HomeMy WebLinkAboutOrdinance 26938-06-2024Ordinance No. 26938-06-2024
AN ORDINANCE ADJUSTING APPROPRIATIONS IN THE 2022 BOND
PROGRAM FUND IN THE AMOUNT OF $5,205,321.00, BY INCREASING
APPROPRIATIONS IN THE 2022 BOND YEAR 2 - CONTRACT 9 PROJECT (CITY
PROJECT NO.104242), AND DECREASING APPROPRIATIONS IN THE STREET
IMPROVEMENT -DETERIORATING STREETS PROGRAMMABLE PROJECT
(CITY PROJECT NO. PB0019) BY THE SAME AMOUNT; PROVIDING FOR A
SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF
PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT
HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That the budget of the City of Fort Worth for Fiscal Year 2023-2024, as enacted by Ordinance 26453-09-
2023, as amended, is hereby further amended to make the following adjustments to appropriations in the 2022
Bond Program Fund in the amount of $5,205,321.00, by increasing appropriations in the 2022 Bond Year 2 -
Contract 9 project (City Project no. 104242), and decreasing appropriations in the Street Improvement -
Deteriorating Streets programmable project (City Project No. P130019 ) by the same amount.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 26453-09-2023 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Douglas Black (lmi 24. 202416:13 CDT)
Assistant City Attorney
ADOPTED AND EFFECTIVE: June 11, 2024
CITY SECRETARY
Jannette S. Goodall
City Secretary
Mayor & Council Map I CPN #104242 FORT WORTH.
2022 Bond YR2 Contract 9
Neighborhood Streets CD #8, 11
.. FIf-�
M IA
287
� � � fe �.,.,� ram.. � .. 4 i - _ / g-, • -. �c ��� a,S'I..i I
` f' •� ky a��� d�
if •r'� : �� _ � .. � -+
MOM,
r
� l
J r .:cjj- • '1 r {j
�> � •, 'Y' �.�i _a `����i- �4 - � ���4;� �a.�sj� �i �4a 54'.
"
�•��T17
t�Mttr.
�+ Q {
J1i��� ;. asax t 'rFs`�T• i ry _
} 3 2F L I
RE ri- WE
MAP ID STREET FROM TO
1 Burton Ave Wesle an Dr 5 Binkle St • yS 1rr ti y„ 1 .x,tt
? 2 Davis Ave E AdxonaAve LouislanaAve"-
3 _ _ Davis Ave, E !a Ave
4 Glencrest Dr Old Mansfield Rd as me Dr ,.� �'� � r� - +► -1'
S s Gulch fairwa Dr Tm6edlne Dr-
6 Kell is St, E Parts St Nolan St��-
7 Kell is St, E Nolan St Fawfaa Ave _rqs`!+• L r - a._. �' - -- - - '
a Nolan 5t E Kellis St Seminary Dr-
9 Paris St E %elks St Mansfield Hwy
- -
ll: 5emina Dr, E Paris St E Dead End
11 u Seminary Dr E 1Nlchita St Paris St�•
Y0 9
rJN1$Ou1u_Cra,GIS, Nv.•mv EMp/ercr.tM Fell aJx. N S
mwarMn, Acow. SaNa. - 1
�n•:W.r w+.+sa a�Kww...���.e.ar. w'�'c..� ��..�s �� i_ ", 1V)
City of Fort worth,
Mayor and
Texas
Council Communication
DATE: 06/11/24 M&C FILE NUMBER: M&C 24-0478
LOG NAME: 202022 BOND YEAR 2 CONTRACT 9 - STABILE
SUBJECT
(CD 8 and CD 11) Authorize Execution of a Contract with Stabile & Winn, Inc., in the Amount of $8,822,307.25, for Combined Street Paving
Improvements, Water and Sanitary Sewer Main Replacements for 2022 Bond Year 2 - Contract 9 Project, Adopt Appropriation Ordinances to
Effect a Portion of Water's Contribution to Fiscal Years 2024-2028 Capital Improvement Program, and Amend the Fiscal Years 2024-2028 Capital
Improvement Program (2022 Bond Program)
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of a contract with Stabile & Winn, Inc., in the amount of $8,822,307.25 for combined street paving improvements in
addition to water and sanitary sewer main replacements for the 2022 Bond Year 2 - Contract 9 project (City Project No. 104242);
2. Adopt the attached appropriation ordinance increasing esfimated receipts and appropriations in the Water and Sewer Capital Projects Fund
in the amount of $4,895,855.00, from available PayGo residuals within the Water and Sewer Capital Projects Fund, for the purpose of
funding the 2022 Bond Year 2- Contract 9 project (City Project No. 104242) to effect a portion of Water's Contribution to the Fiscal Years
2024-2028 Capital Improvement Program;
3. Adopt the attached appropriation ordinance adjusting appropriations in the 2022 Bond Program Fund in the amount of $5,205,321.00, by
increasing appropriations in the 2022 Bond Year 2 - Contract 9 project (City Project No. 104242), and decreasing appropriations in the
Street Improvement -Deteriorating Streets programmable project (City Project No. PB0019) by the same amount; and
