NOTICE OF PROJECT COMPLETION
CSC No. 53332-FP1
Regarding contract 53332 for the Village Creek Biosolids Management and Beneficial Reuse Project as
required by the Water Department and approved by City Council on December 10, 2019 through M&C 19-
0381 the Director of the Water Department, upon the recommendation of the Assistant Director, Capital
Projects Delivery, Water Department has accepted the project as complete.
Original Contract Price:
Amount of Approved Change Orders
Revised Contract Amount:
Total Cost Work Completed:
Less Deductions:
Performance Credit:
Other Deductions:
Total Deduction Amount:
Total Cost of Work Completed
Less Previous Payments:
Final Payment Due:
/nL SAS 0
Recommended for Acceptance
Assistant Director, Water Department
CGII'l.f Oyhel- flGtydEl-
Chn stop her Hard Or(Jun 4, 202412:47 CDT
Accepted
Director, Water Department
Asst. City Manager
$ 58,001,558.00
$ 178,141.00 No. 3
$ 58,179,699.00
$ 58,179,699.00
0Days$1,000/Day
$ 0.00
$ 0.00
$ 58,179,699.00
$ 57,929,699.00
$ 250,000.00
Project Name: Village Creek Biosolids and Beneficial Reuse Project
Date of Warranty Start:
1 1/30/2022
6 /3 / 24
Date
Jun 4, 2024
Date
7_,.c,_
Date
CPN 101961
Date of Final Completion:
4/30/2023
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Synagro of Texas - CDR, Inc.
435 Williams Court, Suite 100
Baltimore, MD 21220
Bill To:
City of Fort Worth
200 Texas Street
Fort Worth, TX 76102
Attn: Director, Water Department
Project: DBOM Village Creek Water Reclamation
Facility Biosolids Management and Reuse
Construction for City of Fort Worth - Retainage
Period 8.14.23
TOTAL
REMIT TO:
Standard Mail Synagro of Texas - CDR, Inc.
c/o Synagro Technologies, Inc.
P.0 Box 1367
Albany, NY 12201-1367
Overnight Address KeyBank - Lockbox Ops Attn: Lockbox
Synagro of Texas - CDR, Inc.
c/o Synagro Technologies, Inc.
555 Patroon Creek Blvd
Albany, NY 12206
ACH
Bank Name: KeyBank
ABA #: 41001039
Account#: 359681613295
Date 4/15/2024
$ 250,000.00
$ 250,000.00
Des; - S(Ail) Tv va.-a
bf) -0 IS
o5/a vc?�
L/f'�-' L
�)A -
***This invoice is not Notarized due to the restrictions associated with the COVID-19 ongoing pandemic and the Stay at Home
Order placed in Maryland by the Governor.
APPLICATION AND CERTIFICATION FOR PAYMENT
TO OWNEF City of Fort Worth PROJECT: DBOM Village Creek Water
Reclamation Facility
200 Texas Street Biosolids Management and
Fort Worth, TX 76102 Reuse
ATTN: Director, Water Department
FROM CONTRACTOR:
Synagro of Texas -CDR, Inc.
CONTRACT FOR:
CONTRACTOR'S APPLICATION FOR PAYMENT
Application is made for payment, as shown below, in connection with the Contract.
Continuation Sheet, AIA Document G703, is attached.
AIA DOCUMENT G702 PAGE ONE OF
APPLICATION NO: 35 Distribution to:
X OWNER
PERIOD FROM: 2/l/2023 ARCHITECT
PERIOD TO: 8/14/2023 CONTRACTOR
PROJECT NOS: 101961
CONTRACT DATE: December 30, 2019 NTP January 1, 2020
The undersigned Contractor certifies that to the best of the Contractor's knowledge,
information and belief the Work covered by this Application for Payment has been
completed in accordance with the Contract Documents, that all amounts have been paid by
the Contractor for Work for which previous Certificates for Payment were issued and
payments received from the Owner, and that current payment shown herein is now due.
PAGES
1. ORIGINAL CONTRACT SUM
$
58,001,558.00
2. Net change by Change Orders
$
178,141.00
CONTRACTOR:
CONTRACT SUM TO DATE (Line 1 t 2)
$
58,179,699.00
fIkK-
4.3.
