HomeMy WebLinkAboutContract 43923-A7City of Fort Worth, Texas Little Fossil Creek Interceptor Improvements
Prof Services Agreement Amendment Template CPN: 1960
Revision Date: 12/08/2023
Page 1 of 2
AMENDMENT No.7
TO CITY SECRETARY CONTRACT No. 43923
WHEREAS, the City of Fort Worth (CITY) and Parsons Water & Infrastructure,
(ENGINEER) made and entered into City Secretary Contract No. 43923, (the CONTRACT)
which was authorized by M&C C-25877 on the 25th day of September, 2012 in the
amount of $391,453.00; and
WHEREAS, the CONTRACT was subsequently revised by: Amendment No. 1 in the
amount of $206,797.00 authorized by M&C C-26229 on 7th day of May, 2013, Amendment
No. 2 in the amount of $43,929.00 which was administratively authorized on 1st
day of May, 2015, Amendment No. 3 in the amount of $52,133.00 which was
administratively authorized on the 25th day of March, 2019, Amendment No. 4 in
the amount of $145,919.00 which was authorized by M&C 19-0379 on the 10th day of
December, 2019, Amendment No. 5 in the amount of $209,281.00 which was authorized
by M&C 21-0920 on the 30th day of November, 2021 and Amendment No. 6 in the amount
of $35,190.00 which was administratively authorized on the 30th day of August,
2022; and
WHEREAS, the CONTRACT involves engineering services for the following
project:
Little Fossil Creek Interceptor Improvements at Various Locations within
the Little Fossil Creek Drainage Basin, CPN 1960; and
WHEREAS, it has become necessary to execute Amendment No. 7 to the CONTRACT
to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their duly
authorized representatives, enter into the following agreement, which amends the
CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional engineering
services specified in proposal attached hereto and incorporated herein. The cost
to City for the additional design services to be performed by Engineer totals
$44,500.00.
2.
Article II of the CONTRACT is amended to provide for an increase in the fee
to be paid to Engineer for all work and services performed under the Contract, as
amended, so that the total fee paid by the City for all work and services shall
be an amount of $1,129,202.00.
3.
All other provisions of the Contract, which are not expressly amended herein,
shall remain in full force and effect.
City of Fort Worth, Texas Little Fossil Creek Interceptor Improvements
Prof Services Agreement Amendment Template CPN: 1960
Revision Date: 12/08/2023
Page 2 of 2
EXECUTED and EFFECTIVE as of the date subscribed by the City’s
designated Assistant City Manager.
APPROVED:
City of Fort Worth ENGINEER
Parsons Water & Infrastructure
Fernando Costa
Assistant City Manager
DATE: _______________
Amit Sengupta, P.E.
Vice President
DATE: _________________
ATTEST:
Jannette Goodall
City Secretary
APPROVAL RECOMMENDED:
Christopher Harder, P.E.
Director,Water Department
Contract Compliance Manager:
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring all
performance and reporting requirements.
_______________________________
Walter Norwood, P.E.
Project Manager
APPROVED AS TO FORM AND LEGALITY:M&C No.#: ______N/A__________
M&C Date: _______N/A _________
Douglas W. Black
Sr. Assistant City Attorney Form 1295: ______N/A__________
Walter Norwood, P.E.
1301 West President George Bush Highway, Suite 350 | Richardson, TX 75080
P: +1 972.244.6000 | F: +1 972.244.6077 | www.parsons.com
April 26, 2024
Walter Norwood, P.E.
Senior Professional Engineer
City of Fort Worth Water Department
200 Texas Street
Fort Worth, Texas 76102
Subject: Revised request for Amendment 7 for Additional Level of Effort (LOE) for Little Fossil
Creek Interceptor Rehabilitation Project Part 2A Locations 1, 3, and 5A Additional
Easements for Location 1
Dear Walter,
This letter represents a request from Parsons Water & Infrastructure Group, Inc. (Parsons) to the City
of Fort Worth Water Department for Amendment 7 for the increased level of effort (LOE) to add
additional temporary construction easements for Location 1.
