HomeMy WebLinkAboutContract 57251-CO1CSC No. 57251-COI
City of Fort Worth
Change Order Request
Project Name N. Riverside Drive from Golden Triangle to Keller Hicks Road
Client Project #(s)1 101567
Project
Description
Contractor
City Project Mgr.1
I City Sec # 1 57251
Widen approx. 2400 LF to 4lane divide thoroughfare including traffic signal at Keller Hicks Rd., shared used paths, street lights, and drainage
improvements.
McClendon Construction
Bereket Birhane
Dept.
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
Amount of Proposed Change Order
Revised Contract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
TPW
$4,125,601.45
Change Order#1 1 1 Datel 4/24/2024
City Inspectorl Stanley Sutterfield
Contract Time
Totals (CD)
$4,125,601.45 480
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 0.00%
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) $5,157,001.81
JUSTIFICATION (REASONS) FOR CHANGE ORDER
- A 1" Water Service not in use at STA 16+50 was encountered during construction and removed. Additionally, a 1" Water Service and a 2" Water Service had to be
removed, replaced, and relocated at STA 18+50. These services were found during the excavation and were not shown on the construction plans.
A street light pole near Golden Triangle was relocated from parkway to median due to utility conflict.
Reimbursement to McClendon Construction for activation fee paid to Tri County Electrical to supply electricity to newly installed traffic signal at N Riverside and Keller Hicks
Parkway.
- Furthermore, a time extension of 14 days for the water work and 29 days for the street light relocation, totaling 43 days, will be added to the contract.
City of Fort Worth staff and consultant team have evaluated proposed quantities and unit prices using recent City and other sources and found them to be acceptable.
- The total cost of $27,642.63 for the scope being added is being offset by an equal reduction in the Construction Contingency bid item, therefore the net contract amount
increase is $0.00.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full (both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below
acknowledges that he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and
reporting requirements.
Contractor's Company Name Contractor
McClendon Construction Co., Inc. (Justin Blair I�—ak I Jun 5, 2024
Inspector/inspection Supervisor
Date
Project and Contract Compliance Manager
Date
s11-116, �
Jun 5, 2024
Jun 4, 2024
Program Manager
Date
Senior Capital Project Officer
Date
F�
Jun 5, 2024
Jun 6, 2024
Assistant Director (Dept)
Date
Director, Contracting Department (Dept)
Date
P
Jun 11,2024
A --a
Jun11,2024
Assistant City Attorney
Date
Ass' istant City Manager
Date
Jun 12, 2024
Jun 18, 2024
44000q M&C Number I M&C Date Approved I l
4 b�
ATTEST: _ � o FORraa
Jannette Goodall, City Secretary pc g o=I.%*o.
ddEa p5
aa"b4q
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORT WORTH City of Fort Worth
1"*1--- Change Order Additions
Project Name I N. Riverside Drive from Golden Triangle to Keller Hicks Road I City Sec # 1 57251
Client Project# 1 101567 1
Contractor McClendon Construction I PMJ Bereket Birhane I Inspector Stanley Sutterfield
Change Order Submittal # 0 Date 1 4/24/2024 1
ADDITIONS
IIEM
UE5(;RIPIIUN
ULHI
Uty '
Unit
Unitl:ost
total 1
C1.1
Remove 1" Water Service not in use at 8 IA 16+5U
IPW
1.000uuuuu
LS
$1,1uu.uu
$1,100.0u1
C1.2
Remove, Replace, Relocate EX 1" Water Service at STA 16+5C
TPW
1.00000000
LS
$3,600.10C
$3,600.001
C1.3
Remove, Replace, Relocate EX 2" Water Service at STA 18+5C
TPW
1.00000000
LS
$4,900.01]
$4,900.001
C1.4
