the test strikes repeated. Table D.1: 0.5 µS — 100Hz Ring Wave Specification Parameter Test Level/Configuration Short Circuit Current Peak 0.5 kA Open Circuit Voltage Peak 6 kV Source Impedance 12 Q Coupling Modes L1 to PE, L2 to PE, L1 to L2 Polarity and Phase Angle Positive at 90' and Negative at 270° Test Strikes 5 for each Coupling Mode and Polarity/Phase Angle combination Time between Strikes 1 minute Total Number of Strikes = 5 strikes x 4 coupling modes x 2 polarity/phase angles = 40 total strikes Test 2) Combination Wave: The luminaire shall be subjected to repetitive strikes of a "C High Combination Wave" or "C Low Combination Wave", as defined in IEEE C62.41.2-2002, Scenario 1, Location Category C. The test strikes shall be applied as specified by Table D.2. The "Low" test level shall be used for luminaires with Basic Electrical Immunity requirements, while the "High" test level shall be used for luminaires with Elevated Electrical Immunity requirements. Prior to testing, the combination wave generator shall be calibrated to simultaneously meet BOTH the specified short circuit current peak and open circuit voltage peak MINIMUM requirements. Note that this may require that the generator charging voltage be raised above the specified level to obtain the specified current peak. Calibrated current probes/transformers designed for measuring high -frequency currents shall be used to measure test waveform currents. Adapted from the DOE MSSLC Model Specification for LED Roadway Luminaires P a g e I D-2 Test Duration Total Test Duration Test waveform current shapes and peaks for all strikes shall be compared to ensure uniformity throughout each set (coupling mode + polarity/phase angle) of test strikes, and the average peak current shall be calculated and recorded. If any individual peak current in a set exceeds by ±10% the average, the test setup shall be checked, and the test strikes repeated. Table D.2: 1.2/50µS — 8/20 µS Combination Wave Specification Parameter Test Level/ Configuration 1.2/50 µS Open Circuit Voltage Peak Low: 6 kV High: 10kV 8/20 µS Short Circuit Current Peak Low: 3 kA High: 10kA Source Impedance 2Q Coupling Modes L1 to PE, L2 to PE, L1 to L2 Polarity and Phase Angle Positive at 90' and Negative at 270° Test Strikes 5 for each Coupling Mode and Polarity/Phase Angle combination Time Between Strikes 1 minute Total Number of Strikes = 5 strikes x 4 coupling modes x 2 polarity/phase angles = 40 total strikes Test 3) Electrical Fast Transient (EFT): The luminaire shall be subjected to "Electrical Fast Transient Bursts", as defined in IEEE C62.41.2 -2002. The test area shall be set up according to IEEE C62.45-2002. The bursts shall be applied as specified by Table D.3. Direct coupling is required; the use of a coupling clamp is not allowed. Table D.3: Electrical Fast Transient (EFT) Specification Parameter Test Level/ Configuration Open Circuit Voltage Peak 3 kV Burst Repetition Rate 2.5 kHz Burst Duration 15 mS Burst Period 300 mS Coupling Modes L1 to PE, L2 to PE, L1 to L2 Polarity Positive and Negative 1 minute for each Coupling Mode and Polarity combination = 1 minute x 7 coupling modes x 2 polarities = 14 minutes Adapted from the DOE MSSLC Model Specification for LED Roadway Luminaires Page I D-3 APPENDIX E PRODUCT SUBMITTAL FORM Luminaire Type' Manufacturer Model number Housing finish color Tenon nominal pipe size (inches) Nominal luminaire weight (lb) Nominal luminaire EPA (ft2) Nominal input voltage (V) ANSI vibration test level Nominal BUG Ratings Make/model of LED light source(s) Make/model of LED driver(s) Dimmability Control signal interface Upon electrical immunity system failure Thermal management Lumen maintenance testing duration (hr Reported lumen maintenance life (hr) 2 Warranty period (yr) Parameter Initial photopic output (Im) Maintained photopic output (Im) Lamp lumen depreciation Initial input power (W) Maintained input power (W) Initial LED drive current (mA) Maintained LED drive current (mA) Drive current used In -situ LED Tc ('C) CCT (K) Additional product description 0 Level 1 (Normal) I ❑ Level 2 (bridge/overpass) ❑ Dimmable I 0 Not dimmable ❑ Possible disconnect ❑ No possible disconnect ❑ Moving parts 0 No moving parts Nominal value I Tolerance (%) See Appendix A, and attach supporting documentation as required. 2 Value shall be no less than as specified in section 1.6-C, and shall not exceed six times the testing duration indicated in the row above. Value shall be consistent with values submitted in the rows below for maintained light output, maintained input power, and maintained drive current. Adapted from the DOE MSSLC Model Specification for LED Roadway Luminaires P a g e I E-1 017823-1 DAP OPERATION AND MAINTENANCE DATA Page 1 of 5 SECTION 0178 23 OPERATION AND MAINTENANCE DATA PART1- GENERAL 1.1 SUMMARY A. Section Includes: 1. Product data and related information appropriate for City's maintenance and operation of products furnished under Contract 2. Such products may include, but are not limited to: a. Traffic Controllers b. Irrigation Controllers (to be operated by the City) c. Butterfly Valves B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 — General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Schedule 1. Submit manuals in final form to the City within 30 calendar days of product shipment to the project site. 1.5 SUBMITTALS A. Submittals shall be in accordance with Section 0133 00. All submittals shall be approved by the City prior to delivery. 