4. Amend the Transportation & Public Works Contribution to the Fiscal Years 2024-2028 Capital Improvement Program.
DISCUSSION:
This Mayor and Council Communication (M&C) is to authorize a construction contract for the Year 2 Neighborhood Streets Improvements project
associated with the 2022 Bond Program. For 2022 Bond Year 2 - Contract 9 project, this includes water, sanitary sewer and street paving
improvements on approximately 4.02 lane miles, on the following streets:
Street
From
To
Scope
Burton Avenue
S. Wesleyan Drive
Binkley Street
Water/Paving
E. Davis Avenue
Arizona Avenue
Louisiana Avenue
WaterlPaving
Glencrest Drive
Old Mansfeld Road
Eastline Drive
WaterlSewerlPaving
E. Kellis Street
Paris Street
Nolan Street
Water/Paving
Paris Street
E. Seminary Drive
E. Kellis Street
Paris Street
=Mansfieldighway
E. Dead End ��WaterlPaving
Water/Paving
Gypsy Gulch Street*
Fairway Drive
Timberline Drive
Sewer
E. Davis Avenue*
Epps Drive
Arizona Avenue
Water
E. Kellis Street*
Nolan Street ��Fairlbx
Avenue
Water
Nolan Street*
Kellis Street
Seminary Drive
Water
i
. Seminary Drive* JJWichita Street JJParis Street
*Due to the close proximity to the 2022 Bond Year 2 Contract 9 project streets above, the Water Department requested that water main extensions
on these streets be included in order to loop the water system and provide increased efficiency. Asphalt paving rehabilitation will be conducted on
the indicated streets subsequent to the water main installation.
The project was advertised for bid on March 14th and March 21 st, 2024 in the Fort Worth Star -Telegram. On April 11 th, 2024 the following bids
were received:
Bidder
Amount
Time of
Completion
Base Bid** (Concrete
Alternate A (Asphalt
Paving)
Paving)
Stabile & Winn, Inc.
$8,822,307.25
$8,959,786.50
Calendar
40 Days
McClendon Construction Company
Inc
$9,016,320.60
$9,046,673.00
Jackson Construction, LTD
$9,474,091.00
$9,109,594.50
**In an attempt to secure alternate bids, staff advertised the project with concrete as the base bid to reconstruct existing streets included in the
bond with concrete travel lanes. Alternative A was bid as a rehabilitation of existing roadway with new asphalt and replacement of damaged curb
and gutter. Staff recommends award of the contract for the base bid (Concrete Option). Concrete paving typically has a twenty-year life span, while
asphalt paving has a ten-year span. In addition, the maintenance cost of concrete pavement is typically less than asphalt pavement.
The Transportation & Public Works (TPW) Department share of this contract is $4,504,877.75. The paving funds for this project are included in the
2022 Bond Program. The Water Department share of this contract is $4,317,429.50 and will be available in the Water & Sewer Capital Projects
Fund for the project (City Project No. 104242). In addition to the contract amount, $837,754.50 (water. $258,133.50, sewer: $104,421.00, and
paving: $475,200.00) is required for project management, material testing, and inspection and $441,114.25 (water $169,400.00, sewer.
