HomeMy WebLinkAboutContract 61249-PM1CSC No. 61249-PM1
FART WORTH
PROJECT MANUAL
FOR
THE CONSTRUCTION OF
Public Paving Improvements
To Serve
UPS Staging — Liberty Connection
IPRC Record No. IPRC23-0188
City Project No.105301
FID No.30114-0200431-105301-EO7685
File No. K-3227
Mattie Parker David Cooke
Mayor City Manager
Christopher Harder, P.E.
Director, Water Department
Lauren Prieur, P.E.
Director, Transportation and Public Works Department
Prepared for
The City of Fort Worth
December 2023
Prepared by:
Kimley)))Horn
Texas Registered Engineering Firm F-928
Kimley-Horn No. 067785911
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
M
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 1 of 6
SECTION 00 0010
TABLE OF CONTENTS
DEVELOPER AWARDED PROJECTS
Division 00 - General Conditions
nn� rfwit tief to Bid efs
Last Revised
03 tv�r20/2020
00 41 00
00 42 43
nn�
Bid Fe
Proposal Form Unit Price
Bid Bon
nn to 4
05/22/2019
nn in4
nn�
00 45 12
Bidders n-o,,, alifieatio '
Prequalification Statement
nn/n 4
09/01/2015
nn�
Bidder nro,,, alit ,.atie,, ,Wlioatian
03 in 0
00 45 26
Contractor Compliance with Workers' Compensation Law
04/02/2014
i
00 45 40
00 52 43
Minority Business Enterprise Goal
Agreement
04 8
06/16/2016
00 61 25
Certificate of Insurance
07/01/2011
00 62 13
Performance Bond
01/31/2012
00 62 14
Payment Bond
01/31/2012
00 62 19
Maintenance Bond
01/31/2012
i i ii
00 72 00
00 73 00
General Conditions
f/app"o-1entafy r,,,-.dideffi
T
07/n�11
0073 10
Standard City Conditions of the Construction Contract for Developer
01/10/2013
Awarded Projects
Division 01 - General Requirements
Last Revised
01 1100
Summary of Work
12/20/2012
01 2500
Substitution Procedures
08/30/2013
01 31 19
Preconstruction Meeting
08/30/2013
013120
P!OotAileeiings
07/01/2011
01 3233
Preconstruction Video
08/30/2013
01 3300
Submittals
08/30/2013
01 35 13
Special Project Procedures
08/30/2013
01 45 23
Testing and Inspection Services
03/20/2020
01 5000
Temporary Facilities and Controls
07/01/2011
01 5526
Street Use Permit and Modifications to Traffic Control
07/01/2011
01 57 13
Storm Water Pollution Prevention Plan
07/01/2011
01 6000
Product Requirements
03/20/2020
01 66 00
Product Storage and Handling Requirements
04/07/2014
01 70 00
Mobilization and Remobilization
04/07/2014
01 7123
Construction Staking
04/07/2014
01 74 23
Cleaning
04/07/2014
01 77 19
Closeout Requirements
04/07/2014
01 78 23
Operation and Maintenance Data
04/07/2014
01 78 39
Project Record Documents
04/07/2014
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised March 20, 2020
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 2 of 6
Technical Specifications which have been modified by the Engineer specifically for this
Project; hard copies are included in the Project's Contract Documents
Division 02 — Existing Conditions
None
Division 03 — Concrete
None
Division 36 — Electrical
None
Division 31 — Earthwork
None
Division 32 — Exterior Improvements
None
Division 33 — Utilities
None
Division 34 — Transportation
None
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised March 20, 2020
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 3 of 6
Technical Specifications listed below are included for this Project by reference and can be
viewed/downloaded from the City's website at:
htty://fortworthtexas.Lov/t )w/contractors/
or
httDs://apps.fortworthtexas.2ov/Proi ectResources/
Division 02 - Existing Conditions Last Revised
0241 13 Selective Site Demolition 12/20/2012
02 41-1-4 T T♦44-y D em e„abLM&n of ff e1 2 /7rz7-202viz
0241 15 Paving Removal 02/02/2016
Division 03 Conerete-
03 30 00 Cat In Naoe Concrete 12''_/�20/2012-
03 3/I 13 Controlled row Strength Material (C S ) 12/20/2012-
n2� Co e«ete Base Material for T«e..,el, Dc��e,..,:« 12/7 z
03-80--00 Meth eatio s to Existing Co e fe-to F/.rUCWr-s 12/20/2012
26 05 00 Work Results f f Eleetr e.,l 1111 /�B
2605 10 TDZ.-.ditl\'1 for Eleetrieal Systems 12/�1-2
3 Deee, ays and Boxes for Eeet«:e.,l Systems 12/7 z
26 05 43 Undefgfe d D;xc�zrana R ee,, ays f f Eleetfieal Systems 0�/n�11
26 05 50 Ea'2xnu:.�oat.-om Multi t: Duet Conduit 02 /moo
Division 31 Earthwork
3'�0 - - r� 11 /�12
3123 16 U:iJ1a3z,.F;ea Exe. ,,at r 01 / 3
31 2323 Berfe 0/�'v1� 28/2013
312400 Embankments 011 /7vzrzvnvi3
31 2500 Erosion and Sediment Control 12/20/2012
313600 GabionS 1 /zzr29120 z
3 1� RipW 1 7 /zzr24120 z
Division 32
3201 17
27�
Exterior- improvements
ient 2; V W.�r
Tempe«e«„ It D epai
12/20/2012
12/7�l1�L
32 01 29
Asphalt Paving
GoneFete Pavirzg norm
12 /�012
12 1123
F exible Base Coufses-
12/7�lhL
32 1129
Lime Treated Base Courses
12/20/2012
1, 1133
Gement Treated Base Couf
Q,124120Q
32 1137
32 1216
Liquid Treated Soil Stabilizer
Asphalt It Paving
08/21/2015
12/�4-2
32 1273
32 13 13
Asphalt It Paving Gr- ek Sealants
Concrete Paving
1 �� /izr2412
12/20/2012
32 13 20
re ete Side , lka Driveways and Barrier Free Ramps
06/05,12018
32 1373
Concrete Paving Joint Sealants
B«: eL .
12/20/2012
32 14 16
32 1613
Unit it Pavia
Concrete Curb and Gutters and Valley Gutters
Q/24120Q
10/05/2016
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised March 20, 2020
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 4 of 6
27� Pavement Mar -kings 1 1 /22/ via
3231 3 Chain > enees a -a Gates Q/7 z
27� Wire Fenees and !'fetes Q/7 z
323129 11 /�12-
323213 Cast i Dleee /'o erete Retaining xx a 06f85/20�
3291 19 Topsoil Placement and Finishing of Parkways 12/20/2012
32 92 13 Hydro -Mulching, Seeding, and Sodding 12/20/2012
2'1� Tfee..and S1.,abs- Q/7 z
Division 3
33-01-30
22�
3303 10
333 04 1
Utilities
Sewef and Manhole Testing 12/20/2012
Closed Cir-e„;t Television (CCTV) TWeet;..,-, 03/0o
%TWA Pumrj„ ��e..,e S.� 11 /��
T2.,,�..�1;,�.gandRleet,-:e.,l isol,tio 12/20/2012
33 04 11
and�
�T-.oint
V 1v%Uo. (`••ntfol Test Stations 12/7 z
3304 12
Nlag. acurs n re,le rethed e Proteetio Syste ffl 11 /�12
33 04 30
3304 40
'\'are, W ter ee .,;ve� 07/n�11
Cleaning and n eeepteree Testing f•Water Mains 02/03
33 04-50
33-05 10
Cleaning of'Sewer Mains 12/7 -2
Utility Tfe 111 DIIJxvftdon, Embedment, .,,-..1 B ekf;11 12/1 0
3305 12
Wat7 Une Lowering 11 /�1-2
3305 13
3305 13.10
>;,ame Cove- and r«e l0 Ringo Cast ife n1 /moo
Ffame, Covef ,1 r_fa e Rings Composite 01 /22/2
Adjusting Manholes, inlets, Valve Boxes, nthef StmetuFert6
33-03-14
22�
3305 17
33 05 20
i
330522
3
and 1 � /�12
Grade
rerefete W tef Vaults 11 /��
Cere«ete Cellafs 12/20/2012
rg 11 /�12
Tunnel Liner- Plate 12,12912012
Steel-Cm/i g Pipe 1 /�;z
Hand T,,....eling Q/2412W2
�3-03-�4
f!''af-:e,- Pipe i (`.,sing 1 T 06/1 n/7n1'2
I�,t�1..latira�I o. or Tu�~�~a� �i�n�late
33 05 26
22�
Utility Ti a-Le.-s/T ojato\rz Q/24120Q
T ee.,tion of Existing Util:12,12412012
33 1105
33 11 0
Belts Nuts, and Gaskets 12/7�0-12
13>;Iefilo Ian Pic 12/20/2012
33 11 11
Due ilo Imn Fittings 12/''�12
33 1 1 �
1
Del....in. Chloride (PVC) Pfesstife Pipe 1 11 1 /1 II9
2
�� 11 1�
33
Bar- V -,,,. pe,1 Steel !''.,1;,...1e,- Type 12/20/20 �
Eene�eto Praov.� Pilo, ��
33 11 11
stool Pirc-and Fittings 12/rt 20/ 012
xxt.,te,- Sefyiees 1 ineh t 2 ;ref rr1/lvzr ^rTr2017
33 0
P- 1211
Large Water- Mete,-s 12/2412012
12P2
33 1220
✓3 12 21
Resilient Seated Gate Valve z
nAVW- Rubber- Seated Bu4teffly V 1y 12/2z
P- 12 2-5
33 1230
Comae ion o D/.iaing Water- Mains 02/n� �20
Combination Air- . Valve Assemblies for- Potable Water- System 1 71 /'l z
33 1240
33 0
L';,� n 11 /n� �2014
Waco: Eatnr).e Stations 1 �i /'%i2
CITY OF FORT WORTH UPS Staging- Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS CPN 105301
Revised March 20, 2020
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 5 of 6
?� P. 15 High Density Pelyethylene (IITDPE) Pip --for F'/anitar, er 12/ 0/2012
33 31 20 D 1.,.,:ft. !''L.le-ide (DSTC) r_,.a-yit f Sanitafy Sew Pipe 06/1 �3
3- P. 31 PelEanisv, er 1 �� /ram 20/20Q
Pipe
2 P. canna., Se r 12/20/2012
.� .�' 3�� �� FJ.ip .mining ��
22� C'�'n,"',:latl^ r2-20r20r2
3339 10 Camf is Pl1aa Co:�at� \�1e1e�
12/7 z
333920 Preeast-Cwno tej Manholes 1'1 /'r�r20/2012
33 39 30 Fiks.-glas3 Nlanholw 12/�1-2
33 39--40 Wastewater „Vn ceess Chamber (W n C) i2/20/2
333960 pz
�-' o T1.:1� f3. L aMar j C o.. e C' 4,-uetum 1 2 /7 z
33 41 10 Rein f ,-. e !`.,,-..,,-ot0 E'ayyef Pipe-/G lye fts 07/01/2011
33 1 ? 11 High Density Polyethylene (II.DPE) Pipe €erSt�-m Dmin 11 2/20/iviz
22� Rein f; ,-. e Pe, ,othlorx) (�,PE>, Pip-- 1 11 1 /1 �
33 4600 Subdr-ainag-e 171 /7z
33 4601 Slotted 9t3-.Tn Dmim- 0�/non
33 4602 Tfenall Dmi:lo 07/non
33 49 10 Cat it Plaoe Manholes and itmetion Boxes 1-2/�Q
33 4920 Garb and Drop inlets 12/�1
33 4940 TDminage uo.,,a.,,.,lls .,...,a W,..,...,.,lls 07/0 /2011
Division-34 Transportation
34 41 10 Tfaffio F'/Analz 10/1�2/20115
34 41 10.01 nt �7� * ,� ll 12/18/2015
�v-r 1-r�ti�G1i1i1eirtri r ntrerle�C-a�inet izTrvrcvz�
34 41 10.02 n t B r r ller- Spo
�vr rrtt-&C�1.3,.n,,.rcrrc�cvrrtf6rrcrapvC�cuti6n i
211 1 111 Tefnpofar-y Traffi . Signals 1 11 1 / 3
311 11 1 3 Removing Tiraf 10 Sl gnalz 1 7 /7zzr2412W 2
211 11 15 ReetangWar Raxi.d Ra-&hind 1111 /''01
34 4120 Roadw Illurreinat o n sso,.. Mies 12 /�12
34 4120.01 Arterial LED n,,.,dw ,, r
� ., rnri��1 az o06/1 c/20-5 34 4120.02 Freeway LED Roadway ay r 06 / 1 c /201 c
�%.in1l�'�1'e6 vvrr✓rLvz�
Zn n�03 �' r r 06/1 c/201 c
Reside �� P.oa�' .�a�ri��1�s o���
34 41 30 Aluminum Signs 11/12/2013
34 4150 Single Mode Fiber- Optie Cab! 02,126,12016
3471 13 Traffic Control 11/22/2013
CITY OF FORT WORTH UPS Staging- Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS CPN 105301
Revised March 20, 2020
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Appendix
FTC-401
G42-403 gra'au
FG-4J1 Lkn&\g2oux
GG 4.G6- I-aoardeu-rrE-im-.-,x m� .al Geed fief at Site
i
7l
GG'�nnn? J9 1 wmit:/..Ix,7 U44ifies
GC-6.21 Pos3i3O.-imi:ut0:1
GC 03 30 00 TPW Mix Design
END OF SECTION
Page 6 of 6
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised March 20, 2020
00 42 43
DAP - BID PROPOSAL
Page 1 of 1
UPS STAGING LOT- LIBERTY WAY CONNECTION
CITY PROJECT NO. 105301
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
UNIT PRICE BID
Bidder's Application
Project Item Information
Bidder's
Proposal
Bidlist
Description
Specification Section No.
Unit of
Bid
Unit Price
Bid Value
Item No.
Measure
Quantity
UNIT III: PAVEMENT IMPROVEMENTS
1
0241.0550 Remove Guardrail
0241 13
LF
58
$43.00
$2,494.00 1
I 2
3213.0103 8" Conc Pvmt (4500osi)
32 13 13
SY
33
$16.50
$544.501
I 3
3471.0001 Traffic Control
3471 13
MO
1
$1,160.00
$1,160.001
I 4
3211.0400 Hvdrated Lime
32 11 29
TN
2
$375.00
$750.001
I 5
3211.0502 8" Lime Treatment
3211 29
SY
53
$14.65
$776.451
6
3291.0100 Topsoil
3291 19
CY
20
$30.00
$600.00 1
I 7
3292.0100 Block Sod Placement
32 92 13
SY
2
$22.00
$44.001
I 8
0544.2001 TxDOT Guardrail End Treatment (Install)
544-2001
EA
1
$895.00
$895.001
TOTAL UNIT III: PAVEMENT IMPROVEMENTS
$7,263.951
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS
Form Version September 1, 2015
Copy of 00 42 43_Bid Proposal - UPS Egress xlsm
UNIT PRICE BID
Bidlist Item
No.
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
00 42 43
DAP-BIDPROPOSAL
Page 7 of 7
Bidder's Application
Project Item Information Bidder's Proposal
Description I Specification I Unit of I Bid Unit Price Bid Value
Section No. Measure Quantity
Bid Summary
UNIT IV: PAVING IMPROVEMENTS
This Bid is submitted by the entity named below:
BIDDER:
CIMA General Contractors
1017 Long Prairie Rd Ste 200
Flower Mound, TX 75022
Contractor agrees to complete WORK for FINAL ACCEPTANCE within
CONTRACT commences to run as provided in the General Conditions.
Total Construction Bid
BY: Mike Cook
TITLE: Director Construction
DATE: 1/25/2024
$7,263.95 1
$7,263.95 1
r45 working days after the date when the
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS
Form Version May 22, 2019
00 42 43_13id SummaryDAP.xls
0045 12
DAP PREQUALIFICATION STATEMENT
Page 1 of I
SECTION 00 45 12
DAP — PREQUALIFICATION STATEMENT
Each Bidder is required to complete the information below by identifying the prequalified contractors
and/or subcontractors whom they intend to utilize for the major work type(s) listed. In the "Major Work
Tvne" box provide the complete maior work tvne and actual description as provided by the Water
Department for water and sewer and TPW for navina.
Major Work Type Contractor/Subcontractor Company Name Prequalification
Expiration Date
Concrete Paving Concrete pavement will be hand pour— no N/A
prequaliticatio❑ required
The undersigned hereby certifies that the contractors and/or subcontractors described in the table above
are currently prequalified for the work types listed.
CIMA General Contractors, Inc
1017 Long Prairie Rd
Suite 200
Flower Mound, TX 75022
BY: Mike Cook
(Signature)
TITLE: Director Construction
DATE: 4/ 19/24
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION PREQUALIFICATION STATEMENT— DEVELOPER AWARDED PROJECTS 0045 12_Prequaliflcation Statement 2015_DAP
Form Version September 1, 2015
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
00 45 26 - 1
CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW
Page 1 of 1
SECTION 00 45 26
CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW
Pursuant to Texas Labor Code Section 406.096(a), as amended, Contractor certifies that it
provides worker's compensation insurance coverage for all of its employees employed on City
Project No. 105015. Contractor further certifies that, pursuant to Texas Labor Code, Section
406.096(b), as amended, it will provide to City its subcontractor's certificates of compliance with
worker's compensation coverage.
CONTRACTOR:
_CIMA General Contractors, Inc
Company
1017 Long Prairie Rd Ste 200
Address
Flower Mound, TX 75022
City/State/Zip
THE STATE OF TEXAS §
COUNTY OF TARRANT §
By: Mike Cook
(Please Print)
Signature: v _ _-_-
Title: Director Construction
(Please Print)
BEFORE ME, the undersigned authority, on this day personally appeared
Joko r i4 , known to me to be the person whose name is
subscribed to the foregoing instrument, and acknowledged to me that he/she executed the same as
the act and deed of w urk�� 6a,,Ap Ao'w vt; ll- for the purposes and
consideration therein expressed and in the capacity therein stated.
GIVEN UNDER MY HAND AND SEAL OF OFFICE this
"Wig°i lr 20'?, -.
Notary Public in and for the State of Texas
day of
NANC'i POBISON
END OF SECTION ma<
<,SNoYary i'uksiir„ ata;ca a4 Ioxas
atlo �' t ornrn, i xPires 06-#7.2026
°r®xQrca gl,�� Notary ID 129460448
CITY OF FORT WORTH LIPS Stating -- Liberly Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS C'PA' 105301
Revised April 2, 2014
DocuSign Envelope ID: E182EODO-OB4B-44B1-8CE6-6FA9BAB76F63
00 52 43 - 1
Developer Awarded Project Agreement
Page 1 of 4
1 SECTION 00 52 43
2 AGREEMENT
3
4 THIS AGREEMENT, authorized on Mav 15. 2024 is made by and between the Developer,
5 United Parcel Service, Inc., an Ohio corporation, authorized to do business in Texas
6 ("Developer") , and CIMA General Contractors. LLC, authorized to do business in Texas, acting
7 by and through its duly authorized representative, ("Contractor").
8 Developer and Contractor, in consideration of the mutual covenants hereinafter set forth, agree as
9 follows:
10 Article 1. WORK
11 Contractor shall complete all Work as specified or indicated in the Contract Documents for the
12 Project identified herein.
13 Article 2. PROJECT
14 The project for which the Work under the Contract Documents may be the whole or only a part is
15 generally described as follows:
16 PUBLIC PAVING IMPROVEMENTS TO SERVE UPS STAGING — LIBERTY
17 CONNECTION
18 CPN:105301
19 Article 3. CONTRACT TIME
20 3.1 Time is of the essence.
21 All time limits for Milestones, if any, and Final Acceptance as stated in the Contract
22 Documents are of the essence to this Contract.
23 3.2 Final Acceptance.
24 The Work will be complete for Final Acceptance within 45 working days after the date
25 when the Contract Time commences to run as provided in Paragraph 12.04 of the Standard
26 City Conditions of the Construction Contract for Developer Awarded Projects.
27 3.3 Liquidated damages
28 Contractor recognizes that time is of the essence of this Agreement and that Developer
29 will suffer financial loss if the Work is not completed within the times specified in
30 Paragraph 3.2 above, plus any extension thereof allowed in accordance with Article 10 of
31 the Standard City Conditions of the Construction Contract for Developer Awarded
32 Projects. The Contractor also recognizes the delays, expense and difficulties involved in
33 proving in a legal proceeding the actual loss suffered by the Developer if the Work is not
34 completed on time. Accordingly, instead of requiring any such proof , Contractor agrees
35 that as liquidated damages for delay (but not as a penalty), Contractor shall pay
36 Developer Zero Dollars $0.00 for each day that expires after the time specified in
37 Paragraph 3.2 for Final Acceptance until the City issues the Final Letter of Acceptance.
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised June 16, 2016
DocuSign Envelope ID: E182EODO-OB4B-44B1-8CE6-6FA9BAB76F63
00 52 43 - 2
Developer Awarded Project Agreement
Page 2 of 4
38 Article 4. CONTRACT PRICE
39 Developer agrees to pay Contractor for performance of the Work in accordance with the Contract
40 Documents an amount in current funds of Seven Thousand Two Hundred Sixty -Three and 95/100
41 Dollars ($7,263.95).
42 Article 5. CONTRACT DOCUMENTS
�.��K�]►YY�1►YIf.�
44
A. The Contract Documents which comprise the entire agreement between Developer and
45
Contractor concerning the Work consist of the following:
46
1.
This Agreement.
47
2.
Attachments to this Agreement:
48
a. Bid Form (As provided by Developer)
49
1) Proposal Form (DAP Version)
50
2) Prequalification Statement
51
3) State and Federal documents (project specific)
52
b. Insurance ACORD Form(s)
53
c. Payment Bond (DAP Version)
54
d. Performance Bond (DAP Version)
55
e. Maintenance Bond (DAP Version)
56
f. Power of Attorney for the Bonds
57
g. Worker's Compensation Affidavit
58
h. MBE and/or SBE Commitment Form (If required)
59
3.
Standard City General Conditions of the Construction Contract for Developer
60
Awarded Projects.
61
4.
Supplementary Conditions.
62
5.
Specifications specifically made a part of the Contract Documents by attachment
63
or, if not attached, as incorporated by reference and described in the Table of
64
Contents of the Project's Contract Documents.
65
6.
Drawings.
66
7.
Addenda.
67
8.
Documentation submitted by Contractor prior to Notice of Award.
68
9.
The following which may be delivered or issued after the Effective Date of the
69
Agreement and, if issued, become an incorporated part of the Contract Documents:
70
a. Notice to Proceed.
71
b. Field Orders.
72
c. Change Orders.
73
d. Letter of Final Acceptance.
74
75
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised June 16, 2016
DocuSign Envelope ID: E182EODO-OB4B-44B1-8CE6-6FA9BAB76F63
00 52 43 - 3
Developer Awarded Project Agreement
Page 3 of 4
►i7. .Wm mile IeI1J0IuIeIIW[91:rY[0eI
77 6.1 Contractor covenants and agrees to indemnify, hold harmless and defend, at its own
78 expense, the city, its officers, servants and employees, from and against any and all
79 claims arising out of, or alleged to arise out of, the work and services to be performed
80 by the contractor, its officers, agents, employees, subcontractors, licenses or invitees
81 under this contract. This indemnification provision is specifically intended to operate
82 and be effective even if it is alleged or proven that all or some of the damages being
83 sought were caused, in whole or in part, by anv act, omission or negligence of the citv.
84 This indemnity provision is intended to include, without limitation, indemnity for
85 costs, expenses and legal fees incurred by the city in defending against such claims and
86 causes of actions.
87
88 6.2 Contractor covenants and agrees to indemnify and hold harmless, at its own expense,
89 the city, its officers, servants and employees, from and against any and all loss, damage
90 or destruction of property of the city, arising out of, or alleged to arise out of, the work
91 and services to be performed by the contractor, its officers, agents, employees,
92 subcontractors, licensees or invitees under this contract. This indemnification
93 provision is specifically intended to operate and be effective even if it is alleged or
94 proven that all or some of the damages being sought were caused, in whole or in part,
95 by anv act, omission or negligence of the city.
96
97 Article 7. MISCELLANEOUS
98 7.1 Terms.
99 Terms used in this Agreement are defined in Article 1 of the Standard City Conditions of
100 the Construction Contract for Developer Awarded Projects.
101 7.2 Assignment of Contract.
102 This Agreement, including all of the Contract Documents may not be assigned by the
103 Contractor without the advanced express written consent of the Developer.
104 7.3 Successors and Assigns.
105 Developer and Contractor each binds itself, its partners, successors, assigns and legal
106 representatives to the other party hereto, in respect to all covenants, agreements and
107 obligations contained in the Contract Documents.
108 7.4 Severability.
109 Any provision or part of the Contract Documents held to be unconstitutional, void or
110 unenforceable by a court of competent jurisdiction shall be deemed stricken, and all
111 remaining provisions shall continue to be valid and binding upon DEVELOPER and
112 CONTRACTOR.
113 7.5 Governing Law and Venue.
114 This Agreement, including all of the Contract Documents is performable in the State of
115 Texas. Venue shall be Tarrant County, Texas, or the United States District Court for the
116 Northern District of Texas, Fort Worth Division.
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN ]05301
Revised June 16, 2016
DocuSign Envelope ID: E182EODO-OB4B-44B1-8CE6-6FA9BAB76F63
00 52 43 - 4
Developer Awarded Project Agreement
Page 4 of 4
117
118 7.6 Authority to Sign.
119 Contractor shall attach evidence of authority to sign Agreement, if other than duly
120 authorized signatory of the Contractor.
121
122 IN WITNESS WHEREOF, Developer and Contractor have executed this Agreement in multiple
123 counterparts.
124
125 This Agreement is effective as of the last date signed by the Parties ("Effective Date").
126
127
Contractor: Developer:
CIMA General Contractors, Inc United Parcel Service, Inc., an Ohio corporation
yyDoccu�u//Siggned by- A
�I�LiI PoLCP�n /'(a.GOfuG
By: _ By: _
(Signature)(Signature)
Mike Cook Kathleen Malone
(Printed Name) (Printed Name)
Director Construction Title: Vice President
CIMA General Contractors, Inc Company name: United Parcel Service, Inc.
1017 Long Prairie Rd Address: 55 Glenlake Pkwy NE
Ste 200
Flower Mound, Texas 75022 City/State/Zip: Atlanta, GA 30328
4/22/24 5/15/2024
Date Date
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised June 16, 2016
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
CONTRACTOR'S BLANKET FLEX ADDITIONAL INSURED
ENDORSEMENT - FORM A
This endorsement modifies insurance provided under the following:
COMMERCIAL GENERAL LIABILITY COVERAGE PART
Policy Number
CPP21058410502
Policy Expiration Date
8/1/2024
Named Insured
Agency Number
0755338
Date
8/l/2023
Agency
CIMA GENERAL CONTRACTORS, INC Upshaw Insurace Agency Inc
Policy Effective Date
8/1/2023
Account Number
20070440
Issuing Company
Amerisure Mutual Insurance Companj
A. SECTION II -WHO IS AN INSURED is amended to add as an additional insured:
1. Any person ororganization with whom you have agreed in a "written agreement" that such person or
organization be added as an additional insured on this policy, and any other person or organization
you are required to add as an additional insured under such "written agreement".
2. If "your work" began under a written letter of intent or written work order, any person or organization
who issued the written letter of intent or written work order, but:
a. such coverage will apply only for 30 calendar days following the date the written letter of intent
or written work order was issued; and
b. the person or organization is an additional insured only for, and to the extent of, liability arising
out of "bodily injury", "property damage", or "personal and advertising injury" caused, in whole
or in part, by your negligent acts or omissions, or the negligent acts or omissions of others
working on your behalf, in the performance of your work as specified in the written letter of
intent or written work order. This coverage does not apply to liability arising out of the
independent acts or omissions of the additional insured.
For the purposes of the coverage provided by this endorsement, a "written agreement" means a written
contract or written agreement that:
1. requires you to include a person or organization as an additional insured for a period of time during
the policy period; and
2. is executed prior to the occurrence of "bodily injury", "property damage", or "personal and
advertising injury" that forms the basis for a claim under this policy.
The insurance provided by this endorsement does not apply to any person or organization that is
specifically listed as an additional insured on another endorsement attached to this policy.
CG 73 24 03 23 Includes copyrighted material of the Insurance Services Office, Inc., with its permission Page 1 of 3
B. The coverage provided to any person or organization added as an additional insured pursuant to Paragraph
AA is limited as follows:
1. If the "written agreement" specifically and exclusively requires you to name the person or organization
as an additional insured using the ISO CG 20 10 endorsement with edition dates of 11 85 or 10 01,
or the ISO CG 20 37 10 01 endorsement, that person or organization is an additional insured, but
only with respect to liability for "bodily injury", "property damage", or "personal and advertising injury"
arising out of "your work" for that insured by or for you.
2. If the "written agreement" requires you to name the person or organization as an additional insured
using the ISO CG 20 10 and or CG 20 37 endorsements without specifically and exclusively requiring
the 11 85 or 10 01 edition dates, that person or organization is an additional insured, but only with
respect to liability for "bodily injury", "property damage", or "personal and advertising injury" caused,
in whole or in part, by your acts or omissions or the acts or omissions of those acting on your behalf.
3. If the "written agreement" requires you to name the person or organization as an additional insured
for operations arising out of your work and does not specify an ISO additional insured endorsement,
that person or organization is an additional insured, but only with respect to liability for "bodily injury",
"property damage", or "personal and advertising injury" arising out of your acts or omissions, or the
acts or omissions of others working on your behalf, in the performance of your work as specified in
the "written agreement". This coverage does not apply to liability arising out of the sole negligence of
the additional insured unless specifically required in the "written agreement".
4. If none of the above paragraphs apply, then the person or organization is an additional insured only
for, and to the extent of, liability arising out of "bodily injury", "property damage", or "personal and
advertising injury" caused, in whole or in part, by your negligent acts or omissions, or the negligent
acts or omissions of others working on your behalf, in the performance of your work as specified in
the "written agreement". This coverage does not apply to liability arising out of the independent acts
or omissions of the additional insured.
However, the insurance afforded to such additional insured only applies to the extent permitted by law.
C. The insurance provided to an additional insured under this endorsement does not apply to:
1. "Bodily injury" or "property damage" included in the "products -completed operations hazard" unless
the "written agreement" specifically requires such coverage (including by specifically requiring the
CG 20 10 11 85). To the extent the "written agreement" requires such coverage for a specified
amount of time, the coverage provided by this endorsement is limited to the amount of time required
for such coverage by the "written agreement".
"Bodily injury", "property damage", or "personal and advertising injury" arising out of an architect's,
engineer's, or surveyor's rendering of, or failure to render, any professional services, including but
not limited to:
a. The preparing, approving, or failing to prepare or approve:
(1) Maps;
(2) Drawings;
(3) Opinions;
(4) Reports;
(5) Surveys;
(6) Change orders;
CG 73 24 03 23 Includes copyrighted material of the Insurance Services Office, Inc., with its permission Page 2 of 3
(7) Design specifications; and
b. Supervisory, inspection, or engineering services.
D. The limits of insurance that apply to the additional insured are the least of those specified in the "written
agreement" or declarations of this policy.
Coverage provided by this endorsement for any additional insured shall not increase the applicable Limits
of Insurance shown in the Declarations. The limits of insurance that apply to the additional insured are
inclusive of, and not in addition to, the Limits of Insurance shown in the Declarations.
E. With respect to the coverage provided by this endorsement, SECTION IV — COMMERCIAL GENERAL
LIABILITY CONDITIONS, Paragraph 4. Other Insurance is deleted and replaced with the following:
4. Other Insurance.
a. Coverage provided by this endorsement is excess over any other valid and collectible insurance
available to the additional insured whether:
(1) Primary;
(2) Excess;
(3) Contingent; or
(4) On any other basis.
In addition, this insurance is excess over any self -insured retentions, deductibles, or captive
retentions payable by the additional insured or payable by any person or organization whose
coverage is available to the additional insured.
However, if the "written agreement" requires primary and non-contributory coverage, this insurance
will be primary and non-contributory relative only to the other insurance available to the additional
insured which covers that person or organization as a Named Insured, and we will not share with
that other insurance. For any other insurance available to the additional insured where that person
or organization is not a Named Insured, this policy will share coverage with that other insurance
based on the terms specified in Paragraph b. Method of Sharing below.
b. Method of Sharing
If all the other insurance permits contribution by equal shares, we will follow this method also. Under
this method, each insurer contributes equal amounts until it has paid its applicable limit of insurance
or none of the loss remains, whichever comes first.
If any of the other insurance does not permit contribution by equal shares, we will contribute by
limits. Under this method, each insurer's share is based on the ratio of its applicable limit of
insurance to the total applicable limits of insurance of all insurers.
CG 73 24 03 23 Includes copyrighted material of the Insurance Services Office, Inc., with its permission Page 3 of 3
16. BROADENED KNOWLEDGE OF OCCURRENCE
Under 2. Duties In The Event Of Occurrence, Offense, Claim, Or Suit, paragraph a. is deleted and replaced
and paragraphs e. and f. are added as follows:
a. You must see to it that we are notified as soon as practicable of an "occurrence" or an offense,
regardless of the amount, which may result in a claim. Knowledge of an "occurrence" or an offense by
your "employee(s)" shall not, in itself, constitute knowledge to you unless one of your partners, members,
"executive officers," directors, or managers has knowledge of the "occurrence" or offense. To the extent
possible, notice should include:
(1) How, when and where the "occurrence" or offense took place;
(2) The names and addresses of any injured persons and witnesses; and
(3) The nature and location of any injury or damage arising out of the "occurrence" or offense.
e. If you report an "occurrence" to your workers compensation carrier that develops into a liability claim for
which coverage is provided by this Coverage Form, failure to report such an "occurrence" to us at the
time of the "occurrence" shall not be deemed a violation of paragraphs a., b., and c. above. However,
you shall give written notice of this "occurrence" to us as soon you become aware that this "occurrence"
may be a liability claim rather than a workers compensation claim.
f. You must see to it that the following are done in the event of an actual or anticipated "covered recall" that
may result in "product recall expense":
(1) Give us prompt notice of any discovery or notification that "your product" must be withdrawn or
recalled. Include a description of "your product' and the reason for the withdrawal or recall;
(2) Cease any further release, shipment, consignment or any other method of distribution of like or
similar products until it has been determined that all such products are free from defects that could
be a cause of loss under the insurance.
