HomeMy WebLinkAboutContract 60033-CO1CSC No. 60033-CO1
Fon-r Wowna
City of Fort Worth
Change Order Request
Emergency Response - 30-Inch
Water Main Break at the Lancaster Avenue/ Collier Street
City Sec No.: 60033
Project Name:I Intersection
Project No.(s)] 560021060043011780
DOE No. I N/A
I City Proj, No,:1 105063
Project 30-Inch Water Main Break at the Lancaster Avenue/ Collier Street
Intersection I
Description:
Contractord William J, Schultz, Inc, dba Circle C Construction Co. Change Order #
1 Date: 5/15/2024
City Project Mgr. Tony Sholola
I City Inspector:
John Robinson I
Phone Number: 817-392-6055
I Phone Number:
817-392-8452
Dept.
Water
Totals Contract Time
(Calender days)
Original Contract Amount
$800,000.00
$800,000,00
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
$800,000.00
$800,000.00
Amount of Proposed Change Order
38,500.00
31500.00
Revised Contract Amount
$138,500,00
$M500.00
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT I
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%) i
JUSTIFICATION (REASONS) FOR CHANGE ORDER
This Change Order No. 1 is authorized by the attached M&C approved on May 14, 2024 which
authorized additional funding to City Secretary Contract No. 60033 with William J. Schultz, Inc. dba
Circle C Construction Co. for emergency services to replace the 30-inch water main at the Lancaster
Avenue/Collier Street intersection.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents
payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order,
Contractor.'s Company Name
Contractor Name
Contractor Signature
Date
Wiliam I Schultz, Inc. dba Circle c Construction co.
Teri Skelly
Inspector /�
Da
Project Manager
Date
15/17/2024
00��
5 .lpij
Tony Sholola
plrector (Z)r iptj
I a
Conpiructl n SupervJpof Yff�ter Dept)
Date
Christopher NarcJer
May 20, 2024%��
��
Senior Assistant City Attomey
Dale
'Assistant CityiManager
Date
> )-;1 1 .
May 22, 2024
May 22, 2024
Council Aotion'(lf Required)
M&C Number 24-0419 (FUNDING) M&C Date Approved 1 5/14/2024 1
- -- - - -- - OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
F---'.?RT WOORTIH City of Fort Worth
Change Order Additions
Project Name Emergency Response- 30-Inch Water Main Break at the Lancaster Avenue/ Collier Street Intersection City Sec No.: 60033
Project No.(s): 5600210600430/1780 DOE No,j N/A I City Proj. No.: 105063
Project ( 30-Inch Water Main Break at the Lancaster Avenue/ Collier Street Intersection
Description
Contractor William J. Schultz, Inc, dba Circle C Construction Co. j Change Order: r Date: 1 5/15/2024
City Project Mgr. I Tony Sholola City Inspector I John Robinson
ADDITIONS
ITEM UESCHIP ION
2 Additional Work Scope
DEPT Qty Unit Unit Cost j Total
Water 1.00 LS $X500.00 $38,500.00
Water $38,500.00
Page 2 of 4 Additions Sub Total $38,500.00
FOPur WORTH City of Fort Worth
Change Order Deletions
Project Name Emergency Response-304nch Water Main Break at the Lancaster Avenue/ Collier Street Intersection City Sec No,: I 60033
Project No,(s): N/A I DOE No, I N/A City Proj. No.: N/A
Project Description I 30-Inch Water Main Break at the Lancaster Avenue/ Collier Street Intersection
Contractor I William J. Schultz, Inc. dba Circle C Const uction Co. I Change Order: Date I 5/16/2024
City Project Mgr, Tony Sholola City Inspector: I John Robinson
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
Water
Page 3 of 4 Deletions Sub Total
MWWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
Co# DATE AMOUNT
Total $0.00
Page 4 of 4
City of Fort Worth, Texas
Mayor and Council Communication
DATE: Tuesday, May 14, 2024 REFERENCE NO.: **M&C 24-0419
LOG NAME: 60EMER 30-IN COLLIER WMREPAIR-CIRCLECFUNDING
SUBJECT:
(CD 9) Adopt Appropriation Ordinance in the Amount of $38,500.00 for 30-Inch Water Main at the
Lancaster Avenue/Collier Street Intersection Emergency Repair to Effect a Portion of Water's Contribution
to the Fiscal Years 2024-2028 Capital Improvement Program
RECOMMENDATION:
It is recommended that the City Council adopt the attached appropriation ordinance increasing estimated
receipts and appropriations in the Water and Sewer Capital Projects Fund in the amount of $38,500.00,
transferred from available PayGo funds within the Water and Sewer Fund, for the purpose of funding the
additional costs associated with the emergency repair and replacement of the 30- inch water main at the
Lancaster Avenue/Collier Street Intersection project (City Project No. 105063) and effect a portion of
Water's contribution to the Fiscal Years 2024-2028 Capital Improvement Program.
DISCUSSION:
On September 26, 2023, (Mayor and Council Communication) (M&C) 23-0827, the City Council
authorized appropriations in the amount of $1,060,000.00 for emergency repair and replacement of the
30-inch water main at the Lancaster Avenue/Collier Street intersection.
On Thursday, August 17, 2023, a water main break erupted at the Lancaster Avenue/Collier Street
intersection. The break is exacerbated by its proximity to the Holly Water Treatment Plant with water being
pushed at over 100 Pounds per Square Inch (PSI) leading to flooding in the Lancaster/Henderson
intersection and also onto private property near the intersection. The water main is a shallow 1930s-era
30-inch cast-iron pipe which had deteriorated. The break was repaired the same day by William J. Schultz,
Inc. dba Circle C Construction Company (Circle C). On Monday, August 22, 2023, the same water main
broke apart again very near the vicinity of the earlier break. Water Field Operations immediately mobilized
to isolate the break and the City utilized the services of Circle C again to conduct the repairs.
With the original pipe having broken twice, via an emergency authorization memorandum of August 24,
2023 and pursuant to the emergency authority found in City Code Chapter 2, Article I, Section 2-9 of the
City's Code of Ordinances, the Water Department initiated emergency procurement of the following
contractors and consultant for the services and costs as indicated below to perform emergency
replacement of an approximately 460-foot segment of the water main and an additional approximately
220-feet of appurtenant 6-inch pipe as shown on the attached Mayor and Council Location map.
• William J. Schultz, Inc. dba Circle C Construction Company (Emergency water main
repair/replacement: $800,000.00) (City Secretary Contract No. 60033)
• Texas Materials Group, Inc. dba Texas Bit (Pavement Repair: $200,000.00) (City Secretary Contract
No. 60011)
• Freese and Nichols, Inc. (Engineering Design $60,000.00) (City Secretary Contract No. 59999)
The total of the contracts was estimated to be $1,060,000.00. Due to actual field conditions that were
encountered during construction, additional quantities of pavement repair will increase Circle C's
construction costs by $38,500.00 for an estimated revised contract amount of $838,500.00.
The purpose of this M&C is to secure funding for a change order to compensate Circle C, for the
additional expense incurred on the project.
It is the practice of the Water Department to appropriate its CIP plan throughout the Fiscal Year (FY),
instead of within the annual budget ordinance, as projects commence, additional funding needs are
identified, and to comply with bond covenants. The actions in the M&C will appropriate funds in support of
the Water's portion of the City of Fort Worth's Fiscal Years 2024-2028 Capital Improvement Program, as
follows:
60EMER 30-IN COLLIER WMREPAIR — CIRCLECFUNDING
Capital
Fund
project
FY2024 CIP Budget Change Revised
Authority FY2024
Name
Name
Appropriations (Increase/Decrease)
Budget
W&S
105063 -
Capital
Emrgncy
Projects
30" WM
$0.00 This M&C $38,500.00 $38,500.00
-- Fund
Rep.
56002
Collier St
Funding is currently available in the Transfer to Water/Sewer account of the Water and Sewer operating
budget for the purpose of funding the Emer 30-in WM Repair at Collier St.
FY2024 — Water PAYGO Appropriations per City Ordinance 26453-09-2023
FY2024
Amended
FY2024
Paygo
Original
(includes any
Adopted
council actions
PayGo
subsequentto
budget
adoption)
YTD PayGo
Approved This M&C
for/Moved to
Capital Projects
FY2024
Remaining
PayGo
Balance
$84,505,035.00 $84,505,035.00 $(72,066,940.36) $(38,500.00) $12,399,594.64
Note: there may be other pending actions or recently approved actions that are not reflected in the table
due to timing.
Appropriations for 30-inch Water Main Repair at the Lancaster Avenue/Collier Street Intersection project,
are as depicted below:
Fund Existing
I Appropriations
W&S Capital
Projects - $1,060,000.00
Fund 56002
Project Total 1 $1,060,000.001
Additional project Total*
Appropriations
*Numbers rounded for presentation purposes.
The project is located in Council District 9.
FISCAL INFORMATION / CERTIFICATION:
$38,500.00 $1,098,500.00
$38,500.0011$1,098,500.001
The Director of Finance certifies that funds are currently available in the Water & Sewer Fund, and upon
approval of the above recommendation and adoption of the attached appropriation ordinance, funds will
be available in the W&S Capital Projects Fund for the Emrgncy 30" WM Rep. Collier St. project to support
the approval of the above recommendation. Prior to any expenditure being incurred, the Water
Department has the responsibility of verifying the availability of funds.
FUND IDENTIFIERS (FIDs):
TO
Fund Department�Accountj Project ctivity Budget Reference # mount
fID ID JProgram
Year I (Chartfield 2)
FROM
Fund Department ccount Project Program ctivity Budget Reference # mount
ID I ID I I Year I (Chartfield 2)
CERTIFICATIONS:
Submitted for City Manager's Office by_ Fernando Costa (6122)
Origi sting Department Head: Chris Harder (5020)
Additional Information Contact: Tony Sholola (6054)
ATTACHMENTS
1. 60EMER 30-IN COLLIER WMREPAIR - CIRCLECFUNDING Map pdf (Public)
2. 6QEMER 30-IN COLLIER WMREPAIR — CIRCLECFUNDING FID Tab ( IWCCF 04.10.24)Atsx (CFW
Internal)
3. 60EMER 30-IN COLLIER WMRUAIR-CIRCLECFUNDING.docx (CFW Internal)
4. ORD.APP 60EMER 30-IN COLLIER WMREPAIR-CIRCLECFUNDING 56002 A024(r1)_(J).docx
(Public)
5. PBS CPN 105063.pd (CFW Internal)
6. SAM.gov Circle C.pdf (CFW Internal)
60EMER 30-IN COLLIER WMREPAIR-CIRCLECFUNDING FID Table
56002
56002
56001
56002
0600430 4956001 105063 2024
0600430 105063 2024
____ _ FIDs�REVENUE or EXPEN:
of # Amount PrniPrt I❑,Activity Budeet
$38,500.00
$38,500.00
$38,500.00
-$38,S00.00
56002 I 0600430 15740010 i 105063 I 001780 i 9999 I I $38,500.00
.Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
TVA�
Signature
Tony Sholola
Name of Employee
Assistant Water Director
Title
P of FORr�°o
p~o o-+d
ATTEST:
d��4
nEXP`oop
lannette Goodall
City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX