HomeMy WebLinkAboutContract 59227-A1City of Fort Worth, Texas WRMC Coliseum, Burnett and Moncrief Design
105158
Revision Date: 12/08/2023
Page 1 of 3
AMENDMENT No. One
TO CITY SECRETARY CONTRACT No. 59227
WHEREAS, the City of Fort Worth (CITY) and PBK Architects, Inc, dba
BEAM Professionals, (ENGINEER) made and entered into City Secretary
Contract No. 59227, (the CONTRACT) which was administratively authorized
on the 13th day of April, 2023 in the amount of $ 99,000.00
; and
WHEREAS, the CONTRACT involves engineering services for the following
project:
Roof Replacement Design for the Coliseum, Burnett and Moncrief Roofs
located at 3401 W. Lancaster, CPN 59227; and
WHEREAS, it has become necessary to execute Amendment No. One to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement, which
amends the CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional
engineering services specified in proposal attached hereto and incorporated
herein. The cost to City for the additional design services to be performed
by Engineer totals $672,000.00. (See Attached Funding Breakdown Sheet,
Page -4-)
2.
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $771,000.00.
3.
All other provisions of the Contract, which are not expressly amended
herein, shall remain in full force and effect.
CSC No. 59227-A1
City of Fort Worth, Texas WRMC Coliseum, Burnett and Moncrief Design
105158
Revision Date: 12/08/2023
Page 2 of 3
EXECUTED and EFFECTIVE as of the date subscribed by the City’s designated
Assistant City Manager.
APPROVED:
City of Fort Worth PBK Architects dba BEAM
Professionals
Dana Burghdoff, AICP Harold Stephens
Assistant City Manager Vice President
DATE: _______________DATE: _________________
ATTEST:
Jannette Goodall
City Secretary
APPROVAL RECOMMENDED:
Marilyn Marvin
Interim Director, Property Management Department
Contract Compliance Manager:
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring all
performance and reporting requirements.
_______________________________
Nikita N. Watts
Senior Capital Projects Officer
APPROVED AS TO FORM AND LEGALITY: M&C No.#: 24-0502 ________
M&C Date: June 11, 2024_____
Douglas W. Black
Sr. Assistant City Attorney
City of Fort Worth, Texas WRMC Coliseum, Burnett and Moncrief Design
105158
Revision Date: 12/08/2023
Page 3 of 3
FUNDING BREAKDOWN SHEET
City Secretary No. 59227
Amendment No. One
Fund Dept ID Account Project
ID
CF1-
Activity
CF2 – Bond
Reference Amount
34030 0240050 2330500 105158 000530 9999 $99000
34030 0240450 5330500 105158 000530 9999 $672000
Total: $
14001 North Dallas Pkwy, Sulte 400
Dallas. Tex�s 752af)
Phone: 972 233-1323
Fax 972-233-1373
www.BE�IVI Prof r,om
April 20, 2023
Mr. Ronald Clements
Registered Architect Property Management Department
City of Ft Worth
rBEAM 401 W 13'h Street
Fort Worth, TX 76102
Reference: Fee Proposal Roof Construction Documents through Construction Administration
for the Coliseum Roof, Burnett Roof, and Moncrief/Watt Arena Roofs at Will Rogers
Center
Dear Mr. Clements:
On behalf of BEAM, we want to express how much we genuinely appreciate the request to provide
Building Envelope Consulting services for reroofing at the above-named facilities.
BEAM will deliver full comprehensive Building Envelope Consulting services for this reroofing projects.
Our team understands the time sensitivity of these projects and stands ready to deliver as needed.
I. SCOPE OF WORK:
Will Roqers Center Coliseum Roof, Burnett Roof and MoncrieflWatt Arena Roofs 3401 W
Lancaster Avel Fort Worth, 7X 76107
Construction Documents:
Provide complete roof replacement construction documents, bidding services and construction
administration services for the above building at the Will Rogers Center address.
BEAM Professionals will provide design, construction documents, assistance in bidding and
construction administration to provide design services for reroofing scopes of the above campuses.