2" Conduit PVC Sch *) (T)
TPW
5.00000000
LF
$13.01J'
$65.001
C1.5
2" Conduit PVC Sch 80 (B)
TPW
46.00000000
LF
$23.00
$1,058.001
C1.6
No 6Insulated Elec Condr
TPW
138.00000000
LF
$4.01J'
$552.001
C1.7
Ground Box Type B
TPW
1.00000000
EA
$1,200.0C
$1,200.001
C1.8
Traffic Control
TPW
1.00000000
MO
$8,950.10C
$8,950.001
C1.9
Street Light Contractor Remobilization
TPW
1.00000000
LS
$3,500.0C
$3,500.001
C1.10
Td County Service Activation Fee
TPW
1.00000000
LS
$2,717.63
$2,717.631
1
1
1
1
1
1
1
1
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
I
TPW
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
$27,642.631
I
I
I
Sub Total
Additions
I
I
$27,642.631
Change Order Additions Page 2 of 4
FORTWORTH City of Fort Worth
-Y. Change Order Deletions
Project Name I N. Riverside Drive from Golden Triangle to Keller Hicks Road City Sec # 1 57251
Client Project# 1 101567 1
Contractor McClendon Construction I PMI Bereket Birhane I Inspectorl Stanley Sutterfeld
Change Order Submittal # 0 Date 1 4/24/2024
DELETIONS
I I LM UtSGRIP I ION ULP I Uty unit unit Gost I otal
99UU.UU1b GON5IHUGHUNGUNIINUENGY IPtN U.UU21421U to $3UU,000.UU $2/,b42.b3
TFW $27,642.63
Sub Total Deletions $27,642.63
Change Order Deletions Page 3 of 4
M/SBE for this Change Order
M/SBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co# DATE I AMOUNT
Total I $0.00 1
P.O. Box 999
McCLENDON CONSTRUCTION CO., INC.
Burleson, Texas 76097 (817) 295-0066 Fax (817) 295-6796
July 14, 2022
City of Fort Worth
Attn: Alex Ayala
Re: N Riverside Drive
Change Order Request
Alex,
There is a discrepancy between the plans and pay items related to the private service
relocation. Work will also be required on the public side of the meter and that requires a
new pay item. In addition, one of the services that was anticipated to be 1" is a 2"
line/meter and no pay item exists to cover this condition. Lastly additional investigation,
clearing, and grading of the channel well beyond what was outlined in the plans was
required to drain/dry the creek section through our project that was holding water. Below
are the prices to complete this work.
Description
Remove 1" Water Service not in use at Station
16+50
Remove, Replace, Relocate Existing 1" Water
Service at Station 18+50
Remove, Replace, Relocate Existing 2" Water
Service at Station 18+50
Quantity I Unit I Unit Price I Total Price
1 LS $1,100.00 $1,100.00
1 LS $3,600.00 $3,600.00
1 LS $4,900.00 $4,900.00
Total Cost $9,600.00
We ask that 14 CD be added to the contract to complete this work and for other delays
experienced on the project due to franchise utilities.
Respectfully,
Justin Blair
P.O. Box 999
McCLENDON CONSTRUCTION CO., INC.
Burleson, Texas 76097 (817) 295-0066 Fax (817) 295-6796
January 11, 2024
City of Fort Worth
Attn: Bereket Birhane
Re: N Riverside Drive
Change Order Request
Bereket,
Below is the price to relocated the final Street Light Pole (#12) form the West Parkway to
the center median per plan revisions.
Justifications:
- Plan revisions require additional pay item quantities needed to change the location
of the street light pole form the parkway to the median which will require boring
under the completed concrete pavement. Remobilization is necessary because we
received the plan revisions after all other work on the project was complete and
lighting contractor had demobilized form the site.
- At the direction of Mark McCoy; McClendon Construction paid for, and will be
reimbursed, the activation fee to Tri County Electrical to supply electricity to the
electrical pedestal servicing the newly installed traffic signal at N Riverside and
Keller Hicks Parkway.