17. UNINTENTIONAL FAILURE TO DISCLOSE HAZARDS
Paragraph 6. Representations is deleted and replaced with the following:
6. Representations
By accepting this policy, you agree:
a. The statements in the Declarations are accurate and complete;
b. Those statements are based upon representations you made to us; and
c. We have issued this policy in reliance upon your representations.
We will not deny coverage under this Coverage Form if you unintentionally fail to disclose all hazards
existing as of the inception date of this policy. You must report to us any knowledge of an error or
omission in the description of any premises or operations intended to be covered by this Coverage
Form as soon as practicable after its discovery. However, this provision does not affect our right to
collect additional premium or exercise our right of cancellation or nonrenewal.
18. TRANSFER OF RIGHTS (BLANKET WAIVER OF SUBROGATION)
Paragraph 8. Transfer of Rights Of Recovery Against Others To Us is deleted and replaced with the
following:
8. If the insured has rights to recover all or part of any payment we have made under this Coverage Form,
those rights are transferred to us. The insured must do nothing after loss to impair them. At our request,
the insured will bring "suit" or transfer those rights to us and help us enforce them. However, if the
insured has waived rights to recover through a written contract, or if "your work" was commenced under a
letter of intent or work order, subject to a subsequent reduction to writing with customers whose
customary contracts require a waiver, we waive any right of recovery we may have under this Coverage
Form.
19. EXTENDED NOTICE OF CANCELLATION AND NONRENEWAL
Includes copyrighted material of Insurance Services Office, Inc.
Page 8 of 11 CG 70 63 04 17
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
006219-1
MAINTENANCE BOND
Page 1 of 4
SECTION 00 62 19 Bond No. HSHNSU0858071
MAINTENANCE BOND
THE STATE OF TEXAS §
KNOW ALL BY THESE PRESENTS:
COUNTY OFTARRANT
That we�ttv1�O1��Jstr�cto lac known as
"Principal" herein and Harco National Insurance Company___a corporate surety
(sureties, if more than one) duty authorized to do business in the State of Texas, known as
"Surety" herein (whether one or more), are held and firmly bound unto the Developer,
(___,BT-OH. LLC }, authorized to do business in Texas ("Developer") and the City
of Fort Worth, a Texas municipal corporation ("City"), in the sum of
Seven Thousand Two Hundred Sixty Three and 95/100 Dollars ($ 7,263.95 ), lawful
money of the United States, to be paid in Fort Worth, Tarrant County, Texas, for payment of
which sum well and truly be made jointly unto the Developer and the City as dual obligees
and their successors, we bind ourselves, our heirs, executors, administrators, successors
and assigns, jointly and severally, firmly by these presents.
19 WHEREAS, Developer and City have entered into an Agreement for the construction of
20 community facilities in the City of Fort Worth by and through a Community Facilities
21 Agreement, CFA Number 24-0018 _,__and
22 WHEREAS, the Principal has entered into a certain written contract with the
23 Developer awarded the 251h_.day of _ January 2024 , which
24 Contract is hereby referred to and a made part hereof for all purposes as if fully set forth
25 herein, to furnish all materials, equipment labor and other accessories as defined by law, in
26 the prosecution of the Work, including any Work resulting from a duly authorized Change
27 Order (collectively herein, the "Work") as provided for in said Contract and designated as
28 UPS Staging — Liberty Connection; and
29
CI I Y OF FORT WORTH UPS Staging --1_ibeity Connection
STANDARD CONSTRUCTION SPECIFICATION DOCIJMI:NIS - DEVEI.OPt:R AWARDED PROJECTS CPN 105301
Revised January 31, 2012
006219.2
MAINTENANCE BOND
Page 2 of 4
1 WHEREAS, Principal binds itself to use such materials and to so construct the Work
2 in accordance with the plans, specifications and Contract Documents that the Work is and
3 will remain free from defects in materials or workmanship for and during the period of two
4 (2) years after the date of Final Acceptance of the Work by the City ("Maintenance Period");
5 and
6 WHEREAS, Principal binds itself to repair or reconstruct the Work in whole or in part
7 upon receiving notice from the Developer and/or City of the need thereof at any time within
8 the Maintenance Period.
9 NOW THEREFORE, the condition of this obligation is such that if Principal shalt
10 remedy any defective Work, for which timely notice was provided by Developer or City, to a
11 completion satisfactory to the City, then this obligation shalt become null and void;
12 otherwise to remain in full force and effect.
13 PROVIDED, HOWEVER, if Principal shall fail so to repair or reconstruct any timely
14 noticed defective Work, it is agreed that the Developer or City may cause any and all such
15 defective Work to be repaired and/or reconstructed with all associated costs thereof being
16 borne by the Principal and the Surety under this Maintenance Bond; and
17 PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in
18 Tarrant County, Texas or the United States District Court for the Northern District of Texas,
19 Fort Worth Division; and
20 PROVIDED FURTHER, that this obligation shalt be continuous in nature and
21 successive recoveries may be had hereon for successive breaches.
22 IN WITNESS WHEREOF, the Principal and the Surety have each SIGNED and
23 SEALED this instrument by duly authorized agents and officers on this the 26_t_h___.... day of..
unc
2024_
25
26
27
CITY OF FORT WORTH UPS Staging- Liberty Connection
STANDARD CONSTRUCTION SKCIFICATION DOCUMENTS- DI:VELOPERAWARDL•D PROJECTS CPN 105301
Revised January 31, 2012
1
2
3
4
5
6
7
Q
9
10
11
12
13
14
15
16
17
18
19
20
21
22
006219.3
MAINTENANCE RONI)
Page 3 of 4
PRINCIPAL:
CIMA General Contractors. Inc. —__—
BY: --
Signature
ATTEST;
IL)----- — NaAw �1,iso,^._..-
(Principal) Secretary Name and Title
Address:_-1017 Long Prairie Rd, Ste 200
Flow -or Mound, TX 75022
Witness as to Principal
SURELY:
Harco Nations Insyrrance Com�any-
-----_ -._.. GAG -/--- - ... _._
Signature
Rick Clements, Attornev-in_Fact
ATTEST: Name and Title
Address: _PO Box 1299
(Surety) Secretary Amarillo, TX 79105v_
23
24
25 Witness as to Surety Telephone Number: _(Q6�468-0400
26
CITY OF FORT WORTH UPS Staging- bborty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS • Di VELOPER AWARDED PROJECTS CPN 105301
Revised January 31, 2012
006219-4
MAINTENANCE BOND
Ilage 4 of 4
1 *Note: If signed by an officer of the Surety Company, there must be on file a certified
2 extract from the by-laws showing that this person has authority to sign such
3 obligation. If Surety's physical address is different from its mailing address, both
4 must be provided.
5
6 The date of the bond shall not be prior to the date the Contract is awarded.
7
CITY OF FORT WORTH
UPS Staging- Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS CPN 705301
Revised January 31, 9012
POWER OF ATTORNEY Bond# HSFINSU0858071
HARCO NATIONAL INSURANCE COMPANY
INTERNATIONAL FIDELITY INSURANCE COMPANY
Member companies of IAT Insurance Group, Headquartered: 4200 Six Forks Rd, Suite 1400, Raleigh, NC 27609
KNOW ALL MEN BY THESE PRESENTS: That HARCO NATIONAL INSURANCE COMPANY, a corporation organized and existing under the laws of
the State of Illinois, and INTERNATIONAL FIDELITY INSURANCE COMPANY, a corporation organized and existing under the laws of the Slate of New
Jersey, and having their principal offices located respectively in the cities of Rolling Meadows, Illinois and Newark, New Jersey, do hereby constitute and
appoint
RICK CLEMENTS, LAUREN LANE, STEPHANIE TAYLOR, CORY B. BENTLEY, ROBERT B. BENTLEY
Amarillo, TX
their true and lawful atlorney(s)-in-fact to execute, seal and deliver for and on its behalf as surely, any and all bonds and undertakings, contracts of
indemnity and other writings obligatory in the nature thereof, which are or may be allowed, required or permitted by law, statute, rule, regulation, contract
or otherwise, and the execution of such instrument(s) in pursuance of these presents, shall be as binding upon the said HARCO NATIONAL
INSURANCE COMPANY and INTERNATIONAL FIDELITY INSURANCE COMPANY, as fully and amply, to all intents and purposes, as if the same had
been duly executed and acknowledged by their regularly elected officers at their principal offices.
This Power of Attorney is executed, and may be revoked, pursuant to and by authority of the By -Laws of HARCO NATIONAL INSURANCE COMPANY
and INTERNATIONAL FIDELITY INSURANCE COMPANY and is granted under and by authority of the following resolution adopted by the Board of
Directors of INTERNATIONAL FIDELITY INSURANCE COMPANY at a meeting duly held on the 13th day of December, 2018 and by the Board of
Directors of HARCO NATIONAL INSURANCE COMPANY at a meeting held on the 13th day of December, 2018.
"RESOLVED, that (1) the Chief Executive Officer, President, Executive Vice President, Senior Vice President, Vice President, or Secretary of the
Corporation shall have the power to appoint, and to revoke the appointments of, Attorneys -in -Fact or agents with power and authority as defined or limited
in their respective powers of attorney, and to execute on behalf of the Corporation and affix the Corporation's seal thereto, bonds, undertakings,
recognizances, contracts of indemnity and other written obligations in the nature thereof or related thereto; and (2) any such Officers of the Corporation
may appoint and revoke the appointments of joint -control custodians• agents for acceptance of process, and Attorneys -in -fact with authority to execute
waivers and consents on behalf of the Corporation; and (3) the signature of any such Officer of the Corporation and the Corporation's seal may be affixed
by facsimile to any power of attorney or certification given for the execution of any bond, undertaking, recognizance, contract of indemnity or other written
obligation in the nature thereof or related thereto, such signature and seals when so used whether heretofore or hereafter, being hereby adopted by the
Corporation as the original signature of such officer and the original seal of the Corporation, to be valid and binding upon the Corporation with the same
force and effect as though manually affixed."
IN WITNESS WHEREOF, HARCO NATIONAL INSURANCE COMPANY and INTERNATIONAL
FIDELITY INSURANCE COMPANY have each executed and attested these presents
on this 31 st day of December, 2023
fY IpfG STATE OP NEW JERSEY STATE OF ILLINOIS p�'o ......SU?.11
County of Essex : ,� Gov°Oa�rF•.n� s
c SEAL '" m County of Cook SEAL
1904
.y `VIERS � --- —TM —_ - � —
Michael F. Zurcher
Executive Vice President, Harco National Insurance Company
and international Fidelity Insurance Company
On this 31s1 day of December, 2023 , before me came the individual who executed the preceding instrument, to me personally known, and,
being by me duly sworn, said he is the therein described and authorized officer of HARCO NATIONAL INSURANCE COMPANY and
INTERNATIONAL FIDELITY INSURANCE COMPANY; that the seals affixed to said instrument are the Corporate Seats of said Companies; that the
said Corporate Seals and his signature were duly affixed by order of the Boards of Directors of said Companies.
,• NY CR°-•., IN TESTIMONY WHEREOF, I have hereunto set my hand affixed my Official Seal, at the City of Newark,
GP.-• ''•�l New Jersey the day and year first above written.
�OTAR� ,
CF NE N Cathy Cruz a Notary Public of New Jersey!
CERTIFICATION My Commission Expires April 16, 2029
I, the undersigned officer of HARCO NATIONAL INSURANCE COMPANY and INTERNATIONAL FIDELITY INSURANCE COMPANY do hereby certify
that I have compared the foregoing copy of the Power of Attorney and affidavit, and the copy of the Sections of the By -Laws of said Companies as set
forth in said Power of Attorney, with the originals on file in the home office of said companies, and (hat the same are correct transcripts thereof, and of the
whole of the said originals, and that the said Power of Attorney has not been revoked and is now in full force and effect.
IN TESTIMONY WHEREOF, I have hereunto set my hand on this day, June 26, 2024
A02200
i
Irene Martins, Assistant Secretary
IMPORTANT NOTICE
To obtain information or make a complaint:
You may contact Harco National Insurance Company
at:
1-800-333-4167
You may also write to: Harco National Insurance
Company c/o IAT Surety at:
Attn: Claims Department
One Newark Center, 20"' Floor
Newark, NJ 07102
You may contact the Texas Department of Insurance
to obtain information on companies, coverages, rights
or complaints at:
1-800-252-3439
You may write the Texas Department of Insurance:
P. 0. Box 149104
Austin, TX 78714-9104
Fax: (512) 490-1007
Web: www.tdi.texas.uov
E.-mail: ConsumerProtectionntdi.tCNaS.9oV
PREMIUM OR CLAIM DISPUTES:
Should you have a dispute concerning your premium
or about a claim you should contact the agent or the
company first. If the dispute is not resolved, you may
contact the Texas Department of Insurance.
ATTACH THIS NOTICE TO YOUR BOND:
This notice is for information only and does not
become a part or condition of the attached document.
AVISO IMPORTANTE
Para obtener informacion o para presentar una queja:
Usted puede corunicarse con su Harco National
Insurance Company al:
1-800-333-4167
Usted tambien puede escribir a Harco National
Insurance Company c/o IAT Surety at:
Attn: Claims Department
One Newark Center, 20"' Floor
Newark, NJ 07102
Puede comunicarse con el Departamento de Seguros de
Texas para obtener informacion acerca de companies,
coberturas, derechos o que,jas al:
1-800-252-3439
Puede escribir al Departamento de Seguros de'rexas:
P. 0. Box 149104
Austin, TX 78714-9104
Fax: (512) 490-1007
Web: www.tdi.texas.rzov
E-mail• ConsumerProtectionntdi.texas.eov
DISPUTES S01311E PRIMAS O RECLAMOS:
Si liene una disputa concerniente a su prima o a un
reclamo, debc comunicarse con el agente o la compania
primero. Si no se resuelve la disputa, puede entonces
comunicarse con el departamento (TDI).
UNA ESTE AVISO A SU FIANZA DE CARANTIA:
Este aviso es solo para proposito de informacion y no
se convierte en parte o condicion del documento
adjunto.
STANDARD CITY CONDITIONS
OF THE CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
STANDARD CITY CONDITIONS OF THE
CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
TABLE OF CONTENTS
Page
Article 1 — Definitions and Terminology...........................................................................................................1
1.01 Defined Terms...............................................................................................................................1
1.02 Terminology.................................................................................................................................. 5
Article2 — Preliminary Matters......................................................................................................................... 6
2.01 Before Starting Construction......................................................................................................... 6
2.02 Preconstruction Conference.......................................................................................................... 6
2.03 Public Meeting.............................................................................................................................. 6
Article 3 — Contract Documents and Amending............................................................................................... 6
3.01 Reference Standards...................................................................................................................... 6
3.02 Amending and Supplementing Contract Documents................................................................... 6
Article4 — Bonds and Insurance........................................................................................................................ 7
4.01 Licensed Sureties and Insurers...................................................................................................... 7
4.02 Performance, Payment, and Maintenance Bonds......................................................................... 7
4.03 Certificates of Insurance................................................................................................................ 7
4.04 Contractor's Insurance.................................................................................................................. 9
4.05 Acceptance of Bonds and Insurance; Option to Replace...........................................................12
Article 5 —
Contractor's Responsibilities.........................................................................................................12
5.01
Supervision and Superintendent.................................................................................................12
5.02
Labor; Working Hours................................................................................................................13
5.03
Services, Materials, and Equipment...........................................................................................13
5.04
Project Schedule..........................................................................................................................14
5.05
Substitutes and "Or-Equals".......................................................................................................14
5.06
Pre -Qualification of Bidders (Prime Contractors and Subcontractors)......................................16
5.07
Concerning Subcontractors, Suppliers, and Others....................................................................16
5.08
Wage Rates..................................................................................................................................18
5.09
Patent Fees and Royalties...........................................................................................................19
5.10
Laws and Regulations.................................................................................................................19
5.11
Use of Site and Other Areas........................................................................................................19
5.12
Record Documents......................................................................................................................
20
5.13
Safety and Protection..................................................................................................................
21
5.14
Safety Representative..................................................................................................................21
5.15
Hazard Communication Programs..............................................................................................
22
5.16
Submittals....................................................................................................................................22
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
5.17 Contractor's General Warranty and Guarantee..........................................................................23
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
5.18 Indemnification ............................................
5.19 Delegation of Professional Design Services
5.20 Right to Audit: ..............................................
5.21 Nondiscrimination ........................................
Article 6 — Other Work at the Site ....................................
6.01 Related Work at Site ....................................
24
24
25
25
......................................................... 26
......................................................... 26
Article 7 — City's Responsibilities.................................................................................................................. 26
7.01 Inspections, Tests, and Approvals............................................................................................... 26
7.02 Limitations on City's Responsibilities........................................................................................26
7.03 Compliance with Safety Program............................................................................................... 27
Article 8 — City's Observation Status During Construction............................................................................ 27
8.01 City's Project Representative...................................................................................................... 27
8.02 Authorized Variations in Work...................................................................................................27
8.03 Rejecting Defective Work.................................................................................................. 27
8.04 Determinations for Work Performed..........................................................................................28
Article9 — Changes in the Work..................................................................................................................... 28
9.01 Authorized Changes in the Work................................................................................................28
9.02 Notification to Surety.................................................................................................................. 28
Article 10 — Change of Contract Price; Change of Contract Time
10.01 Change of Contract Price ..........................................
10.02 Change of Contract Time ..........................................
10.03 Delays........................................................................
Article 11 —
Tests and Inspections; Correction, Removal or Acceptance of Defective Work.......................29
11.01
Notice of Defects........................................................................................................................29
11.02
Access to Work...........................................................................................................................29
11.03
Tests and Inspections..................................................................................................................29
11.04
Uncovering Work..............................................................................................................
30
11.05
City May Stop the Work.............................................................................................................
30
11.06
Correction or Removal of Defective Work.........................................................................
30
11.07
Correction Period........................................................................................................................30
11.08
City May Correct Defective Work.............................................................................................
31
Article 12 —
Completion ..............................
12.01
Contractor's Warranty of Title
12.02
Partial Utilization ....................
12.03
Final Inspection .......................
12.04
Final Acceptance .....................
Article 13 — Suspension of Work........
13.01 City May Suspend Work
32
32
32
32
33
33
33
Article14 — Miscellaneous.............................................................................................................................. 34
CITY OF FORT WORTH UPSStaging—Liberty Connection
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
14.01 Giving Notice..............................................................................................................................34
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
14M Computation of Times
14.03 Cumulative Remedies..
14.04 Survival of Obligations
14.05 Headings
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
34
34
35
35
0073 10-1
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Pagel of35
ARTICLE 1— DEFINITIONS AND TERMINOLOGY
1.01 Defined Terms
A. Wherever used in these General Conditions or in other Contract Documents, the terms listed
below have the meanings indicated which are applicable to both the singular and plural thereof,
and words denoting gender shall include the masculine, feminine and neuter. Said terms are
generally capitalized or written in italics, but not always. When used in a context consistent with
the definition of a listed -defined term, the term shall have a meaning as defined below whether
capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial
capital letters in the Contract Documents include references to identified articles and paragraphs,
and the titles of other documents or forms.
1. Agreement - The written instrument which is evidence of the agreement between Developer
and Contractor covering the Work
2. Asbestos Any material that contains more than one percent asbestos and is friable or is
releasing asbestos fibers into the air above current action levels established by the United
States Occupational Safety and Health Administration.
3. Business Day — A business day is defined as a day that the City conducts normal business,
generally Monday through Friday, except for federal or state holidays observed by the City.
4. Buzzsaw — City's on-line, electronic document management and collaboration system.
5. Calendar Day — A day consisting of 24 hours measured from midnight to the next midnight.
6. City— The City of Fort Worth, Texas, a Texas home -rule municipal corporation, acting by,
its governing body through its City Manager, his designee, or agents authorized pursuant to
its duly authorized charter on his behalf.
7. Community Facilities Agreement (CFA) --A Contract between the Developer and the City
for the Construction of one or more following public facilities within the City public right-of-
way or easement: Water, Sanitary Sewer, Street, Storm Drain, Street Light, and Street Signs.
A CFA may include private facilities within the right-of-way dedicated as private right-of-
way or easement on a recorded plat.
8. Contract —The entire and integrated written document incorporating the Contract
Documents between the Developer, Contractor, and/or City concerning the Work. The
Contract supersedes prior negotiations, representations, or agreements, whether written or
oral.
9. Contract Documents —Those items that make up the contract and which must include the
Agreement, and it's attachments such as standard construction specifications, standard City
Conditions, other general conditions of the Developer, including:
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
0073 10-1
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Pagel of35
An Agreement
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
0073 10-2
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 2 of 35
b. Attachments to the Agreement
i. Bid Form
ii. Vendor Compliance with State Law Non -Resident Bidder
iii. Prequalification Statement
C. Current Prevailing Wage Rates Table (if required by City)
d. Insurance Accord Form
C. Payment Bond
f. Performance Bond
g. Maintenance Bond
h. Power of Attorney for Bonds
i. Workers Compensation Affidavit
j. MWBE Commitment Form( If required by City)
k. General Conditions
1. Supplementary Conditions
M. The Standard City Conditions
n. Specifications specifically made part of the Contract Documents by attachment, if
not attached, as incorporated by reference and described in the Table of Contents of
the Project's Contract Documents
o. Drawings
P. Documentation submitted by contractor prior to Notice of Award.
q. The following which may be delivered or issued after the effective date if the
Agreement and, if issued become an incorporated part of the Contract Documents
i. Notice to Proceed
ii. Field Orders
iii. Change Orders
iv. Letters of Final Acceptance
r. Approved Submittals, other Contractor submittals, and the reports and drawings of
subsurface and physical conditions are not Contract Documents.
10. Contractor —The individual or entity with whom Developer has entered into the Agreement.
11. Day or day —A day, unless otherwise defined, shall mean a Calendar Day.
12. Developer — An individual or entity that desires to make certain improvements within the
City of Fort Worth
13. Drawings —That part of the Contract Documents prepared or approved by Engineer which
graphically shows the scope, extent, and character of the Work to be performed by
Contractor. Submittals are not Drawings as so defined.
14. Engineer —The licensed professional engineer or engineering firm registered in the State of
Texas performing professional services for the Developer.
15. Final Acceptance — The written notice given by the City to the Developer and/or Contractor
that the Work specified in the Contract Documents has been completed to the satisfaction of
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
0073 10-2
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 2 of 35
the City.
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
0073 10-3
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 3 of 35
16. Final Inspection — Inspection carried out by the City to verify that the Contractor has
completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in
conformance with the Contract Documents.
17. General Requirements —A part of the Contract Documents between the Developer and a
Contractor.
18. Laws and Regulations Any and all applicable laws, rules, regulations, ordinances, codes,
and orders of any and all governmental bodies, agencies, authorities, and courts having
jurisdiction.
19. Liens —Charges, security interests, or encumbrances upon Project funds, real property, or
personal property.
20. Milestone —A principal event specified in the Contract Documents relating to an
intermediate Contract Time prior to Final Acceptance of the Work.
21. Non -Participating Change Order —A document, which is prepared for and reviewed by the
City, which is signed by Contractor, and Developer, and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of theAgreement.
22. Participating Change Order —A document, which is prepared for and approved by the City,
which is signed by Contractor, Developer, and City and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of theAgreement.
23. Plans — See definition of Drawings.
24. Project Schedule —A schedule, prepared and maintained by Contractor, in accordance with
the General Requirements, describing the sequence and duration of the activities comprising
the Contractor's plan to accomplish the Work within the Contract Time.
25. Project —The Work to be performed under the Contract Documents.
26. Project Representative —The authorized representative of the City who will be assigned to
the Site.
27. Public Meeting — An announced meeting conducted by the Developer to facilitate public
participation and to assist the public in gaining an informed view of theProject.
28. Regular Working Hours — Hours beginning at 7:00 a.m. and ending at 6:00 p.m., Monday
thru Friday (excluding legal holidays).
29. Samples Physical examples of materials, equipment, or workmanship that are
representative of some portion of the Work and which establish the standards by which such
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
0073 10-3
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 3 of 35
portion of the Work will bejudged.
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
0073 10-4
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 4 of 35
30. Schedule of Submittals —A schedule, prepared and maintained by Contractor, of required
submittals and the time requirements to support scheduled performance of related
construction activities.
31. Site —Lands or areas indicated in the Contract Documents as being furnished by City or
Developer upon which the Work is to be performed, including rights -of -way, permits, and
easements for access thereto, and such other lands furnished by City or Developer which are
designated for the use of Contractor.
32. Specifications —That part of the Contract Documents consisting of written requirements for
materials, equipment, systems, standards and workmanship as applied to the Work, and
certain administrative requirements and procedural matters applicable thereto.
Specifications may be specifically made a part of the Contract Documents by attachment or,
if not attached, may be incorporated by reference as indicated in the Table of Contents
(Division 00 00 00) of each Project.
33. Standard City Conditions — That part of the Contract Documents setting forth requirements
of the City.
34. Subcontractor An individual or entity having a direct contract with Contractor or with any
other Subcontractor for the performance of a part of the Work at theSite.
35. Submittals All drawings, diagrams, illustrations, schedules, and other data or information
which are specifically prepared or assembled by or for Contractor and submitted by
Contractor to illustrate some portion of the Work.
36. Superintendent — The representative of the Contractor who is available at all times and able
to receive instructions from the City and/or Developer and to act for the Contractor.
37. Supplementary Conditions —That part of the Contract Documents which amends or
supplements the General Conditions.
38. Supplier —A manufacturer, fabricator, supplier, distributor, materialman, or vendor having
a direct contract with Contractor or with any Subcontractor to furnish materials or
equipment to be incorporated in the Work by Contractor orSubcontractor.
39. Underground Facilities All underground pipelines, conduits, ducts, cables, wires,
manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any
encasements containing such facilities, including but not limited to, those that convey
electricity, gases, steam, liquid petroleum products, telephone or other communications,
cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or
other control systems.
40. Weekend Working Hours — Hours beginning at 9: 00 a. in. and ending at S: 00 p.m., Saturday,
Sunday or legal holiday, as approved in advance by the City.
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
0073 10-5
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 5 of 35
41. Work —The entire construction or the various separately identifiable parts thereof required
to be provided under the Contract Documents. Work includes and is the result of performing
or providing all labor, services, and documentation necessary to produce such construction
including any Participating Change Order, Non -Participating Change Order, or Field
Order, and furnishing, installing, and incorporating all materials and equipment into such
construction, all as required by the Contract Documents.
42. Working Day — A working day is defined as a day, not including Saturdays, Sundays, or
legal holidays authorized by the City for contract purposes, in which weather or other
conditions not under the control of the Contractor will permit the performance of the
principal unit of work underway for a continuous period of not less than 7 hours between 7
a.m. and 6 p.m.
1.02 Terminology
A. The words and terms discussed in Paragraph 1.023 through D are not defined but, when used in
the Bidding Requirements or Contract Documents, have the indicated meaning.
B. Defective:
1. The word "defective," when modifying the word "Work," refers to Work that is
unsatisfactory, faulty, or deficient in that it:
a. does not conform to the Contract Documents; or
b. does not meet the requirements of any applicable inspection, reference standard, test, or
approval referred to in the Contract Documents; or
c. has been damaged prior to City's written acceptance.
C. Furnish, Install, Perform, Provide:
1. The word "Furnish" or the word "Install" or the word "Perform" or the word "Provide" or
the word "Supply," or any combination or similar directive or usage thereof, shall mean
furnishing and incorporating in the Work including all necessary labor, materials, equipment,
and everything necessary to perform the Work indicated, unless specifically limited in the
context used.
D. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known
technical or construction industry or trade meaning are used in the Contract Documents in
accordance with such recognized meaning.
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
0073 10-6
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 6 of 35
ARTICLE 2 — PRELIMINARY MATTERS
2.01 Before Starting Construction
Baseline Schedules: Submit to City in accordance with the Contract Documents, and prior to starting
the Work. New schedules will be submitted to City when Participating Change Orders or Non -
Participating Change Orders occur.
2.02 Preconstruction Conference
Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as
specified in the Contract Documents.
2.03 Public Meeting
Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor
attending the Public Meeting as scheduled by the City.
ARTICLE 3 — CONTRACT DOCUMENTS AND AMENDING
3.01 Reference Standards
A. Standards, Specifications, Codes, Laws, and Regulations
1. Reference to standards, specifications, manuals, or codes of any technical society,
organization, or association, or to Laws or Regulations, whether such reference be specific or
by implication, shall mean the standard, specification, manual, code, or Laws or Regulations
in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there
were no Bids), except as may be otherwise specifically stated in the Contract Documents.
2. No provision or instruction shall be effective to assign to City, or any of its officers,
directors, members, partners, employees, agents, consultants, or subcontractors, any duty or
authority to supervise or direct the performance of the Work or any duty or authority to
undertake responsibility inconsistent with the provisions of the Contract Documents.
3.02 Amending and Supplementing Contract Documents
A. The Contract Documents may be amended to provide for additions, deletions, and revisions in
the Work or to modify the terms and conditions thereof by a Participating Change Order or a
Non -Participating Change Order.
B. The requirements of the Contract Documents may be supplemented, and minor variations and
deviations in the Work not involving a change in Contract Price or Contract Time, may be
authorized, by one or more of the following ways:
1. A Field Order;
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
0073 10-7
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 7 of 35
1. City's or Engineer's review of a Submittal (subject to the provisions of Paragraph 5.16.C); or
2. City's written interpretation or clarification.
ARTICLE 4 — BONDS AND INSURANCE
4.01 Licensed Sureties and Insurers
All bonds and insurance required by the Contract Documents to be purchased and maintained by
Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized
in the State of Texas to issue bonds or insurance policies for the limits and coverage so required.
Such surety and insurance companies shall also meet such additional requirements and qualifications
as may be provided Section 4.04.
4.02 Performance, Payment, and Maintenance Bonds
A. Contractor shall furnish performance and payment bonds in the name of Developer and City, in
accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount
equal to the Contract Price as security for the faithful performance and payment of all of
Contractor's obligations under the Contract Documents.
B. Contractor shall furnish maintenance bonds in the name of Developer and City in an amount
equal to the Contract Price as security to protect the City against any defects in any portion of the
Work described in the Contract Documents. Maintenance bonds shall remain in effect for two
(2) years after the date of Final Acceptance by the City.
C. All bonds shall be in the form prescribed by the Contract Documents except as provided
otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list
of "Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and
as Acceptable Reinsuring Companies" as published in Circular 570 (amended) by the Financial
Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed
by an agent or attorney -in -fact must be accompanied by a sealed and dated power of attorney
which shall show that it is effective on the date the agent or attorney -in -fact signed each bond.
D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or
its right to do business is terminated in the State of Texas or it ceases to meet the requirements of
Paragraph 4.02.C, Contractor shall promptly notify City and shall, within 30 days after the event
giving rise to such notification, provide another bond and surety, both of which shall comply
with the requirements of Paragraphs 4.01 and4.02.C.
4.03 Certificates of Insurance
Contractor shall deliver to Developer and City, with copies to each additional insured and loss payee
identified in these Standard City Conditions certificates of insurance (and other evidence of
insurance requested by City or any other additional insured) which Contractor is required to
purchase and maintain.
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
0073 10-8
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 8 of35
1. The certificate of insurance shall document the City, an as "Additional Insured" on all
liability policies.
2. The Contractor's general liability insurance shall include a, "per project" or "per location",
endorsement, which shall be identified in the certificate of insurance provided to the City.
3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the
insured, be complete in its entirety, and show complete insurance carrier names as listed in
the current A.M. Best Property & Casualty Guide
4. The insurers for all policies must be licensed and/or approved to do business in the State of
Texas. Except for workers' compensation, all insurers must have a minimum rating of A-:
VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial
strength and solvency to the satisfaction of Risk Management. If the rating is below that
required, written approval of City is required.
All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor
of the City. In addition, the Contractor agrees to waive all rights of subrogation against the
Engineer (if applicable), and each additional insured identified in these Standard City
Conditions. Failure of the City to demand such certificates or other evidence of full
compliance with the insurance requirements or failure of the City to identify a deficiency
from evidence that is provided shall not be construed as a waiver of Contractor's obligation
to maintain such lines of insurance coverage.
6. If insurance policies are not written for specified coverage limits, an Umbrella or Excess
Liability insurance for any differences is required. Excess Liability shall follow form of the
primary coverage.
7. Unless otherwise stated, all required insurance shall be written on the "occurrence basis". If
coverage is underwritten on a claims -made basis, the retroactive date shall be coincident with
or prior to the date of the effective date of the agreement and the certificate of insurance shall
state that the coverage is claims -made and the retroactive date. The insurance coverage shall
be maintained for the duration of the Contract and for three (3) years following Final
Acceptance provided under the Contract Documents or for the warranty period, whichever is
longer. An annual certificate of insurance submitted to the City shall evidence such
insurance coverage.
8. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the
required lines of coverage, nor decrease the limits of said coverage unless such endorsements
are approved in writing by the City. In the event a Contract has been bid or executed and the
exclusions are determined to be unacceptable or the City desires additional insurance
coverage, and the City desires the contractor/engineer to obtain such coverage, the contract
price shall be adjusted by the cost of the premium for such additional coverage plus 10%.
9. Any self -insured retention (SIR), in excess of $25,000.00, affecting required insurance
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
coverage shall be approved by the City in regards to asset value and stockholders' equity. In
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
0073 10-9
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 9 of 35
lieu of traditional insurance, alternative coverage maintained through insurance pools or risk
retention groups, must also be approved by City.
10. Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a
first -dollar basis, must be acceptable to and approved by the City.
11. City, at its sole discretion, reserves the right to review the insurance requirements and to
make reasonable adjustments to insurance coverage's and their limits when deemed
necessary and prudent by the City based upon changes in statutory law, court decision or the
claims history of the industry as well as of the contracting party to the City. The City shall
be required to provide prior notice of 90 days, and the insurance adjustments shall be
incorporated into the Work by Change Order.
12. City shall be entitled, upon written request and without expense, to receive copies of policies
and endorsements thereto and may make any reasonable requests for deletion or revision or
modifications of particular policy terms, conditions, limitations, or exclusions necessary to
conform the policy and endorsements to the requirements of the Contract. Deletions,
revisions, or modifications shall not be required where policy provisions are established by
law or regulations binding upon either party or the underwriter on any such policies.
13. City shall not be responsible for the direct payment of insurance premium costs for
Contractor's insurance.
4.04 Contractor's Insurance
A. Workers Compensation and Employers' Liability. Contractor shall purchase and maintain such
insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers'
Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for
Employers' Liability as is appropriate for the Work being performed and as will provide
protection from claims set forth below which may arise out of or result from Contractor's
performance of the Work and Contractor's other obligations under the Contract Documents,
whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly
or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts
any of them may be liable:
1. claims under workers' compensation, disability benefits, and other similar employee benefit
acts;
2. claims for damages because of bodily injury, occupational sickness or disease, or death of
Contractor's employees.
3. The limits of liability for the insurance shall provide the following coverages for not less
than the following amounts or greater where required by Laws and Regulations
a. Statutory limits
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
0073 10-9
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 9 of 35
b. Employer's liability
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
0073 10-10
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 10 of35
1) $100,000 each accident/occurrence
2) $100,000 Disease - each employee
3) $500,000 Disease - policy limit
B. Commercial General Liability. Coverage shall include but not be limited to covering liability
(bodily injury or property damage) arising from: premises/operations, independent contractors,
products/completed operations, personal injury, and liability under an insured contract. Insurance
shall be provided on an occurrence basis, and as comprehensive as the current Insurance
Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to
any other insurance or self-insurance programs afforded to the City. The Commercial General
Liability policy, shall have no exclusions by endorsements that would alter of nullify
premises/operations, products/completed operations, contractual, personal injury, or advertising
injury, which are normally contained with the policy, unless the City approves such exclusions
in writing.
1. For construction projects that present a substantial completed operation exposure, the City
may require the contractor to maintain completed operations coverage for a minimum of no
less than three (3) years following the completion of the project
2. Contractor's Liability Insurance under this Section which shall be on a per project basis
covering the Contractor with minimum limits of:
a. $1,000,000 eachoccurrence
b. $2,000,000 aggregate limit
3. The policy must have an endorsement (Amendment — Aggregate Limits of Insurance)
making the General Aggregate Limits apply separately to each job site.
4. The Commercial General Liability Insurance policies shall provide "X", "C", and "U"
coverage's. Verification of such coverage must be shown in the Remarks Article of the
Certificate of Insurance.
C. Automobile Liability. A commercial business auto policy shall provide coverage on "any auto",
defined as autos owned, hired and non -owned and provide indemnity for claims for damages
because bodily injury or death of any person and or property damage arising out of the work,
maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by
anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone
for whose acts any of them may be liable.
1. Automobile Liability, Contractor's Liability Insurance under this Section, which shall be in
an amount not less than the following amounts:
a. Automobile Liability - a commercial business policy shall provide coverage on "Any
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
0073 10-10
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 10 of35
Auto", defined as autos owned, hired andnon-owned.
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
0073 10-11
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 11 of35
1) $1, 000, 000 each accident on a combined single limit basis. Split limits are
acceptable if limits are at least:
2) $250,000 Bodily Injury per person
3) $500,000 Bodily Injury per accident /
4) $100,000 Property Damage
D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of
railroad right-of-way, the Contractor shall comply with the following requirements:
1. The Contractor's construction activities will require its employees, agents, subcontractors,
equipment, and material deliveries to cross railroad properties and tracks owned and
operated by: None
Write the name of the railroad company. (If none, then write none)
2. The Contractor shall conduct its operations on railroad properties in such a manner as not to
interfere with, hinder, or obstruct the railroad company in any manner whatsoever in the use
or operation of its/their trains or other property. Such operations on railroad properties may
require that Contractor to execute a "Right of Entry Agreement" with the particular railroad
company or companies involved, and to this end the Contractor should satisfy itself as to the
requirements of each railroad company and be prepared to execute the right -of -entry (if any)
required by a railroad company. The requirements specified herein likewise relate to the
Contractor's use of private and/or construction access roads crossing said railroad company's
properties.
3. The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions
shall provide coverage for not less than the following amounts, issued by companies
satisfactory to the City and to the Railroad Company for a term that continues for so long as
the Contractor's operations and work cross, occupy, or touch railroad property:
a. General Aggregate: None
Enter limits provided by Railroad Company (If none, write none)
b. Each Occurrence:: None
Enter limits provided by Railroad Company (If none, write none)
4. With respect to the above outlined insurance requirements, the following shall govern:
a. Where a single railroad company is involved, the Contractor shall provide one insurance
policy in the name of the railroad company. However, if more than one grade separation
or at -grade crossing is affected by the Project at entirely separate locations on the line or
lines of the same railroad company, separate coverage may be required, each in the
amount stated above.
b. Where more than one railroad company is operating on the same right-of-way or where
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
several railroad companies are involved and operated on their own separate rights -of -
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised January 10, 2013
0073 10-12
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 12 of35
way, the Contractor may be required to provide separate insurance policies in the name
of each railroad company.
c. If, in addition to a grade separation or an at -grade crossing, other work or activity is
proposed on a railroad company's right-of-way at a location entirely separate from the
grade separation or at -grade crossing, insurance coverage for this work must be included
in the policy covering the grade separation.
d. If no grade separation is involved but other work is proposed on a railroad company's
right-of-way, all such other work may be covered in a single policy for that railroad, even
though the work may be at two or more separate locations.
No work or activities on a railroad company's property to be performed by the Contractor
shall be commenced until the Contractor has furnished the City with an original policy or
policies of the insurance for each railroad company named, as required above. All such
insurance must be approved by the City and each affected Railroad Company prior to the
Contractor's beginning work.
6. The insurance specified above must be carried until all Work to be performed on the railroad
right-of-way has been completed and the grade crossing, if any, is no longer used by the
Contractor. In addition, insurance must be carried during all maintenance and/or repair work
performed in the railroad right-of-way. Such insurance must name the railroad company as
the insured, together with any tenant or lessee of the railroad company operating over tracks
involved in the Project.
E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation
or other loss of insurance coverage. Contractor shall stop work until replacement insurance has
been procured. There shall be no time credit for days not worked pursuant to this section.
4.05 Acceptance of Bonds and Insurance; Option to Replace
If City has any objection to the coverage afforded by or other provisions of the bonds or insurance
required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis
of non-conformance with the Contract Documents, the Developer and City shall so notify the
Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence
requested). Contractor shall provide to the City such additional information in respect of insurance
provided as the Developer or City may reasonably request. If Contractor does not purchase or
maintain all of the bonds and insurance required by the Contract Documents, the Developer or City
shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure
to maintain prior to any change in the required coverage.
ARTICLE 5 — CONTRACTOR'S RESPONSIBILITIES
5.01 Supervision and Superintendent
A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting
such attention thereto and applying such skills and expertise as may be necessary to perform the
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-13
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 13 of35
Work in accordance with the Contract Documents. Contractor shall be solely responsible for the
means, methods, techniques, sequences, and procedures of construction.
B. At all times during the progress of the Work, Contractor shall assign a competent, English-
speaking, Superintendent who shall not be replaced without written notice to City. The
Superintendent will be Contractor's representative at the Site and shall have authority to act on
behalf of Contractor. All communication given to or received from the Superintendent shall be
binding on Contractor.
C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of
construction.
5.02 Labor; Working Hours
A. Contractor shall provide competent, suitably qualified personnel to perform construction as
required by the Contract Documents. Contractor shall at all times maintain good discipline and
order at the Site.
B. Except as otherwise required for the safety or protection of persons or the Work or property at
the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work
at the Site shall be performed during Regular Working Hours. Contractor will not permit the
performance of Work beyond Regular Working Hours or for Weekend Working Hours without
City's written consent (which will not be unreasonably withheld). Written request (by letter or
electronic communication) to perform Work:
for beyond Regular Working Hours request must be made by noon at least two (2) Business
Days prior
2. for Weekend Working Hours request must be made by noon of the preceding Thursday
for legal holidays request must be made by noon two Business Days prior to the legal
holiday.
5.03 Services, Materials, and Equipment
A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full
responsibility for all services, materials, equipment, labor, transportation, construction
equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary
facilities, temporary facilities, and all other facilities and incidentals necessary for the
performance, Contractor required testing, start-up, and completion of the Work.
B. All materials and equipment incorporated into the Work shall be as specified or, if not specified,
shall be of good quality and new, except as otherwise provided in the Contract Documents. All
special warranties and guarantees required by the Specifications shall expressly run to the benefit
of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of
required tests) as to the source, kind, and quality of materials and equipment.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-14
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 14 of35
C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed,
connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of
the applicable Supplier, except as otherwise may be provided in the Contract Documents.
5.04 Project Schedule
A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.01
and the General Requirements as it may be adjusted from time to time as provided below.
1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.01 and
the General Requirements) proposed adjustments in the Project Schedule.
2. Proposed adjustments in the Project Schedule that will change the Contract Time shall be
submitted in accordance with the requirements of Article 9. Adjustments in Contract Time
for projects with City participation shall be made byparticipating change orders.
5.05 Substitutes and "Or -Equals"
A. Whenever an item of material or equipment is specified or described in the Contract Documents
by using the name of a proprietary item or the name of a particular Supplier, the specification or
description is intended to establish the type, function, appearance, and quality required. Unless
the specification or description contains or is followed by words reading that no like, equivalent,
or "or -equal" item or no substitution is permitted, other items of material or equipment of other
Suppliers may be submitted to City for review under the circumstances described below.
1. "Or -Equal" Items: If in City's sole discretion an item of material or equipment proposed by
Contractor is functionally equal to that named and sufficiently similar so that no change in
related Work will be required, it may be considered by City as an "or -equal" item, in which
case review and approval of the proposed item may, in City's sole discretion, be
accomplished without compliance with some or all of the requirements for approval of
proposed substitute items. For the purposes of this Paragraph 5.05.A.1, a proposed item of
material or equipment will be considered functionally equal to an item so named if.
a. City determines that:
1) it is at least equal in materials of construction, quality, durability, appearance,
strength, and design characteristics;
2) it will reliably perform at least equally well the function and achieve the results
imposed by the design concept of the completed Project as a functioning whole; and
3) it has a proven record of performance and availability of responsive service; and
b. Contractor certifies that, if approved and incorporated into the Work:
1) there will be no increase in cost to the City or increase in Contract Time; and
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-15
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 15 of35
2) it will conform substantially to the detailed requirements of the item named in the
Contract Documents.
2. Substitute Items:
a. If in City's sole discretion an item of material or equipment proposed by Contractor does
not qualify as an "or -equal" item under Paragraph 5.05.A.1, it may be submitted as a
proposed substitute item.
b. Contractor shall submit sufficient information as provided below to allow City to
determine if the item of material or equipment proposed is essentially equivalent to that
named and an acceptable substitute therefor. Requests for review of proposed substitute
items of material or equipment will not be accepted by City from anyone other than
Contractor.
c. Contractor shall make written application to City for review of a proposed substitute item
of material or equipment that Contractor seeks to furnish or use. The application shall
comply with Section 0125 00 and:
1) shall certify that the proposed substitute item will:
i. perform adequately the functions and achieve the results called for by the general
design;
ii. be similar in substance to that specified;
iii. be suited to the same use as that specified; and
2) will state:
i. the extent, if any, to which the use of the proposed substitute item will prejudice
Contractor's achievement of final completion on time;
ii. whether use of the proposed substitute item in the Work will require a change in
any of the Contract Documents (or in the provisions of any other direct contract
with City for other work on the Project) to adapt the design to the proposed
substitute item;
iii. whether incorporation or use of the proposed substitute item in connection with
the Work is subject to payment of any license fee or royalty; and
3) will identify:
i. all variations of the proposed substitute item from that specified;
ii. available engineering, sales, maintenance, repair, and replacement services; and
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-16
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 16 of35
4) shall contain an itemized estimate of all costs or credits that will result directly or
indirectly from use of such substitute item, including costs of redesign and Damage
Claims of other contractors affected by any resulting change.
B. Substitute Construction Methods or Procedures: If a specific means, method, technique,
sequence, or procedure of construction is expressly required by the Contract Documents,
Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure
of construction approved by City. Contractor shall submit sufficient information to allow City, in
City's sole discretion, to determine that the substitute proposed is equivalent to that expressly
called for by the Contract Documents. Contractor shall make written application to City for
review in the same manner as those provided in Paragraph 5.05.A.2.
C. City's Evaluation: City will be allowed a reasonable time within which to evaluate each
proposal or submittal made pursuant to Paragraphs 5.05.A and 5.05.13. City may require
Contractor to furnish additional data about the proposed substitute. City will be the sole judge of
acceptability. No "or -equal" or substitute will be ordered, installed or utilized until City's review
is complete, which will be evidenced by a Change Order in the case of a substitute and an
accepted Submittal for an "or -equal." City will advise Contractor in writing of its determination.
D. Special Guarantee: City may require Contractor to furnish at Contractor's expense a special
performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall
indemni and hold harmless City and anyone directly or indirectly employed by them from and
against any and all claims, damages, losses and expenses (including attorneys fees) arising out
of the use of substituted materials or equipment.
E. City's Cost Reimbursement: City will record City's costs in evaluating a substitute proposed or
submitted by Contractor pursuant to Paragraphs 5.05.A.2 and 5.05.13. Whether or not City
approves a substitute so proposed or submitted by Contractor, Contractor may be required to
reimburse City for evaluating each such proposed substitute. Contractor may also be required to
reimburse City for the charges for making changes in the Contract Documents.
F. Contractor's Expense: Contractor shall provide all data in support of any proposed substitute or
"or -equal" at Contractor's expense.
G. Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute
shall be incorporated to the Contract by Participating Change Order.
5.06 Pre -Qualification of Bidders (Prime Contractors and Subcontractors)
A. The Contractor and any subcontractors are required to be prequalified for the work types
requiring pre -qualification
5.07 Concerning Subcontractors, Suppliers, and Others
A. Minority and Women Owned Business Enterprise Compliance:
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-17
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 17 of35
❑ Required for this Contract.
(Check this box if there is any City Participation)
® Not Required for this Contract.
It is City policy to ensure the full and equitable participation by Minority and Women Business
Enterprises (MWBE) in the procurement of goods and services on a contractual basis. If the
Contract Documents provide for a MWBE goal, Contractor is required to comply with the intent
of the City's MWBE Ordinance (as amended) by the following:
1. Contractor shall, upon request by City, provide complete and accurate information regarding
actual work performed by a MWBE on the Contract and payment therefor.
2. Contractor will not make additions, deletions, or substitutions of accepted MWBE without
written consent of the City. Any unjustified change or deletion shall be a material breach of
Contract and may result in debarment in accordance with the procedures outlined in the
Ordinance.
3. Contractor shall, upon request by City, allow an audit and/or examination of any books,
records, or files in the possession of the Contractor that will substantiate the actual work
performed by an MWBE. Material misrepresentation of any nature will be grounds for
termination of the Contract. Any such misrepresentation may be grounds for disqualification
of Contractor to bid on future contracts with the City for a period of not less than three years.
B. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors,
Suppliers, and other individuals or entities performing or furnishing any of the Work just as
Contractor is responsible for Contractor's own acts and omissions. Nothing in the Contract
Documents:
1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity
any contractual relationship between City and any such Subcontractor, Supplier or other
individual or entity; nor
2. shall create any obligation on the part of City to pay or to see to the payment of any moneys
due any such Subcontractor, Supplier, or other individual or entity except as may otherwise
be required by Laws and Regulations.
C. Contractor shall be solely responsible for scheduling and coordinating the Work of
Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the
Work under a direct or indirect contract with Contractor.
D. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing
any of the Work shall communicate with City through Contractor.
E. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an
appropriate agreement between Contractor and the Subcontractor or Supplier which specifically
binds the Subcontractor or Supplier to the applicable terms and conditions of these Contract
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-18
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 18 of35
Documents, Contractor shall provide City contract numbers and reference numbers to the
Subcontractors and/or Suppliers.
5.08 Wage Rates
❑ Required for this Contract.
® Not Required for this Contract.
A. Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of
Chapter 2258, Texas Government Code (as amended), including the payment of not less than the
rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in
accordance with Chapter 2258. Such prevailing wage rates are included in these Contract
Documents.
B. Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage
shall, upon demand made by the City, pay to the City $60 for each worker employed for each
calendar day or part of the day that the worker is paid less than the prevailing wage rates
stipulated in these contract documents. This penalty shall be retained by the City to offset its
administrative costs, pursuant to Texas Government Code 2258.023.
C. Complaints of Violations and City Determination of Good Cause. On receipt of information,
including a complaint by a worker, concerning an alleged violation of 2258.023, Texas
Government Code, by a Contractor or Subcontractor, the City shall make an initial
determination, before the 31 st day after the date the City receives the information, as to whether
good cause exists to believe that the violation occurred. The City shall notify in writing the
Contractor or Subcontractor and any affected worker of its initial determination. Upon the
City's determination that there is good cause to believe the Contractor or Subcontractor has
violated Chapter 2258, the City shall retain the full amounts claimed by the claimant or
claimants as the difference between wages paid and wages due under the prevailing wage rates,
such amounts being subtracted from successive progress payments pending a final determination
of the violation.
D. Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of
Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected
worker, shall be submitted to binding arbitration in accordance with the Texas General
Arbitration Act (Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any
affected worker does not resolve the issue by agreement before the 15th day after the date the
City makes its initial determination pursuant to Paragraph C above. If the persons required to
arbitrate under this section do not agree on an arbitrator before the 11th day after the date that
arbitration is required, a district court shall appoint an arbitrator on the petition of any of the
persons. The City is not a party in the arbitration. The decision and award of the arbitrator is
final and binding on all parties and may be enforced in any court of competent jurisdiction.
E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3)
years following the date of acceptance of the work, maintain records that show (i) the name and
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-19
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 19 of35
occupation of each worker employed by the Contractor in the construction of the Work provided
for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be
open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right
to Audit, shall pertain to this inspection.
F. Progress Payments. With each progress payment or payroll period, whichever is less, the
Contractor shall submit an affidavit stating that the Contractor has complied with the
requirements of Chapter 2258, Texas Government Code.
G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at
all times.
H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall
otherwise require all of its Subcontractors to comply with Paragraphs A through G above.
5.09 Patent Fees and Royalties
A. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold
harmless City, from and against all claims, costs, losses, and damages (including but not limited
to all fees and charges of engineers, architects, attorneys, and other professionals and all court
or arbitration or other dispute resolution costs) arising out of or relating to any infringement of
patent rights or copyrights incident to the use in the performance of the Work or resulting from
the incorporation in the Work of any invention, design, process, product, or device not specified
in the Contract Documents.
5.10 Laws and Regulations
A. Contractor shall give all notices required by and shall comply with all Laws and Regulations
applicable to the performance of the Work. Except where otherwise expressly required by
applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor's
compliance with any Laws or Regulations.
B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws
or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such Work.
However, it shall not be Contractor's responsibility to make certain that the Specifications and
Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of
Contractor's obligations under Paragraph 3.01.
5.11 Use of Site and OtherAreas
A. Limitation on Use of Site and OtherAreas:
1. Contractor shall confine construction equipment, the storage of materials and equipment, and
the operations of workers to the Site and other areas permitted by Laws and Regulations, and
shall not unreasonably encumber the Site and other areas with construction equipment or
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-20
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 20 of35
other materials or equipment. Contractor shall assume full responsibility for any damage to
any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas
resulting from the performance of the Work.
2 At any time when, in the judgment of the City, the Contractor has obstructed or closed or is
carrying on operations in a portion of a street, right-of-way, or easement greater than is
necessary for proper execution of the Work, the City may require the Contractor to finish the
section on which operations are in progress before work is commenced on any additional
area of the Site.
3. Should any Damage Claim be made by any such owner or occupant because of the
performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim.
4. Pursuant to Paragraph 5.18, Contractor shall indemnify and hold harmless City, from and
against all claims, costs, losses, and damages arising out of or relating to any claim or
action, legal or equitable, brought by any such owner or occupant against City.
B. Removal of Debris During Performance of the Work: During the progress of the Work
Contractor shall keep the Site and other areas free from accumulations of waste materials,
rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other
debris shall conform to applicable Laws and Regulations.
C. Site Maintenance Cleaning: 24 hours after written notice is given to the Contractor that the clean-
up on the job site is proceeding in a manner unsatisfactory to the City or Developer, if the
Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as
the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the
written notice (by letter or electronic communication), and shall be entitled to recover its cost in
doing so. The City may withhold Final Acceptance until clean-up is complete and cost are
recovered.
D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and
the Work and make it ready for utilization by City or adjacent property owner. At the completion
of the Work Contractor shall remove from the Site all tools, appliances, construction equipment
and machinery, and surplus materials and shall restore to original condition or better all property
disturbed by the Work.
E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded
in any manner that will endanger the structure, nor shall Contractor subject any part of the Work
or adjacent property to stresses or pressures that will endanger it.
5.12 Record Documents
A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor
and approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change
Orders, Field Orders, and written interpretations and clarifications in good order and annotated
to show changes made during construction. These record documents together with all approved
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-21
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 21 of35
Samples and a counterpart of all accepted Submittals will be available to City for reference.
Upon completion of the Work, these record documents, any operation and maintenance manuals,
and Submittals will be delivered to City prior to Final Inspection. Contractor shall include
accurate locations for buried and imbedded items.
5.13 Safety and Protection
A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety
precautions and programs in connection with the Work. Such responsibility does not relieve
Subcontractors of their responsibility for the safety of persons or property in the performance of
their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall
take all necessary precautions for the safety of, and shall provide the necessary protection to
prevent damage, injury or loss to:
1. all persons on the Site or who may be affected by the Work;
2. all the Work and materials and equipment to be incorporated therein, whether in storage on
or off the Site; and
other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks,
pavements, roadways, structures, utilities, and Underground Facilities not designated for
removal, relocation, or replacement in the course of construction.
B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of
persons or property, or to the protection of persons or property from damage, injury, or loss; and
shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall
notify owners of adjacent property and of Underground Facilities and other utility owners when
prosecution of the Work may affect them, and shall cooperate with them in the protection,
removal, relocation, and replacement of their property.
C. Contractor shall comply with the applicable requirements of City's safety programs, if any.
D. Contractor shall inform City of the specific requirements of Contractor's safety program, if any,
with which City's employees and representatives must comply while at the Site.
E. All damage, injury, or loss to any property referred to in Paragraph 5.13.A.2 or 5.13.A.3 caused,
directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any
other individual or entity directly or indirectly employed by any of them to perform any of the
Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor.
F. Contractor's duties and responsibilities for safety and for protection of the Work shall continue
until such time as all the Work is completed and City has accepted the Work.
5.14 Safety Representative
Contractor shall inform City in writing of Contractor's designated safety representative at the Site.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-22
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 22 of35
5.15 Hazard Communication Programs
Contractor shall be responsible for coordinating any exchange of material safety data sheets or other
hazard communication information required to be made available to or exchanged between or
among employers in accordance with Laws or Regulations.
5.16 Submittals
A. Contractor shall submit required Submittals to City for review and acceptance. Each submittal
will be identified as required by City.
1. Submit number of copies specified in the General Requirements.
2. Data shown on the Submittals will be complete with respect to quantities, dimensions,
specified performance and design criteria, materials, and similar data to show City the
services, materials, and equipment Contractor proposes to provide and to enable City to
review the information for the limited purposes required by Paragraph 5.16.C.
3. Submittals submitted as herein provided by Contractor and reviewed by City for
conformance with the design concept shall be executed in conformity with the Contract
Documents unless otherwise required by City.
4. When Submittals are submitted for the purpose of showing the installation in greater detail,
their review shall not excuse Contractor from requirements shown on the Drawings and
Specifications.
5. For -Information -Only submittals upon which the City is not expected to conduct review or
take responsive action may be so identified in the Contract Documents.
6. Submit required number of Samples specified in the Specifications.
7. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers,
the use for which intended and other data as City may require to enable City to review the
submittal for the limited purposes required by Paragraph 5.16.C.
B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any
related Work performed prior to City's review and acceptance of the pertinent submittal will be
at the sole expense and responsibility of Contractor.
C. City's Review:
1. City will provide timely review of required Submittals in accordance with the Schedule of
Submittals acceptable to City. City's review and acceptance will be only to determine if the
items covered by the submittals will, after installation or incorporation in the Work, conform
to the information given in the Contract Documents and be compatible with the design
concept of the completed Project as a functioning whole as indicated by the Contract
Documents.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-23
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 23 of35
2. City's review and acceptance will not extend to means, methods, techniques, sequences, or
procedures of construction (except where a particular means, method, technique, sequence,
or procedure of construction is specifically and expressly called for by the Contract
Documents) or to safety precautions or programs incident thereto. The review and
acceptance of a separate item as such will not indicate approval of the assembly in which the
item functions.
3. City's review and acceptance shall not relieve Contractor from responsibility for any
variation from the requirements of the Contract Documents unless Contractor has complied
with the requirements of Section 01 33 00 and City has given written acceptance of each
such variation by specific written notation thereof incorporated in or accompanying the
Submittal. City's review and acceptance shall not relieve Contractor from responsibility for
complying with the requirements of the Contract Documents.
5.17 Contractor's General Warranty and Guarantee
A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract
Documents and will not be defective. City and its officers, directors, members, partners,
employees, agents, consultants, and subcontractors shall be entitled to rely on representation of
Contractor's warranty and guarantee.
B. Contractor's warranty and guarantee hereunder excludes defects or damage causedby:
1. abuse, modification, or improper maintenance or operation by persons other than Contractor,
Subcontractors, Suppliers, or any other individual or entity for whom Contractor is
responsible; or
2. normal wear and tear under normal usage.
C. Contractor's obligation to perform and complete the Work in accordance with the Contract
Documents shall be absolute. None of the following will constitute an acceptance of Work that is
not in accordance with the Contract Documents or a release of Contractor's obligation to
perform the Work in accordance with the Contract Documents:
1. observations by City;
2. recommendation or payment by City or Developer of any progress or finalpayment;
3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by
City;
4. use or occupancy of the Work or any part thereof by City;
5. any review and acceptance of a Submittal by City;
6. any inspection, test, or approval by others; or
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-24
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 24 of35
7. any correction of defective Work by City.
D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to
other work or property resulting therefrom which shall appear within a period of two (2) years
from the date of Final Acceptance of the Work unless a longer period is specified and shall
furnish a good and sufficient maintenance bond, complying with the requirements of Article
4.02.13. The City will give notice of observed defects with reasonable promptness.
5.18 Indemnification
A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the
City, its officers, servants and employees, from and against any and all claims arising out of, or
alleged to arise out of, the work and services to be performed by the Contractor, its officers,
agents, employees, subcontractors, licenses or invitees under this Contract. THIS
INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE
AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME
OF THE DAMAGES BEING SOUGHT WERE CAUSED. IN WHOLE OR IN PART. BY
ANY ACT. OMISSION OR NEGLIGENCE OF THE CITY. This indemnity provision is
intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by
the City in defending against such claims and causes ofactions.
B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its
officers, servants and employees, from and against any and all loss, damage or destruction of
property of the City, arising out of, or alleged to arise out of, the work and services to be
performed by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees
under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY
INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR
PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE
CAUSED. IN WHOLE OR IN PART. BY ANY ACT. OMISSION OR NEGLIGENCE OF
THE CITY.
5.19 Delegation of Professional Design Services
A. Contractor will not be required to provide professional design services unless such services are
specifically required by the Contract Documents for a portion of the Work or unless such
services are required to carry out Contractor's responsibilities for construction means, methods,
techniques, sequences and procedures.
B. If professional design services or certifications by a design professional related to systems,
materials or equipment are specifically required of Contractor by the Contract Documents, City
will specify all performance and design criteria that such services must satisfy. Contractor shall
cause such services or certifications to be provided by a properly licensed professional, whose
signature and seal shall appear on all drawings, calculations, specifications, certifications, and
Submittals prepared by such professional. Submittals related to the Work designed or certified
by such professional, if prepared by others, shall bear such professional's written approval when
submitted to City.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-25
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 25 of35
C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services,
certifications or approvals performed by such design professionals, provided City has specified
to Contractor performance and design criteria that such services must satisfy.
D. Pursuant to this Paragraph 5.19, City's review and acceptance of design calculations and design
drawings will be only for the limited purpose of checking for conformance with performance
and design criteria given and the design concept expressed in the Contract Documents. City's
review and acceptance of Submittals (except design calculations and design drawings) will be
only for the purpose stated in Paragraph 5.16.C.
5.20 Right to Audit:
A. The City reserves the right to audit all projects utilizing Cityfunds
B. The Contractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of the Contractor involving transactions relating
to this Contract. Contractor agrees that the City shall have access during Regular Working Hours
to all necessary Contractor facilities and shall be provided adequate and appropriate work space
in order to conduct audits in compliance with the provisions of this Paragraph. The City shall
give Contractor reasonable advance notice of intended audits.
C. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that
the subcontractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of such Subcontractor, involving transactions to
the subcontract, and further, that City shall have access during Regular Working Hours to all
Subcontractor facilities, and shall be provided adequate and appropriate work space in order to
conduct audits in compliance with the provisions of this Paragraph. The City shall give
Subcontractor reasonable advance notice of intended audits.
D. Contractor and Subcontractor agree to photocopy such documents as may be requested by the
City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate
published in the Texas Administrative Code in effect as of the time copying is performed.
5.21 Nondiscrimination
A. The City is responsible for operating Public Transportation Programs and implementing transit -
related projects, which are funded in part with Federal financial assistance awarded by the U.S.
Department of Transportation and the Federal Transit Administration (FTA), without
discriminating against any person in the United States on the basis of race, color, or national
origin.
B. Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of
the Act and the Regulations as further defined in the Supplementary Conditions for any project
receiving Federal assistance.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-26
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 26 of35
ARTICLE 6 — OTHER WORK AT THE SITE
6.01 Related Work at Site
A. City may perform other work related to the Project at the Site with City's employees, or other
City contractors, or through other direct contracts therefor, or have other work performed by
utility owners. If such other work is not noted in the Contract Documents, then written notice
thereof will be given to Contractor prior to starting any such other work; and
B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility
owner, and City, if City is performing other work with City's employees or other City
contractors, proper and safe access to the Site, provide a reasonable opportunity for the
introduction and storage of materials and equipment and the execution of such other work, and
properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of
the Work that may be required to properly connect or otherwise make its several parts come
together and properly integrate with such other work. Contractor shall not endanger any work of
others by cutting, excavating, or otherwise altering such work; provided, however, that
Contractor may cut or alter others' work with the written consent of City and the others whose
work will be affected.
C. If the proper execution or results of any part of Contractor's Work depends upon work
performed by others under this Article 7, Contractor shall inspect such other work and promptly
report to City in writing any delays, defects, or deficiencies in such other work that render it
unavailable or unsuitable for the proper execution and results of Contractor's Work. Contractor's
failure to so report will constitute an acceptance of such other work as fit and proper for
integration with Contractor's Work except for latent defects in the work provided by others.
ARTICLE 7 — CITY'S RESPONSIBILITIES
7.01 Inspections, Tests, and Approvals
City's responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph
11.03.
7.02 Limitations on City's Responsibilities
A. The City shall not supervise, direct, or have control or authority over, nor be responsible for,
Contractor's means, methods, techniques, sequences, or procedures of construction, or the safety
precautions and programs incident thereto, or for any failure of Contractor to comply with Laws
and Regulations applicable to the performance of the Work. City will not be responsible for
Contractor's failure to perform the Work in accordance with the Contract Documents.
B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 5.13.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-27
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 27 of35
7.03 Compliance with Safety Program
While at the Site, City's employees and representatives shall comply with the specific applicable
requirements of Contractor's safety programs of which City has been informed pursuant to
Paragraph 5.13.
ARTICLE 8 — CITY'S OBSERVATION STATUS DURING CONSTRUCTION
8.01 City's Project Representative
City will provide one or more Project Representative(s) during the construction period. The duties
and responsibilities and the limitations of authority of City's representative during construction are
set forth in the Contract Documents.
A. City's Project Representative will make visits to the Site at intervals appropriate to the various
stages of construction as City deems necessary in order to observe the progress that has been
made and the quality of the various aspects of Contractor's executed Work. Based on
information obtained during such visits and observations, City's Project Representative will
determine, in general, if the Work is proceeding in accordance with the Contract Documents.
City's Project Representative will not be required to make exhaustive or continuous inspections
on the Site to check the quality or quantity of the Work. City's Project Representative's efforts
will be directed toward providing City a greater degree of confidence that the completed Work
will conform generally to the Contract Documents.
B. City's Project Representative's visits and observations are subject to all the limitations on
authority and responsibility in the Contract Documents.
8.02 Authorized Variations in Work
City's Project Representative may authorize minor variations in the Work from the requirements of
the Contract Documents which do not involve an adjustment in the Contract Price or the Contract
Time and are compatible with the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. These may be accomplished by a Field Order and will be
binding on City Developer, and also on Contractor, who shall perform the Work involved promptly.
8.03 Rejecting Defective Work
City will have authority to reject Work which City's Project Representative believes to be defective,
or will not produce a completed Project that conforms to the Contract Documents or that will
prejudice the integrity of the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. City will have authority to conduct special inspection or
testing of the Work as provided in Article 11, whether or not the Work is fabricated, installed, or
completed.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-28
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 28 of35
8.04 Determinationsfor Work Performed
Contractor will determine the actual quantities and classifications of Work performed. City's Project
Representative will review with Contractor the preliminary determinations on such matters before
rendering a written recommendation. City's written decision will be final (except as modified to
reflect changed factual conditions or more accurate data).