TOTAL COMPLETED & STORED TO
$
58,179,699.00
By: Date: 8/14/2023
DATE (Column G on G703)
5. RETAINAGE:
State of: County of:
a. 5.0 % of Completed Work $
$
Subscribed and sworn to before me this day of
(Column D + E on G703)
Notary Public: N/A
b. % of Stored Material $
My Commission expires:
(Column F on G703)
Total Retainage (Lines 5a+5b or
$
-
Certificate of Design -Build Manager/Engineer of Record
Total in Column I of G703)
$
0.00
In accordance with Section 12.2(C.)(6) we hereby certify (1) CURRENT PAYMENT DUE is payable to
6. TOTAL EARNED LESS RETAINAGE
$
58,179,699.00
the Company, (2) that the Company is neither in default under this Service Contract nor in any breach of
(Line 4 Less Line 5 Total)
any material provision of the Service Contract such that the breach would, with the giving of notice or passage
7. LESS PREVIOUS CERTIFICATES FOR
of time, constitute an Event of Default, and (3) that all items applicable to the work entitling the Compnay
PAYMENT (Line 6 from prior Certificate)
$
57,929,699.00
to the requested payment undr the schedule in Appendix 12 have been completed in accordance herewith
8. CURRENT PAYMENT DUE
$
250,000. 00
in accordance therewith and with the Design and Construction Requirements, as applicable.
9. BALANCE TO FINISH, INCLUDING RETAINAGE
0.00
(Line 3 less Line 6)
AMOUNT CERTIFIED ........... $ S 250,000,00
WER SUMMARY
ADDITIONS DEDUCTIONS
Total changes approved
DESIGN -BUILD MANAGER/ARC=CT OF RECORD
in previous months by Owner���
I$96,445.00
� ?c
1 ��
Total approved this Month
$81,696.00
By: / Date: 8/14/2023
TOTALS
$178,141.00 $0.00
This Certificate is not negotiable. The AMOUNT CERTIFIED is payable only to the
$178.141.00
Contractor named herein. Issuance, payment and acceptance of payment are without
NET CHANGES by Change Order
prejudice to any rights o£the Owner or Contractor under this Contract.
Major Milestone
Item
Engineering
NTP Design
30% Design
60% Design
90% Design
100% Design
Andritz Design/Engineering/Integration
Engineering Coordination During Construction
Construction
NTP Equipment Procurement Package
Design Package # 1 - Piers
Mobilization
Site Prep
Demolition
Dryer Building Concrete
Sitework Concrete
Design Package # 2 - Foundations
Mobilization
Dryer Building Concrete
Sitework Concrete
Design Package #3 - Balance of Construction
Mobilization
Yard Piping
Paving
Sitework Completion
Metals
Equipment- Mechanical
Equipment- Electrical
Equipment - Miscellaneous Equipment
Process Piping
Building
Building Electrical and Instrumentation
HVAC
Equipment Delivery'
Startup/Commissioning
Substantial Completion
Acceptance
CO # 1- Silo Obstruction Lighting
Special Services
NTP Phase Permit
Permits'
Approved Submittals'
0&M Manuals
CO # 2 - Air Permit Amendment - DigesterGas
TOTAL
WORK COMPLETED
This Application
Previous
Total Completed
Percent
Scheduled
Applications
Work In Place I Stored Materials and Stored To Date
Complete Balance To Finish Retainage
Value
$ 7,127,441.32
7,127,441.32
