HomeMy WebLinkAboutIR 9206 INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 9206
To the Mayor and Members of the City Council March 2, 2010
ex Page 1 of 3
SUBJECT: MARY'S CREEK WATER RECYCLING CENTER SITE SELECTION
1870
Purpose
The purpose of this informal report is to summarize the February 9, 2010, staff presentation to the
Infrastructure and Transportation Committee concerning the progress of site selection for the proposed
west side water recycling center/wastewater treatment plant(WRC) in the Mary's Creek Drainage Basin.
Background
Currently, the majority of Fort Worth wastewater flow is transported to the Village Creek Wastewater
Treatment Plant, located on the far eastern side of Fort Worth, bordering the City of Arlington. Without a
satellite treatment plant on the west side of Fort Worth, future development in this region would require
constructing new pipelines through the central city-Trinity River area where available corridors are
restricted. As an example, to transport 25 million gallons per day (MGD) of wastewater from the Mary's
Creek Drainage Basin to the Village Creek Wastewater Treatment Plant would require approximately 31
miles of 72-inch gravity sewer pipe.
Y' Over the years, numerous studies have been prepared to provide for alternatives for wastewater service to
meet the growing demands of the City of Fort Worth and its wholesale customers. Key studies include the
1998 Fort Worth Wastewater Master Plan, 2007 Eastern Parker County Regional Wastewater System
Study, 2008 Fort Worth-Aledo Wastewater Study, and on-going Wastewater Master Plan Study updates.
These studies revealed that the future growth patterns of Fort Worth show substantial increases in the
western part of Fort Worth, resulting in the need of a west side treatment facility.
Furthermore, the Texas Water Development Board Region C Plan projects that 28% of future water supply
for the Metroplex would be derived from conservation and reuse by 2060. The 2007 Fort Worth
Wastewater Reuse Master Plan recommends a west side treatment facility to meet the reuse water
demands from several proposed large scale developments, substantially decreasing the project cost by
having a source of high quality reclaimed water in close proximity.
On February 24, 2009, (M&C C-23367) the City Council authorized an engineering agreement for Mary's
Creek Water Recycling Center Site Selection. The Mary's Creek Drainage Basin stretches from the
confluence of the Clear Fork of the Trinity River near the South Ridglea Golf Course west along Mary's
Creek and South Mary's Creek into eastern Parker County.
Public Involvement
A Community Advisory Committee (CAC) was formed to review the project and provide feedback to the
City on the site selection criteria. The CAC was composed of 17 members representing neighborhoods,
planning agencies, chambers of commerce, public health professionals, development communities, public
water agencies and local environmental groups. Members of the CAC are listed below:
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 9206
Tor+1
To the Mayor and Members of the City Council March 2, 2010
M
Page 2 of 3
a
SUBJECT: MARY'S CREEK WATER RECYCLING CENTER SITE SELECTION
Thad Brundrette Wastewater Master Plan Advisory Committee
Dana Burgdoff City Planning & Development Department
Fran Burns Water Conservation
Jyl Dehaven Development Advisory Committee
Kyle Ferguson Lost Creek Golf Course
Victor Garcia Fort Worth Hispanic Chamber of Commerce
Terry Grafton LINT Health Science Center-Environmental Health
David Jefferson Tarrant County Public Health Department
Adeleide Leavens Streams &Valleys
Don Little Capital Improvement Advisory Committee
Cheryl Onken Old Weatherford Road Association
Darrel Andrews Tarrant Regional Water District
Wayne Owen Tarrant Regional Water District
Mark Presswood Greater Fort Worth Real Estate Council
Becky Richards TCU Environmental Science
Gail Tidwell Lost Creek Estates Neighborhood Association
David Wasson Benbrook Water Authority
?11.s
The CAC met six (6) times between July 2009 and January 2010. CAC members identified and prioritized
24 criteria focused on community livability issues. In addition, CAC members provided feedback on
technical criteria that were used in ranking the short-listed six (6) sites to determine the three finalist sites.
Commitments
In response to the comments received from CAC members throughout the process, the City is committed
to incorporate the following technical considerations into the Mary's Creek plant design and construction:
• State of the art odor control
• Noise abatement
• Appropriate and focused lighting
• Additional buffer zones
• Architectural and landscaping enhancements
• Perimeter fencing
WRC Site Requirements
It has been determined that approximately 100 acres will be necessary for the site. Of that, 45 acres are
required for the ultimate plant capacity of 25 MGD in 2060. The remaining 55 acres are for future joint
community uses, buffer zones, and land that may be required to address potential changes in treatment
requirements.
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 9206
T To the Mayor and Members of the City Council March 2, 2010
[A
Page 3 of 3
a
SUBJECT: MARY'S CREEK WATER RECYCLING CENTER SITE SELECTION
WRC Three Step Site Selection Process
14 preliminary WRC sites were identified within the Mary's Creek Drainage Basin between Loop 820
West-Jim Wright Freeway and Farm-to-Market Road-187-Farmer Road along Mary's Creek or South
Mary's Creek. Each site is approximately 100-acres. Locations are shown on Attachment 1.
These 14 preliminary sites were further screened to 6 semi-finalist sites based on factors such as
availability of land, closeness to existing and potential developments, capability to maximize gravity sewer
service, proximity to discharge into receiving stream, site condition and topography, etc.
All 24 CAC community livability criteria and 27 technical criteria were consolidated into 12 weighted
groups to apply against the 6 semi-finalist sites. Each site was evaluated with respect to adjacent land use
impact, flood plain consideration, plant and pipeline construction costs, recycled water use opportunities,
ability to serve regional or wholesale customers, plant discharge quality, regulatory requirements,
transportation, power supply, etc. The three (3) finalist sites, No. 2, 4 and 10, were determined from this
process as shown on Attachment 2.
Preliminary Costs
The Preliminary Phase I, 5 MGD water recycling plant construction cost is estimated at $50 to $60 million.
The cost estimate is based on 2010 dollars and includes enhanced odor control and architectural features.
Next Steps for the Comina 6-Month Period
City staff have met or corresponded with the three finalist site owners and plan to continue regular
communication. Public outreach and open house meetings will be conducted to keep citizens informed. An
amendment will be submitted for City Council approval to support public outreach effort and begin property
appraisal. City staff will be meeting with the Tarrant Regional Water District and Texas Commission on
Environmental Quality. Proposals will be solicited from engineering firms to perform water quality
monitoring, modeling and environmental assessment.
Project Timeline
The environmental assessment will begin in 2010, with site acquisition scheduled for 2011. Texas
Pollution Discharge Elimination System (TPDES) permitting efforts and preliminary design will begin in
2012. It is anticipated that construction will be completed by 2018.
Should you have any questions please contact me or Water Director Frank Crumb at 817-392-8207.
Dade A. Fisser er P.E.
_4
City Manager
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
e.II_IV `�' *.� ." q—r.4.:':.1y P•l��i1 `'. I ` !-j� .spJ'` �� '4
Jjf
40 1
L T-
T,
1p
�: —YY fir - E { +� I �t � •�^� � w. r�!"
,v�— T�,.. �" a..�! )a -. �ry! 11.5 •Tl� ��'j "
. . n
,c
}F
jpj y ,
4
Est � � �•, ` -ec. • ''� t '1"".ti _•. 7 �''`t.� -0
LU
W ,
G O Y
•
Y
a
� tom•
r
A -v
.. wet: T�.� '• y 1 ���, � ( j4,�`{ .¢t
WL
8 1 __