ARTICLE 9 — CHANGES IN THE WORK
9.01 Authorized Changes in the Work
A. Without invalidating the Contract and without notice to any surety, City may, at any time or
from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall
promptly proceed with the Work involved which will be performed under the applicable
conditions of the Contract Documents (except as otherwise specifically provided). Extra Work
shall be memorialized by a Participating Change Order which may or may not precede an order
of Extra work.
B. For minor changes of Work not requiring changes to Contract Time or Contract Price on a
project with City participation, a Field Order may be issued by the City.
9.02 Notification to Surety
If the provisions of any bond require notice to be given to a surety of any change affecting the
general scope of the Work or the provisions of the Contract Documents (including, but not limited
to, Contract Price or Contract Time), the giving of any such notice will be Contractor's
responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the
effect of any such change.
ARTICLE 10 — CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME
10.01 Change of Contract Price
A. The Contract Price may only be changed by a Participating Change Order for projects with City
participation.
10.02 Change of Contract Time
A. The Contract Time may only be changed by a Participating Change Order for projects with City
participation.
10.03 Delays
A. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or
damages (including but not limited to all fees and charges of engineers, architects, attorneys, and
other professionals and all court or arbitration or other dispute resolution costs) sustained by
Contractor on or in connection with any other project or anticipatedproject.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-29
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 29 of35
ARTICLE 11— TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK
11.01 Notice of Defects
Notice of all defective Work of which City has actual knowledge will be given to Contractor.
Defective Work may be rejected, corrected, or accepted as provided in this Article 13.
11.02 Access to Work
City, independent testing laboratories, and governmental agencies with jurisdictional interests will
have access to the Site and the Work at reasonable times for their observation, inspection, and
testing. Contractor shall provide them proper and safe conditions for such access and advise them of
Contractor's safety procedures and programs so that they may comply therewith as applicable.
11.03 Tests and Inspections
A. Contractor shall give City timely notice of readiness of the Work for all required inspections,
tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required
inspections or tests.
B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any
of the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full
responsibility for arranging and obtaining such independent inspections, tests, retests or
approvals, pay all costs in connection therewith, and furnish City the required certificates of
inspection or approval; excepting, however, those fees specifically identified in the
Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR)
inspections, which shall be paid as described in the Supplementary Conditions.
C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection
with any inspections, tests, re -tests, or approvals required for City's acceptance of materials or
equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment
submitted for approval prior to Contractor's purchase thereof for incorporation in the Work.
Such inspections, tests, re -tests, or approvals shall be performed by organizations approved by
City.
D. City may arrange for the services of an independent testing laboratory ("Testing Lab") to
perform any inspections or tests ("Testing") for any part of the Work, as determined solely by
City.
1. City will coordinate such Testing to the extent possible, with Contractor;
2. Should any Testing under this Section 11.03 D result in a "fail", "did not pass" or other
similar negative result, the Contractor shall be responsible for paying for any and all retests.
Contractor's cancellation without cause of City initiated Testing shall be deemed a negative
result and require a retest.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-30
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 30 of35
3. Any amounts owed for any retest under this Section 11.03 D shall be paid directly to the
Testing Lab by Contractor. City will forward all invoices for retests to
Developer/Contractor.
4. If Contractor fails to pay the Testing Lab, City will not issue a letter of Final Acceptance
until the Testing Lab is Paid
E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by
Contractor without written concurrence of City, Contractor shall, if requested by City, uncover
such Work for observation.
11.04 Uncovering Work
A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it
must, if requested by City, be uncovered for City's observation and replaced at Contractor's
expense.
11.05 City May Stop the Work
If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials
or equipment, or fails to perform the Work in such a way that the completed Work will conform to
the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until
the cause for such order has been eliminated; however, this right of City to stop the Work shall not
give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any
Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent
of any of them.
11.06 Correction or Removal of Defective Work
A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to
an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has
been rejected by City, remove it from the Project and replace it with Work that is not defective.
Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such correction
or removal (including but not limited to all costs of repair or replacement of work of others).
Failure to require the removal of any defective Work shall not constitute acceptance of such
Work.
B. When correcting defective Work under the terms of this Paragraph 11.06 or Paragraph 11.07,
Contractor shall take no action that would void or otherwise impair City's special warranty and
guarantee, if any, on said Work.
11.07 Correction Period
A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may
be prescribed by the terms of any applicable special guarantee required by the Contract
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-31
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 31 of35
Documents), any Work is found to be defective, or if the repair of any damages to the land or
areas made available for Contractor's use by City or permitted by Laws and Regulations as
contemplated in Paragraph 5.10.A is found to be defective, Contractor shall promptly, without
cost to City and in accordance with City's written instructions:
1. repair such defective land or areas; or
2. correct such defective Work; or
3. if the defective Work has been rejected by City, remove it from the Project and replace it
with Work that is not defective, and
4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work
of others or other land or areas resulting therefrom.
B. If Contractor does not promptly comply with the terms of City's written instructions, or in an
emergency where delay would cause serious risk of loss or damage, City may have the defective
Work corrected or repaired or may have the rejected Work removed and replaced. All claims,
costs, losses, and damages (including but not limited to all fees and charges of engineers,
architects, attorneys, and other professionals and all court or other dispute resolution costs)
arising out of or relating to such correction or repair or such removal and replacement (including
but not limited to all costs of repair or replacement of work of others) will be paid by Contractor.
C. Where defective Work (and damage to other Work resulting therefrom) has been corrected or
removed and replaced under this Paragraph 11.07, the correction period hereunder with respect
to such Work may be required to be extended for an additional period of one year after the end
of the initial correction period. City shall provide 30 days written notice to Contractor and
Developer should such additional warranty coverage be required. Contractor's obligations under
this Paragraph 11.07 are in addition to any other obligation or warranty. The provisions of this
Paragraph 11.07 shall not be construed as a substitute for, or a waiver of, the provisions of any
applicable statute of limitation or repose.
11.08 City May Correct Defective Work
A. If Contractor fails within a reasonable time after written notice from City to correct defective
Work, or to remove and replace rejected Work as required by City in accordance with Paragraph
11.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents,
or if Contractor fails to comply with any other provision of the Contract Documents, City may,
after seven (7) days written notice to Contractor and the Developer, correct, or remedy any such
deficiency.
B. In exercising the rights and remedies under this Paragraph 11.09, City shall proceed
expeditiously. In connection with such corrective or remedial action, City may exclude
Contractor from all or part of the Site, take possession of all or part of the Work and suspend
Contractor's services related thereto, and incorporate in the Work all materials and equipment
incorporated in the Work, stored at the Site or for which City has paid Contractor but which are
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-32
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 32 of 35
stored elsewhere. Contractor shall allow City, City's representatives, agents, consultants,
employees, and City's other contractors, access to the Site to enable City to exercise the rights
and remedies under this Paragraph.
C. All claims, costs, losses, and damages (including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals and all court or other dispute resolution
costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph
13.09 will be charged against Contractor, and a Change Order will be issued incorporating the
necessary revisions in the Contract Documents with respect to the Work; and City shall be
entitled to an appropriate decrease in the Contract Price.
D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the
performance of the Work attributable to the exercise of City's rights and remedies under this
Paragraph 11.09.
ARTICLE 12 — COMPLETION
12.01 Contractor's Warranty of Title
Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any
Application for Payment will pass to City no later than the time of Final Acceptance and shall be
free and clear of all Liens.
12.02 Partial Utilization
A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed
part of the Work which has specifically been identified in the Contract Documents, or which
City, determines constitutes a separately functioning and usable part of the Work that can be
used by City for its intended purpose without significant interference with Contractor's
performance of the remainder of the Work. City at any time may notify Contractor in writing to
permit City to use or occupy any such part of the Work which City determines to be ready for its
intended use, subject to the following conditions:
1. Contractor at any time may notify City in writing that Contractor considers any such part of
the Work ready for its intended use.
2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and
Contractor shall make an inspection of that part of the Work to determine its status of
completion. If City does not consider that part of the Work to be substantially complete, City
will notify Contractor in writing giving the reasons therefor.
3. Partial Utilization will not constitute Final Acceptance by City.
12.03 Final Inspection
A. Upon written notice from Contractor that the entire Work is complete in accordance with the
Contract Documents:
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-33
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 33 of 35
1. within 10 days, City will schedule a Final Inspection with Contractor.
2. City will notify Contractor in writing of all particulars in which this inspection reveals that
the Work is incomplete or defective. Contractor shall immediately take such measures as are
necessary to complete such Work or remedy such deficiencies.
12.04 Final Acceptance
A. Upon completion by Contractor to City's satisfaction, of any additional Work identified in the
Final Inspection, City will issue to Contractor a letter of Final Acceptance upon the satisfaction
of the following:
1. All documentation called for in the Contract Documents, including but not limited to the
evidence of insurance required by Paragraph 5.03;
2 consent of the surety, if any, to Final Acceptance;
3. a list of all pending or released Damage Claims against City that Contractor believes are
unsettled; and
4. affidavits of payments and complete and legally effective releases or waivers (satisfactory to
City) of all Lien rights arising out of or Liens filed in connection with the Work.
5. after all Damage Claims have been resolved:
a. directly by the Contractor or;
b. Contractor provides evidence that the Damage Claim has been reported to Contractor's
insurance provider for resolution.
6. Issuing Final Acceptance by the City shall not relieve the Contractor of any guarantees or
other requirements of the Contract Documents which specifically continue thereafter.
ARTICLE 13 — SUSPENSION OF WORK
13.01 City May Suspend Work
A. At any time and without cause, City may suspend the Work or any portion thereof by written
notice to Contractor and which may fix the date on which Work will be resumed. Contractor
shall resume the Work on the date so fixed. During temporary suspension of the Work covered
by these Contract Documents, for any reason, the City will stop contract time on City
participation projects.
B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the
control of and without the fault or negligence of the Contractor, and should it be determined by
mutual consent of the Contractor and City that a solution to allow construction to proceed is not
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-34
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 34 of 35
available within a reasonable period of time, Contractor may request an extension in Contract
Time, directly attributable to any such suspension.
C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall
store all materials in such a manner that they will not obstruct or impede the public unnecessarily
nor become damaged in any way, and he shall take every precaution to prevent damage or
deterioration of the work performed; he shall provide suitable drainage about the work, and erect
temporary structures where necessary.
ARTICLE 14 — MISCELLANEOUS
14.01 Giving Notice
A. Whenever any provision of the Contract Documents requires the giving of written notice, it will
be deemed to have been validly given if:
1. delivered in person to the individual or to a member of the firm or to an officer of the
corporation for whom it is intended; or
2. delivered at or sent by registered or certified mail, postage prepaid, to the last business
address known to the giver of the notice.
B. Business address changes must be promptly made in writing to the otherparty.
C. Whenever the Contract Documents specifies giving notice by electronic means such electronic
notice shall be deemed sufficient upon confirmation of receipt by the receivingparty.
14.02 Computation of Times
When any period of time is referred to in the Contract Documents by days, it will be computed to
exclude the first and include the last day of such period. If the last day of any such period falls on a
Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last
day of the period.
14.03 Cumulative Remedies
The duties and obligations imposed by these General Conditions and the rights and remedies
available hereunder to the parties hereto are in addition to, and are not to be construed in any way as
a limitation of, any rights and remedies available to any or all of them which are otherwise imposed
or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the
Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically
in the Contract Documents in connection with each particular duty, obligation, right, and remedy to
which they apply.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-35
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 35 of 35
14.04 Survival of Obligations
All representations, indemnifications, warranties, and guarantees made in, required by, or given in
accordance with the Contract Documents, as well as all continuing obligations indicated in the
Contract Documents, will survive final payment, completion, and acceptance of the Work or
termination or completion of the Contract or termination of the services of Contractor.
14.05 Headings
Article and paragraph headings are inserted for convenience only and do not constitute parts of these
General Conditions.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1
2
3 PART1- GENERAL
4 1.1 SUMMARY
SECTION 01 1100
SUMMARY OF WORK
011100-1
DAP SUMMARY OF WORK
Page 1 of 3
5 A. Section Includes:
6 1. Summary of Work to be performed in accordance with the Contract Documents
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract
11 2. Division 1 - General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurement and Payment
14 1. Work associated with this Item is considered subsidiary to the various items bid.
15 No separate payment will be allowed for this Item.
16 1.3 REFERENCES [NOT USED]
17 1.4 ADMINISTRATIVE REQUIREMENTS
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
A. Work Covered by Contract Documents
1. Work is to include furnishing all labor, materials, and equipment, and performing
all Work necessary for this construction project as detailed in the Drawings and
Specifications.
B. Subsidiary Work
1. Any and all Work specifically governed by documentary requirements for the
project, such as conditions imposed by the Drawings or Contract Documents in
which no specific item for bid has been provided for in the Proposal and the item is
not a typical unit bid item included on the standard bid item list, then the item shall
be considered as a subsidiary item of Work, the cost of which shall be included in
the price bid in the Proposal for various bid items.
C. Use of Premises
1. Coordinate uses of premises under direction of the City.
2. Assume full responsibility for protection and safekeeping of materials and
equipment stored on the Site.
3. Use and occupy only portions of the public streets and alleys, or other public places
or other rights -of -way as provided for in the ordinances of the City, as shown in the
Contract Documents, or as may be specifically authorized in writing by the City.
a. A reasonable amount of tools, materials, and equipment for construction
purposes may be stored in such space, but no more than is necessary to avoid
delay in the construction operations.
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised December 20, 2012
011100-2
DAP SUMMARY OF WORK
Page 2 of 3
I b. Excavated and waste materials shall be stored in such a way as not to interfere
2 with the use of spaces that may be designated to be left free and unobstructed
3 and so as not to inconvenience occupants of adjacent property.
4 c. If the street is occupied by railroad tracks, the Work shall be carried on in such
5 manner as not to interfere with the operation of the railroad.
6 1) All Work shall be in accordance with railroad requirements set forth in
7 Division 0 as well as the railroad permit.
8 D. Work within Easements
9 1. Do not enter upon private property for any purpose without having previously
10 obtained permission from the owner of such property.
11 2. Do not store equipment or material on private property unless and until the
12 specified approval of the property owner has been secured in writing by the
13 Contractor and a copy furnished to the City.
14 3. Unless specifically provided otherwise, clear all rights -of -way or easements of
15 obstructions which must be removed to make possible proper prosecution of the
16 Work as a part of the project construction operations.
17 4. Preserve and use every precaution to prevent damage to, all trees, shrubbery, plants,
18 lawns, fences, culverts, curbing, and all other types of structures or improvements,
19 to all water, sewer, and gas lines, to all conduits, overhead pole lines, or
20 appurtenances thereof, including the construction of temporary fences and to all
21 other public or private property adjacent to the Work.
22 5. Notify the proper representatives of the owners or occupants of the public or private
23 lands of interest in lands which might be affected by the Work.
24 a. Such notice shall be made at least 48 hours in advance of the beginning of the
25 Work.
26 b. Notices shall be applicable to both public and private utility companies and any
27 corporation, company, individual, or other, either as owners or occupants,
28 whose land or interest in land might be affected by the Work.
29 c. Be responsible for all damage or injury to property of any character resulting
30 from any act, omission, neglect, or misconduct in the manner or method or
31 execution of the Work, or at any time due to defective work, material, or
32 equipment.
33 6. Fence
34 a. Restore all fences encountered and removed during construction of the Project
35 to the original or a better than original condition.
36 b. Erect temporary fencing in place of the fencing removed whenever the Work is
37 not in progress and when the site is vacated overnight, and/or at all times to
38 provide site security.
39 c. The cost for all fence work within easements, including removal, temporary
40 closures and replacement, shall be subsidiary to the various items bid in the
41 project proposal, unless a bid item is specifically provided in the proposal.
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised December 20, 2012
011100-3
DAP SUMMARY OF WORK
Page 3 of 3
1 1.5
SUBMITTALS [NOT USED]
2 1.6
ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
3 1.7
CLOSEOUT SUBMITTALS [NOT USED]
4 1.8
MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
5 1.9
QUALITY ASSURANCE [NOT USED]
6 1.10
DELIVERY, STORAGE, AND HANDLING [NOT USED]
7 1.11
FIELD [SITE] CONDITIONS [NOT USED]
8 1.12
WARRANTY [NOT USED]
9 PART 2 - PRODUCTS [NOT USED]
10 PART 3 - EXECUTION [NOT USED]
11 END OF SECTION
12
13
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised December 20, 2012
1
2
3 PART1- GENERAL
4 1.1 SUMMARY
SECTION 0125 00
SUBSTITUTION PROCEDURES
012500-1
DAP SUBSTITUTION PROCEDURES
Page 1 of 4
5 A. Section Includes:
6 1. The procedure for requesting the approval of substitution of a product that is not equivalent
7 to a product which is specified by descriptive or performance criteria or defined by reference
8 to 1 or more of the following:
9 a. Name of manufacturer
10 b. Name of vendor
11 c. Trade name
12 d. Catalog number
13 2. Substitutions are not "or -equals".
14 B. Deviations from this City of Fort Worth Standard Specification
15 1. None.
16 C. Related Specification Sections include, but are not necessarily limited to:
17 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
18 2. Division 1 — General Requirements
19 1.2 PRICE AND PAYMENT PROCEDURES
20 A. Measurement and Payment
21 1. Work associated with this Item is considered subsidiary to the various items bid. No
22 separate payment will be allowed for this Item.
23 1.3 REFERENCES [NOT USED]
24 1.4 ADMINISTRATIVE REQUIREMENTS
25 A. Request for Substitution - General
26 1. Within 30 days after award of Contract (unless noted otherwise), the City will consider
27 formal requests from Contractor for substitution of products in place of those specified.
28 2. Certain types of equipment and kinds of material are described in Specifications by means of
29 references to names of manufacturers and vendors, trade names, or catalog numbers.
30 a. When this method of specifying is used, it is not intended to exclude from consideration
31 other products bearing other manufacturer's or vendor's names, trade names, or catalog
32 numbers, provided said products are "or -equals," as determined by City.
33 3. Other types of equipment and kinds of material may be acceptable substitutions under the
34 following conditions:
35 a. Or -equals are unavailable due to strike, discontinued production of products meeting
36 specified requirements, or other factors beyond control of Contractor; or,
37 b. Contractor proposes a cost and/or time reduction incentive to the City.
38 1.5 SUBMITTALS
39 A. See Request for Substitution Form (attached)
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
012500-2
DAP SUBSTITUTION PROCEDURES
Page 2 of 4
1 B. Procedure for Requesting Substitution
2 1. Substitution shall be considered only:
3 a. After award of Contract
4 b. Under the conditions stated herein
5 2. Submit 3 copies of each written request for substitution, including:
6 a. Documentation
7 1) Complete data substantiating compliance of proposed substitution with Contract
8 Documents
9 2) Data relating to changes in construction schedule, when a reduction is proposed
10 3) Data relating to changes in cost
1 1 b. For products
12 1) Product identification
13 a) Manufacturer's name
14 b) Telephone number and representative contact name
15 c) Specification Section or Drawing reference of originally specified product,
16 including discrete name or tag number assigned to original product in the
17 Contract Documents
18 2) Manufacturer's literature clearly marked to show compliance of proposed product
19 with Contract Documents
20 3) Itemized comparison of original and proposed product addressing product
21 characteristics including, but not necessarily limited to:
22 a) Size
23 b) Composition or materials of construction
24 c) Weight
25 d) Electrical or mechanical requirements
26 4) Product experience
27 a) Location of past projects utilizing product
28 b) Name and telephone number of persons associated with referenced projects
29 knowledgeable concerning proposed product
30 c) Available field data and reports associated with proposed product
31 5) Samples
32 a) Provide at request of City.
33 b) Samples become the property of the City.
34 c. For construction methods:
35 1) Detailed description of proposed method
36 2) Illustration drawings
37 C. Approval or Rejection
38 1. Written approval or rejection of substitution given by the City
39 2. City reserves the right to require proposed product to comply with color and pattern of
40 specified product if necessary to secure design intent.
41 3. In the event the substitution is approved, if a reduction in cost or time results, it will be
42 documented by Change Order.
43 4. Substitution will be rejected i£
44 a. Submittal is not through the Contractor with his stamp of approval
45 b. Request is not made in accordance with this Specification Section
46 c. In the Developer's opinion, acceptance will require substantial revision of the original
47 design
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
012500-3
DAP SUBSTITUTION PROCEDURES
Page 3 of 4
I d. In the City's or Developer's opinion, substitution will not perform adequately the
2 function consistent with the design intent
3 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
4 1.7 CLOSEOUT SUBMITTALS [NOT USED]
5 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
6 1.9 QUALITY ASSURANCE
7 A. In making request for substitution or in using an approved product, the Contractor represents
8 that the Contractor:
9 1. Has investigated proposed product, and has determined that it is adequate or superior in all
10 respects to that specified, and that it will perform function for which it is intended
11 2. Will provide same guarantee for substitute item as for product specified
12 3. Will coordinate installation of accepted substitution into Work, to include building
13 modifications if necessary, making such changes as may be required for Work to be
14 complete in all respects
15 4. Waives all claims for additional costs related to substitution which subsequently arise
16 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
17 1.11 FIELD [SITE] CONDITIONS [NOT USED]
18 1.12 WARRANTY [NOT USED]
19 PART 2 - PRODUCTS [NOT USED]
20 PART 3 - EXECUTION [NOT USED]
21 END OF SECTION
22
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
1
2
3
4
5
6
7
8
9
10
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
012500-4
DAP SUBSTITUTION PROCEDURES
Page 4 of 4
EXHIBIT A
REQUEST FOR SUBSTITUTION FORM:
PROJECT: DATE:
We hereby submit for your consideration the following product instead of the specified item for the above
project:
SECTION PARAGRAPH SPECIFIED ITEM
Proposed Substitution:
Reason for Substitution:
Include complete information on changes to Drawings and/or Specifications which proposed substitution
will require for its proper installation.
Fill in Blanks Below:
A. Will the undersigned contractor pay for changes to the building design, including engineering and
detailing costs caused by the requested substitution?
B. What effect does substitution have on other trades?
C. Differences between proposed substitution and specified item?
D. Differences in product cost or product delivery time?
E. Manufacturer's guarantees of the proposed and specified items are:
Equal Better (explain on attachment)
The undersigned states that the function, appearance and quality are equivalent or superior to the specified
item.
Submitted By: For Use by City
Signature
Firm
Address
Date
Telephone
For Use by City:
Approved
City
Recommended Recommended as noted
Not recommended Received late
By
Date
Remarks
Date
Rejected
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
1
2
3 PART1- GENERAL
SECTION 013119
PRECONSTRUCTION MEETING
013119-1
DAP PRECONSTRUCTION MEETING
Page 1 of 4
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Provisions for the preconstruction meeting to be held prior to the start of Work to clarify
7 construction contract administration procedures
8 B. Deviations from this City of Fort Worth Standard Specification
9 1. No construction schedule required unless requested by the City.
10 C. Related Specification Sections include, but are not necessarily limited to:
1 1 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
12 2. Division 1 — General Requirements
13 1.2 PRICE AND PAYMENT PROCEDURES
14 A. Measurement and Payment
15 1. Work associated with this Item is considered subsidiary to the various items bid. No
16 separate payment will be allowed for this Item.
17 1.3 REFERENCES [NOT USED]
18 1.4 ADMINISTRATIVE REQUIREMENTS
19 A. Coordination
20 1. Attend preconstruction meeting.
21 2. Representatives of Contractor, subcontractors and suppliers attending meetings shall be
22 qualified and authorized to act on behalf of the entity each represents.
23 3. Meeting administered by City may be tape recorded.
24 a. If recorded, tapes will be used to prepare minutes and retained by City for future
25 reference.
26 B. Preconstruction Meeting
27 1. A preconstruction meeting will be held within 14 days after the delivery of the distribution
28 package to the City.
29 a. The meeting will be scheduled and administered by the City.
30 2. The Project Representative will preside at the meeting, prepare the notes of the meeting and
31 distribute copies of same to all participants who so request by fully completing the
32 attendance form to be circulated at the beginning of the meeting.
33 3. Attendance shall include:
34 a. Developer and Consultant
35 b. Contractor's project manager
36 c. Contractor's superintendent
37 d. Any subcontractor or supplier representatives whom the Contractor may desire to invite
38 or the City may request
39 e. Other City representatives
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
01 31 19 - 2
DAP PRECONSTRUCTION MEETING
Page 2 of 4
1
f.
Others as appropriate
2
4. Preliminary
Agenda may include:
3
a.
Introduction of Project Personnel
4
b.
General Description of Project
5
c.
Status of right-of-way, utility clearances, easements or other pertinent permits
6
d.
Contractor's work plan and schedule
7
e.
Contract Time
8
f.
Notice to Proceed
9
g.
Construction Staking
10
h.
Progress Payments
11
i.
Extra Work and Change Order Procedures
12
j.
Field Orders
13
k.
Disposal Site Letter for Waste Material
14
1.
Insurance Renewals
15
m.
Payroll Certification
16
n.
Material Certifications and Quality Control Testing
17
o.
Public Safety and Convenience
18
p.
Documentation of Pre -Construction Conditions
19
q.
Weekend Work Notification
20
r.
Legal Holidays
21
s.
Trench Safety Plans
22
t.
Confined Space Entry Standards
23
u.
Coordination with the City's representative for operations of existing water systems
24
v.
Storm Water Pollution Prevention Plan
25
w.
Coordination with other Contractors
26
x.
Early Warning System
27
y.
Contractor Evaluation
28
z.
Special Conditions applicable to the project
29
aa.
Damages Claims
30
bb.
Submittal Procedures
31
cc.
Substitution Procedures
32
dd.
Correspondence Routing
33
ee.
Record Drawings
34
f£
Temporary construction facilities
35
gg.
MBE/SBE procedures
36
hh.
Final Acceptance
37
ii.
Final Payment
38
J.
Questions or Comments
39 1.5 SUBMITTALS [NOT USED]
40
1.6
ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
41
1.7
CLOSEOUT SUBMITTALS [NOT USED]
42
1.8
MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
43
1.9
QUALITY ASSURANCE [NOT USED]
44
1.10
DELIVERY, STORAGE, AND HANDLING [NOT USED]
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
0131 19 - 3
DAP PRECONSTRUCTION MEETING
Page 3 of 4
1 1.11 FIELD [SITE] CONDITIONS [NOT USED]
2 1.12 WARRANTY [NOT USED]
3 PART 2 - PRODUCTS [NOT USED]
4 PART 3 - EXECUTION [NOT USED]
5 END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
01 31 19 - 4
DAP PRECONSTRUCTION MEETING
Page 4 of 4
THIS PAGE INTENTIONALLY LEFT BLANK
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
013233-1
DAP PRECONSTRUCTION VIDEO
Page I of 2
SECTION 0132 33
PRECONSTRUCTION VIDEO
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Administrative and procedural requirements for:
a. Preconstruction Videos
B. Deviations from this City of Fort Worth Standard Specification
1. Though not mandatory, it is highly recommended on infill developer projects.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 — General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Preconstruction Video
1. Produce a preconstruction video of the site/alignment, including all areas in the
vicinity of and to be affected by construction.
a. Provide digital copy of video upon request by the City.
2. Retain a copy of the preconstruction video until the end of the maintenance surety
period.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
01 32 33 - 2
DAP PRECONSTRUCTION VIDEO
Page 2 of 2
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
1
2
3 PART1- GENERAL
4 1.1 SUMMARY
SECTION 0133 00
DAP SUBMITTALS
013300-1
DAP SUBMITTALS
Page 1 of 11
5 A. Section Includes:
6 1. General methods and requirements of submissions applicable to the following Work-
7 related submittals:
8 a. Shop Drawings
9 b. Product Data (including Standard Product List submittals)
10 c. Samples
11 d. Mock Ups
12 B. Deviations from this City of Fort Worth Standard Specification
13 1. None.
14 C. Related Specification Sections include, but are not necessarily limited to:
15 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
16 2. Division 1— General Requirements
17 1.2 PRICE AND PAYMENT PROCEDURES
18 A. Measurement and Payment
19 1. Work associated with this Item is considered subsidiary to the various items bid. No
20 separate payment will be allowed for this Item.
21 1.3 REFERENCES [NOT USED]
22 1.4 ADMINISTRATIVE REQUIREMENTS
23 A. Coordination
24 1. Notify the City in writing, at the time of submittal, of any deviations in the submittals from
25 the requirements of the Contract Documents.
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS— DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
013300-2
DAP SUBMITTALS
Page 2 of 11
1 2. Coordination of Submittal Times
2 a. Prepare, prioritize and transmit each submittal sufficiently in advance of performing
3 the related Work or other applicable activities, or within the time specified in the
4 individual Work Sections, of the Specifications.
5 b. Contractor is responsible such that the installation will not be delayed by processing
6 times including, but not limited to:
7 a)
Disapproval and resubmittal (if required)
8 b)
Coordination with other submittals
9 c)
Testing
10 d)
Purchasing
11 e)
Fabrication
12 f)
Delivery
13 g)
Similar sequenced activities
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
c. No extension of time will be authorized because of the Contractor's failure to transmit
submittals sufficiently in advance of the Work.
d. Make submittals promptly in accordance with approved schedule, and in such
sequence as to cause no delay in the Work or in the work of any other contractor.
B. Submittal Numbering
1. When submitting shop drawings or samples, utilize a 9-character submittal cross-reference
identification numbering system in the following manner:
a. Use the first 6 digits of the applicable Specification Section Number.
b. For the next 2 digits number use numbers 01-99 to sequentially number each initial
separate item or drawing submitted under each specific Section number.
c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e. A=2nd
submission, B=3rd submission, C=4th submission, etc.). A typical submittal number
would be as follows:
03 30 00-08-B
1) 03 30 00 is the Specification Section for Concrete
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS— DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
013300-3
DAP SUBMITTALS
Page 3 of 11
1 2) 08 is the eighth initial submittal under this Specification Section
2 3) B is the third submission (second resubmission) of that particular shop drawing
3 C. Contractor Certification
4 1. Review shop drawings, product data and samples, including those by subcontractors, prior
5 to submission to determine and verify the following:
6 a. Field measurements
7 b. Field construction criteria
8 c. Catalog numbers and similar data
9 d. Conformance with the Contract Documents
10 2. Provide each shop drawing, sample and product data submitted by the Contractor with a
11 Certification Statement affixed including:
12 a. The Contractor's Company name
13 b. Signature of submittal reviewer
14 c. Certification Statement
15 1) "By this submittal, I hereby represent that I have determined and verified field
16 measurements, field construction criteria, materials, dimensions, catalog numbers
17 and similar data and I have checked and coordinated each item with other
18 applicable approved shop drawings."
19 D. Submittal Format
20 1. Fold shop drawings larger than 8 % inches x 11 inches to 8 % inches x 11inches.
21 2. Bind shop drawings and product data sheets together.
22 3. Order
23 a. Cover Sheet
24 1) Description of Packet
25 2) Contractor Certification
26 b. List of items / Table of Contents
27 c. Product Data /Shop Drawings/Samples /Calculations
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS— DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
013300-4
DAP SUBMITTALS
Page 4 of 11
l E. Submittal Content
2 1. The date of submission and the dates of any previous submissions
3 2. The Project title and number
4 3. Contractor identification
5 4. The names of:
6 a. Contractor
7 b. Supplier
8 c. Manufacturer
9 5. Identification of the product, with the Specification Section number, page and paragraph(s)
10 6. Field dimensions, clearly identified as such
11 7. Relation to adjacent or critical features of the Work or materials
12 8. Applicable standards, such as ASTM or Federal Specification numbers
13 9. Identification by highlighting of deviations from Contract Documents
14 10. Identification by highlighting of revisions on resubmittals
15 11. An 8-inch x 3-inch blank space for Contractor and City stamps
16
F. Shop Drawings
17
1. As
specified in individual Work Sections includes, but is not necessarily limited to:
18
a.
Custom -prepared data such as fabrication and erection/installation (working) drawings
19
b.
Scheduled information
20
c.
Setting diagrams
21
d.
Actual shopwork manufacturing instructions
22
e.
Custom templates
23
f.
Special wiring diagrams
24
g.
Coordination drawings
25
h.
Individual system or equipment inspection and test reports including:
CITY OF FORT WORTH
UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS— DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
013300-5
DAP SUBMITTALS
Page 5 of 11
l 1) Performance curves and certifications
2 i. As applicable to the Work
3 2. Details
4 a. Relation of the various parts to the main members and lines of the structure
5 b. Where correct fabrication of the Work depends upon field measurements
6 1) Provide such measurements and note on the drawings prior to submitting for
7 approval.
8 G. Product Data
9 1. For submittals of product data for products included on the City's Standard Product List,
10 clearly identify each item selected for use on the Project.
11 2. For submittals of product data for products not included on the City's Standard Product
12 List, submittal data may include, but is not necessarily limited to:
13 a. Standard prepared data for manufactured products (sometimes referred to as catalog
14 data)
15 1) Such as the manufacturer's product specification and installation instructions
16 2) Availability of colors and patterns
17 3) Manufacturer's printed statements of compliances and applicability
18 4) Roughing -in diagrams and templates
19 5) Catalog cuts
20 6) Product photographs
21 7) Standard wiring diagrams
22 8) Printed performance curves and operational -range diagrams
23 9) Production or quality control inspection and test reports and certifications
24 10) Mill reports
25 11) Product operating and maintenance instructions and recommended spare -parts
26 listing and printed product warranties
27 12) As applicable to the Work
28 H. Samples
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS— DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
013300-6
DAP SUBMITTALS
Page 6 of 11
1 1. As specified in individual Sections, include, but are not necessarily limited to:
2 a. Physical examples of the Work such as:
3 1) Sections of manufactured or fabricated Work
4 2) Small cuts or containers of materials
5 3) Complete units of repetitively used products color/texture/pattern swatches and
6 range sets
7 4) Specimens for coordination of visual effect
8 5) Graphic symbols and units of Work to be used by the City for independent
9 inspection and testing, as applicable to the Work
10 I. Do not start Work requiring a shop drawing, sample or product data nor any material to be
11 fabricated or installed prior to the approval or qualified approval of such item.