1.6 INFORMATIONAL SUBMITTALS A. Submittal Form 1. Prepare data in form of an instructional manual for use by City personnel. 2. Format a. Size: 8 1/2 inches x 11 inches b. Paper 1) 40 pound minimum, white, for typed pages 2) Holes reinforced with plastic, cloth or metal c. Text: Manufacturer's printed data, or neatly typewritten CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 01 78 23 - 2 DAP OPERATION AND MAINTENANCE DATA Page 2 of 5 d. Drawings 1) Provide reinforced punched binder tab, bind in with text 2) Reduce larger drawings and fold to size of text pages. e. Provide fly -leaf for each separate product, or each piece of operating equipment. 1) Provide typed description of product, and major component parts of equipment. 2) Provide indexed tabs. f. Cover 1) Identify each volume with typed or printed title "OPERATING AND MAINTENANCE INSTRUCTIONS". 2) List: a) Title of Project b) Identity of separate structure as applicable c) Identity of general subject matter covered in the manual 3. Binders a. Commercial quality 3-ring binders with durable and cleanable plastic covers b. When multiple binders are used, correlate the data into related consistent groupings. 4. If available, provide an electronic form of the O&M Manual. B. Manual Content Neatly typewritten table of contents for each volume, arranged in systematic order a. Contractor, name of responsible principal, address and telephone number b. A list of each product required to be included, indexed to content of the volume c. List, with each product: 1) The name, address and telephone number of the subcontractor or installer 2) A list of each product required to be included, indexed to content of the volume 3) Identify area of responsibility of each 4) Local source of supply for parts and replacement d. Identify each product by product name and other identifying symbols as set forth in Contract Documents. 2. Product Data a. Include only those sheets which are pertinent to the specific product. b. Annotate each sheet to: 1) Clearly identify specific product or part installed 2) Clearly identify data applicable to installation 3) Delete references to inapplicable information 3. Drawings a. Supplement product data with drawings as necessary to clearly illustrate: 1) Relations of component parts of equipment and systems 2) Control and flow diagrams b. Coordinate drawings with information in Project Record Documents to assure correct illustration of completed installation. c. Do not use Project Record Drawings as maintenance drawings. 4. Written text, as required to supplement product data for the particular installation: a. Organize in consistent format under separate headings for different procedures. b. Provide logical sequence of instructions of each procedure. CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 01 78 23 - 3 DAP OPERATION AND MAINTENANCE DATA Page 3 of 5 5. Copy of each warranty, bond and service contract issued a. Provide information sheet for City personnel giving: 1) Proper procedures in event of failure 2) Instances which might affect validity of warranties or bonds C. Manual for Materials and Finishes 1. Submit 5 copies of complete manual in final form. 2. Content, for architectural products, applied materials and finishes: a. Manufacturer's data, giving full information on products 1) Catalog number, size, composition 2) Color and texture designations 3) Information required for reordering special manufactured products b. Instructions for care and maintenance 1) Manufacturer's recommendation for types of cleaning agents and methods 2) Cautions against cleaning agents and methods which are detrimental to product 3) Recommended schedule for cleaning and maintenance 3. Content, for moisture protection and weather exposure products: a. Manufacturer's data, giving full information on products 1) Applicable standards 2) Chemical composition 3) Details of installation b. Instructions for inspection, maintenance and repair D. Manual for Equipment and Systems 1. Submit 5 copies of complete manual in final form. 2. Content, for each unit of equipment and system, as appropriate: a. Description of unit and component parts 1) Function, normal operating characteristics and limiting conditions 2) Performance curves, engineering data and tests 3) Complete nomenclature and commercial number of replaceable parts b. Operating procedures 1) Start-up, break-in, routine and normal operating instructions 2) Regulation, control, stopping, shut -down and emergency instructions 3) Summer and winter operating instructions 4) Special operating instructions c. Maintenance procedures 1) Routine operations 2) Guide to "trouble shooting" 3) Disassembly, repair and reassembly 