Change Order Request
Project Name:I Village Creek WRF Digester Mixing, Flare, Dome Improvements Phase 1 I City Sec No.:I � =5=8 =68=3=========:
Project No.(s):I 56021/0700430/5740010/001780 M&C: I 22-1046 I City Proj. No.: �I _1_02_6_52 ___ __,
Project Description: Digester mixing, flare, and dome improvements, new digeseter gas dryers, and new hydrogen sulfide scrubbers.
Contractor:! Eagle Contracting, LLC �-================-.----------'
City Project Mgr.I Suzy Abbe
Change Order# l.___3 _ _.Date:
::=============: Phone Number:I 817-392-8209
City Inspector: I Kevin Sidebottom
Phone Number:! 817-874-9330
Dept. Sewer
Original Contract Amount $39,773,000.00
Extras to Date $315,341.00
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date $40,088,341.00
!Amount of Proposed Change Order $96,293.00
Revised Contract Amount $40,184,634.00
Original Funds Available for Change Orders $318,184.00
Remaining Funds Available for this CO $305,064.00
Additional Funding (if necessary)
' ,, J '" "'-"L.� --.tlli�
:ij_�□
•·::;q�.r::
�-;r;;
,;..,�?!,;...,'!:(
\
... - � -r-' � -
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS% OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Totals
$39,773,000.00
$315,341.00
$40,088,341.00
$96,293.00
$40,184,634.00
$318,184.00
$305,064.00
7/1/2024
Contract Time
(Calender days)
1,095
!,:Gu'i'.;/1
� � "q
'\ -�'
1 095
12.ili:'j;:!!3
1 095
Change Order No. 3 will provide for low pressure digester gas bypass piping that will redirect digester gas to the existing flares while the tie-in
to the new flares is performed. The bypass will eliminate the need for an extended full solids shut down at the Village Creek Water
Reclamation Facility and will minimize the release of digester gas into the atmosphere, improving safety and reducing the risk of a process
upset during the tie-in to the new flares. Staff concurs with the Contractors request to add 35 calendar days to Milestone 1 for the time
needed to develop a bypass plan, procure materials, and install the bypass ahead of the tie-in.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
\licklr Ograntes
Date
7/2/24 7/2/2024
Date Date
ul3,2024 7/2/24
Senior Assistant c· Attome Date Date
Jul 9, 2024 Jul 9, 2024
uired
M&C Number N/A M&C Date Approved NIA
FC� P T WC) RT H City of Fort Worth
�`'''' Change Order Additions
Project Name Village Creek WRF Digester Mixing, Flare, Dome Improvements Phase 1 City Sec No.: 58683
Project No.(s): 56021/0700430/5740010/001780 DOE No. 22-104 City Proj. No.: 102652
Project
Description
Digester mixing, flare, and dome improvements, new digeseter gas dryers, and new hydrogen sulfide scrubbers.
Contractor Eagle Contracting, LLC Change Order:�3 Date: 711/2024
City Project Mgr. Suzy Abbe City Inspector Kevin Sidebottom
ADDITIONS
�� ' . ' ' � ������
� • � � � : �. � ����,., . 1� ',�. • ��
_ --_--
_ --_--
'_ --_--
_ --�--
_ --_--
_ --_--
_ --_--
_ --_--
� --_--
_ --�--
_ --_--
_ --_--
_ --_--
_ --_--
_ --_--
_ --_--
_ --_--
_ --_--
_ --_--
_ --_--
_ --_--
_ --_--
� --_--
' �. � ��
�- -
. , � -
��� • � � . '��. � ��
FC� RT WC� RT H City of Fort Worth
Change Order Deletions
Project Name Village Creek WRF Digester Mixing, Flare, Dome Improvements Phase 1 City Sec No.: 58683
Project No.(s): 5602110700430/5740010/001780 DOE No. 22-10 City Proj. No.: 102652
Project Description
Digester mixing, flare, and dome improvements, new digeseter gas dryers, and new hydrogen sulfide scrubbers.
Contractor Eagle Contracting, LLC Change Order: �3 Date 7/112024
City Project Mgr. Suzy Abbe City Inspector: Kevin Sidebottom
DELETIONS
Page 1 of 1
MIWBE Breakdown for this Change Order
6/27/2024
CPN 102652
Digester Mixing, Flare, Dome Improvements Phase 1
Chan�e Order 3 Notes
The existing isolation valves on the low-pressure digester gas piping system do not allow tie-ins to the
new flares to be performed without releasing large volumes of digester gas into the atmosphere.
Options to reduce the release of digester gas were explored, including temporary partial and full solids
shut downs to reduce gas production. However, it was determined that the combined risks posed by
both the solids shut down (from a process standpoint) and releasing large volumes of digester gas (from
a safety standpoint) were unacceptable. The consultant proposed a plan to utilize temporary bypass
piping to direct digester gas to the existing flares while allowing the tie-in to the new flares to take
place. Installation of the bypass piping can take place with minimal gas release and no solids shut down.
Labor hours, material costs, and quantities in the contractors' proposal were reviewed, and the City
finds them to be fair and reasonable. The approved CMR (CMR-29) is saved in E-builder.
The contractor is asking for 35 days be added to Milestone 1 for the time needed to develop the bypass
plan, procure the materials, and install the bypass piping. The City agrees to the additional time.
Signature:
.Contract Compliance Manager
By signing I aclmowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Suzanne Abbe
Name of Employee
Senior Engineer, Capital Project Delivery
Title