7,127,441.32
100%
250,000.00
250,000.00
250,000.00
100%
824,701.97
824,701.97
824,701.97
100%
752,847.00
752,847.00
752,847.00
100%
752,847.00
752,847.00
752,847.00
100%
377,616.00
377,616.00
377,616.00
100%
3,234,726.35
3,234,726.35
3,234,726.35
100%
934,703.00
934,703.00
934,703.00
100%
$ 48,861,338.23
48,861,338.23
- 48,861,338.23
100% - -
896,557.48I
896,557.48
- 896,557.48
100% - -
6,235,000.00
6,235,000.00
- 6,235,000.00
100% - -
835,000.00
835,000.00
- 835,000.00
100% - -
600,000.00
600,000.00
- 600,000.00
100% - -
250,000.00
250,000.00
- 250,000.00
100% - -
3,025,000.00
3,025,000.00
- 3,025,000.00
100%
1,525,000.00
1,525,000.00
- 1,525,000.00
100%
6,457,000.00
6,457,000.00
- 6,457,000.00
100%
907,000.00
907,000.00
- 907,000.00
100%
4,025,000.00
4,025,000.00
- 4,025,000.00
100%
1,525,000.00
1,525,000.00
- 1,525,000.00
100%
35,272,780.75
35,272,780.75
- 35,272,780.75
100%
258,000.00
258,000.00
- - 258,000.00
100%
4,100,000.00
4,100,000.00
- - 4,100,000.00
100%
700,000.00
700,000.00
- - 700,000.00
100%
150,000.00
150,000.00
- - 150,000.00
100%
700,000.00
700,000.00
- - 700,000.00
100%
2,050,000.00
2,050,000.00
- - 2,050,000.00
100%
2,050,000.00
2,050,000.00
- - 2,050,000.00
100%
550,000.00
550,000.00
- - 550,000.00
100%
650,000.00
650,000.00
- - 650,000.00
100%
4,050,000.00
4,050,000.00
- - 4,050,000.00
100%
3,550,000.00
3,550,000.00
- - 3,550,000.00
100%
400,000.00
400,000.00
- - 400,000.00
100%
13,162,981.30
13,162,981.30
- - 13,162,981.30
100%
938,779.00
938,779.00
- - 938,779.00
100%
450,000.00
450,000.00
- - 450,000.00
100%
1,416,575.45
1,416,575.45
- - 1,416,575.45
100%
96,445.00
96,445.00
- - 96,445.00
100%
$ 2,190,919.45
2,190,919.45
- - 2,190,919.45
100% -
165,305.00
165,305.00
165,305.00
100%
233,085.75
233,085.75
- - 233,085.75
100%
699,257.25
699,257.25
- - 699,257.25
100%
1,011,575.45
1,011,575.45
- 1,011,575.45
100%
81,696.00
81,696.00
- - 81,696.00
100%
$ 58,179,699.00
58,179,699.00
- - 58,179,699.00
100% -
FORTWORTH rev 03/05/07
WATER ENGINEERING & FISCAL SERVICES
FINAL STATEMENT OF CONTRACT TIME
FINAL STATEMENT NO.: NA
NAME OF PROJECT: Village Creek Biosolids Management and Beneficial Reuse Project
PROJECT NO.: 101961 CONTRACTOR: Synagro of Texas -CDR, Inc.
CITY PROJECT
PERIOD FROM 04/01/24 TO: 04/30/24 FINAL INSPECTION DATE: 6/8/2022
WORK ORDER EFFECTIVE: I/l/2020 CONTRACT TIME: 1581 0 WD OQ CD
DAY OF DAYS REASON FOR DAYS DAY OF DAYS REASON FOR DAYS
MONTH CHARGED CREDITED MONTH CHARGED CREDITED
DURING DURING
1. 1 16. 1
2. 1 17. 1
3. 1 18. 1
4. 1 19. 1
5. 1 20. 1
6. 1 21. 1
7. 1 22. 1
8. 1 23. 1
9. 1 24. 1
10. 1 25. 1
11. 1 26. 1
12. 1 27. 1
13. 1 28. 1
14. 1 29. 1
15. 1 30. 1
31.
SAT, SUN, RAIN, TOO WET, UTILITIES OTHERS* DAYS TOTAL
& HOLIDAYS & TOO COLD RELOCATIONS CHARGED DAYS
THIS
PERIOD 30 30
PREVIOUS 1551 1551
PERIOD
TOTALS 1581 1581
TO DATE
*REMARKS: 11 days of contract time added by CO2 and 538 days of contract time added by CO3. Stop time 4/30/2024
based on Maximo implementation.