4) Alignment, adjusting and checking d. Servicing and lubrication schedule 1) List of lubricants required e. Manufacturer's printed operating and maintenance instructions f. Description of sequence of operation by control manufacturer 1) Predicted life of parts subject to wear 2) Items recommended to be stocked as spare parts g. As installed control diagrams by controls manufacturer It. Each contractor's coordination drawings 1) As installed color coded piping diagrams CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 01 78 23 - 4 DAP OPERATION AND MAINTENANCE DATA Page 4 of 5 i. Charts of valve tag numbers, with location and function of each valve j. List of original manufacturer's spare parts, manufacturer's current prices, and recommended quantities to be maintained in storage k. Other data as required under pertinent Sections of Specifications 3. Content, for each electric and electronic system, as appropriate: a. Description of system and component parts 1) Function, normal operating characteristics, and limiting conditions 2) Performance curves, engineering data and tests 3) Complete nomenclature and commercial number of replaceable parts b. Circuit directories of panelboards 1) Electrical service 2) Controls 3) Communications c. As installed color coded wiring diagrams d. Operating procedures 1) Routine and normal operating instructions 2) Sequences required 3) Special operating instructions e. Maintenance procedures 1) Routine operations 2) Guide to "trouble shooting" 3) Disassembly, repair and reassembly 4) Adjustment and checking f. Manufacturer's printed operating and maintenance instructions g. List of original manufacturer's spare parts, manufacturer's current prices, and recommended quantities to be maintained in storage h. Other data as required under pertinent Sections of Specifications 4. Prepare and include additional data when the need for such data becomes apparent during instruction of City's personnel. 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE A. Provide operation and maintenance data by personnel with the following criteria: 1. Trained and experienced in maintenance and operation of described products 2. Skilled as technical writer to the extent required to communicate essential data 3. Skilled as draftsman competent to prepare required drawings CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 01 78 23 - 5 DAP OPERATION AND MAINTENANCE DATA Page 5 of 5 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] DATE NAME 8/31/2012 D. Johnson 4/7/2014 M.Domenech END OF SECTION Revision Log SUMMARY OF CHANGE 1.5.A.1 — title of section removed Revised for DAP Application CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 FORT WORTH. CITY OF FORT WORTH WATER DEPARTMENT STANDARD PRODUCT LIST Updated: 03/07/2023 Note: All water or sewer pipe larger than 1S inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding maybe required for some pipes. Approval IModel INational Water & Sewer - Manholes & Bases/Components 33-39-10 (Rev 2/3/16) ` 07/23/97 33 05 13 Urethane Hydrophilic Waterstop Asahi Kogyo K.K. Adeka Ultra -Seal P-201 ASTM D2240/D412/1)792 04/26/00 33 05 13 Offset Joint for 4' Diam. MH Hanson Concrete Products Drawing No. 35-0048-001 04/26/00 33 05 13 Profile Gasket for 4' Diam. MIR. Press -Seal Gasket Corp. 250-4G Gasket ASTM C-443/C-361 SS MH 1126199 33 05 13 HOPE Manhole Adjustment Rings Ladtech, Inc HDPE Adjustment Ring Traffic and Non -traffic area 5/13/05 33 05 13 Manhole External Wrap Canusa - CPS WrapidSeal Manhole Encapsulation System er - Manholes & Bases/Fiberelass 33-39-13 (1/8/13 1/26/99 33 39 13 Fiberglass Manhole Fluid Containment, Inc. Flowti[e ASTM 3153 Non -traffic area 08/30/06 33 39 13 Fiberglass Manhole L.F. Manufacturing Non -traffic area 1 j Water & Sewer - Manholes & Bases/Frames & Covers/Rectammlar 33-05-13 (Rev 2/3/16) 1 * 33 05 13 (Manholc Frames and Covers Western Iron Works, Bass & Hays Foundry 1001 24"x40" WE) Water & Sewer - Manholes & Bases/Frames & Covers/Standard Boundl 33-05-13 (Rev 2/3/16) 3305 13 Manhole Frames and Covers Western Iron Works, Bass & Hays Foundry 30024 24" Dia. * 3305 13 Manhole Frames and Covers McKinley Iron Works Inc. A 24 AM 24" Dia. 1 08/24/18 3305 13 Manhole Frames and Covers Neenah Foundry R-1272 ASTM A48 & AASHTO M306 24" Dia. 1 08/24/18 3305 13 Manhole Frames and Covers Neenah Foundry R- 165-LM (Hinged) ASTM A48 & AASHTO M306 24" Dia. 1 08/24/18 3305 13 Manhole Frames and Covers Neenah Foundry NF 1274 ASTM A48 & AASHTO M306 30" Dia. 1 08/24/18 3305 13 Manhole Frames and Covers Neenah Foundry R-1743-LM (Hinged) ASTM A48 & AASHTO M306 30" dia. 1 33 05 13 Manhole Frames and Covers Sigma Corporation MH-144N 1 33 05 13 Manhole Frames and Covers Sigma Corporation MH-143N 1 33 05 13 Manhole Frames and Covers Pont-A-Mousson GTS-STD 24" dia. 1 33 05 13 Manhole Frames and Covers Neenah Casting 24" dia. 1 10/31/06 33 05 13 Manhole Frames and Covers (Hinged) Powerseal Hinged Ductile Iron Manhole ASTM A536 24" Dia. 1 7/25/03 3305 13 Manhole Frames and Covers Saint-Gobain Pipelines (Pamrex/rexus) RE32-R8FS 30" Dia. 1 01/31/06 3305 13 30" Dia. MH