II. SCOPE OF SERVICES:
BEAM understands the scope of work to be as follows:
Construction Documents (CD) —
BEAM will develop a design solution based on existing conditions. We will then develop the design into
a set of documents and specifications that define in sufficient detail all components of the project. This
documentation will be suitable for bidding, permitting. Deliverables in the CD phase will include:
• Roof plans
• Roof Details
• Specifications
• Bidding and Negotiations:
• Pre-Construction meeting:
• Contractor Shop Drawing review:
• Construction Phase Observations:
BEAM will attend a pre-proposal conference/walk with the contractors. BEAM will provide addenda and
clarification during the bidding process for construction and purchasing.
Construction Administration — Contract administration will include the processing of shop drawings
and submittals, site visits by a designated BEAM construction representative will be conducted on a
regular basis, attend OAC meetings weekly or as designated by the district.
To: Mr. Ronald Clements
April 20,2023
Page 2
III. COMPENSATION:
BEAM is pleased to offer our comprehensive corporate design services for this project at an approximate
fee of assessment fee and 6°/a of the estimated roof replacement of the project. Fees will be based off
finale construction cost.
Will Rogers Center Coliseum Re-Roof —
EST. Owners Construction Cost $4,100,000.00
AIE Fees
$246,000.00
Will Rogers Center Burnett Re-Roof —
EST. Owners Construction Cost $3,500,000.00
AIE Fees
$210,000.00
Will Rogers Center Moncrief/Watt Arena Re-Roof —
EST. Owners Construction Cost $3,600,000.00 A/E Fees $216,000.00
Total Total
EST. Owners Construction Cost $11,200000.00 Est AIE Fees $672,000.00
Reimbursables —Reimbursables for this project will include only pre-approved reimbursables by Owner-
potential approved costs associated maybe print andlor reproduction costs associated with project
documentation (deliverables). In addition, Structural andlor MEP engineering costs, if any, will be billed
as a reimbursable. Reimbursables will be billed at cost (no markup).
SCHEDULE
We know this project is important to the city and BEAM has the staff and time to dedicate the appropriate
resources to begin as soon as contracts and PO's are completed.
We sincerely appreciate the opportunity to provide a fee proposal for this exciting project. Please do not
hesitate to contact me at 817-332-4333 if I can provide any further information or clarification at this time.
Sub � e y:
Date: .2 2�
rold Stephens, Vice P sident
BEAM Professionals
Approved by:
Date:
Name:
City of Fort Worth
6/13/24, 8:10 AM
CITY COUNCIL AGENDA
Create New From This M8�C
DATE: 6/11/2024 REFERENCE **M&C 24-
NO.: 0502
CODE: C TYPE:
21 WRMC ROOF
LOG NAME: REPLACEMENT
PROFESSIONAL SERVICES
AGREEMENT
PUBLIC
CONSENT HEARING: NO
F�RT�'�ORTI�
-��-
SUBJECT: (CD 7) Authorize Execution of Amendment No. 1 to a Professional Services
Agreement with PBK Architects, Inc. d/b/a BEAM Professionals in the Amount of
$672,000.00 for Design Services for Will Rogers Memorial Center's Coliseum, Burnett
and Moncrief Roof Replacement Project for a Revised Contract Amount of $771,000.00
RECOMMENDATION:
It is recommended that the City Council authorize execution of Amendment No. 1 to a Professional
Services Agreement with PBK Architects, Inc. d/b/a BEAM Professionals (CSC No. 59227) in the
amount of $672,000.00 for design services for Will Rogers Memorial Center's Coliseum, Burnett and
Moncrief Roof Replacement Project No.105158 for a revised contract amount of $771,000.00.
DISCUSSION:
The purpose of this Mayor and Council is to authorize execution of amendment No. 1 to a professional
services agreement with PBK Architects, Inc. d/b/a BEAM Professionals for design services in the
amount of $672,000.00 for roof replacement design for the Coliseum, Burnett and Moncrief
roofs located at 3401 W. Lancaster, on the Will Rogers Memorial Center campus. A Professional
Services Agreement with BEAM Professionals in the amount of $99,000.00 for Will Rogers Auditorium
roof replacement was administratively authorized on April 13, 2023 (City Secretary Contract No.
59227).
BEAM Professionals will develop a design solution based on existing conditions and provide a set of
construction documents and specifications for each roof. The overall project costs are expected to be
as described in the below table:
�:Z�aJ x� ��Z��'� �'?