Description
Existing Pay Items
2" Conduit PVC Sch *) (T)
2" Conduit PVC Sch 80 (B)
No 6 Insulated Elec Condr
Ground Box Type B
Traffic Control
Quantity Unit Unit Price Total Price
5
LF
$13.00
$65.00
46
LF
$23.00
$1,058.00
138
LF
$4.00
$552.00
1
Ea
$1,200.00
$1,200.00
1
Mo
$8,950.00
$8,950.00
New Items
Street Light Contractor Remobilization 1 LS $3,500.00 $3,500.00
Tri County Service Activation Fee 1 LS $2,717.63 $2,717.63
Total $18,042.63
If contract time was not stopped previously, all days that have past while we were
waiting on this answer will need to be added to the contract.
Respectfully,
Justin Blair
Birhane, Bereket B
From: Justin Blair<jblair@mcclendonconstruction.com>
Sent: Wednesday, March 20, 2024 3:22 PM
To: Birhane, Bereket B; Lopez, Raul
Cc: 'BJ Blair'
Subject: RE: N Riverside Power by TCEC
Attachments: FW: N Riverside Power by TCEC; FW: N Riverside Drive - Electrical Service; RE: DSI
223.06082023 LUM RFI - 1; RE: N Riverside Drive - Electrical Service
CAUTION: This email originated from outside of the City of Fort Worth email system. Do not click any links or open attachments
unless you recognize the sender and know the content is safe.
Bereket,
Attached are a handful of emails dating back to May 2023 discussing the light pole conflict, power supply to the signal,
and another lighting quantity overrun. This was the RFI process for this project, emailing the PM Mark McCoy. I think
this should be what you need.
Also after today I will be out of town until Tuesday March 26, so I will not be able to respond again before then.
Here is a summary of the dates
5-25-23 — initial email to Mark McCoy with lighting conflict and quantity discrepancy
6-9-23 — email Mark Asking for a response to the lighting conflict and quantity discrepancy
6-23-23 — email Mark Asking for a response to the lighting conflict and quantity discrepancy
6-23-23 — Mark responded he hoped to have the answer by the end of the day, but did not
6-29-23 — email Mark McCoy with detail of how he needs to set up an account for the electrical service, He responded
he would handle setting up the account and payment to get the electrical meter set 6-29-23
8-31-23 — email Mark for Status of the electrical service
10-31-23 — McClendon Construction Paid the invoice from the electrical service
11-22-23 — Plans provided for street light relocation
12-19-23 — electrical meter set by Tri County for Keller Hicks Intersection signal
1-11-24 — McClendon provided pricing for the relocation, delay in pricing was due to holidays and original subcontractor
did not want to re mobilize for this work so a new electrical contractor was needed
Approval Date of light pole relocation — Unknow
Time between 1-11-24 and present was to incorporate this work into my sub -contractor existing schedule and then 3-4
week to phase this work.