Background
The project is well documented in previous letters and proposals by Parsons over the 12 years since
project inception, most recently in Amendment 6 documents processed in August 2022. Parsons is
currently in the latter stages of Amendment 6, focused on finalizing the construction drawings and
specifications for the remaining items of the Little Fossil Creek interceptor, especially the solar-
powered meter design for Location 3.
This amendment originates from a decision to add temporary construction easements for reaches of
Location 1. Location 1 was originally contemplated to be performed as rehabilitation. For
Amendment 5, the scope of the pipeline design was changed to completely reconstruct the pipeline,
mostly via conventional cut-and-cover trenching. To facilitate Contractor construction activities, we are
adding 25 ft-wide temporary construction easements parallel to the existing right-of-way where the
pipe will be constructed.
Project Approach
Most of the work will be performed by our subcontracted surveying firm, Gorrondona, a registered
MWBE. Their proposal is attached. They have identified 16 separate TCE documents to be prepared.
We are adding two more to remain conservative in case they discover more while performing the work.
Additional hours are proposed for Parsons for engineering and administration, for the following tasks:
Incorporate depictions of the easements into the design plan & profile drawings
Develop the easement scheme
Managing the subcontractor, including administrative hours for amended subcontracts
Walter Norwood, P.E.
City of Fort Worth Water Department
June 30, 2022
2
Bypass pumping scheme meetings and preliminary design
Management and MWBE reporting for the extended time for this project.
The work products for this amendment are the modification of drawings and production of easement
documents to be submitted to the Citys real estate department. The easements include those along
the pipeline, as well as others required on private property to route the proposed temporary bypass
pumping pipeline generally running down the unnamed water course west of the pipeline.
Budget and Schedule
The Level of Effort Estimate for this task (Attachment 1) spreadsheet details the level of effort required
to perform the complete the design and incorporate it into the existing design package currently under
development.
The following table provides a summary of the contract amounts to date:
Original LOE $391,453
Amendment No. 1 $206,797
Amendment No. 2 $43,929
Amendment No. 3 $52,133
Amendment No. 4 $145,919
Amendment No. 5 $209,281
Amendment No. 6 $35,190
Amendment No.7 $44,500
Total LOE with Amendments 1 through 7 $1,129,202
A revised overall project schedule will be provided immediately upon acceptance of this proposal. We
anticipate 4 weeks to produce the temporary construction easement documents.
With this amendment, the M/WBE participation of the Contract calculates to 2 4.9%, beyond our
project goal of 22%.
Should you have any questions, please dont hesitate to contact me at 713-871-7429.
Sincerely,
Thomas P. Wilshusen, P.E.
Project Manager
Attachment 1 .
Attachment 2
Subconsultant Proposal
Gorrondona & Associates, Inc.
Page 1 of 2
2800 NE Loop 820, Suite 660 Fort Worth, Texas 76137 817.496.1424 Fax 817.496.1768
Texas Surveying Firm Registration No. 10106900
March 26, 2024
PARSONS
4500 Mercantile Plaza Drive
Fort Worth, Texas 76137
Attn: Tom Wilshusen, P.E.
Re: City of Fort Worth Little Fossil Creek Sanitary Sewer
Dear Mr. Wilshusen:
Gorrondona & Associates, Inc. (G&AI) is pleased to submit this proposal for professional land
surveying services for the above referenced project. The following itemized surveying services
are to be provided by Gorrondona & Associates, Inc.:
I. Segment 1 Easement Services
a.) Prepare a metes and bounds description with exhibit for sixteen (16) temporary
construction easements (as shown on the attached Exhibit A) to City of Fort Worth
standards. Easements will be invoiced at a unit rate of $1,500.00 per easement.
Gorrondona & Associates, Inc. can complete the above itemized surveying tasks for a unit
rate fee of $24,000.00. If you have any questions or need additional information, please
contact me at 817-496-1424.
Sincerely,
GORRONDONA & ASSOCIATES, INC.
Richard Kennedy, RPLS
Senior Project Manager
Page 2 of 2
Exhibit A