5/24/2024
CONTRACTOR DATE INSPECTOR DATE
Capital Projects Deliveq, Water Department
The City of Fort Worth • 200 Texas Street • Fort Worth, l'i 76012-6311
(817) 392 - 4477 • Fax: (817) 392 - 8460
CONSENT OF
SURETY COMPANY
TO FINAL PAYMENT
Conforms with the American Institute of
Architects, AIA Document G707
PROJECT:
(name, address)
TO (Owner)
F
CITY OF FORT WORTH
1000 Throckmorton Street
Fort Worth TX 76102
CONTRACTOR: SYNAGRO OF TEXAS - CDR, INC.
OWNER
❑
ARCHITECT
❑
CONTRACTOR
❑
SURETY
OTHER
Bond No ES00000547
ARCHITECT'S PROJECT NO:
CONTRACT FOR:
Design, Build Operate and Maintain Village Creek Water Reclamation
Facility Biosotids Management and Beneficial Reuse - 101961
J CONTRACT DATE: 12/20/2019
In accordance with the provisions of the Contract between the Owner and the Contractor as indicated above, the
(here insert name and address of Surety Company)
EVEREST REINSURANCE COMPANY
PO Box 830
Liberty Corner NJ 07938-0830 , SURETY COMPANY
on bond of (here Insert name and address of Contractor)
SYNAGRO OF TEXAS - CDR, INC.
435 Williams Court, Suite 100
Baltimore 21220 , CONTRACTOR,
hereby approves of the final payment to the Contractor, and agrees that final payment to the Contractor shall not relieve
the Surety Company of any of its obligations to (here Insert name and address of Ownerl
CITY OF FORT WORTH
1000 Throckmorton Street
Fort Worth TX 76102 , OWNER,
as set forth in the said Surety Company's bond.
IN WITNESS, WHEREOF,
the Surety Company has hereunto set its hand this
Attest: Filipe Ramos
(Seal):
21st day of March, 2023
EREST REINSURANCE COMPANY
e Company
�n
Signature of Authorized Repr tative
Francesca Kazmierczak Attorney -in -Fact
Title
NOTE; This form is to be used as a companion document to AIA DOCUMENT G706, CONTRACTOR'S AFFIDAVIT OF PAYMENT OF DEBTS AND CLAIMS,
Current Edition
ONE PAGE
& everest"
POWER OF ATTORNEY
EVEREST REINSURANCE COMPANY
KNOWALL PERSONS BY THESE PRESENTS: That Everest Reinsurance Company, a corporation of the Stale of Delaware ("Company) having its principal
office located at 100 Everest Way, Warren, New Jersey, 07059, do hereby nominate, constitute, and appoint:
Sandra Diaz, Peter Healy, Jennifer L. Jakaitis, Francesca Kazmlerczak, Aklima Noorhassan, Frances Rodriguez,
Susan A. Welsh, Pablo Garcia Horcajo, Anne L. Potter, Valorle Spates, Beverly A. Woolford, Kernel Brkanovlc, Martha Gaines
its true and lawful Atlorney(syin-fact to make, execute, attest, seal and deliver for and on its behalf, as surety, and as its act and deed, where required, any
and all bonds and undertakings In the nature thereof, for the penal sum of no one of which is in any event to exceed UNLIMITED, reserving for Itself the full
power of substitution and revocation.
Such bonds and undertakings, when duly executed by the aforesaid Attomey(s)-in-fact shall be binding upon the Company as fully and to the same extent as
If such bonds and undertakings were signed by the President and Secretary of the Company and sealed with Its corporate seal.
This Power of Attorney Is granted and is signed by facsimile under and by the authority of the following Resolutions adopted by the Board of Directors of
Company ("Board') on April 21, 2016:
RESOLVED, that the President, any Executive Vice President, and any Senior Vice President are hereby appointed by the Board as authorized to
make, execute, seal and deliverforand on behalf of the Company, any and all bonds, undertakings, contracts orobligations in surety orco-surety with others
and that the Secretary or anyAssistant Secretary of the Company be and that each of them hereby is authorized to attest to the execution of any such bonds,
undertakings, contracts or obligations in surety or co -surety and attach thereto the corporate seal of the Company.