12 1. Fabrication performed, materials purchased or on -site construction accomplished which
13 does not conform to approved shop drawings and data is at the Contractor's risk.
14 2. The City will not be liable for any expense or delay due to corrections or remedies required
15 to accomplish conformity.
16 3. Complete project Work, materials, fabrication, and installations in conformance with
17 approved shop drawings, applicable samples, and product data.
18 J. Submittal Distribution
19 1. Electronic Distribution
20 a. Confirm development of Project directory for electronic submittals to be uploaded to
21 City's Buzzsaw site, or another external FTP site approved by the City.
22 b. Shop Drawings
23 1) Upload submittal to designated project directory and notify appropriate City
24 representatives via email of submittal posting.
25 2) Hard Copies
26 a) 3 copies for all submittals
27 b) If Contractor requires more than 1 hard copy of Shop Drawings returned,
28 Contractor shall submit more than the number of copies listed above.
29 c. Product Data
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS— DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
013300-7
DAP SUBMITTALS
Page 7 of 11
1) Upload submittal to designated project directory and notify appropriate City
representatives via email of submittal posting.
2) Hard Copies
a) 3 copies for all submittals
d. Samples
1) Distributed to the Project Representative
2. Hard Copy Distribution (if required in lieu of electronic distribution)
a. Shop Drawings
1) Distributed to the City
2) Copies
a) 8 copies for mechanical submittals
b) 7 copies for all other submittals
c) If Contractor requires more than 3 copies of Shop Drawings returned,
Contractor shall submit more than the number of copies listed above.
b. Product Data
1) Distributed to the City
2) Copies
a) 4 copies
c. Samples
1) Distributed to the Project Representative
2) Copies
a) Submit the number stated in the respective Specification Sections.
3. Distribute reproductions of approved shop drawings and copies of approved product data
and samples, where required, to the job site file and elsewhere as directed by the City.
a. Provide number of copies as directed by the City but not exceeding the number
previously specified.
K. Submittal Review
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS— DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
013300-8
DAP SUBMITTALS
Page 8 of 11
1 1. The review of shop drawings, data and samples will be for general conformance with the
2 design concept and Contract Documents. This is not to be construed as:
3 a. Permitting any departure from the Contract requirements
4 b. Relieving the Contractor of responsibility for any errors, including details, dimensions,
5 and materials
6 c. Approving departures from details furnished by the City, except as otherwise provided
7 herein
8 2. The review and approval of shop drawings, samples or product data by the City does not
9 relieve the Contractor from his/her responsibility with regard to the fulfillment of the terms
10 of the Contract.
11 a. All risks of error and omission are assumed by the Contractor, and the City will have no
12 responsibility therefore.
13 3. The Contractor remains responsible for details and accuracy, for coordinating the Work
14 with all other associated work and trades, for selecting fabrication processes, for
15 techniques of assembly and for performing Work in a safe manner.
16 4. If the shop drawings, data or samples as submitted describe variations and show a
17 departure from the Contract requirements which City finds to be in the interest of the City
18 and to be so minor as not to involve a change in Contract Price or time for performance, the
19 City may return the reviewed drawings without noting an exception.
20 5. Submittals will be returned to the Contractor under 1 of the following codes:
21 a. Code 1
22 1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or comments on
23 the submittal.
24 a) When returned under this code the Contractor may release the equipment
25 and/or material for manufacture.
26 b. Code 2
27 1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of the notations
28 and comments IS NOT required by the Contractor.
29 a) The Contractor may release the equipment or material for manufacture;
30 however, all notations and comments must be incorporated into the final
31 product.
32 c. Code 3
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS— DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
013300-9
DAP SUBMITTALS
Page 9 of 11
1 1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is assigned when
2 notations and comments are extensive enough to require a resubmittal of the
3 package.
4 a) The Contractor may release the equipment or material for manufacture;
5 however, all notations and comments must be incorporated into the final
6 product.
7 b) This resubmittal is to address all comments, omissions and non -conforming
8 items that were noted.
9 c) Resubmittal is to be received by the City within 15 Calendar Days of the date of
10 the City's transmittal requiring the resubmittal.
11 d. Code 4
12 1) "NOT APPROVED" is assigned when the submittal does not meet the intent of the
13 Contract Documents.
14 a) The Contractor must resubmit the entire package revised to bring the submittal
15 into conformance.
16 b) It may be necessary to resubmit using a different manufacturer/vendor to meet
17 the Contract Documents.
18 6. Resubmittals
19 a. Handled in the same manner as first submittals
20 1) Corrections other than requested by the City
21 2) Marked with revision triangle or other similar method
22 a) At Contractor's risk if not marked
23 b. Submittals for each item will be reviewed no more than twice at the City's expense.
24 1) All subsequent reviews will be performed at times convenient to the City and at the
25 Contractor's expense, based on the City's or City Representative's then prevailing
26 rates.
27 2) Provide Contractor reimbursement to the City within 30 Calendar Days for all such
28 fees invoiced by the City.
29 c. The need for more than 1 resubmission or any other delay in obtaining City's review of
30 submittals, will not entitle the Contractor to an extension of Contract Time.
31 7. Partial Submittals
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS— DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
0133 00 - 10
DAP SUBMITTALS
Page 10 of 11
1 a. City reserves the right to not review submittals deemed partial, at the City's discretion.
2 b. Submittals deemed by the City to be not complete will be returned to the Contractor,
3 and will be considered "Not Approved" until resubmitted.
4 c. The City may at its option provide a list or mark the submittal directing the Contractor
5 to the areas that are incomplete.
6 8. If the Contractor considers any correction indicated on the shop drawings to constitute a
7 change to the Contract Documents, then written notice must be provided thereof to the
8 Developer at least 7 Calendar Days prior to release for manufacture.
9 9. When the shop drawings have been completed to the satisfaction of the City, the
10 Contractor may carry out the construction in accordance therewith and no further changes
11 therein except upon written instructions from the City.
12 10. Each submittal, appropriately coded, will be returned within 30 Calendar Days following
13 receipt of submittal by the City.
14 L. Mock ups
15 1. Mock Up units as specified in individual Sections, include, but are not necessarily limited to,
16 complete units of the standard of acceptance for that type of Work to be used on the
17 Project. Remove at the completion of the Work or when directed.
18 M. Qualifications
19 1. If specifically required in other Sections of these Specifications, submit a P.E. Certification
20 for each item required.
21 N. Request for Information (RFI)
22 1. Contractor Request for additional information
23 a. Clarification or interpretation of the contract documents
24 b. When the Contractor believes there is a conflict between Contract Documents
25 c. When the Contractor believes there is a conflict between the Drawings and
26 Specifications
27 1) Identify the conflict and request clarification
28 2. Sufficient information shall be attached to permit a written response without further
29 information.
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS— DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
1
2
3
4
5
6
7
8
9
10
12
13
0133 00 - 11
DAP SUBMITTALS
Page 11 of 11
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
14 PART 3 - EXECUTION [NOT USED]
15
16
DATE
12/20/2012
17
END OF SECTION
Revision Log
NAME SUMMARY OF CHANGE
D. Johnson 1.4.K.8. Working Days modified to Calendar Days
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS— DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
0135 13- 1
DAP SPECIAL PROJECT PROCEDURES
Page 1 of 7
1 SECTION 0135 13
2 SPECIAL PROJECT PROCEDURES
3 PART1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. The procedures for special project circumstances that includes, but is not limited to:
7 a. Coordination with the Texas Department of Transportation
8 b. Work near High Voltage Lines
9 c. Confined Space Entry Program
10 d. Air Pollution Watch Days
11 e. Use of Explosives, Drop Weight, Etc.
12 f. Water Department Notification
13 g. Public Notification Prior to Beginning Construction
14 h. Coordination with United States Army Corps of Engineers
15 i. Coordination within Railroad permits areas
16 j. Dust Control
17 k. Employee Parking
18 B. Deviations from this City of Fort Worth Standard Specification
19 1. None.
20 C. Related Specification Sections include, but are not necessarily limited to:
21 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
22 2. Division 1 — General Requirements
23 3. Section 33 12 25 — Connection to Existing Water Mains
24
25 1.2 REFERENCES
26 A. Reference Standards
27 1. Reference standards cited in this Specification refer to the current reference
28 standard published at the time of the latest revision date logged at the end of this
29 Specification, unless a date is specifically cited.
30 2. Health and Safety Code, Title 9. Safety, Subtitle A. Public Safety, Chapter 752.
31 High Voltage Overhead Lines.
32 3. North Central Texas Council of Governments (NCTCOG) — Clean Construction
33 Specification
34 1.3 ADMINISTRATIVE REQUIREMENTS
35 A. Coordination with the Texas Department of Transportation
36 1. When work in the right-of-way which is under the jurisdiction of the Texas
37 Department of Transportation (TxDOT):
38 a. Notify the Texas Department of Transportation prior to commencing any work
39 therein in accordance with the provisions of the permit
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
0135 13-2
DAP SPECIAL PROJECT PROCEDURES
Page 2 of 7
b. All work performed in the TxDOT right-of-way shall be performed in
compliance with and subject to approval from the Texas Department of
Transportation
B. Work near High Voltage Lines
1. Regulatory Requirements
a. All Work near High Voltage Lines (more than 600 volts measured between
conductors or between a conductor and the ground) shall be in accordance with
Health and Safety Code, Title 9, Subtitle A, Chapter 752.
2. Warning sign
a. Provide sign of sufficient size meeting all OSHA requirements.
3. Equipment operating within 10 feet of high voltage lines will require the following
safety features
a. Insulating cage -type of guard about the boom or arm
b. Insulator links on the lift hook connections for back hoes or dippers
c. Equipment must meet the safety requirements as set forth by OSHA and the
safety requirements of the owner of the high voltage lines
4. Work within 6 feet of high voltage electric lines
a. Notification shall be given to:
1) The power company (example: ONCOR)
a) Maintain an accurate log of all such calls to power company and record
action taken in each case.
b. Coordination with power company
1) After notification coordinate with the power company to:
a) Erect temporary mechanical barriers, de -energize the lines, or raise or
lower the lines
c. No personnel may work within 6 feet of a high voltage line before the above
requirements have been met.
C. Confined Space Entry Program
1. Provide and follow approved Confined Space Entry Program in accordance with
OSHA requirements.
2. Confined Spaces include:
a. Manholes
b. All other confined spaces in accordance with OSHA's Permit Required for
Confined Spaces
D. Use of Explosives, Drop Weight, Etc.
1. When Contract Documents permit on the project the following will apply:
a. Public Notification
1) Submit notice to City and proof of adequate insurance coverage, 24 hours
prior to commencing.
2) Minimum 24 hour public notification in accordance with Section 013 1 13
E. Water Department Coordination
1. During the construction of this project, it will be necessary to deactivate, for a
period of time, existing lines. The Contractor shall be required to coordinate with
the Water Department to determine the best times for deactivating and activating
those lines.
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
013513-3
DAP SPECIAL PROJECT PROCEDURES
Page 3 of 7
1 2. Coordinate any event that will require connecting to or the operation of an existing
2 City water line system with the City's representative.
3 a. Coordination shall be in accordance with Section 33 12 25.
4 b. If needed, obtain a hydrant water meter from the Water Department for use
5 during the life of named project.
6 c. In the event that a water valve on an existing live system be turned off and on
7 to accommodate the construction of the project is required, coordinate this
8 activity through the appropriate City representative.
9 1) Do not operate water line valves of existing water system.
10 a) Failure to comply will render the Contractor in violation of Texas Penal
11 Code Title 7, Chapter 28.03 (Criminal Mischief) and the Contractor
12 will be prosecuted to the full extent of the law.
13 b) In addition, the Contractor will assume all liabilities and
14 responsibilities as a result of these actions.
15 F. Public Notification Prior to Beginning Construction
16 1. Prior to beginning construction on any block in the project, on a block by block
17 basis, prepare and deliver a notice or flyer of the pending construction to the front
18 door of each residence or business that will be impacted by construction. The notice
19 shall be prepared as follows:
20 a. Post notice or flyer 7 days prior to beginning any construction activity on each
21 block in the project area.
22 1) Prepare flyer on the Contractor's letterhead and include the following
23 information:
24 a) Name of Project
25 b) City Project No (CPN)
26 c) Scope of Project (i.e. type of construction activity)
27 d) Actual construction duration within the block
28 e) Name of the contractor's foreman and phone number
29 f) Name of the City's inspector and phone number
30 g) City's after-hours phone number
31 2) A sample of the `pre -construction notification' flyer is attached as Exhibit
32 A.
33 3) Submit schedule showing the construction start and finish time for each
34 block of the project to the inspector.
35 4) Deliver flyer to the City Inspector for review prior to distribution.
36 b. No construction will be allowed to begin on any block until the flyer is
37 delivered to all residents of the block.
38 G. Public Notification of Temporary Water Service Interruption during Construction
39 1. In the event it becomes necessary to temporarily shut down water service to
40 residents or businesses during construction, prepare and deliver a notice or flyer of
41 the pending interruption to the front door of each affected resident.
42 2. Prepared notice as follows:
43 a. The notification or flyer shall be posted 24 hours prior to the temporary
44 interruption.
45 b. Prepare flyer on the contractor's letterhead and include the following
46 information:
47 1) Name of the project
48 2) City Project Number
49 3) Date of the interruption of service
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
0135 13 - 4
DAP SPECIAL PROJECT PROCEDURES
Page 4 of 7
4) Period the interruption will take place
5) Name of the contractor's foreman and phone number
6) Name of the City's inspector and phone number
c. A sample of the temporary water service interruption notification is attached as
Exhibit B.
d. Deliver a copy of the temporary interruption notification to the City inspector
for review prior to being distributed.
e. No interruption of water service can occur until the flyer has been delivered to
all affected residents and businesses.
f. Electronic versions of the sample flyers can be obtained from the Project
Construction Inspector.
H. Coordination with United States Army Corps of Engineers (USACE)
1. At locations in the Project where construction activities occur in areas where
USACE permits are required, meet all requirements set forth in each designated
permit.
I. Coordination within Railroad Permit Areas
1. At locations in the project where construction activities occur in areas where
railroad permits are required, meet all requirements set forth in each designated
railroad permit. This includes, but is not limited to, provisions for:
a. Flagmen
b. Inspectors
c. Safety training
d. Additional insurance
e. Insurance certificates
f. Other employees required to protect the right-of-way and property of the
Railroad Company from damage arising out of and/or from the construction of
the project. Proper utility clearance procedures shall be used in accordance
with the permit guidelines.
2. Obtain any supplemental information needed to comply with the railroad's
requirements.
J. Dust Control
1. Use acceptable measures to control dust at the Site.
a. If water is used to control dust, capture and properly dispose of waste water.
b. If wet saw cutting is performed, capture and properly dispose of slurry.
K. Employee Parking
1. Provide parking for employees at locations approved by the City.
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
013513-5
DAP SPECIAL PROJECT PROCEDURES
Page 5 of 7
1 1.4
SUBMITTALS [NOT USED]
2 1.5
ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
3 1.6
CLOSEOUT SUBMITTALS [NOT USED]
4 1.7
MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
5 1.8
QUALITY ASSURANCE [NOT USED]
6 1.9
DELIVERY, STORAGE, AND HANDLING [NOT USED]
7 1.10
FIELD [SITE] CONDITIONS [NOT USED]
8 1.11
WARRANTY [NOT USED]
9 PART 2 - PRODUCTS [NOT USED]
10 PART 3 - EXECUTION [NOT USED]
11 END OF SECTION
12
Revision Log
DATE NAME SUMMARY OF CHANGE
1.3.B — Added requirement of compliance with Health and Safety Code, Title 9.
8/31/2012 D. Johnson Safety, Subtitle A. Public Safety, Chapter 752. High Voltage Overhead Lines.
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
01 35 13 -6
DAP SPECIAL PROJECT PROCEDURES
Page 6 of 7
EXHIBIT A
(To be printed on Contractor's Letterhead)
Date:
CPN No.:
Project Name:
Mapsco Location:
Limits of Construction:
THIS IS TO INFORM YOU THAT UNDER A CONTRACT WITH THE CITY OF FORT
WORTH, OUR COMPANY WILL WORK ON UTILITY LINES ON OR AROUND YOUR
PROPERTY.
CONSTRUCTION WILL BEGIN APPROXIMATELY SEVEN DAYS FROM THE DATE
OF THIS NOTICE.
IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SAFETY OR ANY OTHER
ISSUE, PLEASE CALL:
Mr. <CONTRACTOR'S SUPERINTENDENT> AT <TELEPHONE NO.>
OR
Mr. <CITY INSPECTOR> AT < TELEPHONE NO.>
AFTER 4:30 PM OR ON WEEKENDS, PLEASE CALL (817) 392 8306
PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
013513-7
DAP SPECIAL PROJECT PROCEDURES
Page 7 of 7
1 EXHIBIT B
2
3
4
FORT WORTH
Daft:
DOE NO. xxxx
Project !lame:
NOTICE OF TEMPORARY WATER SERVICE
INTERRUPTION
DUE TO UTILITY IMPROVEMENTS IN YOUR NEIGHBORHOOD, YOUR
WATER SERVICE WILL BE INTERRUPTED ON
BETWEEN THE HOURS OF AND
IF YOU HAVE QUESTIONS ABOUT THIS SHUT -OUT, PLEASE CALL:
MR. AT
(CONTRACTORS SUPERINTENDENT) (TELEPHONE NUMBER)
OR
MR. AT
(CITY INSPECTOR) (TELEPHONE NUMBER)
THIS INCONVENIENCE WILL BE AS SHORT AS POSSIBLE.
THANK YOU,
,CONTRACTOR
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised August 30, 2013
01 45 23
DAP TESTING AND INSPECTION SERVICES
Page 1 of 2
SECTION 0145 23
TESTING AND INSPECTION SERVICES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Testing and inspection services procedures and coordination
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 — General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
a. Contractor is responsible for performing, coordinating, and payment of all
Quality Control testing.
b. City is responsible for performing and payment for first set of Quality
Assurance testing.
1) If the first Quality Assurance test performed by the City fails, the
Contractor is responsible for payment of subsequent Quality Assurance
testing until a passing test occurs.
a) Final acceptance will not be issued by City until all required payments
for testing by Contractor have been paid in full.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Testing
1. Complete testing in accordance with the Contract Documents.
2. Coordination
a. When testing is required to be performed by the City, notify City, sufficiently in
advance, when testing is needed.
b. When testing is required to be completed by the Contractor, notify City,
sufficiently in advance, that testing will be performed.
3. Distribution of Testing Reports
a. Electronic Distribution
1) Confirm development of Project directory for electronic submittals to be
uploaded to the City's document management system, or another form of
distribution approved by the City.
CITY OF FORT WORTH
UPS Staging — Liberty Connection
CPN 105301
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS
Revised March 20, 2020
01 45 23
DAP TESTING AND INSPECTION SERVICES
Page 2 of 2
2) Upload test reports to designated project directory and notify appropriate
City representatives via email of submittal posting.
3) Hard Copies
a) 1 copy for all submittals submitted to the Project Representative
b. Hard Copy Distribution (if required in lieu of electronic distribution)
1) Tests performed by City
a) Distribute 1 hard copy to the Contractor
2) Tests performed by the Contractor
a) Distribute 3 hard copies to City's Project Representative
4. Provide City's Project Representative with trip tickets for each delivered load of
Concrete or Lime material including the following information:
a. Name of pit
b. Date of delivery
c. Material delivered
B. Inspection
1. Inspection or lack of inspection does not relieve the Contractor from obligation to
perform work in accordance with the Contract Documents.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS ]NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
1040 ZI] Oy X40 I C130
Revision Log
DATE NAME SUMMARY OF CHANGE
03/20/2020 D.V. Magana Removed reference to Buzzsaw and noted that electronic submittals be uploaded
through the City's document management system.
CITY OF FORT WORTH UPS Staging — Liberty Connection
CPN 105301
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS
Revised March 20, 2020
01 50 00 - 1
DAP TEMPORARY FACILITIES AND CONTROLS
Page 1 of 4
1 SECTION 0150 00
2 TEMPORARY FACILITIES AND CONTROLS
3 PART 1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Provide temporary facilities and controls needed for the Work including, but not necessarily
7 limited to:
8 a. Temporary utilities
9 b. Sanitary facilities
10 c. Storage Sheds and Buildings
11 d. Dust control
12 e. Temporary fencing of the construction site
13 B. Deviations from this City of Fort Worth Standard Specification
14 1. None.
15 C. Related Specification Sections include, but are not necessarily limited to:
16 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
17 2. Division 1— General Requirements
18 1.2 PRICE AND PAYMENT PROCEDURES
19 A. Measurement and Payment
20 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate
21 payment will be allowed for this Item.
22 1.3 REFERENCES [NOT USED]
23 1.4 ADMINISTRATIVE REQUIREMENTS
24 A. Temporary Utilities
25 1. Obtaining Temporary Service
26 a. Make arrangements with utility service companies for temporary services.
27 b. Abide by rules and regulations of utility service companies or authorities having jurisdiction.
28 c. Be responsible for utility service costs until Work is approved for Final Acceptance.
29 1) Included are fuel, power, light, heat and other utility services necessary for execution,
30 completion, testing and initial operation of Work.
31 2. Water
32 a. Contractor to provide water required for and in connection with Work to be performed and
33 for specified tests of piping, equipment, devices or other use as required for the completion of
34 the Work.
35 b. Provide and maintain adequate supply of potable water for domestic consumption by
36 Contractor personnel and City's Project Representatives.
37 c. Coordination
38 1) Contact City 1 week before water for construction is desired
39 d. Contractor Payment for Construction Water
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised JULY 1, 2011
01 50 00 - 2
DAP TEMPORARY FACILITIES AND CONTROLS
Page 2 of 4
1 1) Obtain construction water meter from City for payment as billed by City's established
2 rates.
3 3. Electricity and Lighting
4 a. Provide and pay for electric powered service as required for Work, including testing of Work.
5 1) Provide power for lighting, operation of equipment, or other use.
6 b. Electric power service includes temporary power service or generator to maintain operations
7 during scheduled shutdown.
8 4. Telephone
9 a. Provide emergency telephone service at Site for use by Contractor personnel and others
10 performing work or furnishing services at Site.
11 5. Temporary Heat and Ventilation
12 a. Provide temporary heat as necessary for protection or completion of Work.
13 b. Provide temporary heat and ventilation to assure safe working conditions.
14 B. Sanitary Facilities
15 1. Provide and maintain sanitary facilities for persons on Site.
16 a. Comply with regulations of State and local departments of health.
17 2. Enforce use of sanitary facilities by construction personnel at job site.
18 a. Enclose and anchor sanitary facilities.
19 b. No discharge will be allowed from these facilities.
20 c. Collect and store sewage and waste so as not to cause nuisance or health problem.
21 d. Haul sewage and waste off -site at no less than weekly intervals and properly dispose in
22 accordance with applicable regulation.
23 3. Locate facilities near Work Site and keep clean and maintained throughout Project.
24 4. Remove facilities at completion of Project
25 C. Storage Sheds and Buildings
26 1. Provide adequately ventilated, watertight, weatherproof storage facilities with floor above ground
27 level for materials and equipment susceptible to weather damage.
28 2. Storage of materials not susceptible to weather damage may be on blocks off ground.
29 3. Store materials in a neat and orderly manner.
30 a. Place materials and equipment to permit easy access for identification, inspection and
31 inventory.
32 4. Equip building with lockable doors and lighting, and provide electrical service for equipment
33 space heaters and heating or ventilation as necessary to provide storage environments acceptable
34 to specified manufacturers.
35 5. Fill and grade site for temporary structures to provide drainage away from temporary and existing
36 buildings.
37 6. Remove building from site prior to Final Acceptance.
38 D. Temporary Fencing
39 1. Provide and maintain for the duration or construction when required in contract documents
40 E. Dust Control
41 1. Contractor is responsible for maintaining dust control through the duration of the project.
42 a. Contractor remains on -call at all times
43 b. Must respond in a timely manner
44 F. Temporary Protection of Construction
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised JULY 1, 2011
015000-3
DAP TEMPORARY FACILITIES AND CONTROLS
Page 3 of 4
1 1. Contractor or subcontractors are responsible for protecting Work from damage due to weather.
2 1.5 SUBMITTALS [NOT USED]
3 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
4 1.7 CLOSEOUT SUBMITTALS [NOT USED]
5 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
6 1.9 QUALITY ASSURANCE [NOT USED]
7 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
8 1.11 FIELD [SITE] CONDITIONS [NOT USED]
9 1.12 WARRANTY [NOT USED]
10 PART 2 - PRODUCTS [NOT USED]
11 PART 3 - EXECUTION [NOT USED]
12
3.1
INSTALLERS [NOT USED]
13
3.2
EXAMINATION [NOT USED]
14
3.3
PREPARATION [NOT USED]
15
3.4
INSTALLATION
16
A. Temporary Facilities
17
1. Maintain all temporary facilities for duration of construction activities as needed.
18
3.5
[REPAIR] / [RESTORATION]
19
3.6
RE -INSTALLATION
20
3.7
FIELD [OR] SITE QUALITY CONTROL [NOT USED]
21
3.8
SYSTEM STARTUP [NOT USED]
22
3.9
ADJUSTING [NOT USED]
23
3.10
CLEANING [NOT USED]
24
3.11
CLOSEOUT ACTIVITIES
25
A. Temporary Facilities
26
1. Remove all temporary facilities and restore area after completion of the Work, to a condition
27
equal to or better than prior to start of Work.
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised JULY 1, 2011
1 3.12 PROTECTION [NOT USED]
2 3.13 MAINTENANCE [NOT USED]
3 3.14 ATTACHMENTS [NOT USED]
01 50 00 - 4
DAP TEMPORARY FACILITIES AND CONTROLS
Page 4 of 4
4 END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised JULY 1, 2011
01 55 26 - 1
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 1 of 4
1 SECTION 0155 26
2 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
3 PART1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Administrative procedures for:
7 a. Street Use Permit
8 b. Modification of approved traffic control
9 c. Removal of Street Signs
10 B. Deviations from this City of Fort Worth Standard Specification
11 1. None.
12 C. Related Specification Sections include, but are not necessarily limited to:
13 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
14 2. Division 1— General Requirements
15 3. Section 34 71 13 — Traffic Control
16 1.2 PRICE AND PAYMENT PROCEDURES
17 A. Measurement and Payment
18 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate
19 payment will be allowed for this Item.
20 1.3 REFERENCES
21 A. Reference Standards
22 1. Reference standards cited in this specification refer to the current reference standard published
23 at the time of the latest revision date logged at the end of this specification, unless a date is
24 specifically cited.
25 2. Texas Manual on Uniform Traffic Control Devices (TMUTCD).
26 1.4 ADMINISTRATIVE REQUIREMENTS
27 A. Traffic Control
28 1. General
29 a. When traffic control plans are included in the Drawings, provide Traffic Control in
30 accordance with Drawings and Section 34 7113.
31 b. When traffic control plans are not included in the Drawings, prepare traffic control plans in
32 accordance with Section 34 7113 and submit to City for review.
33 1) Allow minimum 10 working days for review of proposed Traffic Control.
34 B. Street Use Permit
35 1. Prior to installation of Traffic Control, a City Street Use Permit is required.
36 a. To obtain Street Use Permit, submit Traffic Control Plans to City Transportation and Public
37 Works Department.
38 1) Allow a minimum of 5 working days for permit review.
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised July 1, 2011
015526-2
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 2 of 4
1 2) Contractor's responsibility to coordinate review of Traffic Control plans for Street Use
2 Permit, such that construction is not delayed.
3 C. Modification to Approved Traffic Control
4 1. Prior to installation traffic control:
5 a. Submit revised traffic control plans to City Department Transportation and Public Works
6 Department.
7 1) Revise Traffic Control plans in accordance with Section 34 71 13.
8 2) Allow minimum 5 working days for review of revised Traffic Control.
9 3) It is the Contractor's responsibility to coordinate review of Traffic Control plans for
10 Street Use Permit, such that construction is not delayed.
11 D. Removal of Street Sign
12 1. If it is determined that a street sign must be removed for construction, then contact City
13 Transportation and Public Works Department, Signs and Markings Division to remove the sign.
14 E. Temporary Signage
15 1. In the case of regulatory signs, replace permanent sign with temporary sign meeting
16 requirements of the latest edition of the Texas Manual on Uniform Traffic Control Devices
17 (MUTCD).
18 2. Install temporary sign before the removal of permanent sign.
19 3. When construction is complete, to the extent that the permanent sign can be reinstalled, contact
20 the City Transportation and Public Works Department, Signs and Markings Division, to reinstall
21 the permanent sign.
22 F. Traffic Control Standards
23 1. Traffic Control Standards can be found on the City's Buzzsaw website.
24 1.5 SUBMITTALS [NOT USED]
25 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
26 1.7 CLOSEOUT SUBMITTALS [NOT USED]
27 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
28 1.9 QUALITY ASSURANCE [NOT USED]
29 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
30 1.11 FIELD [SITE] CONDITIONS [NOT USED]
31 1.12 WARRANTY [NOT USED]
32 PART 2 - PRODUCTS [NOT USED]
33 PART 3 - EXECUTION [NOT USED]
34 END OF SECTION
35
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised July 1, 2011
015526-3
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 3 of 4
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised July 1, 2011
015526-4
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 4 of 4
THIS PAGE INTENTIONALLY LEFT BLANK
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised July 1, 2011
01 57 13 - 1
DAP STORM WATER POLLUTION PREVENTION
Page 1 of 4
1 SECTION 01 5713
2 STORM WATER POLLUTION PREVENTION
3 PART 1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Procedures for Storm Water Pollution Prevention Plans
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
11 2. Division 1— General Requirements
12 3. Section 3125 00 — Erosion and Sediment Control
13 1.2 PRICE AND PAYMENT PROCEDURES
14 A. Measurement and Payment
15 1. Construction Activities resulting in less than 1 acre of disturbance
16 a. Work associated with this Item is considered subsidiary to the various Items bid. No
17 separate payment will be allowed for this Item.
18 2. Construction Activities resulting in greater than 1 acre of disturbance
19 a. Measurement and Payment shall be in accordance with Section 3125 00.
20 1.3 REFERENCES
21 A. Abbreviations and Acronyms
22 1. Notice of Intent: NOI
23 2. Notice of Termination: NOT
24 3. Storm Water Pollution Prevention Plan: SWPPP
25 4. Texas Commission on Environmental Quality: TCEQ
26 5. Notice of Change: NOC
27 A. Reference Standards
28 1. Reference standards cited in this Specification refer to the current reference standard
29 published at the time of the latest revision date logged at the end of this Specification,
30 unless a date is specifically cited.
31 2. Integrated Storm Management (iSWM) Technical Manual for Construction Controls
32 1.4 ADMINISTRATIVE REQUIREMENTS
33 A. General
34 1. Contractor is responsible for resolution and payment of any fines issued associated with
35 compliance to Stormwater Pollution Prevention Plan.
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised July 1, 2011
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
01 57 13 - 2
DAP STORM WATER POLLUTION PREVENTION
Page 2 of 4
B. Construction Activities resulting in:
1. Less than 1 acre of disturbance
a. Provide erosion and sediment control in accordance with Section 3125 00 and
Drawings.
2. 1 to less than 5 acres of disturbance
a. Texas Pollutant Discharge Elimination System (TPDES) General Construction
Permit is required
b. Complete SWPPP in accordance with TCEQ requirements
1) TCEQ Small Construction Site Notice Required under general permit
TXR150000
a) Sign and post at job site
b) Prior to Preconstruction Meeting, send 1 copy to City Department of
Transportation and Public Works, Environmental Division, (817) 392-6088.
2) Provide erosion and sediment control in accordance with:
a) Section 3125 00
b) The Drawings
c) TXR150000 General Permit
d) SWPPP
e) TCEQ requirements
3. 5 acres or more of Disturbance
a. Texas Pollutant Discharge Elimination System (TPDES) General Construction
Permit is required
b. Complete SWPPP in accordance with TCEQ requirements
1) Prepare a TCEQ NOI form and submit to TCEQ along with required fee
a) Sign and post at job site
b) Send copy to City Department of Transportation and Public Works,
Environmental Division, (817) 392-6088.
2) TCEQ Notice of Change required if making changes or updates to NOI
3) Provide erosion and sediment control in accordance with:
a) Section 3125 00
b) The Drawings
c) TXR150000 General Permit
d) SWPPP
e) TCEQ requirements
4) Once the project has been completed and all the closeout requirements of TCEQ
have been met a TCEQ Notice of Termination can be submitted.
a) Send copy to City Department of Transportation and Public Works,
Environmental Division, (817) 392-6088.
39 1.5 SUBMITTALS
40
41
42
43
44
45
46
47
A. SWPPP
Submit in accordance with Section 01 33 00, except as stated herein.
a. Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City as
follows:
1) 1 copy to the City Project Manager
a) City Project Manager will forward to the City Department of Transportation
and Public Works, Environmental Division for review
B. Modified SWPPP
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised July 1, 2011
015713-3
DAP STORM WATER POLLUTION PREVENTION
Page 3 of 4
1 1. If the SWPPP is revised during construction, resubmit modified SWPPP to the City in
2 accordance with Section 0133 00.
3 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
4 1.7 CLOSEOUT SUBMITTALS [NOT USED]
5 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
6 1.9 QUALITY ASSURANCE [NOT USED]
7 1.10 DELIVERY, STORAGE, AND HANDLING SNOT USED]
8 1.11 FIELD [SITE] CONDITIONS [NOT USED]
9 1.12 WARRANTY [NOT USED]
10 PART 2 - PRODUCTS [NOT USED]
11 PART 3 - EXECUTION [NOT USED]
12 END OF SECTION
13
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised July 1, 2011
015713-4
DAP STORM WATER POLLUTION PREVENTION
Page 4 of 4
THIS PAGE INTENTIONALLY LEFT BLANK
CITY OF FORT WORTH Public Paving Improvements to
UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN V=
Revised July 1, 2011
01 60 00
DAP PRODUCT REQUIREMENTS
Page 1 of 2
SECTION 0160 00
PRODUCT REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. References for Product Requirements and City Standard Products List
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 — General Requirements
1.2 PRICE AND PAYMENT PROCEDURES [NOT USED]
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A list of City approved products for use is available through the City's website at:
httlis://arms,;fortworthtexas.=/ProiectResources/` and following the directory
path: 02 - Construction Documents\Standard Products List
A. Only products specifically included on City's Standard Product List in these Contract
Documents shall be allowed for use on the Project.