Original Design Contract Auditorium Roof
(Contract No. 59227)
Design WRMC Coliseum
Design WRMC Burnett
Design WRMC Moncrief
� t�� �_1 �•'i
�
�
Estimated Construction for all three (4) Facilities
ProjectAdministration Costs
PROJECT TOTAL
M&C Review
$99,000.00
$246,000.00
$210,000.00
$216,000.00
$8,700,000.00
$129,000.00
$9,600,000.00
Waiver of Building Permits - In accordance with the City Code of Ordinances, Part II, Chapter 7-1
Fort Worth Building Administrative Code, Section 109.2.1, Exception 2; "Work by non-City personnel
on property under the control of the City of Fort Worth shall be exempt from the permit fees only if the
work is for action under a contract that will be or has been approved by City Council with notes in the
contract packages stating the fee is waived."
Funding - Funding for this project is the result of M&C 23-085, approved by the City of Fort Worth
Council on October 17, 2023. The M&C authorizing the issuance of City of Fort Worth, Texas Special
apps.cfwnet.org/council_packet/mc_review.asp?ID=32209&councildate=6/11 /2024 1 /2
6/13/24, 8:10 AM
M&C Review
Tax Revenue Bonds, (Tax-Exempt) Series 2023A, in an aggregate principal amount not to exceed
$32,000,000.00 for the purpose of (i) paying costs paid or incurred as part of the planning, design,
engineering, land acquisition, construction, reconstruction, equipping, furnishing and opening the
Series 2023A project improvements at the Will Rogers Memorial Center as an Adjacent Support
Facilities project as part of the Venue project, and (ii) paying certain costs of issuance; authorizing
execution of all related documents; approving the sale of the bonds subject to certain parameters
being met; designating City officials authority to effect the sale; and ordaining related matters.
Tranche 1, available January 1, 2024 provided $6,000,000.00 for City Project No. 105158, WRMC
Roof Rep Col Bur Mon, and Tranche 2, available January 1, 2025 will provide the remaining balance
of $3,600,000.00, bringing the total project budget for City Project No. 105158, WRMC Roof Rep Col
Bur Mon, to $9,600,000.00.
Business Equity —Awaiver of the goal for Business Equity subcontracting requirements was
requested, and approved by the DVIN, in accordance with the applicable Ordinance, because the
waiver request is based on the Engineering firm is a pre-approved City vendor that specializes in roof
design.
The Will Rogers Memorial Center is located in COUNCIL DISTRICT 7.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are available in the current capital budget, as previously
appropriated, in the Spcial Tax Rev Bnd Serie 2023A Fund for the WRMC Roof Repair Col Mon Bur
project to support the approval of the above recommendation and execution of the agreement. Prior
to an expenditure being incurred, the Property Management and Public Events Departments have the
responsibility of verifying the availability of funds.
TO
CFund Department Account Project Program Activity Budget Reference # Amount
ID ID Year (Chartfield 2)
Fund Department Account Project
ID ID
Submitted for City Manager's Office by_
Originating Department Head:
Additional Information Contact:
ATTACHMENTS
Program I Activity I Budget
Year
Dana Burghdoff (8018)
Marilyn Marvin (7708)
Nikita Watts (2028)
Reference # Amount
Chartfield 21
21 WRMC ROOF REPLACEMENT PROFESSIONAL SERVICES AGREEMENT FID TABLE.xlsx (CFW Internal)
21WRMC ROOF REPLACEMENT PROFESSIONAL SERVICESAGREEMENT funds availability_pdf (CFW Internal)
Form 1295 Certificate 101196433 BEAM Professionals WRMC 042924.pdf (CFW Internal)
MC Revisions to 21 WRMC ROOF REPLACEMENT(dwbRL5.21.24).docx (CFW Internal)
SAM PBKArchitects Inc dba BEAM Professionals.pdf (CFW Internal)
Waiver Request Form Approval.pdf (CFW Internal)
Will Rogers Memorial CenterAuditorium Reroof map.pdf (CFW Internal)
WRMC MAP.pdf (Public)
apps.cfwnet.org/council_packet/mc_review.asp?ID=32209&councildate=6/11 /2024 2/2