RESOLVED, FURTHER, that the President, any Executive Vice President, and any SeniorVice President are hereby authorized to execute powers
of allomey qualifying the attorney named in the given power of attorney to execute, on behalf of the Company, bonds and undertakings in surety orco-surety
with others, and that the Secretary or any Assistant Secretary of the Company be, and that each of them is hereby authorized to attest the execution of any
such power of attorney, and to allach thereto the corporate seal of the Company.
RESOLVED, FURTHER, that the signature of such officers named in the preceding resolutions and the corporate seal of the Company may be
affixed to such powers of attorney or to any certificate relating thereto by facsimile, and any such power of attorney or certificate beating such facsimile
signatures or facsimile seal shall be thereafter valid and binding upon the Company with respect to any bond, undertaking, contract or obligation in surety or
co -surety with others to which it is attached.
IN WITNESS WHEREOF, Everest Reinsurance Company has caused their corporate seals to be affixed hereto, and these presents to be signed by their duly
authorized officers this 1 V day of February 2023.
r
�C+l
Everest Reinsurance Company
SEAL
«
By: Anthony Romano, Senior Vice President
On this 150, day of February 2023, before me personally came Anthony Romano, known to me, who, being duly swom, did execute the above instrument;
that he knows the seal of said Company; that the seal affixed to the aforesaid instrument is
such corporate seal and was affixed thereto; and that he executed
said instrument by like order.
LINDA ROBINS
Notary Pu blic, State of New York//
No 01R06239736
Qualified in Queens County
f
Term Expires April 25, 2027
Linda Robins, Notary Public
I, Nicole Chase, Assistant Secretary of Everest Reinsurance Company do hereby certify that
I have compared the foregoing copy of the Power of Attomey and
affidavit, and the copy of the Section of the bylaws and resolutions of said Corporation as
set forth In said Pourer of Attomey, with the ORIGINALS ON FILE IN
THE HOME OFFICE OF SAID CORPORATION, and that the same are correct transcripts thereof, and of the whole of the said originals, and that the said
Power of Attorney has not been revoked and is now in full force and effect.
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the seal of said Company, this 21 St day of March 2023.
epsuraryeP
�
w SEAL
J'•
y /y� 1973 W
-a W\VARY' �
*
By: Nicole Chase, Assistant Secretary
ES 00 01 04 16
AFFIDAVIT
I, John Goodwin, hereby affirm on behalf of Synagro of Texas -CDR, Inc., as its Senior Vice
President, Engineering, and not personally, as follows:
1. All payments to all vendors performing design, equipment supply and construction
services in connection with the permitting, construction, testing and placement into
operation of the Biosolids Processing Facility Capital Improvements for the City of Fort
Worth, Texas, funded through the Texas Development Water Board's (TWDB) clean
water state revolving fund program have been made.
2. There remains no outstanding invoices from, or amounts payable to, any vendor
performing design, equipment supply or construction services in connection with the
permitting, construction, testing and placement into operation of the Biosolids
Processing Facility Capital Improvements for the City of Fort Worth, Texas, funded
through the TWDB.
I hereby declare that the above statements are true and correct to the best of my knowledge
and belief
9%?` /zG2��
S�gn ture Date `
1
Subscribed and sworn to before me thi day of /�� 2024.
Notary Public,
My Commission Expires:
CONSTANCE A. REYNOLDS
NOTARY PUBLIC
ANNE ARUNDEL COUNTY
MARYLAND
My Commleaion Expires 09-06-2027
SYNAGRO
YOUR PARTNER FOR A CLEANER, GREENER WORLD
Steven L. Nutter, REM, CEA
Environmental Program Manager
Village Creek Water Reclamation Facility
Plant Operations Division
Fort Worth Water Department
Subject: Final Completion — Warranty Letter
Dear Mr. Nutter:
April 29, 2024
Submitted via email and BIM360
Synagro of Texas -CDR, Inc. (Synagro) is providing this written notice to the City to document the warranty
period according to Article X, Section 10.18 of the Service Contract.