$46,471.00, and paving: $225,243.25) is provided for project contingencies.
This project will have no impact on the operating budgets of the TPW Department or the Water Department when completed. The sanitary sewer
component of this project is part of the Sanitary Sewer Overflow Initiative Program of the Water Department. Approximately 8,474 linear feet of
cast iron water pipe will be removed and replaced as part of this project.
The action in this M&C will amend TPWs contribution to the Fiscal Years 2024-2028 Capital Improvement Program as follows:
I
Revised
Capital Fund
Project Name
Existing
Budget Change
FY2024
Name
Appropriations
Increase/Decrease
_
Budget
2022 Bond
Street Imprv-
Program - Fund
Deteriorating Sts-
$48,059,424.00
($5,205,321.00)
$42,854,103.00
34027
PB0019
It is the practice of the Water Department to appropriate its CIP plan throughout the Fiscal Year, instead of within the annual budget ordinance, as
projects commence, additional funding needs are identified, and to comply with bond covenants. The actions in the M&C will appropriate funds in
support of the Water Department's portion of the City of Fort Worth's Fiscal years 2024-2028 Capital Improvement Program, as follows:
2022 Bond Year 2 Contract 9 - Stabile
Revised
Capital Fund
Project Name
FY2024
Authority
Change
EIncreasel
FY2024
Name
Appropriations
Decrease
Budget
W&S Capital
Projects - Fund
56002
104242 - 2022
Bond Year2 -
Contract 9
$0.00
This M&C
$4,895,855.00
$4,895,855.00
11
Funding is currently available in the Unspecified All -Funds project within the Water & Sewer Capital Projects Fund for the purpose of funding the
2022 Bond Year 2 - Contract 9 project. Funding is also budgeted in the 2022 Bond Program Fund in the Street Improvement -Deteriorating Streets
programmable project.
Appropriations for the water, sanitary sewer, and paving improvements for 2022 Bond Year 2 - Contract 9 project by Fund will consist of the
following:
Existing
Additional
Fund
Appropriations
Appropriations
Project Total'
2022 Bond Program - Fund
$418,002.00
$5,205,321.00
$5,623,323.00
34027
W&S Capital Projects - Fund
$321,625.00
$4,895,855.00
$5,217,480.00
56002
Project Total
1.$739,627.0011
$10,101,176.00
$10,840,803.00
'Numbers rounded for presentation purposes.
Business Equity: Stabile & Winn, Inc. is in compliance with the City's Business Equity Ordinance by committing to 3.04% Business Equity
participation and documenting a good faith effort. Stabile & Winn, Inc. identified several subcontracting and supplier opportunities. However, the
firms contacted in the areas identified did not respond or did not submit the lowest bids. The City's Business Equity goal on this project is 18%.
This project is included in the 2022 Bond Program. The City's Extendable Commercial Paper (ECP) (M&C 22-0607; Ordinance 25765-08-2022)
provided liquidity to support the appropriation. Available resources will be used to actually make any interim progress payments until debt is
issued. Once debt associated with a project is sold, debt proceeds will reimburse the interim financing source in accordance with the statement
expressing official Intent to Reimburse that was adopted as part of the ordinance canvassing the bond election (Ordinance 25515-05-2022).
This project is located in COUNCIL DISTRICTS 8 AND 11.
FISCAL INFORMATION ! CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Street Imprv-DeterioratingSts programmable project within the 2022 Bond
Program Fund and in Unspecified All -Funds project within the W&S Capital Project Funds and upon the approval of the above recommendations
and adoption of the attached appropriation ordinances, funds will be available in the W&S Capital Projects Fund and 2022 Bond Program Fund
for the 2022 Bond Yr 2 - Contract 9 project to support the above recommendations and execution of the construction contract. Prior to any
expenditure being incurred, the Transportation & Public Works and Water Departments have the responsibility of verifying the availability of funds.
Submitted for Cily Manager's Office b . Jesica McEachern 5804
Originating Business Unit Head: Lauren Prieur 6035
Additional Information Contact:, Monty Hall 8662