HomeMy WebLinkAboutResolution 5973-06-2024A Resolution
NO.5973-06-2024
STATEMENT EXPRESSING
OFFICIAL INTENT TO REIMBURSE
EXPENDITURES WITH PROCEEDS OF FUTURE DEBT FOR THE AVONDALE HASLET
ROAD PROJECT
WHEREAS, the City of Fort Worth, Texas (the "City") is a home -rule municipality and
political subdivision of the State of Texas; and
WHEREAS, the City expects to pay expenditures in connection with the design, planning,
acquisition and construction for the Avondale Haslet Road Project (the "Project") prior to the
issuance of obligations by the City in connection with the financing of the Project from available
funds; and
WHEREAS, the City finds, considers, and declares that the reimbursement of the City for the
payment of such expenditures will be appropriate and consistent with the lawful objectives of the
City and, as such, chooses to declare its intention, in accordance with the provisions of Section 1.150-
2 of the Treasury Regulations, to reimburse itself for such payments at such time as it issues
obligations to finance the Project;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF FORT WORTH, TEXAS, THAT:
Section 1. The City reasonably expects debt, as one or more series of obligations, may
be issued or incurred by the City with an aggregate maximum principal amount not to exceed
$275,000.00 for the purpose of paying the aggregate costs of the Project.
Section 2. All costs to be reimbursed pursuant hereto will be capital expenditures. No
obligations will be issued by the City in furtherance of this Statement after a date which is later than
18 months after the later of (1) the date the expenditures are paid or (2) the date on which the
property, with respect to which such expenditures were made, is placed in service.
Section 3. The foregoing notwithstanding, no obligation will be issued pursuant to this
Statement more than three years after the date any expenditure which is to be reimbursed is paid.
ADOPTED this 25t' day of June, 2024.
ATTEST:
Jannette S. Goodall, City Secretary
�.44��nan
100000
0
d®° o
os
Q1 0
Iro 0*0
0 a
a�
000 0°0 a * 0...".0� yAc
a�aan TEx4�4
MAYOR AND COUNCIL COMMUNICATION
60AVO N DA L E H ROAD36I N W M-H D R
\ 9A
)RTHt,
mm
A • ' A • • •
MIL
7f}lilllll '
i",1! filler ~
ott an ur! :°af
w.' ali ill%FEurlluai aFa . y'i1E"
JI
SON
Aam
Ni
• t �w jlfU P.`y� �, ..i .� I
�► ♦Irr F
D.ISIIiRlI,�i' - 10 ,IiFJII]�jr �`
r� l•kri/11w�.� +Y+h
lke~i�t�dirtiil7l,eb�
00 '*f1lRi 0
rr1�
rrr
• • 4 ����SR�7si !� ,
k = � • • 116n�ea!!ir�id +aR�e�.ti`,It�tlldW�
5���tl
City of Fort Worth,
Mayor and
Texas
Council Communication
DATE: 06/25/24 M&C FILE NUMBER: M&C 24-0599
LOG NAME: 60AVONDALEHROAD36INWM-HDR
SUBJECT
(CD 10) Authorize Execution of an Engineering Agreement with HDR Engineering, Inc. in the Amount of $157,602.00 for Design of the Avondale
Haslet Road Installation Project, Adopt Resolution Expressing Official Intent to Reimburse Expenditures and Proceeds of Future Debt and Adopt
Appropriation Ordinance to Effect a Portion of Water's Contribution to the Fiscal Years 2024-2028 Capital Improvement Program
RECOMMENDATION:
1. Authorize execution of an Engineering Agreement with HDR Engineering, Inc. in the amount of $157,602.00 for the design of the Avondale
Haslet Road Projects 36-inch water main installation;
2. Adopt the attached resolution expressing official intent to reimburse expenditures with proceeds of future debt for the design of the Avondale
Haslet Road Projecfs 36-inch water main installation; and
3. Adopt the attached appropriation ordinance adjusting appropriations in the Water & Sewer Commercial Paper Fund by increasing
appropriations in the Avondale Haslet Road project (City Project No.101014) in the amount of $228,346.00 and decreasing appropriations
in the W&S Commercial Paper project (City Project No. UCMLPR) by the same amount, to effect a portion of Waters contribution to the
Fiscal Years 2024-2028 Capital Improvement Program.