Ring and Cover East Jordan Iron Works V1432-2 and V1483 Designs AASFITO M306-04 30" Dia. 11/02/10 3305 13 30" Dia. MH Ring and Cover Sigma Corporation MH165IFWN & MH16502 30" Dia 1 07/19/1 t 3305 13 30" Dia. MH Ring and Cover Star Pipe Products NIH32FTWSS-DC 30" Dia 1 08/10/11 3305 13 30" Dia. MH Ring and Cover Accucast 220700 Heavy Duty with Gasket Ring 30" Dia 30" ERGO XL Assembly 10/14/13 3305 13 30" Dia. MH Ring and Cover, (Hinged & Lockable) East Jordan Iron Works with Cam Lock/MPIC/T-Gasket ASSEITO MI 05 & ASTM A536 30" Dia 06/01/17 3405 13 30" Dia. MH Ring and Cover (Hinged & Lockable) CI SIP Industries 2280 (32") ASTM A 48 30" Dia. CAP-ONE-30-FTW, Composite, w/ Lack .111111 33 OS 13 30" Dia. MH Ring and Cover Composite Access Products, L.P. w/o Hmg 30" Dia. 10/07/21 3405 13 30" Dia. MH Ring and Cover Trumbull Manufacturing 32"(30") Frame and Cover 30" Dia. Water &der - Manholes & Bases/Frames & Covers/Water Tight & Pressure Tight 33-05-13 (Rev 2/3/1� 33 05 13 Manhole Frames and Covers Pont-A-Mousson Pamtight 24" Dia. * 3305 13 Manhole Frames and Covers Neenah Casting 24" Dia. * 3305 13 Manhole Frames and Covers Western Iron Works,Bass & Hays Foundry 300-24P 24" Dia. * 3305 13 Manhole Frames and Covers McKinley Iron Works Inc. WPA24AM 24" Dia. 03/08/00 3305 13 Manhole Frames and Covers Accucast RC-2100 ASTM A 48 24" Dia. 04/20/01 3305 13 Manhole Frames and Covers (SIP)Serampore Industries Private Ltd. 300-24-23.75 Ring and Cover ASTM A 48 24" Dia. �Wr - Manholes & Bases/Precast Concrete l2ev 33 39 10 Manhole, Precast Concrete 1/8/13 Hydro Conduit Corp SPL Item 449 ASTM C 478 41" * 33 39 10 Manhole, Precast Concrete Wall Concrete Pipe Co. hic. ASTM C-443 48" 09/23/96 33 39 10 Manhole, Precast Concrete Concrete Product Inc. 48" I.D. Manhole w/ 32" Cone ASTM C 478 48" w/32" cone 05/08/18 33 39 10 Manhole, Precast Concrete The Turner Company 48", 60" I.D. Manhole w/ 32" Cone ASTM C 478 48", 60" 10/27/06 33 39 10 Manhole, Precast Concrete Oldeastle Precast Inc. 48" I.D. Manhole w/ 24" Cone ASTM C 478 48" Diam w 24" Ring 1 06/09/10 33 39 10 Manhole, Precast (Reinforced Polymer)Conaete US Composite Pipe Reinforced Polymer Concrete ASTM C-76 48" to 72" 1 09/06/19 33 3920 Manhole, Precast Concrete Forterra Pipe and Precast 60" & 72" I.D. Manhole w/32" Cone ASTM C-76 60" & 72" 10/07/21 32 39 20 Manhole, Precast Concrete Forterra Pipe and Precast 48" I.D. Manhole w/32" Cone ASTM C-77 48" 10/07/21 33 3920 Manhole, Precast (Reinforced Polymer) Concrete Armorock 48" & 60" I.D. Manhole w/32" Cone 48" & 60" 10/07/21 33 3920 Manhole, Precast (Hybrid) Polymer & PVC Predl Systems 48" & 60" I.D. Manhole w/32" Cone 48" & 60" Non Traffic Areas ASTM C-478; ASTM C-923; 03/07/23 33 3920 Manhole, Precast Concrete AmeriTex Pi a and Products, LLC 48" & 10" I.D. Manhole w/32" Cone ASTM C-443 03/07/23 33 3920 IManhole, Precast (Reinforced Pol er) Concrete P3 Polymers, RockHards 48" & 60" I.D. Manhole w/32" Cone 04/28/07 IManholc, Precast (Reinforced Polymcr) Concrete Amitech USA Meyer Polycrete Pipe Eater & Sewer - Manholes & Bases/Rehab Svstems/Cementitlous EI-14 Manhole Rehab Systems Quadex 04/23/01 EI-14 Manhole Rehab Systems Standard Cement Materials, Inc. Relmer MSP E1-14 Manhole Rehab Systems AP/M Permaform 4120101 E I-14 Manhole Rehab System Strong Company Strong Seal MS2A Rehab System 5/12/03 EI-14 Manhole Rehab System (Liner) Triplex Lining System MH repair product to stop infiltration ASTM D5813 08/30/06 General Concrete Repair FlexKrete Technologies Vinyl Polyester Repair Product Mise. Use * From Original Standard Products List CITY OF FORT WORTH FORT WORTH. WATER DEPARTMENT STANDARD PRODUCT LIST Updated: 03/07/2023 Note: All water or sewer pipe larger than 1S inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding maybe required for some pipes. Approv pec No./ IManufacturer Model1. National Spec Water &Sewer - an o es Bases/Rehab Svstems/NonCementitiousI mmmmw`Moir 05/ 00/96 E1-14 Manhole Rehab Systems Sprayroa, Spray Wall Polyurethane Coating ASTM D639/D790 I 12/14/01 Coating for Corrosion protection(Exterior) ERTECH Series 20230 and 2100 (Asphatic Emulsion) Structures Only I01/31/06 Coatings for Corrosion Protection Chesterton Arc 791, S1BB, Sl, S2 Acid Resistance Test Sewer Applications I8/28/2006 Coatings for Corrosion Protection Warren Environmental S-301 and M-301 Sewer Applications » v�33 nu�pP�ooung i�P�ayolloull- x `Structures 03/19/18 I 39 20� Coating for Corrosion orotection(Exterim) Sherwin Williams Grade (Asohatic Emulsion) Only I 33 05 13 Manhole Insert ME Knutson Enterprises Made to Order - Plastic ASTM D 1248 For 24" dia. I * 33 05 13 Manhole Insert South Western Packaging Made to Order - Plastic ASTM D 1248 For 24" dia. I I * 3305 13 Manhole Insert Noflow-Inflow Made to Order - Plastic ASTM D 1248 For 24" dia. I I 09/23/96 3305 13 Manhole Insert Scuthwestcon Packing & Seals, Inc. Lifesaver - Stainless Steel For 24" dia. I I 09/23/96 3305 13 Manhole Insert Southwestern Packing & Seals, Inc. TetherLok - Stainless Steel For 24" dia I I 711111.72 ara e�Sewer - Pine Casim SDacers 33-05-24 (07/01/13) I Steel Band