1. Any subsequently approved products will only be allowed for use upon specific
approval by the City.
B. Any specific product requirements in the Contract Documents supersede similar
products included on the City's Standard Product List.
1. The City reserves the right to not allow products to be used for certain projects even
though the product is listed on the City's Standard Product List.
C. Although a specific product is included on City's Standard Product List, not all
products from that manufacturer are approved for use, including but not limited to, that
manufacturer's standard product.
D. See Section 01 33 00 for submittal requirements of Product Data included on City's
Standard Product List.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised March 20, 2020
01 60 00
DAP PRODUCT REQUIREMENTS
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
DATE NAME
END OF SECTION
Revision Log
SUMMARY OF CHANGE
Page 2 of 2
10/12/12 D. Johnson Modified Location of City's Standard Product List
4/7/2014 M.Domenech Revised for DAP application
03/20/2020 D.V. Magana Removed reference to Buzzsaw and noted that the City approved products list is
accessible through the City's website.
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised March 20, 2020
016600-1
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 1 of 4
SECTION 0166 00
PRODUCT STORAGE AND HANDLING REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Scheduling of product delivery
2. Packaging of products for delivery
3. Protection of products against damage from:
a. Handling
b. Exposure to elements or harsh environments
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division I — General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY AND HANDLING
A. Delivery Requirements
1. Schedule delivery of products or equipment as required to allow timely installation
and to avoid prolonged storage.
2. Provide appropriate personnel and equipment to receive deliveries.
3. Delivery trucks will not be permitted to wait extended periods of time on the Site
for personnel or equipment to receive the delivery.
CITY OF FORT WORTH
UPS Staging Lot — Liberty Connection
CPN 105301
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS
Revised April 7, 2014
016600-2
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 2 of 4
4. Deliver products or equipment in manufacturer's original unbroken cartons or other
containers designed and constructed to protect the contents from physical or
environmental damage.
5. Clearly and fully mark and identify as to manufacturer, item and installation
location.
6. Provide manufacturer's instructions for storage and handling.
B. Handling Requirements
1. Handle products or equipment in accordance with these Contract Documents and
manufacturer's recommendations and instructions.
C. Storage Requirements
1. Store materials in accordance with manufacturer's recommendations and
requirements of these Specifications.
2. Make necessary provisions for safe storage of materials and equipment.
a. Place loose soil materials and materials to be incorporated into Work to prevent
damage to any part of Work or existing facilities and to maintain free access at
all times to all parts of Work and to utility service company installations in
vicinity of Work.
3. Keep materials and equipment neatly and compactly stored in locations that will
cause minimum inconvenience to other contractors, public travel, adjoining owners,
tenants and occupants.
a. Arrange storage to provide easy access for inspection.
4. Restrict storage to areas available on construction site for storage of material and
equipment as shown on Drawings, or approved by City's Project Representative.
5. Provide off -site storage and protection when on -site storage is not adequate.
a. Provide addresses of and access to off -site storage locations for inspection by
City's Project Representative.
6. Do not use lawns, grass plots or other private property for storage purposes without
written permission of owner or other person in possession or control ofpremises.
7. Store in manufacturers' unopened containers.
8. Neatly, safely and compactly stack materials delivered and stored along line of
Work to avoid inconvenience and damage to property owners and general public
and maintain at least 3 feet from fire hydrant.
9. Keep public and private driveways and street crossings open.
10. Repair or replace damaged lawns, sidewalks, streets or other improvements to
satisfaction of City's Project Representative.
a. Total length which materials may be distributed along route of construction at
one time is 1,000 linear feet, unless otherwise approved in writing by City's
Project Representative.
CITY OF FORT WORTH
UPS Staging Lot — Liberty Connection
CPN 105301
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS
Revised April 7, 2014
016600-3
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 3 of 4
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 ERECTION [NOT USED]
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE -INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL
A. Tests and Inspections
1. Inspect all products or equipment delivered to the site prior to unloading.
B. Non -Conforming Work
1. Reject all products or equipment that are damaged, used or in any other way
unsatisfactory for use on the project.
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION
A. Protect all products or equipment in accordance with manufacturer's written directions.
B. Store products or equipment in location to avoid physical damage to items while in
storage.
C. Protect equipment from exposure to elements and keep thoroughly dry if required by
the manufacturer.
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
CITY OF FORT WORTH UPS Staging Lot —Liberty Connection
CPN 105301
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS
Revised April 7, 2014
01 66 00 - 4
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 4 of 4
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
CITY OF FORT WORTH UPS Staging Lot —Liberty Connection
CPN 105301
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS
Revised April 7, 2014
01 70 00 - 1
DAP MOBILIZATION AND REMOBILIZATION
Page 1 of 4
SECTION 0170 00
MOBILIZATION AND REMOBILIZATION
PART1-GENERAL
1.1 SUMMARY
A. Section Includes:
1. Mobilization and Demobilization
a. Mobilization
1) Transportation of Contractor's personnel, equipment, and operating
supplies to the Site
2) Establishment of necessary general facilities for the Contractor's operation
at the Site
3) Premiums paid for performance and payment bonds
4) Transportation of Contractor's personnel, equipment, and operating
supplies to another location within the designated Site
5) Relocation of necessary general facilities for the Contractor's operation
from 1 location to another location on the Site.
b. Demobilization
1) Transportation of Contractor's personnel, equipment, and operating
supplies away from the Site including disassembly
2) Site Clean-up
3) Removal of all buildings and/or other facilities assembled at the Site for
this
Contract
c. Mobilization and Demobilization do not include activities for specific items of
work that are for which payment is provided elsewhere in the contract.
2. Remobilization
a. Remobilization for Suspension of Work specifically required in the Contract
Documents or as required by City includes:
1) Demobilization
a) Transportation of Contractor's personnel, equipment, and operating
supplies from the Site including disassembly or temporarily securing
equipment, supplies, and other facilities as designated by the Contract
Documents necessary to suspend the Work.
b) Site Clean-up as designated in the Contract Documents
2) Remobilization
a) Transportation of Contractor's personnel, equipment, and operating
supplies to the Site necessary to resume the Work.
b) Establishment of necessary general facilities for the Contractor's
operation at the Site necessary to resume the Work.
3) No Payments will be made for:
a) Mobilization and Demobilization from one location to another on the
Site in the normal progress of performing the Work.
b) Stand-by or idle time
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised April 7, 2014
017000-2
DAP MOBILIZATION AND REMOBILIZATION
Page 2 of 4
c) Lost profits
Mobilizations and Demobilization for Miscellaneous Projects
a. Mobilization and Demobilization
1) Mobilization shall consist of the activities and cost on a Work Order basis
necessary for:
a) Transportation of Contractor's personnel, equipment, and operating
supplies to the Site for the issued Work Order.
b) Establishment of necessary general facilities for the Contractor's
operation at the Site for the issued Work Order
2) Demobilization shall consist of the activities and cost necessary for:
a) Transportation of Contractor's personnel, equipment, and operating
supplies from the Site including disassembly for each issued Work
Order
b) Site Clean-up for each issued Work Order
c) Removal of all buildings or other facilities assembled at the Site for
each Work Oder
b. Mobilization and Demobilization do not include activities for specific items of
work for which payment is provided elsewhere in the contract.
4. Emergency Mobilizations and Demobilization for Miscellaneous Projects
a. A Mobilization for Miscellaneous Projects when directed by the City and the
mobilization occurs within 24 hours of the issuance of the Work Order.
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 — General Requirements
OW.1077V/uI11Q189Z119J111119&1
A. Measurement and Payment
1. Mobilization and Demobilization
a. Measure
1) This Item is considered subsidiary to the various Items bid.
b. Payment
1) The work performed and materials furnished in accordance with this Item
are subsidiary to the various Items bid and no other compensation will be
allowed.
2. Remobilization for suspension of Work as specifically required in the Contract
Documents
a. Measurement
1) Measurement for this Item shall be per each remobilization performed.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" will be paid for at the unit
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised April 7, 2014
017000-3
DAP MOBILIZATION AND REMOBILIZATION
Page 3 of 4
price per each "Specified Remobilization" in accordance with Contract
Documents.
c. The price shall include:
1) Demobilization as described in Section 1.1.A.2.a.1)
2) Remobilization as described in Section 1.1.A.2.a.2)
d. No payments will be made for standby, idle time, or lost profits associated this
Item.
3. Remobilization for suspension of Work as required by City
a. Measurement and Payment
1) This shall be submitted as a Contract Claim in accordance with Article 10
of Section 00 72 00.
2) No payments will be made for standby, idle time, or lost profits associated
with this Item.
4. Mobilizations and Demobilizations for Miscellaneous Projects
a. Measurement
1) Measurement for this Item shall be for each Mobilization and
Demobilization required by the Contract Documents
b. Payment
1) The Work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" will be paid for at the unit
price per each "Work Order Mobilization" in accordance with Contract
Documents. Demobilization shall be considered subsidiary to mobilization
and shall not be paid for separately.
c. The price shall include:
1) Mobilization as described in Section 1.1.A.3.a.1)
2) Demobilization as described in Section 1.1.A.3.a.2)
d. No payments will be made for standby, idle time, or lost profits associated this
Item.
5. Emergency Mobilizations and Demobilizations for Miscellaneous Projects
a. Measurement
1) Measurement for this Item shall be for each Mobilization and
Demobilization required by the Contract Documents
b. Payment
1) The Work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" will be paid for at the unit
price per each "Work Order Emergency Mobilization" in accordance with
Contract Documents. Demobilization shall be considered subsidiary to
mobilization and shall not be paid for separately.
c. The price shall include
1) Mobilization as described in Section 1.1.A.4.a)
2) Demobilization as described in Section 1.1.A.3.a.2)
d. No payments will be made for standby, idle time, or lost profits associated this
Item.
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised April 7, 2014
017000-4
DAP MOBILIZATION AND REMOBILIZATION
Page 4 of 4
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
1.5 SUBMITTALS [NOT USED]
1.6 INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised April 7, 2014
017123-1
CONSTRUCTION STAKING AND SURVEY
Page 1 of 7
1 SECTION 017123
2 CONSTRUCTION STAKING AND SURVEY
3 PART1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Requirements for construction staking and construction survey
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. See Changes (Highlighted in Yellow).
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
11 2. Division 1 — General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurement and Payment
14 1. Construction Staking
15 a. Measurement
16 1) This Item is considered subsidiary to the various Items bid.
17 b. Payment
18 1) The work performed and the materials furnished in accordance with this
19 Item are subsidiary to the various Items bid and no other compensation will
20 be allowed.
21 2. Construction Survey
22 a. Measurement
23 1) This Item is considered subsidiary to the various Items bid.
24 b. Payment
25 1) The work performed and the materials furnished in accordance with this
26 Item are subsidiary to the various Items bid and no other compensation will be
27 allowed.
28 3. As -Built Survey
29 a. Measurement
30 1) This Item is considered subsidiary to the various Items bid.
31 b. Payment
32 1) The work performed and the materials furnished in accordance with this
33 Item are subsidiary to the various Items bid and no other compensation will be
34 allowed.
35 1.3 REFERENCES
36 A. Definitions
37 1. Construction Survev - The survey measurements made prior to or while
38 construction is in progress to control elevation, horizontal position, dimensions and
39 configuration of structures/improvements included in the Project Drawings.
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised February 14, 2018
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
01 71 23 - 2
CONSTRUCTION STAKING AND SURVEY
Page 2 of 7
2. As -built Survev —The measurements made after the construction of the
improvement features are complete to provide position coordinates for the features
of a project.
3. Construction Staking — The placement of stakes and markings to provide offsets
and elevations to cut and fill in order to locate on the ground the designed
structures/improvements included in the Project Drawings. Construction staking
shall include staking easements and/or right of way if indicated on the plans.
4. Survev "Field Checks" — Measurements made after construction staking is
completed and before construction work begins to ensure that structures marked on
the ground are accurately located per Project Drawings.
B. Technical References
1. City of Fort Worth — Construction Staking Standards (available on City's Buzzsaw
website) — 01 71 23.16.01— Attachment A —Survey Staking Standards
2. City of Fort Worth - Standard Survey Data Collector Library (fxl) files (available
on City's Buzzsaw website).
3. Texas Department of Transportation (TxDOT) Survey Manual, latest revision
4. Texas Society of Professional Land Surveyors (TSPS), Manual of Practice for Land
Surveying in the State of Texas, Category 5
20 1.4 ADMINISTRATIVE REQUIREMENTS
21 A. The Contractor's selection of a surveyor must comply with Texas Government
22 Code 2254 (qualifications based selection) for this project.
23 1.5 SUBMITTALS
24 A. Submittals, if required, shall be in accordance with Section 0133 00.
25 B. All submittals shall be received and reviewed by the City prior to delivery of work.
26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS
27 A. Field Quality Control Submittals
28 1. Documentation verifying accuracy of field engineering work, including coordinate
29 conversions if plans do not indicate grid or ground coordinates.
30 2. Submit "Cut -Sheets" conforming to the standard template provided by the City
31 (refer to 01 71 23.16.01 — Attachment A — Survey Staking Standards).
32 1.7 CLOSEOUT SUBMITTALS
33 B. As -built Redline Drawing Submittal
34 1. Submit As -Built Survey Redline Drawings documenting the locations/elevations of
35 constructed improvements signed and sealed by Registered Professional Land
36 Surveyor (RPLS) responsible for the work (refer to 01 71 23.16.01 — Attachment A
37 — Survey Staking Standards) .
38 2. Contractor shall submit the proposed as -built and completed redline drawing
39 submittal one (1) week prior to scheduling the project final inspection for City
40 review and comment. Revisions, if necessary, shall be made to the as -built redline
41 drawings and resubmitted to the City prior to scheduling the construction final
42 inspection.
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised February 14, 2018
017123-3
CONSTRUCTION STAKING AND SURVEY
Page 3 of 7
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
2 1.9 QUALITY ASSURANCE
3 A. Construction Staking
4 1. Construction staking will be performed by the Contractor.
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
2. Coordination
a. Contact City and Developer's Project Representative at least one week in
advance notifying the City of when Construction Staking is scheduled.
b. It is the Contractor's responsibility to coordinate staking such that
construction activities are not delayed or negatively impacted.
3. General
a. Contractor is responsible for preserving and maintaining stakes. If
Developer's Project Representative is required to re -stake for any reason, the
Contractor will be responsible for costs to perform staking. If in the opinion of
the City, a sufficient number of stakes or markings have been lost, destroyed
disturbed or omitted that the contracted Work cannot take place then the
Contractor will be required to stake or re -stake the deficient areas.
B. Construction Survey
1. Construction Survey will be performed by the Contractor.
2. Coordination
a. Contractor to verify that horizontal and vertical control data established in the
design survey and required for construction survey is available and in place.
3. General
a. Construction survey will be performed in order to construct the work shown
on the Construction Drawings and specified in the Contract Documents.
b. For construction methods other than open cut, the Contractor shall perform
construction survey and verify control data including, but not limited to, the
following:
1) Verification that established benchmarks and control are accurate.
2) Use of Benchmarks to furnish and maintain all reference lines and grades
for tunneling.
3) Use of line and grades to establish the location of the pipe.
4) Submit to the City copies of field notes used to establish all lines and
grades, if requested, and allow the City to check guidance system setup prior
to beginning each tunneling drive.
5) Provide access for the City, if requested, to verify the guidance system and
the line and grade of the carrier pipe.
6) The Contractor remains fully responsible for the accuracy of the work and
correction of it, as required.
7) Monitor line and grade continuously during construction.
8) Record deviation with respect to design line and grade once at each pipe
joint and submit daily records to the City.
9) If the installation does not meet the specified tolerances (as outlined in
Sections 33 05 23 and/or 33 05 24), immediately notify the City and correct
the installation in accordance with the Contract Documents.
C. As -Built Survey
1. Required As -Built Survey will be performed by the Contractor.
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised February 14, 2018
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
01 71 23 - 4
CONSTRUCTION STAKING AND SURVEY
Page 4 of 7
2. Coordination
a. Contractor is to coordinate with City to confirm which features require as -
built surveying.
b. It is the Contractor's responsibility to coordinate the as -built survey and
required measurements for items that are to be buried such that construction
activities are not delayed or negatively impacted.
c. For sewer mains and water mains 12" and under in diameter, it is acceptable
to physically measure depth and mark the location during the progress of
construction and take as -built survey after the facility has been buried. The
Contractor is responsible for the quality control needed to ensure accuracy.
3. General
a. The Contractor shall provide as -built survey including the elevation and
location (and provide written documentation to the City) of construction
features during the progress of the construction including the following:
1) Water Lines
a) Top of pipe elevations and coordinates for waterlines at the following
locations:
(1) Minimum every 250 linear feet, including
(2) Horizontal and vertical points of inflection, curvature,
etc.
(3) Fire line tee
(4) Plugs, stub -outs, dead-end lines
(5) Casing pipe (each end) and all buried fittings
2) Sanitary Sewer
a) Top of pipe elevations and coordinates for force mains and siphon
sanitary sewer lines (non -gravity facilities) at the following locations:
(1) Minimum every 250 linear feet and any buried fittings
(2) Horizontal and vertical points of inflection, curvature,
etc.
3) Stormwater — Not Applicable
b. The Contractor shall provide as -built survey including the elevation and
location (and provide written documentation to the City) of construction
features after the construction is completed including the following:
1) Manholes
a) Rim and flowline elevations and coordinates for each manhole
2) Water Lines
a) Cathodic protection test stations
b) Sampling stations
c) Meter boxes/vaults (All sizes)
d) Fire hydrants
e) Valves (gate, butterfly, etc.)
f) Air Release valves (Manhole rim and vent pipe)
g) Blow off valves (Manhole rim and valve lid)
h) Pressure plane valves
i) Underground Vaults
(1) Rim and flowline elevations and coordinates for each
Underground Vault.
3) Sanitary Sewer
a) Cleanouts
(1) Rim and flowline elevations and coordinates for each
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised February 14, 2018
017123-5
CONSTRUCTION STAKING AND SURVEY
Page 5 of 7
1 b) Manholes and Junction Structures
2 (1) Rim and flowline elevations and coordinates for each
3 manhole and junction structure.
4 4) Stormwater — Not Applicable
5 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
6 1.11 FIELD [SITE] CONDITIONS [NOT USED]
7 1.12 WARRANTY
8 PART2- PRODUCTS
9
A. A construction survey will produce, but will not be limited to:
10
1.
Recovery of relevant control points, points of curvature and points of intersection.
11
2.
Establish temporary horizontal and vertical control elevations (benchmarks)
12
sufficiently permanent and located in a manner to be used throughout construction.
13
3.
The location of planned facilities, easements and improvements.
14
a. Establishing final line and grade stakes for piers, floors, grade beams, parking
15
areas, utilities, streets, highways, tunnels, and other construction.
16
b. A record of revisions or corrections noted in an orderly manner for reference.
17
c. A drawing, when required by the client, indicating the horizontal and vertical
18
location of facilities, easements and improvements, as built.
19
4.
Cut sheets shall be provided to the City inspector and Survey Superintendent for all
20
construction staking projects. These cut sheets shall be on the standard city template
21
which can be obtained from the Survey Superintendent (817-392-7925).
22
5.
Digital survey files in the following formats shall be acceptable:
23
a. AutoCAD (.dwg)
24
b. ESRI Shapefile (.shp)
25
c. CSV file (.csv), formatted with X and Y coordinates in separate columns (use
26
standard templates, if available)
27
6.
Survey files shall include vertical and horizontal data tied to original project
28
control and benchmarks, and shall include feature descriptions
29 PART 3 - EXECUTION
30 3.1 INSTALLERS
31 A. Tolerances:
32 1. The staked location of any improvement or facility should be as accurate as
33 practical and necessary. The degree of precision required is dependent on many
34 factors all of which must remain judgmental. The tolerances listed hereafter are
35 based on generalities and, under certain circumstances, shall yield to specific
36 requirements. The surveyor shall assess any situation by review of the overall plans
37 and through consultation with responsible parties as to the need for specific
38 tolerances.
39 a. Earthwork: Grades for earthwork or rough cut should not exceed 0.1 ft. vertical
40 tolerance. Horizontal alignment for earthwork and rough cut should not exceed
41 1.0 ft. tolerance.
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised February 14, 2018
017123-6
CONSTRUCTION STAKING AND SURVEY
Page 6 of 7
1 b. Horizontal alignment on a structure shall be within .0.1ft tolerance.
2 c. Paving or concrete for streets, curbs, gutters, parking areas, drives, alleys and
3 walkways shall be located within the confines of the site boundaries and,
4 occasionally, along a boundary or any other restrictive line. Away from any
5 restrictive line, these facilities should be staked with an accuracy producing no
6 more than 0.05ft. tolerance from their specified locations.
7 d. Underground and overhead utilities, such as sewers, gas, water, telephone and
8 electric lines, shall be located horizontally within their prescribed areas or
9 easements. Within assigned areas, these utilities should be staked with an
10 accuracy producing no more than 0.1 ft tolerance from a specified location.
11 e. The accuracy required for the vertical location of utilities varies widely. Many
12 underground utilities require only a minimum cover and a tolerance of 0.1 ft.
13 should be maintained. Underground and overhead utilities on planned profile,
14 but not depending on gravity flow for performance, should not exceed 0.1 ft.
15 tolerance.
16 B. Surveying instruments shall be kept in close adjustment according to manufacturer's
17 specifications or in compliance to standards. The City reserves the right to request a
18 calibration report at any time and recommends regular maintenance schedule be
19 performed by a certified technician every 6 months.
20 1. Field measurements of angles and distances shall be done in such fashion as to
21 satisfy the closures and tolerances expressed in Part 3.1.A.
22 2. Vertical locations shall be established from a pre -established benchmark and
23 checked by closing to a different bench mark on the same datum.
24 3. Construction survey field work shall correspond to the client's plans. Irregularities
25 or conflicts found shall be reported promptly to the City.
26 4. Revisions, corrections and other pertinent data shall be logged for future reference.
27
28 3.2 EXAMINATION [NOT USED]
29 3.3 PREPARATION [NOT USED]
30 3.4 APPLICATION
31 3.5 REPAIR / RESTORATION
32 A. If the Contractor's work damages or destroys one or more of the control
33 monuments/points set by the Developer's Project Representative, the monuments shall be
34 adequately referenced for expedient restoration.
35 1. Notify City or Developer's Project Representative if any control data needs to be
36 restored or replaced due to damage caused during construction operations.
37 a. Contractor shall perform replacements and/or restorations.
38 b. The City or Developer's Project Representative may require at any time a
39 survey "Field Check" of any monument or benchmarks that are set be verified
40 by the Developer's Project Representative before further associated work can
41 move forward.
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised February 14, 2018
017123-7
CONSTRUCTION STAKING AND SURVEY
Page 7 of 7
1 3.6 RE -INSTALLATION [NOT USED]
2 3.7 FIELD [OR] SITE QUALITY CONTROL
3 A. It is the Contractor's responsibility to maintain all stakes and control data placed by the
4 Developer's Project Representative in accordance with this Specification. This includes
5 easements and right of way, if noted on the plans.
6 B. Do not change or relocate stakes or control data without approval from the City.
7 3.8 SYSTEM STARTUP
8 A. Survey Checks
9 1. The City reserves the right to perform a Survey Check at any time deemed
10 necessary.
11 2. Checks by City personnel or 3rd party contracted surveyor are not intended to
12 relieve the contractor of his/her responsibility for accuracy.
13
14
3.9
ADJUSTING [NOT USEDI
15
3.10
CLEANING [NOT USED
16
3.11
CLOSEOUT ACTIVITIES [NOT USED]
17
3.12
PROTECTION [NOT USED]
18
3.13
MAINTENANCE [NOT USED]
19
3.14
ATTACHMENTS [NOT USED]
20
21
22
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
8/31/2012 D.Johnson
Added instruction and modified measurement & payment under 1.2; added
8/31/2017 M. Owen definitions and references under 1.3; modified 1.6; added 1.7 closeout submittal
requirements; modified 1.9 Quality Assurance; added PART 2 — PRODUCTS ;
Added 3.1 Installers; added 3.5 Repair/Restoration; and added 3.8 System Startup.
Removed "blue text"; revised measurement and payment sections for Construction
Staking and As -Built Survey; added reference to selection compliance with TGC
2/14/2018 M Owen 2254; revised action and Closeout submittal requirements; added acceptable depth
measurement criteria; revised list of items requiring as -built survey "during" and
"after" construction; and revised acceptable digital survey file format
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised February 14, 2018
0174 23 -1
DAP CLEANING
Page 1 of
1 SECTION 0174 23
2 CLEANING
3 PART1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Intermediate and final cleaning for Work not including special cleaning of closed systems specified
7 elsewhere
8 B. Deviations from this City of Fort Worth Standard Specification
9 1. None.
10 C. Related Specification Sections include, but are not necessarily limited to:
11 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
12 2. Division 1— General Requirements
13 3. Section 32 9213 — Hydro -Mulching, Seeding and Sodding
14 1.2 PRICE AND PAYMENT PROCEDURES
15 A. Measurement and Payment
16 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment
17 will be allowed for this Item.
18 1.3 REFERENCES [NOT USED]
19 1.4 ADMINISTRATIVE REQUIREMENTS
20 A. Scheduling
21 1. Schedule cleaning operations so that dust and other contaminants disturbed by cleaning process will not
22 fall on newly painted surfaces.
23 2. Schedule final cleaning upon completion of Work and immediately prior to final inspection.
24 1.5 SUBMITTALS [NOT USED]
25 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
26 1.7 CLOSEOUT SUBMITTALS [NOT USED]
27 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
28 1.9 QUALITY ASSURANCE [NOT USED]
29 1.10 STORAGE, AND HANDLING
30 A. Storage and Handling Requirements
31 1. Store cleaning products and cleaning wastes in containers specifically designed for those materials.
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised April 7, 2014
017423-2
DAP CLEANING
Page 2 of 4
1 1.11 FIELD [SITE] CONDITIONS [NOT USED]
2 1.12 WARRANTY [NOT USED]
3 PART 2- PRODUCTS
4 2.1 OWNER -FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED]
5 2.2 MATERIALS
6 A. Cleaning Agents
7 1. Compatible with surface being cleaned
8 2. New and uncontaminated
9 3. For manufactured surfaces
10 a. Material recommended by manufacturer
11 2.3 ACCESSORIES [NOT USED]
12 2.4 SOURCE QUALITY CONTROL [NOT USED]
13 PART 3 - EXECUTION
14
3.1
INSTALLERS [NOT USED]
15
3.2
EXAMINATION [NOT USED]
16
3.3
PREPARATION [NOT USED]
17
3.4
APPLICATION [NOT USED]
18
3.5
REPAIR / RESTORATION [NOT USED]
19
3.6
RE -INSTALLATION [NOT USED]
20
3.7
FIELD [oR] SITE QUALITY CONTROL [NOT USED]
21
3.8
SYSTEM STARTUP [NOT USED]
22
3.9
ADJUSTING [NOT USED]
23
3.10
CLEANING
24
A. General
25
1. Prevent accumulation of wastes that create hazardous conditions.
26
2. Conduct cleaning and disposal operations to comply with laws and safety orders of governing authorities.
27
3. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in storm or sanitary drains or
28
sewers.
29
4. Dispose of degradable debris at an approved solid waste disposal site.
30
5. Dispose of nondegradable debris at an approved solid waste disposal site or in an alternate manner
31
approved by City and regulatory agencies.
32
6. Handle materials in a controlled manner with as few handlings as possible.
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised April 7, 2014
017423-3
DAP CLEANING
Page 3 of
1 7. Thoroughly clean, sweep, wash and polish all Work and equipment associated with this project.
2 8. Remove all signs of temporary construction and activities incidental to construction of required permanent
3 Work.
4 9. If project is not cleaned to the satisfaction of the City, the City reserves the right to have the cleaning
5 completed at the expense of the Contractor.
6 10. Do not burn on -site.
7 B. Intermediate Cleaning during Construction
8 1. Keep Work areas clean so as not to hinder health, safety or convenience of personnel in existing facility
9 operations.
10 2. At maximum weekly intervals, dispose of waste materials, debris and rubbish.
11 3. Confine construction debris daily in strategically located container(s):
12 a. Cover to prevent blowing by wind
13 b. Store debris away from construction or operational activities
14 c. Haul from site at a minimum of once per week
15 4. Vacuum clean interior areas when ready to receive finish painting.
16 a. Continue vacuum cleaning on an as -needed basis, until Final Acceptance.
17 5. Prior to storm events, thoroughly clean site of all loose or unsecured items, which may become airborne
18 or transported by flowing water during the storm.
19 C. Exterior (Site or Right of Way) Final Cleaning
20 1. Remove trash and debris containers from site.
21 a. Re -seed areas disturbed by location of trash and debris containers in accordance with Section 32 92
22 13.
23 2. Sweep roadway to remove all rocks, pieces of asphalt, concrete or any other object that may hinder or
24 disrupt the flow of traffic along the roadway.
25 3. Clean any interior areas including, but not limited to, vaults, manholes, structures, junction boxes and
26 inlets.
27 4. If no longer required for maintenance of erosion facilities, and upon approval by City, remove erosion
28 control from site.
29 5. Clean signs, lights, signals, etc.
30 3.11 CLOSEOUT ACTIVITIES [NOT USED]
31 3.12 PROTECTION [NOT USED]
32 3.13 MAINTENANCE [NOT USED]
33 3.14 ATTACHMENTS [NOT USED]
34
35
36
37
38
39 END OF SECTION
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised April 7, 2014
017423-4
DAP CLEANING
Page 4 of 4
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
CITY OF FORT WORTH UPS Staging— Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised April 7, 2014
1
2
3 PART1- GENERAL
4 1.1 SUMMARY
SECTION 0177 19
CLOSEOUT REQUIREMENTS
017719-1
DAP CLOSEOUT REQUIREMENTS
Page 1 of 4
5 A. Section Includes:
6 1. The procedure for closing out a contract
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
11 2. Division 1 — General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurement and Payment
14 1. Work associated with this Item is considered subsidiary to the various Items bid. No
15 separate payment will be allowed for this Item.
16 1.3 REFERENCES [NOT USED]
17 1.4 ADMINISTRATIVE REQUIREMENTS
18 A. Guarantees, Bonds and Affidavits
19 1. No application for final payment will be accepted until all guarantees, bonds, certificates,
20 licenses and affidavits required for Work or equipment as specified are satisfactorily filed
21 with the City.
22 B. Release of Liens or Claims
23 1. No application for final payment will be accepted until satisfactory evidence of release of
24 liens has been submitted to the City.
25 1.5 SUBMITTALS
26 A. Submit all required documentation to City's Project Representative.
27 1.6 INFORMATIONAL SUBMITTALS [NOT USED]
28 1.7 CLOSEOUT SUBMITTALS [NOT USED]
29 PART 2 - PRODUCTS [NOT USED]
30 PART 3 - EXECUTION
31 3.1 INSTALLERS [NOT USED]
32 3.2 EXAMINATION [NOT USED]
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised April 7, 2014
017719-2
DAP CLOSEOUT REQUIREMENTS
Page 2 of 4
3.3 PREPARATION [NOT USED]
2 3.4 CLOSEOUT PROCEDURE
3 A. Prior to requesting Final Inspection, submit:
4 1. Project Record Documents in accordance with Section 0178 39
5 2. Operation and Maintenance Data, if required, in accordance with Section 0178 23
6 B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section 01 74
7 23.
8 C. Final Inspection
9 1. After final cleaning, provide notice to the City Project Representative that the Work is
10 completed.
11 a. The City will make an initial Final Inspection with the Contractor present.
12 b. Upon completion of this inspection, the City will notify the Contractor, in writing
13 within 10 business days, of any particulars in which this inspection reveals that the
14 Work is defective or incomplete.
15 2. Upon receiving written notice from the City, immediately undertake the Work required to
16 remedy deficiencies and complete the Work to the satisfaction of the City.
17 3. Upon completion of Work associated with the items listed in the City's written notice,
18 inform the City, that the required Work has been completed. Upon receipt of this notice,
19 the City, in the presence of the Contractor, will make a subsequent Final Inspection of the
20 project.
21 4. Provide all special accessories required to place each item of equipment in full operation.
22 These special accessory items include, but are not limited to:
23 a. Specified spare parts
24 b. Adequate oil and grease as required for the first lubrication of the equipment
25 c. Initial fill up of all chemical tanks and fuel tanks
26 d. Light bulbs
27 e. Fuses
28 f. Vault keys
29 g. Handwheels
30 h. Other expendable items as required for initial start-up and operation of all equipment
31 D. Notice of Project Completion
32 1. Once the City Project Representative finds the Work subsequent to Final Inspection to be
33 satisfactory, the City will issue a Notice of Project Completion (Green Sheet).
34 E. Supporting Documentation
35 1. Coordinate with the City Project Representative to complete the following additional forms:
36 a. Final Payment Request
37 b. Statement of Contract Time
38 c. Affidavit of Payment and Release of Liens
39 d. Consent of Surety to Final Payment
40 e. Pipe Report (if required)
41 £ Contractor's Evaluation of City
42 g. Performance Evaluation of Contractor
43 F. Letter of Final Acceptance
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised April 7, 2014
017719-3
DAP CLOSEOUT REQUIREMENTS
Page 3 of 4
1
1. Upon review and acceptance of Notice of Project Completion and Supporting
2
Documentation, in accordance with General Conditions, City will issue Letter of Final
3
Acceptance and release the Final Payment Request for payment.