DISCUSSION:
This Mayor and Council Communication (M&C) is to authorize the preparation of plans and specifications for the construction of the Avondale
Haslet Road project's 36-inch water main installation from Sendera Ranch Boulevard to 3,350 linear feet east to facilitate the reconstruction of
Avondale Haslet Road to a four -lane divided roadway in accordance with the current Master Thoroughfare Plan (MTP).
The proposed scope of services include design for the transmission main and construction phase services. HDR Engineering, Inc. proposes to
provide the necessary services for a fee not to exceed $157,602.00. Staff considers the proposed fee to be fair and reasonable for the scope of
services proposed.
In addition to the contract amount, $70,744.00 is required for project management and material testing. This project is anticipated to be included in
a future revenue bond issue for the Water & Sewer Fund.
Available cash within the Water and Sewer portfolio and the City's portfolio along with the appropriation authority authorized under the callable
Commercial Paper Program (CP) will be used to provide interim financing for this project until debt is issued. Once debt associated with this
project is sold, bond proceeds will be used to reimburse the Water and Sewer portfolio and the City's portfolio in accordance with the attached
Reimbursement Resolution. Under federal law, debt must be issued within approximately three years in order for these expenses to be
reimbursable. Adoption of the attached resolution does not obligate the City to sell bonds, but preserves the ability to reimburse itself from tax-
exempt bond proceeds.
It is the practice of the Water Department to appropriate its CIP plan throughout the Fiscal Year (FY), instead of within the annual budget ordinance,
as projects commence, additional funding needs are identified, and to comply with bond covenants. The actions in the M&C will appropriate funds
in support of the Water's portion of the City of Fort Worth's Fiscal Years 2024-2028 Capital Improvement Program.
Funding for the Design of the Avondale Haslet Road projects 36-inch Water Main Installation is depicted below:
60AVONDALEHROAD36INWM-HDR
Budget
Capital Fund
Project Name
FY2024 CIP
Authority
Change
Revised
Y
Namo
Appropriations
(increase/
- Budget
B
Decrease)
56023 --
W&S Commercial
Paper Fund
101014
Avondale Haslet
Road
$0.00
!!n
$228,346.00
$228,346.00
Funding will be budgeted in the W&S Commercial Paper project within the W&S Commercial Paper Fund for the purpose of funding the Avondale
Haslet Road projecf's 36-inch water main installation after the sale of Water and Sewer Bonds.
Funding for the design of Avondale Haslet Road project's 36-inch water main installation is depicted below:
Existing
Fund
Ap tons
Additional Appropriations
Project Total*
2018 Bond
Program
$3,434,404.00
$0.00
$3,434,404.00
Fund
F
$0 00
$228,346.00
$228,346.
Project
Total J
$3,434,404.001
$228,346.00
$3,662,750.00
I
*Numbers rounded for presentation purposes.
Business Equity: HDR Engineering, Inc., is in compliance with City's Business Equity Ordinance by committing to 16.13 percent MWBE
participation on this project. The City's MWBE goal on this project is 13 percent.
The project is located in COUNCIL DISTRICT 10.
FISCAL, INFORMATION I CERTIFICATION:
The Director of Finance certifies that funds will be available after the sale of the Water and Sewer Bonds in the Commercial Paper project within
the W&S Commercial Paper Fund and upon approval of the above recommendations and adoption of the attached appropriation ordinance, funds
will be available in the W&S Commercial Paper Fund for the Avondale Haslet Road project to support the above recommendations and execution
of the contract. Prior to an expenditure being incurred, the Water Department has the responsibility of verifying the availability of funds.
Submitted
for City Manager's Office h .
Femando Costa
6122
Originating
Business Unit Head:
Chris Harder
5020
Additional Information Contact: Preeti KC 5467
Expedited