Casing Spacers Advanced Products and Systems, Inc. Carbon Steel Spacers, Model SI IO2/02/93 Stainless Steel Casing Spacer Advanced Products and Systems, Inc. Stainless Steel Spacer, Model SSI I04/22/87 Casing Spacers Cascade Waterworks Manufacturing Casing Spacers I09/14/10 Stainless Steel Casing Spacer Pipeline Seal and Insulator Stainless Steel Casing Spacer Up to 48" I09/14/10 Coated Steel Casin Spacers Pipeline Seal and Insulator Coated Steel Casin Spacers Up to 48" I 05/10/11 Stainless Steel Casing Spacer Powerseal 4810 Powerchock Up to 48" 03/19/18 Casing Spacers BWM SS-12 Casing Spacer(Stainleas Steel) 03/19/18 Casing Spacers BWM FB-12 Casing Spacer (Coated Carbon Steel) for Non_pressure Pipe and Grouted Casing 03/29/22 33 05 13 Casing Spacers CCI Pipeline Systems CSC12, CSS12 PEW I Water & Sewer - Pines/Ductile Iron 33-11-10(1/8/13) i I * 33 11 10 Ductile Iron Pipe Griffin Pipe Products, Co. Super Bell-Tite Ductile Iron Pressure Pipe, AW WA C150, C151 3" thrn 24" OS/24/18 33 11 10 Ductile Iron Pipe American Ductile Iron Pipe Co. American Fastite Pipe (Bell Spigot) AW WA C150, C151 4" thrn 30" 08/24/18 33 11 10 Ductile Iron Pipe American Ductile Iron Pipe Co. American Flex Ring (Restrained Joint) AW WA C150, C151 4" thin 30" * 33 11 10 Ductile Iron Pipe U.S. Pipe and Foundry Co. AW WA C150, C151 * 33 11 10 Ductile Iron Pipe McWane Cast Iron Pipe Co. AW WA C150, C151 I Water & Sewer - Utility Line Marker (08/24/2018) I I ewer - Coatinss/EDD -39-60 (01/08/13) I INEK 02/25/02 Epoxy Lining System Sauereisen, Inc SewerGard 21 ORS LA County 9210-1.33 I 12/14/01 Epmv Lmmg System Ertech Technical Coatings Ertcch 2030 and 2100 Series I I 04/14/05 Interim Ductile Iron Pipe Coating Induron Protecto 401 ASTM B-117 Ductile Iron Pipe Only I I01/31/06 Coatings for Corrosion Protection Chesterton Arc 791, S1HB, Sl, S2 Acid Resistance Test Sewer Applications I I8/28/2006 Coatings for Corrosion Protection Warren Environmental S-301 and M-301 Sewer Applications I I INNE Sewer - Coatings/Polvurethane I I Sewer - Combination Air Valves I I 05/25/18 I 33-31-70 Air Release Valve A.R.I. USA, Inc. D121LTP02(Compwite Body) 2" I I Sewer - Pines/Concrete I * EI-04 C. Pipe, Reinforced Wall Concrete Pipe Co. Inc. ASTM C 76 I E I-04 Conc. Pipe, Reinforced Hydro Condun Corporation Class III T&G, SPL Item #77 ASTM C 76 I I E I-04 Conc. Pipe, Reinforced Hanson Concrete Products SPL item 495 hirsaliele, 998 Pipe ASTM C 76 I IE I-04 Conc. Pipe, Reinforced Concrete Pipe & Products Co. Inc. ASTM C 76 I I Sewer - Pine Enlargment Svstem (Method)33-31-23 (01/18/13). I Svstem PIM Corporation Polyethylene PIM Corp., Piscata Way, N.J. Approved Previously �Plm McConnell Systems McLat Construction Polyethylene Houston, Texas Approved Previously I TRS Systems Trenchless Replacement System Polyethylene Calgary, Canada Approved Previously I I Sewer - PiDe/Fibere as_ss Reinforced/ 33-31-13(1/8/13) I Hobas Pipe USA, Inc. Holies Pipe (Non -Pressure) ASTM D3262/D3754 I 7/21 /97 33 31 13 Cent. Cast Fiberglass (FRP) I 03/22/10 333 13 Fiberglass It,. (FRP) Ameroa Bondstmod RPMP Pipe AST- D3262-3154 I 04/09/21 33 31 13 Glass -Fiber Reinforced Polviner Pipe FRP Thompson Pie Group Thompson Pipe Flowtite ASTM D32621D3754 03/07/23 3331 13 lFiber.lass Pine (FRP) Future Pine Industries Fiberstron¢ FRP ASTM D3212. ASTM D3681. ASTM D4161. AW WA M45 Sewer - PiDe/Polvmer Pine 4/14/OS Polvmer Modified Concrete Pioe Amrtech USA Meyer Polycrete Pioe ASTM C33, A276, F477 8" tp 1112", Class V I06/09/10 El-9 Reinforced Polymer Concrete Pipe US Composite Pipe Reinforced Polymer Concrete Pioe ASTM C-76 I I I /HDPE 33-31-23(1/8/13) * From Original Standard Products List CITY OF FORT WORTH FORT WORTH. WATER DEPARTMENT STANDARD PRODUCT LIST Updated: 03/07/2023 Note: All water or sewer pipe larder than 1S inch diameter shall be approved for use by the Water Department on a proiect specific basis. Special bedding maybe required for some I ' hdsity polyethylene pipe Phillips Driswpipe, Inc. Opticore Ductile Polyethylene Pipe ASTM D 1248 8" I * gh-density polyethylene pipe �'Ih�gh_d_maitv PI- Inc. ASTM D 1248 8" * gh-density polyethylene pipe Polly Pipe, Inc. ASTM D 1248 8" polyethylene pipe CSR Hydro CondmUPioelme Systems McConnell Pipe Enlargement ASTM D 1248 Sewer - PiDes/PVC (Pressure Sewer) 33-11-12 (4/1/13) 12/02/11 33-11-1� DR -Id PVC Pressure Pipe Prpelife Jetstream PVC PressurePipe AWWA C900 4"[tiro 12" 10/22/14 33-11-12 DR-14 PVC Pressure Pipe Royal Building Products Royal Seal PVC Pressure Pipe AW WA C900 4" thru 12" 33-31-20 PVC Sewer Poe 12/23/97* 33-31-20 PVC Sewer Pipe * 33-31-20 PVC Sewer Pipe 01/18/18 33-31-20 PVC Sewer Pipe 11/11/98 33-31-20 PVC Sewer Pipe * 33-31-20 PVC Sewer Pipe 09/11/12 33-31-20 PVC Sewer 05/06/05 33-31-20 , PVC Sohd Wall Pipe 04/27/06 33-31-20 PVC Sewer Fittings * 33-31-20 PVC Sewer Fittings 1 3/19/2018 33 3120 PVC Sewer Pipe 1 3/19/2018 33 3120 PVC Sewer Pre 1 3/29/2019 33 3120 Gasketed Fittings (PVC) 1 10/21/2020 33 3120 PVC Sewer Pipe 1 10/22/2020 33 3120 PVC Sewer Pipe 1 10/21/2020 33 3120 PVC Sewer Pipe P 33-31-12 1 * Cured in Place Pipe 05/03/99 Cured in Place Ape 05/29/96 Cured in Place Pipe Sewer - Pipes/Rehab/Fold & Form Fold and Form Pi 11/03/98 Fold and Form Pipe Fold and Form Pipe 12/04/00 Fold and Form Pipe 06/09/03 Fold and Form Pipe 1-M Manufacturing Co., Inc. (JM Eagle) Diamond Plastics Corporation Lamson Vylon Pipe Vinyltech PVC Pipe Diamond Plastics Corporation J-M Manufacturing Co, Inc. (JM Eagle) P,qq life Jet Stream Diamond Plastics Corporation Harco Plastic Trends, Inc.