HomeMy WebLinkAboutContract 58659-CO1DocuSign Envelope ID: E8254C17-6E58-441A-8ECE-16BBBE8FE5BC
FORT WORTH City of Fort Worth
Change Order Request
CSC No. 58659-COl -.
Project Name:I Marine Creek Interceptor M-279A & M-365 Improvements Phase II Part II City Sec No.: I 58659 :::· ============:::: Project No.(s):I 56021-0700430-5740010-1780 DOE No. �N_/_A __ � City Proj. No.: �I _1_00_2_7 4_-_2 __ �
Project Description: Install 42 Inch Dia. Sewer Transmission Main
Contractor: I McKee Utility Contractors, LLC
City Project Mgr.I Walter Norwood
Phone Number: I 817-392-5026
Dept. Sewer
Original Contract Amount $4,650,000.00 Extras to Date
Credits to Date .,
Pending Change Orders (in M&C Process)
Contract Cost to Date $4,650,000.00
!Amount of Proposed Change Order $0.00
Revised Contract Amount $4,650,000.00 Original Funds Available for Change Orders $209,250.00 Remaining Funds Available for this CO $209,250.00
Additional Funding {if necessary)
"
-
u-
Change Order# .___ _ ____.Date:
-
City Inspector: Carmen Drake
Phone Number:! 817-392-8347
Totals
$4,650,000.00
-
-� $4,650,000.00
$0.00
$4,650,000.00 -$209,250.00 " $209,250.00
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS% OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
0.00%
$5,812,500.00
JUSTIFICATION (REASONS) FOR CHANGE ORDER
7/2/2024
Contract Time
(Calender days)
360
�
360
030
390
Change Order No. 1 provides for lowering a manhole to match the parking lot elevation. The parking lot serves a Tarrant Regional Water
District (TRWD) boat ramp. Subsequent to installation of the sewer main on Marine Creek Lake, TRWD requested that the restored gravel
parking lot surface be lowered by four feet to allow for reconstruction of the parking lot with concrete to provide an ADA accessible boat ramp.
Staff concurs with the addition of 30 calendar days for this change order.
II is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Contractor's Com an Name Contractor Name Contractor Si nature Contractors, LLC Tyler McKee
Date
Jul 11, 2024 -,:--.,..i.e...._.
Council Action If Required
M&C Number N/A M&C Date Approved
DocuSign Envelope ID: E8254C17-6E58-441A-8ECE-16BBBE8FE5BC
FORT WORTH City of Fort Worth
Change Order Additions
Project Name Marine Creek Interceptor M-279A & M-365 Improvements Phase II Part II City Sec No.: 58659
Project No.(s): 56021-0700430-5740010-1780 DOE No. N/A City Proj. No.: 100274-2
Project
Description
Install 42 Inch Dia. Sewer Transmission Main
Contractor McKee Utility Contractors, LLC Change Order� Date: 712/2024
City Project Mgr. Walter Norwood City Inspector Carmen Drake
ADDITIONS
DEPT Q Unit Unit Cost Total
46 Epoxy Manhole Liner (4' & 5' MH's) Sewer 5.00 VF $350.00 $1,750.00
48 Adjust 5' Dia. Concrete Manhole Sewer 1.00 EA $14,500.00 $14,500.00
49 Mobilization Sewer 1.00 LS $13,250.00 $13,250.00
Sewer $29,500.00
Page 1 of 1 Additions Sub Total $29,500.00
DocuSign Envelope ID: E8254C17-6E58-441A-8ECE-16BBBE8FE5BC
FORT WORTH City of Fort Worth
Change Order Deletions
Project Name Marine Creek Interceptor M-279A & M-365 Improvements Phase II Part II
Project No.(s): 56021-0700430-5740010-1780 DOE No. N/A
Project Description
City Sec No.
City Proj. No.:
58659
100274-2
Install 42 Inch Dia. Sewer Transmission Main
Contractor McKee Utility Contractors, LLC Change Order: �1 Date 7/2I2024
City Project Mgr. Walter Norwood City Inspector: Carmen Drake
DELETIONS
Page 4 of 4
6/13/2024
Marine Creek Interceptor M-279A & M-365 Phase 2, Part II
CSC: 58659
CPN: 100274-2
Change Order 1 Notes
Staff has reviewed the requested prices and addition to calendar days and considers
them to be fair and reasonable.
Signature:
Email:
.Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Walter Norwood
Name of Employee
Project Manager
Title
ATTEST:
Jannette Goodall
City Sec re ta ry