HomeMy WebLinkAboutOrdinance 26948-06-2024Ordinance No. 26948-06-2024
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER AND SEWER CAPITAL PROJECTS FUND
IN THE AMOUNT OF $1,594,629.00, FROM AVAILABLE PAYGO RESIDUALS
IN THE WATER AND SEWER CAPITAL PROJECTS FUND, FOR THE
PURPOSE OF FUNDING THE 16 INCH TO 24 INCH CAST IRON WATER MAINS
REPLACEMENTS IN EASTWOOD AND TIMBERLINE ELEVATED STORAGE
TANKS PROJECT (CITY PROJECT NO. 105070); PROVIDING FOR A
SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF
PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT
HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That the budget of the City of Fort Worth for Fiscal Year 2023-2024, as enacted by Ordinance 26453-09-
2023, as amended, is hereby further amended to make the following adjustments by increasing estimated
receipts and appropriations in the Water and Sewer Capital Projects Fund in the amount of $1,594,629.00,
from available PayGo Residuals in the Water and Sewer Capital Projects Fund, for the purpose of funding the
16 inch to 24 inch Cast Iron Water Mains Replacements in Eastwood and Timberline Elevated Storage Tanks
Project (City Project No. 105070).
SECTION 2.
That should any portion, section or part of section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent j urisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 26453-09-2023 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Dau 1., DEack (j— 24, 2024 16:22 CDT)
Douglas W. Black
Senior Assistant City Attorney
ADOPTED AND EFFECTIVE: June 11, 2024
CITY SECRETARY
A.
Jannette S. Goodall
City Secretary
4gdiunniln�
T
a ;# 0,0 000c, a�
y�Q °o
rOp O 4
Qaa
Woo o° %(c
fAIII��� 0t r
_000 ^C
w �
MAYOR AND COUNCIL COMMUNICATION
60SOUTHEAST CASTIRONWMREP LACE-AECOM
_#lilt iiiir
G ypp _ � '�1�F�)� $��� ! yq� fig` r ■■ yi
MOM
Ito
W1911MIN
INIM
CF 4YE. Cllt !p i�r
si to i'�Rs � IM11:1 V. ®��� °fa A ;!!
IRA yW M . � � l ��I7'{� �1.�Q �
�r
REED
*i�C ;
i.r:+r r.rn
C.• .NCIL �'� ��'
�RIYI iI i.R
COMANCHE
LJ
70
• iieR ~ ye e i
-A
• !
[1�H RDEMAN ST
CHILDRESS ST
r -
• ITA ST
< MECCA ST
TIMBERLINE DR LL
all
EST
rw
R�
�; I■� yyaa'
♦#li
.. .• �r
fmti �.h+ r.. 6 veer „� rasm,rae sit5� 'nut w
It
ia:ysII���r•
�:�����iiii��i� •
• ' iA�:`i�lf�`
91419ip
LITTLEJOHN
AVE.
CAROL AVE
R'rHA AVE
EASTW000
E5T..`
RICHARDON STUJI
or _..
0
W
I
i
a�
t�SSf
EASTLAND ST
QUAIL_J LN
a
c
O'
co Li_
-� U)
w
RE
W
J
S
MOBERL
yi.
PIERCL AVL
FAIRLANF AVE
sr2 mu��.
W
N
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 06/11/24 M&C FILE NUMBER: M&C 24-0514
LOG NAME: 60SOUTHEAST CASTIRONWMREPLACE - AECOM
SUBJECT
(CD 5, CD 8, and CD 11) Authorize Execution of an Engineering Agreement with AECOM Technical Services, Inc, in the Amount of
$1,282,621.00, forthe 16 Inch to 24 Inch Cast Iron Water Main Replacements for Eastwood and Timberline Elevated Storage Tanks
Project and Adopt Appropriation Ordinance to Effect a Portion of Water's Contribution to Fiscal Years 2024-2028 Capital Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of an engineering agreement with AECOM Technical Services, Inc. in the amount of $1,282,621.00, for the 16 inch to 24
inch Cast Iron Water Main Replacements in Eastwood and Timberline Elevated Storage Tanks Project; and
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water and Sewer Capital Projects Fund
in the amount of $1,694,629.00 from available PayGo residuals within the Water and Sewer Capital Projects Fund for the purpose of funding
the 16 inch to 24 inch Cast Iron Water Mains Replacements in Eastwood and Timberline Elevated Storage Tanks Project (City Project
No. 105070) and to effect a portion of Water's contribution to Fiscal Years 2024-2028 Capital Improvement Program.