(Westlak ) Pipelife Jet Stream Pipelife Jet Stream GPK Products, Inc. NAPCO(Westlake) Sanderson Pipe Corp. NAPCO(Westlake) Insimfrrm Texark, Inc National Envirotech Group Remolds Inc/Inliner Technolgy (Inliner USA) Cullum Pipe Systems, Inc. Insimfirm Technologies, Inc. American Pipe & Plastics, Inc. Ultralmer Miller Pipeline Corp. Sewer - PiDes/ODen Prot -de Laree Diameter i 09/26/91 E100-2 PVC Sewer Pipe, Ribbed Lamson Vvlon Pipe 09/26/91 E100-2 PVC Sewer Pipe, Ribbed Extmsim Technologies, Inc. E100-2 PVC Sewer Pipe, Ribbed Up -or ETI Company 11/10/10 (E100-2) Polypropylene (PP) Sewer Pipe, Double Wall Advanced Drainage Systems (ADS) 11/10/10 (E100-2) Polypropylene (PP) Sewer Pipe, Triple Wall Advanced Drainage Systems (ADS) 05/16/11 Steel Reinforced Polyethylene Pipe ConTech Construction Products SDR-26 SDR-26 Gravity Sewer "S" Gravity Sewer Pipe SDR 26/35 PS 115/46 SDR-26 and SDR-35 SDR 26/35 PS 115/46 SDR-26 and SDR-35 Gasket Fittings Gasketed PVC Sewer Main Finings SDR 35 SDR 26 SDR 26 SDR 26 SDR 26 SDR 26/35 PS 115/46 National Liner, (SPL) Item #27 Inliner Technology Insim "NuPIpe" Ultralmer PVC Alloy Pipelmer EX Method Carlon Vylon H.C. Closed Profile Pipe, Ultra -Rib Open Profile Sewer Pipe SaniTite HP Double Wall (Corrugated) SamTne HP Triple Wall Pipe Durmaxx ASTM D 3034 ASTM D 3034 ASTM F 789 ASTM D3034 ASTM F 679 ASTM F 679 ASTM F-679 ASTM F-679 ASTM D-3034, D-1784, etc ASTM D 3034 ASTM F679 ASTM D3034 ASTM D3034/F-679 ASTM D3034 ASTM D3034 ASTM F-679 ASTM F 1216 ASTM F-1216/D-5813 ASTM F 1216 ASTM F-1504 ASTM F-1504, 1871, 1867 ASTM F-1504, F-1947 ASTM F 679 ASTM F 679 ASTM F 2736 ASTM F 2764 ASTM F 2562 4" - 15" 4" thru 15" 4" thru 15" 4" thru 15" 18" to 27" 18" - 28" 18" 18" to 48" 4" - 11" 18"- 24" 4"- 15" 4"- 15" 4" - 15" 4"- 15" 18"- 36" Demo. Purpose Only Up to 18" diameter 18" to 48" 18" to 48" 24"-30" 30" to 60" 24" to 72" * From Original Standard Products List CITY OF FORT WORTH FORT WORTH. WATER DEPARTMENT STANDARD PRODUCT LIST Updated: 03/07/2023 Note: All water or sewer pipe larger than 1S inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding maybe required for some pipes. Approval Spec I on 1W Manufacturer Model1. National Spec Water - Aoour�enancesgig -10 (07/Ol/13) Ol/18/18 33-12-10 Double Strap Saddle Romac 202NS Nylon Coated AWWA C800 1"-2"SVC, no 124"Pipe 08/28/02 Double Strap Saddle Smith Blair 4317 Nylon Coated Double Strap Saddle 07/23/12 33-12-10 Double StrapService Saddle Mueller Company U-S Double SS Strap DI Saddle AWWA C800 1"-2" SVC, u to 24" Pi e 03/07/23 33-12-10 Double StrapService Saddle Powerseal 3450AS, Inc. Corp. Stop, ON Strap, Stainless NSF ANSI 372 1"-2" SVC, u to 24 Pi e 10/27/87 Curb Stops -Ball Meter Valves McDonald 6100M,6100MT & 610MT 3/4" and 1" 10/27/87 Curb Stops -Ball Meter Valves McDonald 4603B, 4604B, 610UM, 6100TM and 6101M 1 h" and 2" FB600-7NL, FB1600-7-NL, FV23-777-W-NL, 1/25/2018 33-12-10 Curb Stops -Ball Meter Valves Ford Meter Box Co., Inc. L22-77NL AWWA C800 2" FB600-6-NL, FB1600-6-NL, FV23-666-W- 1111018 33-12-10 Curb Stops -Ball Meter Valves Ford Meter Box Co., Inc. NL, L22-66NL AWWA C800 1-1/2" FB600-4-NL, FB1600-4-NL, B11-444-WR- 1111018 33-12-1. Curb Stops -Ball Meter Valves Ford Meter Box Co., Inc. NL, B22444-WR-NL, L28-44NL AWWA C800 I " 13-25000N, B-24277N-3, B-20200N-3, H- AWWA C800, ANSF 61, 1/25/2018 33-12-10 Curb Stops -Ball Meter Valves Mueller Co., Ltd. 15000N, , H-1552N, H142276N ANSI/NSF 372 _ B-25000N, B-20200N-3, B-24277N-3,H- AWWA C800, ANSF 61, 1111.1. 33-12-1. Curb Stops -Ball Meter Valves Mueller Co., Ltd. 15000N, H-14276N, H-15525N ANSI/NSF 372 1-1/2" 5/25/2018 33-12-10 Curb Stops -Ball Meter Valves Mueller Co., Ltd. 15530N ANSI/NSF 372 V, 01/26/00 Coated Tapping Saddle with Double SS Straps 1CM Industries, Inc. #406 Double Band SS Saddle 1"-2" Taps on up to 12" 0/5/21/12 33-12-25 Tapping Sleeve (Coated Steel) 1CM Industries, Inc. 412 Tapping Sleeve ESS AWWA C-223 Up to 30" w/12" Out 03/29/22 33-12-25 Tapping Sleeve (Coated or Stainless Steel) 1CM Industries, Inc. 415 Tapping Sleeve AWWA C-223 Concrete Pipe Only 05/10/11 Tapping Sleeve (Stainless Steel) Powerseal 3490AS (Flange) & 3490MJ 4"-1" and 16" 02/29/12 33-12-25 Tapping Sleeve (Coated Steel) Romac FTS 420 AWWA C-223 U p to 42" w/24" Out 02/29/12 33-12-25 Tapping Sleeve (Stainless Steel) Romac SST Stainless Steel AWWA C-223 Up to 24" w/12" Out 02/29/12 33-12-25 Tapping Sleeve (Stainless Steel) Romac SST III Stainless Steel AWWA C-223 Up to 30" w/12" Out 05/10/11 Joint Repair Clamp Powerseal 3232 Bell Joint Repair Clamp 4" to 30" Plastic Meter Box w/Composite Lid DFW Plastics lnc. DFW37C-12-lEPAFFTW Plastic Meter Box w/Composite Lid DFW Plastics