4 3.5
REPAIR / RESTORATION [NOT USED]
5 3.6
RE -INSTALLATION [NOT USED]
6 3.7
FIELD [OR] SITE QUALITY CONTROL [NOT USED]
7 3.8
SYSTEM STARTUP [NOT USED]
8 3.9
ADJUSTING [NOT USED]
9 3.10
CLEANING [NOT USED]
10 3.11
CLOSEOUT ACTIVITIES [NOT USED]
11 3.12
PROTECTION [NOT USED]
12 3.13
MAINTENANCE [NOT USED]
13 3.14
ATTACHMENTS [NOT USED]
14 END OF SECTION
15
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised April 7, 2014
017719-4
DAP CLOSEOUT REQUIREMENTS
Page 4 of 4
THIS PAGE INTENTIONALLY LEFT BLANK
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised April 7, 2014
017823-1
DAP OPERATION AND MAINTENANCE DATA
Page 1 of 5
SECTION 0178 23
OPERATION AND MAINTENANCE DATA
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Product data and related information appropriate for City's maintenance and
operation of products furnished under Contract
2. Such products may include, but are not limited to:
a. Traffic Controllers
b. Irrigation Controllers (to be operated by the City)
c. Butterfly Valves
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 — General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Schedule
1. Submit manuals in final form to the City within 30 calendar days of product
shipment to the project site.
1.5 SUBMITTALS
A. Submittals shall be in accordance with Section 01 33 00. All submittals shall be
approved by the City prior to delivery.
1.6 INFORMATIONAL SUBMITTALS
A. Submittal Form
1. Prepare data in form of an instructional manual for use by City personnel.
2. Format
a. Size: 8 '/z inches x 11 inches
b. Paper
1) 40 pound minimum, white, for typed pages
2) Holes reinforced with plastic, cloth or metal
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised April 7, 2014
017823-2
DAP OPERATION AND MAINTENANCE DATA
Page 2 of 5
c. Text: Manufacturer's printed data, or neatly typewritten
d. Drawings
1) Provide reinforced punched binder tab, bind in with text 2) Reduce larger
drawings and fold to size of text pages.
f. Provide fly -leaf for each separate product, or each piece of operating
equipment.
1) Provide typed description of product, and major component parts of
equipment.
2) Provide indexed tabs.
g. Cover
1) Identify each volume with typed or printed title "OPERATING AND
MAINTENANCE INSTRUCTIONS".
2) List:
a) Title of Project
b) Identity of separate structure as applicable
c) Identity of general subject matter covered in the manual
3. Binders
a. Commercial quality 3-ring binders with durable and cleanable plastic covers
b. When multiple binders are used, correlate the data into related consistent
groupings.
4. If available, provide an electronic form of the O&M Manual.
B. Manual Content
1. Neatly typewritten table of contents for each volume, arranged in systematic order
a. Contractor, name of responsible principal, address and telephone number
b. A list of each product required to be included, indexed to content of the volume
c. List, with each product:
1) The name, address and telephone number of the subcontractor or installer
2) A list of each product required to be included, indexed to content of the
volume
3) Identify area of responsibility of each
4) Local source of supply for parts and replacement
d. Identify each product by product name and other identifying symbols as set forth
in Contract Documents.
2. Product Data
a. Include only those sheets which are pertinent to the specific product.
b. Annotate each sheet to:
1) Clearly identify specific product or part installed
2) Clearly identify data applicable to installation
3) Delete references to inapplicable information
3. Drawings
a. Supplement product data with drawings as necessary to clearly illustrate:
1) Relations of component parts of equipment and systems
2) Control and flow diagrams
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised April 7, 2014
017823-3
DAP OPERATION AND MAINTENANCE DATA
Page 3 of 5
b. Coordinate drawings with information in Project Record Documents to assure
correct illustration of completed installation.
c. Do not use Project Record Drawings as maintenance drawings.
4. Written text, as required to supplement product data for the particular installation:
a. Organize in consistent format under separate headings for different procedures.
b. Provide logical sequence of instructions of each procedure.
5. Copy of each warranty, bond and service contract issued a.
Provide information sheet for City personnel giving:
1) Proper procedures in event of failure
2) Instances which might affect validity of warranties or bonds
C. Manual for Materials and Finishes
1. Submit 5 copies of complete manual in final form.
2. Content, for architectural products, applied materials and finishes:
a. Manufacturer's data, giving full information on products
1) Catalog number, size, composition
2) Color and texture designations
3) Information required for reordering special manufactured products
b. Instructions for care and maintenance
1) Manufacturer's recommendation for types of cleaning agents and methods
2) Cautions against cleaning agents and methods which are detrimental to
product
3) Recommended schedule for cleaning and maintenance
3. Content, for moisture protection and weather exposure products:
a. Manufacturer's data, giving full information on products
1) Applicable standards
2) Chemical composition
3) Details of installation
b. Instructions for inspection, maintenance and repair
D. Manual for Equipment and Systems
1. Submit 5 copies of complete manual in final form.
2. Content, for each unit of equipment and system, as appropriate:
a. Description of unit and component parts
1) Function, normal operating characteristics and limiting conditions
2) Performance curves, engineering data and tests
3) Complete nomenclature and commercial number of replaceable parts
b. Operating procedures
1) Start-up, break-in, routine and normal operating instructions
2) Regulation, control, stopping, shut -down and emergency instructions
3) Summer and winter operating instructions
4) Special operating instructions
c. Maintenance procedures
1) Routine operations
2) Guide to "trouble shooting"
3) Disassembly, repair and reassembly
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised April 7, 2014
017823-4
DAP OPERATION AND MAINTENANCE DATA
Page 4 of 5
4) Alignment, adjusting and checking
d. Servicing and lubrication schedule
1) List of lubricants required
e. Manufacturer's printed operating and maintenance instructions
f. Description of sequence of operation by control manufacturer
1) Predicted life of parts subject to wear
2) Items recommended to be stocked as spare parts
g. As installed control diagrams by controls manufacturer
h. Each contractor's coordination drawings
1) As installed color coded piping diagrams
i. Charts of valve tag numbers, with location and function of each valve
j. List of original manufacturer's spare parts, manufacturer's current prices, and
recommended quantities to be maintained in storage
k. Other data as required under pertinent Sections of Specifications
Content, for each electric and electronic system, as appropriate:
a. Description of system and component parts
1) Function, normal operating characteristics, and limiting conditions
2) Performance curves, engineering data and tests
3) Complete nomenclature and commercial number of replaceable parts
b. Circuit directories of panelboards
1) Electrical service
2) Controls
3) Communications
c. As installed color coded wiring diagrams
d. Operating procedures
1) Routine and normal operating instructions
2) Sequences required
3) Special operating instructions
e. Maintenance procedures
1) Routine operations
2) Guide to "trouble shooting"
3) Disassembly, repair and reassembly
4) Adjustment and checking
f. Manufacturer's printed operating and maintenance instructions
g. List of original manufacturer's spare parts, manufacturer's current prices, and
recommended quantities to be maintained in storage
h. Other data as required under pertinent Sections of Specifications
4. Prepare and include additional data when the need for such data becomes apparent
during instruction of City's personnel.
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE
A. Provide operation and maintenance data by personnel with the following criteria:
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised April 7, 2014
017823-5
DAP OPERATION AND MAINTENANCE DATA
Page 5 of 5
1. Trained and experienced in maintenance and operation of described products
2. Skilled as technical writer to the extent required to communicate essential data
3. Skilled as draftsman competent to prepare required drawings
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
8/31/2012 D. Johnson 1.5.A.1 — title of section removed
4/7/2014 M.Domenech Revised for DAP Application
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised April 7, 2014
017839-1
DAP PROJECT RECORD DOCUMENTS
Page 1 of 4
1 SECTION 0178 39
2 PROJECT RECORD DOCUMENTS
3 PART1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Work associated with the documenting the project and recording changes to project
7 documents, including:
8 a. Record Drawings
9 b. Water Meter Service Reports
10 c. Sanitary Sewer Service Reports
11 d. Large Water Meter Reports
12 B. Deviations from this City of Fort Worth Standard Specification
13 1. None.
14 C. Related Specification Sections include, but are not necessarily limited to:
15 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
16 2. Division 1 — General Requirements
17 1.2 PRICE AND PAYMENT PROCEDURES
18 A. Measurement and Payment
19 1. Work associated with this Item is considered subsidiary to the various Items bid.
20 No separate payment will be allowed for this Item.
21 1.3 REFERENCES [NOT USED]
22 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
23 1.5 SUBMITTALS
24 A. Prior to submitting a request for Final Inspection, deliver Project Record Documents to
25 City's Project Representative.
26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
27 1.7 CLOSEOUT SUBMITTALS [NOT USED]
28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
29 1.9 QUALITY ASSURANCE
30 A. Accuracy of Records
31 1. Thoroughly coordinate changes within the Record Documents, making adequate
32 and proper entries on each page of Specifications and each sheet of Drawings and
33 other Documents where such entry is required to show the change properly.
34 2. Accuracy of records shall be such that future search for items shown in the Contract
35 Documents may rely reasonably on information obtained from the approved Project
36 Record Documents.
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised April 7, 2014
017839-2
DAP PROJECT RECORD DOCUMENTS
Page 2 of 4
1 3. To facilitate accuracy of records, make entries within 24 hours after receipt of
2 information that the change has occurred.
3 4. Provide factual information regarding all aspects of the Work, both concealed and
4 visible, to enable future modification of the Work to proceed without lengthy and
5 expensive site measurement, investigation and examination.
6 1.10 STORAGE AND HANDLING
7 A. Storage and Handling Requirements
8 1. Maintain the job set of Record Documents completely protected from deterioration
9 and from loss and damage until completion of the Work and transfer of all recorded
10 data to the final Project Record Documents.
11 2. In the event of loss of recorded data, use means necessary to again secure the data
12 to the City's approval.
13 a. In such case, provide replacements to the standards originally required by the
14 Contract Documents.
15 1.11 FIELD [SITE] CONDITIONS [NOT USED]
16 1.12 WARRANTY [NOT USED]
17 PART 2 - PRODUCTS
18 2.1 OWNER -FURNISHED [OR] OWNER -SUPPLIED PRODUCTS [NOT USED]
19 2.2 RECORD DOCUMENTS
20 A. Job set
21 1. Promptly following receipt of the Notice to Proceed, secure from the City, at no
22 charge to the Contractor, 1 complete set of all Documents comprising the Contract.
23 B. Final Record Documents
24 1. At a time nearing the completion of the Work and prior to Final Inspection, provide
25 the City 1 complete set of all Final Record Drawings in the Contract.
26 2.3 ACCESSORIES [NOT USED]
27 2.4 SOURCE QUALITY CONTROL [NOT USED]
28 PART 3 - EXECUTION
29 3.1 INSTALLERS [NOT USED]
30 3.2 EXAMINATION [NOT USED]
31 3.3 PREPARATION [NOT USED]
32 3.4 MAINTENANCE DOCUMENTS
33 A. Maintenance of Job Set
34 1. Immediately upon receipt of the job set, identify each of the Documents with the
35 title, "RECORD DOCUMENTS - JOB SET".
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised April 7, 2014
017839-3
DAP PROJECT RECORD DOCUMENTS
Page 3 of 4
1 2. Preservation
2 a. Considering the Contract completion time, the probable number of occasions
3 upon which the job set must be taken out for new entries and for examination,
4 and the conditions under which these activities will be performed, devise a
5 suitable method for protecting the job set.
6 b. Do not use the job set for any purpose except entry of new data and for review
7 by the City, until start of transfer of data to final Project Record Documents.
8 c. Maintain the job set at the site of work.
9 3. Coordination with Construction Survey
10 a. At a minimum clearly mark any deviations from Contract Documents
11 associated with installation of the infrastructure.
12 4. Making entries on Drawings
13 a. Record any deviations from Contract Documents.
14 b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the
15 change by graphic line and note as required.
16 c. Date all entries.
17 d. Call attention to the entry by a "cloud" drawn around the area or areas affected.
18 e. In the event of overlapping changes, use different colors for the overlapping
19 changes.
20 5. Conversion of schematic layouts
21 a. In some cases, on the Drawings, arrangements of conduits, circuits, piping,
22 ducts, and similar items, are shown schematically and are not intended to
23 portray precise physical layout.
24 1) Final physical arrangement is determined by the Contractor, subject to the
25 City's approval.
26 2) However, design of future modifications of the facility may require
27 accurate information as to the final physical layout of items which are
28 shown only schematically on the Drawings.
29 b. Show on the job set of Record Drawings, by dimension accurate to within 1
30 inch, the centerline of each run of items.
31 1) Final physical arrangement is determined by the Contractor, subject to the
32 City's approval.
33 2) Show, by symbol or note, the vertical location of the Item ("under slab", "in
34 ceiling plenum", "exposed", and the like).
35 3) Make all identification sufficiently descriptive that it may be related
36 reliably to the Specifications.
37 c. The City may waive the requirements for conversion of schematic layouts
38 where, in the City's judgment, conversion serves no useful purpose. However,
39 do not rely upon waivers being issued except as specifically issued in writing
40 by the City.
41 B. Final Project Record Documents
42 1. Transfer of data to Drawings
43 a. Carefully transfer change data shown on the job set of Record Drawings to the
44 corresponding final documents, coordinating the changes as required.
45 b. Clearly indicate at each affected detail and other Drawing a full description of
46 changes made during construction, and the actual location of items.
47 c. Call attention to each entry by drawing a "cloud" around the area or areas
48 affected.
CITY OF FORT WORTH UPS Staging —Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised April 7, 2014
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
017839-4
DAP PROJECT RECORD DOCUMENTS
Page 4 of 4
d. Make changes neatly, consistently and with the proper media to assure
longevity and clear reproduction.
2. Transfer of data to other Documents
a. If the Documents, other than Drawings, have been kept clean during progress of
the Work, and if entries thereon have been orderly to the approval of the City,
the job set of those Documents, other than Drawings, will be accepted as final
Record Documents.
b. If any such Document is not so approved by the City, secure a new copy of that
Document from the City at the City's usual charge for reproduction and
handling, and carefully transfer the change data to the new copy to the approval
of the City.
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE -INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP Application
CITY OF FORT WORTH UPS Staging — Liberty Connection
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 105301
Revised April 7, 2014
FORT WORTH® CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT
STANDARD PRODUCTS LIST AS OF 12/O1/2023
Approval
I
Spec No.
Concrete
Classification
Manufacturer
Model No. National Spec
19/9/2022
03 30 00
Mix Design
American Concrete Company
30CAF029 3000 psi Concrete for Sidewalks & ADA Ramps
19/9/2022
03 30 00
Mix Design
American Concrete Company
OIJAF382 1000 psi Concrete Base Materal for Trench Repair
19/9/2022
03 30 00
Mix Design
American Concrete Company
40CNF065 4000 psi Concrete for Manholes & Utility Structures
19/9/2022
03 30 00
Mix Design
American Concrete Company
45CAF076 4500 psi Concrete for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Argos
D 10000001737 4500 psi Concrete for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Argos
D10000001791 4500 psi Concrete for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Argos
D10000001793 4500 psi Concrete for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Argos
D10000001103 4500 psi Concrete for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Argos
D10000002107 4500 psi Concrete for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Argos
D10000001273 4500 psi Concrete for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Argos
D 10000001617 3600 psi Concrete for Machine Placed Paving
19/9/2022
03 30 00
Mix Design
Argos
D10000008381 4500 psi Concrete for HES Paving
19/9/2022
03 30 00
Mix Design
Argos
D 10000009857 50 psi Flowable Fill - CLSM
19/9/2022
03 30 00
Mix Design
Argos
D10000001055 3000 psi Concrete for Inlets, Junction Boxes, Manholes, Channel Liners, Sidewalks, Driveways, Curb & Gutter
19/9/2022
03 30 00
Mix Design
Argos
D1000001043S 3000 psi Concrete for Sidewalks, Curbs
19/9/2022
03 30 00
Mix Design
Argos
D1000001565S 3000 psi Concrete for Curbs, Curb & Gutters, Sidewalks, Driveways, ADA Ramps
19/9/2022
03 30 00
Mix Design
Argos
D 100000 1615 3600 psi Concrete for Inlets, Boxes, Encasement, Blocking
19/9/2022
03 30 00
Mix Design
Argos
D10000001061 3600 psi Concrete for Inlets, Boxes, Encasement, Blocking
19/9/2022
03 30 00
Mix Design
Argos
D100000010835 4000 psi Concrete for Valve Pads, Inlets, Structures, Headwalls, Thrust Blocking
19/9/2022
03 30 00
Mix Design
Argos
D10000001083 4000 psi Concrete for Valve Pads, Inlets, Structures, Headwalls, Thrust Blocking
19/9/2022
03 30 00
Mix Design
Argos
D10000001685 4000 psi Concrete for Valve Pads
19/9/2022
03 30 00
Mix Design
Argos
D 10000005751 750 Psi Concrete Base for Trench Repair
19/9/2022
03 30 00
Mix Design
Argos
D 100000016814000 psi Concrete for Headwalls, Retaining Walls, Box Culverts, Valley Gutters
19/9/2022
03 30 00
Mix Design
Big D Concrete
7SKGRT 3000 psi Concrete for Grouting
19/9/2022
03 30 00
Mix Design
Big D Concrete
14500AE 4500 psi Concrete for High Early Strength Paving
1 5/2/2023
32 13 13
Mix Design
Big D Concrete
CM14520AE 4500 psi Concrete for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Big Town Concrete
452065-1 4500 psi hand placed paving
19/9/2022
03 30 00
Mix Design
Big Town Concrete
450065-1 4500 psi hand placed paving
19/9/2022
03 30 00
Mix Design
Borneo Texas
45U500BG 4500 psi Concrete Mix for Hand Placed Paving, Storm Structures
19/9/2022
03 30 00
Mix Design
Borneo Texas
40U553BG 4000 psi Concrete Mix for Machine Placed Paving
19/9/2022
03 30 00
Mix Design
Borneo Texas
55U 120AG 4000 psi Concrete Mix for High Early Strength Paving
19/9/2022
03 30 00
Mix Design
Borneo Texas
30U 100AG 3000 psi Concrete Mix for Pipe Collars, Inlets, Thrust Blocks, Sidewalks, ADA Ramps
19/9/2022
03 30 00
Mix Design
Borneo Texas
30U 101 AG 3000 psi Concrete Mix for Flatwork
I9/9/2022
03 30 00
Mix Design
Bumco Texas
30U500BG 3000 psi Concrete Mix for Blocking, Encasement, Curb Inlets, Junction Boxes, Fire Hydrant Pads, Driveways, Curb & Gutters,
Sidewalks, ADA Ramps
19/9/2022
03 30 00
Mix Design
Borneo Texas
40U500BG 4000 psi Concrete Mix for Storm Drain Structures, Driveways, Screen Walls, Collars
19/9/2022
03 30 00
Mix Design
Borneo Texas
36U500BG 3600 psi Concrete Mix for Lighting and Traffic Signal Foundations
19/9/2022
03 30 00
Mix Design
Borneo Texas
08Y450BA 800 psi Concrete Mix for Base for Trench Repair
19/9/2022
03 30 00
Mix Design
Borneo Texas
OIY69OBF 100 psi Concrete Mix for Flowable Fill
14/1/2023
0334 16
Mix Design
Borneo Texas
l OYH50BF 1000 psi Concrete Base Material for Trench Repair
19/9/2022
03 30 00
Mix Design
Carder Concrete
FWCC602021 4500 psi concrete for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Carder Concrete
FWCC552091 3600 psi for Machine Placed Paving
19/9/2022
03 30 00
Mix Design
Carder Concrete
FWCC602091 3600 psi for Machine Placed Paving
19/9/2022
03 30 00
Mix Design
Carder Concrete
FWCC359101 Flowable Fill - CLSM
19/9/2022
03 30 00
Mix Design
Carder Concrete
FWFF237501 Flowable Fill - CLSM
19/9/2022
03 30 00
Mix Design
Carder Concrete
FWCC602001 4000 psi Concrete for Storm Drain Structures, Manholes, Headwalls, Retaining Walls, Valley Gutters, Drive Approaches
19/9/2022
03 30 00
Mix Design
Carder Concrete
FWCC502021 3500 psi concrete for Sidewalks, Driveways, Ramps, Curb & Gutter
19/9/2022
03 30 00
Mix Design
Carder Concrete
FWCC502001 3000 psi for Sidewalks, Driveways, Ramps, Curb & Gutter, Flatwork
19/9/2022
03 30 00
Mix Design
Charleys Concrete
4142 3600 psi Concrete for Curb Inlets, Junction Boxes
19/9/2022
03 30 00
Mix Design
Charleys Concrete
4518 4000 psi Concrete for Headwalls, Wingwalls
19/9/2022
03 30 00
Mix Design
Charleys Concrete
5167 3600 psi Concrete Mix for Machine Placed Paving
19/9/2022
03 30 00
Mix Design
Charleys Concrete
4609 4500 psi Concrete Mix for Hand Placed Paving, Manholes
19/9/2022
03 30 00
Mix Design
Charleys Concrete
6103 4500 psi Concrete Mix for Hand Placed Paving, Manholes
19/9/2022
03 30 00
Mix Design
Charleys Concrete
4502 3000 psi Concrete Mix for Sidewalks
19/9/2022
03 30 00
Mix Design
Charleys Concrete
3759 3000 psi Concrete Mix for Sidewalks
19/9/2022
03 30 00
Mix Design
Charleys Concrete
1502 150 psi Concrete for Flowable Fill-CLSM
19/9/2022
03 30 00
Mix Design
Charleys Concrete
1518 150 Psi Concrete for Flowable Fill-CLSM
19/9/2022
03 30 00
Mix Design
Charleys Concrete
5642 4000 psi Concrete for Storm Drain Structures
19/9/2022
03 30 00
Mix Design
Charleys Concrete
6595 5000 psi Concrete Mix for High Early Strength Paving
19/9/2022
03 30 00
Mix Design
Charleys Concrete
6589 4500 psi Concrete Mix for High Early Strength Paving
19/9/2022
03 30 00
Mix Design
Chisholm Trail Redi Mix
C13020AE 3000 psi Concrete for Driveways, Curb & Gutter
19/9/2022
03 30 00
Mix Design
City Concrete Company
11-350-FF 50-150 psi Concrete for Flowable Fill-CLSM
FORT WORTH® CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT
Approval
Spec No.
STANDARD PRODUCTS LIST AS OF 12/O1/2023
Classification Manufacturer
Model No. National Spec
Concrete (Cm tinned)
19/9/2022
03 30 00
Mix Design
City Concrete Company
30HA25II 3000 psi Concrete for Rip -Rap
19/9/2022
03 30 00
Mix Design
City Concrete Company
30HA20II 3000 psi Concrete Mix for Blocking, Sidewalks, Flatwork, Pads
19/9/2022
03 30 00
Mix Design
City Concrete Company
45NG25II 3600 psi Concrete Mix for Drilled Shafts/Lighting and Traffic Signal Foundations
19/9/2022
03 30 00
Mix Design
City Concrete Company
50QG25II 3600 psi Slurry Displaced Drilled Shaft
19/9/2022
03 30 00
Mix Design
City Concrete Company
45NA20II 4500 psi Concrete Mix for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
City Concrete Company
36LA2011 3600 psi Concrete Mix for Machine Placed Paving
19/9/2022
03 30 00
Mix Design
City Concrete Company
36JA001J 3600 psi Concrete Mix for Machine Placed Paving
19/9/2022
03 30 00
Mix Design
City Concrete Company
40LA2011 4000 psi Concrete Mix for Storm Drain Structures
1 11 /16/2022
03 30 00
Mix Design
City Concrete Company
CLNG25II 3600 psi Concrete for Drilled Shaft/Lighting and Traffic Signal Foundations
1 5/5/2023
03 30 00
Mix Design
City Concrete Company
CCNA25OAG 3600 psi Concrete for Drilled ShaftsLighting and Traffic Signal Foundations
1 5/5/2023
03 30 00
Mix Design
City Concrete Company
CSSQA25OAG 3,600 psi Concrete for Slurry Displacement Shafts, Underwater Shafts
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
250 3000 psi Concrete Mix for Sidewalks, Driveways, ADA Ramps
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
350 3000 psi Concrete Mix for Sidewalks, Driveways, ADA Ramps
19/9/2022
0334 13
Mix Design
Cow Town Redi Mix
9 70 psi Flowable Fill - CLSM
19/9/2022
0334 13
Mix Design
Cow Town Redi Mix
9-5-2 70 psi Flowable Fill - CLSM
19/9/2022
0334 13
Mix Design
Cow Town Redi Mix
220-8 50 psi Concrete Mix for Flowable Fill - CLSM
19/9/2022
0334 13
Mix Design
Cow Town Redi Mix
320-8 50 psi Concrete Mix for Flowable Fill - CLSM
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
230-8 750 psi Concrete Base Material for Trench Repair
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
330-58 750 psi Concrete Base Material for Trench Repair
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
353 3000 psi Concrete Mix for Sidewalks, ADA Ramps, Driveways, Curb & Gutter, Safety End Treatments, Non-TxDOT Retaining Walls
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
253-W 3000 psi Concrete Mix Sidewalks, ADA Ramps, Driveways, Curb & Gutter, Safety End Treatments, Non-TxDOT Retaining Walls
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
260 4000 psi Concrete Mix for Bridge Slabs, Box Culverts, Headwalls
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
260-1 3600 psi Concrete Mix for Headwalls
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
260-2 3600 psi Concrete Mix for Box Culverts, Headwalls
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
360 4000 psi Concrete Mix for Bridge Slabs, Box Culverts, Headwalls
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
360-1 3600 psi Concrete Mix for Box Culverts, Headwalls, Wingwalls
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
264-N 4500 psi Concrete Mix for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
366 4500 psi Concrete Mix for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
265 4500 psi Concrete Mix for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
365 4500 psi Concrete Mix for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
370-NC 4500 psi Concrete for HES Paving
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
370-1NC 5000 psi Concrete for HES Paving
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
375-NC 5000 psi Concrete for HES Paving
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
267 4200 psi Concrete Mix for Manholes and Drainage Structures
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
270 5000 psi Concrete Mix for Cast -in -Place Box Culverts
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
370 5000 psi Concrete Mix for Cast -in -Place Box Culverts
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
255-2 3000 psi Concrete Mix for Inlets, Thrust Blocking, Concrete Encasement
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
257 3600 psi Concrete mix for Valley Gutters
1 11/14/2022
32 13 13
Mix Design
Cow Town Redi Mix
357-M 3600 psi Concrete Mix for Machine Placed Paving
19/9/2022
33 13 13
Mix Design
Cow Town Redi Mix
257-M 3600 psi Concrete Mix for Machine Placed Paving
19/9/2022
3413 13
Mix Design
Cow Town Redi Mix
260-M 4000 psi Concrete Mix for Machine Placed Paving
19/9/2022
35 13 13
Mix Design
Cow Town Redi Mix
360-M 4000 psi Concrete Mix for Machine Placed Paving
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
255-LP 3000 psi Concrete Mix for Curb & Gutter
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
355-LP 3000 psi Concrete Mix for Curb & Gutter
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
255 3500 psi Concrete Mix for Flatwork, Inlets, Thrust Blocking Concrete Encasement
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
355 3000 psi Concrete Mix for Inlets, Thrust Blocking, Concrete Encasement
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
365-STX 4000 psi Concrete for Bridge slabs, top slabs of direct traffic culverts, approach slabs
19/9/2022
03 30 00
Mix Design
Cow Town Redi Mix
357 3600 psi Concrete Mix for Valley Gutters
16/21/2023
03 30 00
Mix Design
Cow Town Redi Mix
360-DS 3600 psi Concrete for Drilled Shaft/Lighting and Traffic Signal Foundation
1 1/18/2023
03 30 00
Mix Design
Cow Town Redi Mix
380-NC 4500 psi Concrete for HES Paving
19/9/2022
03 30 00
Mix Design
GCH Concrete Services
GCH4000 4000 psi Concrete for for Sidewalks, Ramps, Headwalls, Inlets, and Storm Drain Structures
19/9/2022
03 30 00
Mix Design
GCH Concrete Services
GCHV5 4000 psi Concrete for Machine Placed Paving
19/9/2022
03 30 00
Mix Design
GCH Concrete Services
GCH4500 4500 psi Concrete Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Ingram Concrete & Aggregates
C47PV5E5 3000 psi Concrete for Sidewalks, ADA Ramps
19/9/2022
03 30 00
Mix Design
Ingram Concrete & Aggregates
2MWR-70J23504 3000 psi Concrete for Sidewalks, ADA Ramps
19/9/2022
03 30 00
Mix Design
Ingram Concrete & Aggregates
2M1vVR-147QW5D5 3000 psi Concrete Mix for Sidewalks, ADA Ramps
19/9/2022
03 30 00
Mix Design
Ingram Concrete & Aggregates
2MWR-056PS5D5 4000 psi Concrete Machine Placed Paving
19/9/2022
03 30 00
Mix Design
Ingram Concrete & Aggregates
2MWR-161UV5DM 4500 psi Concrete for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Ingram Concrete & Aggregates
2MWR-IOMQS50N 4500 psi Concrete for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Ingram Concrete & Aggregates
161PS5EM 4500 psi Concrete for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Ingram Concrete & Aggregates
C47PV5E5 3000 psi Concrete Mix for Sidewalks, ADA Ramps
1 4/7/2023
03 30 00
mix Design
Ingram Concrete & Aggregates
1 OLQS50N 3,600 psi Concrete for Drilled Shafts/Lighting and Traffic Signal Foundations
19/9/2022
03 30 00
Mix Design
Ingram Concrete & Aggregates
161PS5EM 4500 psi Concrete Mix for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Holcim - SOR, Inc.
1551 3000 psi Concrete Mix for Blocking
FORT WORTH® CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT
Approval
Spec No.
STANDARD PRODUCTS LIST AS OF 12/01/2023
Classification Manufacturer
Model No. National Spec
I
Concrete(Con inued)
19/9/2022
03 30 00
Mix Design
Holum - SOR, Inc.
5177 3000 psi Concrete Mix for Sidewalks
19/9/2022
03 30 00
Mix Design
Holum - SOR, Inc.
1261 3000 psi Concrete Mix for Sidewalks
19/9/2022
4 30 00
Mix Design
Holum - SOR, Inc.
2125 4500 psi Concrete for HES Paving
19/9/2022
03 30 00
Mix Design
Holum - SOR, Inc.
1701 4000 psi Concrete Mix for Stone Drain Structures, Sanitary Sewer Manholes, Junction Box
19/9/2022
03 30 00
Mix Design
Holum - SOR, Inc.
5409 4000 psi Concrete Mix for Sidewalks, Inlets
19/9/2022
03 30 00
Mix Design
Holden - SOR, Inc.
5507 4500 psi Concrete Mix for Hand Placed Paving
112/15/2022
3 30 00
Mix Design
Holden - SOR, Inc.
3741 100 psi concrete for flowable ftIUCSLM
19/9/2022
04 30 00
Mix Design
Holden - SOR, Inc.
5017 200 psi Concrete for Base Material for Trench Repair
19/9/2022
03 30 00
Mix Design
Holden - SOR, Inc.
9600 3600 psi Concrete for Drill Shafts/Lighting and Traffic Signal Foundations
19/9/2022
03 30 00
Mix Design
Holden - SOR, Inc.
1851 4500 psi Concrete for Storm Drain Structures, Hand Placed Paving
112/5/2022
4 30 00
Mix Design
Holden - SOR, Inc.
1822 3600 psi Concrete for Drilled Shafts/Lighting and Traffic Signal Foundations
19/9/2022
03 30 00
Mix Design
Holden - SOR, Inc.
1859 4000 psi Concrete for Drilled Shafts/Lighting and Traffic Signal Foundations
14/7/2023
03 30 00
Mix Design
Liquid Stone
C301D 3,000 psi Concrete for Sidewalks, Approaches, and Driveways.
