HomeMy WebLinkAboutOrdinance 26870-04-2024Ordinance No. 26870-04-2024
AN ORDINANCE ADJUSTING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER & SEWER CAPITAL PROJECT 2019 FUND,
BY INCREASING ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE
BENBROOK WATER AUTHORITY WATER CONNECTION PROJECT (CITY
PROJECT NO. 105248) IN THE AMOUNT OF S1,230,506.00 AND DECREASING
ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE UNSPECIFIED -ALL
FUNDS PROJECT (CITY PROJECT NO. UNSPEC) BY THE SAME AMOUNT;
PROVIDING FOR A SEVERABILITY CLAUSE; MAKING THIS ORDINANCE
CUMULATIVE OF PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN
CONFLICT HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2023-2024 in the
Budget of the City Manager, there shall also be adjusted estimated receipts and appropriations in the Water &
Sewer Capital Project 2019 Fund, by increasing estimated receipts and appropriations in the Benbrook Water
Authority Water Connection project (City Project No. 105248) in the amount of $1,230,506.00 and decreasing
estimated receipts and appropriations in the Unspecified -All Funds project (City Project No. UNSPEC) by
the same amount.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion orj udgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 26453-09-2023 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Douglas Blaca (May 1, 2024 17:33 75
Assistant City Attorney
ADOPTED AND EFFECTIVE: April 23, 2024
CITY SECRETARY
Jannette S. Goodall
City Secretary o��ata�aA�n
F�O* �?Hna 0����
a
° ox
o
Q� W 0 0 o
°o o� d
:E�
c
00
DD
�z
o
m0
Mc
0z
O n
z�
M0
C) O
--49
�ig
r C
rZ
00
O�
c_
O
z
I
MAYOR AND COUNCIL COMMUNICATION
60BWAWATERCON NECT-WI LLCOU
17
J�Q.a' • t -- r k r
a v� , Dal
�O. n
N
i
1 r.
EMERGENCY WATER
w! CONNECTION LOCATION
FORT WORTH®
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 04/23/24 M&C FILE NUMBER: M&C 24-0358
LOG NAME: 6013WA WATERCONNECT - WILLCOU
SUBJECT
(CD 3) Authorize Execution of a Contract with Willco Underground, LLC, in the Amount of $1,054,059.00, for the Benbrook Water Authority Water
Connection Project, and Adopt Appropriation Ordinance to Effect a Portion of Water's Contribution to the Fiscal Years 2024-2028 Capital
Improvement Program
RECOMMENDATION:
1. Authorize execution of a contract with Willco Underground, LLC, in the amount of $1,054,059.00, for the Benbrook Water Authority Water
Connection Project; and
2. Adopt the attached appropriation ordinance adjusting appropriations in the Water & Sewer Capital Project 2019 Fund by increasing
appropriations in the Benbrook Water Authority Water Connection project (City Project No. 105248) in the amount of $1,230,506.00 and
decreasing appropriations is the Unspecified-AII Funds project (City Project No. UNSPEC) by the same amount.
DISCUSSION:
This project provides for an emergency water connection between the Benbrook Water Authority and the City of Fort Worth Water Department to
allow each utility to take water from the other should the need ever arise.
The project was advertised for bids on February 1, 2024, and February 8, 2024, in the Fort Worth Star -Telegram. On February 29, 2024, the
following bids were received:
Bidder
Amount
Time of Completion
Willco Underground, LLC
$1,054, 359.00
150 Calendar Days
Blue Star Utilities, LLC
$1,301,322.00
In addition to the contract amount, $123,744.00 is required for project management, material testing and inspection, and $52,703.00 is provided
for project contingencies.
This project will have no impact on the Water Department's operating budget when completed.
It is the practice of the Water Department to appropriate its CIP Plan throughout the Fiscal Year (FY), instead of within the annual budget ordinance,
as projects commence, additional funding needs are identified, and to comply with bond covenants. The actions in the Mayor & Council
Communciation (M&C) will appropriate funds in support of the Waters portion of the City of Fort Worth's Fiscal Years 2024-2028 Capital
Improvement Program, as follows:
6013WA WATERCONNECT - WILLCOU
Capital
Project
FY2024 CIP
Budget
Revised
Fund
Name
q
Appropriations
Authority
Adjustment
FY2024
Name
Budget
WS
105248 —
Capital
Benbrook
Project
WWR
$0.00.This
M&C
$1,230,506.00
$1,230,506.00
2019—
Auth
nd
WfR
016
F
Connect
Funding is currently available in the Unspecified All -Funds project within the WS Capital Project 2019 Fund for the purpose of funding the
Benbrook Water Authority Connection project.
Appropriations for the Benbrook Water Authority Water Connection project are as depicted below:
Existing Additional
Fund Appropriations Appropriations Project Total*
WS Capital Project
2019 Fund 56016
$0 00
$1,230,506.00,1$1,230,506.00
Project Total
1 $0.00
$1,230,506.00
$1,230,506.001
"Numbers rounded for presentation purposes.
Business Equity: Willco Underground, LLC, is in compliance with the City's Business Equity Ordinance by committing to 15 percent MWBE
participation on this project. The City's MWBE goal on this project is 12 percent.
The project is located in COUNCIL DISTRICT 3.
The Directorof Finance certifies that funds are currently available in the Unspecified All -Funds project within the WS Capital Project 2019 Fund,
and upon approval of the above recommendations and adoption of the attached appropriation ordinance, funds will be available in the WS Capital
Project 2019 Fund for the Benbrook WTR Auth WTR Connect project to support the above recommendations and execution of the contract. Prior
to any expenditure being incurred, the Water Department has the responsibility of verifying the availability of funds.
Submitted for City Managers
Office bye
Femando Costa
6122
Originating Business Unit
Head:
Chris Harder
5020
Additional Information contara: Russell Redder 4970