lnc. DFW39C-12-lEPAFFTW 08/30/06 Plastic Meter Box w/Composite Lid DFW Plastics Inc. DFW65C-14-lEPAF FTW Class "A" Concrete Meter Box Bass & Hays CMB37-B12 1118 LID-9 Concrete Meter Box Bass & Hays CMB-18-Dual 1416 LID-9 Concrete Meter Box Bass & Hays CMB65-B65 1527 LID-9 r Water - Combination Air Release 33-31-70 (01/08/13) 1 E I -I I Au Release Valve GA Industries, Inc. Empve Air and Vacuum Valve, Model 935 ASTM A 126 Class B, ASTM A 1" &W21' * EI-11 [oribriation ombmation Ar Release Valve Multiplex Manufacturing Co. Crispin Air and Vacuum Valves, Model No. 1/2", 1" & 2" EI-11 ombination Air Release Valve Valve and Primer Corp. APCO #143C, #145C and #147C 1", 2" & 3" Water Barrel Fire Hvdrants 10/Ol/87 E-1-12 Dry Barrel Fire Hydrant American -Darting Valve Drawing Nos. 90-18608, 94-18560 AWWA C-502 03/31/88 E-1-12 Dry Barrel Fire Hydrant American Darling Valve Shop Drawing No. 94-18791 AWWA C-502 09/30/87 E-1-12 Dry Barrel Fire Hydrant Clow Corporation Shop Drawing No. D-19895 AWWA C-502 01/12/93 E-1-12 Dry Barrel Fire Hydrant American AVK Company Model 2700 AWWA C-502 08/24/88 E-1-12 Dry Barrel Fire Hydrant Clow Corporation Drawings D20435, D20436, B20506 AWWA C-502 E-1-12 Dry Barrel Fire Hydrant ITT Kennedy Valve Shop Drawing No. D-80783FW AWWA C-502 0.1.7 E-1-12 Dry Barrel Fire Hydrant M&H Valve Company Shop Drawing No. 13476 AWWA C-502 Shop Drawings No. 6461 t0/14/87 E-1-12 Dry Barrel Fire Hydrant Mueller Company A-423 Centurion AW WA C-502 01/15/88 E1-12 Dry Barrel Fire Hydrant Mueller Company A-423 Super Centurion 200 AWWA C-502 10/09/87 E-1-12 Dry Barrel Fire Hydrant U.S. Pipe & Foundry Shop Drawing No. 960250 AWWA C-502 09/16/87 E-1-12 Dry Barrel Fire Hydrant American Flow Control (AFC) Waterous Pacer WB67 AWWA C-502 08/12/16 33-12-40 Dry Barrel Fire Hydrant EI (East Jordan Iron Works) WaterMaster 5CD250 I 02/05/93 E101-5 Detector Check Meter Ames Company Model 1000 Detector Check Valve AWWA C550 4" - 10" 08/05/04 Magnetic Drive Vertical Turbine Hersey Magnetic Drive Vertical AWWA C701, Class 1 3/4" - 6" * From Original Standard Products List CITY OF FORT WORTH FORT WORTH. WATER DEPARTMENT STANDARD PRODUCT LIST Updated: 03/07/2023 Note: All water or sewer pipe larger than 1S inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding maybe required for some pipes. Approval IModel INational Water -Pines/PVC(Pressure Waterl33-31-70(01/08/13) -W MEL M` —AL I 01/18/18 33-11-12 PVC Pressure Pipe Vinyltech PVC Pipe DR14 ASTM D1784 V-12" I I 3/19/2018 33 11 12 PVC Pressure Pipe Pipelife Jet Stream DR14 AWWA C900 4"-12" I I 3/19/2018 33 11 12 PVC Pressure Pipe Pipelife Jet Stream DR18 AWWA C900 16"-24" I I 5/25/2018 33 11 12 PVC Pressure Pipe Diamond Plastics Corporation DR 14 AWWA C900 4"-12" I 5/25/2018 3311 12 PVC Pressure Pipe Diamond Plastics Corporation DR 18 AWWA C900 16"-24" AWWA C900-16 UL 1285 12/6/2018 3311 12 PVC Pressure Pipe J-M Manufacnrring Co., Inc d/b/a JM Eagle DR 14 ANSI/NSF 61 4"-28" FM 1612 12/6/2018 33 11 12 PVC Pressure Pipe J-M Manufacturing Co., Inc d/b/a JM Eagle DR 18 ° 16"-24" 9/6/2019 33 11 12 PVC Pressure Pipe Underground Solutions Inc. DR14 Fusible PVC AWWA C900 4" - 8" 9/6/2019 33 11 12 PVC Pressure Pipe NAPCO(Westlake) DR18 AWWA C900 16"-24" 9/6/2019 33 11 12 PVC Pressure Pipe NAPCO(Westlake) DR14 AWWA C900 4"-12" 9/6/2019 33 11 12 PVC Pressure Pipe Sanderson Pipe Corp. DR14 AWWA C900 4"- 12" I Water - Pines/Valves & Fittin¢s/Ductile Iron Fittines 33--11 (01/08/13) I 07/23/92 EI-07 Ductile Iron Fittings Star Pipe Products, Inc. Mechanical Joint Finings AW WA C153 & C110 I EI-07 Ductile Iron Fittings Griffin Pipe Products, Co. Mechanical Joint Fittiq @ AWWA C 110 I * E1-07 Ductile Iron Fittings McWane/Tyler Pipe/ Union Utilmes Division Mechanical Joint Finings, SSB lass 350 AWWA C 153, C 110, C 111 I 08/11/98 E1-07 Ductile Iron Fittings Sigma, Co. Mechanical Joint Finings, SSB Class 351 AWWA C 153, C 110, C 112 I 02/26/14 E1-07 MJ Fittings Accucast Class 350 C-153 MJ Fittings AW WA C153 4"-12" I 05/14/98 E1-07 Ductile Iron Joint Restraints Ford Meter Box Co./Uni-Flange Uni-Flange Series 1400 AW WA C111/C153 4" to 36" I 05/14/98 E1-24 PVC Joint Restraints Ford Meter Box Co./Uni-Flange Uni-Flange Series 1500 Circle -Lock AW WA C111/C153 4" to 24" I 11/09/04 E1-07 Ductile Iron Joint Restraints One Bolt, Inc. One Bolt Restrained Joint Fitting AWWA C111/C116/C153 4" to 12" I I 02/29/12 33-11-11 Ductile Iron Pipe Mechanical Joint Restraint EBAA Iron, Inc. Megalug Series 1100 (for DI Pipe) AWWA C111/C116/C153 4" to 42" I I 02/29/12 33-11-11 PVC Pipe Mechanical Joint Restraint EBAA Iron, hic. Megalug Series 2000 (for PVC Pipe) AWWA C111/C116/C153 4" to 24" I I 08/05/04 E1-07 Mechanical Joint Retainer Glands(PVC) Sigma, Co. Sigma One-Lok SLC4 - SLC10 AW WA C111/C153 4" to 10" I I 03/06/19 33-11-11 Mechanical Joint Retainer GlandaFVC) Sigma, Co. Sigma One-Lok SLCS4 - SLCS12 AW WA C111/C153 4" to 12" I I 08/05/04 E1-07 Mechanical Joint Retainer Glands(PVC) Sigma, Co. Sigma One-Lok SLCE AW WA C111/C153 12" to 24" I I 08/10/98 E1-07 MJ Fiffir IP) Sigma, Co. Sigma One-Lok SLDE AW WA C153 4" - 24" I I 10/12/10 