Warranty started on Acceptance Date (November 30, 2022) and remained in effect for a period of one year
following the Acceptance Date.
Should questions arise, please contact me at (443) 442-4213 or bvairavan@svnagro.com.
Sincerely,
Synagro
Bala Vairavan
Synagro
Attachments
cc: John Goodwin, Synagro of Texas -CDR, Inc.
Suzanne Abbe, City of Fort Worth
Mark Martinez, Synagro of Texas -CDR, Inc.
SYNAGRO
YOUR PARTNER FOR A CLEANER, GREENER WORLD
Steven L. Nutter, REM, CEA
Environmental Program Manager
Village Creek Water Reclamation Facility
Plant Operations Division
Fort Worth Water Department
May 17, 2024
Submitted via email
Subject: Releasing Final Retainage — Project Acceptance Letter
Biosolids Management and Beneficial Reuse
Texas Water Development Board (TWDB) Clean Water State Revolving Fund Program
City Project No. 101961
Dear Mr. Nutter:
Synagro of Texas -CDR, Inc. (Synagro) is providing this letter to certify that the above referenced project has
been completed according to the approved plans and specifications.
Should questions arise, please contact me at (443) 442-4213 or bvairavan@svnagro.com.
Sincerely,
Synagro
Bala Vairavan
Sr. Project Engineer/Director of Capital Projects
Synagro
Attachments
cc: John Goodwin, Synagro of Texas -CDR, Inc.
Suzanne Abbe, City of Fort Worth
Mark Martinez, Synagro of Texas -CDR, Inc.
FORTWORTH
MAY 20, 2024
BALA VAIRAVAN
DIRECTOR, CAPITAL PROJECTS
SYNAGRO OF TEXAS -CDR, INC.
435 WILLIAMS COURT, SUITE 100
BALTIMORE, MD 21220
RE: PROJECT ACCEPTANCE
Mr. Vairavan,
Conditional Acceptance of the Biosolids Processing Facility Capital Improvements was obtained
on November 30, 2022 (see Attachment A). A series of final inspections were conducted with
punch list items being generated beginning March 1, 2022 and ending September 20, 2022.
Punchlist items were completed November 8, 2022 with additional site cleaning and fence repair
completed by March 27"', 2023. The facility's air permit modification was completed and then
submitted to the City on September 21, 2023. The City will continue working with Synagro on
Maximo Implementation. The project has been completed according to the approved plans and
specifications (see Attachment B) and is therefore accepted by the City.
If you have any questions concerning this letter then please feel free to contact me at
(817) 392-4965.
Sincerely,
Steven L. Nutter
Environmental Program Manager
Plant Operations Division
Fort Worth Water Department
Enclosure
WATER DEPARTMENT
PLANT OPERATIONS DIVISION
THE CITY OF FORT WORTH * 4500 WILMA LANE * ARLINGTON, TEXAS 76012
(817) 392-4960 * ADMINISTRATION FAX (817)392-4957
cc: John Goodwin P.E; Sr. Vice President, Synagro
Mark Martinez; Plant Manager, Synagro
Suzanne Abbe, P.E. Senior Engineer
Project File
CONDITIONAL ACCEPTANCE LETTER
MARCH 14, 2023
FORTWORTH
MARCH 14, 2023
BALA VAIRAVAN
DIRECTOR, CAPITAL PROJECTS
SYNAGRO OF TEXAS -CDR, INC.
435 WILLIAMS COURT, SUITE 100
BALTIMORE, MD 21220
RE: ACCEPTANCE — BIOSOLIDS PROCESSING FACILITY CAPITAL IMPROVEMENTS
Mr. Vairavan,
A review of the City's records shows the following timeline associated with the Acceptance Date
of the Biosolids Processing Facility Capital Improvements:
• Notice to Proceed — January 1, 2020. Acceptance Date established as June 30, 2022.
• Change Order #1 (August 27", 2021) — Acceptance Date moved to July I1", 2022
because of winter weather. Final Completion moved to November 9', 2022.
• City letter granting Substantial Completion — June 7'1, 2022.
• City letter dated June 140', 2022 — Acceptance Date moved to July 22"d due to delays
associated with natural gas supply.