DISCUSSION:
Replacement of existing cast iron water lines, installed before the general use of concrete cylinder pipe and ductile iron pipe, is a major goal of the
Fort Worth Water Department (FWWD) due to cast iron pipe's excessive break record. The Water Department has routinely replaced cast iron
waterlines as part of water replacementlrehabilitation projects and in support of street bond (street rehabilitation) projects. However, due to the
severe street damage and flooding resulting from large cast iron (16-inch and larger) water main breaks, the department is placing a high priority
on replacement of large diameter cast iron water transmission mains.
This Mayor and Council Communication (M&C) is to authorize the execution of an engineering agreement with AECOM Technical Services, Inc. in
the amount of $1,282,621.00, for the 16 inch to 24 inch Cast Iron Water Main Replacements in Eastwood and Timberline Elevated Storage Tanks
Project for the preparation of plans and specifications for water and sanitary sewer main replacements as indicated on the following streets in the
Southeast area of the City:
Scope
Street
From
To C
of
Work
Timberline
Trueland Drive
Elevated
Lomita Street
Water 1
Sewer
Storage Tank
Timberline Drive
ITrueland Drive
Wichita Street
Water 1 I
Sewer
Knox Avenue f
Erath Street
Shackleford Street
Water
Lomita Street
Trueland Drive
Wichita Street
Water!
Sewer
Wichita Street
Wilbarger
Street
Lomita Street
Water
W ilbarger Street
Wichita Street
Shackleford Street
Water
Sewer
Shackleford
Street
Wilbarger
Street
Collin StreetWater
Collin Street
Shackleford
Street
US HWY287
Water
Ratan Street
lbarger
kStreet
Chickasaw Avenue
Water
Miller Avenue
Forbes Street
Martin Street
Water 1
Sewer
Richardson
Miller Avenue
Pate Avenue
Water
Street
Eastover Avenue
Richardson
Street
South 572feet
Wafer
North
�Easement
of Wiman Street
Miller Avenue
Pate Avenue
Wafer
Easement South
West 435 feet then 372
of Hardeman
Miller Avenue
feet northwest then north
Water
Street
62 feet
Reed Street
Miller Avenue
Pate Drive
Water
In addition to the contract amount, $312,008.00 (Water: $244,708.00; Sewer: $67,300.00) is required for project management, real property
acquisition, utility coordination, and material testing. This project will have no impact on the Water Department's operating budget when completed.
The sewer component of the project is part of the Water Department's Sanitary Sewer Overflow Initiative Program.
It is the practice of the Water Department to appropriate its CIP plan throughout the Fiscal Year (FY), instead of within the annual budget ordinance,
as projects commence, additional funding needs are identified, and to comply with bond covenants. The actions in the M&C will appropriate funds
in support of the Water's portion of the City of Fort Worth's Fiscal Years 2024-2028 Capital, as follows:
60SOUTHEAST CASTIRONWMREPLACE -AECOM
Capital
Fund
Name
Project
Name
FY2024 CiP
Appropriations
Authority
Budget Change
(increase/Decrease)
Revised
FY2024
Budget
105070 -
W&S
16 to
Capital
24in Cl
Projects -
WM Repl.
$0.00
This M&C
$1,594,629.00'
$1,594,629.00
Fund
For EW
56002
and TL
EST
Funding is available in the Unspecified All -Funds project within the Water & Sewer Capital Project Fund for the purpose of funding the 16 inch to
24 inch Cast Iron Water Main Replacements for Eastwood and Timberline Elevated Storage Tanks project.
Appropriations for the 16 inch to 24 inch Cast Iron Water Main Replacements Eastwood and Timberline Elevated Storage Tanks project are as
depicted below:
Fund
Existing
Appropriations
Additional
Appropriations
Project Total•
W&S Capital
Projects - Fund
56002
$0.00
$1,594,629,00
$1,594,629.00
Project Total
$0.0_0�J
$1,594,629.00
$1,594,629.00
Business Equity: AECOM Technical Services, Inc. is in compliance with the City's Business Equity Ordinance by committing to 23.69 percent
MWBE participation on this project. The City's MWBE goal on this project is eight percent.
The project is located in COUNCIL DISTRICTS 5, 8 and 11.
FISCAL INFORMATION 1 CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Unspecified All -Fund project within the W&S Capital Projects Fund, and
upon approval of the above recommendations and adoption of the attached appropriation ordinance, funds will be available in the W&S Capital
Projects Fund for the 16 — 24 in Cl WM Repl for EW & TL EST to support the above recommendations and execution of the engineering
agreement. Prior to any expenditure being incurred, the Water Department has the responsibility of verifying the availability of funds.
Submitted for City Manager's Office bye Fernando Costa 6122
Odminating Business Unit Head: Chris Harder 5020
Additional Information Contacl: Dena Johnson 7866