E1-24 Interim Restrained Joint Svatem S & B Techncial Products Bulldog System ( Diamond Lok 21 & JM ASTM F-1624 4" to 12" I I 08/16/06 E1-07 Mechanical Joint Fittings SIP Ind-nies(Serampore) Mechanical Joint Fittings AW WA C153 4" to 24" I I 11/07/16 33-11-11 Mechanical Joint Retainer Glands Star Pipe Products, Inc. PVC Stargrip Series 4000 ASTM A536 AW WA CI I I I I 11/07/16 33-11-11 Mechanical Joint Retainer Glands Star Pipe Products, Inc. DIP Stmgrip Series 3000 ASTM A536 AW WA CI I I I EZ Grip Joint Restraint (EZD) Black For DIP 03/19/18 33-11-I1 Mechanical Joint Retainer Glands SIP Industries(Seramnore) ASTM A536 AW WA CI I I 3"-48" EZ Grip Joint Restraint (EZD) Red for C900 03/19/18 33-11-11 Mechanical Joint Retainer Glands SIP Industries(Serampore) DRl4 PVC Ape ASTM A536 AW WA CI I I 4"-12" 03/19/18 33-11-11 Mechanical Joint Retainer Glands SIP Industries(Sersmpore) �` vuP, V11i. nn, oa„ �,.t.�`VJ nGLL �V1 �J°✓ ASTM A536 AW WA CI11 16"-24" I Water - Pioes/Valves & Fittings/Resilient Seated Gate Valve* 33-12-20 (05/13/15). I Resilient Wedged Gate Valve w/no Gears American Flow Control Series 2500 Drawing # 94-20247 16" I 12/13/02 Resilient Wedge Gate Valve American Flow Control Series 2530 and Series 2536 AWWA C515 30" and 36" I I 08/31/99 Resilient Wedge Gate Valve American Flow Control Series 2520 & 2524 (SD 94-20255) AW WA C515 20" and 24" I I 05/18/99 Resilient Wedge Gate Valve American Flow Control Series 2516 (SD 94-20247) AWWA C515 16" I I 10/24/00 E1-26 Resilient Wedge Gate Valve American Flow Control Series 2500 (Ductile Iron) AWWA C515 4" to 12" I I 08/05/04 Resilient Wedge Gate Valve American Flow Control 42" and 48" AFC 2500 AWWA C515 42" and 48" I I 05/23/91 E1-26 Resilient Wedge Gate Valve American AVK Company American AVK Resilient Seeded GV AWWA C509 4" to 12" I I01/24/02 E1-26 Resilient Wedge Gate Valve American AVK Company 20" and smaller I I * E1-26 Resilient Seated Gate Valve Kennedy 4" - 12" I I E1-26 Resilient Seated Gate Valve M&H 4" - 12" I I * E1-26 Resilient Seated Gate Valve Mueller Co. 4" - 12" I I 11/08/99 Resilient Wedge Gate Valve Mueller Co. Series A2361 (SD 6647) AWWA C515 16" I I 01/23/03 Resilient Wedge Gate Valve Mueller Co. Series A2360 for 18"-24" (SD 6709) AWWA C515 24" and smaller I 05/13/05 Resilient Wedge Gate Valve Mueller Co. Mueller 30" & 36", C-515 AW WA C515 30" and 36" I 01/31/06 Resilient Wedge Gate Valve Mueller Co. Mueller 42" & 48", C-515 AW WA C515 42" and 48" I 01/28/88 EI-26 Resilient Wedge Gate Valve Clow Valve Co. AWWA C509 4" - 12" I 10/04/94 Resilient Wedge Gate Valve Clow Valve Co. 16" RS GV (SD D-20995) AW WA C515 16" I 11/08/99 EI-26 Resilient Wedge Gate Valve Clow Valve Co. Clow RW Valve (SD D-21652) AW WA C515 24" and smaller I 11/29/04 Resilient Wedge Gate Valve Clow Valve Co. Clow 30" & 36" C-515 AWWA C515 30" and 36" (Note 3) 11/30/12 Resilient We Crate Valve Clow Valve Co. Clow Valve Model 2638 AW WA C515 24" to 48" (Nora 3) 05/08/91 E1-26 Resilient Seat Gate Valve Stockham Valves & Fittings AWWA C 509, ANSI 420 - stem, 4" - 12" I E1-26 Resilient Seated Gate Valve U.S. Pipe and Foundry Co. Mcoesw1250, regwremerts SPL #74 3" to 16" 11/26/16 33-12-20 Resilient Seated Gate Valve EJ (East Jordan Iron Works) EJ Fluo Master Gat. Valve & Boxes 08/24/18 I Mateo Gate Valve Matco-Norca 225 MR AWWA/ANSI C115/An21.15 4" to 16" I * From Original Standard Products List FORT WORTH® Note: All water or CITY OF FORT WORTH WATER DEPARTMENT STANDARD PRODUCT LIST than 1S inch diameter shall be approved for use by the Water basis. for some Updated: 03/07/2023 I * E1-30 Rubber Seated Butterfly Valve Henry Pratt Co. AW WA C-504 24" I * E1-30 Rubber Seated ButterFly Valve Mueller Co. AW WA C-504 24"and smaller 1/11/99 E1-30 Rubber Seated Butterfly Valve De ik Valves Co. AW WA C-504 24" and larger 06/12/03 E1-30 Valmatm American Butterfly Valve Valmanc Valve and Manufacturing Cert. Valmatic American Butterfly Valve. AW WA C-504 Up to 84" diameter 04/06/07 E1-30 Rubber Seated ButterFly Valve M&H Valve M&H Style 4500 & 1450 AW WA C-504 24" to 48" 03/19/18 33 12 21 Rubber Seated Butterfly Valve G. A. Industries (Golden Anderson) AW WA C504 Butterfly Valve AW WA C-504 30"-54" Water�ne Encasement 33-11-10 (01/08/13) 05/12/OS EI-13 Polyethylene Encasment Flessol Packaging Fulton Enterprises AW WA C105 8 mil LLD 05/12/05 EI-13 Polyethylene Encasment Mountain States Plastics (MSP) and AEP Ind. Standard Hardware AW WA C105 8 mil LLD 05/12/05 E1-13 Polyethylene Encasment AEP Industries Bullstrong by Cowtown Bolt & Gasket AW WA C105 8 mil LLD 09/06/19 33-11-11 Polyethylene Encasment Northtown Products Inc. PE Encasement for DIP AW WA C105 8 mil LLD Water - Samnlint= Station 03/07/23 33 12 50 Water Sam lin Station I Eclipse Number 88 , 12-inch Depth of Bur As shown in spec. 33 12 50 00,1,-k Water - Automatic Flusher Automated Flushing System Mueller Hydrogaud HG2-A-IN-2-PVC-018-LPLG(Permanent) 04/09/21 Automated Flushing System Kupf le Foundry Company Eclipse #9800wc 04/09/21 Automated Flushing System Kupf le Foundry Company Eclipse 99700 (Portable) * From Original Standard Products List