• Commencement of Acceptance Testing — June 2811, 2022
• City letter dated August 151, 2022 (see attached) — Acceptance Testing to be completed by
September 12", 2022 (new Acceptance Date Deadline). Final Completion Deadline
established as November 24'1, 2022,
• Air permit stack testing performed August 30'11 — September 151, 2022
• Closed loop cooling system in service — October 4"', 2022.
• Plate clarifier performance testing conducted November 14" — 30"1, 2022.
• Revised Acceptance Test Report submitted to the City - January 30'1, 2023
The following actions have been taken and/or remain outstanding in regards to Acceptance:
• Pending — obtaining an air permit amendment from TCEQ for facility emissions. An
application for the amendment was submitted to TCEQ for expedited review (January
30"', 2023).
WATER DEPARTMENT
PLANT OPERATIONS DIVISION
THE CITY OF FORT WORTH * 4500 WILMA LANE * ARLINGTON, TEXAS 76012
(817) 392-4960 * ADMINISTRATION FAX (817)392-4957
Pending - full Maximo implementation as required by the Performance Guarantee for
O&M Reliability (Contract — Technical Appendix 3.6).
• Pending - submittal of a "no default certification" as required by the contract - Section
11.2(B)(4).
• Pending — Contract Section 11(2)(C), certification by the Company that all performance
standards have been achieved
The City is willing to grant conditional Acceptance while the air permit amendment is being
reviewed and processed by TCEQ. Please note that once the air permit amendment is issued
Synagro will have sole responsibility to provide any process, material, labor or equipment
upgrades that are needed to meet permit condition.
Based on the information above the City has determined that the Acceptance Date was achieved
on the last day of performance testing activities (November 30t", 2022). The November 30" date
constitutes 79 calendar days beyond the September 120' deadline established in the City's August
lst letter. That same letter also stipulated a November 20' deadline for achieving Final
Completion as defined in Section 10.21 of the contract. The following summary lists the
outstanding items associated with Final Completion:
• Pending - Submittal of all deliverables, including equipment warranties and manuals;
• Pending - Spare parts inventory;
• Pending - Clean up and removal of all construction materials and debris;
• Pending - Affidavit of payment of claims;
• While not required by contract, please include a consent of surety for retainage release as
this will be needed for final payment;
• While Maximo implementation is part of the Performance Guarantee for O&M
Reliability, and thus a requirement for obtaining Acceptance, the City is willing to defer
this obligation to a condition for Final Completion.
The City is requesting prompt submittal and completion of all outstanding items associated with
facility Acceptance and Final Completion as this will affect the project closeout timeline and
release of retainage. Furthermore the contract authorizes the City to assess performance credits
for failure to achieve Final Completion. If you have any questions concerning this letter
then please feel free to contact me at (817) 392-4965.
Sincerely,
Steven L. Nutter, REM, CEA
Environmental Program Manager
Plant Operations Division
Fort Worth Water Department
Enclosure: City Letter Dated August 1", 2022
cc: Andrew Bosinger; Vice President, Synagro
John Goodwin P.E; Sr. Vice President, Synagro
Mathew Busch; Sr. Vice President, Synagro
Bala Vairavan P.E; Director Capital Projects, Synagro
Mark Martinez; Plant Manager, Synagro
Chris Harder P.E.; Water Director
Shannon Dunne; Water Assistant Director
James McDonald; Sr. Capital Projects Officer
David Townsend, P.E. Engineering Manager
Suzanne Abbe, P.E. Senior Engineer
Project File
AUGUST 1, 2022
BALA VAIRAVAN
DIRECTOR, CAPITAL PROJECTS
SYNAGRO OF TEXAS -CDR, INC.
435 WILLIAMS COURT, SUITE 100
BALTIMORE, MD 21220
RE: ACCEPTANCE TESTING & OPERATING CHARGE
Mr. Vairavan,
The City has been monitoring dryer facility operations and ongoing construction activities during
the 30-Day Acceptance Test period which began on June 28, 2022. While encountering some
initial problems during the first two weeks of testing, the solids treatment train has become much
more consistent in regards to treating Village Creek's feedstock as well as producing a Class A
pelletized product. The City appreciates the hard work of Synagro and its subcontractors on the
construction side of the project as well as the ongoing efforts of the operations and maintenance
team.