Thanks,
Justin Blair
McClendon Construction
817-295-0066
From: Birhane, Bereket B <Bereket.Birhane@fortworthtexas.gov>
Sent: Wednesday, March 20, 2024 9:53 AM
Riverside I Classic Schedule Layout I 06-Feb-24 10,08
Activity ID Activity Name ginal ing chedule Start Finish I% l)022 Qtr2,2022 Qtr 3,2022 Qtr4,2022 Q1I, 2023 Qtr2,2023 Qir3,2023 Qtr4,2023 Qtr 1, 2024 IUrz LUL4
-- a— „ 1—I Lib Mar I Apr I May I Jun I Jul Aug Sep I Od Nov Dec Jan Feb I Mar I Apr I May I Jun I Jul I Aug P I � I Nov I Dec I Jan Feb I Mar I Apr Jay
A1000
Initial Survey, SWPPP, Startup
5 5
100% 30-Mar-22
05-Apr-22
G A1010
Stage 2&3A-Storm Drain, Channel, Culvert, Paving
172 17,
100% 05-Apr--22
304Jov-22
= A1020
Stage3B&4ANorth(@Kelerticks)-Excavatori
31 31
100%I 02-Dec-22
13Jan-Jan
p A1050
Stage 6- Paving, Sidewalks, Traffic Marldngs
69 69
100%I 16Jan-Jan
21-Apr-23
p A1030
Stage 4B South(@ Golden Triangle) - Excavation, Pavi
27 27
100%I 17Jan-Jan
22-Feb-23
p A1040
Stage 5 (@ Keller Hicks)
29 29
100%I 23-Feb-23
04-Apr-23
p A1060
SteetLights, Signals
50 50
100%I 01-May-23
07JuF23
p A1070
Activate Signal afterTd County Delay
5 5
100%I 19-Dec-23
26-Deo-23
p A1080
CO- Bore, Cable, Ground Box, Install last light pole due
22 22
0%I 19-Feb-24
19-Mar-24
Actual Level of Effort 0 Remaining Work ♦ ♦Milestone
Actual Work Critical Remaining Work �/summary
9-Mar-�4
p Inihal Survey. SWPI P,SNarQap
Stage 2 & 3Ar Stomi Drain, Channel, Culvert, Paving
Stage 3B & 4ANorth (@ Keller Hicks)-Excavaton, Paving, Sidewalks
;Stage 6',-Pavingl, Sidewalks, Traffic Mzjdangs
...:......:......:.....:......:......:......: _.... ;....� Stage 4B South(@Golden Triangle); Excavation, Pa..9.. __.._ __.__ _.__�_..__
Stage 5 (@ Keller Hicks)
O Street Lights, Signals
In ActivatPignal aferTrj County
Page 1 of 1
TASK filter. All Activities
0 Oracle Corporation
FORT WORTH.
Routing and Transmittal Slip
Transportation & Public Works
Department
DOCUMENT TITLE:
N. Riverside Drive (Golden Triangle to Keller Hicks Road)
Change Order #1
M&C: N/A CPN: 101567 CSO: 57251
DOC#: N/A
Date:
2/29/2024
To:
Name
Department Initials
Date Out
1.
Ann Estes
TPW - Review 4
Jun 4, 2024
2.
Bereket Birhane
TPW - Signature 88 as
Jun 4, 2024
3.
Justin Blair
McClendon - Sign � `
Jun 5, 2024
4.
Stanley Sutterfield
TPW - Signature HSSHSS
Jun 5, 2024
5.
Raul Lopez
TPW - Signature -c-z-
Jun 5, 2024
6.
Lissette Acevedo
TPW — Signature C Cv
Jun 6, 2024
7.
Patricia Wadsack
TPW — Signature PLW
Jun 11, 2024
8.
Lauren Prieur
TPW — Signature W—
Jun 11, 2024
9.
Doug Black
Legal — Signature �a
Jun 12, 2024
PB
10.
Jesica McEachern
CMO — Signature
Jun 18, 2024
r
11.
Jannette Goodall
CSO - Signature J-G-49-
Jun 18, 2024
12.
TPW Contracts
CC: Program Manager, Sr. CPO, TPW BSPAP Recon Team, TPW Records Room, TPW
Contracts
DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any and all
City Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, David will review
and take the next steps.
NEEDS TO BE NOTARIZED: ❑YES ®No
RUSH: ❑YES ®No SAME DAY: ❑YES ®No NEXT DAY: ❑YES ®No
ROUTING TO CSO: ®YES ❑No
Action Reauired: ❑ Attach Signature, Initial and Notary Tabs
❑ As Requested
❑ For Your Information
® Signature/Routing and or Recording
❑ Comment
❑ File
Return To: Please notify TPWContracts(i�fortworthtexas.eov for pickup when complete. Call ext.
7233 or ext. 8363 with questions. Thank you!