1 4/27/2023
03 30 00
Mix Design
Liquid Stone
C361DNFA 3,600 psi Concrete for Retaining wall, driveway, junction box apron, approach
14/7/2023
03 30 00
Mix Design
Liquid Stone
C361DHR 3,600 psi Concrete for Drilled Shaft/Lighting and Traffic Signal Foundations
1 1/24/2023
03 30 00
Mix Design
Liquid Stone
C451DHR-A 4500psi Concrete for HES Paving
19/9/2022
03 30 00
Mix Design
Martin Marietta
R2132214 3,000 psi Concrete for Sidewalks & Ramps
19/9/2022
03 30 00
Mix Design
Martin Marietta
D9490SC 3,000 psi Concrete for Sidewalks & Ramps
19/9/2022
03 30 00
Mix Design
Martin Marietta
R2131214 3,000 psi Concrete for Sidewalks & Ramps
19/9/2022
03 30 00
Mix Design
Martin Marietta
R2131314 3,000 psi Concrete for Sidewalks & Ramps
19/9/2022
03 30 00
Mix Design
Martin Marietta
R2136014 3,000 psi Concrete for Sidewalks & Ramps
19/9/2022
03 30 00
Mix Design
Martin Marietta
R2136214 3,000 psi Concrete for Sidewalks & Ramps
19/9/2022
03 30 00
Mix Design
Martin Marietta
R2141224 4,000 psi Concrete for Sidewalks & Ramps
19/9/2022
03 30 00
Mix Design
Martin Marietta
R2141024 4,000 psi Concrete for Sidewalks & Ramps
19/9/2022
03 30 00
Mix Design
Martin Marietta
R2136224 3,600 psi Concrete for Curb Inlets
19/9/2022
03 30 00
Mix Design
Martin Marietta
R2141233 3,600 psi Concrete for Storm Structures, Inlets, Blocking & Encasement
19/9/2022
03 30 00
Mix Design
Martin Marietta
FLOW25A 50 psi Concrete for Flowable Fill/CLSM
19/9/2022
03 30 00
Mix Design
Martin Marietta
R2142233 3,600 psi Concrete for Manholes, Inlets & Headwalls
19/9/2022
03 30 00
Mix Design
Martin Marietta
R2146333 3,600 psi Concrete for Manholes, Inlets & Headwalls, Concrete Encasement
19/9/2022
03 30 00
Mix Design
Martin Marietta
R21412304,000 psi Concrete for Manholes, Inlets & Headwalls, Valve Pads
19/9/2022
03 30 00
Mix Design
Martin Marietta
R2146035 4,000 psi Concrete for Manholes, Inlets & Headwalls, Valve Pads
19/9/2022
03 30 00
Mix Design
Martin Marietta
R2146335 4,500 psi Concrete for Hand Placed Paving, Inlets, Storm Drain Structures
1 11/2/2022
32 13 13
Mix Design
Martin Marietta
Q2141 N27 4,000 psi Concrete for Machine Placed paving
1 11/2/2022
32 13 13
Mix Design
Martin Marietta
Q2141K30 4,000 psi Concrete for Machine Placed Paving
1 11/2/2022
32 13 13
Mix Design
Martin Marietta
R2146N36 4,500 psi Concrete for Hand Placed Paving
1 11/15/2022
33 13 13
Mix Design
Martin Marietta
R2146K36 4,500 psi Concrete for Hand Placed Paving
1 11/15/2022
3413 13
Mix Design
Martin Marietta
R2146P36 4,500 psi Concrete for Hand Placed Paving
1 11/2/2022
32 13 13
Mix Design
Martin Marietta
R2146K36 4,500 psi Concrete for Hand Placed Paving
1 11/2/2022
32 13 13
Mix Design
Martin Marietta
R2146N35 / 6.11 sacks / 4,500 psi concrete for Hand Place Paving, Inlets, Manholes, Headwalls
1 11/2/2022
32 13 13
Mix Design
Martin Marietta
R2146K34 4,000 psi Concrete for Inlets, Manholes, Headwalls
1 11/2/2022
32 13 13
Mix Design
Martin Marietta
R2141N24 4,000 psi Concrete for Sidewalks and Ramps
1 11/2/2022
32 13 13
Mix Design
Martin Marietta
R2141K24 4,000 psi Concrete for Junction Boxes, Sidewalks and Ramps
19/9/2022
03 30 00
Mix Design
Martin Marietta
R2146038 4,500 psi Concrete for Inlets, Storm Drain Structures
19/9/2022
03 30 00
Mix Design
Martin Marietta
R2146036 4,500 psi Concrete for Hand Placed Paving, Inlets
19/9/2022
03 30 00
Mix Design
Martin Marietta
R2146042 4,500 psi Concrete for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Martin Marietta
R2146242 4,500 psi Concrete for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Martin Marietta
R2146236 4,500 psi Concrete for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Martin Marietta
D9493SC 4,500 psi Concrete for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Martin Marietta
R2147241 4,500 psi Concrete for Hand Placed Paving
14/l/2023
32 13 20
Mix Design
Martin Marietta
R2136N14 / 5.00 sacks / 3,000 psi concrete for Sidewalks
14/l/2023
03 30 00
Mix Design
Martin Marietta
R21461`33 / 6.01 sacks / 4,000 psi concrete for Bridge Deck
14/l/2023
03 30 00
Mix Design
Martin Marietta
R2146033 4,000 psi Concrete for Ripmp
14/7/2023
32 13 20
Mix Design
Martin Marietta
R2136K14 3,000 psi concrete for sidewalks and ramps
14/7/2023
32 13 13
Mix Design
Martin Marietta
R2161K70 6,000 psi (3,000 psi @ 24Ius.) for HES Paving
14/l/2023
03 30 00
Mix Design
Martin Marietta
310LBP 3,600 psi Concrete for Retaining Walls
1 5/22/2023
32 13 13
Mix Design
Martin Marietta
R2146K37/6.22 sack / 4,500 psi Concrete for Hand Placed Paving
14/l/2023
03 30 00
Mix Design
Martin Marietta
R2141030 4,000 psi Concrete for Ripmp
FORT WORTH® CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT
Approval
Spec No.
STANDARD PRODUCTS LIST AS OF 12/O1/2023
Classification Manufacturer
Model No. National Spec
I
Concrete(Con inued)
1 5/3/2023
03 30 00
Mix Design
Martin Marietta
M7842344 4,000 psi Concrete for Bridge Deck
16/1/2023
32 1320
Mix Design
Martin Marietta
R2136R20 3,000 psi Concrete for Sidewalks and Ramps
16/1/2023
32 1320
Mix Design
Martin Marietta
R2136N20 3,000 psi Concrete for Sidewalks and Ramps
1 6/27/2023
03 30 00
Mix Design
Martin Marietta
U2146N41 / 6.44sacks / 3,600 psi Concrete for Drilled Shafts / Lighting and Traffic Signal Foundations
1 6/27/2023
03 30 00
Mix Design
Martin Marietta
U2146K45 / 6.65 sacks / 3,600 psi Concrete for Drilled Shafts / Lighting and Trafic Signal Foundations
1 8/4/2023
03 30 00
Mix Design
Martin Marietta
U2146R41 / 6.44 sacks / 4,500 psi Concrete for Drilled Piers/Light Pole bases.
1 8/4/2023
03 30 00
Mix Design
Martin Marietta
R2136R14 / 5.00 sacks / 3,500 psi Concrete for Sidewalks and Ramps
1 8/4/2023
32 1320
Mix Design
Martin Marietta
R2141 R24 / 5.53 / 4,000 psi Concrete for Junction Box, Box Culvert, Sidewalks and Ramps.
1 8/4/2023
03 30 00
Mix Design
Martin Marietta
R2146R35 / 6.11 / 4,500 psi Concrete for Inlets, Manholes, and Headwalls
1 8/4/2023
32 13 13
Mix Design
Martin Marietta
R2146R36 / 6.17 / 4,500 psi Concrete for Hand Placed Paving
1 8/30/2023
03 30 00
Mix Design
Martin Marietta
R2141 R30 / 5.85 SK / 4,000 psi Concrete for Box Culverts & Headwalls
1 8/4/2023
32 13 13
Mix Design
Martin Marietta
Q2141 R27 / 5.69 sacks / 4,000 psi Concrete for Machine Placed Paving
1 11/20/2023
03 30 00
Mix Design
Martin Marietta
R2146R33 / 6.01 Sacks / 4,000 psi Concrete Mix for CIP Sewer Manholes
1 11 /20/2023
03 30 00
Mix Design
Martin Marietta
R2146K33 / 6.01 Sacks / 4,000 psi Concrete Mix for CIP Sewer Manholes.
19/9/2022
32 1320
Mix Design
NCS Redi Mix
NCS5020A 3000 psi Concrete Mix for Curb & Gutter, Driveways, Sidewalks
19/9/2022
03 30 00
Mix Design
NBR Ready Mix
TX C-YY 3000 psi Concrete Mix for Curb Inlets
19/9/2022
03 30 00
Mix Design
NBR Ready Mix
TX C-NY 3000 psi Concrete Mix for Curb Inlets
19/12/2023
03 30 00
Mix Design
NBR Ready Mix
CLS Pl-YY / 6.00 Sacks / 4,000 psi Concrete for Collars, Manholes, Box Culverts
1 10/4/2023
03 30 00
Mix Design
NBR Ready Mix
CLS A-YY / 5.00 Sacks / 3,000 psi Concrete for Sidewalks & Ramps, and Curb & Gutter
1 10/4/2023
03 30 00
Mix Design
NBR Ready Mix
CLS A -NY/ 5.00 Sacks / 3,000 psi Concrete for Sidewalks & Ramps, and Curb & Gutter
1 10/4/2023
32 13 13
Mix Design
NBR Ready Mix
TX C SF-YY / 5.50 Sacks / 3,600 psi Concrete for Machine Placed Paving
1 10/4/2023
32 13 13
Mix Design
NBR Ready Mix
TX C SF -NY 5.50 Sacks / 3,600 psi Concrete for Machine Placed Paving
1 10/4/2023
32 13 13
Mix Design
NBR Ready Mix
CLS P2-YY / 6.50 Sacks / 4,500 psi Concrete for Hand Placed Paving
1 10/4/2023
32 13 13
Mix Design
NBR Ready Mix
CLS P2-NY / 6.50 Sacks / 4,500 psi Concrte for Hand Placed Paving
1 10/4/2023
0334 13
Mix Design
NBR Ready Mix
FTW FLOW FILL / 150 psi concrete for Flowable
17/10/2023
03 30 00
Mix Desigg
Osborn
30A50MR / 5 SK / 3,000 psi Concrete for Sidewalks
17/10/2023
32 13 13
Mix Design
Osborn
45A60MR / 6 SK / 4,500 psi Concrete for Hand Placed Paving
1 1/24/2023
03 30 00
Mix Design
Rapid Redi Mix
RRM6320AHP 4500 psi Concrete for Hand Placed Paving
1 1/24/2023
03 30 00
Mix Design
Rapid Redi Mix
RRM5525A 3600 psi Concrete for Valley Gutters, Sidewalks, Approaches, ADA Ramps
1 1/18/2023
03 30 00
Mix Design
Rapid Redi Mix
RRM6020ASS 4000 psi Concrete for Strom Drain Structures
1 1/18/2023
03 30 00
Mix Design
Rapid Redi Mix
RRM5320A 3000 psi Concrete for Blocking
1 1/18/2023
03 30 00
Mix Design
Rapid Redi Mix
RRM5020A 3000 psi Concrete for Curb, Gutter, Driveways, Sidewalk, Ramps
19/9/2022
03 30 00
Mix Design
Redi-Mix
DCA2E554 3000 psi Concrete Mix for Rip Rap
19/9/2022
03 30 00
Mix Design
Redi-Mix
VOJ11524 3000 psi Concrete Mix for Curb & Gutter
19/9/2022
0334 13
Mix Design
Redi-Mix
FOCIO021 215 psi Flowable Fill - CLSM
19/9/2022
03 30 00
Mix Design
Redi-Mix
1 OJI 1524 3000 psi Concrete Mix for Driveways, Sidewalks, ADA Ramps
19/9/2022
03 30 00
Mix Design
Redi-Mix
1OJ11504 3000 psi Concrete Mix for Sidewalks
19/9/2022
03 30 00
Mix Design
Redi-Mix
1OL11504 / 6.00 Sacks / 4,000 psi Concrete Mix for Sidewalks, Curb & Gutter, Sewer Manhole, Inlets, & Junction Boxes
19/9/2022
03 30 00
Mix Design
Redi-Mix
1OL11524 / 6.00 Sacks / 4,000 psi Concrete Mix Manholes, Inlets, Junction Boxes, Headwalls
19/9/2022
03 30 00
Mix Design
Redi-Mix
1RJ11524 3500 psi Concrete Mix for Thrust Blocks, Valve Pads
1 9/29/2022
03 30 00
Mix Design
Redi-Mix
1 OL21524 4000 psi Concrete Mix for Manholes
19/9/2022
03 30 00
Mix Design
Redi-Mix
15611524 4000 psi Concrete Mix for Cast -in -Place Storm Drain Structures
19/9/2022
03 30 00
Mix Design
Redi-Mix
1OL115E4 3600 psi Concrete Mix for Bridge substructures
19/9/2022
03 30 00
Mix Design
Redi-Mix
156115D4 4000 psi Bridge Slabs
19/9/2022
0334 13
Mix Design
Redi-Mix
F35238VN 100 psi Flowable Fill - CLSM
19/9/2022
0334 13
Mix Design
Redi-Mix
FOD138VM 100 psi Flowable Fill - CLSM
19/9/2022
0334 13
Mix Design
Redi-Mix
1 OJI1554 3000 psi Concrete Mix for Rip -Rap
19/9/2022
03 30 00
Mix Design
Redi-Mix
POG138K9 1000 psi Concrete Mix for Trench Repair Base Material
19/9/2022
03 30 00
Mix Design
Redi-Mix
1 OK11524 3600 psi Concrete Mix for Encasement
19/9/2022
03 30 00
Mix Design
Redi-Mix
1 ON11507 4500 psi (2600 psi @ 24 hrs.) Concrete Mix for HES Paving
19/9/2022
03 30 00
Mix Design
Redi-Mix
1 ON11504 5000 psi (3600 psi @ 2 days) Concrete Mix for HES Paving
19/9/2022
03 30 00
Mix Design
Redi-Mix
50KI 1524 3600 psi Concrete Mix for Machine Placed Paving
19/9/2022
03 30 00
Mix Design
Redi-Mix
1 OM115D4 4500 psi Concrete Mix for Hand Placed Paving, Storm Drain Structures
19/9/2022
03 30 00
Mix Design
Redi-Mix
1 OM11524 4500 psi Concrete Mix for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Redi-Mix
1 OM11504 4500 psi Concrete Mix for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Redi-Mix
145CD5P4 4500 psi Concrete Mix for Hand Placed Paving, Storm Drain Structures
1 11/2/2022
03 30 00
Mix Design
Redi-Mix
1451`251`4 4500 psi Concrete for Storm Drain Structures
1 12/5/2022
03 30 00
Mix Design
Redi-Mix
1 OK115C4 3500 psi Concrete for Thrust Blocks, Valve Pads
1 12/5/2022
03 30 00
Mix Design
Redi-Mix
156115C4 4000 psi Concrete for CIP Storm Drain Structures
1 12/5/2022
03 30 00
Mix Design
Redi-Mix
1 OL115C4 3600 psi Concrete for Manhole, Inlet, Junction Box, Headwall
15/15/2023
03 30 00
Mix Design
Redi-Mix
80L115135 3600 psi Concrete for Drilled Shafts/Lighting and Traffic Signal Foundations
15/15/2023
03 30 00
Mix Design
Redi-Mix
1 ON115D6 Slurry Displacement Shafts, Underwater Drilled shafts
19/9/2022
0334 13
Mix Design
SRM Concrete
30000 3,000 psi Concrete for Sidewalks and Ramps, Curb & Gutter
19/9/2022
0334 13
Mix Design
SRM Concrete
40050 4,000 psi Concrete for Headwalls, Retaining Wall, Collars
19/9/2022
03 30 00
Mix Design
SRM Concrete
35023 3,600 psi Concrete for Machine Placed Paving
19/9/2022
03 30 00
Mix Design
SRM Concrete
40068 3,600 psi Concrete for Machine Placed Paving
19/9/2022
03 30 00
Mix Design
SRM Concrete
45000 4,500 psi Concrete for Hand Placed Paving
FORT WORTH® CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT
Approval
Spec No.
STANDARD PRODUCTS LIST AS OF 12/01/2023
Classification Manufacturer
Model No. National Spec
I
Concrete(Con
inued)
19/9/2022
03 30 00
Mix Design
SRM Concrete
45300 4,500 psi Concrete for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
SRM Concrete
40326 4,500 (3,00 (il 3-days) psi Concrete for HES Paving
19/9/2022
03 30 00
Mix Design
SRM Concrete
35022 3,600 psi Concrete for Junction Box, Retaining Walls
19/9/2022
03 30 00
Mix Design
SRM Concrete
30050 3,000 psi Concrete for Sidewalks, Ramps, Inlets, Junction Boxes, Thrust Blocks, Curb and Gutter, Driveways, Barrier Ramp
12/10/2023
03 30 00
Mix Design
SRM Concrete
50310 5,000 psi Concrete for HES Paving
1 1/13/2023
32 13 13
Mix Design
SRM Concrete
45023 4,500 psi Concrete for Hand Placed Paving
15/5/2023
03 30 00
Mix Design
SRM Concrete
D100008553CB 4,000 psi Concrete for Bdridge Approach Slab, Deck Slab
19/9/2022
03 30 00
Mix Design
Tarrant Concrete
FW60AHP 4500 psi Concrete Mix for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Tarrant Concrete
FW6020AHP 4500 psi Concrete Mix for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Tarrant Concrete
TCFW6020AHP 4500 psi Concrete Mix for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
Tarrant Concrete
FW7520AMR 4500 (3000 psi to) 3-days) psi Concrete HES Paving
19/9/2022
03 30 00
Mix Design
Tarrant Concrete
FW6520AMR 4500 (3000 psi (d 3-days) psi HES Paving
19/9/2022
03 30 00
Mix Design
Tarrant Concrete
FW5520AMP 3600 psi Concrete for Machine Placed Paving
19/9/2022
03 30 00
Mix Design
Tarrant Concrete
FW5320A 3000 psi Concrete Mix for Blocking
19/9/2022
0334 13
Mix Design
Tarrant Concrete
FWFF150CLSM 50-150 psi Flowable Fill - CLSM
19/9/2022
0334 13
Mix Design
Tarrant Concrete
FWFF275 50-150 psi Flowable Fill - CLSM
19/9/2022
03 30 00
Mix Design
Tarrant Concrete
FW6020A2 4000 psi Concrete Mix for Storrs Drain Structures
1 10/10/2022
03 30 00
Mix Design
Tarrant Concrete
TCFW6025A2 4000 psi Concrete for Manholes
1 10/10/2022
03 30 00
Mix Design
Tarrant Concrete
TCFW5020A 3000 psi Concrete for Sidewalks
19/9/2022
03 30 00
Mix Design
Tarrant Concrete
FW5025A 3000 psi Concrete Mix for Curb & Gutter, Driveways, Sidewalks, ADA Ramps
19/9/2022
03 30 00
Mix Design
Titan Ready Mix
3020AE 3000 psi Concrete for Sidewalks
19/9/2022
03 30 00
Mix Design
Tarrant Concrete
CP5020A 3000 psi Concrete Mix for Curb and Gutter
19/9/2022
03 30 00
Mix Design
Tarrant Concrete
FW5525A2 3600 psi Concrete Mix for Sidewalks, Drive Approaches, ADA Ramp
19/9/2022
03 30 00
Mix Design
Titan Ready Mix
TRC4520 4500 psi Concrete for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
True Grit Redi Mix
0250.230 3000 psi Concrete Mix for Flatwork, Curb & Gutter, Driveways, Sidewalks, ADA Ramps
19/9/2022
03 30 00
Mix Design
True Grit Redi Mix
270.230 5000 psi Concrete for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
True Grit Redi Mix
0250.2301 3000 psi Concret Mix for Curb & Gutter, Driveways, Sidewalks, ADA Ramps
19/9/2022
03 30 00
Mix Design
True Grit Redi Mix
0260.2302 4000 psi Concrete Mix for Machine Placed Paving
19/9/2022
03 30 00
Mix Design
True Grit Redi Mix
0255.2301 3600 psi Concrete Mix for Machine Placed Paving
19/9/2022
03 30 00
Mix Design
True Grit Redi Mix
0260.2301 4500 psi Concrete Mix for Hand Placed Paving
19/9/2022
03 30 00
Mix Design
True Grit Redi Mix
0265.2301 4500 psi Concrete Mix for Valley Gutters, Hand Placed Paving
1 11/30/2023
32 13 13
Mix Design
Wildcatter Redi-Mix
3620AI / 6.00 Sacks / 3,600 psi Concrete Mix for Machine Placed Paving
1 11/20/2023
32 13 13
Mix Design
Wildcatter Redi-Mix
4520AI / 6.50 Sacks / 4,500 psi Concrete Mix for Hand Placed paving
1 11/20/2023
03 30 00
Mix Design
Wildcatter Redi-Mix
3020AI / 5.00 Sacks / 3,000 psi Concrete Mix for Sidewalks and Inlets
1 11/30/2023
03 30 00
Mix Design
Wildcatter Redi-Mix
4020AI / 6.00 Sacks / 4,000 psi Concrete Mix for Sidewalks and Inlets
19/9/2022
03 30 00
Mix Design
Wise Redi Mix
3678 3600 psi Concrete Mix for Lighting and Traffic Signal Foundations
Aall Payin�j
19/9/2022
32216
Mix Desr
Austin Asphalt
FT5D137965 PG64-22 Type D Fine Surface
19/9/2022
32 1216
Mix Desr
Austin Asphalt
DA51)135965 PG64-22 Type D Fine Surface
19/9/2022
32 1216
Mix Desr
Austin Asphalt
FT5B 117965 PG64-22 Type B Fine Base
19/9/2022
32 12 16
Mix Des�n
Austin Asphalt
FT1B139965 PG64-22 Type B Fine Base
19/9/2022
32 12 16
Mix Des�n
Austin Asphalt
FT1B117.2 PG64-22 Type B Fine Base
19/9/2022
32 12 16
Mix Desr
Reynolds Asphalt
1901D PG64-22 Type D Fine Surface
19/9/2022
32 12 16
Mix Desr
Reynolds Asphalt
1112B PG64-22 Type B Fine Base
19/9/2022
32 12 16
Mix Design
Reynolds Asphalt
1612B PG64-22 Type B Fine Base
1 11/20/2023
32 12 16
Mix Design
Reynolds Asphalt
2101D PG64-22 Type D Fine Surface
19/9/2022
32 12 16
Mix Design
Surmount Paving
341DV6422 PG64-22 Type D Fine Surface
1 11/26/2022
32 12 16
Mix Design
Surmount Paving
340DV6422 PG64-22 Type D Fine Surface
1 12/5/2022
33 12 16
Mix Design
Sunmount Paving
3076BV6422 PG62-22 Type B Fine Base
19/9/2022
32 12 16
Mix Design
Sunmount Paving
341-BRAP6422ERG PG64-22 Type B Fine Base
19/9/2022
32 12 16
Mix Design
TXBIT
37-211305-20 PG64-22 Type B Fine Base
19/9/2022
32 12 16
Mix Design
TXBIT
44-211305-17 PG64-22 Type B Fine Base
19/9/2022
32 12 16
Mix Design
TXBIT
211305 (1757) PG64-22 Type B Fine Base
19/9/2022
32 12 16
Mix Design
TXBIT
222475 (1857) PG64-22 Type D Fine Surface
19/9/2022
32 12 16
Mix Design
TXBIT
29-222475-19 PG64-22 Type D Fine Surface
19/9/2022
32 12 16
Mix Design
TXBIT
1-222475-20 PG64-22 Type D Fine Surface
19/9/2022
32 12 16
Mix Design
TXBIT
64-224125-18 PG70-22 Type D Fine Surface
19/9/2022
32 12 16
Mix Design
TXBIT
12-222475-19 PG64-22 Type D Fine Surface
Detectable Wami Surface
19/9/2022
32 13 20
DW -Pavers
Pine Hall Brick (Winston Salem, NC)
Tactile Pavers
19/9/2022
32 1320
DWS - Pavers
Western Brick Co. (Houston, TX)
Detectable Warning Pavers
19/9/2022
32 1320
DWS - Composite
Engineered Plastics, Inc. (Williamsville,
7 Armor Tile
19/9/2022
32 1320
DWS - Composite
ADA Solutions (Wilmington, MA)
Heritage Brick CIP Composite Paver
14/7/2023
32 1320
DWS - Pavers
ADA Solutions (Wilmington, MA)
Detectable Warning Pavers
FORT WORTH® CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT
STANDARD PRODUCTS LIST AS OF 12/01/2023
Approval Spec No. Classification Manufacturer Model No. National Spec
Silicone Joint
Sealant
19/9/2022
132 1373
Joint Sealant
Dow
890SL - Cold Applied, Single Component, Silicone Joint Sealant
ASTM D5893
19/9/2022
132 1373
Joint Sealant
Tremco
900SL - Cold Applied, Single Component, Silicone Joint Sealant
ASTM D5893
19/9/2022
132 1373
Joint Sealant
Pecom
300SL - Cold Applied, Single Component, Silicone Joint Sealant
ASTM D5893
19/9/2022
132 1373
Joint Sealant
Cralbo
RoadSaver Silicone - Cold Applied, Single Component, Silicone Joint Sealant
ASTM D5893
Utili . Trench Embedment Sand
19/9/2022
33 05 ]0
Embedment Sand
Silver Creek Materials
Utility Embedment Sand
ASTM C33
19/9/2022
3305 10
Embedment Sand
Crouch Materials
Utility Embedment Sand
ASTM C33
19/9/2022
3305 10
Embedment Sand
F and L Dirt Movers
Utility Embedment Sand
ASTM C33
19/9/2022
3305 10
Embedment Sand
F and L Dirt Movers
Utility Embedment Sand
ASTM C33
19/9/2022
3305 10
Embedment Sand
Tin Top Martin Marietta
Utility Embedment Sand
ASTM C33
Storm Sewer
- Manholes & Bases/Frames & 47bvers/Standard (Round) 33-05-13
19/28/2018
3305 13
Manhole Frames and Covers
AccuCast (Govind Steel Company, LTD)
MHRC 4220605 (Size - **24" Dia.)
ASTM A48 AASHTO M306
19/28/2018
3305 13
Manhole Cover
Neenah Foundry
NF-1274-1791 (Size - 32" Dial
ASTM A48 AASHTO M306
19/28/2018
3305 13
Manhole Frames and Covers
Neenah Foundry
NF-1743-LM (Hinged) (Size - 32" Dial
ASTM A48 AASHTO M306
19/28/2018
3305 13
Manhole Frame
Neenah Foundry
NF-1930-30 (Size - 32.25" Dial
ASTM A48 AASHTO M306
19/28/2018
3305 13
Manhole Frames and Covers
Neenah Foundry
R-1743-ITV (Size - 32" Dia.)
ASTM A48 AASHTO M306
1 4/3/2019
3305 13
Manhole Frames and Covers
SIP Industries ++
2279ST (Size - 24" Dia.)
ASTM A48 AASHTO M306
1 4/3/2019
3305 13
Manhole Frames and Covers
SIP Industries ++
2280ST (Size - 32" Dia.)
ASTM A48 AASHTO M306
1 10/8/2020
3305 13
Manhole Frames and Covers
EJ ( Formally East Jordan Iron Works)
EJ1033 Z2/A (Size - 32.25" Dia.)
ASTM A536 AASHTO M306
**Note: All new development
and new installation manhole lids sha l meet the minimum 30-inch opening requirement as specified in City Specification 33 0513. Any smaller opening sizes will only be allowed for existing manholes that require replacement frames and
covers.
FORT WORTH® CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT
Approval
Spec No.
STANDARD PRODUCTS LIST AS OF 12/O1/2023
Classification Manufacturer
Model No.
National Spec
Storm Sewer - Inlet & Structures 33-05-13
110/8/2020
33 49 20
Curb Inlets
Fortenra
FRT-1 Ox3-405-PRECAST** (Size - 10' X 3')
ASTM C913
110/8/2020
33 49 20
Curb Inlets
Fortema
FRT-100-406-PRECAST** (Size - 10' X 3')
ASTM C913
110/8/2020
33 49 20
Curb Inlets
Fortema
FRT-lOx4.5-407-PRECAST** (Size - 10' X 4.5')
ASTM C913
110/8/2020
33 49 20
Curb Inlets
Fortema
FRT-lOx4.5-420-PRECAST** (Size - 10' X 4.5')
ASTM C913
110/8/2020
33 39 20
Manhole
Fortema
FRT-4X4-409-PRECAST-TOP (Size - 4' X 4')
ASTM C913
110/8/2020
33 39 20
Manhole
Fortema
FRT-4X4-409-PRECAST-BASE (Size - 4' X 4')
ASTM C913
110/8/2020
33 39 20
Manhole
Fortema
FRT-5X5-410-PRECAST-TOP (Size - 5' X 5')
ASTM C913
110/8/2020
33 39 20
Manhole
Fortema
FRT-5X5-410-PRECAST-BASE (Size - 5' X 5')
ASTM C913
110/8/2020
33 39 20
Manhole
Fortema
FRT-6X6-411-PRECAST-TOP (Size - 6' X 6')
ASTM C913
110/8/2020
33 39 20
Manhole
Fortema
FRT-6X6-411-PRECAST-BASE (Size - 6' X 6')
ASTM C913
13/19/2021
33 49 20
Curb Inlets
Thompson Pipe Group
TPG-IOX3-405-PRECAST INLET** (Size - 10' X 3')
ASTM 615
13/19/2021
33 49 20
Curb Inlets
Thompson Pipe Group
TPG-15X3-405-PRECAST INLET** (Size - 15' X 3')
ASTM 615
13/19/2021
33 49 20
Curb Inlets
Thompson Pipe Group
TPG-20X3-405-PRECAST INLET** (Size - 20' X T)
ASTM 615
13/19/2021
33 39 20
Manhole
Thompson Pipe Group
TPG-4X4-409-PRECAST TOP (Size - 4' X 4')
ASTM 615
13/19/2021
33 39 20
Manhole
Thompson Pipe Group
TPG-4X4-409-PRECAST BASE (Size - 4' X 4')
ASTM 615
13/19/2021
33 39 20
Manhole
Thompson Pipe Group
TPG-4X4-412-PRECAST 4-FT RISER (Size - 4' X 4')
ASTM 615
13/19/2021
33 39 20
Manhole
Thompson Pipe Group
TPG-5X5-410-PRECAST TOP (Size - 5' X 5')
ASTM 615
13/19/2021
33 39 20
Manhole
Thompson Pipe Group
TPG-5X5-410-PRECAST BASE (Size - 5' X 5')
ASTM 615
13/19/2021
33 39 20
Manhole
Thompson Pipe Group
TPG-5X5-412-PRECAST 5-FT RISER (Size - 5' X 5')
ASTM 615
13/19/2021
33 39 20
Manhole
Thompson Pipe Group
TPG-6X6-411-PRECAST TOP (Size - 6' X 6)
ASTM 615
13/19/2021
33 39 20
Manhole
Thompson Pipe Group
TPG-6X6-411-PRECAST BASE (Size - 6' X 6')
ASTM 615
13/19/2021
33 39 20
Manhole
Thompson Pipe Group
TPG-6X6-412-PRECAST 6-FT RISER (Size - 6' X 6')
ASTM 615
13/19/2021
33 39 20
Manhole
Thompson Pipe Group
TPG-7X7-411-PRECAST TOP (Size - TX T)
ASTM 615
13/19/2021
33 39 20
Manhole
Thompson Pipe Group
TPG-7X7-411-PRECAST BASE (Size - TX T)
ASTM 615
13/19/2021
33 39 20
Manhole
Thompson Pipe Group
TPG-7X7-412-PRECAST 4-FT RISER (Size - TX T)
ASTM 615
13/19/2021
33 39 20
Manhole
Thompson Pipe Group
TPG-8X8-411-PRECAST TOP (Size - 8' X 8')
ASTM 615
13/19/2021
33 39 20
Manhole
Thompson Pipe Group
TPG-8X8-411-PRECAST BASE (Size - 8' X 8')
ASTM 615
13/19/2021
33 39 20
Manhole
Thompson Pipe Group
TPG-8X8-412-PRECAST 5-FT RISER (Size - 8' X 8')
ASTM 615
13/19/2021
33 49 20
Drop Inlet
Thompson Pipe Group
TPG-4X4-408-PRECAST INLET (Size - 4' X 4')
ASTM 615
13/19/2021
33 49 20
Drop Inlet
Thompson Pipe Group
TPG-5X5-408-PRECAST INLET (Size - 5' X 5')
ASTM 615
13/19/2021
33 49 20
Drop Inlet
Thompson Pipe Group
TPG-6X6-408-PRECAST INLET (Size - 6' X 6')
ASTM 615
18/28/2023
3349 10
Manhole
Oldcastle
Precast 4' x 4' Stacked Manhole (Size - 4' X 4)
ASTM C478
18/28/2023
3349 10
Manhole
Oldcastle
Precast 5' x 8' Storm Junction Box (Size - 5' X 8')
ASTM C478
18/28/2023
3349 10
Manhole
Oldcastle
Precast 4' x 4' Storm Junction Box (Size - 4' X 4')
ASTM C478
18/28/2023
3349 10
Manhole
Oldcastle
Precast 5' x 5' Storm Junction Box (Size - 5' X 5')
ASTM C478
18/28/2023
3349 10
Manhole
Oldcastle
Precast 6' x 6' Storm Junction Box (Size - 6' X 6')
ASTM C478
18/28/2023
3349 10
Manhole
Oldcastle
Precast 8' x 8' Storm Junction Box Base (Size - 8' X 8)
ASTM C478
18/28/2023
3349 10
Manhole
Oldcastle
Precast 5' x 8' Storm Junction Box Base (Size - 5' X 8)
ASTM C478
18/28/2023
3349 10
Manhole
Rinker Materials
Reinforced 48" Diameter Spread Footing Manhole (Size - 4' X 4')
ASTM C433
18/28/2023
33 39 20
Curb Inlet 10 'x 3' Riser
Thompson Pipe Group
Inlet Riser (Size - 3 FT)
ASTM C913-16
18/28/2023
33 39 20
Curb Inlet 15 'x 3' Riser
Thompson Pipe Group
Inlet Riser (Size - 3 FT)
ASTM C913-16
18/28/2023
33 39 20
Curb Inlet 20' x 3' Riser
Thompson Pipe Group
Inlet Riser (Size - 3 FT)
ASTM C913-16
**Note: Pre -cast
inlets are
appoved for the stage 1 portion of the structure (basin) only. Stage 11 portion of the structure
are required to he cast in place. No exceptions to this requirement shall be allowed
Storm Sewer - Pipes & Boxes 33-05-13
14/9/2021
3341 13
Steno Drain Pipes
Advanced Drainage Systems, Inc. (ADS)
ADS HP Storm Polypropylene (PP) Pipe (Size - 12" - 60")
ASTM F2881 & AASHTO M330
18/28/2023
3349 10
Storm Drain Pipes
Rinker Materials
Reinforced Concrete Pipe Tongue and Groove Joint Pipe (Size - 21" or larger)
ASTM C76, C655
18/28/2023
3349 10
Culvert Box
Rinker Materials
Reinforced Concrete Box Culvert (Sze - Various)
ASTM C789, C850
1 10/12/2023
3341 10
Storm Drain Pipes
AmeriTex Pipe &Products
Reinforced Concrete Pipe Tongue and Groove Joint Pipe* (Size - 15" or larger)
ASTM C76, C506
1 10/12/2023
3441 10
Culvert Box
AmeriTex Pipe &Products
Reinforced Concrete Box Culvert (size - Various))
ASTM C1433,C1577
1 10/18/2023
3541 10
Storm Drain Pipes
The Turner Co.
Reinforced Concrete Pipe Tongue and Groove Joint Pipe* (Size - 15" or larger)
ASTM C76, C506
110/18/2023
3641 10
Culvert Box
The Turner Co.
Reinforced Concrete Box Culvert (size - Various)
ASTM C1433,C1577