HomeMy WebLinkAboutOrdinance 26746-02-2024Ordinance No. 26746-02-2024
AN ORDINANCE ADJUSTING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER & SEWER CAPITAL PROJECT 2019 FUND,
BY INCREASING ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE
VILLAGE CREEK WATER RECLAMATION FACILITY BIOSOLIDS
MANAGEMENT AND REUSE PROJECT (CITY PROJECT NO. 101961) IN THE
AMOUNT OF $158,992.00 AND DECREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE UNSPECIFIED -ALL FUNDS PROJECT (CITY
PROJECT NO. UNSPEC) BY THE SAME AMOUNT; PROVIDING FOR A
SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF
PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT
HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2023-2024 in the
Budget of the City Manager, there shall also be adjusted estimated receipts and appropriations in the Water &
Sewer Capital Project 2019 Fund, by increasing estimated receipts and appropriations in the Village Creek
Water Reclamation Facility Biosolids Management and Reuse project (City Project No. 101961) in the
amount of $158,992.00 and decreasing estimated receipts and appropriations in the Unspecified -All Funds
project (City Project No. UNSPEC) by the same amount.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 26453-09-2023 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Douglas Black (Mar 5, 202416:44 CST)
Douglas W. Black
Senior Assistant City Attorney
ADOPTED AND EFFECTIVE: February 27, 2024
CITY SECRETARY
Jannette S. Goodall
City Secretary
44pb�1'3��
RT
kOD°oWQ
ACV 4j►0G
C 0° °oop a
° ° �F
0.0 °
T ��dunEx`
"N
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 02/27/24 M&C FILE NUMBER: M&C 24-0178
LOG NAME: 60VCWRF MASTER PLAN UPDATE AMEND 6
SUBJECT
(CD 5) Authorize Execution of Amendment No. 6 to an Engineering Agreement with CH2M Hill Engineers, Inc., in the Amount of $158,992.00 for
Village Creek Biosolids Management and Beneficial Reuse Facility Project and Adopt Appropriation Ordinance to Effect a Portion of Water's
Contribution to Fiscal Years 2024-2028 Capital Improvement Program
RECOMMENDATION:
1t is recommended that the City:
1. Authorize execution of Amendment No. 6 to City Secretary Contract No. 50018, an Engineering Agreement with CH2M Hill Engineers, Inc. in
the amount of $158,992.00, for a revised contract amount of $1,408,335.00, for the Village Creek Biosolids Management and Beneficial
Reuse Facility project (City Project No. 101961); and
2. Adopt the attached appropriation ordinance adjusting estimated receipts and appropriations in Water & Sewer Capital Project 2019 Fund
by increasing estimated receipts and appropriations in the Village Creek Water Reclamation Facility Biosolids Management and Reuse
project (City Project No. 101961) in the amount of $158,992.00 and decreasing estimated receipts and appropriations in the Unspecified -All
Funds project (City Project No. UNSPEC) by the same amount for the purpose of funding Village Creek Water Reclamation Facility
Biosolids Management and Reuse project (City Project No. 101961) and effect a portion of Water's contribution to the Fiscal Years 2024-
2028 Capital Improvement Program.
DISCUSSION:
On November 14, 2017, Mayor and Council Communication (M&C) C-28475, the City Council authorized an Engineering Agreement in the
amount of $282,822.00 with CH2M Hill Engineers, Inc., for the Village Creek Biosolids Management and Beneficial Reuse Facility project. The
agreement was subsequently revised by Amendment No. 1, in the amount of $77,296.00, administratively authorized September 4, 2018, that
provided for additional wastewater solids process modeling work, long-term growth projections and additional alternatives analysis, as well as the
preparation of an engineering feasibility report submitted to the Texas Water Development Board (TWDB) as part of a Clean Water State
Revolving Fund (CWSRF) Loan application. Amendment No. 2, in the amount of $245,461.00, authorized February 12, 2019 (M&C C-29039) that
provided for the development of a the Request for Qualifications (RFQ) and Request for Proposals (RFP) as part of the procurement process for a
design -build -operate contract for biosolids management project and responding to requests for information (RFls) during the procurement
process, for providing technical analysis and recommendations during the evaluation of vendor submittals and during the negotiation of the
agreement. Amendment No. 3, authorized June 23, 2020 (M&C 20-0463) in the amount of $539,620.00 that provided for inspection, testing, and
construction administration for the biosolids dryer facility, Amendment No. 4, in the amount of $50,000.00, administratively authorized October 12,
2023, provided for claims review and technical assistance and Amendment No. 5, authorized January 23, 2024 (M&C 24-0071) in the amount of
$54,144.00 provided for the sampling and testing of materials from the sludge ponds at the Village Creek Biosolids and Beneficial Reuse Facility.
Amendment No. 6 provides for an operations and maintenance evaluation of the City's sludge centrifuge/dewatedng facility and the City's beltAlme
facility to identify potential performance improvements at the facility.
It is the practice of the Water Department to appropriate its C1P plan throughout the Fiscal Year, instead of within the annual budget ordinance, as
projects commence, additional funding needs are identified, and to comply with bond covenants. The actions in the M&C will appropriate funds in
support of the Water's portion of the City of Fort Worth's Fiscal Years 2024-2028 Capital Improvement Program, as follows:
-60VCWRF MASTER PLAN UPDATE AMEND 6
Capital
Fund
Name
Project
Name
FY2024 CIP
Appropriations
Authority
Budget Change
(IncreaselDecrease)
Revised
FY2024
Budget
WS
Capital
101961-
Project
VCWRF
2019—
Biosolids
$54,144.00
This M&C
$158,992.00
$213,136.00
Fund
Mgmt &
56016
Reuse
Funding for the Village Creek Water Reclamation Facility Biosolids Management & Reuse project is depicted below:
Fund Existing Additional
lApproprlatlons Appropriations Project Total"
W&S Capital
Projects Fund
$1,112,098.25
$0.00
$1,112,098.25
56002
WS Capital
Project 2019 Fund
$299,605.00
$158,992.00
$458,597.00
56016
WS Capital
Project 2020 Fund
$60,000,000.00
$0.00
$60,000,000.00
56018
W&S Bond'2020A
Fund 56017
$715,000.00
$0.00
$715,000.0Q
Project Total
$62,126,703,25
$158,992.00
$62,285,695.25
*Numbers rounded for presentation purposes.
Funding is available for appropriations in the Unspecified -All Funds project within the WS Capital Project 2019 Fund forthe purpose of funding
the Village Creek Water Reclamation Facility Biosolids Management & Reuse project.
Business Equity: A waiver of the goal for Business Equity subcontracting requirements was requested, and approved by the DVIN, in accordance
with the applicable Ordinance, because the purchase of goods or services is from sources where subcontracting or supplier opportunities are
negligible.
This project serves the entire City and is located in COUNCIL DISTRICT 5.
A Form 1295 is not required because: This contract will be with a publicly -traded business entity or a wholly -owned subsidiary of a publicly -traded
business entity: CH2M Hill Engineers,inc.
FISCAL INFORMATION 1 CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Unspecified -All Funds project within the WS Capital Project 2019 Fund
and upon approval of the above recommendations and adoption of the attached appropriation ordinance, funds will be available in the WS Capital
Project 2019 Fund for the VCWRF Biosolids Mgmt & Reuse project to support the above recommendations and execution of the amendment.
Prior to any expenditure being incurred, the Water Department has the responsibility to validate the availability of funds.
Submitted for City Manager's Office--W. Fernando Costa 6122
Originating Business Unit Head: Chris Harder 5020
Additional Information Contact: David Townsend 8430
Expedited