While the solids treatment train is now producing more consistent results, the entire Biosolids
Processing Solution has not been operational during the contractually mandated 30-Day
Acceptance Test period. As such additional testing is needed to validate the solids treatment train
and support systems. Additional testing will cover all systems associated with the Biosolids
Processing Solution, including the following:
® Continue to demonstrate that the solids treatment train can consistently process the
feedstock from Village Creek and produce a Class A product;
® Bring the closed loop cooling system online to operate as designed, and as a result
eliminate discharges to the Peak Flow Basin;
® Validate the performance of the plate clarifier wastewater treatment system
® Implement improvements to facilitate wastewater conveyance from the dryer facility to
the ponds, with the purpose of eliminating overflows fi•om manholes and air vents;
® Finish work to enclose the centrifuge room so that the room's odor control system can be
fully validated;
® Finish startup activities associated with the pellet oil system, and demonstrate that this
system will operate on a consistent basis.
® hiclude TCEQ stack testing activities that are currently scheduled before the end of
August 2022.
WATER DEPARTMENT
PLANT OPERATIONS DIVISION
THE CITY OF FORT WORTH * 4500 WILMA LANE * ARLINGTON, TEXAS 76012
(817) 392-4960 * ADMINISTRATION FAX (817)392-4957
As stated in the contract it is important that all systems associated with the Biosolids Processing
Solution be fully tested for 30 continuous days. Furthermore the 30-Day Acceptance Test needs
to be completed by September 12111, 2022, with final completion obtained no later than November
24, 2022. Synagro has already developed a plan and a schedule to correct the deficiencies
described above — please continue to expedite work on these systems and bring these units online
as soon as possible.
This letter serves to accept and formalize the schedule dates listed above, without the need for a
change order or amendment to the contract. We would like to reiterate that we understand that
delays and some system failures are inevitable during startup and testing of a new facility;
however, by contract the timelines have already been exceeded for this work. We present the
above dates as firm and final extensions and that further delays exceeding them associated with
the completion of Acceptance Testing need to be avoided or we will be forced to implement the
penalty provisions of the contract related thereto.
As the solids treatment train is now showing consistent results, Synagro will be reimbursed at the
contractual rate of $169.51 per dry ton effective July 2811, 2022. Please feel free to contact me at
(817) 392-4965 if you have any questions.
Sincerely
Steven L. Nutter, REM, CEA
Environmental Program Manager
Plant Operations Division
Fort Worth Water Department
cc: Dick Zink, Synagro of Texas -CDR, Inc.
Eduardo Prospero, Synagro of Texas -CDR, Inc.
David Townsend, P.E. Engineering Manager
Suzanne Abbe, P.E. Senior Engineer
Project File
I_�t _« 20
JACOBS PROJECT REVIEW & APPROVAL
ON
,jacobs
777 Main Street
Fort Worth, TX
United States
T + 1.817.735.6000
May 2, 2024
Steven L. Nutter
Environmental Program Manager
Plant Operations Division
Fort Worth Water Department
Village Creek Water Reclamation Facility
4500 Wilma Lane
Arlington, TX 76012
Subject: Village Creek Water Reclamation Facility
Biosolids Management and Beneficial Reuse Project
Dear Steve,
The above referenced project was constructed by Archer -Western (Contractor) and inspected
by City of Fort Worth staff. Jacobs provided detailed review of the construction documents
during the design phase of the project, weekly construction observation, submittal review, and
contract document review during construction. To the best of my knowledge and belief, the
project was constructed in accordance with the plans and specifications reviewed by the Texas
Water Development Board (TWDB) and in compliance with 30 TAC § 217; the construction is
now complete.
If you need any further information on this project, please do not hesitate to contact me at 214-
755-1344 or via email at Timothy. Lyons@jacobs.com.
Sincerely,
Jacobs P
Timothy A. Lyons, P. E.
Project Manager
Copies To: