HomeMy WebLinkAboutOrdinance 26904-05-2024Ordinance No. 26904-05-2024
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER AND SEWER CAPITAL PROJECTS FUND
IN THE AMOUNT OF $1,443,540.00, TRANSFERRED FROM AVAILABLE
PAYGO RESIDUALS WITHIN THE WATER AND SEWER CAPITAL PROJECTS
FUND, FOR THE PURPOSE OF FUNDING THE SANITARY SEWER
REHABILITATION CONTRACT 91 (CITY PROJECT NO. C01957); PROVIDING
FOR A SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE
OF PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT
HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That the budget of the City of Fort Worth for Fiscal Year 2023-2024, as enacted by Ordinance 26453-09-
2023, as amended, is hereby further amended to make the following adjustments by increasing estimated
receipts and appropriations in the Water and Sewer Capital Projects Fund in the amount of $1,443,540.00,
from available PayGo residuals within the Water and Sewer Capital Projects Fund, for the purpose of funding
the Sanitary Sewer Rehabilitation Contract 91 (City Project No. C01957).
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 26453-09-2023 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinariFe shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
D—glas Slack (May 28, 2024 10:09 COY)
Assistant City Attorney
ADOPTED AND EFFECTIVE: May 14, 2024
CITY SECRETARY
A,.,? C'6'
Jannette S. Goodall
�4N� Secretary
4 Q9000000
000° p000 � o o0%t
Wa
C) p 1• v
Y� rWO00000 T'
�� II cy
L` 4lZ :1�'a0
MAYOR AND COUNCIL COMMUNICATION MAP
20WESTCPIANDSS91 P2-CIRCLEC
MAIL
r . w,
a t FOLK DR
SUFFOLK DR
r.RLY Per
'2 x *'' '
<tN p c cy
�► 1N SEMINARY; pR:e ,y,� O`��
�-WIN IN
:.i -. . fzoi
."","`E":f., ,.►yet' a: ..
.•" �, � �� a, =W.SEMINARYtDR y.,..:'
"1
i � �. .. � (1 L . +,A .a - �, � Vie: �✓.,
City of Fort Worth,
Mayor and
DATE: 05/14/24
Texas
Council Communication
MSC FILE NUMBER: M&C 24-0393
LOG NAME: 20SWM WESTCLIFF PH 1 AND CONTRACT 91 PT 2 CHANGE ORDER 2
SUBJECT
(CD 3 and CD 9) Authorize Execution of Change Order No. 2, with a Net Total Amount of $1,657,740.00 after Deducts and the Addition of 190
Calendar Days, to the Contract with William J. Schultz, Inc. dba Circle C Construction Company for the Construction of Westcliff Drainage
Improvements, Phase 1, and Sanitary Sewer Rehabilitation Contract 91, Part 2 and Adopt Appropriation Ordinance to Effect a Portion of Waters
Contribution to the Fiscal Years 2024-2028 Capital Improvements Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize the execution of Change Order No. 2 in the amount of $1,657,740.00 and the addition of 190 calendar days to City Secretary
Contract No. 57280 a contract with William J. Schultz, Inc, dba Circle C Construction Company, for the Westcliff Drainage Improvements,
Phase 1, and Sanitary Sewer Rehabilitation Contract 91 Project, Part 2, for a revised contract amount of $16,380,492.60; and
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water and Sewer Capital Projects Fund
in the amount of $1,443,540.00, from available PayGo residuals within the Water and Sewer Capital Projects Fund, for the purpose of
funding the Sanitary Sewer Rehabilitation Contract 91 project (City Project No. C01957) Part 2 and to effect a portion of Waters Contribution
to the Fiscal Years 2024-2028 Capital Improvement Program.
DISCUSSION:
On February 22, 2022, by Mayor and Council Communication (M&C) 22-0120, the City Council authorized a contract with William J. Schultz, Inc.
dba Circle C Construction Company in the amount of $14,663,252.60 for the construction of Westcliff Drainage Improvements, Phase 1, and
Sanitary Sewer Rehabilitation Contract 91, Part 2. The contract was subsequently revised by Change Order No. 1 in the net amount of $59,500.00
administratively authorized January 19, 2023, that primarily provided pay item quantity for temporary pavement repair, additional traffic control on
the project and additional street cleaning. This is a combined project between the Water Department and the Transportation and Public Works
(TPW) Department Stormwater Division (Stormwater).
Change Order No. 2 will provide for three main changes to the scoped project. The first change includes the construction of new water pipes on
Trail Lake Drive, Wyndale Court, and Sierra Court, as requested by the Water Department as part of its cast iron replacement initiative. The
change order also provides for mill and overlay paving for all streets impacted by water and sewer pipe construction in lieu of permanent pavement
repair. The second change is that the Stormwater scope will add a retaining wall at the downstream pipe outfall into the channel to prevent
stormwater facilities from encroaching onto adjacent properties. This change was identified after additional surrey was performed during the
construction phase which better defined right-of-way constraints due to slope stability issues. Lastly, the change order includes adjustments for
quantity overruns such as concrete paving repair, gate valves, and block sod placement. These are due to changes brought on by existing field
conditions that were encountered during construction. TPWs share of the change order is $214,200.00, while the Water Department's share is
$1,443,540.00 (Water: $1,006,192.00; Sewer: $437,348.00).
The sanitary sewer component of this change order is part of the Water Department's Sanitary Sewer Overflow Initiative Program. Approximately
1,107 linear feet of cast iron water pipe will be removed and replaced as part of this change order.
Staff recommends that the contract time be extended by 190 calendar days due to the changes in scope discussed above and for the time the
contractor expended assisting the Water Department with emergency water line repairs due to the February 2023 winterweather event which
impacted their work schedule on the Westcliff Project.
Contract item additions have been evaluated by City staff as necessary, and the unit prices were determined to be fair and reasonable when
compared to City standard prices and recently bid projects.
The following table summarizes previous contract action and change orders:
Construction Contract
Date
Scope
Amount
Original Contract (M&C
22-0120)
2/22/2022
$14,663,252.60
Change Order No. 1
11119/2023
Bid item changes such as type of water pipe installed and new bid items, such as
temporary paving and trash pick up.
$59,500.00
Change Order No. 2
Pending
[Additional water pipe, mill and overlay paving, retaining wall, and quantity adjustments.
$1,657,740.00
Revised Contract
$16,380,492.60
Amount
It is the practice of the Water Department to appropriate its CIP plan throughout the Fiscal Year (FY), instead of within the annual budget ordinance,
as projects commence, additional funding needs are identified, and to comply with bond covenants. The actions in the M&C will appropriate funds
in support of the Water's portion of the City of Fort Worth's Fiscal Years 2024-2028 Capital Improvement Program, as follows:
Sanitary Sewer Rehabilitation Contract 91 project:
Capital
Project
FY2024 CIP
Budget Change
Revised
Fund
Name
Appropriations
Authority
(increase/Decrease)
FY2024
Name
Budget
W&S
C01957
Capital
— SS
Projects—
Rehab
$11,064,561.00
This M&C
$1,443,540.00
$12,508,101.00
Fund
Contract
56002
91
Appropriations for Sanitary Sewer Rehab Contract 91 project:
Fund
Existing Appropriations
Additional Appropriations
Project Total
30100 General Capital Projects (C01957)
$1,050,034.00
$0.00
$1,050,034.00
56002 Water & Sewer Capital Projects Fund (C01957)
$11,064,561.00
$1,443,540.00
$12,508,101.00
59601 W&S Capital Projects
$4,000.00
$0.00
$4,000.00
59607 Sewer Capital Legacy
$498,439.00
$0.00
$498,439.00
Fr7jectTotal
$12,617,034.00
$1,443,540.00
$14,060,574.00
Funding is available for appropriation from available funds within the W&S Capital Projects Fund for the purpose of funding the SS REHAB
CONTRACT 91 project and funding is available within the Stormwater Capital Projects Fund for the Westcliff Drainage project.
This project is located in COUNCIL DISTRICTS 3 AND 9.
DVIN: A waiver of the goal for Business Equity subcontracting requirements was requested, and approved by the DVIN, in accordance with the
applicable Ordinance, because the purchase of goods or services is from sources where subcontracting or supplier opportunities are negligible;
FISCAL INFORMATION 1 CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Unspecified -All Funds project within the W&S Capital Projects Fund, and
upon approval of the above recommendations and adoption of the appropriation ordinance, funds will be available in the W&5 Capital Projects
Fund for the SS REHAB CONTRACT 91 project. Prior to any expenditure being incurred, the Transportation & Public Works and Water
Departments have the responsibility of verifying the availability of funds.
Submitted for Cily Manager's Office b : Jesica McEachem 5804
Originating Business Unit Head: Lauren Prieur 6035
Additional Information Contact: Linda Young 2485